A Design Review of Waterproofing Codes

Size: px
Start display at page:

Download "A Design Review of Waterproofing Codes"

Transcription

1 A Design Review of Waterproofing Codes Section 1807 of Chapter 18 of the International Building Code addresses waterproofing under the section title of Dampproofing and Waterproofing. The section defines the essentials of waterproofing design as when it is to be applied, where to apply it and drainage issues. The code also provides a good description of what is considered waterproofing and what is considered dampproofing, while defining where they are required. The intent of this article is to include some of the waterproofing codes that pertain to design elements and provide interpretation Where required. Walls or portions thereof that retain earth and enclose interior spaces and floors below grade shall be waterproofed and dampproofed in accordance with this section. With the exception of those spaces containing groups other than residential and institutional where such omission is not detrimental to the building or occupancy. Ventilation crawl spaces shall comply with Section This section implies that all occupied below-grade spaces require the application of a waterproofing or dampproofing material. The exception is to all unoccupied spaces. Once is has been determined that waterproofing or dampproofing is required the next important decision is to determine where it is required. Typically, waterproofing or dampproofing should be applied over all below grade concrete surfaces (walls and floors). There are several established building components that require waterproofing or dampproofing protection, they are: Underground structures Elevated structural slabs over underground spaces Structural slabs below grade Structural slabs above grade Foundations Lagging walls Plazas Terraces Promenades Planters

2 Ground-water control. Where the ground-water table is lowered and maintained at an elevation not less than 6 inches (152 mm) below the bottom of the lowest floor, the floor and walls shall be dampproofed in accordance with Section The design of the system to lower the ground-water table shall be based on accepted principles of engineering that shall consider, but not necessarily be limited to, permeability of the soil, rate at which water enters the drainage system, rated capacity of pumps, head against which pumps are to operate and the rated capacity of the disposal area of the system. This section implies that dampproofing is required if the water table is maintained a minimum of six (6) inches below the bottom of the structure. If the water table is maintained within six (6) inches of the bottom of the structure or if hydrostatic pressure exists, than waterproofing is required. It is the designer s responsibility to review site-engineering analysis for water table conditions and soil analysis to determine if and what type of dampproofing or waterproofing is required. The section also implies that the ground-water table must be lowered by implementing a drainage system that is designed to meet the following engineering principles: 1. Permeability of the soil 2. Rate at which water enters the drainage system 3. Rated capacity of the pumps 4. Head against which pumps are to operate 5. Rate capacity of the designed area of the system Dampproofing required. Where hydrostatic pressure will not occur as determined by Section , floors and walls for other than wood foundation systems shall be dampproofed in accordance with this section. Wood foundation systems shall be constructed in accordance with AF&PA Technical Report No. 7. This section implies that dampproofing is required to all below grade floors and walls where hydrostatic pressure will not occur. ASTM defines dampproofing as the treatment of a surface or structure to block the passage of water in the absence of hydrostatic pressure. Fundamentally, it only has the ability to resist vapor migration. If soil analysis concludes that there is no hydrostatic pressure or if the water table is more than six (6) inches below the lowest floor, than dampproofing may be considered.

3 Dampproofing is always applied at the exterior (wet) face of the wall. The most common dampproofing material for walls is a bituminous coating, either solvent-based (cutback asphalt) or emulsion, brushed, sprayed, roller-coated or troweled on the substrate. Dampproofing systems may also include membranes. The general difference between waterproofing systems and dampproofing systems is that dampproofing membranes maximize at 10-mil film thickness and waterproofing membranes exceed this thickness. The section also implies that wood foundations shall be constructed in accordance with AF&PA Technical Report No. 7, Basic Requirements for Permanent Wood Foundation Systems Waterproofing required. Where the ground-water investigation required by Section indicates that a hydrostatic pressure condition exists, and the design does not include a ground-water control system as described in Section , walls and floors shall be waterproofed in accordance with this section. This section implies that a waterproofing application is completed when the site ground water table is maintained at an elevation of not less than six (6) inches below the bottom of the ground slab. The section states that waterproofing is required when hydrostatic pressure will occur. It is the responsibility of the architect or designer to make certain that the waterproofing component is in compliance with the applicable Federal, State or Local codes. The primary distinction of the codes in regards to water table and hydrostatic pressure. A proper engineering study of the grounds is required to establish this criterion for the design phase. ASTM states that dampproofing or waterproofing is required for slabs on ground and foundation retaining walls Floors. Floors required to be waterproofed shall be of concrete and designed and constructed to withstand the hydrostatic pressures to which the floors will be subjected. This section implies that all floors that require waterproofing shall be constructed of concrete and shall be of structural integrity to withstand hydrostatic pressure. The waterproofing applied to the floors shall consist of one of the following membranes: Rubberized asphalt Butyl Rubber Fully adhered/hdpe 6-mil+ polyvinyl chloride (PVC) The membrane joints shall be lapped a minimum of six (6) inches and shall be applied in accordance with the membrane manufacturers latest printed requirements.

4 Walls. Walls required to be waterproofed shall be of concrete or masonry and shall be designed and constructed to withstand the hydrostatic pressures and other lateral loads to which the walls will be subjected. This section implies that all walls that require waterproofing shall be constructed of concrete or masonry and shall be of structural integrity to withstand hydrostatic pressure and lateral loads. The waterproofing applied at the walls shall consist of one of the following membranes: Two-ply hot moped felts 6-mil+ polyvinyl chloride (PVC) 40-mil polymer modified asphalt 6-mil polyethylene The waterproofing should be applied a minimum of 12 inches above the highest point of the ground water table. The membrane joints shall be lapped in accordance with the membrane manufacturers latest printed requirements Surface preparation of walls. Prior to the application of waterproofing materials on concrete or masonry walls, the walls shall be prepared in accordance with Section This section implies that the wall substrate must be properly prepared to receive waterproofing materials. The wall must be free of all voids, openings, cracks, honeycombs, fissures and other imperfections prior to the application of the waterproofing material. Concrete walls can be repaired using bituminous materials or other products approved by the material manufacturer. Masonry walls shall be parged below ground level on the exterior surface using not less than inch (9.5 mm) of Portland cement. The only exception is approved for application directly to the masonry Joints and penetrations. Joints in walls and floors, joints between the wall and floor and penetrations of the wall and floor shall be made water-tight utilizing approved methods and materials.

5 This section implies that all wall and floor joints must be properly waterproofed. Waterproofing application at joints includes approved sealants. Proper sealant application is completed using proper materials and application methods. The success of the construction sealant is based on proper selection and use of the various sealant materials for a specific application. Sealant selection should be based on the adhering substrates. General recommendations for sealant selection typical in roof applications are as follows: Concrete-to-Concrete: Two part polyurethane Brick to Brick: Two part polyurethane Metal-to-Metal: Perimeter silicone sealant Metal to Brick: Perimeter silicone sealant Metal-to-Metal: Perimeter silicone sealant Metal to Brick: Perimeter silicone sealant The sealant must have the ability to move with the adjacent building substrates while maintaining a watertight barrier. In application it is generally discovered that a thin bead of sealant will accommodate more movement than a thick bead. In joints where excessive movement is expected the building sealant should be no thicker than 1/2 inch and no thinner than 1/8 inch. At typical building joints the ratio of joint width to sealant depth should be a minimum of 2:1. At building expansion joints the designed joint should be at least twice the total anticipated joint movement. However, due to construction tolerances and material variations it is recommended that the joint design be four times the anticipated movement. Preparation of the Joints The joint must be thoroughly cleaned prior to any sealant application. This can be completed by removing all foreign matter and contaminants such as grease, oil, dust, water, frost, surface dirt, old sealants and protective coatings. Porous substrates can be cleaned by grinding; blast cleaning (sand or water) saw cutting or mechanical abrading. A combination of these cleaning methods can also be utilized. All dust and loose particles from these cleaning operations must be removed by vacuum or compressed air to leave a dry, clean surface for sealant application. Metal, glass and plastic surfaces can be cleaned with mechanical or solvent procedures. Check the manufacturers latest printed specifications for the use of detergent or soap and water treatments, they are generally not allowed as suitable cleaning methods. Solvents should be wiped off with clean, oil - and - lint - free cloths.

6 Masking All areas adjacent to the building joints should be masked prior to sealant application. This is to allow for neat sealant lines. Masking the adjoining surfaces also guards against sealant contact with any incompatible surfaces. Uncured sealants can leave a film on a surface that may change the aesthetic surface characteristics of the substrate. In some cases, the only method of sealant removal may be grinding or saw cutting. Generally these surfaces can be cleaned with special cleaning solvents. The masking should be removed immediately following the tooling of the sealant. Sealant Application Install all back up material or joint filler prior to sealant application. Backer rods and joint filler material must be in accordance with the manufacturers latest printed specifications. Open cell polyurethane foam or closed cell polyethylene are the recommended back up materials for most joints. Polyethylene tape may be used for joints that are too shallow for backer rod. The sealant should be applied in a continuous operation using positive pressure to properly fill and seal the joint. Tooling should be completed in a continuous stroke immediately after the sealant application prior to the formation of the sealant skin. The sealant should be tooled with light pressure to spread the material against the back up material and the joint surfaces. The tool should have a concave profile to keep the sealant in the joint. Contrary to popular opinion, a finger is not the proper tool for sealant application Subsoil drainage system. Where a hydrostatic pressure condition does not exist, dammproofing shall be provided and a base shall be installed under the floor and a drain installed around the foundation perimeter. A subsoil drainage system designed and constructed in accordance with Section shall be deemed adequate for lowering the ground water table. This section implies that a subsoil drainage system is required in instances where hydrostatic pressure does not exist. The subsoil drain shall be installed by applying a base layer under the floor and installing a drain around the foundation perimeter. Proper below-grade waterproofing design must include a system for collecting, draining, and discharging groundwater away from the structure. The most effective way to properly collect and discharge groundwater is through the use of foundation drains. Foundation drains can be field-constructed drainage systems or prefabricated soil drainage systems.

7 Field-constructed drainage systems consist of a perforated pipe (typically PVC) that is set in a bed of gravel at the bottom of the foundation. The perforation in the pipe is applied downward to allow the water to flow into the gravel bed. A drainpipe is installed next to the structure slightly above the bottom of the foundation to prevent the soil under the foundation from washing away. The pipe is set to slope the water towards drain fields, bare soil or sump pits. A layer of coarse gravel is set around the drainage pipe for additional water accumulation. In some cases, meshes and/or mats can be applied over the top gravel layer to prevent soil build-up from interfering with water flow to the drainage system. The biggest disadvantage with these systems is that they rely on proper field construction (not always completed properly) and over time they become clogged with dirt, soil and contaminants. It is the designer s responsibility to review site-engineering analysis for water table conditions and soil analysis to determine if and what type of dampproofing or waterproofing is required. The section also implies that the ground-water table must be lowered by implementing a drainage system that is designed to meet the following engineering principles: 1. Permeability of the soil 2. Rate at which water enters the drainage system 3. Rated capacity of the pumps 4. Head against which pumps are to operate Rate capacity of the designed area of the system Foundation drain. A drain shall be placed around the perimeter of a foundation that consists of gravel or crushed stone containing not more than 10-percent that passes through a No. 4 (4.75 mm) sieve. The drain shall extend a minimum of 12 inches (305 mm) beyond the outside edge of the footing. The thickness shall be such that the bottom of the drain is not higher than the bottom of the base under the floor, and that the top of the drain is not less than 6 inches (152 mm) above the top of the footing. The top of the drain shall be covered with an approved filter membrane material. Where a drain tile or perforated pipe is used the invert of the pipe or tile shall be placed higher than the floor elevation. The pipe or tile shall be placed on not less than 2 inches (51 mm) of gravel or crushed stone complying with Section , and shall be covered with not less than 6 inches (152 mm) of the same material.

8 This section provides the requirements for foundation drain placement. requirements and provides a basis for design: The section is precise in the Foundation Drain: 1. Apply a drain around the perimeter of the foundation that consists of gravel or crushed stone. The gravel or crushed stone shall be a minimum of 4.75 mm or larger. 2. The drain shall extend a minimum of 12 inches (305 mm) beyond the outside edge of the footing. 3. The thickness shall be such that the bottom of the drain is not higher than the bottom of the base under the floor, and that the top of the drain is not less than 6 inches (152 mm) above the top of the footing. 4. Cover the top of the drain with an approved filter material. 5. If a drain tile or perforated pipe is used the invert of the pipe or tile shall be placed higher than the floor elevation. 6. The pipe or tile shall be placed on a minimum of two (2) inches of gravel or crushed stone. The gravel or crushed stone shall be a minimum of 4.75 mm or larger Backfill. The backfill in the annular space around columns not embedded in poured footings shall be by one of the following methods: 1. Backfill shall be of concrete with an ultimate strength of 2,000 psi (13.8 MPa) at 28 days. The hole shall not be less than 4 inches (102 mm) larger than the diameter of the column at its bottom or 4 inches (102 mm) larger than the diagonal dimension of a square or rectangular column. 2. Backfill shall be clean sand. The sand shall be thoroughly compacted by tamping in layers not more than 8 inches (203 mm) in depth. 3. Backfill shall be controlled low-strength material (CLSM). This section implies that backfill material shall be in accordance with code requirements. This section was originally contained in the Waterproofing and Dampproofing Section of the BOCA code. In it s original form it addressed backfill around foundations a pertinent component of a waterproofing application. Therefore, it provides relevance and requires addressing from a waterproofing perspective. This section implies that the excavation outside of the foundation shall be backfilled with soil that is free of all organic material, construction debris and large rocks. The backfill shall be placed in lifts no more than 8 inches (203 mm) in depth and compacted or tampered in a manner that has no adverse effect or cause damage to the substrate or the waterproofing or dampproofing material.

BUILDING CODES Presented by CORUM ENGINEERING

BUILDING CODES Presented by CORUM ENGINEERING BUILDING CODES Presented by CORUM ENGINEERING AGENDA I. The Basics of Foundations A. Footer Designs B. Foundation Walls 1. Non-Backfilled Walls 2. Backfilled Walls (Retaining Walls) C. Slabs vs. Crawl

More information

A. The work of this section includes, but is not limited to, the following:

A. The work of this section includes, but is not limited to, the following: SECTION 07 14 00 FLUID APPLIED WATERPROOFING SYSTEM PART 1: GENERAL 1.1 RELATED DOCUMENTS A. All of the Contract Documents, including General and Supplementary Conditions and Division 01 General Requirements,

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DISTRIBUTION EQUIPMENT SPECIFICATION EO-1007 REVISION 13 DECEMBER 2013 EFFECTIVE DATE DECEMBER 16,

More information

SECTION JOINT SEALERS 1.03 THIS SECTION INCLUDES JOINT SEALERS FOR THE FOLLOWING LOCATIONS:

SECTION JOINT SEALERS 1.03 THIS SECTION INCLUDES JOINT SEALERS FOR THE FOLLOWING LOCATIONS: PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 07900 - A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this

More information

ROOF REPLACEMENT AND ALTERATIONS TO WOODSTOCK Barrett Architecture, PC WASTE WATER TREATMENT FACILITY - Woodstock, VT February 28, 2019 SECTION

ROOF REPLACEMENT AND ALTERATIONS TO WOODSTOCK Barrett Architecture, PC WASTE WATER TREATMENT FACILITY - Woodstock, VT February 28, 2019 SECTION SECTION 079200 PART 1 - GENERAL 1.1 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS which are hereby made a

More information

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular

More information

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure

Groundwater Seepage. Causes of Basement Seepage and Leaks Hydrostatic Pressure Groundwater Seepage The following guide can be used by you and your crews when assessing seepage at a property. Bear in mind that this guide is not all-inclusive, and should be used in a supplementary

More information

SECTION PENETRATION FIRESTOPPING PART 1- GENERAL PART 2- PRODUCTS 1.1 RELATED DOCUMENTS

SECTION PENETRATION FIRESTOPPING PART 1- GENERAL PART 2- PRODUCTS 1.1 RELATED DOCUMENTS SECTION 07 8413- PENETRATION FIRESTOPPING PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate Colphene BSW Training and Application Guide Colphene BSW Waterproofing Membrane. 1. Prepare substrate Substrate must be structurally sound. Surface must be free of voids, spalled areas, loose aggregate,

More information

SECTION JOINT SEALANTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION JOINT SEALANTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 07-9200 - JOINT SEALANTS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED

PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED Ministry of Municipal Affairs PROPOSED CHANGE TO THE 2012 BUILDING CODE O. REG. 332/12 AS AMENDED CHANGE NUMBER: SOURCE: B-09-13-03 Ontario-NBC CODE REFERENCE: Division B / 9.13.3. DESCRIPTION OF THE PROPOSED

More information

Construction Standards PAGE

Construction Standards PAGE Construction Standards PAGE 071619-1 SECTION 071619 PART 1 - GENERAL 1.1 M.S.U. ISSUES A. Below grade construction should be protected by self-adhering sheet waterproofing in accordance with SECTION 071326

More information

1 Exam Prep The NRCA Waterproofing Manual 2005 Tabs and Highlights

1 Exam Prep The NRCA Waterproofing Manual 2005 Tabs and Highlights 1 Exam Prep The NRCA Waterproofing Manual 2005 Tabs and s These 1 Exam Prep Tabs are based on the National Roofing Contractors Association (NRCA) manual listed below: Waterproofing Manual - 2013 Each 1

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-07 11 13 (August 2011) Change 1-05/17 --------------------------- Preparing Activity: NAVFAC Superseding UFGS-07 11 13 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Delivery, Storage, and Handling

Delivery, Storage, and Handling TECH DATA SHEET Sections - 071000 / 071300 / 071313 / 071326 / 071352 AVM Aussie Mate 580-AL UV Stable Heavy Duty 60 Mil Bellow Grade Bituminous Waterproofing Sheet Membrane, with Aluminum Backing Product

More information

SECTION BUILT-UP BITUMINOUS WATERPROOFING

SECTION BUILT-UP BITUMINOUS WATERPROOFING SECTION 07 12 00 BUILT-UP BITUMINOUS WATERPROOFING SPEC WRITER NOTE: Delete any item or paragraph not applicable in the section and renumber the paragraphs. PART 1 - GENERAL 1.1 DESCRIPTION: This section

More information

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS 701-1 DESCRIPTION 701-1.1 This item shall consist of the construction of pipe culverts, and storm drains, removal of existing storm pipes, connections to existing

More information

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage. DELTA -DRAIN 6200 Section 07 10 00 Dampproofing and Waterproofing PART 1 GENERAL 1.1 SECTION INCLUDES A. Below grade waterproofing. B. Below grade drainage sheets. C. Plaza deck and planter drainage sheets.

More information

SECTION (07100) - DAMPPROOFING AND WATERPROOFING

SECTION (07100) - DAMPPROOFING AND WATERPROOFING SECTION 07 10 00 (07100) - DAMPPROOFING AND WATERPROOFING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Sheet Membrane Waterproofing 2. Under-Slab-On-Grade Vapor Barrier B. Related Sections: 1.02

More information

SOILS AND FOUNDATIONS

SOILS AND FOUNDATIONS CHAPTER 1 SOILS AND FOUNDATIONS This chapter has been revised in its entirety; there will be no marginal markings. SECTION 101 GENERAL 101.1 Scope. The provisions of this chapter shall apply to building

More information

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage. DELTA -DRAIN Section 07 10 00 Dampproofing and Waterproofing PART 1 GENERAL 1.1 SECTION INCLUDES A. Below grade drainage sheets. B. Plaza deck and planter drainage sheets. 1.2 RELATED SECTIONS A. Section

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance www.epa.gov/iaq/moisture Foundations Issue Building foundations are vulnerable to moisture problems for a number of reasons, including: Water from rain and from plumbing leaks is drawn by gravity to foundations,

More information

SECTION SHEET MEMBRANE WATERPROOFING

SECTION SHEET MEMBRANE WATERPROOFING PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 07 13 00 SHEET MEMBRANE WATERPROOFING A. The provisions of the General Conditions, Supplementary Conditions, and the Sections included under Division 1, General

More information

A. Product Data: Submit manufacturer s product data, with complete general and specific installation instructions, recommendations, and limitations.

A. Product Data: Submit manufacturer s product data, with complete general and specific installation instructions, recommendations, and limitations. SECTION 071700 - BENTONITE WATERPROOFING PART 1 - GENERAL 1.1 WORK SUMMARY A. The work of this section includes, but is not limited to the furnishing and installing the following materials, per project

More information

SECTION UNIT PAVERS

SECTION UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Concrete pavers. 2. Detectable warning pavers. 3. Warning stripe pavers. 1.2 SUBMITTALS A. Product Data: For the following: 1. Pavers.

More information

1.3 Work shall include all reinforcement and accessories necessary to complete installation.

1.3 Work shall include all reinforcement and accessories necessary to complete installation. CERAMIC TILING GENERAL INFORMATION 1.1 Ceramic mosaic tile floors and bases, glazed wall tile wainscots and walls, and marble thresholds. 1.2 Installation will typically be with latex-portland cement mortar

More information

LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap

LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS. Diagram 1: Standard Membrane Continuation 150 mm Overlap LIQUID RUBBER INDUSTRIES ENGINEERING SPECIFICATIONS FOR ENGINEERS AND ARCHITECTS Diagram 1: Standard Membrane Continuation 150 mm Overlap Ensure Membrane to Membrane Contact Diagram 2: Membrane Continuation

More information

***************************************************************************************************************

*************************************************************************************************************** 09330 QUARRY TILE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 09 30 16 ***************************************************************************************************************

More information

SECTION SELF-ADHERING SHEET MEMBRANE WATERPROOFING

SECTION SELF-ADHERING SHEET MEMBRANE WATERPROOFING SECTION 07 13 26 PART 1 - GENERAL 1.1 SUMMARY A. Scope: 1. Apply waterproofing to: a. Exterior of walls below grade: 1) Waterproofing shall include exterior of walls surrounding elevator pits and sumps.

More information

SECTION WASTE WATER DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-Place Concrete.

SECTION WASTE WATER DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-Place Concrete. SECTION 02735 WASTE WATER DRAINAGE SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02221 - Excavating, Backfilling, and Compaction for Utilities. 2. 03300 - Cast-in-Place Concrete. 1.02 REFERENCES

More information

FirstEnergy Program Overview

FirstEnergy Program Overview FirstEnergy Program Overview Builder incentives $400 per unit + $0.10/kWh in projected savings Eligibility Located in service area of a FirstEnergy Utility Certificate of Occupancy Dates: FirstEnergy Ohio

More information

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs November 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements....................................

More information

FLUID APPLIED WATERPROOFING

FLUID APPLIED WATERPROOFING SECTION 07120 FLUID APPLIED WATERPROOFING PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03300 - Cast-In-Place Concrete. 2. 09200 - Metal Studs, Metal Lath, Suspension Ceilings, Plaster, and Stucco.

More information

Radon Resistant New Construction. Topic 8 - Audio 64

Radon Resistant New Construction. Topic 8 - Audio 64 Topic 8 - Audio 64 EPA Map of Radon Zones Designations drawn in by county boundary to match code jurisdictions Indicates the potential for a short-term measurement in the lowest portion of the home to

More information

Dist. by: BEST MATERIALS Ph:

Dist. by: BEST MATERIALS Ph: Dist. by: BEST MATERIALS Ph: 800-474-7570 www.bestmaterials.com Email: Sales@BestMaterials.com NOVALINK SL SELF-LEVELING CONSTRUCTION SEALANT DIVISION 7 - THERMAL AND MOISTURE PROTECTION SECTION 07 92

More information

***********************************************************************************

*********************************************************************************** AQUAFIN-2K/M Two-Component Cement-based Acrylic-based Waterproofing GUIDE AQUAFIN, Inc. SPECIFICATION PART 1 - GENERAL 1.1 SECTION INCLUDES SECTION 07 16 14 ACRYLIC MODIFIED (FLEXIBLE) CEMENTITIOUS WATERPROOFING

More information

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items:

ITEM 431 PNEUMATICALLY PLACED CONCRETE. All material shall conform to the pertinent requirements of the following items: ITEM 431 PNEUMATICALLY PLACED CONCRETE 431.1. Description. This Item shall govern for furnishing and placing of "Pneumatically Placed Concrete" for encasement of designated structural steel members, the

More information

1. Rubberized asphalt waterproofing membrane, reinforced. 2. Molded sheet drainage panels. 3. Insulation. 4. Plaza deck pavers.

1. Rubberized asphalt waterproofing membrane, reinforced. 2. Molded sheet drainage panels. 3. Insulation. 4. Plaza deck pavers. SECTION 071413 HOT FLUID APPLIED RUBBERIZED ASPHALT WATERPROOFING PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Rubberized asphalt waterproofing membrane, reinforced. 2. Molded sheet drainage panels.

More information

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS SECTION 32 14 13.16 PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs used as ballast and/or paving on

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

SECTION CAST-IN-PLACE CONCRETE

SECTION CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 03 30 00 CAST-IN-PLACE CONCRETE A. Cast-in-place concrete building frame members, floors, shear walls, elevator shaft walls, foundation walls, footings, and

More information

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals.

See the IRC for additional information. See CPD-DS Information Bulletin 100 for Requirements for 1 & 2 Family Dwelling plan submittals. As a customer service initiative, the Kansas City, Missouri, City Planning and Development Department/Development Services, in cooperation with the Greater Kansas City Home Builders Association, has developed

More information

2/23/2009 R15-R20R20

2/23/2009 R15-R20R20 Foundations What is important to know about foundations? You (probably) won t design it What are the components that make up a properly designed and built foundation? Determine whether house has a good

More information

SECTION CAST IN PLACE CONCRETE PART 1 GENERAL 1.01 RELATED DOCUMENTS

SECTION CAST IN PLACE CONCRETE PART 1 GENERAL 1.01 RELATED DOCUMENTS SECTION 03301 - CAST IN PLACE CONCRETE PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

***************************************************************************************************************

*************************************************************************************************************** 02735 WASTE WATER DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 22 14 00 ***************************************************************************************************************

More information

Section Pre-Applied Sheet Membrane Waterproofing

Section Pre-Applied Sheet Membrane Waterproofing Section 071324 Pre-Applied Sheet Membrane Waterproofing PART 1 GENERAL 1.01 SUMMARY A. The Work of this Section includes, but is not limited to, pre-applied sheet membrane waterproofing that forms an integral

More information

ITEM 458 WATERPROOFING FOR STRUCTURES

ITEM 458 WATERPROOFING FOR STRUCTURES ITEM 458 WATERPROOFING FOR STRUCTURES 458.1. Description. This Item shall govern for the furnishing and placing of waterproofing on concrete and steel bridge decks of railroad structures and on other structures

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

PLATON FOUNDATION WRAP

PLATON FOUNDATION WRAP DRAINAGE SOLUTIONS SINCE 1908 PLATON FOUNDATION WRAP RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS DRY ADVANCED TECHNOLOGY EASY INSTALLATION PROVEN PERFORMANCE ARMTEC.COM

More information

CARLISLE DECK COATING INSTALLATION OVER EXISTING POLYURETHANE COATINGS

CARLISLE DECK COATING INSTALLATION OVER EXISTING POLYURETHANE COATINGS CARLISLE DECK COATING INSTALLATION OVER EXISTING POLYURETHANE COATINGS 1. GENERAL A. When coating over existing coatings, Carlisle can not assume responsibility for the adhesion of the existing coating,

More information

RESIDENTIALFOUNDATION GUIDELINE

RESIDENTIALFOUNDATION GUIDELINE Department of Community Development 04/01/2019 RESIDENTIALFOUNDATION GUIDELINE Johnson County Building Officials Association Residential Foundation Guideline This document is provided through endorsement

More information

B. Fiberglass for construction in back lot easements placed on cast-in-place base.

B. Fiberglass for construction in back lot easements placed on cast-in-place base. Section 02083 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Fiberglass manholes for unpaved areas placed on top of a precast base to form a manhole. B. Fiberglass for construction in back lot easements

More information

Pacific Polymers Elasto-Deck 5000X2 Guide Specification

Pacific Polymers Elasto-Deck 5000X2 Guide Specification 1 071813-1 July 2018 Pacific Polymers Elasto-Deck 5000X2 Guide Specification SECTION 071813 TRAFFIC COATINGS ELASTO-DECK 5000X2 OVER CONCRETE 2 071813-2 July 2018 Pacific Polymers Elasto-Deck 5000X2 Guide

More information

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS

GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS GUIDELINES FOR RETAINING WALLS 4-0 IN HEIGHT OR LESS Version 2014-11-11 Prepared by: Building Development Division Department of Development Services 5 County Complex Ct. Suite 120 Prince William, VA 22192

More information

Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018

Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018 Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018 TK Products A Division of Sierra Corporation TK-HYDROMAX 2001 SB DAMPPROOF COATING, TK-HYDROMAX 2002 SB FOUNDATION WATERPROOF

More information

BITUMEN-SET PRECAST CONCRETE PAVING SLABS

BITUMEN-SET PRECAST CONCRETE PAVING SLABS SECTION 32 14 13.16 BITUMEN-SET PRECAST CONCRETE PAVING SLABS (1995 MasterFormat Section 02784) NOTE: This guide specification is the U.S. for concrete paving slabs adhered with a neoprene mastic to a

More information

4 EXTREME FOUNDATION PANELS

4 EXTREME FOUNDATION PANELS 4 EXTREME FOUNDATION PANELS For House Crawl Space On Concrete Footings 1. The type of soil is a factor in determining foundation construction details such as footing design, backfill, and drainage provisions.

More information

INSTALLATION GUIDELINES

INSTALLATION GUIDELINES INSTALLATION GUIDELINES Please Note: Read these instructions thoroughly before installation to ensure proper use of VaporBlock Plus. ASTM E 1465, ASTM E 2121 and, ASTM E 1643 also provide valuable information

More information

SECTION FLUID-APPLIED WATERPROOFING

SECTION FLUID-APPLIED WATERPROOFING SECTION 07140 FLUID-APPLIED WATERPROOFING PART 1 GENERAL 1.1 SUMMARY A. Section includes fluid applied rubberized asphalt and/or elastomeric membrane waterproofing; and surface dusting and/or protective

More information

SECTION SEALANTS AND CAULKING

SECTION SEALANTS AND CAULKING SECTION 07920 SEALANTS AND CAULKING PART 1 - GENERAL 1.1 DESCRIPTION: Section covers all sealant and caulking materials and their application, wherever required for complete installation of building materials

More information

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE:

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE: SECTION 07651 FLEXIBLE COPPER SHEET FLASHINGS Advanced Building Products, Inc. manufacturer many types of flexible copper sheet flashings. Due to their ductility, high tensile strength, and resistance

More information

SECTION MODIFIED BITUMINOUS SHEET WATERPROOFING

SECTION MODIFIED BITUMINOUS SHEET WATERPROOFING PART 1 - GENERAL 1.1 DESCRIPTION SECTION 07 13 52 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between //----// if not applicable to project. Also delete any other item or paragraph

More information

INSTALLATION GUIDELINES

INSTALLATION GUIDELINES Please Note: Read these instructions thoroughly before installation to ensure proper use of VaporBlock Plus. ASTM E 1465, ASTM E 2121 and, ASTM E 1643 also provide valuable information regarding the installation

More information

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public

More information

GUIDE SPECIFICATION FOR MEL-ROL : ROLLED, SELF-ADHERING WATERPROOFING MEMBRANE

GUIDE SPECIFICATION FOR MEL-ROL : ROLLED, SELF-ADHERING WATERPROOFING MEMBRANE GUIDE SPECIFICATION FOR MEL-ROL : ROLLED, SELF-ADHERING WATERPROOFING MEMBRANE SECTION 07 13 26 SELF-ADHERING SHEET WATERPROOFING Specifier Notes: This guide specification is written according to the Construction

More information

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2 INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS 410. 1 SCOPE... 2 410. 2 DEFINITIONS 2.1 Tunneling and Jacking... 2 2.2 Tunneling... 2 2.3 Jacking... 2 410. 3 MATERIALS 3.1 General...

More information

SECTION DAMPPROOFING AND WATERPROOFING

SECTION DAMPPROOFING AND WATERPROOFING SECTION 07100 DAMPPROOFING AND WATERPROOFING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Sheet Membrane Waterproofing 2. Under-Slab-On-Grade Vapor Retarder B. Related Sections: 1. Section 03300

More information

Excel Medical Waste - Equipment Installation Section SECTION JOINT SEALANTS

Excel Medical Waste - Equipment Installation Section SECTION JOINT SEALANTS SECTION 07 92 00 JOINT SEALANTS PART 1 - GENERAL 1.1 DESCRIPTION: Section covers all sealant and caulking materials and their application, wherever required for complete installation of building materials

More information

SECTION SELF-ADHERING SHEET FLASHING

SECTION SELF-ADHERING SHEET FLASHING MANUFACTURER S GUIDE SPECIFICATIONS SECTION 076526 SELF-ADHERING SHEET FLASHING 900 Hensley Lane Wylie TX 75098 800-527-7092 www.carlisleccw.com 604129 03.24.15 Carlisle, Flexphalt, Sure-Seal and CAV-GRIP

More information

Waterproofing and Types of Drains

Waterproofing and Types of Drains Waterproofing and Types of Drains 4 PVC Downspout Burial w/ Y Fitting for Future Clean-out Yard Drain Box 12 Drain Box 12885 Old Frederick Road Sykesville, MD 21784 Office 410-442-2445 Fax 410-489-4312

More information

INSTALLATION GUIDELINES - With VaporSeal Tape

INSTALLATION GUIDELINES - With VaporSeal Tape INSTALLATION GUIDELINES - With Tape Please Note: Read these instructions thoroughly before installation to ensure proper use of VaporBlock Plus. ASTM E 1465, ASTM E 2121 and, ASTM E 1643 also provide valuable

More information

Pacific Polymers Elasto-Deck 5000MR Guide Specification

Pacific Polymers Elasto-Deck 5000MR Guide Specification 1 071813-1 July 2018 Pacific Polymers Elasto-Deck 5000MR Guide Specification SECTION 071813 TRAFFIC COATINGS ELASTO-DECK 5000MR OVER CONCRETE 2 071813-2 July 2018 Pacific Polymers Elasto-Deck 5000MR Guide

More information

City of Grand Island Tuesday, March 25, 2014 Council Session (Corrected)

City of Grand Island Tuesday, March 25, 2014 Council Session (Corrected) City of Grand Island Tuesday, March 25, 2014 Council Session (Corrected) Item F-4 #9481 - Consideration of Amending Chapter 8-14 of the Grand Island City Code Relative to Buildings Staff Contact: Craig

More information

PART 1 GENERAL 1.1 SECTION INCLUDES. A. Below grade waterproofing and dampproofing 1.2 RELATED SECTIONS 1.3 REFERENCES

PART 1 GENERAL 1.1 SECTION INCLUDES. A. Below grade waterproofing and dampproofing 1.2 RELATED SECTIONS 1.3 REFERENCES HYDROSTAR AG Series HDPE Dampproofing and Drainage Membrane 07 00 00 Thermal and Moisture Protection 07 10 00 Dampproofing 07 13 00 Sheet Waterproofing 07 13 54 Thermoplastic Sheet Waterproofing NOTE TO

More information

SECONDARY CONTAINMENT COATING SPECIFICATION

SECONDARY CONTAINMENT COATING SPECIFICATION SECONDARY CONTAINMENT COATING SPECIFICATION 1.0 GENERAL PROVISIONS Applicable to the following areas: Typical concrete secondary containment structure with occasional exposure acidic and alkaline compounds

More information

SECTION SELF-ADHERING SHEET WATERPROOFING

SECTION SELF-ADHERING SHEET WATERPROOFING SECTION 07 13 26 SELF-ADHERING SHEET WATERPROOFING This guide specification has been prepared by Polyguard Products Inc., in printed and electronic media, as an aid to specifiers in preparing written construction

More information

SELF-ADHERING SHEET WATERPROOFING

SELF-ADHERING SHEET WATERPROOFING PART 1 - GENERAL 1.1 SUMMARY SECTION 07 13 26 SELF-ADHERING SHEET WATERPROOFING A. Furnish and install modified bituminous sheet waterproofing system where shown on the drawings, as specified herein, and

More information

SECTION PRECAST CONCRETE BIOSOLIDS STORAGE TANK

SECTION PRECAST CONCRETE BIOSOLIDS STORAGE TANK PART 1 GENERAL 1.1 Summary SECTION 13200 PRECAST CONCRETE BIOSOLIDS STORAGE TANK A. Biosolids Storage Tank 1.2 System Description A. Precast concrete storage tank with precast concrete roof, beams, columns,

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Triton WP Waterproof Membrane

Triton WP Waterproof Membrane 1 Triton WP Waterproof Membrane Industry Leading Waterproof Membrane System. Manufactured to provide a consistent layer of protection throughout your wet area Vapor barrier and waterproof load bearing

More information

RECOMMENDED DESIGN SPECIFICATION

RECOMMENDED DESIGN SPECIFICATION RECOMMENDED DESIGN SPECIFICATION SILICONE COATED SPF ROOFING 1 General 1.1 Section Includes A. Silicone coated SPF roofing system, including substrate board, roof insulation boards, foam insulation materials,

More information

CONCRETE TILE PAVERS

CONCRETE TILE PAVERS Section 32 14 13 CONCRETE TILE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for the U.S. is for the installation of concrete tile paving units whose thickness are less than the

More information

Redundancy in Subgrade Waterproofing

Redundancy in Subgrade Waterproofing December 2017 Redundancy in Subgrade Waterproofing BY JESSE TORRES, RRC, RRO AND DOUGLAS STIEVE, AIA, RRC, WISS, JANNEY, ELSTNER ASSOCIATES INC. Each subgrade waterproofing membrane system and application

More information

JOB SPECIFIC BELLEVUE AVENUE NEWPORT, RHODE ISLAND PORTLAND CEMENT CONCRETE PAVEMENT

JOB SPECIFIC BELLEVUE AVENUE NEWPORT, RHODE ISLAND PORTLAND CEMENT CONCRETE PAVEMENT PORTLAND CEMENT CONCRETE PAVEMENT This Specification consists of furnishing and placing full-panel replacement of Portland Cement Concrete Pavement on Bellevue Avenue. Portland Cement Concrete Pavement

More information

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.

E. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage. DELTA -MS CLEAR Section 07 10 00 Dampproofing and Waterproofing PART 1 GENERAL 1.1 SECTION INCLUDES A. Below grade waterproofing and dampproofing. 1.2 RELATED SECTIONS A. Section 07 11 13 - Bituminous

More information

THIS IS A COURTESY COPY OF THIS RULE. ALL OF THE DEPARTMENT S RULES ARE COMPILED IN TITLE 7 OF THE NEW JERSEY ADMINISTRATIVE CODE.

THIS IS A COURTESY COPY OF THIS RULE. ALL OF THE DEPARTMENT S RULES ARE COMPILED IN TITLE 7 OF THE NEW JERSEY ADMINISTRATIVE CODE. (f) The minimum requirements for construction, materials and foundations of grease traps shall be the same as those required for septic tanks, as prescribed in N.J.A.C. 7:9A-8.2. (g) The inlet and outlet

More information

SECTION COLD APPLIED RUBBER MODIFIED ASPHALT WATERPROOFING

SECTION COLD APPLIED RUBBER MODIFIED ASPHALT WATERPROOFING P.O. Box 599 - Mars, PA 16046 800-321-3337 SECTION 07555 COLD APPLIED RUBBER MODIFIED ASPHALT WATERPROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including

More information

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa).

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa). SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION HYDRAULIC CEMENT UNDERLAYMENT

SECTION HYDRAULIC CEMENT UNDERLAYMENT ARDEX GUIDE SPECIFICATION ARDEX K 520 Self-Leveling Concrete Topping Self-Leveling Topping for Indoor Fast-Track Resurfacing SECTION 03 54 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings, general

More information

SECTION SELF-ADHERING SHEET WATERPROOFING (650 MEMBRANE SYSTEM)

SECTION SELF-ADHERING SHEET WATERPROOFING (650 MEMBRANE SYSTEM) SECTION 07 13 26 SELF-ADHERING SHEET WATERPROOFING (650 MEMBRANE SYSTEM) This guide specification has been prepared by Polyguard Products Inc., in printed and electronic media, as an aid to specifiers

More information

SECTION SEALANTS AND CAULKING

SECTION SEALANTS AND CAULKING 07951-1 of 5 SECTION 07951 SEALANTS AND CAULKING 07951.01 GENERAL A. Description Sealants and caulking shall include, but not necessarily be limited to, furnishing and installing caulking, sealants, and

More information

AVM System 500. Aussie Membrane 500

AVM System 500. Aussie Membrane 500 Generic Spec TECH DATA SHEET Sections - 071000 / 071400 / 071416 ICC ESR-2503 L.A. RR#: 25550 Heavy Duty Below Grade Bituminous Waterproofing Membrane Sections 071000 / 071400 / 071416 Fluid Applied Waterproofing

More information

AVM System 500. Aussie Membrane 500

AVM System 500. Aussie Membrane 500 Generic Spec TECH DATA SHEET Sections - 071000 / 071400 / 071416 ICC ESR-2503 L.A. RR#: 25550 Heavy Duty Below Grade Bituminous Waterproofing Membrane Sections 071000 / 071400 / 071416 Fluid Applied Waterproofing

More information

Construction Inspection Checklists

Construction Inspection Checklists III. Construction Inspection Checklists 33 Bioretention - Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: Construction Sequence Satisfactory / Unsatisfactory Comments

More information

SECTION mil thickness REINFORCED LIQUID-APPLIED WATERPROOFING

SECTION mil thickness REINFORCED LIQUID-APPLIED WATERPROOFING SECTION 07143 CCW-MIRASEAL @ 120 mil thickness REINFORCED LIQUID-APPLIED WATERPROOFING PART 1 - GENERAL 1.1 SECTION INCLUDES: Installation of waterproofing membrane on surfaces indicated on drawings, consisting

More information

SECTION FILL AND BACKFILL

SECTION FILL AND BACKFILL PART 1 GENERAL 1.1 SECTION INCLUDES A. Filling, backfilling, and compacting for building volume below grade, footings, slabs-on-grade, paving, site structures, and utilities within the building. B. Backfilling

More information

2018 British Columbia Building Code Public Review of Proposed Changes

2018 British Columbia Building Code Public Review of Proposed Changes 2018 British Columbia Building Code Public Review of Proposed Changes PROPOSED CHANGE: Asbestos CHANGE NUMBER: 2018-BCBC-03-Asbestos CODE REFERENCE: 2015 National Building Code Division B Various Articles

More information

DOWSIL FC Parking Structure Sealant

DOWSIL FC Parking Structure Sealant Technical Data Sheet Ultra-low modulus silicone sealant for parking structure joints that experience extreme movement Features & Benefits Good weatherability Resilient Long life reliability Fast cure Unaffected

More information