Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Size: px
Start display at page:

Download "Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP"

Transcription

1 Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP Canadian Energy Law Foundation March 1, :00 a.m. 12:00 p.m.

2 Introduction Purpose of presentation is to provide a high-level review of common project delivery methods / contracting strategies used in Canada. Three major concerns in any Owner/Contractor negotiation: 1. Schedule 2. Cost 3. Quality (or Completion Risk) Presentation does not discuss: 1. Tax considerations 2. Corporate structure to mitigate liability (e.g. Joint Ventures / Incorporation of Project corporation) 3. Financing of Project 1

3 Market Trends *Information on this slide was taken from albertacanada.com In June 2012 the value of the Inventory of Major Alberta Projects was $193.5 billion, up from $188.2 billion in June The current Inventory is comprised of 874 projects with the infrastructure sector having the largest number of projects. Pipelines accounted for 4% of the new projects (projects added between April 1 and June ) with a value of almost $1.2 billion. Alberta's engineering and construction sector generates annual revenues of $56.5 billion. 2

4 Scale of Projects Most of the construction projects in the Oils Sands are, by their nature, large Capital budgets for such projects range from $250 million to $7+ billion Design and construction of a $3 billion dollar Oil Sands project can involve: Engineering Effort 3.5 million work hours at a cost of $100/h 40,000 to 50,000 design drawings 10,000 to 20,000 vendor and shop drawings Construction Effort 15 million man-hours at a cost of $ per hour Labour force of 10,000 workers with a turnover of 30,000 people Supported by staff personnel Organize, store and retrieve 80,000,000 material items Source: Jergeas, G.F., & Ruwanpura, J. (2010). Why Cost and Schedule Overruns on Mega Oil Sands Projects? Practice Periodical on Structural Design and Construction, 15(1),10. 3

5 Scale of Projects Recent examples of major cost and schedule overruns include: Suncor Millennium Project (2002) months behind schedule, at a cost of $3.4 billion, about 70% percent over the original budget of $2 billion Shell Canada Athabasca (Muskeg River) Project (2003), months behind schedule, at a cost of $5.7 billion, roughly 50% more than the original $3.8 billion estimate The Syncrude Upgrader Expansion 1 Project (2006), roughly two years behind schedule, at a cost of $7.8 billion, about 90% over the original budget of $4.1 billion Phase 1 of the CNRL Horizon Project (2009), months behind schedule, at a cost of $9.7 billion, 43% above the original budget of $6.8 billion first set in 2004 Imperial Oil recently announced that Phase 1 of the Kearl Oil Sands mine will cost $12.9 billion, $2 billion higher than a revised estimate released just 21 months ago, and roughly $5 billion higher than initial estimates 4

6 Understanding Risks With a clear understanding of the desired business deal, the Owner will be in a better position to identify, evaluate and assign associated risks in its contracts. Risk is contractually managed by drafting appropriate: 1. Legal terms (allocate risks between parties) 2. Insurance provisions (pass certain risks to insurance company) 3. Performance Security provisions (pass certain risks to surety, parent company or financial institution) Party best able to manage and mitigate the risk should bear it. 5

7 Overview of Project Delivery Methods Common contract forms include: 1. Design Bid Build Contracts 2. Design Build Contracts 3. Engineering, Procurement, and Construction Management ("EPCM") Agreements 4. Engineering, Procurement, and Construction ("EPC") Agreements 6

8 Design Bid Build Contracts Owner Vendors Engineering Design Trade Contractors Subcontractor Sub-Vendor Owner is the project manager. Owner retains an architect or engineer to design the project and, usually through a tender process, will then hire a Contractor to build the project as designed. 7

9 Design Build Contracts Owner Design/Contractor Design Professional Owner deals with a single entity for both design and construction. Design builder is typically a contractor who sub-contracts the design. Primarily intended to save time. Unlike the Design Bid Build method, the design does not need to be complete prior to tender or construction. 8

10 EPCM Agreements Owner Owner Specialized Process Vendors EPCM Work Contractors EPCM Subcontractors Subvendors as agent for Owner Works Contractor Specialized Process Vendors Pros Owner gets the benefit of independent expertise regarding construction management. Potential to match the best EPCM with the best Construction Contractor. Breaks up the project into smaller, more manageable pieces, wider potential field of RFP applicants to choose from than perhaps would be the case if a single EPC structure was employed. By breaking up the project into smaller pieces, there is the potential to reduce the "risk premiums" often seen when a single entity takes responsibility for the entire management. Cons No single point of contact on disputes relating to risk and commercial matters. Potential for disputes if scopes of work for EPCM and Construction Contractor are not concise (i.e. work that is not clearly allocated to one scope of work or another, referred to as the "gap" problem). Potential for duplication and inefficiencies (duplication in QA/QC across construction Contractor / EPCM) - counter this by having concise scopes of work. 9

11 EPC Agreements 1(a) or 1(b) Owner Owner EPC Contractor EPC EPC EPC Subs Subs Subs Subs Subs Subs Pros Cons 1(a) & (b) Administratively simple (1 point of contact). Less Owner involvement/use of resources by Owner, as opposed to other structures. More potential to shift risk from Owner to EPC Contractor if it is a "turn-key" contract. More potential to avoid labour problems associated with unions (at least from the Owner s perspective) as EPC Contractor usually has pre-existing relationships with multiple unions. 1(a) Avoids integration problems such as gaps in scope of work. 1(a) 1(b) Less control and further reliance on EPC Contractor. Having a single EPC Contractor take responsibility for entire project may result in a narrowing of the field of potential successful EPC bidders (for large projects) which may contribute to higher initial bids. May require some oversight/coordination of multiple EPC Contractors by the Owner (or possibly a Project Management Contractor. May give rise to problems regarding integration of the project gap problem. 10

12 Variations in EPC and EPCM Structures Owner Construction Only Engineering or Engineering and Procurment Procurement only Construction only or Construction and Construction Management Pros Potential to continuously evaluate performance and add or subtract responsibility. More significant control in hands of Owner. Can match specific expertise of contractors to specific task. Flexibility in changing market (Owner hasn t committed to everything up front). Cons Requires more front-end planning and strategy than pure EPC / EPCM structures. Requires increased Owner resources and involvement, organization, follow-up (directly or through Project Manager) in all phases of the project. Multiple interfaces has potential to increase the gap problem. Increased potential for duplication / repetition among Contractors. 11

13 Which Contract to Use? Design Bid Build Contract: If the Owner wants a significant amount of control over the end product and is comfortable with the traditional method of project construction. Design Build Contract: By a sophisticated Owner who wants to save time and have construction begin before design is completed. EPC Agreement: Where Owner wants minimal risk, minimal control and the costs of the final project to be relatively certain. EPCM Agreement: In large and complex projects where the Owner wants to supplement the experience of its project management staff, and the Owner wants control over the design and construction process. 12

14 PAYMENT / COMPENSATION: Fitting the Compensation Regime with the Risk Profile Who Bears the Price Risk? Contractor s Risk Owner s Risk Lump Sum Unit Price Cost Reimbursable ("Cost Plus") *Target Price (can apply to all 3) 13

15 Pricing Scheme: Lump-Sum Owner pays a specified fixed price for all goods and services related to the work - subject to amendment only by Change Order/Change Directive. Contractor bears risk of all out-of-pocket costs. Contractor takes risk/reward of future cost deviation in performing the Work. Higher obligation on Contractor to deliver the work at agreed price. Risk of Contractor attempting to minimize costs vs. quality Owner requires (increased importance of properly negotiated warranty). 14

16 Pricing Scheme: Unit Rate Used when there are quantifiable, well-defined "units", priced on a per-unit basis (similar to a basket of lump-sum prices). Contractor bears risk of delivering particular quantum of units at the agreed price (and often also schedule). Contractor takes risk/reward of future cost deviation of materials required for each unit. If schedule not agreed, Owner takes risk of Contractor productivity. 15

17 Pricing Scheme: Reimbursable Used mainly when scope-of-work or deliverables are not known as of time of Contract award. Owner bears cost-risk (and risk of marketplace supply of materials, equipment and labour). Perception in industry is that there is less impact on Contractor quality as Contractor has no incentive to keep costs down. Audit rights of Owner become key in this type of contract. More administration required of Owner. 16

18 Pricing Scheme: Target Price Used most often with reimbursable pricing but can be applied to all three pricing mechanisms. Target-incentive pricing can be based on a number of factors (e.g. quality, safety, etc.) but is most often based on predetermined target cost or schedule, or both. Risk of controlling costs and schedules shared by Owner and Contractor (usually not shared equally deal specific). 17

19 Project Risks Schedule Delay Delay on a construction project occurs when: the construction of a project or a part of the project is not completed within the time period originally intended and as specified in the contract; or the scope of the work as contemplated in the contract increases to the extent that more work is required to be performed within the original contract time. Options in dealing with delay risk include: Linking compensation to schedule Acceleration clauses The Float Liquidated damages Consequential damages 18

20 Project Risks Cost Overruns Cost over-runs are the additional percentage or dollar amount by which actual costs exceed estimates for the project. This is one area where the parties can be creative in their negotiations when selecting the proper risk allocation for cost over-runs. If Owner's biggest concern is cost, it may want to consider a lump-sum contract. However, Contractor may simply inflate its lump sum price. Options in dealing with cost over-runs include: Incentives for meeting or coming under budget Owner/Contractor sharing of increased costs (e.g. Contractor forfeits its profits up to a specified maximum amount or percentage) 19

21 Project Risks Scope Definition Risks of inadequate scope definition include: Schedule Delays Change Orders/Cost Overruns Rework/Quality Issues 20

22 Project Risks Quality (Completion Risk) Quality is a primary Owner concern. Will the Plant start up and run to design capacity. Completion is a important trigger: project financing warranty periods transfer of risk Incentives/penalties 21

23 Project Risks - Warranty How do warranties differ from construction warranties? Construction warranties usually extend the warranty concept considerably Key Distinction construction warranties are key tools the Owner has to expressly bind the Contractor to perform the construction work, not just a boilerplate confirmation of status 22

24 Project Risks - Warranty What is the purpose of a Construction Warranty? To protect the Owner against defects or failures within the warranty period To provide a remedy to the Owner for defects discovered before or after completion To provide the Owner with a remedy against parties it does not have a contract with (manufacturers, subcontractors and suppliers) but who provide warranties that benefit Owner To define responsibility between the parties 23

25 Project Risks - Warranty Warranty Drafting Points Construction warranties typically are heavily negotiated. The relative strength of negotiating provisions and skill are therefore key Knowledge/Circumstances are also key for example, is this an area where both the Owner and Contractor have expertise? To illustrate we will examine typical components of construction warranty provisions and highlight certain key points for negotiation 24

26 Project Risks - Warranty Warranty Provisions 1. Contractor warrants and guarantees the work Components of this: A.Work shall comply strictly with an agreed upon standard: Owner typically want broad, general standard tied to the scope of the work Contractor typically wants narrow standard or no specified standard Issue of fit for purpose may also be addressed - Contractors increasingly resist use of this term Note: Knowledge of Owner key for example, LNG is a new industry for many Owners and therefore, relies more heavily on Contractors 25

27 Project Risks - Warranty B. Materials and workmanship are free from defects and new Owner wants new Contractor wants flexibility C. Design and engineering free from defects - this relates more to design defects 26

28 Project Risks - Warranty 2. Length of Warranty Owner wants longer term and warranty to start from commercial operations date. Owner may also try and link warranty commencement to when defect is discovered but this creeps into statutory limitation periods and the common law. Owner often seeks explicit language allowing common law and equitable remedies as well as explicit contract remedies. Contractor wants shorter term and warranty to start from installation or immediately after testing/substantial completion (especially on large, multi-faceted projects). Contractor often seeks explicit exclusion of common law and equitable remedies. 27

29 Project Risks - Warranty 3. Warranty Remedies In addition to usual contract remedies for material breach, construction contract warranty provisions often include rework (reperformance of work) obligations for Contractor. Owner typically wants repeated rework by Contractor until the problem fixed. This may be coupled with Owner right to retain self or third party re-works rights at Contractor expense if Contractor re-work fails to remedy defect. 28

30 Project Risks - Warranty 3. Warranty Remedies Contractor wants limited re-work obligations with option to pay specified liquidated damages in event Contractor can t (or if too expensive, won t) fix the problem. LD s usually sliding scale linked to contracted performance standard versus actual impaired performance. Contractor typically wants Owner to pay for in and out costs for warranty re-work. Contractor does not like Owner re-work rights because Contractor can t control quality or costs. 29

31 Project Risks - Insurance Insurance is one option available to ensure that financial capability exists to manage risks. An owner may also want to limit its exposure to nonperformance or defaults by the Contractor by way of: Performance Bond Parent Company Guarantee Letter of Credit 30

32 Project Risks Liability Caps Amount Types 31

33 Project Risks Additional Issues Prime Contractor HSE Technology Counterparty creditworthiness Political Labour Force Majeure Brownfield/Greenfield 32

34 QUESTIONS! 33

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center

EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center EJCDC Contract Documents for America s Infrastructure Buy online at the ACEC Business Resource Center N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

PROFESSIONAL PRACTICE 544

PROFESSIONAL PRACTICE 544 PROFESSIONAL PRACTICE 544 April 20, 2015 Contracting Methods Alternative Project Delivery Methods Michael J. Hanahan, Esq. Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives

More information

CONSTRUCTION MANAGEMENT CORE COMPETENCIES

CONSTRUCTION MANAGEMENT CORE COMPETENCIES CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...

More information

Professional Practice 544

Professional Practice 544 Spring Semester 2017 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights

More information

Professional Practice 544

Professional Practice 544 Spring Semester 2018 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Document Synopses by Series

Document Synopses by Series Document Synopses by Series AIA Contract Documents are divided into six alphanumeric series by document use or purpose: A Series: Owner/Contractor Agreements B Series: Owner/Architect Agreements (p. 13)

More information

Choosing a TSO Supplier

Choosing a TSO Supplier Choosing a TSO Supplier TM on Technical Support Organization (TSO) Roles and Responsibilities John Moore Nuclear Power Engineering Section j.h.moore@iaea.org Vienna, May 16, 2013 International Atomic Energy

More information

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects George F. Jergeas PhD, PEng Professor of Project Management, University of Calgary October 24, 2012: BREAKOUT:

More information

PUBLIC CONTRACT CODE SECTION

PUBLIC CONTRACT CODE SECTION PUBLIC CONTRACT CODE SECTION 22160 22169 22160. (a) The Legislature finds and declares that the design build method of project delivery, using a best value procurement methodology, has been authorized

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

Connoisseur Solutions Project Procurement Management

Connoisseur Solutions Project Procurement Management Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes

More information

Federal Buildings Initiative Qualification Requirements

Federal Buildings Initiative Qualification Requirements Federal Buildings Initiative Qualification Requirements Important Note: Companies who wish to be qualified under the Federal Buildings Initiative (FBI) and who wish to bid on a project for which a Request

More information

The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents

The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents The Greater Toronto Electrical Contractors Association endorses the following CCDC/CCA Documents CCDC Standard Construction Documents CCDC 2-1994 Stipulated Price Contract Standard prime contract between

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL REQUEST FOR PROPOSAL ACQUISITION & IMPLEMENTATION OF A CORPORATE WIDE BOX STYLED STANDARD LOCKERS Proposal Release Date: March 25, 2008 Proposal Due Date: April 25, 2008 Page - 1 - of 9 TABLE OF CONTENTS

More information

Common Myths and Best Practices. By Gr e g o r y A. Ga r r e t t

Common Myths and Best Practices. By Gr e g o r y A. Ga r r e t t Common Myths and Best Practices By Gr e g o r y A. Ga r r e t t 16 Contract Management October 2009 Examining 10 common myths and several best practices of risk management can help you apply an effective

More information

How do FIDIC contracts work

How do FIDIC contracts work How do FIDIC contracts work Zoltán Záhonyi (MSc civil engineer, postgraduate in law) FIDIC Contracts Committee member FIDIC Accredited Trainer Z&Partners Consulting Engineers Ltd. Leading Partner, managing

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY

AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY AMERICAN INSTITUTE OF ARCHITECTS (AIA) DOCUMENT SUMMARY Conventional Project Family A101 2007 (formerly A101 1997) Standard Form of Agreement Between Owner and Contractor where the basis of payment is

More information

Five Global Pty Ltd ABN (0) (0)

Five Global Pty Ltd ABN (0) (0) Five Global Pty Ltd ABN 78 158 704 226 +61 (0) 468 999 561 +61 (0) 427 119 234 Introduction What is the optimum project management model that an Owner should employ to deliver a successful project? It

More information

Meeting the Standard of Care in an Evolving Project Delivery Environment

Meeting the Standard of Care in an Evolving Project Delivery Environment Meeting the Standard of Care in an Evolving Project Delivery Environment Russell Jumper & Tim Fandrey Gray Reed & McGraw Texas Society of Professional Engineers Denton Chapter March 9, 2018 Gray Reed &

More information

What Every APPA Member Needs To Know About Construction Contracts

What Every APPA Member Needs To Know About Construction Contracts 2 What Every APPA Member Needs To Know About Construction Contracts June 18, 2018 Judah Lifschitz, Esq. Principal & Co-President Shapiro, Lifschitz & Schram P.C. lifschitz@slslaw.com (202) 689-1900 3 What

More information

BARBADOS WATER AUTHORITY

BARBADOS WATER AUTHORITY BARBADOS WATER AUTHORITY TENDER FOR BILL PRINTING SERVICES November 2016 1. GENERAL On October 17, 2013, the Barbados Water Authority (BWA) and the Canadian Commercial Corporation (CCC) signed an Agreement

More information

RISK REDUCTION IN DESIGN-BUILD

RISK REDUCTION IN DESIGN-BUILD WHITE PAPER RISK REDUCTION IN DESIGN-BUILD The Design-Build Process Can Dramatically Reduce The Risk Involved In New Facility There is no such thing as a business venture without risk. Expansion, merger,

More information

Owners Perspective on Contracting Domestic Projects

Owners Perspective on Contracting Domestic Projects Projects have become larger and more complicated. Take advantage of the Economy of Scale in the commodity markets. Increased instrumentation due to Process Safety Management. Perception that only large

More information

WEBINAR. The FIDIC 2017 Suite of Agreements. Presenter: Vincent Leloup FIDIC Contracts Committee. Exequatur, 2017

WEBINAR. The FIDIC 2017 Suite of Agreements. Presenter: Vincent Leloup FIDIC Contracts Committee. Exequatur, 2017 WEBINAR The FIDIC 2017 Suite of Agreements Presenter: Vincent Leloup FIDIC Contracts Committee Exequatur, 2017 PROGRAMME 1. FIDIC 2017 SUITE OF AGREEMENTS ROOTS & HISTORY 2. FIDIC 2017 WHITE BOOK MAIN

More information

COMMERCIAL MANAGEMENT. Construction Law Competencies

COMMERCIAL MANAGEMENT. Construction Law Competencies COMMERCIAL MANAGEMENT Construction Law Competencies To exhibit an understanding of contract and civil engineering construction law, to support and recommend appropriate strategies to other members of the

More information

Benefits and Limits to Performance Contracting

Benefits and Limits to Performance Contracting Benefits and Limits to Performance Contracting Massachusetts Municipal Assn November 7, 2008 Steve Morgan President Clean Energy Solutions, Inc. Co-authored by Dave Birr, Synchronous Solutions Benefits

More information

STANDING COMMITTEE ON FINANCE AND ECONOMIC AFFAIRS

STANDING COMMITTEE ON FINANCE AND ECONOMIC AFFAIRS STANDING COMMITTEE ON FINANCE AND ECONOMIC AFFAIRS July 21, 2017 CANADIAN VEHICLE MANUFACTURERS ASSOCIATION (CVMA) SUBMISSION REGARDING BILL 148 AN ACT TO AMEND THE EMPLOYMENT STANDARDS ACT, 2000 AND THE

More information

The Practitioner s Blueprint to Construction Auditing Ron Risner, MBA, CIA, CCA, CCP 2012, The IIA Research Foundation.

The Practitioner s Blueprint to Construction Auditing Ron Risner, MBA, CIA, CCA, CCP 2012, The IIA Research Foundation. The Practitioner s Blueprint to Construction Auditing Ron Risner, MBA, CIA, CCA, CCP 2012, The IIA Research Foundation Table of Contents List of Figures Executive and Preface Acknowledgments About the

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

Legal Issues Related to Design Build

Legal Issues Related to Design Build Legal Issues Related to Design Build Presented by Aaron O. Martin CLARK, MIZE & LINVILLE, CHARTERED 129 S. 8 th, St. Salina, KS 67401 Telephone: (785) 823 6325 Facsimile: (785) 823 1868 aomartin@cml law.com

More information

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical experience in how to organize the contract administration

More information

Decision to Tender or Obtain Quotes

Decision to Tender or Obtain Quotes Decision to Tender or Obtain Quotes The main determinate in deciding whether to tender a request or to simply obtain quotes is not only a matter of value but also depends upon how complicated the purchase

More information

LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA

LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA LAW ON PUBLIC-PRIVATE PARTNERSHIP IN THE REPUBLIC OF SRPSKA Article 1 This Law regulates the scope, principles, manner, and forms of public-private partnership, requirements for the establishment of a

More information

Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017

Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 OPENING REMARKS Kinney Poynter Moderator Executive Director NASACT Alan Pennington Speaker Vice

More information

Construction Contract Basics

Construction Contract Basics PDHonline Course P120 (2 PDH) Construction Contract Basics Instructor: Kevin D. Waddell, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

AIA Contract Documents

AIA Contract Documents AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).

More information

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell: CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process

More information

Procurement Documents for Progressive Design-Build Projects

Procurement Documents for Progressive Design-Build Projects Procurement Documents for Progressive Design-Build Projects March 22, 2013 John Awezec, P.E., DBIA HDR Engineering, Inc. John Doller, P.E. Carollo Engineers, Inc. Peter Hughes Executive Director WDBC Model

More information

Dealing with the EU Data Protection Regulation in Practice. William Long, Partner Sidley Austin LLP February 11, 2016

Dealing with the EU Data Protection Regulation in Practice. William Long, Partner Sidley Austin LLP February 11, 2016 Dealing with the EU Data Protection Regulation in Practice William Long, Partner Sidley Austin LLP February 11, 2016 Do you need to comply? The Regulation will apply to a business processing personal data:

More information

Public procurement rules

Public procurement rules Major infrastructure and energy projects in CEE Public procurement rules Case Study: Poland The European Union will invest 170 billion in ten former Eastern block countries in Central and Eastern Europe

More information

NW&RA & SWANA Joint Advisory 4/17/2015

NW&RA & SWANA Joint Advisory 4/17/2015 JOINT ADVISORY ON DESIGNING CONTRACTS FOR PROCESSING OF MUNICIPAL RECYCLABLES A. INTRODUCTION This joint advisory is being issued by the National Waste & Recycling Association (NW&RA) and the Solid Waste

More information

Section 6: Returnable Bidding Forms / Checklist

Section 6: Returnable Bidding Forms / Checklist Section 6: Returnable Bidding Forms / Checklist This form serves as a checklist for preparation of your Proposal. Please complete the Returnable Bidding Forms in accordance with the instructions in the

More information

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013

FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS. June 1, 2013 FREQUENTLY ASKED QUESTION FOR VDOT DESIGN-BUILD PROJECTS June 1, 2013 For general guidance the following information is provided as an aid to those preparing submittals in response to Design-Build solicitations.

More information

Recommended Practices for Subcontractor Management

Recommended Practices for Subcontractor Management Recommended Practices for Subcontractor Management Athens PM Conference June 18, 2012 Christos Vassilicos Agenda Introduction & Context A Subcontractor Management Case Study Recommended practices across

More information

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff 11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff AUDIT EXECUTION Selecting Audit Samples and Evidence Requirements Sample 2 Sample is a part or proportion of the whole

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

Quality Assurance When Outsourcing: Risk Management to Ensure Quality of Overseas Engineering and Fabrication

Quality Assurance When Outsourcing: Risk Management to Ensure Quality of Overseas Engineering and Fabrication Quality Assurance When Outsourcing: Risk Management to Ensure Quality of Overseas Engineering and Fabrication Classification: Internal 2011-04-04 CANADIAN INSTITUTE ENERGY GROUP S 3RD ANNUAL CONFERENCE

More information

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract

More information

SEPARATED PROJECT DELIVERY SYSTEMS

SEPARATED PROJECT DELIVERY SYSTEMS SEPARATED PROJECT DELIVERY SYSTEMS Separated (aka Traditional) The traditional delivery method typically involves three sequential project phases: The design phase, which requires the services of a designer

More information

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1) The first tier in the systematic approach developed in this guidebook is the Analytical Delivery Decision Approach discussed in Chapter

More information

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for

More information

UNDP Procurement. UNDP Angola Procurement

UNDP Procurement. UNDP Angola Procurement UNDP Procurement The term procurement refers to the process of acquiring goods, works and services. The process spans the whole cycle from identification of needs, choosing the adequate procurement methods,

More information

G , Request for Proposal Land Survey

G , Request for Proposal Land Survey G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994

More information

MINUTES OF THE PRE-BID CONFERENCE MEETING, SWAKOPMUND CLARIFICATIONS 1

MINUTES OF THE PRE-BID CONFERENCE MEETING, SWAKOPMUND CLARIFICATIONS 1 26 March 2013 MINUTES OF THE PRE-BID CONFERENCE MEETING, SWAKOPMUND CLARIFICATIONS 1 CONSTRUCTION OF THE ARTS AND CRAFTS CENTRE IN SWAKOPMUND, ERONGO REGION Ref. MCAN/COM/IFB/1B02008 It is MCA-N policy

More information

Single or multi-sourcing model?

Single or multi-sourcing model? Outsourcing 2007/08 Single and multi-sourcing models Anthony Nagle and Alistair Maughan, Morrison & Foerster www.practicallaw.com/8-380-6567 Once an organisation decides to outsource, one of its biggest

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

Construction Webinar. A comparison of EPC and EPCM contracting and the key risk mitigation measures

Construction Webinar. A comparison of EPC and EPCM contracting and the key risk mitigation measures Construction Webinar A comparison of EPC and EPCM contracting and the key risk mitigation measures 28 January 2016 Overview Different procurement methods Engineer, Procure and Construct (EPC) Engineering,

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER

BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER BASIC HOST COUNTRY CONSTRUCTION CONTRACTING FOR DEVELOPMENT PROFESSIONALS: A PRIMER January 2012 This Primer was produced for the United States Agency for International Development (USAID). It was prepared

More information

Procurement Management Processes

Procurement Management Processes Procurement Management Processes Olga Botero PM630-1004A-01 Contracting and procurement in project management Dr. Tony Prensa October 8 th 2010 Project Procurement Management includes the processes necessary

More information

Considerations for Mechanical, Electrical and Plumbing (MEP) Engineers Pursuing Design Build Projects

Considerations for Mechanical, Electrical and Plumbing (MEP) Engineers Pursuing Design Build Projects www.acec.org/camee CAMEE Council of American Mechanical and Electrical Engineers Considerations for Mechanical, Electrical and Plumbing (MEP) Engineers Pursuing Design Build Projects The material in this

More information

TERMS OF USE CONTRACTOR ENGAGEMENT SOLUTION (CE SOLUTION) FOR SUPPLY OF SERVICES AND EQUIPMENT HIRE IN AUSTRALIA

TERMS OF USE CONTRACTOR ENGAGEMENT SOLUTION (CE SOLUTION) FOR SUPPLY OF SERVICES AND EQUIPMENT HIRE IN AUSTRALIA November 2018 TERMS OF USE CONTRACTOR ENGAGEMENT SOLUTION (CE SOLUTION) FOR SUPPLY OF SERVICES AND EQUIPMENT HIRE IN AUSTRALIA 1. THE CE SOLUTION General These Terms of Use govern the engagement of the

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

19A NCAC 02E.0702 Solicitation and Award of Contract 19A NCAC 02E.0703 Prequalifying to Award - Professional Services Firms

19A NCAC 02E.0702 Solicitation and Award of Contract 19A NCAC 02E.0703 Prequalifying to Award - Professional Services Firms FISCAL NOTE Rule Citation: Rule Topic: NCDOT Division: 19A NCAC 02E.0702 Solicitation and Award of Contract 19A NCAC 02E.0703 Prequalifying to Award - Professional Services Firms Revision of the Requirements

More information

PROFESSIONAL SERVICES CONTRACTING

PROFESSIONAL SERVICES CONTRACTING PROFESSIONAL SERVICES CONTRACTING Table Of Contents Glossary Overview Background Investigative Process Findings And Recommendations Attachments (PDF*) PROFESSIONAL SERVICES CONTRACTING OVERVIEW In San

More information

Section IV. Bidding Forms

Section IV. Bidding Forms Section IV. Bidding Forms 1-1 Section IV. Bidding Forms Table of Forms Letter of Bid... 3 Form of Bid Security (Bank Guarantee)... 6 Form of Bid Security (Bid Bond)... 7 Form of Bid-Securing Declaration...

More information

Construction Contracts

Construction Contracts Construction Contracts By Dr. Ibrahim Assakkaf Construction Contracts By Dr. Ibrahim Assakkaf 1 The Need Web-based Contracts Supporting scheduling Controlling Regulating Analyzing Auditing the procurement

More information

NZ Building Industry Regulation & Compliance Conference Tina Hwang (Associate of Queen City Law) & Brett Heaven (Director of N Compass)

NZ Building Industry Regulation & Compliance Conference Tina Hwang (Associate of Queen City Law) & Brett Heaven (Director of N Compass) NZ Building Industry Regulation & Compliance Conference 2018 Tina Hwang (Associate of Queen City Law) & Brett Heaven (Director of N Compass) The Interplay between Head Contracts & Subcontractors Tina Hwang

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

Procurement Policies and Procedures

Procurement Policies and Procedures Center for Economic and Social Development Procurement Policies and Procedures 1. Purpose of procurement standards. The purpose of these standards is to establish procedures for the Center for Economic

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

Contract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services

Contract Administration: Tips for Improving your Contract Administration Process. Jennifer Adling Director of Procurement Services Contract Administration: Tips for Improving your Contract Administration Process Jennifer Adling Director of Procurement Services Contract Administration Following the award of a contract, the management

More information

SUMMARY OF KEY PPA TERMS AND CONDITIONS BACKGROUND

SUMMARY OF KEY PPA TERMS AND CONDITIONS BACKGROUND MESABA ENERGY PROJECT REPORT TO THE MINNESOTA PUBLIC UTILITIES COMMISSION SECTION VI SUMMARY OF KEY PPA TERMS AND CONDITIONS EXCELSIOR ENERGY INC. December 2005 SUMMARY OF KEY PPA TERMS AND CONDITIONS

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

Re: Expert Review of Prompt Payment and Adjudication on Federal Construction Contracts

Re: Expert Review of Prompt Payment and Adjudication on Federal Construction Contracts March 23, 2018 Singleton Urquhart Reynolds Vogel LLP 150 King St West, Suite 2512 Toronto, ON M5H 1J9 Attn: Bruce Reynolds/Sharon Vogel Re: Expert Review of Prompt Payment and Adjudication on Federal Construction

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Introduction to FIDIC Conditions of contract OUTLINE. What is FIDIC? Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor

Introduction to FIDIC Conditions of contract OUTLINE. What is FIDIC? Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor New tendency in contracts worldwide Introduction to FIDIC Conditions of contract Dr. Mirosław J. Skibniewski, A.J. Clark Chair Professor 1 2 OUTLINE 1. What is FIDIC? 2. Characteristics of FIDIC Conditions

More information

Procurement Australian Clean Energy Summit 2017

Procurement Australian Clean Energy Summit 2017 pwc.com.au Procurement Australian Clean Energy Summit 2017 July 2017 Contents 1 Procurement & Solar Market Snapshot 1 3 ECI / AWA 2 Free-issue Equipment 3 Procurement & Solar Market Snapshot Procurement

More information

Joint Ventures & Teaming Agreements Opportunities 2018 Making Dollars and Sense Selling to the Government

Joint Ventures & Teaming Agreements Opportunities 2018 Making Dollars and Sense Selling to the Government Joint Ventures & Teaming Agreements Opportunities 2018 Making Dollars and Sense Selling to the Government Gregg Funkhouser, Partner 1 Speaker Information Gregg Funkhouser, Partner Dixon Hughes Goodman,

More information

INNOVATIVE CONTRACTING TECHNIQUES AND REASSESSING YOUR CONSTRUCTION CONTRACT IN LIGHT OF THE DEMISE OF MAINZEAL

INNOVATIVE CONTRACTING TECHNIQUES AND REASSESSING YOUR CONSTRUCTION CONTRACT IN LIGHT OF THE DEMISE OF MAINZEAL INNOVATIVE CONTRACTING TECHNIQUES AND REASSESSING YOUR CONSTRUCTION CONTRACT IN LIGHT OF THE DEMISE OF MAINZEAL 19 June 2013 Brian Clayton, Partner 2870273.1 WHAT I WILL COVER Innovative contracting techniques:

More information

Bidding Conditions Attachment C

Bidding Conditions Attachment C Bidding Conditions Attachment C REV Date: November 9, 2018 Project Name (Permit Nos. xxx) at the Fresno Chaffee Zoo Project No. xxxx Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS

More information

Construction Auditing: Where To Start And How to make It Work For Your Organization. Baker Tilly refers to Baker Tilly Virchow Krause, LLP,

Construction Auditing: Where To Start And How to make It Work For Your Organization. Baker Tilly refers to Baker Tilly Virchow Krause, LLP, Construction Auditing: Where To Start And How to make It Work For Your Organization Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International.

More information

2016 National Tribal Transportation Conference

2016 National Tribal Transportation Conference Alaska Tribal Technical Assistance Program Center 2016 National Tribal Transportation Conference Construction Management Darrel Williams Introductions Introduction to Construction Administration Construction

More information

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS

THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS THE ROLE OF CERN IN THE LARGE CONSTRUCTION CONTRACTS FOR LHC CIVIL WORKS Pedro d Aça Castel-Branco ST Division Civil Engineering Group (ST/CE) CERN, Geneva, Switzerland Abstract The contracts for the civil

More information

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY

BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION. for the COUNTY OF ORANGEBURG. Project Number: FY BIDDING INFORMATION FOR HOLLY HILL ADMINISTRATION COMPLEX RENOVATION AND ADDITION for the COUNTY OF ORANGEBURG Project Number: FY13-1206 October 18, 2012 1180 Columbia Avenue Suite 201 29063 (803) 781-1451

More information

Request for Proposal. Labour Supply-Demand Study. Reference Number: Issued: May 9, 2016 Responses Due: May 23, 2016

Request for Proposal. Labour Supply-Demand Study. Reference Number: Issued: May 9, 2016 Responses Due: May 23, 2016 Labour Supply-Demand Study Reference Number: 1605-01 Issued: May 9, 2016 Responses Due: May 23, 2016 Calgary Economic Development Ltd. 731 1 st Street SE Calgary, AB T2G 2G9 Phone: (403) 221-7831 or 1-888-222-5855

More information

Quad Cities Chamber of Commerce. Request for Proposals for HUMAN RESOURCES MANAGED SERVICES

Quad Cities Chamber of Commerce. Request for Proposals for HUMAN RESOURCES MANAGED SERVICES Quad Cities Chamber of Commerce Request for Proposals for HUMAN RESOURCES MANAGED SERVICES Project Manager: Leslie Anderson, Vice President Finance landerson@quadcitieschamber.com 1601 River Dr., Suite

More information

AIA Contract Documents Price List

AIA Contract Documents Price List The American Institute of Architects AIA Contract Documents Price List All products may be purchased from your local AIA Contract Documents Distributor or by calling (800) 365-2724 1/9/2018 Document No.

More information