The safe management and control of Temporary Works

Size: px
Start display at page:

Download "The safe management and control of Temporary Works"

Transcription

1 The safe management and control of Temporary Works

2 What are TW s? The HSE describe Temporary Works (TW s) as; an engineered solution that may include any structure, provision for access, item or technique used during the course of the construction process. It is to enable the permanent works to be constructed or to support or protect the permanent works until they become self-supporting. The temporary works can be incorporated into the permanent works, or left in place, but do not necessarily contribute to the performance of the permanent works.

3 Legal Bits BS 5975:2008 Code of practice for temporary works procedures and the permissible stress design of falsework - gives full guidance and standards on Temporary Works however there are some general and specific statutory requirements under the CDM Regulations 2015 to managing design, temporary works and structures. Copies of BS5975 and the CDM Regulations are available for viewing within CIMS/EHS/Legal Information All personnel that are or may be involved in temporary works are required to familiarise themselves with the Chalcroft TW s Procedure in CIMS/EHS/TW s. This includes: Estimators, Operations Directors, QS s, Contracts Managers, Build Managers, Project Managers, Site Managers, Site Supervisors, Operatives/Working Site Managers and any persons responsible for planning or co-ordinating a project. External viewers of this presentation are welcome to request further information via: toddhallam@chalcroft.co.uk

4 Example TW s Piling, crane or MEWP mats/bases Underpinning of structures Excavations Cofferdams Scaffolding Formwork Falsework Hoists Propping Façade retention Loading bays Hoarding/fencing Signage boards Spoil heaps

5 Example Chalcroft TW s

6 Example Chalcroft TW s

7 Example Chalcroft TW s

8 Example Chalcroft TW s

9 TW s Responsibilities Designers Under the CDM Regulations 2015 designers are responsible for considering Temporary Works and designing out risk where possible. Where this is not possible risks should be reduced and residual risks highlighted for consideration during the tender stage. Residual risks should also be raised to the site team to be appropriately managed where appropriate. Estimator/project co-ordinators/bid managers The Estimator, or person(s) responsible for reviewing, calculating and preparing tender submissions or budgets etc is responsible for identifying temporary works and the appropriate construction methods and resources required and conveying this information to relevant persons.

10 TW s Responsibilities Quantity Surveyors QS s must ensure that any identified Temporary Works that are the responsibility of Chalcroft have suitable costs, provisions and resources allocated to address the works. They must also ensure that any orders placed with the supply chain incorporate the requirements for identifying and addressing temporary works and; advising the project team. Contracts/Project/Build Managers Are responsible for applying Temporary Works management on a project and ensuring individuals are appointed to manage the temporary works on site and; that they are competent to do so. The appointments must be made (for F10 HSE Notifiable projects) via the formal TW s Appointment Letters and for smaller, short duration projects (not F10 HSE notifiable) via RAMS and the Non-Notifiable Construction Phase Plan. The individuals appointed must be competent to manage and control the TW s. This includes having the knowledge, skills and experience for the specific TW s that are to be carried out and controlled.

11 TW s Responsibilities Temporary Works Co-ordinator (TWC) The TWC shall be a Site Manager or Site Supervisor (or in certain occasions the Contracts/Build/Project Managers or other competent person for small works or short duration works see TW Procedure) who is: - Sufficiently experienced to recognise the need for Temporary Works - Experienced and knowledgeable in construction methods to be used - Recognises their own limits to their technical abilities and when to request assistance - Competent in communicating and administrating - Has attended a Temporary Works Co-ordinator course

12 TW s Responsibilities Temporary Works Co-ordinator (TWC) The TWC is responsible to carry out: - Control and co-ordination of all TW activities - Communication of information amongst all parties involved in TW including the Principle Designer (where more than one contractor on site) and for inclusion of information in the CPP or NNCPP - Registering and recording all correspondence and documents relating to TW - Preparation of a meaningful and comprehensive design brief - Monitoring the progress at all stages of the TW - Verifying the design and construction methods

13 TW s Responsibilities Temporary Works Co-ordinator (TWC) The TWC shall ensure that: - The design is checked and any queries are referred back to the designer - Changes and corrections are designed, verified and carried out as required - Inspections are done at critical stages during construction and before loading - The strength of the permanent works is adequate to permit removal of the TW - Formal permits to load/dismantle are issued on the appropriate forms - Any temporary works designs match the design brief and residual risks are entered into the register The TWC has the authority to enforce the requirements of: - The company health and safety policy - The contract for the project - The design brief - The approved design The TWC is to not allow works to proceed or continue where the controls of the TW s cannot be met

14 TW s Responsibilities Temporary Works Supervisor (TWS) The TWS could be an experience operative, foreman, engineer or site supervisor who: - Is safety trained able to spot potential hazards - Experienced and knowledgeable in construction methods to be used - Is technically aware can understand drawings and methods involved The TWS is responsible for: - Safety at all times especially during erection, use and dismantling of TW - Contributing to the design brief method, skills, plant, materials, access etc - Ensuring the standard of workmanship is good paying careful attention to detail - Supervising the erection, loading and removal in the correct sequence - Ensuring the checking procedures are being carried out as required by the design - Ensuring the correct materials and methods are being used to comply with the agreed design

15 TW s Responsibilities Temporary Works Supervisor (TWS) The TWS duties are: - Safety - Understanding the drawings - To ask for more detail from the TWC if not completely sure what is required - To recognise the authority and carry out his/her instructions - To not change any details or methods unless with the written agreement of the TWC - To advise the TWC of unforeseen conditions, impractical details etc if they arise - To ensure that any equipment to be used is inspected and in good working order The TWS has the authority: - To organise all construction activities relating to the TW - To enforce the checking regime required by the TW design and the projects contract - Not proceed or cease works if all the TW s controls cannot or are not being met

16 TW s Responsibilities Temporary Works Designer (TWD) The TWD can be: - An experienced engineer with proven design competence - An external consultant with proven design competence - A supplier or subcontractors design office with proven design competence The TWD is responsible to produce: - A conforming design which satisfies all the requirements of the design brief (Form A) - Detailed documents which are comprehensive and easily understood by those using them - Resolutions to technical queries - Any design changes as requested by the TWC - An appreciation of the effects of the TW on the Permanent Works - Design notes to highlight all the critical stages of construction and necessary checks Temporary Works Design Checker (TWDC) Where a TWDC is required they must be independent of the TWD and appointed based on the category of the design check within the TW Register. The qualifications, duties and authority are similar to that of the TWD and they are to verify the design and confirm that to the TWC.

17 TW s Procedure Enquiry/tender for work is reviewed taking into account potential TW s 2. Contract awarded and Contracts/Project/Build Manager appointed 3. CM/PM/BM appoints Temporary Works Co-ordinator (Site Manager/ Supervisor or competent person see TW Procedure in CIMS Page 3-4) The CM/BM/PM can self-appoint as TWC for small works/short duration projects however a Temporary Works Supervisor (TWS) must be appointed on site. A TWS does not have to have completed a TWC course but must understand the procedure and be competent to manage the specific TW s and controls and; accept the appointment 4. Temporary Works Register is completed by the TWC (or with assistance from CM/BM/PM or EHS Department) 5. TWC completes Design/RAMS Brief (Form A) for each item on the TW Register

18 TW s Procedure TWC issues completed Form A with a blank Design/RAMS Certificate (Form B) to the relevant Temporary Works Designer (for Category 1-3) or; the person/s responsible for producing RAMS (Category 0) 7. Design/RAMS Certificate (Form B) is issued back to the TWC by the allotted time (detailed in TW Register and on Form A Section 9) with the relevant information ie drawings, specs, requirements, detailed hazards/risks or; for a CAT 0 the completed RAMS. 8. The details and documents detailed and supplied are reviewed by the TWC and Section 6 on Form B is then completed when accepted. Any queries are to be sent to the issuer noted on Section 5 of Form B. 9. Completed Forms A and B with a blank Form C (Permit to Proceed), and a copy of the TW Register, can now be issued to site with all associated documents/drawings etc. 10. Form C - Permit to Proceed is issued by the TWC or TWS on site as required with the agreed safe method, design or process followed accordingly.

19 TW s Key Points Only until Forms A to B have been fully completed and all required documents/drawings are received can a Form C Permit to Proceed be issued No deviation from the agreed work or method is allowed and any design/scope changes are to be referred back to the appropriate designer or issuer of RAMS and Forms A-C completed again accordingly Other site working documents such as Scaffold Inspections, Excavation Permits and Inspections shall also be utilised in conjunction with any relevant temporary works Form C Permit to Proceed may be issued on a daily basis or for the duration of that works. It is dependent on the design or scope of works or requirements noted in Form C under Section 3.0 Particular Requirements Review and inspection of the works are to be carried out as specified within Form C as deemed from information provided in Form B Works must not be allowed to proceed or must be immediately ceased where the required controls cannot be met or; there is a change which requires the TW s controls to be reassessed or; the TWC or TWS is not comfortable/competent with the works

20 TW s Classifications When completing the TW s Register a classification must be given to each temporary works identified. This classification is on a basis of risk and assigns it with the level of design or consideration of controls required to safely manage and control the works. The table on the next page is based on BS 5975:2008 and is broken down into the four following categories 0-3: - Cat 0 Generally low risk works where a standard solution can be applied - Cat 1-2 Medium risk works where a design is required - Cat 3 High risk works where a design is required The level of input into design, design checking, construction methods and controls is relevant to the level of risk. TW s classifications table on following page..

21 Category Scope Comment Independence of Checker 0 Restricted to standard solutions only. Must ensure the site conditions do not conflict with the scope or limitations of the chosen standard solution. This applies to the use of standard solutions and not the original design, which will require both structural calculation and checking to category 1, 2, 3 as appropriate. Because this is a site issue, the check of RAMS, for example, may be carried out by another member of the site or design team (if appl). 1 For simple designs. These may include; formwork, falsework (where top restraint is not assumed), needling and propping to brickwork openings in single storey construction. Such designs would be undertaken using simple methods of analysis and be in accordance with the relevant standards, suppliers technical literature or other reference publications. The check may be carried out by another member of the design team. 2 On more complex or involved designs. Designs for excavations, hoarding, for foundations, for structural steelwork connections, for reinforced concrete. Category 2 checks would include designs where a considerable degree of interpretation of loading or soils information is required before the design of the foundation, excavation support or slope. The check should be carried out by an individual not involved in the design and not consulted by the designer. 3 For more complex or innovative designs, which result in complex sequences of moving and/or construction of either temporary works or permanent works. The designs include unusual designs or where significant departures from standards, novel methods of analysis or considerable exercise of engineering judgement are involved. The check should be carried out by another design organisation.

22 TW s Classifications The majority of Chalcroft s temporary works fall around the 0-2 Categories. The following table is a guide only to assist in identifying a classification. Further guidance should be sourced from a design team, subcontractor, supplier or; the EHS Department. Piling platforms Type Category Ground support including proprietary support systems <1.2m 1.2-3m >3m Ground support systems less than 3mtrs deep in poor ground condition Trench box design <4m >4m Formwork for concrete (height) <1.2m 1.2-3m >3m Falsework (height) <3m >3m Tower Crane bases Temporary foundations including mobile crane outrigger pads Sheeted scaffolds including debris netting (irrespective of height) Simple scaffolding TG20 <15m >15m Trenches with timber shoring (or other supports) <1.2m 1.2-3m >3m Designed scaffolding (cantilever or hanging scaffold) Complex structural steelwork Material Loading Bays Sheet pile temporary retaining walls

23 TW s Appointment Letters When completing the TW s Register a classification must be given to each temporary works identified. This classification is on a basis of risk and assigns it with the level of design or consideration of controls required to safely manage and control the works. The table on the next page is based on BS 5975:2008 and is broken down into the four following categories 0-3: - Cat 0 Generally low risk works where a standard solution can be applied - Cat 1-2 Medium risk works where a design is required - Cat 3 High risk works where a design is required The level of input into design, design checking, construction methods and controls is relevant to the level of risk.

24 TW s Documents The following sections are the templates and examples of the documents to be utilised in the TW s process: Appointment Letters TWC and TWS TW Register list of all TW s for the project, their category and document requirements Form A Design or RAMS Brief completed by the TWC Form B Design or RAMS Certificate completed by the RAMS author or provider of documents for the TW s Form C Permit to Proceed issued by the TWC or TWS on site for the specific TW s to commence with the relevant controls and adherence to RAMS and associated documents

25

26

27

28

29

30

31 TW s controls What happens without them

32 TW s controls What happens without them

33 TW s controls What happens without them

34 TW s controls What happens without them

35 TW s controls What happens without them

36 Causes of TW s failures Failure to recognise what constitutes temporary works Not appointing someone competent to manage the temporary works Not following the procedure Failing to ensure RAMS and other associated documents are received and checked Not checking the controls are provided, in place and being followed Inadequate design brief or failure to carry out proper investigation of ground conditions, underground services or structural condition of existing buildings/structures Unauthorised changes to an approved TW design and/or RAMS Lack of competency of personnel/contractors carrying out the works Incorrect estimation of loads to be supported (overloading) Inadequate horizontal (vertical) support or; diagonal (side) bracing to resist lateral loads ie wind, spoil heaps, plant movement.

37 Consequences of TW s failures Major failures may result in serious harm or fatalities to workers and/or members of the public Minor failures may result in harm or injuries occurring and delays to the works and increased costs Failure to instigate and properly manage temporary works on site can lead to an HSE notice or prosecution. A failure does not need to have occurred A failure in the temporary works may result in an HSE notice or prosecution. Harm or injury does not need to have occurred An HSE prosecution could result in: - a significant fine - prison sentence - damage to company reputation

38 Further information and guidance This presentation provides clear information on the requirements and expectations for the safe management and control of temporary works on construction projects of any size, value or duration. For further information or guidance or to gain access to the company temporary works documents go to: CIMS/EHS/Temporary Works CIMS/EHS/Legal Info and Guidance HSE Temporary Works Designing Buildings Wiki - Temporary Works Temporary Works Forum For further assistance and advice contact a member of the Chalcroft EHS Department or; toddhallam@chalcroft.co.uk

Health and and Safety Executive. Temporary Works. Phil Chester HM Inspector of Health and Safety

Health and and Safety Executive. Temporary Works. Phil Chester HM Inspector of Health and Safety Health and and Safety Executive Temporary Works Phil Chester HM Inspector of Health and Safety Legal obligations CDM Regulations 2015 Reg 4(4) client s duty to provide pre-construction information, e.g.

More information

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE The purpose of the health and safety questionnaire is to provide Clients with assurances that all companies on

More information

The Construction (Design and Management) Regulations 2015 sets out the duties of Designers and Contractors.

The Construction (Design and Management) Regulations 2015 sets out the duties of Designers and Contractors. TEMPORARY WORKS AND DESIGN PROCEDURE. Legislation The Working at Height Regulations 2005, require Strength and Stability calculations for any arrangement of scaffolding that is not covered by a recognised

More information

Annex I: Summary of duty holders

Annex I: Summary of duty holders The Construction (Design and Management) Regulations 2007: Industry Guidance Annex I: Summary of duty holders Summary of key changes in CDM 2007 Regulations are re-ordered to group duties together by duty

More information

Site Safety Plus Temporary Works Supervisor Training Course (TWSTC) Course appendix M

Site Safety Plus Temporary Works Supervisor Training Course (TWSTC) Course appendix M Site Safety Plus Temporary Works Supervisor Training Course (TWSTC) Course appendix M 1. Introduction 2. Aims and objectives 3. Entry requirements 4. Assessment 5. Delegate numbers 6. Course duration and

More information

Building Standards Customer Journey

Building Standards Customer Journey Building Standards Customer Journey Are you doing building work or home improvements? If so, this guide is for you. Building Standards Customer Journey Contents 2 Contents Building Standards Customer Journey

More information

Annex I: Summary of duty holders

Annex I: Summary of duty holders The Construction (Design and Management) Regulations 2007: Industry Guidance Annex I: Summary of duty holders Summary of key changes in CDM 2007 Regulations are re-ordered to group duties together by duty

More information

Control of Equipment on Masts, Towers and Rooftops BOP018.8

Control of Equipment on Masts, Towers and Rooftops BOP018.8 Control of Equipment on Masts, Towers and Rooftops BOP018.8 1.0 Introduction This document defines the rules to be followed for all works on Arqiva owned or managed sites/structures that have a structural

More information

SAFETY, HEALTH & WELFARE AT WORK (CONSTRUCTION) REGULATIONS Briefing Note 1 for Clients, Designers and Project Supervisor Design Process

SAFETY, HEALTH & WELFARE AT WORK (CONSTRUCTION) REGULATIONS Briefing Note 1 for Clients, Designers and Project Supervisor Design Process SAFETY, HEALTH & WELFARE AT WORK (CONSTRUCTION) REGULATIONS 2006 1. Introduction Briefing Note 1 for Clients, Designers and Project Supervisor Design Process ISSUED NOVEMBER 2006 BY ACEI, EI, RIAI and

More information

Contractor and Supplier Expectations

Contractor and Supplier Expectations Contractor and Supplier Expectations GUI/1548 Issue 15 Page 1 of 10 16 September 2016 Contents 1. INTRODUCTION AND SCOPE 3 2. RICARDO ENERGY & ENVIRONMENT POLICIES 3 3. SUSTAINABILITY 4 4. MANAGEMENT OF

More information

HUGHS LIMITADA- SHEQ HSE RESPONSIBILITIES

HUGHS LIMITADA- SHEQ HSE RESPONSIBILITIES HSE RESPONSIBILITIES All levels of Management take an active interest in the development and implementation of the Health & Safety and Environmental Management System. Demonstrating Leadership in HSE Participation

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI - CoP 40.0 False Work (Formwork) Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude Abu Dhabi

More information

Safe planning and operation for Mobile Elevated Working Platforms (MEWPs)

Safe planning and operation for Mobile Elevated Working Platforms (MEWPs) Safe planning and operation for Mobile Elevated Working Platforms (MEWPs) This document sets out the Morgan Sindall standards for the control of Mobile Elevated Work Platforms (MEWP) on its projects. It

More information

MGF Excavation Support Systems. Broad Street Rugby Football Club

MGF Excavation Support Systems. Broad Street Rugby Football Club MGF Excavation Support Systems Broad Street Rugby Football Club PLANNING & CONTROLLING EXCAVATION WORKS Peter Dunnion - Regional Manager (Midlands & East Anglia) Agenda MGF s commitment to improving excavation

More information

Construction Regulations 2014 vs Construction Regulations 2003

Construction Regulations 2014 vs Construction Regulations 2003 Construction Regulations 2014 vs Construction Regulations 2003 By Mark Winter Safe Working Practice Tel: 071 6032213 / 021 7121643 mwinter@safepractice.co.za Why the new Construction Regulations? What

More information

Practice Notes For Construction Managers PNCM 7: Timber Formwork First Issue, January 2006

Practice Notes For Construction Managers PNCM 7: Timber Formwork First Issue, January 2006 Practice Notes For Construction Managers PNCM 7: Timber Formwork First Issue, January 2006 (Index under: Temporary Works) Contents Page 1. Scope of this Practice Note...1 2. Statutory Ordinance, Regulations

More information

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy.

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy. Bowmer Kirkland & Kirkland & Accommodation Health & Safety Policy December 2013 www.bandk.co.uk Index Policy Statement Page 3 Interaction of Health and Safety Responsibilities Page 5 Organisation Page

More information

SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland

SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland SUP 02 Avoiding danger from underground services during ground works Unified procedures for use within NHSScotland April 2015 Contents Page Acknowledgements... 4 1. Preface... 5 1.1 Introduction... 5 1.3

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY SECTION 1. GENERAL POLICY STATEMENT: Director Responsible for Safety: A.C. Appleton The Director responsible for safety will ensure the adoption and maintenance of proper standards of safety, health and

More information

HEALTH AND SAFETY CONTRACT BETWEEN EMPLOYER AND MANDATORY (CONTRACTOR) SECTION 37(2) OF THE OHS ACT, ACT 85 OF 1993

HEALTH AND SAFETY CONTRACT BETWEEN EMPLOYER AND MANDATORY (CONTRACTOR) SECTION 37(2) OF THE OHS ACT, ACT 85 OF 1993 P a g e 1 SUBJECT ISSUED BY APPROVED BY CONTRACT CONTRACT BETWEEN EMPLOYER AND MANDATORY SAFETY MANAGER: SUN CITY RESORT DIRECTOR OF OPERATIONS PAGE 1 OF 15 EFFECTIVE: REVISION NO: 1 HEALTH AND SAFETY

More information

A-one+ Supply Chain Standards

A-one+ Supply Chain Standards A-one+ Supply Chain Standards A-one+ Page 1 of 12 Introduction We at A-one+ are committed to achieving an incident and accident free environment through our health and safety strategy. We demand Supply

More information

Annex G to Loughborough University Facilities Management Health and Safety Procedure

Annex G to Loughborough University Facilities Management Health and Safety Procedure Annex G to Loughborough University Facilities Management Health and Safety Procedure Working with Contractors Including the Construction (Design and Management Regulations) 2015 General 1. The Construction

More information

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD FORMWORK & FALSEWORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Temporary Works Forum (TWf) Chairman: Bill Hewlett MA CEng FICE Secretary: John Carpenter CEng, FICE, FIStructE, CFIOSH

Temporary Works Forum (TWf) Chairman: Bill Hewlett MA CEng FICE Secretary: John Carpenter CEng, FICE, FIStructE, CFIOSH TW/11/027 Rev F (issued: February 12). Rev G (minor changes March 12) COMPETENCIES OF THE TWC 1 1 Background It is important that those individuals appointed to the roles of Temporary Works Coordinators

More information

CDM FAQ Sheet

CDM FAQ Sheet CDM 2015 - FAQ Sheet 1. The change to the regulations means Domestic works are now included. What if you are doing DIY in your own house? Do the regulations apply to this? If the home owner is doing the

More information

ESSENTIAL STANDARD no.1. Excavations

ESSENTIAL STANDARD no.1. Excavations ESSENTIAL STANDARD no.1 Excavations KEY MESSAGES Ensure that public safety and the safety of those doing the work is the number one priority. Plan to use the best/correct method. For example, where space

More information

CDM 2015 In Practice. Craig Foyle CFIOSH IMaPS / Raymond Bone CMIOSH CFaPS. Version 1.0

CDM 2015 In Practice. Craig Foyle CFIOSH IMaPS / Raymond Bone CMIOSH CFaPS. Version 1.0 CDM 2015 In Practice Craig Foyle CFIOSH IMaPS / Raymond Bone CMIOSH CFaPS Version 1.0 Speakers Craig Foyle Involved in engineering construction / construction projects for over twenty years working in

More information

Determination 2007/67. Retaining wall at 71 Beach Road, Waihi Beach, Western Bay of Plenty. 1 The matter to be determined

Determination 2007/67. Retaining wall at 71 Beach Road, Waihi Beach, Western Bay of Plenty. 1 The matter to be determined Determination 2007/67 Retaining wall at 71 Beach Road, Waihi Beach, Western Bay of Plenty 1 The matter to be determined 1.1 This is a determination under Part 3 Subpart 1 of the Building Act 2004 ( the

More information

LEGIONELLA CONTROL ASSOCIATION STATEMENT OF COMPLIANCE

LEGIONELLA CONTROL ASSOCIATION STATEMENT OF COMPLIANCE INTRODUCTION The Company was founded in 1973, as a designer, manufacturer and installer of glass reinforced plastic water cooling towers. Services offered include the design and manufacture of cooling

More information

WILTSHIRE POLICE FORCE PROCEDURE

WILTSHIRE POLICE FORCE PROCEDURE Form 535 Template v3 WILTSHIRE POLICE FORCE PROCEDURE MANAGEMENT OF CONTRACTORS PROCEDURE Date of Publication: September 2017 Version: 6.0 Next Review Date: September 2018 TABLE OF CONTENTS PROCEDURE OVERVIEW...

More information

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification

More information

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3

GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) 3 Page 1 Page 2 GUIDANCE NOTES - CONSTRUCTION DESIGN AND MANAGEMENT (CDM) ROLES AND RESPONSIBILITIES The CLIENT must: 1. Be satisfied that all

More information

University of Portsmouth Safe System of Work Policy

University of Portsmouth Safe System of Work Policy University of Portsmouth Safe System of Work Policy Document title University of Portsmouth Safe System of Work Policy Document author and department Jonathan Latter Health & Safety Compliance Manager

More information

BRITISH CONSTRUCTIONAL STEELWORK ASSOCIATION LIMITED

BRITISH CONSTRUCTIONAL STEELWORK ASSOCIATION LIMITED SAFE SITE HANDOVER CERTIFICATE AND CHECKLIST 2008 Introduction Safety during steelwork erection is a key focus of BCSA and its member companies; issues such as safety when working at height, personal protective

More information

OHS Management of Contractors in Capital Works and Maintenance

OHS Management of Contractors in Capital Works and Maintenance OHS Management of Contractors in Capital Works and Maintenance Physical Resources/Risk, Health and Safety Prepared by: Physical Resources/Risk, Health and Safety Version: 08/04/2008 Contents Page 1. INTRODUCTION...

More information

Occupational Health and Safety Management Manual v2.2

Occupational Health and Safety Management Manual v2.2 Occupational Health and Safety Management Manual v2.2 Written: February 2013 Author: David Seymour, Director of Operations Co Author: Mathew Sprake, Operations Manager Approved: Board of Directors 1. Introduction

More information

Control and Management of Temporary Works

Control and Management of Temporary Works Control and Management of Temporary Works A guide to good practice PLAN AND ALLOCATE RISK DESIGN AND VERIFY PROCURE AND CONSTRUCT VERIFY AS-BUILTS / SAFE REMOVAL MANAGE CHANGE Publication Published by

More information

CONTENTS. Quality Policy Statement. Managing Invitations to Tender. Rev 9

CONTENTS. Quality Policy Statement. Managing Invitations to Tender. Rev 9 QUALITY PLAN CONTENTS Section 1 Section 2 Section 3 Section 4 Section 5 Quality Policy Statement Quality System Managing Invitations to Tender Design and Drawings Contract Management Section 1 Quality

More information

Special Provision No. 199S53 January 2018

Special Provision No. 199S53 January 2018 PERFORMANCE REQUIREMENT - QUALITY PROCESSES Special Provision No. 199S53 January 2018 1.0 SCOPE This Special Provision describes the performance requirements for quality processes, assessment of conformance

More information

Apply for Working at Heights Permit

Apply for Working at Heights Permit Apply for Working at Heights Permit Details of revisions Level Details Date Initial 1 Creation of initial document for use 05/09/2017 MW 2 Amendment to implement time frames 23/03/2018 MW Title: Apply

More information

Special Provision No. 199S53 February 2012

Special Provision No. 199S53 February 2012 PERFORMANCE REQUIREMENT QUALITY PROCESSES Special Provision No. 199S53 February 2012 1.0 SCOPE This Special Provision describes the performance requirements for quality processes, assessment of conformance

More information

Position Description: Site Manager Reports to: Project Manager

Position Description: Site Manager Reports to: Project Manager Position Description: Site Manager Reports to: Project Manager Overall Responsibilities To live the organisational values of Creating Opportunities, Building Communities and Empowering Lives. Responsible

More information

Construction (Design & Management) Regulations 2015 Briefing Note

Construction (Design & Management) Regulations 2015 Briefing Note construction Construction (Design & Management) Regulations 2015 Briefing Note Introduction The Construction (Design & Management) Regulations 2015 ("CDM 2015") are in force on 6 April 2015 (Regulation

More information

Position Description: Site Supervisor Reports to: Site Manager/Project Manager

Position Description: Site Supervisor Reports to: Site Manager/Project Manager Position Description: Site Supervisor Reports to: Site Manager/Project Manager Overall Responsibilities Direct onsite supervision of staff and subcontractors. Application of knowledge, skills, tools, and

More information

Training Standard Draft Only

Training Standard Draft Only Title Duration Purpose/ Scope Occupational Relevance Health and Safety in Construction (Site Manager) Minimum 5 days of 6 learning hours per day Purpose: The purpose of training delivered against this

More information

NZQA registered unit standard 9184 version 6 Page 1 of 5

NZQA registered unit standard 9184 version 6 Page 1 of 5 Page 1 of 5 Title Erect and dismantle non-notifiable prefabricated frame scaffolding up to five metres in height Level 3 Credits 5 Purpose People credited with this unit standard are able to: demonstrate

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

Auckland Transport HS07-01 Competency and Training

Auckland Transport HS07-01 Competency and Training Auckland Transport HS07-01 Competency and Training (Procedure uncontrolled when printing) Relating to Standard: HS07 Competency and Training December 2016 Health and Safety-Procedure-HS07-01-Competency

More information

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification

Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification Level 2 NVQ Diploma in Accessing Operations And Rigging (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

HIGH RISK ACTIVITIES. GD02 Scaffold planning and work at height activities checklist. Design stage. Tender stage. Element Yes No N/A Comments

HIGH RISK ACTIVITIES. GD02 Scaffold planning and work at height activities checklist. Design stage. Tender stage. Element Yes No N/A Comments GD02 Scaffold planning and work at height activities checklist Company name Location Project title Contract no. Design stage Considerations at design stage (pre-construction information/temporary works

More information

CHAS Assessment Standards

CHAS Assessment Standards CHAS Assessment Standards Section 1 - All Prosecutions or Enforcement Notices The Supplier has provided details of any enforcement notices or prosecutions served on them in the last three years by the

More information

Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015)

Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015) Alcester Academy To be the best that we can be Managing Contractors Policy (ratified by Full Governing Body 7 th July 2015) ALCESTER ACADEMY MANAGING CONTRACTORS POLICY REVIEW PROCEDURES The Managing Contractors

More information

Good Practice Guide for the Management of Shoring in Excavations Part 1 - Management Process. CPA Good Practice Guide

Good Practice Guide for the Management of Shoring in Excavations Part 1 - Management Process. CPA Good Practice Guide Good Practice Guide for the Management of Shoring in Excavations Part 1 - Management Process CPA Good Practice Guide Working in Partnership Reference No. STIG 13/01 First Published: June 2013 First Revision:

More information

Management of Contractors Procedure

Management of Contractors Procedure Management of Contractors Procedure Version Control Sheet Version Date Reviewed By Revision Details 1.0 28/08/2015 Louise Newsham Changes to job titles and roles. Reviewed to include recent legislative

More information

Apply for Access Permit

Apply for Access Permit Apply for Access Permit Details of revisions Level Details Date Initial 01 Creation of initial document for use 15-Aug-16 J.O S 02 Consideration of feedback from stakeholders 22-Aug-16 J.O S 03 Incorporating

More information

TECHNICAL SUPPORT ASSOCIATES HEALTH AND SAFETY POLICY STATEMENT

TECHNICAL SUPPORT ASSOCIATES HEALTH AND SAFETY POLICY STATEMENT TECHNICAL SUPPORT ASSOCIATES HEALTH AND SAFETY POLICY STATEMENT Technical Support Associates 57-59 High Street Bagshot Surrey GU19 5AH Tel: 01276 476237 Email: enquiries@tsaservices.co.uk Website: www.tsaservices.co.uk

More information

M.B. Power Services (Essex) Ltd

M.B. Power Services (Essex) Ltd M.B. Power Services (Essex) Ltd HEALTH & SAFETY POLICY 1 POLICY STATEMENT The company recognises that under the Health & Safety at Work Act 1974 the Company has a legal duty to ensure so far as is reasonably

More information

Good Practice Guide for the Management of Shoring in Excavations Part 1 - Management Process. CPA Good Practice Guide

Good Practice Guide for the Management of Shoring in Excavations Part 1 - Management Process. CPA Good Practice Guide Compl i ment ar ypr i nt edcopy Cour t es yofmgf E x c a v a t i o ns S u p p or t S y s t e ms E x c a v a t i o n a f e t y S o l u t i o n s www. mgf. l t d. uk Good Practice Guide for the Management

More information

Safety, Health and Welfare at Work (Construction) Regulations 2013 Part 1: Guidance for Homeowners

Safety, Health and Welfare at Work (Construction) Regulations 2013 Part 1: Guidance for Homeowners Safety, Health and Welfare at Work (Construction) Regulations 2013 Part 1: Guidance for Homeowners Summary Quick Guide - Amendment of Definition of Client to Include Domestic Homeowners Why are these changes

More information

Special Provision No. 199S66 March For the purpose of this Special Provision, the following definitions apply:

Special Provision No. 199S66 March For the purpose of this Special Provision, the following definitions apply: QUALITY CONFORMANCE REQUIREMENTS Special Provision No. 199S66 March 2018 1.0 SCOPE This Special Provision describes the process for the assessment of conformance to the quality requirements and the administrative

More information

Health and Safety Policy STATEMENT OF INTENT

Health and Safety Policy STATEMENT OF INTENT Health and Safety Policy STATEMENT OF INTENT East Kent Housing is committed to achieving a high standard of health and safety compliance in all service areas through effective, proactive management and

More information

External Supplier Control Obligations

External Supplier Control Obligations External Supplier Control Obligations Health and Safety Barclays recognises that we have clear Health and Safety (H&S) responsibilities towards everyone impacted by our business operations including,

More information

CDM 2007 Are you ready? The Construction (Design and Management) Regulations 2007 An introduction to the new regulations

CDM 2007 Are you ready? The Construction (Design and Management) Regulations 2007 An introduction to the new regulations CDM 2007 Are you ready? The Construction (Design and Management) Regulations 2007 An introduction to the new regulations The Construction (Design and Management) Regulations 2007 Coming into force on the

More information

The Health & Safety Policy

The Health & Safety Policy The Health & Safety Policy April 2014 Issue: 3 Page 1 of 16 Review Date: April 2015 Introduction This document sets out the Health & Safety arrangements for Astra Signs Ltd and represents our commitment

More information

CAPITAL ASSET MANAGEMENT LTD (THE COMPANY )

CAPITAL ASSET MANAGEMENT LTD (THE COMPANY ) CAPITAL ASSET MANAGEMENT LTD (THE COMPANY ) AUDIT AND RISK COMMITTEE CHARTER 1. Purpose 1.1 The Audit and Risk Committee (hereinafter referred to as the Committee )assists the Board of Directors in fulfilling

More information

Health, Safety & Wellbeing Policy

Health, Safety & Wellbeing Policy Clacton County High School Health, Safety & Wellbeing Policy This Document was originally approved: January 2013 This Document was Last Reviewed: September 2017 This Document is due for review: September

More information

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 539 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS

More information

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3

Contents. Before you begin. Introduction: Installing trench support 1. Element 1: Planning and preparing 3 Contents Contents Before you begin v Introduction: Installing trench support 1 Element 1: Planning and preparing 3 Section 1.1 Accessing, interpreting and applying compliance documentation 4 to the work

More information

CDM Regulations Implications of the Changes for Road & Lighting Projects

CDM Regulations Implications of the Changes for Road & Lighting Projects CDM Regulations 2007 Implications of the Changes for Road & Lighting Projects There will be a Question and Answer session at the end of this presentation Changes to the Regulations are highlighted in YELLOW

More information

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 SITE SAFETY RULES - SILVERSTONE CLASSIC 2018 The following is an outline of the Safe Working Requirements for all Companies, staff and any other persons for this event. Please note that the terms Company

More information

N.B.:- Please ensure all requested documents are included with your submission, as failure to do this will delay your submission

N.B.:- Please ensure all requested documents are included with your submission, as failure to do this will delay your submission Pre-qualification Questionnaire for acceptance onto the Eurosafe UK Approved List of Contractors for Health and Safety Contractors with 5 or more employees N.B.:- Please ensure all requested documents

More information

05/10/2017 CDM. A look at Clients duties CDM. The perception

05/10/2017 CDM. A look at Clients duties CDM. The perception A look at Clients duties James Chester NPS Property Consultants Ltd Jane Carrington Lewis Safety & Training Ltd The perception Project Health & Safety 1 The aim Healthy Project & Safe Project A common

More information

Contractor Management of Notifiable Construction Projects, Non Notifiable Construction Projects, Non Construction Projects (BAU)

Contractor Management of Notifiable Construction Projects, Non Notifiable Construction Projects, Non Construction Projects (BAU) Title Contractor Management of Notifiable Construction Projects, Non Notifiable Construction Projects, Non Construction Projects (BAU) Reference Number AR-RMD-HSMS17 DOCUMENT HISTORY Review dates Issue

More information

To Loughborough University Facilities Management (FM) Health and Safety Policy

To Loughborough University Facilities Management (FM) Health and Safety Policy Annex DD To Loughborough University Facilities Management (FM) Health and Safety Policy Work involving excavations Purpose According to the Occupational Safety and Health Administration (OSHA), the fatality

More information

Corporate Policy and Procedure

Corporate Policy and Procedure Corporate Policy and Procedure POLICY CATEGORY AUTHORITY RELATED POLICIES APPROVED BY Safety Management When Outside Contractors are Retained (Contractor Safety Management Program) (the Policy ) Health

More information

Release: 1. CPCCBC4002A Manage occupational health and safety in the building and construction workplace

Release: 1. CPCCBC4002A Manage occupational health and safety in the building and construction workplace Release: 1 CPCCBC4002A Manage occupational health and safety in the building and construction workplace CPCCBC4002A Manage occupational health and safety in the building and construction workplace Modification

More information

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2

Construction, Demolition & Excavation Works Doc Reference: DoMN-WHSMS 3.14 Version Number: 2.2 Purpose This procedure provides guidance to the Diocese of Maitland Newcastle (DoMN), principal contractors and other persons conducting a business or undertaking (PCBU) who commission or carry out construction,

More information

Safe Management of Contractors Policy

Safe Management of Contractors Policy Safe Management of Contractors Policy Stour Federation Stour Federation Safe Management of Contractors, Page 1 1.! INTRODUCTION 1.1! Shipston-on-Stour Primary School and Acorns Primary School accept the

More information

Engagement of Agency Workers Policy and Procedure

Engagement of Agency Workers Policy and Procedure Engagement of Agency Workers Policy and Procedure leedsbeckett.ac.uk V0517 Policy Statement Purpose and Core Principles Our University recognises that there may be times when it is necessary to engage

More information

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1.

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1. PROBUILD SUBCONTRACTOR QUALITY MANAGEMENT GUIDE Section Two Project Specific Quality Management Plans Version No 1. PREFACE This document has been developed to assist subcontractors to meet Probuild s

More information

1. Company Policies. 1.1 Project Control & Methodology Brief Methodology. Construction Program. Trade Budgets. Site Establishment Plan

1. Company Policies. 1.1 Project Control & Methodology Brief Methodology. Construction Program. Trade Budgets. Site Establishment Plan 1. Company Policies 1.1 Project Control & Methodology Upon award of any project a Contract Commencement and Handover Meeting is held internally where the project team is confirmed and a Project Plan is

More information

SPECIFICATION OF JACKED ANCHOR FOR RETAINING STRUCTURES

SPECIFICATION OF JACKED ANCHOR FOR RETAINING STRUCTURES SPECIFICATION OF JACKED ANCHOR FOR RETAINING STRUCTURES 1.0 GENERAL This specification deals with jacked anchors and shall be read in conjunction with the conditions of contract and the Specification for

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy December 2017 1. Purpose Manningham Housing Association has a legal duty to ensure the health and safety of its employees, tenants, leaseholders and other stakeholders in relation

More information

Selection of Proprietary Shoring Equipment

Selection of Proprietary Shoring Equipment CPA Safety Guidance Selection of Proprietary Shoring Equipment Introduction Every contractor involved with groundwork must ensure the safe support of trenches and excavations as part of their risk assessment.

More information

REFURBISHMENT DEMOLITION

REFURBISHMENT DEMOLITION CONTRACTOR WHS HAZARD STANDARD REFURBISHMENT DEMOLITION EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

Construction Safety Audit Scoring System (ConSASS) Audit Checklist

Construction Safety Audit Scoring System (ConSASS) Audit Checklist I 1.1 1 OSH Policy The occupier's management with executive or site responsibility shall define and document its policy for safety including objectives for its commitment to safety. (CP79 - Section 1.2)

More information

CONSTRUCTION MANAGER

CONSTRUCTION MANAGER The South African Council for the Project and Construction Management Professions CONSTRUCTION MANAGER IDENTIFICATION OF WORK AND SCOPE OF SERVICES FOR CONSTRUCTION MANAGERS REGISTERED IN TERMS OF THE

More information

Workplace Safety and Health Guidelines Contractor Management

Workplace Safety and Health Guidelines Contractor Management Published in September 2011 by the Workplace Safety and Health Council in collaboration with the Ministry of Manpower. All rights reserved. This publication may not be reproduced or transmitted in any

More information

Urzgan Rural Access Program

Urzgan Rural Access Program 00083939 Urzgan Rural Access Program Rehabilitation of Gravel Road from Surkhliz to Chinartu, Ch. (18+000-27+000)km in Urzgan Province of Afghanistan Lot 3 United Nations Office for Project Services (

More information

Establish health and safety requirements

Establish health and safety requirements 16. 1for Establish health and safety requirements projects The Health and Safety at Work Act (Section 2 (2) (a)) requires that employers should provide and maintain plant and systems of work that are,

More information

Page 19 : Usage and Safety Guidelines, Erection and Dismantling, Tools, Transportation, Page 20 : Do s and Don ts, General

Page 19 : Usage and Safety Guidelines, Erection and Dismantling, Tools, Transportation, Page 20 : Do s and Don ts, General Contents Page 1 : Introduction, Design, Identification of Components, Pages 2-8 : Identification of Components, Page 9 : Stacking and Handling, Pages 10-12 : Connections, Page 13 : Connections, Typical

More information

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF) EHS Regulatory Instrument Code of Practice EHS RI - CoP 41.0 Steel Erection Version 2.0 February 2012 ACKNOWLEDGEMENTS With gratitude Abu Dhabi EHS Center

More information

Welcome to the July Edition of BSG Training News

Welcome to the July Edition of BSG Training News Welcome to the July Edition of BSG Training News As a delegate at one of our courses in the past, or someone who organises the training for your company, our training newsletter keeps you up to date with

More information

Job Profile Information: Senior Highway Engineer

Job Profile Information: Senior Highway Engineer Job Profile Information: Senior Highway Engineer This supplementary information for Senior Highway Engineer is for guidance and must be used in conjunction with the Job Capsule for family Technical at

More information

Quality Assurance Manual

Quality Assurance Manual Quality Assurance Manual Current Electrical is committed to leading the market in satisfying customer needs by providing versatile and innovative electrical and control solutions We take pride in the ability

More information

Management of Health and Safety Files

Management of Health and Safety Files Estates Procedure Manual Background Health and Safety Files are critical tools for enabling structures to be safely used, maintained and adapted. They contain important safety information about the structure,

More information

Guidelines for Multi-Point Suspended Scaffolds (MPSS)

Guidelines for Multi-Point Suspended Scaffolds (MPSS) Guidelines for Multi-Point Suspended Scaffolds (MPSS) For more copies, please contact Publications Section Ministry of Labour 655 Bay St., 14th Floor Toronto ON M7A 1T7 (416) 326-7731 Toll-free: 1-800-268-8013

More information

Related manuals Health & Safety Part 1 Section 1; H&S Part 1 Section 2; H&S Part 1 Section 3 ; Part 2 Section 1; Corporate Services Part 5 Section 1

Related manuals Health & Safety Part 1 Section 1; H&S Part 1 Section 2; H&S Part 1 Section 3 ; Part 2 Section 1; Corporate Services Part 5 Section 1 H&S01_05_V4 - Page No.1 summary Health and Safety Audit & Review document control Responsible Author Sig for Sig for RB Issue Date Review Date Director CFO/CE ACFO B Hoad July 2013 July 2015 Related documents

More information

SENIOR PROJECT MANAGER

SENIOR PROJECT MANAGER POSITION Reports To; Direct Reports; Key Relationships; SENIOR PROJECT MANAGER Regional Construction Manager Site Managers, other staff allocated to assigned projects Project Directors, Clients, Consultants,

More information

Head of HSE. Group Services, Risk

Head of HSE. Group Services, Risk Policy Title: Document Owner: Owning Department: Classification: Environmental Sustainability Policy Head of HSE Group Services, Risk KCOM Group Internal use only Business Units affected by this Policy:

More information