FLOW DIAGRAMS & PIPING LISTS. Copyright 2007 Fluor Corporation. Lesson Objectives: Lesson Objectives. Flow Diagrams. Flow Diagrams
|
|
- Barry Bradley
- 6 years ago
- Views:
Transcription
1 Copyright 2007 Fluor Corporation FLOW DIAGRAMS & PIPING LISTS Lesson Objectives: Lesson Objectives Flow Diagrams Flow Diagrams
2 Process Flow Diagram (PFD) Process Flow Diagram Process Flow Diagram (PFD) (Sample) 28-B-1 L.O. STILL REBOILER 379mm BTU/NR 28-D-7 L.O. STILL 60 I.D. X 61-0 T-T 180 PSIG 28-D-B L.O. STILL OVERHEAD ACCUMULATOR 48 I.D. X 17-0 T-T 170 PSIG 137 F Process Flow Diagram (PFD) (Sample) PFD Symbology - Vessels
3 Process Flow Diagram (PFD) (Sample) PFD Symbology - Pumps Process Flow Diagram (PFD) (Sample) PFD Symbology Heat Exchangers Process Flow Diagram (PFD) (Sample) PFD Symbology
4 Mechanical Flow Diagram (MFD) aka Piping and Instrumentation Diagram (P&ID) Mechanical Flow Diagram (aka) Piping and Instrumentation Diagram (P&ID) Line Identification Line size Material specification Number of line Unit number Insulation type Tracing Quantity & size of tracers 11-4A6 Ih ST (2-3/8 ) Insulation:
5 Insulation Installation: Typical details for insulated sub-in or tee Typical details for insulated ell Insulation Chart: Personnel Protection:
6 Insulation Details: Typical details at support for piping with shoes: Typical details at support for piping without shoes: Commodity Flow Upstream & Downstream: LINE LIST SAMPLE Copyright 2007 Fluor Corporation
7 Pipe Line List Mechanical Flow Diagram Symbols: INSIDE BOTTOM OF VESSEL H.P.F.S. HEIGHT SET BY PROCESS TANGENT LINE HEIGHT SET BY PROCESS HORIZONTAL VESSEL VERTICAL VESSEL Mechanical Flow Diagram (Sample)
8 Process vs Mechanical Flow Diagrams (Exchangers) Process Flow Diagram Systems & Mechanical Flow Diagrams Process vs Mechanical Flow Diagrams (Exchangers) PROCESS FLOW DIAGRAM SYSTEMS & MECHANICAL FLOW DIAGRAMS Process vs Mechanical Flow Diagrams (Exchangers, cont.) PROCESS FLOW DIAGRAM SYSTEMS & MECHANICAL FLOW DIAGRAMS
9 Mechanical Flow Diagram Symbols: Pump Drivers Electric Motor Steam Turbine Process vs Mechanical Flow Diagrams (Pumps) PROCESS FLOW DIAGRAM SYSTEMS & MECHANICAL FLOW DIAGRAMS CENTRIFUGAL PUMP CENTRIFUGAL IN-LINE PUMP VERTICAL CAN CENTRIFUGAL PUMP Process vs Mechanical Flow Diagrams (Pumps, cont.) PROCESS FLOW DIAGRAM SYSTEMS & MECHANICAL FLOW DIAGRAMS ROTARY PUMP RECIPROCATING PUMP
10 BUILDING AREA 80 - AR CS1T01-3" 80 - AR CS1T01-6" 6" x 3" 10" x 6" 6" 3" 6" 6" 6" 3" VCM UNIT PVC UNIT PE UNIT SD- ETHYLENE UNIT TO C2/C3 STORAGE 75-SD- TO C2/C3 STORAGE C2=/C3=FLARE 10-SD- TO ETHYLENE UNIT 8" x 6" 70-SD-2016 FROM UTILITIES 80 - AR_ CS1T01-12" UTILITIES UNIT 8" x 6" LAO UNIT 75-SD- TO LAO TANKAGE 75-SD- TO LAO TANKAGE 75-SD- TO TRUCK LOADING 75-SD- TO TRUCK LOADING 80 - AR CS1T01-6" 10" x 6" 6" x 3" EO/EG UNIT 6" x 3" 80 - AI CG0T01-2" 8O - AR CG0T01-2" TO GLYCOL TANKING 75-SD- 75-SD- TO GLYCOL STORAGE 77-SD- TO WASTE WATER TREATMENT 80 - AI CG0T85-3" 77-SD- TO WASTE WATER TREATMENT 80 - AR CS1T01-3" 80 - AI CG0T85-3 COOLING WATER / SEAWATER UNIT METERING TO ETHYLENE GROUND FLARE TO ETHYLENE GROUND FLARE TO LAO GROUND FLARE TO LAO GROUND FLARE B A GENERAL: 1. SEE DRAWINGS 00-SD-0002 THRU 00-SD-0006 FOR STANDARD SYMBOLS AND NOMENCLATURE. 2. ALL INSTRUMENT NUMBERS AND PIPING SPECIALTY ITEMS ON THIS P&ID ARE PREFIXED BY WBS NUMBER " 80 " UNLESS OTHERWISE NOTED. NOTES: 1. LOCATED AT UNIT BATTERY LIMITS. 2. LINE SIZES ARE PRELIMINARY. REFERENCE DRAWING TITLE REV DATE PROCESSCTRL SYS PIP EICS PROJ B A None ISSUED FOR IN-HOUSE REVIEW ISSUED FOR IN-HOUSE REVIEW C. HOLLOWELL 06/27/01 Utility Flow Diagrams Utility Flow Diagrams Utility Flow Diagram: (Sample) Utility Flow Diagram: (Sample) 80 - AI CG0T85-4" ETHYLENE UNIT UTILITIES UNIT 80 - AR CS1T01-8" 80 - AI CG0T85-10" 80 - AR CS1T01-3" 80 - AI CG0T85-3" WASTE WATER TREATMENT MAIN FLARE 80 - AR CS1T01-3" PALNT AIR 30-SD- TO LAO UNIT 30-SD- TO LAO UNIT 80 - AR CS1T01-3" 80 - AI CG0T85-3" 78-SD- TO COOLING WATER AREA 78-SD- TO COOLING WATER AREA 80 - AI CG0T85-4" 86-SD- TO BUILDINGS 86-SD- TO BUILDINGS 10-SD- TP ETHYLENE UNIT 72-SD-2016 FROM UTILITIES 72-SD-2016 FROM UTILITIES 20-SD- TO EO / EG UNIT 20-SD- TO EO / EG UNIT 3" x 2" 3" x 2" C2/C3 STORAGE LAO STORAGE TO C2 / C3 FLARE TO C2 / C3 FLARE TRUCK LOADING GLYCOL STORAGE 93-SD- TO METERING STATION 93-SD- TO METERING STATION PIPING AND INSTRUMENT DIAGRAM UTILITIES AND OFFSITES INTERCONNECTING PIPING / PIPE RACKS / 80-SD SD-3008.igr B
11 Questions??
SEA Certified Piping Design Engineer
SEA Certified Piping Design Engineer Certification Course Course Title Eligibility Criteria : SEA CERTIFIED PIPING DESIGN ENGINEER : Mechanical Engineer, Chemical & Petroleum Engineer Duration of Course
More informationGreen Data Center CRYOGEL Ice Ball Thermal Storage
Green Data Center CRYOGEL Ice Ball Thermal Storage Victor J. Ott, P.E. CRYOGEL, San Diego, CA Tuesday, March 1, 2011 4:30 5:30 PM, ACC, Room 207B Copyright Cryogel 2001 Telephone (858) 457-1837 Email:
More informationSURFACE PRODUCTION OPERATIONS
Training Title SURFACE PRODUCTION OPERATIONS Training Duration 5 days Training Venue and Dates Surface Production Operations 5 29 Sep 03 Oct $3,750 Abu Dhabi, UAE In any of the 5 star hotel. The exact
More informationMeasurement Schematics & Facility Delineation Requirements Required by September 11, 2014
Alberta Energy Regulator (AER) Directive 017 - Measurement Requirements for Oil and Gas Operations Version - September 2012 Measurement Schematics & Facility Delineation Requirements Required by September
More informationEnergy. vecta. Forward Thinking
Our people have expertise that has centred around the Energy Industry in Australia, with skills in the development of green field and brown plants. Our people have core competencies in the following areas:
More informationCopyright 2016 ThinkReliability. How a Reactor Works
Cause Mapping Problem Solving Incident Investigation Root Cause Analysis Risk Mitigation Root Cause Analysis Case Study Angela Griffith, P.E. webinars@thinkreliability.com www.thinkreliability.com Office
More informationFUNDAMENTALS OF PROCESS & MECHANICAL ENGINEERING
Training Title FUNDAMENTALS OF PROCESS & MECHANICAL ENGINEERING Training Duration 5 days Training Date Fundamentals Of Process & Mechanical Engineering 5 03 07 May $4,250 Dubai, UAE In any of the 5 star
More informationThermal & Fluids PE References Exam Errata
Thermal & Fluids PE References Exam Errata This product has been updated to incorporate all changes shown in the comments on the webpage and email comments as of February, 2 2018. If you have purchased
More informationSynergies between process energy efficiency and relief loads
Synergies between process energy efficiency and relief loads Mary Kay O Connor Process Safety Center 2008 Symposium Rob Brendel Jacobs Consultancy Inc. (Chicago) Petroleum, Chemicals & Energy Practice
More informationPROCESS OPERATIONS. Introduction to Operations. Diagrams for the Operating Unit. Revised 11/30/18 1
TOPIC Introduction to Operations Diagrams for the Operating Unit OBJECTIVES 1. Discuss the importance of this course as a capstone experience in the Process Technology program and how the material learned
More informationPath Introductory Module to Fundamentals of 01 Oil & Gas Industry. No. Course Title Duration Dates 01 Introductory Module to Fundamentals
Introductory Module to Fundamentals of Oil & Gas Industry Duration Dates Introductory Module to Fundamentals w Feb-Apr 28 of Oil & Gas Industry Sep-Nov 28 14 15 16 17 18 19 20 Process Training Program
More informationSELECTIVE CATALYTIC REDUCTION
SELECTIVE CATALYTIC REDUCTION WHY DO WE HAVE TO USE IT? HOW DOES IT IMPACT THE FACILTY? RON MILLER Gas / Electric Partnership Conference Houston, Texas February 9,2017 THE PRIMARY FUNCTION OF SELECTIVE
More informationProblems at the Cumene Production Facility, Unit 800
Problems at the Cumene Production Facility, Unit 800 Background Cumene (isopropyl benzene) is produced by reacting propylene with benzene. During World War II, cumene was used as an octane enhancer for
More informationPTAC 1302 INTRODUCTION TO PROCESS TECHNOLOGY
Course Overview History of the Process Industry Green Technologies and Related Industries (Optional) Your Career as a Process Technician 1. Describe the following components (aspects) of the PTAC Program:
More informationDirective 017 Heavy Oil GOR Testing Requirements
Directive 017 Heavy Oil GOR Testing Requirements Colby Ruff, Senior Advisor (Measurement Specialist), Industry Operations IMG General Meeting, January 10, 2017 Outline: Current Heavy Oil GOR Testing Requirements
More informationBrazosport College. Syllabus for PTAC Process Technology I Equipment
Brazosport College Syllabus for PTAC 1410 - Process Technology I Equipment Instructor: Gregg Curry Office Phone: N/A Alt. Phone: 979.230.3618 Office: N/A email: gregg.curry@brazosport.edu I. COURSE DESCRIPTION
More informationthermon has a solution for all your heat tracing needs
thermon has a solution for all your heat tracing needs Thermon engineers and specialists located throughout the world ensure that all factors are considered Thermon can provide detailed design engineering,
More informationCOMPLETE REVISION April Process Industry Practices Piping. PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.
April 2012 Process Industry Practices Piping PIP PNC00004 Piping Stress Analysis Criteria for ASME B31.3 Metallic Piping PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost
More informationIHRDC s Competency-Based e-learning Pathways for Petrochemicals Technicians
International Human Resources Development Corporation V.1.0 IHRDC s Competency-Based e-learning Pathways for Petrochemicals Technicians Competency-Based Training pathways for petrochemicals Technicians
More informationINTEGRATION OF A NEW CCGT PLANT AND AN EXISTING LNG TERMINAL AT BARCELONA PORT Abstract ID Number: 155
INTEGRATION OF A NEW CCGT PLANT AND AN EXISTING LNG TERMINAL AT BARCELONA PORT Abstract ID Number: 155 Authors: Rafael Peiró Ripoll, Foster Wheeler Iberia, S.A., Spain Joaquín Gil Abad, Foster Wheeler
More informationPTAC PROCESS TECHNOLOGY II - SYSTEMS. Last Reviewed: Page 1 of 10
Systems Overview Water Systems: Potable Water Fire Water Water Systems: Service/Utility Waste Water Storm Water 1. Describe how process industry facilities are divided into systems. Identify the types
More informationValidation of Deration of Heat Transfer Coefficient with Brine Usage
International Journal of Engineering Research and Development e-issn: 2278-067X, p-issn: 2278-800X, www.ijerd.com Volume 12, Issue 3 (March 2016), PP.20-27 Validation of Deration of Heat Transfer Coefficient
More informationSTEAM BALANCING. Steam Best Practices Sheet 7 WHAT IS STEAM BALANCING? ACCOMPLISHING A STEAM BALANCE END RESULTS OF A STEAM BALANCE
STEAM BALANCING Steam Best Practices Sheet 7 WHAT IS STEAM BALANCING? The steam balance is the most efficient method of gaining knowledge of all aspects of the steam system, such as steam generation, distribution,
More informationField Testing and Independent Review of Post-Combustion CO 2 Capture Technology
Field Testing and Independent Review of Post-Combustion CO 2 Capture Technology Presented by Phil Boyle, President and COO, Powerspan Corp. McIlvaine Company, Carbon Management Strategies & Technologies
More informationLNG Hub in Klaipėda. Mindaugas Aleška Head of Business Development Division SC Klaipėdos Nafta 1
Hub in Klaipėda Mindaugas Aleška Head of Business Development Division SC Klaipėdos Nafta 1 Agenda 1.Introduction to SC Klaipėdos Nafta 2.Regional Drivers for Small-Scale 3. Hub for the Baltic Sea 2 1.
More informationSENSE Level I Welding Process Certification Test Module 3: Drawing and Welding Symbol Interpretation
Multiple Choice: Circle the letter which corresponds to the correct answer. 1. The primary element of any welding symbol is referred to as the a) arrow. b) tail. c) reference line. d) weld symbol. 2. Information
More informationAppendix 8.5 Equipment Summary & Specification Sheets
Appendix 8.5 Equipment Summary & Specification Sheets 59 EQUIPMENT NR. : NAME : REACTORS, COLUMNS & VESSELS SUMMARY R0 Monolith Reactor R02 Riser Regenerator C0 Depropanizer C04 Deethanizer C05 PP splitter
More informationENGINEERING DESIGN GUIDE UNITHERM...
ENGINEERING DESIGN GUIDE UNITHERM... Preface This Engineering Design Guide is directed to the design engineer as a guide for the use of UNITHERM products and accessories in a heat traced system. Product
More informationOil after the Wellhead And the Value of Data
Oil after the Wellhead And the Value of Data A panel discussion featuring: Emile Coetzer Christine Kemp Rhon Rose 1 Copyright 2015, PPDM Association. All Rights Reserved OBJECTIVE Equip Data Managers with
More informationIHRDC s Competency-Based e-learning Pathways for Refinery Technicians
International Human Resources Development Corporation V.1.0 IHRDC s Competency-Based e-learning Pathways for Refinery Technicians Competency-Based Training pathways for Refinery Technicians Our highly
More informationIHRDC s Competency-Based e-learning Pathways for Refinery Personnel
International Human Resources Development Corporation V.2.0 IHRDC s Competency-Based e-learning Pathways for Refinery Personnel COMPETENCY-BASED TRAINING PATHWAYS FOR REFINERY TECHNICIANS Our highly regarded
More informationMulti Well Pad Facility Design. Driving Efficiency & Process
Multi Well Pad Facility Design Driving Efficiency & Process 1 Background Lance McKinnon P Eng. 20 Year Professional Engineer - Alberta, British Columbia Experience from Wellhead to Market - Gas Transmission
More informationIntegrating Risk-Based Inspection Recommendations with Inspection Programs and Integrity Operating Windows
Integrating Risk-Based Inspection Recommendations with Inspection Programs and Integrity Operating Windows Lynne Kaley, PE Principal Trinity Bridge, LLC Savannah, GA W. Clay White Fixed Equipment Network
More informationContents Page. Foreword... xi. 9.8 Pump intake design Introduction Purpose Scope...1
Contents Page Foreword... xi 9.8 Pump intake design...1 9.8.1 Introduction...1 9.8.1.1 Purpose...1 9.8.1.2 Scope...1 9.8.1.3 Nomenclature, primary symbols, and units...1 9.8.2 Design objectives...8 9.8.3
More informationOPERATION SKILLS ENHANCEMENT-MEASUREMENT & INSTRUMENT FOR PROCESS VARIABLES
Training Title OPERATION SKILLS ENHANCEMENT-MEASUREMENT & INSTRUMENT FOR PROCESS VARIABLES Training Duration 5 days Training Venue and Dates REF PE015 Operation Skills Enhancement -Measurement & Instrument
More informationICC-SRCC LISTING. DIVISION: PLUMBING Section: Residential Solar Domestic Water Heater System
ICC-SRCC LISTING SRCC TM Solar Heating & Cooling Code & Standard Listing Program Listing Number: SRCC-16004 Effective Date: May 27, 2017 This listing is subject to re-examination in one year. www.solar-rating.org
More informationModular Oil & Gas Equipment Onshore & Offshore
Modular Oil & Gas Equipment Onshore & Offshore Separators & Desalters AI Energy Solutions onshore and offshore oil process solutions offer innovative technologies packaged with global project management
More informationThe following sub-systems are provided and the integration of these is described below:
The following sub-systems are provided and the integration of these is described below: Pretreatment Plant The Pretreatment Plant typically comprises an amine system for gas sweetening and a molecular
More informationA RISK BASED MAINTENANCE APPROACH for PSM FACILITIES
A RISK BASED MAINTENANCE APPROACH for PSM FACILITIES Mary Kay O Conner O Process Safety Center October 2007 Symposium Adrian L. Sepeda, P.E. President, A. L. Sepeda Consulting Inc. COMMON MAINTENANCE APPROACHES
More informationEnvironmental Testing of an Advanced Flare Tip for a Low-Profile Flare Burning Ethylene
American-Japanese Flame Research Committee Joint International Symposium Advances in CombustionTechnology: Improving the Environment and Energy Efficiency Marriott Waikoloa, Hawaii October 22-24, 2007
More informationIndustrial Mechanic (Millwright) Level 3
Level 3 C1 Shaft Alignment II Duration: 10 hours 3 hours 7 hours This unit is designed to introduce knowledge of the procedures for shaft alignment using the reverse dial method. It is also designed to
More informationCopyright 2004 and 2005 by The American Institute of Architects (AIA)
Page 232500-1 Copyright 2004 and 2005 by The American Institute of Architects (AIA) Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA Modified by MSU Physical
More informationComplicated AQ Regulations
Keeping up with Complicated AQ Regulations IPEC Conference November 10, 2016 Robert Liles (505) 266-6611 NSPS OOOOa Affected Facility Production (Well Site) Gathering Gas Processing Transmission and Storage*
More informationNatural Gas Processing
Natural Gas Processing Technology and Engineering Design Alireza Bahadori, Ph.D. School of Environment, Science and Engineering, Southern Cross University, Lismore, NSW, Australia AMSTERDAM BOSTON HEIDELBERG
More informationFLUID FLOW - PUMPS. Discharge Section. Section. Two main types of pumps: Positive Displacement pumps Centrifugal pumps.
FLUID FLOW - PUMPS 4 3 Control valve Suction Section Discharge Section Two main types of pumps: Positive Displacement pumps Centrifugal pumps ChE 453 - Design I FLUID FLOW - PUMP PERFORMANCE Mechanical
More information3. Design of Structures, Components, AP1000 European
APPENDIX 3E HIGH-ENERGY PIPING IN THE NUCLEAR ISLAND This appendix identifies high-energy piping in the nuclear island with a diameter larger than 1 inch (DN 25 mm). Candidate leak-before-break piping
More informationICC-SRCC LISTING. DIVISION: PLUMBING Section: Residential Solar Domestic Water Heater System
ICC-SRCC LISTING ICC-SRCC Solar Thermal Listing Program Listing Number: SRCC-16004 Effective Date: May 31, 2018 This listing is subject to re-examination in one year. www.solar-rating.org (888) 422-7233
More informationBraemar Technical Services
Braemar Technical Services Cargo Handling and Emergency Shutdown Systems in an LNG cargo vessel - What is the Connection? By Ray Martyn 20 th April 2017 Overview Introduction to the Cargo Handling System
More informationIFC Issued for Construction Jul 30, 2013
Jul 30, 013 Jul 30, 013 Jul 30, 013 Jul 30, 013 4 3 1 NOTES: 1. SEE RAWINGS 00.0000.000.041.007 THRU 016 FOR SYMBOL IENTIFICATION GENERAL NOTES & CONNECTION ETAILS.. ALL INSTRUMENT TAG NUMBERS ARE PREFIXE
More informationUNIT I: UNIFORM FLOW PART B
UNIT I: UNIFORM FLOW PART-A 1 Define open channel flow with example BT-1-1 2 Distinguish between open channel flow and pipe flow. BT-4-1 3 Compute the hydraulic mean depth of a small channel 1m wide, 0.5m
More informationApplying Dynamic Process Simulations Toward Flaring Reduction
Applying Dynamic Process Simulations Toward Flaring Reduction White Paper Siemens AG 2018, All rights reserved 1 Dynamic process simulation has traditionally been a tool of process engineers and process
More informationNOVADOS DIAPHRAGM AND PLUNGER METERING PUMPS
NOVADOS DIAPHRAGM AND PLUNGER METERING PUMPS For more than 80 years, Bran+Luebbe - now SPX Flow Technology has been providing customers with high quality metering, processing and analysing equipment. As
More informationLNG Systems for Marine Application. LNG Reliquefaction & LNG Regasification. Oil & Gas Systems
LNG Systems for Marine Application LNG Reliquefaction & LNG Regasification Oil & Gas Systems LNG reliquefaction plant arrangement for a Q-flex membrane tanker Reliquefaction system for LNG Carriers Hamworthy
More informationINCREASING THE CAPACITY OF NGL RECOVERY TRAINS. Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas de Mayo de 2004
INCREASING THE CAPACITY OF NGL RECOVERY TRAINS Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas WHO IS TECHNIP? 2 World Class Engineering & Construction Group in Oil & Gas Public Company
More informationCentral Plant Management EU 302
Central Plant Management EU 302 Jay Becker, P.E. COURSE OVERVIEW Central Heating & Chiller Plants CHP / Cogeneration / High Voltage Systems Maintenance Staffing COURSE OVERVIEW, continued Contract Work
More informationChallenges in Industrial Waste Heat Recovery. Texas Technology 2006 Showcase Tony Dafft December 6 & 7, 2006
Challenges in Industrial Waste Heat Recovery Texas Technology 2006 Showcase Tony Dafft December 6 & 7, 2006 Outline Plant Statistics and Energy History Tools Used to Identify Projects Sample of Projects
More informationCITY OF SUMNER: CENTRAL WELL DEVELOPMENT
April 27, 2018 2:45 PM PNWS-AWWA Section Conference Room 317 CITY OF SUMNER: CENTRAL WELL DEVELOPMENT Case Study for Manganese and Polysulfide Removal Barney Santiago, PE RH2 Engineering, Inc. AGENDA 1.
More informationPNWS AWWA Annual Conference Eugene, Oregon 2014 Chemical System Design 30 Years of Lessons Learned May 2014
PNWS AWWA Annual Conference Eugene, Oregon 2014 Chemical System Design 30 Years of Lessons Learned May 2014 Mark D. Ryan, P.E. BCEE CDM Smith Portland, Oregon ryanmd@cdmsmith.com CHEMICAL SYSTEM PROBLEMS
More informationCentral Plant Management EU 302
Central Plant Management EU 302 Jay Becker, P.E. KEY POINTS TAKE AWAYS Plants are vital Know Needs & Meet Needs Reliability Economics Planning & Communication O & M; Efficiency; Sustainable Staff (training,
More informationNatural Gas Dehydration
Natural Gas Dehydration Lessons Learned from Natural Gas STAR Producers Technology Transfer Workshop Devon Energy and EPA s Natural Gas STAR Program Fort Worth, TX June 6, 2006 Natural Gas Dehydration:
More informationAnnexure-1 Brief on Production and manufacturing process ONGC Petro additions Ltd (OPaL), a joint venture Company of Oil and Natural Gas Corporation Limited (ONGC), Gas Authority of India Limited (GAIL)
More informationthermon has a solution for all your heat tracing needs
thermon has a solution for all your heat tracing needs Thermon engineers and specialists located throughout the world ensure that all factors are considered Thermon can provide detailed design engineering,
More informationQuest GHG and Energy Report
Controlled Document Quest CCS Project Quest GHG and Energy Report Project Document Title Quest CCS Project Quest GHG and Energy Report Document Number Document Revision Document Status Operate Revised
More informationTraining Certification Categories
Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and
More informationOPTIMIZATION OF DISTRICT HEATING SYSTEMS
OPTIMIZATION OF DISTRICT HEATING SYSTEMS STEAM VS. HOT WATER TKDA Presenters TKDA Presenters Lon Fiedler and Rusty Steitz Optimization of District Heat Systems Steam vs. Hot Water District Heat System
More informationAppendix A. An Introduction to Steam Turbine Selection
Operator s Guide to General Purpose Steam Turbines: An Overview of Operating Principles, Construction, Best Practices, and Troubleshooting. Robert X. Perez and David W. Lawhon. 2016 Scrivener Publishing
More informationEDITORIAL REVISION August Process Industry Practices Insulation. PIP INEG2000 Guidelines for Use of Insulation Practices
August 2013 Process Industry Practices Insulation PIP INEG2000 Guidelines for Use of Insulation Practices PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry
More informationCentral Heating Plants EU 311
Central Heating Plants EU 311 Jay Becker, P.E. KEY POINTS TAKE AWAYS Why Central Plants? Boilers & Fuels Water Treatment Environmental Issues Clean Air & Clean Water COURSE OVERVIEW Central vs. Individual
More informationChemSepT Engineering Pvt. Ltd
Your Partner for Complete Turnkey Solutions ChemSepT Engineering Pvt. Ltd Project Design Manufacturing Procurement Service Commissioning www.chemsept.in info@chemsept.in +91-9763-36-4744 Complete Turnkey
More informationMetropolitan Community College COURSE OUTLINE FORM
(Page 1 of 7) Course Title: Course Prefix & No.: PROT 2310 Steam Plant Operation I LEC: LAB: 4.5 0 Credit Hours: 4.5 COURSE DESCRIPTION: This course introduces students to skills generally required for
More informationPumps, Turbines, and Pipe Networks, part 2. Ch 11 Young
Pumps, Turbines, and Pipe Networks, part 2 Ch 11 Young Pump and Turbine Dimensional Analysis (11.5 Young) Say we want to replace turbines on the Hoover Dam Want to have a good design Essentially impossible
More information20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile
Contents Power Plants Steam Power plants Binary Power plants Geothermal Power Plants Single flash systems Binary systems 1 Equipment Well head Gathering piping system Steam separators and moisture separators
More informationBRAZOSPORT COLLEGE. Syllabus for PTAC 1302 Introduction to Process Technology
BRAZOSPORT COLLEGE Syllabus for PTAC 1302 Introduction to Process Technology Instructor: Paul Meiller Office Phone: 979.230.3618 Alt. Phone: Office: No office email: paul.meiller@brazosport.edu I. COURSE
More information16 Construction/Start-Up Phase
16 Construction/Start-Up Phase An Illustration of the Checklist Analysis and Safety Review Methods 16.1 Problem Definition Background It is the third year of ABC's project and they are finishing their
More informationThermal Distribution in District Energy and Cogeneration Systems
International District Energy Association Thermal Distribution in District Energy and Cogeneration Systems Presented by William A. Liegois, P.E. Stanley Consultants, Inc. Topics Principles of Hot Water
More informationhydraulic piping B1E7451EEF6816B06D3316AA77C4CAA3 Hydraulic Piping 1 / 6
Hydraulic Piping 1 / 6 2 / 6 3 / 6 Hydraulic Piping This Handbook covers several technical aspects which are meant to help in the engineering process of a system together with standards. Hydraulic Piping
More information[4163] T.E. (Mechanical) TURBO MACHINES (2008 Pattern) (Common to Mech. S/W) (Sem. - II)
Total No. of Questions : 12] P1061 SEAT No. : [Total No. of Pages : 7 [4163] - 218 T.E. (Mechanical) TURBO MACHINES (2008 Pattern) (Common to Mech. S/W) (Sem. - II) Time : 3 Hours] [Max. Marks :100 Instructions
More informationAP1000 European 9. Auxiliary Systems Design Control Document
9.2 Water Systems 9.2.1 Service Water System The service water system (SWS) supplies cooling water to remove heat from the nonsafety-related component cooling water system (CCS) heat exchangers in the
More informationABENER. Challenges in Thermal Energy Storage Systems. Abener Engineering and Construction Services. Presented by: Mark Cowell
ABENER Abener Engineering and Construction Services Challenges in Thermal Energy Storage Systems Presented by: Mark Cowell Engineering and construction for sustainability Challenges in thermal energy storage
More informationProcess Equipment Cost Estimation
DOE/NETL-2002/1169 Process Equipment Cost Estimation Final Report Prepared for: National Energy Technology Center P.O. Box 10940, 626 Cochrans Mill Road Pittsburgh, PA 15236-0940 and P.O. Box 880, 3610
More information(a) the inlet and exit vane angles, (b) work done (c) Efficiency of the system. [16]
Code No: R05310302 Set No. 1 III B.Tech I Semester Regular Examinations, November 2007 HYDRAULIC MACHINERY AND SYSTEMS ( Common to Mechanical Engineering and Automobile Engineering) Time: 3 hours Max Marks:
More informationKeys to Excellence in the Practice of Process Engineering. An overview by Scott D. Love, P.E. October 2016
Keys to Excellence in the Practice of Process Engineering An overview by Scott D. Love, P.E. October 2016 Outline What is excellence? How do I learn about my process? Learning examples Summary Questions?
More informationField GHG Reduction Projects Dehydration Optimization. February 10, 2016
Field GHG Reduction Projects Dehydration Optimization 1 Dehydration Optimization Video 2 Overview CPC currently has approximately 80 operating dehydration facilities Industry has 2000+ operating dehydration
More informationTHE MISSING LINK - OBJECT ORIENTED ESTIMATING
71 THE MISSING LINK - OBJECT ORIENTED ESTIMATING A PAPER BY AAFJE JANSEN-ROMIJN During the decision making process of investment projects, it is often not possible to wait for the final cost estimate,
More informationAPPA Institute, Dallas TX, February
Heating System Distribution EU 332 Jay W. Becker, PE Key Points Take Aways Planning is vital Build for the future Know Campus layout Reliability meeting needs Economics / options / trade offs Good Design
More informationProducts II 1 VERTICAL LINE SHAFT PRODUCT AND OIL LUBRICATED PUMPS II 2 SUBMERSIBLE PUMPS II 3 MIX FLOW PRODUCT AND OIL LUBRICATED PUMPS
II Products II 1 VERTICAL LINE SHAFT PRODUCT AND OIL LUBRICATED PUMPS PAGE II-2 II 2 SUBMERSIBLE PUMPS PAGE II-4 II 3 MIX FLOW PRODUCT AND OIL LUBRICATED PUMPS PAGE II-5 II 4 AXIAL FLOW PRODUCT AND OIL
More informationOptimized System for Your Bottom Line. Trane Training Class 1 Dec, 2017
Optimized System for Your Bottom Line Trane Training Class 1 Dec, 2017 Total Cost of Ownership Setting your system for great payback Where is money spent over a 30 year lifetime? First Cost 4.9% Service
More informationUNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT
UNIQUE DESIGN CHALLENGES IN THE AUX SABLE NGL RECOVERY PLANT Presented at the 81 st Annual Convention of the Gas Processors Association March 11, 2002 Dallas, Texas Joe T. Lynch, P.E. Ortloff Engineers,
More informationManure Management Program
Manure Management Program www.manuremanagement.cornell.edu Anaerobic Digestion at Aurora Ridge Farm: Case Study Curt Gooch, P.E. and Jennifer Pronto Dept. of Biological and Environmental Engineering, Cornell
More informationPUMPS MANUFACTURING COMPANY POSITIVE DISPLACEMENT PUMPS FOR OIL&GAS AND MARINE APPLICATIONS. Technical Specification. since 1952
PUMPS MANUFACTURING COMPANY POSITIVE DISPLACEMENT PUMPS FOR OIL&GAS AND MARINE APPLICATIONS Technical Specification since 1952 1 2 index HR/HRV Twin Screw Pump Series 4 HD/HDL/HDV Twin Screw Pump Series
More informationLARGE STORAGE TANK PROJECT
INTRODUCTION The Fairbanks Large Storage Tank is part of the Interior Energy Project (IEP) designed to expand natural gas distribution in Fairbanks and Interior Alaska. A tank with a capacity of 0.44 Bcf
More informationInsulated Jacketed Tubing
Insulated Jacketed COILED STICK CUT TO LENGTH Pre-Insulated UTC Pre-Insulated tubing is designed for the applications where a minimum heat loss is requested. This product provides a solution for maintaining
More informationDownsizing a Claus Sulfur Recovery Unit
INFRASTRUCTURE MINING & METALS NUCLEAR, SECURITY & ENVIRONMENTAL Downsizing a Claus Sulfur Recovery Unit OIL, GAS & CHEMICALS By Charles L. Kimtantas and Martin A. Taylor ckimtant@bechtel.com & mataylo1@bechtel.com
More informationGreen economy with natural refrigerants
Green economy with natural refrigerants by Reducing Ammonia Charge in Industrial Refrigeration Systems Using Direct Expansion by Bruce I. Nelson, P.E. President Colmac Coil Manufacturing, Inc. Background
More informationYour Service Partner Service Solutions for the Oil and Gas Industry
Your Service Partner Service Solutions for the Oil and Gas Industry A Partner You Can Trust Customized and innovative service solutions help you to reduce maintenance time and cost, and improve the efficiency
More informationVERIS Accelabar. Superior Flow Measurement Accuracy
VERIS Superior Flow Measurement Accuracy Designs, materials, weights and performance ratings are approximate and subject to change without notice. Visit for up-to-date information. ...A New Idea in Flow
More informationFinal Report for Chevron Vapor Recovery Unit Project
Final Report for Chevron Vapor Recovery Unit Project Submitted to: Wesley Brubaker, Project Engineer Chevron Houston, Texas Prepared by: Leslie Esparza Krisha Mehta Sean Swearingen, Team Leader Mechanical
More informationGreen FSRU for the future
Green FSRU for the future Presentation at GREEN4SEA Athens April 6 th 2016 Dr. John Kokarakis Vice President Technology & Business Development, Africa, S. Europe Hellenic, Black Sea & Middle East Zone
More informationTarget Inline Flowmeter
Principle of Operation Flow is measured in terms of dynamic force acting on a target (solid disk) in the flow stream. Hermetically sealed, bonded strain gages in a bridge circuit configuration mounted
More informationDistillation Experiment--Flooding
Lab Report Distillation Experiment--Flooding by Andrew Yu-Hao Chang Karri Lynn Crawford David Marion Genna [NOTE: The report has been minimally edited for clarity and consistency.] Submitted to Dr. C.
More information