Design and construction of an immersed concrete tunnel using an integrated dock facility

Size: px
Start display at page:

Download "Design and construction of an immersed concrete tunnel using an integrated dock facility"

Transcription

1 Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN Design and construction of an immersed concrete tunnel using an integrated dock facility C. Bauduin BESIX, Brussels, Belgium University of Brussels, Brussels, Belgium P. Depuydt BESIX, Brussels, Belgium ABSTRACT: The construction of the A73 highway (the Netherlands) involved the construction of a 2.4 km long, 2*2 lane tunnel to mitigate the impact of traffic on the city of Roermond and to cross the 1 km wide valley of the river Roer. Given the ground conditions (mainly dense sand and gravel), required cross section and tunnel depth, an immersed tunnel appeared to be the most economic solution to cross the valley. However, a facility to permit precasting of the RC tunnel elements needed to be established. The small depth and width of the Roer prevented transportation of tunnel elements by use of the river and dewatering was not permitted due to the associated environmental impact. The analysis of the geotechnical data indicated the presence of a 5 m thick local loam layer over a length of 350 m along the tunnel alignment, located at the eastern part of the Roer valley. This impervious layer offered the opportunity to excavate a 350 m long dock along the axis of the tunnel between temporary anchored sheetpiles that were installed into the loam layer. Two precast tunnel elements of approximately 158 m long could be constructed in this dock. A trench was excavated between and temporary sheetpiles were installed 5 m outside the future tunnel location, thus permitting the transportation and immersion of a total of four such tunnel elements in two installments from the dock to their final location. The remaining part of the tunnel was constructed in what was previously the dry dock after the immersion of the elements. This paper describes how the concrete structure was designed and specified (concrete weight and tolerances) with allowances for the specific geotechnical and hydraulic conditions (water depth, concrete weight and freeboard, water level management in the trench, excavation depth and uplift of the impervious layer etc.). The paper describes the behavior and provisions of the concrete structure on the gravel bed foundation, which was preferred to sand flow to minimize the risks of liquefaction as the area is mode-rately seismic. 1 INTRODUCTION As part of the new 40 km A73 Highway in the south of the Netherlands, the Ministry of Transport Public Works and Water Management (Rijkswaterstaat) planned to build a 2*2 lanes, 2.4 km long tunnel, partly adjacent to the city of Roermond and partly under the 1 km wide valley of the river Roer. The tunnel solution was selected in order to minimize the impact of the highway in the urban area and to preserve the natural environment of the Roer valley. The Ministry prepared the tender for the tunnel works as a Design and Construct contract and the client s specifications were stated on a rather abstract level, leaving a large degree of design freedom to the competing contractors. In 2004 the contract was awarded to the lowest bidding contractor that conformed to the client s specifications. The design and the construction were the contractor s responsibility, under process supervision by the Ministry. The contract was awarded to Besix, the works were executed by Besix-Strukton Betonbouw JV, the design was undertaken by Besix Design Department and the preparation, design and execution of immersion operations was undertaken by Mergor (part of Strukton Betonbouw). Severe environmental constraints applied to the design and construction of the tunnel: To preserve nature and to avoid settlement of neighboring structures, with no permitted changes to ground water levels The construction should not influence the course of the River Roer and not reduce the discharge capacity of the Roer Valley in case of flooding 781

2 Figure 3. Tunnel cross section TE1/TE2, concrete pouring stages. period: 1/10 years), (return period: 1/100 years) which corresponds to a river width of 1 km. The design water level was m NAP (return period 1/10000 years). The maximum top ground level is 20.5 m NAP. The ground water piezometric head reacts moderately to variations in the river level. The geometric requirements of the tunnel were: Figure 1. Location of the tunnel. Figure 2. Typical CPT in construction pit. Vibrations and noise should not adversely impact the natural environment or cause hindrance or damage to neighboring structures and persons. The ground conditions are characterized by medium dense sand and sandy-loam top layers, overlying dense to very dense, highly pervious sand and gravel layers. Stiff loam layers with low permeability were found locally between these layers. The discharge of the River Roer is governed by rainfall and the melting of snow in upstream regions. The water level is mainly governed by the discharge, the water level in the Meuse and by the opening or closing of the upstream dams. In normal discharge conditions, the Roer is approximately 15 m wide and 4 m deep; in extreme conditions, however, the valley is flooded over its whole width between the winter dikes (approximately 1 km). The water level varies from m NAP (minimum level) to m NAP (return 782 The cross section was to consist of two tubes (two carriageways each) separated by a central emergency evacuation tunnel (fig. 3). Internal free height requirements: 5.0 m (including an allowance for electro-mechanical installation) and width between the walls: m minimum to be increased to allow for construction tolerances. The height between bottom and top slab is 5.6 m to allow for ballast concrete, road pavement construction and settlement tolerances (fig. 3). Specific to the tunnel in the Roer Valley: the top level of the roof slab was to be located at m NAP maximum over approximately 200 m width of the valley in order to avoid adverse effects of the tunnel on the groundwater flow. The overburden combined with the design water level governed the maximum values of the actions for designing the tunnel cross sections (fig. 4). The design specifications required that a minimum contact stress of 5 kpa due to the absence of overburden over approximately half of the tunnel length to accommodate possible future natural changes of the river bedding be included in the design. This governed the volume of structural and ballast concrete that was required for the internal volume of the tunnel, given the unit weight of the concrete and the amount of reinforcement. The concrete volume and internal net open volume determined the free board. The smaller the free board, the easier the immersion and ballast exchange operations.

3 2 GENERAL DESCRIPTION OF THE TUNNEL Four main areas can be identified (fig. 7): An open access ramp at the western side was designed as a polder construction formed by a PE sheet placed underwater on the bottom and the slopes of a deep dredged open trench. Backfill on the sheet compensated for uplift ground water pressure. Piled open ramp and tunnel section, west of the Roer valley. The deepest part of the access ramp and a 60 m long part of the tunnel west of the dike, including the main technical building and sump pit, were designed as reinforced concrete structures supported by GEWI piles and constructed between permanent anchored sheet piles or combiwalls. A temporary unreinforced concrete floor was designed below the RC structure between the sheet piles and anchored by the GEWI piles to avoid dewatering. This design was chosen because the required width in the trench for the PE sheet was not available and also due to the complexity of the structures to be built. Crossing of the valley, as far as the eastern dikes (see chapter 3). An urban section of the tunnel, which is located partly under the urban ringroad to the south of Roermond; the alignment being crossed at ground level by local access roads at several locations. The urban part was designed as a cut and cover cast in-situ reinforced concrete structure. 3 TUNNEL CROSSING THE VALLEY The design for the crossing of the RoerValley was a key element to the project due its very important economic impact on the total construction cost. Several solutions complying with the fundamental requirements were predesigned and evaluated in terms of cost and risk. Immersed tunnel solutions appeared to be the most appropriate because they would require no piling works and construction materials could be used efficiently provided that: the trench could be constructed using temporary facilities such as recoverable sheet piles an efficient and economic solution for the area for precasting the immersed elements could be found while preventing the need for dewatering The trench along the tunnel alignment was supported by temporary anchored sheet pile walls located 5 m beyond the planned tunnel, thus permitting recovery of the sheet piles after completion of the works. The use of the Roer to transport elements was not feasible as it has insufficient depth and width. Careful analysis of the ground conditions indicated the presence of a 5 m thick loam layer along the tunnel alignment at the eastern 350 m of the valley, the bottom of the layer being at approximately 2mNAP. This geotechnical feature was the key to the design of the construction area for the precast RC elements of the immersed tunnel, as it permitted the construction of a construction pit along the axis of the planned tunnel, i.e. in the same alignment as the trench, without the need for dewatering provided that the retaining wall could penetrate sufficiently deeply into the impervious layer. This construction pit was used to construct two tunnel elements (each of which was approximately 135 and 158 m long), after which the pit was inundated and the tunnel elements were floated out of the pit and subsequently immersed (fig. 4). The pit was then dewatered and used again to construct the next two tunnel elements which were similarly transported and immersed at their final location. Finally the pit was dewatered again to construct a remaining part of tunnel approximately 350 m long as a cast in-situ cut and cover tunnel using the framework of the immersed parts. After backfilling the trench and the construction pit, the sheetpiles located adjacent to the trench and the construction pit were removed. In order to achieve the conceptual design described above, it was necessary to successfully balance a number of oppositely interacting parameters, as shown in table 1. Analysis of the interaction between these parameters has indicated that, for a given level of the underside of the loam layer and thus the allowable excavation depth, the feasibility of the concept was governed by: The required tunnel height for resistance with full overburden and uplift safety without overburden, including tolerances on settlement The required water level in the Roer The ability to predict the unit weight of the reinforced concrete adequately and the control of this value during construction, in addition to the control of dimensions during construction Several scenarios were analyzed, which finally led to the following design (fig. 4): For the deepest and thus most heavily loaded elements 1 and 2, the required slab thickness was too large to be compatible with the probable low water levels in the Roer and maximum allowable excavation depth in the construction pit. It was decided to install a lock wall in the trench which allowed the water level in the construction pit and the adjacent part of the trench to be controlled independently of the water level of the Roer. The elements were then towed to the deepest parts of the trench and finally the lock was opened after equating the two water levels.the elements 1 and 2 were designed for a free 783

4 Parameter If parameter is It favorably affects It unfavorably affects Parameter is initial condition or design parameter Deep excavation level construction pit Thickness of loam layer Deep Water depth required in Roer to enable floating of TE Thick Excavation depth (higher uplift resistance) Total tunnel height High Strength of roof and bottom slab Allowable thickness of ballast concrete Vertical tolerance for immersion and accuracy of predicted settlements Total tunnel height Low Required water depth for floating conditions (relative levels between the Roer and the depth of excavations) Water level Roer High Floating conditions (low free board) Clearance under TE Uplift of loam layer Dimensions retaining structure of pit Design parameter - To be determined by critical ground investigations Required water depth for floating conditions (relative levels between the Roer and the depth of excavations) Strength of roof and bottom slab Allowable thickness of ballast concrete Vertical tolerance for immersion and accuracy of predicted settlements Determined by free height, ballast thickness and roof/ bottom slab thickness Determined by free height (design requirement), ballast thickness and roof/bottom slab thickness Variable, slightly predictable, unmanageable Water level Roer Low Requires high free board Variable, slightly predictable, unmanageable Free board TE Low Floating conditions Ballast quantity Equilibrium after immersion Free board TE High Required depth of construction pit. Required depth trench Required minimum level of Roer to enable floating of TE Depth of tunnelr element in final position (thus maximum value of overburden on roof) Clearance for ballast concrete in tunnel Weight of reinforced concrete Maximum level of tunnel roof after immersion No overburden on tunnel roof Follows from vertical alignment The smaller the depth, the smaller the floor and roof thickness thus total element height High Uplift in absence of overburden Allowable uncertainty on settlement Low High free board, thus required depth etc Design requirement Design requirement Required water depth for floating conditions (relative levels between the Roer and the depth of excavations) to enable floating Immersion (high volume of ballast water) Exchange of water ballast to permanent ballast Design parameter, minimum free board (0.2 m) to enable floating of TE Design parameter, limited by strength requirement for applied load Allows optimization of roof thickness Total tunnel height Design parameter limiting deviations to gravel bed Effective contact stress under bottom slab Height of the tunnel (limiting level of tunnel roof) Minimum thickness of ballast concrete (moderately) Design parameter Design requirement to minimize effects of tunnel on ground water flow Design requirement 784

5 of the final in-situ part of the tunnel under the Roer Valley The structural design of the tunnel and temporary structures was undertaken so that the aforementioned requirements were accommodated. 4 CONCRETE Concrete grade C28/35 was selected as: Its spalling behavior is more favorable when compared with concrete of a higher strength Because it develops manageable internal temperatures in its initial hardening stage (hydration process). In order to avoid cracking, it was specified that the maximum tensile stress in the hardening concrete during the hydration process was not to exceed half of the average instantaneous tensile strength. FE heat and stress calculations were performed for the selected concrete mix to check this criterion and to determine the amount of water cooling that was necessary to concrete the pouring stages (stage 1: floor slab, stage 2: internal walls; stage 3: external walls and roof). The specified design life for the tunnel is 100 years. Durability of the structure was achieved by adopting a concrete cover of 50 mm, specifying environmental class XD3/XF4, using CEM III cement with a minimum slag content of 50 % and a maximum water penetration of 20 mm. The value and range of variation of the unit weight of the concrete are of large importance for the immersed tunnel. Values were specified on the initial concrete mix type tests. The unit weight of the concrete (γ = kn/m kn/m3 ) and the as built dimensions were measured continuously during the construction in order that they remained within the acceptable limits for successful floating and immersion operations. Figure 4. Overview of floating immersion operations. 5 board of 20 cm to 50 cm depending on the assumed tolerances on concrete weight and dimensions. For the two highest and thus less loaded elements 3 and 4, a design with a high free board (greater than 1 m) was adopted, as the possibility of using the lock wall no longer existed following the immersion of elements 1 and 2 After immersion, the fourth element was strutted and preloaded under water against the longitudinal walls of the construction pit in order to avoid loss of compression in the Gina profile, which could occur during the subsequent dewatering of the construction pit which was necessary for the construction Due to the seismic risk in the Roermond area, a gravel bed foundation was preferred to classical sand flow in order to minimize the risk of liquefaction during an earthquake event. This foundation consists of nine ridges, 1.65 m wide at their top level and 0.5 m high per 22.6 m long tunnel section (fig. 5). The interaction between the foundation and the tunnel was determined by the stiffness of the ridges and by the uniformity of their top level. The load-settlement relationship of a single ridge was established using FE geotechnical calculations assuming a hardening soil model for the natural ground and Mohr-Coulomb behavior for the gravel ridges. The behavior that was predicted for the ridge was confirmed by plate load 785 FOUNDATION DESIGN

6 Figure 6. Flow scheme of design and specification of gravel bed Figure 5. Plan view ridges for one TE and detail of ridges. tests that were undertaken on full scale ridges which were constructed using the intended gravel. Deviations of the actual top levels of the ridges from the theoretical levels provoked non-uniform reactions which had to be accounted for. Deviations of the top levels may be stochastic or systematic, but are not known during the design. They interact with the structure differently depending on the scale (area over which local deviations are averaged) of the deviation: Stochastic deviations act at a local level; particularly at stiff points as protruding ridges in the span of the bottom slab are unfavorable when compared with a uniformly distributed soil reaction. These effects have been mitigated by reducing the thickness of the lower face of the bottom slab in the centre of the span below the tunnel cells and by the design methodology Systematic deviations over areas of a quarter to half of the area of a section mainly act at a global level in a single tunnel section provoking torsion or cross spanning of the tunnel from one outer wall to the other Systematic deviations over areas that are approximately the area of a whole tunnel section (22.6 m*27.64 m) result in the shear forces being transferred from the poorly supported section to the well supported section Separate non-linear analysis models were constructed to simulate each of the types of aforementioned deviations. In all of these models, the non-linear behavior of the spring and possible gaps between the top of ridges were modeled. A large number of calculations have been undertaken with these non-linear models in order to develop a full understanding of the effects of the assumed deviations. These calculations led to envelopes of internal forces that were used to construct equivalent deterministic simple 2D-models which were then used for routine design, of which the results had been proven to be conservative when compared with the envelopes that were obtained from the non-linear models. The different simplified models that were used for the design have been incorporated into the permanent works by introducing: Specifications for the placement of the ridges Acceptance criteria for the gravel bed as placed in-situ, by introducing limits on the measured deviations of the as built levels when compared with the theoretical. The flow diagram shown in fig 6 indicates the design steps that were followed to establish the possible effects of any deviation, to convert these models to easy-to-handle routine design models, and to specify allowable mean deviations of the ridges over areas of different sizes. The non-linear models were used to predict the most probable value of settlement due to backfill after immersion as well as the upper and lower limits of these settlements (as approximated 5% and 95% 786

7 Figure 7. Overall view of the tunnel and design solutions adopted. ranges).the theoretical level of the gravel bed has been corrected on the basis of the calculated most probable values of settlement (35 mm in the deepest section reducing to 5 mm in highest section). After backfill, the deviation between the as built level and theoretical level was for 90% of the measurements less than 5 mm, extreme deviation was 15 mm. satisfied, the actual measured in-situ ridge levels were introduced in the relevant calculation models to check the design (slab reinforcement, shear force in shear key, etc.) for the actual as built situation. If necessary, profile of the gravel bed had to be adapted. 7 6 ACCEPTANCE PROCEDURE FOR GRAVEL BED The ridges were placed by an underwater scrader that was specially developed for the project.the top level of the ridges was measured in-situ by use of a multi-beam. Transforming the measured data into a calculated average level per meter length, the level of the ridges and the levels of the assumed areas in the design could be easily checked against the acceptance criteria. If the three criteria (fig. 6) were met, the foundation bed was accepted. If one or maybe several criteria were not CONCLUSION Strict client s specifications on environmental conditions and geometric boundaries were applied in the design and construction of the tunnel. Considering the local ground conditions, an immersed tunnel was the optimum design solution in terms of costs and risks. Integration of design, construction methods, specifications and monitoring was the key issue for a successful project. The construction pit was started in November 2004 and tunnel elements were immersed in May and October-November The project was delivered in November

8

Settlements of HSL immersed tunnels

Settlements of HSL immersed tunnels Settlements of HSL immersed tunnels H. Mortier CFE Beton- en waterbouw, Dordrecht, The Netherlands Ch. J.A. Hakkaart BAM / Delta Marine Consultants, Gouda, The Netherlands W.M. t Hart Ballast Nedam Infra,

More information

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Tagus Crossing at Carregado (Portugal): A project respectful of its sensitive environment

More information

Steel screw settlement reduction piles for a raft foundation on soft soil

Steel screw settlement reduction piles for a raft foundation on soft soil Proc. 18 th NZGS Geotechnical Symposium on Soil-Structure Interaction. Ed. CY Chin, Auckland Alexei Murashev Opus International Consultants Limited, Wellington, New Zealand. Keywords: piled raft, settlement

More information

Downloaded from Downloaded from /1

Downloaded from  Downloaded from  /1 PURWANCHAL UNIVERSITY VI SEMESTER FINAL EXAMINATION-2003 LEVEL : B. E. (Civil) SUBJECT: BEG359CI, Foundation Engineering. Full Marks: 80 TIME: 03:00 hrs Pass marks: 32 Candidates are required to give their

More information

Progressive Erection Applied to Box Girder with Strutted Wing Slab

Progressive Erection Applied to Box Girder with Strutted Wing Slab Progressive Erection Applied to Box Girder with Strutted Wing Slab Koji Osada 1, Taketo Kanamoto 1, Kimito Saito 2, Takahiro Arai 2 1 Introduction The Uchimaki Viaduct is a multi-span continuous box girder

More information

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. Roger Woodhead, PhD, P.Eng., SNC-Lavain Inc. Paper prepared for

More information

ICD Brookfield Place, Dubai. Risk Management for a Deep Basement Excavation. Andrew Smith. Coffey Geotechnics Ltd.

ICD Brookfield Place, Dubai. Risk Management for a Deep Basement Excavation. Andrew Smith. Coffey Geotechnics Ltd. ICD Brookfield Place, Dubai Risk Management for a Deep Basement Excavation Andrew Smith Coffey Geotechnics Ltd. CONTENTS 1. Project description and site history 2. Ground Conditions 3. Assessment of risks

More information

APPENDIX B ABC STRUCTURES DESIGN GUIDE

APPENDIX B ABC STRUCTURES DESIGN GUIDE APPENDIX B ABC STRUCTURES DESIGN GUIDE The Cohos Evamy Partners TABLE OF CONTENTS Page No. DISCLAIMER... I 1. STRUCTURAL DESIGN GUIDELINES... 1 2. GENERAL REQUIREMENTS (FIGURE B.2, STEP 1)... 1 3. GENERAL

More information

Precast segmental design and construction in China

Precast segmental design and construction in China Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Precast segmental design and construction in China Dong, Xu, Huichi Li & Chao Liu

More information

Contents. Glossary 9. Foreword 10

Contents. Glossary 9. Foreword 10 Glossary 9 Foreword 10 1 Design considerations 11 1.1 Introduction 11 1.2 Client's general requirements 11 1.3 The ground 11 1.3.1 The concept of effective stress 11 1.3.2 Ground profile 13 1.3.3 Groundwater

More information

Table of Contents 18.1 GENERAL Overview Responsibilities References

Table of Contents 18.1 GENERAL Overview Responsibilities References Table of Contents Section Page 18.1 GENERAL... 18.1-1 18.1.1 Overview... 18.1-1 18.1.2 Responsibilities... 18.1-1 18.1.3 References... 18.1-2 18.2 MISCELLANEOUS FOUNDATION DESIGNS... 18.2-1 18.2.1 Buildings...

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK Immersed Tunnels Richard Lunniss and Jonathan Baber CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Group, an informa business A SPON BOOK Contents

More information

Presentation Outline. Need for Creative Solutions in Technical Construction Problems. creativity, imagination, and innovative skills.

Presentation Outline. Need for Creative Solutions in Technical Construction Problems. creativity, imagination, and innovative skills. Construction Engineering Process and Knowledge Requirements for Fostering Creative Design Solutions on Infrastructure Projects Robert B. Bittner, Bittner-Shen Consulting Engineers Robert L. Schmitt, University

More information

Strengthening of prestressed viaducts by means of a reinforced concrete overlay

Strengthening of prestressed viaducts by means of a reinforced concrete overlay Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Strengthening of prestressed viaducts by means of a reinforced concrete overlay R.W.

More information

The HKIE Structural Examination Written Examination

The HKIE Structural Examination Written Examination The HKIE Structural Examination Written Examination Section 2: Design Questions (80% of the Written Examination) Date: 28 November 2014 (Friday) Time: 12:00 nn - 06:00 pm Answer ONE question only Question

More information

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil Geotechnical Aspects of Underground Construction in Soft Ground Viggiani (ed) 2012 Taylor & Francis Group, London, ISBN 978-0-415-68367-8 Evaluation of negative skin friction on sheet pile walls at the

More information

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications.

Box Culverts. Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. Box Culverts Box Culverts Easy to install, suitable for very shallow or deep fill, ideal for use in a wide variety of civil engineering applications. 2 3 System Overview Forterra is one of the largest

More information

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2*

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2* Golden Jubilee Conference of the IGS Bangalore Chapter, Geo-Innovations, 30-31 October 2014 Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering

More information

The Study of Reservoir Immersion of a Hydropower Station

The Study of Reservoir Immersion of a Hydropower Station 2017 2 nd International Conference on Architectural Engineering and New Materials (ICAENM 2017) ISBN: 978-1-60595-436-3 The Study of Reservoir Immersion of a Hydropower Station Shi You Zhang, Ai Guo Li

More information

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5 .364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. Due: Friday December 2. This question concerns the stability of an open slope cutting that will be used to provide construction access for a 3.2m deep

More information

POSTER PAPER PROCEEDINGS

POSTER PAPER PROCEEDINGS ITA - AITES WORLD TUNNEL CONGRESS 21-26 April 2018 Dubai International Convention & Exhibition Centre, UAE POSTER PAPER PROCEEDINGS Advanced Developments in Steel and RC Immersed Tunnels Hideki Sakaeda

More information

B701 WATERMAINS- OPSS 701

B701 WATERMAINS- OPSS 701 B701 - OPSS 701 701.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong Geotechnical Engineering Office Civil Engineering Department The Government of the Hong Kong Special Administrative Region

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Ground Improvement Techniques

Ground Improvement Techniques Geotechnics Day 12 th November 2013 Ground Improvement Techniques David Shohet MSc DIC CEng MICE Specialist Geotechnical Engineer Introduction and Objectives To provide an overview of the more common ground

More information

The HKIE Structural Examination Written Examination 2017

The HKIE Structural Examination Written Examination 2017 The HKIE Structural Examination Written Examination 2017 Section 2: Design Questions (80% of the Written Examination) Date: 5 December 2017 (Tuesday) Time: 12:00 nn 06:00 pm (Duration: 6 hours) Question

More information

B441 - WATERMAINS - OPSS GENERAL

B441 - WATERMAINS - OPSS GENERAL B441 - - OPSS 441 441.1 GENERAL Watermains are a component of a water supply network. Watermains are a system of engineered hydraulic components designed for the conveyance of water from storage to consumption.

More information

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc. Design and Construction of the SH58 Ramp A Flyover Bridge over IH70 Gregg A. Reese, PE, CE, Summit Engineering Group, Inc., Littleton, CO ABSTRACT: The SH58 Ramp A bridge in Golden, CO is the latest on

More information

Note on the assessment:

Note on the assessment: EXCERPTS Note on the assessment: The following is an excerpt from the book Post-disaster shelter: 10 Designs, IFRC, 2013. Inclusion of this design is for information purposes and does not necessarily imply

More information

DIRECT TRANSFER COAL FACILITY

DIRECT TRANSFER COAL FACILITY DIRECT TRANSFER COAL FACILITY Excavation and Dewatering MANAGEMENT PLAN - Final SUBMITTED June 1st, 2014 FRASER SURREY DOCKS COAL TRANSLOAD FACILITY PIT EXCAVATION AND DEWATERING MANAGEMENT PLAN Table

More information

CEX6230 GEOTECHNICS Dear Student:

CEX6230 GEOTECHNICS Dear Student: CEX6230 GEOTECHNICS 31.05.2010 Dear Student: Geotechnics (CEX6230) discusses design and construction aspects of Geotechnical Engineering. Even though this course requires a pass in CEX4230, I find that

More information

Structural Performance of Immersed Tunnel Element at Flexible Joint. Jian Sun Tongji University August 4, 2015

Structural Performance of Immersed Tunnel Element at Flexible Joint. Jian Sun Tongji University August 4, 2015 Structural Performance of Immersed Tunnel Element at Flexible Joint Jian Sun Tongji University August 4, 2015 Immersed Tunnel Fit for underwater transportation passage project Prefabricated tunnel tube

More information

Testing of ground anchorages for a deep excavation retaining system in Bucharest

Testing of ground anchorages for a deep excavation retaining system in Bucharest XV Danube - European Conference on Geotechnical Engineering (DECGE 2014) H. Brandl & D. Adam (eds.) 9-11 September 2014, Vienna, Austria Paper No. 176 Testing of ground anchorages for a deep excavation

More information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information Table of Contents Section Page 5.1 GENERAL... 5.1-1 5.1.1 Overview... 5.1-1 5.1.2 Investigation and Engineering Information... 5.1-2 5.2 PRELIMINARY GEOTECHNCIAL REPORTS... 5.2-1 5.2.1 Preliminary Geotechnical

More information

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc. Paper prepared for presentation at the Bridges in a Climate of Change

More information

UNIT V RETAINING WALLS RETAINING WALL 2.5. Retaining walls are structures used to retain earth or water or other materials such as coal, ore, etc; where conditions do not permit the mass to assume its

More information

Chapter 1. Introduction to Engineering Ground Modification. The Need for Engineered Ground Improvement

Chapter 1. Introduction to Engineering Ground Modification. The Need for Engineered Ground Improvement Chapter 1 Introduction to Engineering Ground Modification The Need for Engineered Ground Improvement As more and more land becomes subject to urban or industrial development, good construction sites and

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Hamilton Rapid Transit Preliminary Design and Feasibility Study

Hamilton Rapid Transit Preliminary Design and Feasibility Study Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT DESIGN BRIEF Version:1.0 Hamilton Rapid Transit Preliminary Design and Feasibility Study B-LINE STRUCTURAL ASSESSMENT

More information

Building Construction

Building Construction Building Construction Shallow Foundations Module-III Introduction The foundation can be classified broadly into two types: Shallow foundations Deep foundations Shallow foundations Shallow Foundations When

More information

ANALYSIS AND ASSESSMENT OF ARTICULATED SKEW HOLLOW SLAB BEAM BRIDGE

ANALYSIS AND ASSESSMENT OF ARTICULATED SKEW HOLLOW SLAB BEAM BRIDGE Istanbul Bridge Conference August 11-13, 2014 Istanbul, Turkey ANALYSIS AND ASSESSMENT OF ARTICULATED SKEW HOLLOW SLAB BEAM BRIDGE Ying Yang 1 Yiqiang Xiang 2 Xiaoyang He 2 Yuliang He 2 ABSTRACT When a

More information

Earth Retaining System

Earth Retaining System Hashemite University Department of Civil Engineering Foundation Engineering Dr. Omar Al-Hattamleh Earth Retaining System Earth slopes and earth retaining structures Used to maintain two different ground

More information

DISPLACEMENT OF DIAPHRAGM WALL FOR VERY DEEP BASEMENT EXCAVATION IN SOFT BANGKOK CLAY

DISPLACEMENT OF DIAPHRAGM WALL FOR VERY DEEP BASEMENT EXCAVATION IN SOFT BANGKOK CLAY Geotec., Const. Mat. & Env., DOI: https://doi.org/10.21660/2018.46.7291 ISSN: 2186-2982 (Print), 2186-2990 (Online), Japan DISPLACEMENT OF DIAPHRAGM WALL FOR VERY DEEP BASEMENT EXCAVATION IN SOFT BANGKOK

More information

Blaxland's Crossing Bridge, Wallacia NSW Bearing Replacement

Blaxland's Crossing Bridge, Wallacia NSW Bearing Replacement Blaxland's Crossing Bridge, Wallacia NSW Bearing Replacement ABSTRACT Ken Maxwell, Arcadis Australia Pacific, Sydney, Australia The existing bridge (known as Blaxland s Crossing) carries Silverdale Road

More information

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

Passage under Lövstavägen at Bypass Stockholm From Design to Realization Passage under Lövstavägen at Bypass Stockholm From Design to Realization Roslin Mattias 1, Borio Luca 2 and Tomas Hellström 3 1 Swedish Transport Administration, Solna Strandväg 98, 171 54 Solna, mattias.roslin@trafikverket.se

More information

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) ,

Steve Haines, P.E., Parsons, (303) , James Studer, Kiewit, (926) , PLACEMENT OF PRECAST PRESTRESSED CONCRETE GIRDER BRIDGE SPANS WITH SELF PROPELLED MODULAR TRANSPORTERS PIONEER CROSSING DESIGN/BUILD PROJECT, AMERICAN FORK, UT Steve Haines, P.E., Parsons, (303) 831-8100,

More information

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND AND Introduction to Structural Analysis TYPES OF STRUCTURES LOADS INTRODUCTION What is the role of structural analysis in structural engineering projects? Structural engineering is the science and art

More information

Sabah Shawkat Cabinet of Structural Engineering 2017

Sabah Shawkat Cabinet of Structural Engineering 2017 3.9 Concrete Foundations A foundation is a integral part of the structure which transfer the load of the superstructure to the soil without excessive settlement. A foundation is that member which provides

More information

Pile foundations Introduction

Pile foundations Introduction Engineering manual No. 12 Updated: 06/2018 Pile foundations Introduction Program: Pile, Pile CPT, Pile Group The objective of this engineering manual is to explain the practical use of programs for the

More information

DFI DEEP FOUNDATIONS. Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist F E

DFI DEEP FOUNDATIONS. Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist F E U N DAIONS IN O F P D DFI S I U DP FOUNDAIONS Mar/Apr 2012 he Magazine of the Deep Foundations Institute Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist op slab construction

More information

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING PART 1 GENERAL SECTION 02221 TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING 1.01 SECTION INCLUDES A. Excavation, dewatering and backfilling with compaction of trenches for pipes, conduits, channels

More information

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015

Tolerances for Concrete Construction. Tolerances for Concrete Construction. Tolerance 6/16/2015 Tolerances for Concrete Construction Thomas J Downs P.E., FACI President Forensic Experts Minneapolis, MN What is it? Tolerances for Concrete Construction When did we start this anyway? Who said we needed

More information

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG Meeting September 5 th, 2006 1 Agenda 1. Study Update 2. Construction Staging for Tunneling 3. Other Business 2 Deep Borehole Program 3 Status Update - Engineering

More information

REPORT STATUS: DATE: Report n :

REPORT STATUS: DATE: Report n : REPORT: Expanded clay LWA in CEA Lightweight fill and thermal insulation products for civil engineering applications. Installation and structural quality control on site. STATUS: Technical report DATE:

More information

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan Possible solution to past CM exam question Question 2 July 2015 New city centre office block by Rajavel Inbarajan The information provided should be seen as an interpretation of the brief and a possible

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

Performance review of a pipe jacking project in Hong Kong

Performance review of a pipe jacking project in Hong Kong Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Performance review of a pipe jacking project in Hong Kong

More information

Transverse flexural and torsional strength of Prestressed Precast Hollow-Core Slabs

Transverse flexural and torsional strength of Prestressed Precast Hollow-Core Slabs Tailor Made Concrete Structures Walraven & Stoelhorst (eds) 2008 Taylor & Francis Group, London, ISBN 978-0-415-47535-8 Transverse flexural and torsional strength of Prestressed Precast Hollow-Core Slabs

More information

Austral Deck Design for Construction Loading. Permanent formwork and Span capability

Austral Deck Design for Construction Loading. Permanent formwork and Span capability Austral Deck Design for Construction Loading Permanent formwork and Span capability Introduction The purpose of this document is to demonstrate the process of designing Austral Deck as formwork complying

More information

MIDAS Training Series

MIDAS Training Series MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session

More information

Performance of Mechanically Stabilized Earth walls over compressible soils

Performance of Mechanically Stabilized Earth walls over compressible soils Performance of Mechanically Stabilized Earth walls over compressible soils R.A. Bloomfield, A.F. Soliman and A. Abraham The Reinforced Earth Company, Vienna, Virginia, USA ABSTRACT: Two projects have recently

More information

Section 1: Summary and recommendations Volumes 1 3

Section 1: Summary and recommendations Volumes 1 3 Section 1: Summary and recommendations Volumes 1 3 Volume 1: Seismicity, soils and the seismic design of buildings Section 2: Seismicity In this section the Royal Commission discusses the forces giving

More information

EXPERIMENTAL INVESTIGATION ON THE INTERACTION OF REINFORCED CONCRETE FRAMES WITH PRECAST-PRESTRESSED CONCRETE FLOOR SYSTEMS

EXPERIMENTAL INVESTIGATION ON THE INTERACTION OF REINFORCED CONCRETE FRAMES WITH PRECAST-PRESTRESSED CONCRETE FLOOR SYSTEMS EXPERIMENTAL INVESTIGATION ON THE INTERACTION OF REINFORCED CONCRETE FRAMES WITH PRECAST-PRESTRESSED CONCRETE FLOOR SYSTEMS B.H.H. Peng 1, R.P. Dhakal 2, R.C. Fenwick 3, A.J. Carr 4 and D.K. Bull 5 1 PhD

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk dr inż. Marcin Blockus INGEO Sp. z o.o. Mobile: +48 505 24 38 37 E-mail: blockus@ingeo.com.pl The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah

Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT. Steven Bartlett, University of Utah 1 Long-Term Settlement Performance Monitoring, I-15 Reconstruction Project, Salt Lake City, UT Steven Bartlett, University of Utah Roadway Widening (I-15 Project) Salt Lake City Utah, USA 2002 Host of

More information

Civil Engineering Construction I (CBE5031)

Civil Engineering Construction I (CBE5031) Civil Engineering Construction I (CBE5031) Basement 1 1 Quick Revision 1.1 Problems arising from basement construction a) Excavation method. b) Surface and ground water control c) Lateral stability of

More information

DETENTION, RETENTION AND RECHARGE STRUCTURES

DETENTION, RETENTION AND RECHARGE STRUCTURES DETENTION, RETENTION AND RECHARGE STRUCTURES Introduction Foundation, trenchwall, bedding and backfill considerations for multiple barrel detention systems are not unlike those for conventional CSP installations.

More information

ENGINEERING DIRECTIVE

ENGINEERING DIRECTIVE Number: E-95-001 Date: 2/2/95 ENGINEERING DIRECTIVE Ross B. Dindio (Signature on Original) CHIEF ENGINEER The purpose of this engineering directive is to formally notify ALL Department engineering personnel

More information

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

Prepared by Elie F. Issa, Eng. D.E.C. August 2016 Prepared by Elie F. Issa, Eng. D.E.C. August 2016 SAMA BEIRUT Sama Beirut is the tallest reinforced concrete tower in Lebanon soaring at a height of 220m from ground level Project Entities Owner Antonios

More information

Tarbutton Road Interchange and I-20 Frontage Roads. Estimating and Planning Group

Tarbutton Road Interchange and I-20 Frontage Roads. Estimating and Planning Group Tarbutton Road Interchange and I-20 Frontage Roads Dr. N. Wasiuddin Braden Smith Jared Taylor John Harrison Sarah Wells Samantha Tatro Ryan Ross Instructor Project Manager Transportation Group Geotechnical

More information

(laboratory) (fall semester)

(laboratory) (fall semester) Civil Engineering Courses-1 CIV 211/Surveying Prerequisite: MAT 127 An introduction to the theory and applications of modern surveying processes. Students use optical and digital land surveying instruments

More information

Underground Construction Technology

Underground Construction Technology Underground Construction Technology Course Lectures Part 4.2 Permanent support Dr Ákos TÓTH 1 Segmental Lining in TBM Tunnelling Segmental lining is the support system for shield TBM excavated tunnels.

More information

Shallow Cover Tunnel Under Heritage Listed Brick Buildings: Brisbane Boggo Road Busway Tunnel

Shallow Cover Tunnel Under Heritage Listed Brick Buildings: Brisbane Boggo Road Busway Tunnel Shallow Cover Tunnel Under Heritage Listed Brick Buildings: Brisbane Boggo Road Busway Tunnel by Ted Nye, Tunnel Designer Manager, Sinclair Knight Merz and Max Kitson, Senior Geotechnical Engineer, Sinclair

More information

Risk Management of the Restoration of Shanghai Metro Line 4

Risk Management of the Restoration of Shanghai Metro Line 4 ISGSR2007 First International Symposium on Geotechnical Safety & Risk Oct. 18~19, 2007 Shanghai Tongji University, China Risk Management of the Restoration of Shanghai Metro Line 4 X. P. Yu, W. J. Zhu

More information

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1 Alberta Environment Page 13-1 13.0 DROP INLET SPILLWAYS 13.1 General The drop inlet spillway is commonly used for providing flood protection for earth dams which have smaller reservoirs and/or smaller

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3 CITY OF TORONTO TS 3.70 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS 3.70.01 SCOPE...3 TS

More information

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall Geotechnical Aspects of Underground Construction in Soft Ground Yoo, Park, Kim & Ban (Eds) 2014 Korean Geotechnical Society, Seoul, Korea, ISBN 978-1-138-02700-8 Case study of deep excavation in existing

More information

Groundwater Control for Design & Construction

Groundwater Control for Design & Construction PDH Course C587 (2 PDH) Groundwater Control for Design & Construction Instructor: T. E. McLaughlin, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088

More information

SECANT PILE. Introduction:

SECANT PILE. Introduction: SECANT PILE Introduction: Over the last few decades construction of retaining walls in urban areas has grown significantly, as a result of territorial and economical development of the cities. In most

More information

3.4.2 DESIGN CONSIDERATIONS

3.4.2 DESIGN CONSIDERATIONS 3.4.2 DESIGN CONSIDERATIONS Formwork Where Flatdeck sheet is used as formwork, the profile provides resistance to wet concrete (G) and construction loads (Q). Maximum formwork spans given in Section 3.4.4.1

More information

Case Histories in Geotechnical Engineering

Case Histories in Geotechnical Engineering Fourth International Conference on Case Histories in Geotechnical Engineering March 8 12, 1998, St. Louis, Missouri, USA Editor : Shamsher Prakash Prediction and performances of short embedded cast in-situ

More information

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting.

ARMOR-BLOCK. Installation guide. Installation Manual: ARMOR-BLOCK Retaining Wall System. Cap Block. Exposed void for planting. ARMOR-BLOCK Installation guide Cap Block Exposed void for planting In situ soil Engineered backfill Compacted and prepared base Setback Lip Ph 0800 655 00 or visit www.csppacific.co.nz 19 February 08 /

More information

Challenges of quick clay excavation in urban area with sloping ground

Challenges of quick clay excavation in urban area with sloping ground Challenges of quick clay excavation in urban area with sloping ground R. M. Nalbant 1 Multiconsult AS, Oslo, Norway ABSTRACT The paper presents the overall stability evaluation for a deep excavation in

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing Horizontal Ellipse By eliminating the need for concrete footings this shape can often provide the lowest overall installed cost of any long span structure. If a natural stream bottom is desired the invert

More information

reinforced besser block retaining walls

reinforced besser block retaining walls reinforced besser block retaining walls Preface The designs shown in the brochure are based on limit state design in accordance with the provisions of AS4678-2002 Earth retaining structures standard including

More information

of New Hampshire, USA

of New Hampshire, USA Centrifuge Test to Evaluate Internal Strut Loads in Shallow Underground Retaining Structures Adrienne HILL a, Jill GETCHELL a and Majid GHAYOOMI b,1 a Research Assistant, Department of Civil and Environmental

More information

UHPC Connection of Precast Bridge Deck

UHPC Connection of Precast Bridge Deck Jan L. Vitek, Metrostav, a.s. and CTU in Prague Jiri Kolisko, CTU in Prague, Klokner Institute David Citek, CTU in Prague, Klokner Institute Stanislav Rehacek, CTU in Prague, Klokner Institute Robert Coufal,

More information

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS AFTER FEBRUARY 1, 2011 ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS 481.1 Description. This specification shall govern for the construction of monolithic, reinforced concrete box sewers of the size,

More information

An information series from the national authority on concrete masonry technology. Drainage swale. (optional) Cap unit. (optional)

An information series from the national authority on concrete masonry technology. Drainage swale. (optional) Cap unit. (optional) Provided by: Brown's Concrete Products Limited An information series from the national authority on concrete masonry technology ROLES AND RESPONSIBILITIES ON SEGMENTAL RETAINING WALL PROJECTS TEK 15-3A

More information

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS Peter, BAUER Spezialtiefbau GmbH, Schrobenhausen, Germany, +49 8252 974266, +49 8252 971496, peter.banzhaf@bauer.de

More information

S. Gandhi *1, Syed Rizwan 2

S. Gandhi *1, Syed Rizwan 2 2017 IJSRSET Volume 3 Issue 3 Print ISSN: 2395-1990 Online ISSN : 2394-4099 Themed Section: Engineering and Technology Analysis and Design of Tall Building (G+21) Using ETABS S. Gandhi *1, Syed Rizwan

More information

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

NPTEL Course GROUND IMPROVEMENT USING MICROPILES Lecture 22 NPTEL Course GROUND IMPROVEMENT USING MICROPILES Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Email: gls@civil.iisc.ernet.in Contents

More information

Application of Vibro Techniques for Infrastructure Projects in India

Application of Vibro Techniques for Infrastructure Projects in India Application of Vibro Techniques for Infrastructure Projects in India Rainer Wegner Contract Manager, Keller Grundbau GmbH, Germany Dr. V.R. Raju Director, Keller Ground Engineering India Pvt Ltd, India

More information

October BC MoTI

October BC MoTI 7.1 SCOPE... 2 7.5 STRUCTURAL DESIGN... 3 7.5.2 Load factors... 3 7.5.5 Seismic requirements... 4 7.5.5.4 Seismic design of concrete structures... 4 7.6 SOIL-METAL STRUCTURES... 4 7.6.2 Structural materials...

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information