1 Mid-rise Costing STUDY Atlantic WoodWORKS!
2 About us Atlantic WoodWORKS! is a program of the Maritime Lumber Bureau (MLB) and part of a National industry lead initiative of the Canadian Wood Council (CWC) Atlantic Funders: National Sponsors:
3 Definition of Mid-rise adjective 1.(of a building) having a moderately large number of stories, usually 5 to 10, and equipped with an elevator.
4 Introduction 2015 NBC Major Occupancies Group C or D 2010 NBC 4 Storey - C = m 2 D = m NBC 6 Storey - C = m 2 D = m 2 Velo 4 storey wood, Gottingen St. Halifax, NS Mixed Use Bottom 2 Storeys -Schools -Commercial Spaces - Restaurants Gardenview 6 storey wood, Maine St. Dartmouth, NS
5 Cost Comparison 2010 Ontario WW Source: (Walker Consulting Group and Ontario Wood WORKS!, 2010)
6 Cost Comparison 2013 Ontario BILD Estimated cost savings of $30 - $40 per square foot of construction when compared to concrete and steel materials [1]. Source: [1]. Unlocking the Potential for Mid-Rise Buildings, BILD, ONT (2013)
7 Cost Comparison 2013 REMY Construction Schedule Costing 4 Storey Opportunities with mid-rise... Wood panelized construction resulted in a 23% reduction in overall project schedule.
8 Opportunities with mid-rise... Construction Schedule Costing 4 Storey Wood panelized construction resulted in a 23% reduction in overall project schedule.
9 Opportunities with mid-rise... Construction Schedule Costing 4 Storey Wood panelized construction resulted in a 23% reduction in overall project schedule.
10 Opportunities with mid-rise... Construction Schedule Costing 4 Storey Wood panelized construction resulted in a 23% reduction in overall project schedule.
11 Cost Comparison 2017 CCMPA
12 Cost Comparison 2017 CCMPA
13 Cost Comparison 2017 CCMPA Addendum
14 Cost Comparison 2017 March AWW Summary: 10 Page Case Study Detailed Report 34 Page Analysis Study Objective: Analyze building types to create a like comparison
15 Presentation Outline Ontario Mid-rise Market Share / Trends Mid-rise Cost Comparison Study - Methodology and Credibility - Special Inclusions & Exclusions - Additional Considerations Major Cost Comparative Results Pricing Considerations Mid-rise Resources Conclusion *Time permits Fire and Acoustics relative to Mid-rise Wood Frame
16 Mid-rise by the numbers Across Canada 100 wood mid-rise projects completed 188 in construction at final design stage being considered
17 Cost Comparison Study Cost Comparison Study 1Concrete + 5Wood/6Wood/6Steel/6Concrete Summary: 10 Page Case Study Detailed Report 34 Page Analysis
18 Cost Comparative Study Under construction: 44 Paul Street, Kamploops, BC Mixed use: 1 Storey Concrete + 5 Storey Wood (LWF) GFA: 113,380 ft units
19 Cost Comparative study Fire Wall Detailing NB Code Meeting January 2017
20 Cost Comparative study Fire Wall Detailing NB Code Meeting January 2017
21 Cost Comparative study Methodology & Credibility Base model design converted to steel, concrete and all-wood building elements by QS Online cost consultants Professional engineer vetted building assemblies and made adjustments for apples to apples structural comparison
22
23 Cost Comparative study Methodology & Credibility Base model design converted to steel, concrete and all-wood building assemblies by QS Online cost consultants Professional engineer vetted building assemblies and made adjustments for apples to apples structural comparison Electrical and mechanical engineers reviewed assemblies and commented on cost differences between the building models
24
25 Cost Comparative study Special Inclusions: Insurance included within general req. Firewall Analysis Design and pricing allowance (10%) Construction allowance (4%) Exclusions: Underground parking removed all include foundation with 4 slab on grade Soft costs Productivity HST
26 Cost Comparative study Other important considerations Retail material pricing Supply and Install (HRM pricing) *Pricing consistent with rest of Canada Commercial Space in base model is open space Elevator Shaft and Stairwell cost/performance exceeds code requirement in 2015 NBC for wood types ~ comparable to ONT CLT used in base model design for roof and projections ~ $100,000 premium ($15/ft 2 $37/ft 2 with roof coverings) Drawings not 100% complete lead to minor assumptions Costs represent a finished building not just comparative elements
27 Cost Comparative study
28
29 Upper Floor Construction Level 3, 4, 5, 6 Wood Framed Floor concrete top 1 1/2" 5/8" ply Wood I Joists (varying capacity) 16" o.c. Corridor x 6" 12" o.c. acoustic batt insulation - R28 Corridor Partition GWB 5/8" - paint ready GWB - 5/8" - taped Stud - 2 x 6" - 16" o.c. fibreglass insulation 6 Tie rod system & compensators Demising Partition Non-demising Partition GWB 5/8" - paint ready GWB - 5/8" - taped Stud - 2 x 4" - 16" o.c. fibreglass insulation 3 Note: STC not taken into consideration for steel and concrete models
30 Upper Floor Construction Level 2, 3, 4, 5, 6
31 Upper Floor Construction Level 2, 3, 4, 5, 6 Support System 3 1/2" x 9 1/2" Structural composite lumber (SCL) $350,000 Premium 7" x 9 1/2" SCL 4 ply - 2 x 6 Stud packs - multi-ply posts - SPF Wood Framed Elevator Shafts and Stairwell ~ $250,000 total cost (inc. roof & stairs) 4 layers 5/8" type X (exceeds code requirements) 2x6 studs fire batt Firewall - 2nd to Level 6 - ($18/ft 2 ) ~ $75,000 Premium 10 CMU Applies to all building types
32 Upper Floor Construction Level 2, 3, 4, 5, 6 Metal Framed Upper Floor horizontal and vertical steel - allowance - 12 psf ($1.50lb) metal deck concrete top 1 ½ Various assembly items (ie. place and screed, power trowel finish and construction joints) Concrete Stairwell & Elevator shaft 10 CMU vertical with stairs $250,000 total (+35%) Note: - Acoustic measures were not taken into consideration
33 Upper Floor Construction Concrete Framed Upper Floor concrete 8" dp - allow 25 Mpa (3,625 PSI) - $135/CY rebar - allow 8 Lbs / SF formwork Various assembly items (ie. place and screed, power trowel finish and construction joints) Concrete Stairwell & Elevator Shaft Vertical slabs with stairs Column Support concrete - allow 25 Mpa (3,625 PSI) formwork - 57' 7 each side rebar-15m stirrup - 12" o.c. rebar M vert 61,244 Lbs
34 Upper Floor Construction Similar Upper Floor Elements as Base Model Major difference = wood on 1 st storey Further Research Consideration (stud spacing): Image Courtesy of BC mid-rise video
35
36 Roof Construction Roof Construction 5/8" ply T&G Corridor - 2 x 6" 12" o.c. - 6' 9 Wood I Joists (varying capacity) 16" o.c. CLT panels - 5 ply ~ ($15/ft 2 $37/ft 2 with roof coverings) Note: CLT has finished underside which translate to finishing savings Ontario Mid-rise workshops February 2017
37 Roof Construction Steel Roof Construction horizontal and vertical steel - allowance - 12 psf metal deck - std allow 15% for miscellaneous metals allow 10% for connections and fittings miscellaneous sundries Concrete Roof Construction concrete 8" dp - allow 25 Mpa (3,625 PSI) rebar - 8 Lbs / SF formwork place and screed power trowel finish construction joints Note: -Similar to upper floor construction -Unit rates are higher for both steel and concrete vs. wood - Acoustic measures were not taken into consideration
38 Roof Construction Roof Construction 5/8" ply T&G Corridor - 2 x 6" 12" o.c. - 6' 9 Wood I Joists (varying capacity) 16" o.c. Parallel cord truss Note: CLT was replaced with lower cost regional products like parallel cord truss and wood I-joist systems (similar construction to upper floor) as CLT is not produced in Atlantic Canada 6% overall cost reduction in roof construction element
39
40 Cost Comparative study
41 Partitions Interior Unit Partitions GWB 5/8" - paint ready stud - 2 x 4" - 16" o.c. fibreglass insulation 3 GWB 5/8" - paint ready Corridor Partition - Lobby GWB 5/8 stud - 2 x 6" - 16" o.c. fibreglass insulation 6 GWB 5/8" - paint ready Note: Quantity = 26,945ft 2 (Base) vs. 32,133ft 2 (6 Wood)
42 Partitions Interior Unit Partitions GWB 5/8" - paint ready 20G metal stud - 2 x 4" - 16" o.c. fibreglass insulation 3 GWB 5/8" - paint ready Corridor Partition - Lobby GWB 5/8 20G metal stud - 2 x 6" - 16" o.c. fibreglass insulation 6 GWB 5/8" - paint ready Note: - All demising, corridor, bathroom, bedroom and closet partitions are non load bearing, therefore, all are accounted for in the partitions element - Quantity = 112,062ft 2 of partitions
43 Hanscomb Wood stud vs. Steel Stud Hanscomb Mass Timber Cost Comparison Report:
44 Cost Comparative study
45 Ceiling Finishes Base Model & 6 Storey Wood Ceiling Finishes ground level - unfinished - sealed concrete ground floor lobby - residential - suspended acoustic tile level 2, 3, 4, 5, 6, GWB 5/8" - paint ready GWB - 5/8" - taped strapping to joists - 1 x 3" - 16" o.c paint to ceiling Corridor Partition - Lobby GWB 5/8 stud - 2 x 6" - 16" o.c. fibreglass insulation 6 GWB 5/8" - paint ready Note: Quantity = 26,945ft 2 (Base) vs. 32,133ft 2 (6 Wood)
46 Ceiling Finishes Concrete & Steel Ceiling Finishes Suspended acoustic tile Ceiling finishes allowance ground level - unfinished - sealed concrete Suspended GWB 5/8" - paint ready 93,984 SF ,912 Paint to ceiling Note: More work and cost associated with suspending ceiling tile and gypsum
47 Cost Comparative study
48 Electrical *Cost Savings Conservative estimation as not much detail was provided architecturally and structurally at time of calculation. * Increased provisions for wiring in 2015 NBC so savings could be minimized Code permits polymer coated (NMD90) cable for wood frame Metallic sheathed for cable steel/concrete $5.31/ft 2 $6.25/ft2 Ontario Mid-rise workshops February 2017
49 Cost Comparative study Ontario Mid-rise workshops February 2017
50 Cost Comparison (11%) (12%)
51 Additional Research 1. Underground parking 2. More costing detail Class A or B level on a simple building design 3. Explore different structural assemblies for wood construction 4. Analyze productivity
52 Pricing Considerations Steel Studs
53 Pricing Considerations Wood Studs
54 Pricing Considerations Concrete Less Foundation and Slab on Grade
55 Most important take home message 1. All or nothing approach 2. Retail vs. Wholesale pricing model 3. Over compensation for fire treatment (this study is an example) 4. Pricing inclusions (ie. Mass timber architectural finish) 5. Heavy or complex connections & Inefficient sizing 6. Site considerations Exposure to site risk (ie. Stickbuilt vs. Prefabrication vs. Modular) Interaction of trades (who is supplying what Union coordination & Labour Pricing) 7. Guesswork! Conservative assumptions by designers and cost consultants, coupled with all or nothing scenarios, can easily kill viable wood projects.
56 Design Resources
57 Design Resources
58 Conclusion Best Practice Construction Management Approach - Bring all stakeholders to the table as soon as possible Design steps NBC mid-rise provision comparison (Can t pick b/w 2010 & 2015) - Review design guides and WoodWORKS! resources - Stick, prefab or modular - Educate on shear design, fire stopping, STC, and shrinkage performance - Design Assist? Integrated construction -Treat like a Commercial project - Architect and Engineer to have regular meetings with CM (if applicable), - Challenges create an opportunity for integration! - Order of Construction seek experience (Drywall and windows) Fire Site Safety Planning - Review Ontario s Guideline
59
60 Ontario $5 Million available in each province Eligible buildings must be 10+ storeys Monies cannot be used toward construction Only design and testing.
61 Follow Wood for Mid-rise online documents
62 Thank you Patrick Crabbe Project Coordinator Atlantic WoodWORKS! Toll Free:
PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION
PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION An overview of costing strategies for wood framed construction elements CREATING A PROJECT ENDLESS POSSIBILITIES COMPATORS LIST A FLOOR Cast in Place
More informationGardenView Residential Development. Class 'C' Construction Cost Estimate (Rev #2)
GardenView Residential Development Dartmouth, Nova Scotia Job No: 100123 Class 'C' Construction Cost Estimate (Rev #2) EXECUTIVE SUMMARY The 'Hard' Construction Cost Estimate can be summarized as follows
More informationWORKSHOP Progressive Multi- Family Design: New Opportunities for Light Frame Mid-Rise Structures
WORKSHOP Progressive Multi- Family Design: New Opportunities for Light Frame Mid-Rise Structures February 14 16, 2017 San Diego, Long Beach, San Francisco The Wood Products Council is a Registered Provider
More informationTHE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND CONDOMINIUMS
THE CITY OF WALTHAM MASSACHUSETTS PURCHASING DEPARTMENT PHASE II RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING CONDOMINIUMS AND PHASE III RENOVATIONS TO THE FORMER BANKS SCHOOL ELDERLY HOUSING
More informationTown of Berwick. Rec Park Muilt-Use Bldg. Cover Project number Date Drawn by Checked by
No. Description ISSUED FOR TENDER 08-04-05 Cover Project number Drawn by Checked by 0 8-04-04 KH BMB A0 08-04-04 7:7:6 PM N S 8' - 0" 6' - 0" 8' - 0" 6' - 0" 6' - 0" 6' - 0 3/4" 4' - /4" 7' - 0" 8' - 8"
More information6 STOREY MID-RISE COST COMPARISONS BETWEEN WOOD, STEEL AND CONCRETE STRUCTURES
6 STOREY MID-RISE COST COMPARISONS BETWEEN WOOD, STEEL AND CONCRETE STRUCTURES INTRODUCTION QS Online Cost Consultants Inc. from Halifax completed a Class C cost estimate for a six storey building that
More informationStructural Technical Report #2 By Robert Whitaker
Structural Technical Report #2 By Robert Whitaker Robert Whitaker Structural ~ Parfitt Parkview at Bloomfield Station Bloomfield, NJ 10-31-05 Executive Summary This report covers the comparative redesign
More informationTHE SPENCER RESIDENCE J&S ARCHITECT
THE SPENCER RESIDENCE J&S ARCHITECT 75 POURED CONCRETE FOUNDATION WALL (0MPa) 97.94 50Ø WEEPER TILE C/W SOCK W/MIN. 50 GRANULAR COVER F.D. E.P.B. F.D. 00 POURED CONCRETE FOUNDATION WALL (0MPa) 475 X 00
More informationDead Load Weight of Roof Trusses. Dead Load Weight of Floor Trusses
Dead Load Weight of Roof Trusses Top Chord Bottom Chord Webs Weight per Lineal Foot (plf) 2x4 2x4 2x4 4.3 2x4 2x8 2x4 5.6 2x6 2x4 2x4 4.8 2x6 2x6 2x4 5.5 2x6 2x6 2x6 6.2 2x6 2x8 2x4 5.9 2x6 2x10 2x4 6.6
More informationAttachment A. USG Minimum Design and Construction Requirements for Wood Framed Structures
Attachment A USG Minimum Design and Construction Requirements for Wood Framed Structures 1. General Design Criteria 1.1. Per Adopted Georgia State Minimum Standard Building Code 1.2. Minimum Live Loads
More informationResidential Building Permits
JWS INSPECTION SERVICE 3407-43B Avenue Lloydminster, Saskatchewan S9V-2G1Ph:780-808-5704 Email: jsydoruk@sasktel.net Residential Building Permits A residential building is a one or two unit dwelling, along
More informationNEWS LETTER MARCH 27, 2009
PLANNING, BUILDING & DEVELOPMENT SERVICES DEPARTMENT 580-1 Street S.E. Medicine Hat, Alberta T1A 8E6 Telephone: 529-8374 FAX 502-8038 1 NEWS LETTER MARCH 27, 2009 GENERAL As you are probably aware there
More informationShaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Boston & Waltham Workshops, December 6 & 7, 2017
Shaft Wall Solutions for Wood-Frame Structures Ricky McLain, PE, SE WoodWorks Wood Products Council Boston & Waltham Workshops, December 6 & 7, 2017 Shaft Walls Shaft Walls Form Shaft Enclosures The purpose
More informationHOUSE ADDITIONS A guide to the plans required when applying for a Building Permit
PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT HOUSE ADDITIONS A guide to the plans required when applying for a Building Permit November 2017 contents Introduction... 3 Site Plan... 4 Floor Plan... 6 Foundation
More informationJackson Crossing. Proposal. Alexandria, Virginia. Michael Bologna Structural Option. December 11, 2015 Advisor: Dr. Linda Hanagan
Jackson Crossing Alexandria, Virginia Proposal Michael Bologna Structural Option December 11, 2015 Advisor: Dr. Linda Hanagan Executive Summary... 3 Introduction Purpose... 4 Scope... 4 General Building
More information- Inbound/Outbound window placement - Window buck & air sealing - Weep holes IN THE WOODS DETAILS - WINDOW SILL
- Inbound/Outbound window placement - Window buck & air sealing - Weep holes IN THE WOODS DETAILS - WINDOW SILL PRE-EXISTING SITE Program: Traditional farmhouse Single level living potential Garage connection
More informationLISTING INFORMATION OF Mitek Design No. MCI/WI SPEC ID: MiTek Canada, Inc. 100 Industrial Road Bradford, ON L3Z 3G7 Canada
LISTING INFORMATION OF Mitek Design No. MCI/WI 60-02 SPEC ID: 27680 MiTek Canada, Inc. 100 Industrial Road Bradford, ON L3Z 3G7 Canada This report is for the exclusive use of Intertek s Client and is provided
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee Hill Elementary
More informationWOOD USE IN NONCOMBUSTIBLE BUILDINGS
INTRODUCTION The National Building Code of Canada (NBCC) 1 requires that some buildings be of noncombustible construction under its prescriptive requirements. Its use in certain types of buildings such
More informationThe Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee
The Structural Redesign of Boyds Bear Country and its Related Systems Included in this Presentation: Background and Existing System Proposal Problem / Solution Structural System Redesigns Pre-cast Concrete
More informationHAMBRO COMPOSITE FLOOR SYSTEM
HAMBRO COMPOSITE FLOOR SYSTEM OUR EXPERTISE AT YOUR SERVICE Canam has been offering owners, real estate developers, architects, engineers and contractors an array of construction solutions since 1970.
More informationShaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Charlotte WSF, November 2, 2017
Shaft Wall Solutions for Wood-Frame Structures Ricky McLain, PE, SE WoodWorks Wood Products Council Charlotte WSF, November 2, 2017 Course Description It is fairly common for light wood-frame commercial
More informationJ.DAVID POUNDER LIMITED CONSULTING ENGINEER AND ARCHITECT
J.DAVID POUNDER LIMITED CONSULTING ENGINEER AND ARCHITECT Using a Multidisciplinary Approach to Projects for Over 0 Years Project 5 Mapleview Terrace Apartments, 59 South Pelham Road, Welland Addendum
More informationHow to Estimate the Cost of a Medical Office Building Using Conceptual BIM (DProfiler)
How to Estimate the Cost of a Medical Office Building Using Conceptual BIM (DProfiler) CPE Candidate No. 0115805 July 2015 1 P age How to Estimate the Cost of a Medical Office Building Using Conceptual
More informationInterior FRT Wood. References of Previous Model Building Codes
Interior FRT Wood References of Previous Model Building Codes Table of Contents SBBCI Standard Building Code 1 ICBO Uniform Building Code 3 BOCA National Building Code 5 10-SBBCI STANDARD BUILDING CODE
More informationUCC Permit Application Procedures
How do I apply for a permit? UCC Permit Application Procedures 1. Please complete the CodeMaster Pan Review Application 2. Please provide the scope of work description and/or construction documents/plans.
More informationStructural Inspection
General: Background: An inspection and structural analysis have been performed for the purpose of evaluating the buildings structural systems and components. A full set of structural drawings was utilized
More informationBuilding for Energy Efficiency Part 2 Advanced Framing Workshop. Objectives for this presentation...
Building for Energy Efficiency Part 2 Advanced Framing Workshop Aaron Grin Corporation www.buildingscience.com Objectives for this presentation... 1. Brief History of Advanced Framing 2. Overview 3. Benefits
More informationFraming Methods Structural Components
Framing Methods Structural Components Balloon Framing *Balloon framing or Eastern framing the exterior studs run from the top of the foundation to the top of the highest level. Benefits of this type of
More informationModular Wood Framing Goes Vertical
Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported
More informationResidential Building Inspections
Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved
More informationPOST AND FRAME STRUCTURES (Pole Barns)
POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:
More informationINSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT
INSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT MAY 2009 prepared by N. A. JACOBSEN, P.Eng. CIVIL ENGINEERING CONSULTANT Whitehorse, Yukon ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT MAY
More informationCHAPTER 6 TYPES OF CONSTRUCTION
CHAPTER 6 TYPES OF CONSTRUCTION SECTION 61 GENERAL 61.1 Scope. The provisions of this chapter shall control the classification of buildings as to type of construction. SECTION 62 CONSTRUCTION CLASSIFICATION
More informationGARAGE MAIN FLOOR PLAN
12'-0" 4'-6" 3'-0" 4'-6" 3040 14'-0" LADDER LT LINE BUNK CABIN 11'-4" x 13'-4" 14'-0" BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS.
More informationNRC Research Update on Mid-Rise Wood Construction. Joseph Su Principal Research Officer, Fire Safety
NRC Research Update on Mid-Rise Wood Construction Joseph Su Principal Research Officer, Fire Safety Outline Benefits and uses of wood structures Code developments to permit midrise R&D for solutions and
More information'Rose Avenue Project'
B1 B2 A1 A2 'Rose Avenue Project' Drafting & Design Tom Masters SITE PLAN A1 Kelowna, BC (250)317-2446 kelowna635@gmail.com NOTES PROVIDE FIRE STOPS IN ACCORDANCE WITH BC BUILDING CODE REFERENCE 9.10.15
More information6-Storey Residential Buildings Combustible Construction. A Regulator s Perspective City of Richmond, BC Canada
6-Storey Residential Buildings Combustible Construction A Regulator s Perspective City of Richmond, BC Canada Our first...learning curve Remy mid-rise Project 5388 Cambie Street, Richmond BC It s Allowed
More informationCustomer A101. Front Elevation. Roof Peak 24' /32" Roof 17' - 6" Main Floor 9' - 6" Floor Joist 8' - 6" Basement 0' - 6" Grade 0' - 0"
/300 ROOF VENTILATION REQUIRED TYPICAL ROOF OVERHANG '-6" 2 7 Peak 24' - 9/32" 7' - 6" 9' - 6" Floor Joist Grade 0' - 0" Front Elevation 24"x8" STRIP. FOOTING (TYP.) MIN. 42" HIGH GUARD AROUND DECK (TYP.)
More informationCLASS A OFFICE BUILDING
Century Management Company 1 E n t e r p ri s e Wa y, Ro s e v i l le, CA V I N E YA R D P O I N T E B U S I N E S S P A R K SF, - ±6 e, ±2 abl Avail TWO-STORY CLASS A OFFICE BUILDING Ro s e v i lle, CA
More informationOverview of the New Mid-Rise Handbook Alberta Wood Solutions Fair
Overview of the New Mid-Rise Handbook Alberta Wood Solutions Fair Conroy Lum, P.Eng. Research Leader Structural Performance Group Advanced Building Systems February 12, 2015 Calgary Copyright Materials
More informationTimmins Library & Judy A. Shank Integrated Services Building
Timmins Library & Judy A. Shank Integrated Services Building Table of contents Timmins Library / Judy A. Shanks Integrated Services Building 2 Introduction 3 Building Descriptions 5 Structure 7 Cost Efficiency
More informationThe better way to build TM
The better way to build TM Product Catalog Exterior Wall SIP The Exterior Wall SIP is the most common panel manufactured by Thermapan with numerous applications in residential and commercial construction
More informationSupplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC)
Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) P.C. Engineer: Phone:
More informationADDENDUM A CONSTRUCTION SPECIFICATIONS
ADDENDUM A Description of Improvements: CONSTRUCTION SPECIFICATIONS The Improvements shall consist of constructing an approximate square foot single-family residence including car garage on the real property
More informationThesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact
Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact Executive Summary:, located in Pigeon Forge, Tennessee, is designed as a multifunctional space and
More informationFIRE RATING AND FIRE PERFORMANCE
FIRE RATING AND FIRE PERFORMANCE FOR WOOD BUILDINGS St. John s, NL February 3, 2015 Introductions Fire Ratings Background Where are They Needed How are they Achieved Fire Performance AGENDA Historical
More informationTable of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5
WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 1 OCTOBER 5, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI Table of Contents Table of Contents
More informationBuilding Guide. olorado Chapter of the International Conference of Building Officials. Lancaster County Building Department
olorado Chapter of the International Conference of Building Officials Lancaster County Building Department Single Family Residential One Story Detached Garage How to Use this Guide Provide two sets of
More informationCode Compliance for Fire Resistance-Rated Assemblies in Light-Frame Buildings
Code Compliance for Fire Resistance-Rated Assemblies in Light-Frame Buildings Michelle Kam-Biron, PE, SE, SECB Senior Director, Education American Wood Council Copyright This presentation is protected
More informationG703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project
Billing Requirements G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project Sitework / Paving Excavation and Grading Labor
More informationOWNERS: EASTSIDE 2008 EQUITIES INC. DEVELOPED, MANAGED AND LEASED: EAST PORT PROPERTIES LIMITED
OWNERS: EASTSIDE 2008 EQUITIES INC. DEVELOPED, MANAGED AND LEASED: EAST PORT PROPERTIES LIMITED FOR LEASING INQUIRIES: John Lindsay, President (902) 468 2145 Judy Wall, Vice President (902) 468 8056 Kim
More informationType III Fire-Resistant Design and Detailing: Exterior walls, Intersections and Balconies. For Light-Frame Wood Construction
Type III Fire-Resistant Design and Detailing: Exterior walls, Intersections and Balconies For Light-Frame Wood Construction The Wood Products Council is a Registered Provider with The American Institute
More informationGARAGES/ONE-STORY City of Grand Rapids Building Safety Division
GARAGES/ONE-STORY City of Grand Rapids Building Safety Division 218-326-7601 www.cityofgrandrapidsmn.com This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building
More informationCarpentry/Carpenter CIP Task Grid
Secondary Task List 100 SAFETY/OCCUPATIONAL ORIENTATION 101 Identify and follow all basic safety practices and procedures. 102 Identify and follow all lab safety practices and procedures. 103 Identify
More information#G445 Plans, 48'x28' x 10' detached garage with bonus room By SDS-CAD Specialized Design Systems
Architectural asphalt shingles and horizontal True Wood 7" Reveal siding over structural panel. Nailing schedule is 6" on ends 12" on centers 6d nails. Trusses are engineered on Bonus attic trusses 24"
More informationBuilding Division Informational Handout
CITY OF SAN JOSÉ, CALIFORNIA Building Division Informational Handout Conventional Light Frame Construction Design Provisions 2007 CBC Handout No. 2-21 Published: 1/1/08 Page 1 of 3 This document summarizes
More informationPOST AND FRAME STRUCTURES (Pole Barns)
POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:
More informationThe Homeowner s Building Application Checklist for Constructing a Residential Addition
The Homeowner s Building Application Checklist for Constructing a Residential Addition This checklist provides homeowners a summary of the Building Permit submission requirements for constructing a residential
More informationHAMBRO COMPOSITE FLOOR SYSTEM
HAMBRO COMPOSITE FLOOR SYSTEM OUR EXPERTISE AT YOUR SERVICE Canam has been offering owners, real estate developers, architects, engineers and contractors an array of construction solutions since 1970.
More informationHelping You Pick the Right Products and Fire Resistance Assemblies
Trafalgar Landing Great Gulf Homes Credit: H+ME Technologies Mid-rise Tips Helping You Pick the Right Products and Fire Resistance Assemblies Andy Teasell, P.Eng. National Manager ELP Design Services Weyerhaeuser
More informationSample Plan Not for Construction for pricing
26' x 48' Screen Porch Garage Plans Trussed Roof, 2x Construction, 8' Walls Asphalt Shingles, Garage Space Office Space, Screened Porch 48'-0" 4" 5" 12'-0" 5" 4" 4'-0" 12'-0" 4'-0" 4'-0" 10'-0" 24'-0"
More informationColorado Chapter of the International Conference of Building Officials. Building Guide. The Colorado Chapter of the International
Building Guide Colorado Chapter of the International Conference of Building Officials Colorado Building Chapter of the International Guide Code Council Single Family Residential One Story Detached Garage
More informationAcoustics and Mass Timber: Room-to-Room Noise Control
Acoustics and Mass Timber: Room-to-Room Noise Control Richard McLain, PE, SE Senior Technical Director WoodWorks Photo: Corey Gaffer courtesy Perkins + Will T3 Minneapolis Architect: MGA Michael Green
More informationOAK TREE LIQUOR STORE
DRAWING LIST ARCHITECTURAL A000 - COVER SHEET D0 - DEMOLITION PLANS & ELEVATIONS A0 - PLANS, ELEVATIONS & DETAILS A40 - BUILDING S A40 - BUILDING S ARCHITECT: Engineering (00) Inc. 6 Great George Street,
More informationShaft Wall Solutions for Wood-Frame Structures. Ricky McLain, PE, SE WoodWorks Wood Products Council Atlanta WSF, April 25, 2018
Shaft Wall Solutions for Wood-Frame Structures Ricky McLain, PE, SE WoodWorks Wood Products Council Atlanta WSF, April 25, 2018 Course Description It is fairly common for light wood-frame commercial and
More informationGARAGE MAIN FLOOR PLAN
BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. SHED TO BE BUILT AS PER IRC, UBC OR CURRENT LOCAL CODE To the best of my knowledge
More informationTP: 89'-0" BP: 86'-6 1/4" 2'-0" Typ TP: 89'-0" BP: 86'-6 1/4" 2'-0" Typ S201 TW: 89'-0" TF: 86'-0" S201 TW: 87'-11 1/4" S201 TF: 86'-10 1/4" S201
Resource reginc.com 0.. '-" P: '-" 0'-0" " P: '- /" 0'-" '-" '-0" '-0" 0'-0" '-0" '-" '- /" TF: '-0" TW: '-0" TF: '-0" TW: '-0" TF: '-0" TW: '- /" TF: '-" " Typ Sim. P: '-" " TF: '-0" C '- /" '-" Varies
More informationCode Compliance for Fire Resistance-Rated Assemblies in Light-Frame Buildings. John Buddy Showalter, PE VP, Technology Transfer American Wood Council
Code Compliance for Fire Resistance-Rated Assemblies in Light-Frame Buildings John Buddy Showalter, PE VP, Technology Transfer American Wood Council Copyright This presentation is protected by US and International
More informationCode Compliance for Fire Resistance-Rated Assemblies in Light-Frame Buildings
Code Compliance for Fire Resistance-Rated Assemblies in Light-Frame Buildings Michelle Kam-Biron, PE, SE, SECB Senior Director, Education American Wood Council Copyright This presentation is protected
More informationStructural Concepts and Existing Conditions Report
Daniel Chwastyk F.W. Olin Center Louis Geschwindner Advisor Structural Concepts and Existing Conditions Report Executive Summary The following report discusses many of the structural concepts that were
More informationPremier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017
Premier Inn, Wilson Street, Middlesbrough, TS1 1AE Site progress report February 2017 Site set up Currently 4 weeks in to the build the site has been cleared and hoardings have been erected. Welfare cabins
More informationProject. San Jose City College Physical Education Building. Prepared For. Prepared By PLACE IMAGE HERE. Ken Bauer, AIA Principal
Project San Jose City College Physical Education Building PLACE IMAGE HERE Prepared For Ken Bauer, AIA Principal LPAS 2484 Natomas Park Drive Sacramento, CA 95833 916.443.0335 Prepared By Steve Ratchye,
More informationTable of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8
WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2
More informationOne and Two Family Additions
One and Two Family Additions An addition to a house, duplex, garage, or an accessory structure requires a building permit prior to performing any construction. Building Department & Permit Office Mon-Fri
More informationCustom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems
P O Box 34 Mendon, Utah Custom 22' x 40' - 16' Tall Garage Plan #g22 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical
More informationHilton Baltimore Convention Center Hotel Western Podium
Hilton Baltimore Convention Center Hotel Western Podium CHRIS SIMMONS Structural Option Faculty Consultant: Dr. Ali M. Memari Technical Report 2 TABLE OF CONTENTS EXECUTIVE SUMMARY. Page 3 INTRODUCTION..
More informationGARAGE MAIN FLOOR PLAN
BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. SHED TO BE BUILT AS PER IRC, UBC OR CURRENT LOCAL CODE To the best of my knowledge
More informationStructural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report
1 THE ODYSSEY ARLINGTON, VA Aaron Snyder Structural Option Advisor: M. Kevin Parfitt, PE Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report Executive
More informationThermal Characteristics of Exterior Building Wall (Above Heritage Building
Minimum Required R Value for Wall (Above Ground) RSI 2.78 (R 15.8) Thermal Characteristics of Exterior Building Wall (Above Ground) @ Heritage Building W1 W2 Exterior Wall - Stucco Cladding @ 1st Floor
More informationBVSC BVSC. Midwest Technical Inspections Survey Worksheet. Account / Account Code: Insured: Policy #: Building Data - Section 1
Midwest Technical Inspections Survey Worksheet BVSC BVSC Account / Account Code: Agency: Insured: Policy #: Telephone: Alt. Phone: Building Data - Section 1 Building Name (Entire Valuation) Section Name
More informationOntario Standard Building Spec for A277 Mini Homes- March 2018 Specifications based on Mini Home with insulated floor
Ontario Standard Building Spec for A277 Mini Homes- March 2018 Specifications based on Mini Home with insulated floor Building Code: * CSA A277 Standard * 2010 National Building Code of Canada (NBC) *
More informationSupplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC)
Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) Plan Check Engineer:
More informationCustom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems
P O Box 34 Mendon, Utah Custom 30 x 48-14' Tall Garage Plan #g226 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical Section
More informationTHE ASHTON PERSPECTIVE VIEW
THE ASHTON PERSPECTIVE VIEW TYPICAL DETAILS GENERAL DESIGN NOTES: 1. THESE DRAWINGS ARE OF A GENERAL NATURE AND ARE NOT INTENDED TO CONVEY THE METHOD OR MEANS OF CONSTRUCTION. IT IS ASSUMED THAT ALL WORK
More informationAirport Vicinity Acoustic Insulation
PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT Airport Vicinity Acoustic Insulation By-law No. 6419/94 of the City of Winnipeg to establish minimum acoustic insulation requirements for buildings within
More informationMAIN FLOOR PLAN. #G x 14 x 8 Shed - Chicken Coop By SDS-CAD Specialized Design Systems 10'-0" 3'-0" 1'-0" 14'-0" 14'-0" 1'-0" 6'-0" 3'-0"
10'-0" BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. BARN TO BE BUILT AS PER LOCAL CODE REQUIREMENTS 14'-0" BWP BWP BWP ABWP 101
More informationTable of Contents. Page Title
Page Title Table of Contents 1 Floor plan/ Room utilization 2 Elevation (EAST) 3 Elevation (SOUTH) 4 Elevation (WEST) 5 Elevation (NORTH) 6 Foundation plan details 7 Foundation cross sections A Main grade
More informationCarroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage
Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public
More informationDRY CONSTRUCTION SYSTEMS
DRY CONSTRUCTION SYSTEMS Adrienn LEPEL BUTE Dry construction systems Prefabricated elements assembly on site Minimal use of water dry construction systems Assembled partitions Suspended ceilings Raised
More informationBuilding Excellence IV Capital Levy Projects Under Construction
Building Excellence IV Capital Levy Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 14 Genesee Hill Elementary
More informationLIGHTWEIGHT STEEL FRAME M A R G A R E T K R A M E R K E L L Y S T R A U S B E R G E R
LIGHTWEIGHT STEEL FRAME M A R G A R E T K R A M E R K E L L Y S T R A U S B E R G E R BASIC USES Interior Partitions Curtain Walls Load Bearing Walls Floor Joists Roof Trusses INTERIOR PARTITIONS Most
More informationACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings
ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory
More informationA New Path Forward for Tall Wood Construction: Code Provisions and Design Steps
A New Path Forward for Tall Wood Construction: Code Provisions and Design Steps Dallas Wood Design Symposium Ricky McLain, PE, SE Senior Technical Director Tall Wood WoodWorks Wood Products Council Ricky.McLain@Woodworks.org
More informationWood Solutions Fair, 2014, Toronto
Overview of Changes to CSA O86-2014 & Structural Design Provisions for Mid-Rise in OBC Wood Solutions Fair, 2014, Toronto Jasmine Wang, Ph.D., P.Eng. Canadian Wood Council Copyright Materials This presentation
More informationDATE: 4/1/2014 SCALE: 3/16"=1'- 0" SHEET:
Terrace Level First Floor Second Floor Total Back Porch Front Porch Finished NA 1397 SF 743 SF 2140 SF 63 SF 195 SF Unfinished NOTES: All dimensions are framing dimensions, NOT finished dimensions Exterior
More informationEach proposed project will be reviewed for compliance with the following codes as applicable.
VILLAGE OF PALATINE DEPARTMENT OF BUILDING AND INSPECTION SERVICES 200 EAST WOOD STREET PALATINE, IL 60067-5339 Telephone (847)359-9042 Obtaining a Residential Building Permit: Submittal Requirements The
More informationJackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna
Jackson Crossing Located in Alexandria, VA Technical Report 1 Michael Bologna Structural Option Advisor: Dr. Linda Hanagan September 11, 2015 Table of Contents Executive Summary.3 Introduction 4 Purpose..4
More informationLonsdale Building Inspections Department 415 Central Street W. PO Box 357 Lonsdale, MN (507) fax (507)
Lonsdale Building Inspections Department 415 Central Street W. PO Box 357 Lonsdale, MN 55046 (507) 744-2327 fax (507) 744-5554 2006 RESIDENTIAL CONSTRUCTION CHECKLIST The following checklist has been designed
More informationMID-RISE DESIGN & CONSTRUCTION
TECHNICAL BULLETIN No.38-021616 Rev072116 MID-RISE DESIGN & CONSTRUCTION Logix effective R-values range from R-24 to R-28+ Insulated concrete forms (ICF) are becoming a main stream choice for the construction