1 EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS) (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 1 of 23
2 The following presentation discusses the review, evaluation and repair of a corrosion damaged post-tensioned roof lift slab. The process used may be applicable to many similar structures that are in service today throughout the country. The subject structure is a three story post-tensioned lift slab residential structure along the Central Coast of California. The 8 thick slabs were lifted in two sections (approximate section area of 5000 sq. ft). Built in or around 1960, the roof slab due to its location and a combination of poor detailing, lack of proper maintenance and old technology suffered serious corrosion deterioration to significant portion of its prestressing steel. (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 2 of 23
3 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 3 of 23
4 1. Visual Inspection and Site Assessment 2. Review of As Built Structural Plans 3. Destructive and Non-Destructive Testing to allow Inspection of Post-Tensioning Wires, Mild Reinforcement, Anchorages, Embeds, Etc 4. Structural Analysis and determination of possible Repair Options: a. Evaluation of Original Capacity b. Evaluation of Existing Capacity c. Determination as to the Need of Repair d. Review of possible repair options e. Analyze roof slab with the different retrofit options 5. Execution of Chosen Repair Method 6. Durability Considerations (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 4 of 23
5 1. Visual Inspection and Site Assessment: a. Scan the site for spalled or excessively cracked concrete b. Document locations of visibly broken tendons c. Inspect tendons live and dead ends locations d. Document locations of apparent rust / corrosion e. Review slab to column connections It is worth stating that in this case, the extent of spalled concrete at the slab to column connections, prompted the engineer to require that shoring be installed at all locations with apparent damage. Further investigation was needed to assess the damage and determine the appropriate action. Patched Area at Slab Collar (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 5 of 23
6 Spalled Concrete at a Broken Tendon near a Column (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 6 of 23
7 Broken wire Tendon exposed Upon Removal of Roofing Material Broken Tendon due to severe corrosion (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 7 of 23
8 2. Review of As Built Structural Drawings Often times, as-built plans for privately owned buildings are not well kept and finding structural information can prove to be a difficult task. In this case, a partial set of structural drawings for a twin building was located. Though certain connections were done differently based on the actual field conditions (slab collars to column connections in this case), useful information was obtained from these documents: a. Material properties for concrete, mild reinforcement and prestressing b. Member sizes and reinforcement cover c. Reinforcement size and quantities d. Post-tensioning system used e. Post-tensioning forces and profiles This information was vital in assessing available capacities and the extent of structure retrofit work. In their absence, a tremendous amount of destructive and non-destructive testing would be required to develop a sense of the slab capacity. (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 8 of 23
9 3. Destructive and non-destructive Testing to allow inspection of Post-Tensioning wires, mild reinforcement, anchorages, and slab collar to column connections: Even though the as-built plans are helpful in providing the conditions of the building at the time of construction completion, destructive testing is essential in determining the condition of the embedded items within the concrete at the time of the investigation. Rust stains, spalling of concrete are the symptoms and exposing these various elements can expose the root of the problem and its extent. As the investigative engineer, it is our responsibility to develop a comprehensive testing plan that provide the necessary information to provide an opinion upon which an owner and his contractor can determine the feasibility of structure repair or replacement. Depending on the evidence of corrosion, sufficient number of tendons need to be exposed and examined at high points, and possibly low points as well near their anchorages. In the case of the roof slab herein, every tendon was exposed at one of their high points. Additionally, the anchorages at the tendons dead and live ends were exposed at several spots. Furthermore, all accessible slab collar to column connections were exposed at the slab soffit with some at the slab surface as well to ensure that the connection was not undermined by corrosive action of the salt water. Furthermore non destructive testing of the welds was performed (Magnetic particle imaging). This is important as the failure of these connections would be catastrophic. The result of the testing showed that the slab column connections were not impaired. However, due to the use of a continuous 8 wide pour strip at the tendons stressing ends, and pour water proofing conditions, extensive damage was observed near the tendons live ends and along the tendons near the slab surface (high points). The investigation showed that for the 202 tendons in the roof slab, there were 15 broken tendons, 64 corroded tendons and 123 rusted tendons (no significant pitting). (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 9 of 23
10 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 10 of 23
11 Exposed Slab / column connection (slab soffit) Exposed Slab / column connection (roof slab surface) (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 11 of 23
12 Pitted Wire Tendon Another example of Pitted Wire Tendon (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 12 of 23
13 Exposed Anchor at Dead End (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 13 of 23
14 Severely Corroded Anchor Plate Completely Corroded ¼ wires at Live End of Tendon (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 14 of 23
15 Exposed Tendons at High Point of Profile (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 15 of 23
16 Preparation for lift off of a Wire Tendon (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 16 of 23
17 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 17 of 23
18 4. Structural Analysis and selection of retrofit scheme: The structural analysis of the existing roof slab involved four stages: a. Determine required reinforcement based on self weight and code prescribed live load slab. Also, compute service stresses and deflection assuming all PT tendons are fully effective (to establish the available level of redundancy). b. Determine the present load carrying capacity based on the loss of the broken and the severely corroded tendons (based on all testing and investigation results). Determine need of repair and its extent c. Review of possible repair options d. Analyze roof slab with the different retrofit options a. Determine required reinforcement based on self weight and code prescribed live load slab. This step is performed early prior to completion of the bulk of investigation of visual inspection but subsequent to the execution of visual inspection. It is important as it serves as a clear indication of the redundancy of the slab (specifically in lean designs where little redundancy is available). As lift slabs are designed for construction loads and the stresses they are subjected to during the lifting operation, the analysis, in this case showed that for the load (floor dead load and code live load), the concrete experienced no tension stresses for all practical considerations. This in turn allowed the engineer more options in the retrofit schemes. b. Determine the present load carrying capacity based on the loss of the broken and the severely corroded tendons (based on all testing and investigation results). The investigation showed that a significant portion of the tendons were corroded or broken (more than one third of the total). This portion of the analysis showed that the residual slab reinforcement, with the damaged tendons considered ineffective, is not adequate to support the roof dead and live load and that the slab needs to be repaired. (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 18 of 23
19 c. Review of possible repair options. Three repair options were considered. The first two options considered a long term solution to the corrosion issue. These options addressed the fact that all the tendons had incurred some damage (since the investigation did not look at the entire length of every tendon). Option one involves the introduction of a network of upturned beams to carry the roof slab and it called for a portion (to be determined by analysis) of the existing tendons to be replaced with 0.6 diameter strands. The second option called for all existing wire tendons to be replaced with 0.6 diameter strand tendons. The third option considered the immediate need for repair and called for all the broken or severely damaged tendons to be replaced using 0.6 diameter strand. d. Analyze roof slab with the different retrofit options The analysis of the roof slab using newly placed network of upturned beams showed that 25% of the existing tendons need to be replaced using 0.6 diameter strand tendons. With this option, the loss of all remaining wire tendons would have no impact on the capacity of the retrofitted roof system to carry its service loads. The analysis of the roof slab considering the replacement of all wire tendons with strand tendons did not yield positive results and led to the withdrawal of this option. The analysis of the roof slab considering the replacement of approximately 80 wire tendons (effective force of 46.4 kips) with 0.6 strand tendon (effective force of 40 kips) showed that the repaired slab met the code strength requirement for the roof service loads. (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 19 of 23
20 5. Execution of chosen repair method: With option one and three to choose from, the owner opted to deal with their immediate needs and decided to repair the broken or severely corroded tendons. Since those tendons requiring replacement were spread out throughout the structure, the work was performed with little inconvenience to the residents. Tendons replacement was sequenced as to eliminate shoring of the slab. Tendons anchorage areas were chipped out and removed allowing access to remove the existing wires. The void was then pumped full with grease. Bare 0.6 diameter strands were further greased and pulled through the existing void. New encapsulated anchorages were applied in the field. High strength grout was poured behind the anchorages and the tendons were stressed and anchored. New 0.6 diameter Strand Tendon at Live End (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 20 of 23
21 New 0.6 diam. Strand Tendon with Encapsulated Anchor at Live End (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 21 of 23
22 New 0.6 diameter Strand Tendon at Dead End (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 22 of 23
23 6. Durability considerations: It is interesting to note that the removed wire strands exhibited corrosion damage for portion that were closest to the top of the concrete (high points). Also, due to the type of roof water proofing moisture appeared to cause serious corrosion damage at the cold joint between the main roof slab and the stressing pockets of the wire strands (no grease was observed to be left at these locations). Additional concrete top cover and proper detailing of water proofing at the cold joint as well as periodic maintenance of the roof membrane could very likely prevented much of the corrosion damage observed. (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHT RESERVED 23 of 23
Post-tensioned Structures Solutions for Repair and Protection
Post-tensioned Structures Solutions for Repair and Protection Concrete Preservation Alliance Vector Construction, Vector Corrosion Technologies, and Vector Corrosion Services are working to advance the
More informationEvaluation and Repair of Existing Post- Tensioned Buildings with Paper Wrapped Tendons Experiencing Corrosion Damage
Evaluation and Repair of Existing Post- Tensioned Buildings with Paper Wrapped Tendons Experiencing Corrosion Damage K. Dirk Bondy, S.E. President Seneca Structural Engineering, Inc. The Great American
More informationThe Assessment of Concrete Structures affected by Steel Corrosion
THE HIGHWAYS AGENCY BA 51/95 THE SCOTTISH OFFICE DEVELOPMENT DEPARTMENT THE WELSH OFFICE Y SWYDDFA GYMREIG THE DEPARTMENT OF THE ENVIRONMENT FOR NORTHERN IRELAND The Assessment of Concrete Structures affected
More informationCSU GUIDELINES. April 27, 2018 FOR POST-TENSIONED CONCRETE STRUCTURES.
CSU GUIDELINES FOR POST-TENSIONED CONCRETE STRUCTURES April 27, 2018 http://www.calstate.edu/cpdc/ae California State University Seismic Review Board Technical Guidelines January 9, 2018 The CSU Seismic
More information1. Cast-in-place concrete is specified in Section
SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record
More informationEvaluation and Repair of Post-Tensioned Concrete
Evaluation and Repair of Post-Tensioned Concrete Tank and Thin Shell Roof by Keith Kesner, Ph.D., PE P.E. Randall W. Poston, Ph.D., P.E. (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page
More informationSUNSHINE SKYWAY BRIDGE
SUNSHINE SKYWAY BRIDGE Retrofit of the Post-Tensioned Precast Transition Pier Columns on the Sunshine Skyway Bridge Presented by: Antonio Ledesma, P.E. May 7, 2012 SUNSHINE SKYWAY BRIDGE, FLORIDA Presentation
More informationNDT in Grouted PT Inspection for Bridges
NDT in Grouted PT Inspection for Bridges PTI Technical Conference & Exhibition Miami, FL May 8, 2007 Hong-gang gang Cao CTLGroup (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 1 of 37
More informationEvaluation of Corrosion Damage in Unbonded Post-Tensioned Concrete Structures:
Evaluation of Corrosion Damage in Unbonded Post-Tensioned Concrete Structures: Misunderstandings, Misinformation and Moving Forward by Keith Kesner Randall W. Poston Introduction 16 Years Ago Corrosion
More informationRak Production Technology of Concrete Structures (2015) Concrete Reinforcement
Rak-82-2121 Production Technology of Concrete Structures (2015) Concrete Reinforcement 09.10.2015 1 Learning Outcomes To acquaint the student with concrete reinforcement 2 Reinforcement The of concrete
More informationConcrete Design Guide
Number 7 38 TheStructuralEngineer Technical July 2015 Post-tensioned slabs Concrete Design Guide No. 7: Design of post-tensioned slabs This series is produced by The Concrete Centre to enable designers
More informationGUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410
GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific
More informationSPECIAL SPECIFICATION 4401 Prestressed Ground Anchors
2004 Specifications CSJ 0581-02-121 & 0200-11-100 SPECI SPECIFICATION 4401 Prestressed Ground Anchors 1. Description. Install post-tensioned permanent ground anchors in place, with grouting as required
More informationFlorida DOT efforts toward improving Post Tension Durability
Florida DOT efforts toward improving Post Tension Durability By William Nickas 1 (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page 1 of 73 Post-Tensioning Strategies Enhanced PT Systems
More informationPOST TENSIONED SLABS. Imagineering the possibilities
POST TENSIONED SLABS Imagineering the possibilities imagineering... CCL post - tensioned slab solutions represent continuous development through involvement in building structures worldwide. CCL systems
More informationStone and Masonry Veneer
Stone and Masonry Veneer R703.7 Stone and masonry veneer, general. Stone and masonry veneer shall be installed in accordance with this chapter, Table R703.4 and Figure R703.7. These veneers installed over
More informationADDENDA #9- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services
ADDENDA #9- RFP Sylvania CC building Re-Roof Progressive Design Build for Sylvania Campus CC Building Re-Roof Services Addenda Dated: 01/25/2019 PURPOSE: The purpose of this Addenda #9 is to provide a
More informationThe Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1
Department of Civil Engineering Lecture 2.1 Methods of Prestressing Advantages of Prestressing Section remains uncracked under service loads Reduction of steel corrosion (increase durability) Full section
More informationMondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014
Mondol Fabrics Ltd Nayapara,kasimpur, Gazipur (23.990028N, 90.317336E0) 8th March 2014 1 2 Observations 3 Column Stresses in Toilet Area North of Building Cursory calculations indicate that column size
More informationPost-tensioned Concrete Design PT Installation Guidance
Post-tensioned Concrete Design PT Installation Guidance Lee Maartensz Construction Manager - Structural Systems UK Ltd PT Installation Bonded Flat Slabs Installation 1 Flat Slabs Beam and Slab Installation
More informationIncluded in our report are our visual observations, recommendations for follow-up evaluation, and conceptual repair recommendations.
Ms. Pamela J. Irwin Community Management Associates 384 Ralph McGill Blvd Atlanta, GA 30312 Re: Phase I Condition Assessment Central City Condominiums Pool Deck Atlanta, Georgia Walter P Moore Project
More informationTechnical Notes. Mandatory Barrier Cable Inspection Requirements
Technical Notes From M-10: Unbonded Tendon Committee Issue 20 December 2015 Mandary Barrier Cable Inspection Requirements Inspection of barrier cable installation in accordance with the PTI M10.4-07, Specification
More informationIn Association with. DSE PROJECTS - Lebanon
In Association with DSE PROJECTS - Lebanon Pre-Stressing System Pre-Stressing, results in thinner slabs, which produces valuable extra space, and in turn will be used to create additional floors. This
More informationSECTION STRUCTURAL PRECAST HOLLOW CORE SLABS
PART 1 GENERAL 1.01 SCOPE OF WORK A. The Contractor shall furnish all labor, materials, equipment and incidentals to provide a complete structural precast hollow core slab system as shown on the Contract
More informationConcrete Prestressed Concrete Pretensioned Concrete Posttensioned Concrete Typical Tendon Layout
Concrete 45 1.13.0 Prestressed Concrete Concrete in which internal stresses (forces) are induced by means of prestressing steel tendons such that tensile stresses resulting from loads are counteracted
More informationConstruction Management Study
Construction Management Study CONSTRUCTION MANAGEMENT STUDY A construction management study of the alternate concrete system was done to examine the impact that changing the building s superstructure material
More informationNatural Sweater Village Ltd
Natural Sweater Village Ltd Raju Tower, Gouripur, Ashulia, Dhaka (23.887817E,90.318335N) 19 December 2013 1 2 Building 1 Building Observations 3 Drawings do not correspond with constructed condition in
More informationEXECUTIVE DEPARTMENT OFFICE OF GENERAL SERVICES DESIGN AND CONSTRUCTION GROUP - DIVISION OF DESIGN PROFESSIONAL CONSULTATION REPORT
EXECUTIVE DEPARTMENT OFFICE OF GENERAL SERVICES DESIGN AND CONSTRUCTION GROUP - DIVISION OF DESIGN PROFESSIONAL CONSULTATION REPORT Structural Survey S1390 March 21, 2005 Study Backboard Structural Support
More informationGUIDELINES FOR EXECUTION OF ADAPT-PT 1
Structural Concrete Software System GUIDELINES FOR EXECUTION OF ADAPT-PT 1 Update: December 09, 2004 TN172 guide_to_run_pt_12 120904 The guidelines presented will assist you in the selection of design
More information1. CORROSION OF REINFORCEMENT
MAB 1033 Structural Assessment and Repair 1. CORROSION OF REINFORCEMENT Professor Dr. Mohammad bin Ismail C09-313 Learning Outcome At the end of the course students should be able to understand Mechanism
More informationSPECIAL SPECIFICATION 4492 Tie Back Anchors
2004 Specifications CSJ 0504-02-022 SPECI SPECIFICATION 4492 Tie Back Anchors 1. Description. This Item shall govern for the installation of tie-back anchors in place, with grouting as required in accordance
More informationAtkinson Engineering, Inc.
Atkinson Engineering, Inc. Atkinson Engineering, Inc. One of the problems in underpinning a typical post-tensioned foundation is support for the slab part that spans between the stiffening beams. An example
More informationTable of Contents. List of Drawings
SCOPE OF WORK Hastings Stadium Exhibition Park, 81 London Road, Guelph, Ontario Structural and Maintenance Remedial Work Prepared For City of Guelph City Hall, 1 Carden Street, Guelph, ON N1H 3A1 Prepared
More informationGreen Street Parking Garage East and West End Study City of Ithaca, New York
Green Street Parking Garage East and West End Study City of Ithaca, New York FINAL Report Stantec PN: 191060345 Prepared for: City of Ithaca 108 E. Green Street Ithaca, New York 14850 Prepared by: Stantec
More informationPOST-TENSIONING APPLICATION AND TECHNOLOGY. Moe Kyaw Aung
POST-TENSIONING APPLICATION AND TECHNOLOGY Moe Kyaw Aung Overview 1. Background 2. Basic Design Concept 3. Application and Benefits 4. Components of Post-tensioning System 5. Installation Process 6. Construction
More informationSTRUCTURAL PRECAST CONCRETE
SECTION 03410 STRUCTURAL PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Provide labor, materials, necessary equipment, services and included, but not limited to, related work to complete the structural
More informationSMITHFIELD-LIBERTY HELIX RAMP REHABILITATION
SMITHFIELD-LIBERTY HELIX RAMP REHABILITATION LONGEVITY ENTRY SMITHFIELD-LIBERTY HELIX RAMP REHABILITATION LONGEVITY FEATURES The rehabilitation of the Smithfield-Liberty Parking Garage was undertaken in
More informationCorrosion Evaluation of Post-Tensioned Tendons on Mid-Bay Bridge
Corrosion Evaluation of Post-Tensioned Tendons on Mid-Bay Bridge by Siva Venugopalan Principal SCS, Inc. siva007@verizon.net (610) 692-6551 6551 March 7, 2007 Count on Concrete for Performance Slide 1
More informationBarrier Cable Systems, Inc.
055220 BARRIER CABLE SYSTEMS PART 1- GENERAL 1.1 DESIGN The 2012 IBC compliant barrier systems must meet both following requirements: A. For automobile restraint: the systems shall be able to withstand
More informationPro-Con Structural Study of Alternate Floor Systems
Andrew Covely Structural Dr. Linda Hanagan The Helena New York City, NY October 27, 2004 Pictures courtesy of Fox & Fowle Architects Pro-Con Structural Study of Alternate Floor Systems Executive Summary
More information2/16/17. Copyright Material. A Repair Technician s Guide to the ACI Chapter 10 Quality Assurance. The Big Picture. Who is a Repair Technician?
Copyright Material This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of the presentation without permission of the speaker is prohibited.
More informationHARVEY MUDD COLLEGE TEACHING AND LEARNING CENTER SECTION Page 1 of 6 VOIDED CONCRETE SLAB
030111 Page 1 of 6 PART 1 - GENERAL 1.1 SUMMARY A. This Section specifies: 1. Voided concrete floor and roof slab system consisting of structural reinforced concrete containing hollow (bubbles) spherical
More informationAlif Apparels Ltd. (9813) Goldstar Garments Ltd. (9844)
Alif Apparels Ltd. (9813) Goldstar Garments Ltd. (9844) 23/8 B&C, Holding #24/2, Khilje Road, Shyamoli Cinema Complex Building (2 nd Floor), Shyyamoli, Dhaka-1207 (+ 23.774489N, 90.365164E) 16.AUGUST.2014
More informationTable of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5
WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 1 OCTOBER 5, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI Table of Contents Table of Contents
More informationGLULAM BEAM REPAIR/REINFORCEMENT TINORA HIGH SCHOOL DEFIANCE, OHIO
GLULAM BEAM REPAIR/REINFORCEMENT TINORA HIGH SCHOOL DEFIANCE, OHIO By: Gary W. Gray, PE and Paul C. Gilham, PE Introduction In January of 2004, a structural roof beam bending failure occurred in the gymnasium
More informationExecutive Summary. Champlain Bridge Approach Spans Edge Girder Condition Assessment and Rehabilitation Requirements.
Executive Summary "Les Ponts Jacques Cartier et Champlain Incorporée" (PJCCI) requested that Buckland & Taylor (B&T) study the overall condition of the approach span edge girders of the Champlain Bridge
More informationNovember 30, University of Virginia Facilities Management Engineering & Design Division P.O. Box Charlottesville, VA
University of Virginia Facilities Management Engineering & Design Division P.O. Box 400726 Charlottesville, VA 22904-4726 Attention: Reference: William Blodgett, AIA Project Manager University of Virginia
More informationThe assessment is based on the following fire test from SINTEF NBL as.:
Page 2 of 7 The assessment is based on the following fire test from SINTEF NBL as.: /1/ Fire test report no. 131.94: Fire test of steel columns and HSQ-beams, corrugated steel roof element and concrete
More informationIntermountain Section AWWA Conference - 2.0MG Layton Water Tank. Jake O Brien
Intermountain Section AWWA Conference - 2.0MG Layton Water Tank Jake O Brien Presentation Outline Layton City s decision process Tank Design/Construction Tendon Tanks - don t shed the good stuff Layton
More information***************************************************************************************************************
03410 STRUCTURAL PRECAST CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 41 00 ***************************************************************************************************************
More informationASSESSMENT, REPAIR AND MONITORING OF THE GENTILLY-1 CONCRETE CONTAINMENT STRUCTURE
ASSESSMENT, REPAIR AND MONITORING OF THE GENTILLY-1 CONCRETE CONTAINMENT STRUCTURE A.A. Khan, M. Gray, B. Shenton, D. Panesar and M. Elgohary Atomic Energy of Canada Limited, Mississauga, Ontario, Canada
More informationCommercial Structures
Commercial Structures Structural Components Footing Piles Foundation Beams Joists Column Substructure Superstructure Reinforced concrete Re-bar Pre-cast concrete panel Deflection Cantilever Footings A
More informationExtreme Loading for Structures Version 3.1
Extreme Loading for Structures Version 3.1 Corrosion Effects Option April 2010 1. Introduction Corrosion of gusset plates was identified as one of the main causes for failure in the catastrophic collapse
More informationTechnical Assignment 1 10/8/03
Executive Summary Technical Assignment 1 10/8/03 The is 55 story high-rise condominium being built off the northern Miami coast. The structural design presented in this building is a direct result of its
More information***************************************************************************************************************
03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************
More informationEXECUTIVE SUMMARY POST-TENSIONING TENDON PROTECTION STRATEGIES FOR PRECAST ELEMENTS
EXECUTIVE SUMMARY POST-TENSIONING TENDON PROTECTION STRATEGIES FOR PRECAST ELEMENTS Larry B. Krauser, General Technologies, Inc., Stafford, TX Post-tensioning tendon protection strategies for precast elements
More informationMr. Eric Ryffel, Manager October 5, 2015 Sanibel Beach Club 626 Nerita Street Sanibel Island, Florida 33957
TRC Worldwide Engineering Restoration & Inspection, LLC 11926 Fairway Lakes Drive Fort Myers, Florida 33913 Phone: (239) 939-1414 F: (239) 278-4289 www.trcww.com C.O.A. No. 30761 Mr. Eric Ryffel, Manager
More informationEast Lyme Middle School EAST LYME MIDDLE SCHOOL
Description: N EAST LYME MIDDLE SCHOOL The school consists of a multi story building with lower, main and upper level floors. The typical floor framing for the main and upper levels is wide flange steel
More informationPost-Tech PTI Impregnation System. Corrosion Protection System for Bonded Post-Tension Tendons
Post-Tech PTI Impregnation System Corrosion Protection System for Bonded Post-Tension Tendons Post-Tech PTI Impregnation System Corrosion Protection System for Bonded Post-Tension Tendons Post-Tech PTI
More informationCONCRETE TECHNOLOGY CORPORATION
PRECAST, PRESTRESSED HOLLOW CORE SLABS DESIGN CRITERIA & SPAN-LOAD CHARTS FOR STORM WATER DETENTION VAULT LIDS (CHARTS REVISED /18/08) Introduction Design Criteria for Development of the Span-Load Charts
More informationSUMMARY SHEETS OF INTEGRAL CONNECTIONS
APPENDIX F SUMMARY SHEETS OF INTEGRAL CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix F F-1 APPENDIX F SUMMARY SHEETS OF INTEGRAL CONNECTIONS NCHRP 12-88 Connection Evaluations Appendix F F-2
More informationB. Related work in other Sections related to Post-tensioned Concrete include: 1. Section Structural Testing Laboratory Services.
SECTION 03 38 00 POST-TENSIONED CONCRETE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification
More informationSPECIFICATION FOR PRECAST/ COMPOSITE CONCRETE FLOORS/ ROOF DECKS SECTION E60
SPECIFICATION FOR SECTION E60 A 2007-09-26 S.W. Revision Date Issue Authorised By Approved for Issue SW Date 24.09.07 clarkebond Page 1 of 6 To be read with Preliminaries/ General Conditions. GENERAL 10
More informationGIRDER DESIGN FOR BUILDINGS
POST-TENSIONED TRANSFER GIRDER DESIGN FOR BUILDINGS Overload, Restraint and Construction Staging g Issues Almıla Uzel and Neb Erakovic (C) COPYRIGHT POST-TENSIONING INSTITUTE, ALL RIGHTS RESERVED Page
More informationS T R U C T U R. Structural Failures. magazine
Structural Failures Investigating failures, their consequences and resolutions... Glulam Beam Repair/Reinforcement Tinora High School Defiance, Ohio By Gary W. Gray, P.E. and Paul C. Gilham, P.E. In January
More informationStay-Cable Replacement Design
Stay-Cable Replacement Design Mississippi River Bridge Luling, Louisiana Christopher Ligozio CTLGroup Copyright Post-Tensioning Institute all rights reserved. Page 1 of 35 Luling Bridge Copyright Post-Tensioning
More informationConcrete Parking Garage Degradation
Concrete Parking Garage Degradation Concrete Parking Garage Degradation With proper care and maintenance, the life of a concrete parking garage can span several decades. The integrity and strength of structural
More informationDeflection Analysis with Shoring Load Transfer Coefficient for Post-Tensioned Slab
Deflection Analysis with Shoring Load Transfer Coefficient for Post-Tensioned Slab *Ah Sir Cho 1) and Thomas Kang 2) 1), 2) Department of Architecture & Architectural Engineering, Seoul National University,
More informationHickam Air Force Base Headquarters
Hickam Air Force Base Headquarters Crawl-space Column Repairs and Corrosion Mitigation By Tore O. Arnesen and J. Christopher Ball The Hickam Air Force Base Headquarters Pacific Air Forces (PACAF) Building
More informationTopic Outline. Two Stage Analysis Procedure: Podium Design. Part 2: Rigid Lower Portion Philip Miller, S.E. 2/8/2018
Two Stage Analysis Procedure: Podium Design Part 2: Rigid Lower Portion Philip Miller, S.E. Topic Outline Types of Podium Construction Example Buildings PT Basics PT Analysis Modeling Tips Load Balancing
More informationSurface Repair Using Form-and- Pour Techniques
ACI RAP Bulletin 4 American Concrete Institute Advancing concrete knowledge FIELD GUIDE TO CONCRETE REPAIR APPLICATION PROCEDURES Surface Repair Using Form-and- Pour Techniques Surface Repair Using Form-and-Pour
More informationUS-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer
US-131 Over the Muskegon River Corey Rogers, P.E. Bridge Construction Engineer NB and SB US-131 Each bridge is a three-span, 580 foot long, cast-in-place, post-tensioned concrete box girder structure resting
More informationWJE ENGINEERS SPECIALIZED POST-TENSIONING ASSESSMENT AND REPAIR. Western Bridge Engineers Seminar. September 10, :30 AM
Western Bridge Engineers Seminar September 10, 2015 8:30 AM SPECIALIZED POST-TENSIONING ASSESSMENT AND REPAIR WJE ENGINEERS ARCHITECTS MATERIALS SCIENTISTS Outline WJE PT assessments PT basics Initial
More informationPost-Tensioned Concrete in Buildings
Post-Tensioned Concrete in Buildings A Half-Century Overview By Ken Bondy PTI Convention May 2012, Nashville 49 Years Ago It was 1963 I was 23 years old I had completed my MSCE course work at UCLA I was
More informationDISTRESS PHENOMENA OFTEN MISTAKEN FOR FOUNDATION MOVEMENT
Issued for Website Publishing Foundation Performance Association Structural Committee Page 1 of 5 PHENOMENA OFTEN MISTAKEN FOR FOUNDATION MOVEMENT by The Structural Committee of The Foundation Performance
More informationACI MANUAL OF CONCRETE PRACTICE-2009
ACI MANUAL OF CONCRETE PRACTICE-2009 The ACI Manual of Concrete Practice is a six-part compilation of current ACI standards and committee reports. -ACI117-06 to ACI224.3R-95(08) Part 2-ACI 225-99(05) to
More informationADAPT PT7 TUTORIAL FOR BEAM FRAME 1
ADAPT PT7 TUTORIAL FOR BEAM FRAME 1 Technical Note Structural Concrete Software System TN189_PT7_tutorial_beam_frame 012705 1 BEAM FRAME The objective of this tutorial is to demonstrate the step-by-step
More informationCorrosion Evaluation of Prestressed Piles in Refit Wharf #3
Corrosion Evaluation of Prestressed Piles in Refit Wharf #3 Naval Submarine Base Kings Bay, GA, USA December 8, 2010 Siva Venugopalan President, Principal Engineer Siva Corrosion Services (SCS) (610) 692-6551
More informationIntroduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures
Journal of Civil Engineering and Architecture 9 (2015) 213-224 doi: 10.17265/1934-7359/2015.02.010 D DAVID PUBLISHING Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation,
More informationSTRENGTH EVALUATION OF A CRACKED SLAB REINFORCED WITH GROUTED TENDONS 1
Your Partner in Structural Concrete Design TN402_ULS_cracks_grouted_032211 STRENGTH EVALUATION OF A CRACKED SLAB REINFORCED WITH GROUTED TENDONS 1 Bijan O. Aalami 2 First draft: March 22, 2011 This Technical
More informationGuidelines for the Design of Post-Tensioned Floors
5.2 Guidelines for the Design of Post-Tensioned Floors BY BIJAN O. AALAMI AND JENNIFER D. JURGENS his article presents a set of guidelines intended to T assist designers in routine post-tensioning design,
More informationInvestigation for the Removal of Steel Tie Rods in a Historic Segmental Arch Floor
Investigation for the Removal of Steel Tie Rods in a Historic Segmental Arch Floor J. Lan 1, R. Gilsanz 2, and M. Lo 3 1 Gilsanz Murray Steficek, LLP, 129 West 27 th St., 5 th Floor, New York, NY 10001
More informationEffect of Grout Filling Condition on Corrosion of Prestressing Steel in Existing Prestressed Concrete Bridges
Effect of Grout Filling Condition on Corrosion of Prestressing Steel in Existing Prestressed Concrete Bridges Shu Kobayashi 1*, Yuichi Kitano 1*, Hideaki Taniguchi 1*, Yasushi Kunitomi 1* Yoshitomi Kimura
More informationCONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT SPECIFICATION EO-1007 REVISION 13 DECEMBER 2013 EFFECTIVE DATE DECEMBER 16,
More information3. INSPECTION FINDINGS
3. INSPECTION FINDINGS Pier 40 is in overall Poor condition with 22% of the H-piles rated Major and 35% of the H-piles rated Severe, primarily due to severe corrosion within the splash zone at the top
More informationTHE NEW ACI STANDARD SPECIFICATION FOR UNBONDED TENDONS
PTI Journal Viewpoints THE NEW ACI STANDARD SPECIFICATION FOR UNBONDED TENDONS By KEN BONDY Authorized reprint from: August 2015 issue of the PTI Journal Copyrighted 2015, Post-Tensioning Institute All
More informationAn Introductory Study on Void Detection Inside Internal Polymeric Post-Tension Ducts Using Ground Penetrating Radar
PTI Journal Technical Paper An Introductory Study on Void Detection Inside Internal Polymeric Post-Tension Ducts Using Ground Penetrating Radar By: Todd Allen Dilip Choudhuri Authorized reprint from: May
More informationStructural Option April 7 th, 2010
Gravity System (Depth Topic I) Post Tensioned Slab A new floor system was designed in an attempt to create a more consistent flooring system throughout the entire building. This new design consists of
More informationKORA_Req._for_Eng._Studies_on_Stouffer_Apts. KU Reference No
000130 1 PURPOSE: Professional Engineering Consultants, P.A. (PEC) was engaged by University of Kansas Design & Construction Management to perform an assessment of Stouffer Place Apartment Building 20
More informationPOST-TENSIONED SLABS SPECIALISED ENGINEERED SOLUTIONS FOR STRUCTURES.
POST-TENSIONED SLABS SPECIALISED ENGINEERED SOLUTIONS FOR STRUCTURES 02/03 Uncover the true potential of your structure...while building confidence DESIGN SOLUTIONS CCL carries out complete designs for
More informationCONCRETE TECHNOLOGY CORPORATION
PRECAST, PRESTRESSED HOLLOW CORE SLABS DESIGN CRITERIA & SPAN-LOAD CHARTS Introduction 2 Design Criteria for Development of the Span-Load Charts 2 Related Publications 3 Manufacturing Tolerances 4 8" Bare
More informationA MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS
A MEDLEY OF PRECAST AND PRESTRESSED CONCRETE SYSTEMS Neil F. Dunbar Ketch u m-kon ke l-barrett-n i cke I-A u sti n Consulting Engineers Denver, Co!oredo Describes several structural systems using both
More informationNorth Mountain IMS Medical Office Building
North Mountain IMS Medical Office Building Phoenix, Arizona Michael Hopple Technical Assignment 2 October 29 th, 2007 AE 481W-Senior Thesis The Pennsylvania State University Faculty Adviser: Dr. Ali Memari,
More informationPlan Check No. Checked by: An Appointment Is Required for Verification
SUPPLEMENTAL CORRECTION SHEET UNREINFORCED MASONRY (URM) RETROFIT ( 2002 LABC ) Plan Check No. Checked by: Permit Appl. # An Appointment Is Required for Verification Job Address: For appt. call: APPLICATION
More informationSECTION ARCHITECTURAL PRECAST CONCRETE. C. Section Joint Sealers: Perimeter joints with sealant and backing.
SECTION 03451 ARCHITECTURAL PRECAST CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. Architectural precast concrete wall panels; with integral insulation. B. Supports, anchors, and attachments. C. Intermediate
More informationDISTRESS PHENOMENA OFTEN MISTAKENLY ATTRIBUTED TO FOUNDATION MOVEMENT
Issued for Website Publishing Foundation Performance Association Structural Committee Page 1 of 5 PHENOMENA OFTEN MISTAKENLY ATTRIBUTED TO FOUNDATION MOVEMENT by The Structural Committee of The Foundation
More informationElevated Slab Sequence
Elevated Slab Sequence The following group of photos shows the sequence for installa4on of a one- way elevated slab. (Slab & Beam with Reinforcing & Post- Tensioning) Columns Placed & Form Support (Scaffolding)
More informationTECHNICAL SPECIFICATION
TECHNICAL SPECIFICATION ITEM 03100 CONCRETE FORMWORK 1.0 GENERAL 1.1 DESCRIPTION This section defines requirements and limitations for design, construction, erection, and removal of concrete formwork for
More informationCHAPTER 8. Concrete Work
Concrete Work Clay Bricklaying Made Easy CONCRETE WORK Foundations for walls and piers All loadbearing walls and piers are required to stand on a concrete foundation, which must be able to receive and
More informationMajor Building and Special Structures
TECHNICAL SESSION 1 Major Building and Special Structures Moderator Russell B. Price, P.E. Suncoast Post-Tension L.P. Houston, Texas 2004 PTI Technical Conference Session 1 Dennis Wittry -- Denver's Invesco
More information