1 Locrete Building System: the Technology Handbook 1

2 3... Introduction 4... Characteristics 6... Locrete Production 8... Locrete Testing Building with Locrete Shuttering System External Walls Internal Partitions Slabs Adaptability for Expansion Service Installation Photo Gallery 2 CONTENTS

3 Locrete is an innovative patent protected building system for constructing walls and structural slabs. It consists of precast, prestressed concrete elements that have a unified cross section and variable lengths and can span up to six metres. Locrete is intended for various applications in the construction industry ranging from small developments to social housing projects. The system provides a substantial improvement in quality of structure as well as major savings in construction cost, time, equipment and labour. Particular characteristics make Locrete a preferred solution, especially for projects with repetitive nature and modular form. The prestressed Locrete element is the basic building block of this system. It is used in constructing ground beams, insulated external walls, internal partitions and slabs. The system has proven advantages in the construction of boundary walls, retaining walls, hard landscape, highway noise barriers and road barriers. Its applications are various and limited only by the client's imagination. Locrete is currently expanding its global reach through the construction of production facilities where the system advantages can be optimised and where its simple method of application can be best used and developed. 3 Introduction

4 Locrete elements are machine cast, compacted concrete reinforced with prestressed steel wires or strands. The element is designed with a fixed cross sectional dimension and form to allow construction of walls and slabs efficiently and economically, maintaining international and national building codes with superior quality, less cost, time and complexity. The maximum useful length of the element is six metres. The weight of the element is 10kg per metre length. This allows human handling during construction. Concrete strength in the fully cured element is around 50 MPa. The industrialized production of Locrete allows: Virtually limitless configuration of plans and spaces Volumes & Areas Area of cross section is 42.5 cm 2 Volume of a square metre of Locrete in slab is m 3 Elements weigh 10.5 kg per metre Accurate calculation of prices Easy and repetitive structural analysis for the ground beams, walls, suspended beams and slabs Preparation of construction drawings with ease through minimising architectural, structural and services details. 4 General Characteristics

5 Locrete is easy to handle, transport and construct without the use of heavy equipment and with a minimal use of formwork material. It introduces technical benefits in terms of durability, structural sturdiness and the ability to perform better in terms of fire resistance, heat, water and noise insulation. Locrete homes are energy efficient and practially soundproof. They are environmentally responsible, will not rot or rust and require low maintenance and fewer repairs. It provides the best shelter against the elements. The practical and technical advantages of Locrete are provided with a substantial reduction in cost compared to other systems used in the market. Advantages of Locrete Sustainability: minimal maintenance and use of long life material. Affordability: reduction of labour and equipment cost and optimized use of material and reduced waste. Availability: made of commonly available material. Constructability: simplification of construction methods and standardization of technology. 5 General Characteristics

6 Production process is characterised by: Automation of production is a function of the capital value, to be invested in the factory machinary and equipment. Locrete elements are produced in steel pallets, with each pallet able to produce up to 34 sqm per casting. Up to 54 pallets of Locrete elements can be produced in 8-9 hours of work. Annual production can be doubled if double shift work system is adopted. Slab elements are reinforced with 7.94 mm strands, with wall elements are reinforced with 5 mm wires. Slab elements are reinforced with 7.94 mm strands, with wall elements are reinforced with 5 mm wires. Thermal curing rooms are part of the production line. The pallets are stacked in curing rooms by means of a specially designed and fabricated lifting overhead crane. The pallets are lifted from the curing rooms and placed in lines for de-tensioning and emptying. The elements are emptied from the pallets by labour force. Bundles of Locrete elements are compiled and strapped for easy transportation to construction sites. Post emptying the pallets are cleaned and oiled and recharged with the plastic dividers and the strands or wires for re-concreting. Components of a typical production facility include: Batching and mixing plant (30 m3 / hour) 54 pallets Pedestals and pallets pushing motors Casting and concrete vibration equipment Overhead lifting cranes Curing rooms Tensioning and de-tensioning jacks and clamps Locrete elements handling, lifting and loading 6 Locrete Production

7 8 Production Facility

8 A solid slab at six metres span can take up to 250kg dead load and 250kg live load, apart from its own weight. Load bearing tests Tests conducted by VTT of Finland, Labortech of Italy and the Kuwait Institue for Scientific Research found Locrete to be compliant with ACI code Locrete Testing

9 The World Federation of Technical Assessment Organisation (WFTAO) identied six essential requirements for fitness for intended use of construction products: Mechanical resistance and stability Safety, in case of fire Non-threat to hygiene, health and environment Safety in use Protection against noise Locrete is made of concrete, which is: Easily and economically produced for different purposes and to fulfil specified classifications concerning fire-resistance. Durable, exceeding the durability of most other common building materials without requiring additional surface treatment. Highly resistant to moisture and other weather conditions and does not corrode or decay, thus reducing overall maintenance costs. Capable of storing heat which, in turn, helps reduce energy consumption and provides a comfortable indoor climate. This helps insulate building environments from fluctuations in outdoor temperatures. Offers good sound insulation properties. This property finds increased application in certain specialised structures (i.e. highway noise barriers). 10 Locrete Testing

10 Load bearing capacity as a function of span and topping thickness. 11 Structural Results

11 12 Building with Locrete

12 Wall elements are fitted into a pre-fabricated steel shuttering system which forms the caston-site columns. Each column is fitted with the structurally required reinforcement. The walls are built in two planes with 5 cm thick insulation panels fitted into the cavity. After the construction of the walls to the levels specified in the drawings the columns are then concreted and left to dry with the result being a load bearing wall with rigid connections at the column points. The shuttering system is fabricated by the builder according to the design specifications. The specially designed shuttering system for Locrete columns allows for the wall elements, internally and externally, to be constructed to the required heights prior to casting the columns. If building a double wall, 5 cm insulation material in the cavity is enough to meet the heat insulation and energy saving requirements of the construction. This layer can be increased to any thickness to meet required standards of energy saving. Pictured is a section of a Locrete structure with shuttering system still in place. 13 Shuttering System

13 Locrete suspended beams are formed by keeping the central panel independent from the corner columns of the shutter. The custom designed shuttering system for Locrete columns allows the construction of the external and internal walls to the required heights prior to casting the columns. The reinforced concrete columns, once cast, will permanently and rigidly hold the wall elements in position. The inner shutter elements are levelled to the suspended slab level. 14 Shuttering System

14 Strands of Locrete elements overlap with the column reinforcement which enhances the rigidity of hinging Locrete wall elements with the column. The inner shutter elements are levelled to the suspended slab level. Once the reinforced columns are cast permanently, and the shuttering removed, the resulting columns form a rigid hold cementing the wall elements in position. The Locrete system requires the vertical shuttering of the columns only. This allows for designing a flexible and user friendly shutter system that has various applications. Investment in a shuttering system is mandatory but is offset considering the savings in environmental impact, cost of shuttering material, shutter installation, time and effort. 15 Shuttering System

15 Locrete walls are constructed by stacking cut-to-length Locrete elements that are delivered with the wire strand extending 5-10 cm on each end. Door and window openings are accounted for during the production process and the Locrete elements that are delivered are already cut to size and ready for installation. There should be no need to cut Locrete elements on site except for odd shapes or for post-construction modifications. Door and window openings can be framed with precast concrete panels, marble, plastered in frame or as part of internal and/or external wall plastering. Cantilevered slabs are also possible using the Locrete system. 16 Exterior Walls

16 Locrete elements can be cut on-site with a hand tool. The elements on exterior plane of the double wall - or single wall with a beam - can be cut at the existing slab level to allow resting new slab elements for expansion of the structure. Wall elements can be cut, after casting, to allow modification of partitions and opening of doorways, subject to leaving enough elements at the higher level to support the suspended slab units. Single wall partitions are built along with the exterior walls in the manner previously described. A Locrete beam is introduced to take the loads of the slab elements that are suspended and resting on a single beam. The beams are always filled with reinforced or plain concrete depending on the structural calculations. 17 Exterior Walls

17 Locrete wall elements span up to six metres. In all cases, the elements must be hinged on at least one end into cast-on-site reinforced concrete columns. Walls have horizontal joints which can be closed by plastering the walls or by placing bituminous lining between consecutive elements or by lining the joint with chemically treated cementation lining mix. 1 cubic metre of concrete renders m 2 in single-wall area 1 cubic metre of concrete renders m 2 in double-wall area A 1 metre high wall requires 15 elements Sound insulation value (STC rating) is 47 db per square metre 18 Locrete Walls

18 Internal partitions are mostly a single layer of Locrete elements with a total thickness that does not exceed 80mm. 19 Internal Partitions

19 Locrete slabs are made by resting the Locrete elements, cut to the required length, on opposite walls or beams. The slab element bundled and lifted to slab level are stacked side by side. Slab elements are best propped up temporarily when spans are 3-6 metres. Minimal thickness reinforcement steel mesh is installed and the services networks are built above the Locrete elements to counter the effect of shrinkage. Bathroom slabs can be lowered in level to allow for the installation of the services. Plain concrete is cast over the Locrete elements to form a structural suspended slab. The load bearing capacity varies according to span and the thickness of the topping layer, amongst other factors. 20 Slabs

20 Slanted roof with cantilever and flat slabs. Slanted roof with insulation. 21 Slabs

21 Six metre Locrete slab over six metre Locrete beams. 22 Slabs

22 The Locrere Building System makes it easy to introduce architectural modifications to existing buildings, including: 1. Adding window openings by simply cutting through the elements to the width between the jointing columns at a suitable height without jeopordizing the integrity of the structure. 2. Extension of the roof slabs in any direction. One way this can be achieved is by diskcutting the outer two elements at the level of the existing slab or any other preferred level to allow supporting the extension elements on the existing wall elements and then casting the concrete topping. 3. Vertical extensions which can be built with minimal effort or destruction to the existing structure. 23 Adaptability for Expansions

23 Electric conduits are normall flush mounted. Conduit routes in internal partitions are chased out by cutting with a concrete-cutting disk mounted on a hand tool. Pipes are installed in the external wall cavity of the double walls. Service conduits are installed simultaneously with the construction of walls. In slabs, networks are installed prior to casting the plain concrete topping. 24 Service Installation

24 Proposed design for an hospital in The Comoros 25 Photo Gallery

25 Private housing project in Iraq. 27 Photo Gallery

26 Proposed design for a water resorvoir. 28 Photo Gallery

27 30 Photo Gallery

28 31 Photo Gallery

29 Highway barrier. 32 Photo Gallery

30 34 Photo Gallery

Concrete Framing Systems - Walls and Columns

Concrete Framing Systems - Walls and Columns Concrete Framing Systems - Walls and Columns Casting a Concrete Wall Wall Footing Reinforcing Wall Forms Pouring Concrete Finishing the Concrete Controlling Cracking Insulating Concrete Forms (ICF) Tilt-Up

More information

3.4.2 DESIGN CONSIDERATIONS

3.4.2 DESIGN CONSIDERATIONS 3.4.2 DESIGN CONSIDERATIONS Formwork Where Flatdeck sheet is used as formwork, the profile provides resistance to wet concrete (G) and construction loads (Q). Maximum formwork spans given in Section 3.4.4.1

More information

Hollow Core Slabs Applications

Hollow Core Slabs Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Hollow Core Slabs Applications Hollow Core Slabs Technology for the Precast and Prestressed Concrete Industry HOLLOW RESIDENTIAL,

More information

ACOTEC. Acotec panel production D /EN/E 1(14) PROCESS DESCRIPTION ACOTEC PANEL PRODUCTION

ACOTEC. Acotec panel production D /EN/E 1(14) PROCESS DESCRIPTION ACOTEC PANEL PRODUCTION 1(14) ACOTEC Acotec panel production Key words: Acotec, Acotec Line by Elematic, Acotec Panel, partition wall, party wall, internal wall, Aco 2(14) Content page 1. Introduction... 3 1.1. Advantages...

More information

Feasibility of Construction with Hollow-Core Concrete Slabs over R.C.C. Construction: A Case Study

Feasibility of Construction with Hollow-Core Concrete Slabs over R.C.C. Construction: A Case Study Page15 Feasibility of Construction with Hollow-Core Concrete Slabs over R.C.C. Construction: A Case Study Prateek Ghosh, Student, B.E. Final Year, Department of Civil Engineering, BIT Durg. ABSTRACT: After

More information

Miller Collective Safety at Height Solutions EPIC ULTRA Barrier System EPIC Post-N-Barrier System EPIC Basic Barrier System

Miller Collective Safety at Height Solutions EPIC ULTRA Barrier System EPIC Post-N-Barrier System EPIC Basic Barrier System For over 65 years the Miller brand has been synonymous with personal fall protection products and services. As the global leader in safety at height solutions, Honeywell Safety Products introduces a new

More information

PERFECT SLABS Bernie de Klerk

PERFECT SLABS  Bernie de Klerk PERFECT SLABS www.perfectslabs.co.za perfectslabs@gmail.com Bernie de Klerk 071 622 99 33 WHAT ARE PRE-STRESSED HOLLOW CORE SLABS? Hollow core slabs are pre-stressed panels constructed with hollow cores

More information

CONCRETE BLOCK MASONRY

CONCRETE BLOCK MASONRY CONCRETE BLOCK MASONRY CONTENT Introduction Types Manufacturing process Properties Advantages Introduction These are the concrete blocks either hollow or solid. A hollow unit is that unit which has core

More information

Learning Objectives. A Brief History

Learning Objectives. A Brief History Slide 1 Precast Structures and Frames Miles L. Blackman, P.E. Slide 2 Learning Objectives Discuss precast concrete characteristics, advantages and benefits, typical construction methods and construction

More information

TECHNICAL EVALUATION REPORT No. 27/2008/2060

TECHNICAL EVALUATION REPORT No. 27/2008/2060 TECHNICAL EVALUATION REPORT No. 27/2008/2060 Sheet 1 of 16 Sheets This report is a correct record of the measurements and observations made. The report is intended for the private information of those

More information

COMMON ERRORS DURING CONSTRUCTION OF NEW BUILDINGS AND EFFECT OF WORKMANSHIP

COMMON ERRORS DURING CONSTRUCTION OF NEW BUILDINGS AND EFFECT OF WORKMANSHIP Harmonization of European Sound Insulation Descriptors and Classification Standards Florence, December 14 th 2010 COMMON ERRORS DURING CONSTRUCTION OF NEW BUILDINGS AND EFFECT OF WORKMANSHIP Patrizio Fausti

More information

Section 1 - Introduction 1.1 Introduction Welcome to Fox Blocks. You have made an excellent decision to use Fox Blocks Insulated Concrete Forms (ICFs)

Section 1 - Introduction 1.1 Introduction Welcome to Fox Blocks. You have made an excellent decision to use Fox Blocks Insulated Concrete Forms (ICFs) Section 1 Introduction 1.1 Introduction 1.2 Company History 1.3 Description of General Types of ICF Wall System Products 1.4 Description of Fox Blocks ICF Wall System Products 1.5 The Fox Blocks Clever

More information

Construction applications

Construction applications Construction applications General description The 3D steel panels technology was developed in France 25 years ago With an impressive and immediate success (EuroDisney, High Rise in Paris La Defense, the

More information

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction...

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction... TABLE OF CONTENT Equipment kit.... 6 Description of the technology.... 8 Installation of equipment.... 10 Start of construction.... 14 Erection of walls and partitions.... 17 Second floor printing....

More information

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Precast Concrete 1 Definition of Precast Concrete Precasting means casting a concrete member at a place other than where it will be used and then moving it to

More information

High Performance Insulating Concrete Form

High Performance Insulating Concrete Form Insulating Concrete Form High Performance Insulating Concrete Form The Best Way to Build! liteform.com FlexxBlock Insulating Concrete Forms PROVIDE sustainable, energy efficient building envelopes. LiteForm

More information

INSULATING CONCRETE FORMWORK SYSTEM

INSULATING CONCRETE FORMWORK SYSTEM Cl/SfB (21) Gn7+Eq4 November 2004 BecoWallform INSULATING CONCRETE FORMWORK SYSTEM A modern building system which provides extra performance to satisfy current and future building standards Structure and

More information

VARIOUS TYPES OF SLABS

VARIOUS TYPES OF SLABS VARIOUS TYPES OF SLABS 1 CHOICE OF TYPE OF SLAB FLOOR The choice of type of slab for a particular floor depends on many factors. Economy of construction is obviously an important consideration, but this

More information

ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE

ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE ECHO FLOORS (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE Introduction to Echo Floors The oldest company in the group, established in Gauteng in 1982. The core business is the manufacture

More information

Prestressed Hollowcore Slabs PRECAST CONCRETE SOLUTIONS.

Prestressed Hollowcore Slabs PRECAST CONCRETE SOLUTIONS. PRECAST CONCRETE SOLUTIONS Prestressed Hollowcore Slabs HOLLOWCORE: THE CONCEPT Hollowcore slabs are prestressed concrete elements that have a constant cross section. They are manufactured using high tensile

More information

Lecture 13 CONCRETE WORKS

Lecture 13 CONCRETE WORKS Lecture 13 TSP-308 MPK Ferdinand Fassa CONCRETE WORKS Concrete works Concrete is a man-made (rock) construction material, which is a mixture of portland cement, water, aggregates, and in some cases, admixtures.

More information

Concrete Bridge Design and Construction series

Concrete Bridge Design and Construction series www.thestructuralengineer.org 41 CBDC series July 2014 Concrete Bridge Design and Construction series This series is authored by the Concrete Bridge Development Group (CBDG). The group aims to promote

More information

Concrete. Copyright: Quasar Management Services Pty Ltd

Concrete. Copyright: Quasar Management Services Pty Ltd Concrete This training package provides information on basic concrete, including materials, reinforcement, formwork, concrete mix, placement and curing for village infrastructure and houses common in South-

More information

beam - filler block floors beam floors prefabricated in full cross-section

beam - filler block floors beam floors prefabricated in full cross-section Gábor Becker PhD / Gyula Dési titular Docent BUILDING CONSTRUCTIONS 1 Floor structures 2: RC floors and vaults www.epszerk.bme.hu Budapest University of Technology and Economics Faculty of Architecture

More information

cornish concrete products Crosswall Construction low carbon fast track buildings

cornish concrete products Crosswall Construction low carbon fast track buildings cornish concrete products Crosswall Construction low carbon fast track buildings / Basements / double walls / crosswall / Thermofloor / Thermowall / Stairs Introduction What is thermal mass? 30 o C Comfort

More information

Issue Date: April 2003 Release: I. Product Specifications

Issue Date: April 2003 Release: I. Product Specifications Issue Date: April 2003 Release: I Product Specifications Forming System Components Standard System Commercial System Issue Date: April 2003 Release: I 1.1 Issue Date: April 2003 Release: I 1.2 Specification

More information

Reinforced concrete double walls

Reinforced concrete double walls Reinforced concrete double walls Build faster, pay less. Strength in building technology Uses The Kerkstoel reinforced double walls consist of two slabs of reinforced concrete joined to each other by lattice

More information

KANPUR SMART CITY LIMITED

KANPUR SMART CITY LIMITED Nagar Nigam Mukhyalay, 3 rd Floor, Moti Jheel, Kanpur - 208002 Tel.: +91 512 2541258, 2546194 Email:ksclkanpur@gmail.com KANPUR SMART CTY LMTED No.: KSCL/PMC/Open Gym/01/2 Date: 17/02/2018 Reply to queries

More information

Framing Methods Structural Components

Framing Methods Structural Components Framing Methods Structural Components Balloon Framing *Balloon framing or Eastern framing the exterior studs run from the top of the foundation to the top of the highest level. Benefits of this type of

More information

Chapter 2 Notation and Terminology

Chapter 2 Notation and Terminology Reorganized 318 Chapter Titles Chapter 1 General 1.1 Scope 1.2 Purpose 1.3 Interpretation 1.4 Drawings and Specifications 1.5 Testing and Inspection 1.6 Administatration and Enforcement 1.6.1 Retention

More information

PENTABLOCK Technical Information 190mm Series

PENTABLOCK Technical Information 190mm Series PENTABLOCK Technical Information 190mm Series The PENTABLOCK Walling System was developed in consultation with masonry construction stakeholders with an aim of reducing labor time and material costs required

More information

Concrete Block Machines Typical Fixed Block Machine

Concrete Block Machines Typical Fixed Block Machine SEAOG 2016 Masonry Workshop Concrete Masonry Units and Terminology Concrete Masonry in Georgia Georgia World Congress Center Reference: Inspector s Handbook Masonry Institute of America Roy Keck, FACI

More information

Civil Engineering Construction Chapter 5

Civil Engineering Construction Chapter 5 Civil Engineering Construction Chapter 5 Introduction to Floor Dr Mohamad Syazli Fathi Department of Civil Engineering UTM RAZAK School of Engineering & Advanced Technology UTM International Campus August

More information

TOTAL PRECAST SOLUTIONS

TOTAL PRECAST SOLUTIONS TOTAL PRECAST SOLUTIONS SPANCRETE GLOBAL SERVICES GLOBAL HEADQUARTERS, USA SPANCRETE. DECADES OF DEDICATION. When Henry Nagy began the company that became Spancrete in 1946, he focused on his customers

More information

Modular Wood Framing Goes Vertical

Modular Wood Framing Goes Vertical Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported

More information

exceed your energy performance levels

exceed your energy performance levels exceed your energy performance levels www..co.uk discover the better way to build Welcome to Thermohouse Thermohouse is one of the highest quality low energy building system available in Europe today.

More information

Technical Manual. The difference is.

Technical Manual. The difference is. Technical Manual The difference is www.rlsd.com innovation, commitment, support. 2 www.rlsd.com For a service with a difference, choose Richard Lees Steel Decking, the UK specialist steel decking company

More information

COPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31

COPYRIGHTED MATERIAL. Contents. 1 Making Buildings 3. 3 Wood Foundations and. Preface to the Sixth Edition xi. Sitework 31 Contents Preface to the Sixth Edition xi 1 Making Buildings 3 Learning to Build 4 Buildings and the Environment 5 The Work of the Design Professional 11 The Work of the Construction Professional 19 Trends

More information

WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK )

WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK ) WALL SYSTEMS ( Ref: The Building Illustrated, Ching, Francis DK ) 1.0 Comparative wall systems Wood stud walls * walls are normally 2x4, but may be 2x6. * studs are spaced 16. * studs carry vertical loads.

More information

Note on the assessment:

Note on the assessment: Excerpt from: Transitional shelter: 8 designs, IFRC, 2012 Note on the assessment: The following is an excerpt from the Book Transitional Shelters: 8 Designs, IFRC, 2012, available from www.sheltercasestudies.org.

More information

PRE-CAST HOUSE CONSTRUCTION

PRE-CAST HOUSE CONSTRUCTION PRE-CAST HOUSE CONSTRUCTION BDA is a Planning and Development Authority Jurisdictional Area is 1370 sq.km. Developed 64 Layouts Distributed 1,40,000 of sites Developed Infrastructure Works like Ring Roads

More information

Concrete Elements. Concrete Experience... Technology for the Precast and Prestressed Concrete Industry ELEMENTS AND APPLICATIONS PLANT LAYOUT CONCRETE

Concrete Elements. Concrete Experience... Technology for the Precast and Prestressed Concrete Industry ELEMENTS AND APPLICATIONS PLANT LAYOUT CONCRETE Technology for the Precast and Prestressed Industry Elements VIneYARD Posts AND LIntels NORDIMPIANTI CASTING MACHINES ANCILLARY EQUIPMENT CONCRETE ELEMENTS AND APPLICATIONS PLANT LAYOUT SPARES & TECHNICAL

More information

Inverted Double T BEAMS and SLABS Applications

Inverted Double T BEAMS and SLABS Applications NORDIMPIANTI P R O D U C T S APPLICATIONS T U R N K E Y S E R V I C E G L O B A L Inverted Double T BEAMS and SLABS Applications Inverted Double T Beams U Panels Inverted Double T Slabs Inverted Triple

More information

Demidec. cornish concrete products Demidec Flooring and Permanent Formwork

Demidec. cornish concrete products Demidec Flooring and Permanent Formwork Demidec cornish concrete products Demidec Flooring and Permanent Formwork Demidec What is Demidec? Demidec is a thin precast concrete plate, typically 60mm deep, although this can vary depending on the

More information

ORDINANCE NO BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BOULDER, COLORADO: CHAPTER 98 - Baled Straw Structures SECTION PURPOSE

ORDINANCE NO BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BOULDER, COLORADO: CHAPTER 98 - Baled Straw Structures SECTION PURPOSE ORDINANCE NO. 5891 AN ORDINANCE AMENDING CHAPTER 10-5, B.R.C. 1981, CONCERNING ALTERNATIVE BUILDING MATERIALS, INCLUDING ADOBE AND STRAW BALE CONSTRUCTION AND RECYCLED LUMBER. BE IT ORDAINED BY THE CITY

More information

Cellular Lightweight Concrete Technical Specifications

Cellular Lightweight Concrete Technical Specifications Cellular Lightweight Concrete Technical Specifications Cellular Lightweight Concrete building systems have been successfully developed and implemented for more than 85 years to create cost-effective, functional

More information

Structural Technical Report #2 By Robert Whitaker

Structural Technical Report #2 By Robert Whitaker Structural Technical Report #2 By Robert Whitaker Robert Whitaker Structural ~ Parfitt Parkview at Bloomfield Station Bloomfield, NJ 10-31-05 Executive Summary This report covers the comparative redesign

More information

TRITEC light Steel Panel Formwork

TRITEC light Steel Panel Formwork TRITEC light Steel Panel Formwork Perfection made in Germany Various practical illustrations of TRITEC Panel Combinations Guaranteed the largest possible range of sizes with the least possible amount of

More information

Contec is AAC. 1. Contec is AAC

Contec is AAC. 1. Contec is AAC 1. Contec is AAC 1.1 Introduction 1.2 About Contec 1.3 Contec and AAC 1.4 List of Products 1.5 Applications of Contec AAC Products 1.6 Manufacturing Process 1.7 Quality control 1.8 Benefits of Contec AAC

More information

Innovation Construction CIC: B2B Event on MiC

Innovation Construction CIC: B2B Event on MiC Innovation Construction CIC: B2B Event on MiC Presented by Dragages Hong Kong Limited / Dragages Singapore Pte. Limited 06 November 2018 Dragages Hong Kong Introduction ABIGAIL TAM Business Development

More information

PAN PAC PULPMILL TREATMENT TANK

PAN PAC PULPMILL TREATMENT TANK PAN PAC PULPMILL TREATMENT TANK B. PENG 1, M. ROMANES 2, P. GABY 1 1 Holmes Consulting Group 2 Concrete Structures (NZ) Ltd ABSTRACT The recently completed MBBR and AS tank is part of a multi-million dollar

More information

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION An overview of costing strategies for wood framed construction elements CREATING A PROJECT ENDLESS POSSIBILITIES COMPATORS LIST A FLOOR Cast in Place

More information

Atkinson Engineering, Inc.

Atkinson Engineering, Inc. Atkinson Engineering, Inc. Atkinson Engineering, Inc. One of the problems in underpinning a typical post-tensioned foundation is support for the slab part that spans between the stiffening beams. An example

More information

Elevated Slab Sequence

Elevated Slab Sequence Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)

More information

Vision. Values. Truth Integrity Respect

Vision. Values. Truth Integrity Respect www.bnprecast.com WALLTEC WALLS are non-load bearing concrete hollowcore walls manufactured under the strictest quality control in our highly automated state of the art factory using a zero slump concrete

More information

Prestressed Concrete Tanks. Design & Construction

Prestressed Concrete Tanks. Design & Construction Prestressed Concrete Tanks Design & Construction The PRELOAD Advantage PRELOAD has maintained a focused vision on designing and constructing the highest-quality and most-durable liquid storage tanks for

More information

ACI MANUAL OF CONCRETE PRACTICE-2009

ACI MANUAL OF CONCRETE PRACTICE-2009 ACI MANUAL OF CONCRETE PRACTICE-2009 The ACI Manual of Concrete Practice is a six-part compilation of current ACI standards and committee reports. -ACI117-06 to ACI224.3R-95(08) Part 2-ACI 225-99(05) to

More information

Introduction to Masonry Materials and Assemblages

Introduction to Masonry Materials and Assemblages 2:15 PM 4:15 PM Bennett Banting Introduction to Masonry Materials and Assemblages Lecture Outline 1. Overview (5) 2. Masonry Materials a) Concrete Block (20) b) Mortar (15) c) Grout (15) 3. Masonry Assemblages

More information

Residential Building Inspections

Residential Building Inspections Residential Building Inspections Foundations, Grade Beams, Pile Caps, Foundation Pads 1. All trenches or excavations and formwork shall be in accordance with the size(s) and configuration(s) as per approved

More information

Building Products. Mentis Angle Bead. Available ex stock. Tolerances

Building Products. Mentis Angle Bead. Available ex stock. Tolerances Specific building products are made by Mentis for the building industry on special purpose machines. These products are mainly used as reinforcing to prevent plaster and walls cracking. Corners of a building

More information

Guide to using the Ultimate Building Block

Guide to using the Ultimate Building Block Energy efficient Solid Concrete Core High Thermal & Acoustic Insulation All weather Construction Create Curved Walls BRANZ Appraised -#362 4hr FFR- Fire Rated Mechanical Fixing for Linings-Interior & Exterior

More information

AceWall. Injection-Moulded Full-Height Wall Panels. A development of AceWall International Pty Ltd Adelaide, South Australia

AceWall. Injection-Moulded Full-Height Wall Panels. A development of AceWall International Pty Ltd Adelaide, South Australia AceWall Injection-Moulded Full-Height Wall Panels A development of AceWall International Pty Ltd Adelaide, South Australia 1 AceWall AceWall is a fibre-reinforced, reinforced, water-resistant, resistant,

More information

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The Ashland Project Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage The garage and bedroom extend from the front of this three bedroom home, drawing you visually into the entryway. Brick and stucco

More information

ORAK PRECAST LIFELONG BUILDING HIGH QUALITY PRODUCTS DESIGN ENGINEERS SHORT TIME SCHEDULE PRODUCTION EXPERTS TRANSPORTATION FLEET REASONABLE PRICES

ORAK PRECAST LIFELONG BUILDING HIGH QUALITY PRODUCTS DESIGN ENGINEERS SHORT TIME SCHEDULE PRODUCTION EXPERTS TRANSPORTATION FLEET REASONABLE PRICES ORAK PRECAST DESIGN ENGINEERS HIGH QUALITY PRODUCTS PRODUCTION EXPERTS SHORT TIME SCHEDULE TRANSPORTATION FLEET REASONABLE PRICES INSTALLATION TECHNICIANS PROFESSIONAL SERVICES LIFELONG BUILDING Table

More information

1. Non-load-bearing steel framing systems for interior gypsum board assemblies. 2. Suspension systems for interior gypsum ceilings and soffits.

1. Non-load-bearing steel framing systems for interior gypsum board assemblies. 2. Suspension systems for interior gypsum ceilings and soffits. SECTION 09 2216 - PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Non-load-bearing steel framing systems for interior gypsum board assemblies. 2. Suspension systems for interior gypsum ceilings and

More information

SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT

SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT SIMULATED OFFICE PROJECT 2008 TECHNICAL REPORT NEW FACILITY FOR ADULT BASIC EDUCATION AND VOCATIONAL TRAINING By Leigh Hartl Student Number: 207514952 A Report Submitted in Partial Fulfilment of the Requirements

More information

thermal sound insulation

thermal sound insulation The letters LECA stand for Light Expanded Clay Aggregate. Expanded clay aggregates are porous ceramic products with uniform pore structure of fine, closed cells and with densely sintered, firm external

More information

0331 Brick and block construction

0331 Brick and block construction 0331 BRICK AND BLOCK CONSTRUCTION 1 GENERAL 1.1 STANDARDS Materials and construction: To AS 4773.1 and AS 4773.2. 2 PRODUCTS 2.1 DURABILITY Exposure environment: [complete/delete] Exposure locations: To

More information

AN ISO 9001 & COMPANY TENDER DOCUMENT. TENDER No: EPI/WRO/CON/757/0119 FOR

AN ISO 9001 & COMPANY TENDER DOCUMENT. TENDER No: EPI/WRO/CON/757/0119 FOR AN ISO 9001 & 14001 COMPANY TENDER DOCUMENT TENDER No: EPI/WRO/CON/757/0119 FOR Construction of Boundary Wall and allied works for DHH & MCH Hospital at Kendrapara at Odisha state VOLUME III PRICE BID

More information

Bison Precast Flooring Specification

Bison Precast Flooring Specification Page: 1 of 4 1.0 SCOPE OF THE SPECIFICATION 1.01 Floor types: This specification covers the design, manufacture and associated site work for the following floor types; Hollow core floors Composite hollow

More information

cornish concrete products Structural precast

cornish concrete products Structural precast cornish concrete products Structural precast / Ground and edge beams / Retaining Walls / crosswall construction / concrete frames / Staircases and Floors / seating and terracing / Loading Bays / Lift shafts

More information

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed Construction Measurement III SBQ3314 Precast Pre stressed Concrete Works Dr. Sarajul Fikri Mohamed Table of Contents 1. Pre stressed concrete in bridgeworks: technological aspects 2. SMM2 measurement rules

More information

WHATEVER THE CHALLENGE, PHILLIPS HAS YOU COVERED.

WHATEVER THE CHALLENGE, PHILLIPS HAS YOU COVERED. WHATEVER THE CHALLENGE, PHILLIPS HAS YOU COVERED. Build walls and ceilings with a strong base, sturdy reinforcements and much more with Phillips extensive line of high quality products. As a single source

More information

Custom fabrication in two weeks or less, guaranteed.

Custom fabrication in two weeks or less, guaranteed. Custom fabrication in two weeks or less, guaranteed. Ramco is the midwest Kawneer distributor and fabricator. ramcometals.com got lead times? Ramco offers custom fabrication in two weeks or less, guaranteed!

More information

Temporary Structures. Form Materials and Accessories ATCE--II. Advanced Topics in Civil Engineering Form Materials and Accessories ATCE-II

Temporary Structures. Form Materials and Accessories ATCE--II. Advanced Topics in Civil Engineering Form Materials and Accessories ATCE-II Temporary Structures Form Materials and Accessories Practically all formwork jobs require some lumber. Local supplier will advise what material and sizes are in stock or promptly obtainable, and the designer

More information

A monolithic finish, faster and easier

A monolithic finish, faster and easier PLASTER veneers A monolithic finish, faster and easier A smooth, easily plastered surface is essential if you re going to create an even monolithic finish. Begin with an uneven brick surface and you can

More information

Polycrete Big Block Standard Specification

Polycrete Big Block Standard Specification Polycrete Big Block Standard Specification SECTION 03 11 19 INSULATED CONCRETE FORMING 10/13 PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent

More information

Bonner Bridge Replacement Update:

Bonner Bridge Replacement Update: Bonner Bridge Replacement Update: Jerry D. Jennings, PE - NCDOT Division 1 Engineer Pablo A. Hernandez, - NCDOT Resident Engineer September 18, 2017 Bonner Bridge Replacement Timeline Refresher Bonner

More information

ThermaSteel Corporation ASSEMBLY MANUAL

ThermaSteel Corporation ASSEMBLY MANUAL ThermaSteel Corporation ASSEMBLY MANUAL TABLE OF CONTENTS 1- INTRODUCTION 1.1 THERMASTEEL TM WALL PANELS 1.2 Drawing and Element Numbers 2- ASSEMBLY 2.1 Sequence of Assembly 2.2 Preparation of Foundation

More information

RESIDENTIAL COMMERCIAL INDUSTRIAL. Distributed by L.P. Murphy THE ECONOMICAL ALTERNATIVE

RESIDENTIAL COMMERCIAL INDUSTRIAL. Distributed by L.P. Murphy THE ECONOMICAL ALTERNATIVE RESIDENTIAL COMMERCIAL INDUSTRIAL Distributed by L.P. Murphy THE ECONOMICAL ALTERNATIVE WHAT IS ECO-SLAB? BENEFITS OF ECO-SLAB ECO-SLAB is a new building material that is formed by two surface boards with

More information

ECHO PRESTRESS DURBAN (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE

ECHO PRESTRESS DURBAN (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE ECHO PRESTRESS DURBAN (PTY) LTD HOLLOW-CORE CONCRETE FLOORING A NAME TRULY CAST IN CONCRETE INTRODUCTION TO ECHO PRESTRESS In today s world of innovation and fast tracking, the Echo Prestress hollow-core

More information

Value Benefits of Modular Construction in Building Extensions

Value Benefits of Modular Construction in Building Extensions Value Benefits of Modular Construction in Building Extensions SPEED OF INSTALLATION Extensions to existing buildings using modular units can be constructed in less than 50% of the time required for conventional

More information

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site Installing DELTABEAM Installation of DELTABEAM These DELTABEAM installation instructions are intended to complement the project s erection plan. Peikko s technical support can help with the erection plan

More information

Definition of Wall. A continuous, vertical structure Thin relatively to its length and height

Definition of Wall. A continuous, vertical structure Thin relatively to its length and height Walls & Partition Learning Objectives Briefly explain the functions & functional requirements of walls Differentiate and compare between load bearing and non-load bearing walls Briefly describe the characteristics,

More information

HOLLOW CORE FLOORS SPEED AND STRENGTH

HOLLOW CORE FLOORS SPEED AND STRENGTH HOLLOW CORE FLOORS SPEED AND STRENGTH CONTENTS 2 3 4 5 7 8 9 10 12 13 14 INTRODUCTION PRECAST CONCRETE FLOORS T HE A DVANTAGES BISON HOLLOW CORE FLOORS BEARINGS FALSE CEILINGS AND SOFFIT FIXINGS BISON

More information

PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades

PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades PERI UP Easy * The lightweight and fast frame scaffold for safe working on facades Product Brochure * If approval is required for the scaffolding system PERI UP Easy to be placed on the market in a country,

More information

Research on the Economy of Assembled Steel Structure Building Jian-feng LI, Qi-hui ZHAO and Lu-lu HAO

Research on the Economy of Assembled Steel Structure Building Jian-feng LI, Qi-hui ZHAO and Lu-lu HAO 2017 International Conference on Applied Mechanics and Mechanical Automation (AMMA 2017) ISBN: 978-1-60595-471-4 Research on the Economy of Assembled Steel Structure Building Jian-feng LI, Qi-hui ZHAO

More information

ECO-THERM. MOBILE FACTORY Technical information on innovative construction methods

ECO-THERM. MOBILE FACTORY Technical information on innovative construction methods ECO-THERM MOBILE FACTORY Technical information on innovative construction methods The shuttering system ECO-THERM The energy-efficient construction system that can withstand earthquakes In light of the

More information

BISON PRECAST FLOORING SPECIFICATION

BISON PRECAST FLOORING SPECIFICATION BISON PRECAST FLOORING SPECIFICATION 1.0 SCOPE OF THE SPECIFICATION 1.01 Relates to: This specification covers the design, manufacture and associated site work of the following types of floors:- Hollowcore

More information

INTERNSHIP REPORT GOUTHAM.J

INTERNSHIP REPORT GOUTHAM.J INTERNSHIP REPORT GOUTHAM.J M.E Structural Engineering SNS College of Technology, Coimbatore Mail : tcegoutham@gmail.com TEEMAGE PRECAST IN College Road, 1st Cross Street, Tirupur 641602. TamilNadu, India.

More information

_spav prefabbricati s.p.a. historical notes

_spav prefabbricati s.p.a. historical notes _spav prefabbricati s.p.a. historical notes The activity Spav Prefabbricati started its activity in 1960 in the outskirts of Udine (north east of Italy) Until this time it has realized more than 2000 buildings

More information

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION Page 210500-1 SECTION 210500 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

1 Exam Prep Concrete Masonry Handbook Questions and Answers

1 Exam Prep Concrete Masonry Handbook Questions and Answers 1 Exam Prep Concrete Masonry Handbook Questions and Answers 1. According to Concrete Masonry Handbook, a masonry unit is considered as normal weight if it has a density or unit weight of more than pounds

More information

Your guide to the use of ALL PURPOSE CEMENT

Your guide to the use of ALL PURPOSE CEMENT Your guide to the use of ALL PURPOSE CEMENT www.afrisam.com Creating Concrete Possibilities AfriSam All Purpose Cement Mixes for concrete Low-strength concrete 10-15MPa (nominal at 28 days) Suitable for

More information

Unit 4 Brick Masonry. Part Ⅰ Illustrated Words and Concepts. Figure 4-1 Basic Vocabulary of Bricklaying

Unit 4 Brick Masonry. Part Ⅰ Illustrated Words and Concepts. Figure 4-1 Basic Vocabulary of Bricklaying Part ⅠIllustrated Words and Concepts Figure 4-1 Basic Vocabulary of Bricklaying Figure 4-2 The Procedure for Building Brick Walls Figure 4-3 A Reinforced Brick Load bearing Wall Part ⅡPassages Passage

More information

FIREMASTER 60 SERIES. Fire Resistant, Affordable, Innovative

FIREMASTER 60 SERIES. Fire Resistant, Affordable, Innovative FIREMASTER 60 SERIES Fire Resistant, Affordable, Innovative Firemaster 60 Series is a fire resistant, affordable, innovative, and optimal solution for residential and permanent housing applications, providing

More information

Lattice Plate Flooring

Lattice Plate Flooring Lattice Plate Flooring Introduction Pekso Precast manufacturers and supplies a range of precast concrete structural building products ranging from foundations and flooring systems that includes Lattice

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 092216 - NON-STRUCTURAL METAL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-03 11 13.00 10 (May 2014) --------------------------------- Preparing Activity: USACE Superseding UFGS-03 11 13.00 10 (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Housing and Industrialization in Iran

Housing and Industrialization in Iran SESSION One Housing and Industrialization in Iran ROA D, HOUSING A N D URBAN DEVELOPMENT RESEA RCH CENTER (BHRC) FACILITATED BY: Ghazal Raheb Head of architecture and urban development institute, BHRC

More information