1 FEARNSIDES AND ASSOCIATES FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES File Note- 001-Delay Methodology-18-July-16 Subject: Delay Analysis Methodology 1. Delay Analysis Methodology The delay analysis methodology to be prepared by T&T seeks to establish the as-built critical path running through the as-built works from actual start to actual finish of the Works. To enable the as-built critical path to be established from the project contemporary updated progressed programmes, a retrospective approach will be undertaken in conjunction with both a dynamic and static analysis of the Contractor s updated progressed programmes. Dynamic v Static, Dynamic analyses involve schedule calculations, through simulation using computers and scheduling software. Static analyses rely on the components and common sense of the schedule while avoiding significant computer calculations Dynamic Analysis In respect of the dynamic analysis, the updated progressed programmes have been used to identify the critical paths identified at each update data date advised from the activities that have started and not finished or are to start no more than 3 days after any updated progressed programme s data date. This method of locating the as-built critical path is suitable to use as a form of window analysis. Window analysis is especially helpful when a critical path programme which was updated on a regular basis was employed on the project. To delay project completion, the critical activities of the project must have been delayed. The window analysis only analyses critical activities occurring during specific periods of time on a project. The periods analysed are the same periods of time as those when the project was updated. For instance, if the project was updated monthly then the window analysis would be monthly." 2 To facilitate the dynamic window analysis based on the updated progressed programmes, TT have undertaken the development of a float map. 1
2 FEARNSIDES AND ASSOCIATES FORENSIC PLANNING DELAY ANALYSIS, EXPERT WITNESS, CLAIMS AND CONTRACT ADMINISTRATION SERVICES 1 Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology, David Barry, January 2009, 2 Kris R. Nielsen and Patricia D. Galloway (1984) 'Proof Development for Construction Litigation'. American Journal of Trial Advocacy 7,
3 Float mapping, put simply, is the process of extracting the float values for each activity from each of the contemporaneous CPM programme updates, then grouping and filtering those activities that were driving the longest path, which also had the least amount of float, to determine the as-built critical path. 3 The use of the float map technique enables all the updated progressed programmes to be viewed on one sheet, and as such the critical path and near critical activities can be viewed from update to update as the Works were progressed over the actual construction period. On T&T s float map all the programming information is made available (Start and Finish Dates, % Complete, Total Float, Driving and Non-Driving activities and all the activity codes). The use of the float map technique enables the contemporary critical activities to be identified from progress update to progress update according to the updated progressed programmes advised by the Contractor. However, this technique used to identify the as-built critical path identifies the as-built critical path based on the float values generated only to the future (right) of the data date. The AACEI RP-FSA states: The as-built critical path cannot be directly computed using CPM logic alone on the past portion (left) of the data date since networked computations that generate float values can be generated only to the future (right) of the data date. Because of this technical reason, the critical set of as- built activities is often called the controlling activities as opposed to critical activities. Even in a modeled collapsible as-built (3.8) float is not a relevant indicator of criticality because the late dates are not used in modeling the as-built schedule. The closest the analyst can come to a direct computational determination is to cumulatively collect from successive schedule updates of the activities that reside on the critical path between the data date and the data date of the subsequent update. The same technique can be used to determine the as built near-critical activities Static Analysis 3 Delay Analysis in Construction Contracts, P. J. Keane & A. F. Caletka, Chapter 6, page AACEI RP-FSA, page 21 3
4 In respect of the as-built critical path derived from the contemporary updated progressed programmes, the updated progressed programmes need to be competent for the as-built critical path stated upon the updated progressed programmes to be a realistic statement of what were the critical as-built Works as the project progressed over time. The AACEI RP-FSA further states: In the absence of competent schedule updates the analyst must err on the side of over-inclusion in selecting the controlling set of as-built activities. The determination must be a composite process based on multiple sources of project data including the subjective opinion of the percipient witnesses. 5 And the AACEI RP-FSA then goes on to state: Contemporaneous perception of criticality by the project participants is just as important as the actual fact of criticality because important project execution decisions are often made based on perceptions. 6 With the above in consideration, it is not to say that the contemporary updates are not competent, however, there are degrees of accuracy to which updated progressed programmes may or may not be accurate. Progress updates can provide a misleading definition of criticality, and often because updating progressed programmes often requires changes of logic and contract methodologies that change the order and sequence of the as-planned for works to the right of data date line. Not changing the logic to reflect the Contractor s future changing intent on the progressed programmes can make any future critical statements relied upon by them as inaccurate. John Barry stated in his address to the SCL titled: Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology : an accurate updating exercise is still very time consuming, largely because inputting progress tends to overwrite some of the schedule s logic, and therefore significant new logic can be required. Moreover, things change and plans need to be adjusted as the project progresses. Most schedules 5 AACEI RP-FSA, page 21 6 AACEI RP-FSA, page 22 3
5 are susceptible to the domino effect, and therefore it is not always simple to incorporate a change in strategy or tactics. It is not unusual to discover that even good faith schedule updates misrepresent the true mathematical contemporaneous status of the project. 7 And he went on to state: Moreover, it is often the case that the project is really run on the basis of two or four weeks look ahead schedules, and upon investigation it is revealed that these bear little relationship to the overall project schedule. While technology has made it efficient to produce and publish schedules, it is wrong to presume that the published schedules are rigorous and accurate. Check the context, check the content. 8 And stated in his final paragraph stated: some of the delay analysis techniques require significant adjustment to the logic within the project schedules, as well as the introduction of new activities to represent delay events. Whenever this is required, supreme caution is needed to ensure an objective and accurate result is returned. While the marriage of computing and construction planning has provided the modern project manager, planner and delay analyst with a most powerful tool from which to launch dynamic delay analyses, great caution is needed for therein lie the dark arts! 9 To determine the as-built critical path statically, an As-planned versus as-built windows analysis method will be used in conjunction with common sense standards that take into account: 1. A detailed understanding of the project scope; 2. the plan (schedule, method statements, resources etc); 3. the actual as-built progress data and the contemporaneous records of the project, including photographs, correspondence, reports, minutes etc Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology, page 12, David Barry, January 2009, 8 Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology, page 13, David Barry, January 2009, 9 Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology, page 13, David Barry, January 2009, 10 Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology, page 9, David Barry, January 2009, 4
6 Then the following sequence/analysis review will be undertaken: 1. Apply common sense in reviewing the as-built progress in the context of the plan and factual matrix; 2. Apply practical planning and project management experience in reviewing the as-built progress in the context of the plan and factual matrix; 3. Apply discrete schedule calculations using planning software where it is necessary to distinguish the relative criticality of competing paths Conclusion To conclude, by applying the static approach combined with comparing and contrasting the dynamic approach (point 3 of the sequence/analysis review using the contemporary updates in the form of a float map) the as-built critical path will be able to be determined according to the accuracy of the contemporary as-built information available. Whilst some subjective conclusions will be inevitable, the delay analysis conclusions drawn will be based upon contemporary facts rather than alternative and less reliable theoretical delay analysis approaches. 11 Beware the Dark Arts! Delay Analysis and the Problems with Reliance on Technology, page 10, David Barry, January 2009, 5
Assessing Extensions of Time Tony Farrow Trett Consulting March 2006
Assessing Extensions of Time Tony Farrow Trett Consulting March 2006 Contracts require the Works to be completed by a set date, subject to the Contractor s entitlement of extensions of time under the Conditions
More informationProject Controls Expo
Project Controls Expo 9 Nov 2, London DELAY AND FORENSIC ANALYSIS Robert McKibbin : Director, Navigant Consulting Copyright @ 2. All rights reserved Introduction Delay in Construction Contracts: On-going
More informationAndrew Avalon, P.E., PSP
Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Andrew Avalon,
More informationLONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA
Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
More informationPrinciples of Schedule Contingency Management
Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation
More information4-Part Series. Schedule Delay Analysis: Forensic Methods and Practical Applications. Register Today! Owes. Who. What?
Who EARN Owes 10.5 CEU Who CREDITS Schedule Delay Analysis: Forensic Methods and Practical Applications What? Starts Wednesday, September 13, 2017 4-Part Series Who Should Attend? Agenda at a Glance Construction
More information1.1.3 In order to achieve effective time management there must be:
1.1 Core p rinciples 1.1.1 The Guide is a practical treatise on the processes to be followed and standards to be achieved in the effective management of time. It is not based upon any contractual regime,
More informationSAMPLE. SCHEDULE LOGS TCM Framework: 10.1 Project Performance Assessment. AACE International Recommended Practice No. 93R-17
E 93R17 SA M PL SCHEDULELOGS AACE International Recommended Practice No. 93R-17 SCHEDULE LOGS TCM Framework: 10.1 Project Performance Assessment Rev. Note: As AACE International Recommended Practices evolve
More informationConsulting Newsletter
Spring 2014 Newsletter In this, our 2014 Spring newsletter, are 2 articles. The first article is Programme Review and Acceptance. Our second article is titled, Acceleration Roger Gibson June 2014 PROGRAMME
More informationPROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA
This section is used for projects under $1,000,000 use other section if more than $1M SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 SCOPE A. Preliminary Contract Schedule, Contract
More informationDelay Analysis in Construction Contracts
Delay Analysis in Construction Contracts Delay Analysis in Construction Contracts P. J. Keane & A. F. Caletka A John Wiley & Sons, Ltd., Publication This edition first published 2008 2008 Blackwell Publishing
More informationDelay Analysis in Construction Contracts
Delay Analysis in Construction Contracts Delay Analysis in Construction Contracts 2 nd Edition P. J. Keane & A. F. Caletka This edition first published 2015 2015 John Wiley & Sons, Ltd 2015 Blackwell
More informationDesign & Development of a Schedule Management Plan. Session #PRJ10
Design & Development of a Schedule Management Plan Session #PRJ10 Chris Carson, PMP, PSP, CCM Alpha Corporation 2010 Permission is granted to PMI for PMI Marketplace use only Chris Carson, PSP, CCM, PMP
More informationRequesting a Time Extension. Presented by: Ted Trauner, P.E., P.P. Brian Furniss, PSP
Requesting a Time Extension from FDOT. WILL IT FLOAT??? Presented by: Ted Trauner, P.E., P.P. Brian Furniss, PSP 1 WHAT DETERMINES IF A CONTRACTOR IS ENTITLED TO A TIME EXTENSION ON AN FDOT PROJECT? 2
More informationReflections on Planning & Scheduling By Chris Carson, PSP, CCM, PMP
Reflections on Planning & Scheduling By Chris Carson, PSP, CCM, PMP Corporate Director of Project Controls, Alpha Construction and Engineering Corporation 1 The key to successful projects is effective
More informationJames M. Bolin and Andrew Avalon, P.E., PSP
James M. Bolin and Andrew Avalon, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com
More informationProject Forecast Survey Results Good Scheduling Practices June 2016
Good Scheduling Practices 5 June 6 Good Scheduling Practices 5 June 6 Executive Summary There is a saying failing to plan is planning to fail, but what if the plan itself is a failure? The scheduling of
More informationTimely Time Extensions: The Owner s Duty
Timely Time Extensions: The Owner s Duty John Orr, PSP URS Corporation Construction CPM Conference New Orleans, LA January 27 th to 30 th, 2013 Author Biography: John P. Orr, PSP Degrees / Certifications:
More informationTHE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition
THE CONTRACTS GROUP LTD. THE SOCIETY OF CONSTRUCTION LAW DELAY & DISRUPTION PROTOCOL 2 nd Edition 18 January 2017 SCL Delay & Disruption Protocol 2 nd Edition INTRODUCTION TIME - Methods of Delay Analysis
More information6 PROJECT TIME MANAGEMENT
CHAPTER 6 PROJECT TIME MANAGEMENT LEARNING OBJECTIVES After reading this chapter, you will be able to: Understand the importance of project schedules and good project time management Define activities
More informationFORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment
E 29R03 SA M PL FORENSI CSCHEDULEANAL YSI S AACE International Recommended Practice No. 29R-03 E FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment PL Rev. Note: As AACE International
More informationTime Management PLANNING
Time Management 6.1 Plan Schedule Management: The process of establishing policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule # Schedule
More informationCIOB s Contribution to the Effective Management of Time in Construction Projects
CIOB s Contribution to the Effective Management of Time in Construction Projects Patrick Weaver PMP, PMI-SP, FCIOB. patw@mosaicprojects.com.au 1 Outline Focus: proactively managing time to achieve success!
More informationSECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 GENERAL 1.01 SECTION INCLUDES A. Preliminary schedule. SECTION 01 32 00 SECTION 01 32 00 B. Construction progress schedule, with network analysis diagrams and reports. C. Daily construction reports.
More informationMassport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.
Massport Capital Programs Enterprise Schedule Management Document 11 A Primavera Schedule Toolkit Vertical Projects July 2017 Version 1.5 Contents 1.0 INTRODUCTION 2 1.1 DISCLAIMER 2 2.0 TOOLKIT SCHEDULE
More informationEast Central College
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationWhat Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc.
What Should an Owner Do With the Contractor s Schedules? Seminar for the FEFPA Ted Trauner Trauner Consulting Services, Inc. Schedule? A PLAN Schedule? Schedule? A PLAN With Respect to Time Schedule? A
More informationThe Effects of Comparative 4D Models on Schedule Development and Controls. Abstract
The Effects of Comparative 4D Models on Schedule Development and Controls Kevin Coyne, P.E. Managing Engineer, Exponent, Inc. Abstract In this paper the argument is made that the use of comparative 4D
More informationHow to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional
How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional Session ID: 10686 Prepared by: Raquel Shohet, PSP Vice President Hill International, Inc. How to Develop, Manage
More informationAwarding Extensions of Time Christopher Miers. 23rd October 2013
Awarding Extensions of Time Christopher Miers 23rd October 2013 an extension of time provision confers benefits on both parties; in particular it enables a contractor to recover reasonable extensions
More information// Improving Project Plans using a Schedule Maturity Framework
// Improving Project Plans using a Schedule Maturity Framework An Introduction to the S1 > S5 Schedule Maturity Framework Dr. Dan Patterson, PMP CEO & President, Acumen August 2010 www.projectacumen.com
More informationHydra White Paper. Scheduling technologies: Resource centric versus Task centric
Hydra White Paper Scheduling technologies: Resource centric versus Task centric Introduction Historically all project management products have revolved around a common set of techniques to determine the
More information2017 Construction CPM Conference Ron Winter, PSP, FAACE Schedule Analyzer Software CPM ACTIVITY STATUS
2017 Ron Winter, PSP, FAACE Schedule Analyzer Software CPM ACTIVITY STATUS Ron Winter, PSP, FAACE Bachelor of Science in Engineering Construction Scheduler US Air Force Navigator Construction Scheduler
More informationSECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS
SECTION 01 32 00.3 CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS Note: This section is intended to include general procedural requirements for the preparation, submittal and updating
More informationPlanning & Scheduling
Planning & Scheduling Dr. Nabil I. El Sawalhi Assistant Professor of Construction Management Chapter 3 1 Planning Successful Project Management depends on continues planning. The activities of Designers,
More informationSchedule Margin. Contingency for Schedulers. John Owen, Product Manager Schedule and Risk, Deltek
Schedule Margin Contingency for Schedulers John Owen, Product Manager Schedule and Risk, Deltek Contingency / Management Reserve Let s start with a question Have you ever seen a project without any Contingency
More informationForensic Schedule Analysis and Discretionary Logic
TECHNICAL ARTICLE Forensic Schedule Analysis and Discretionary Logic John C. Livengood Esq., CCP CFCC PSP FAACE Abstract: Forensic Schedule Analysis (FSA) and real time schedule reviews do not handle CPM
More information// How Traditional Risk Reporting Has Let Us Down
// How Traditional Risk Reporting Has Let Us Down Dr. Dan Patterson, PMP CEO & President, Acumen November 2012 www.projectacumen.com Table of Contents Introduction... 3 What is Project Risk Analysis?...
More informationSECTION NETWORK ANALYSIS SCHEDULES (NCA)
PART 1- GENERAL 1.1 DESCRIPTION: SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULES (NCA) SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Coordinate this section with the paragraphs of FAR
More informationCONSTRUCTION SCHEDULES
CONSTRUCTION SCHEDULES Analysis, Evaluation, and Interpretation of Schedules in Litigation and Dispute Resolution FOURTH EDITION Michael T. Callahan H. Murray Hohns JURIS Questions About This Publication
More informationTHE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION
THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Twenty-five years ago, I was taught that project management was built
More informationTHE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION
THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION A BASIS White Paper by Dr. Dan Patterson, PMP Introduction Twenty-five years ago, I was taught that project management was built upon the premise of
More informationNAVSEA STANDARD ITEM. 1.1 Title: Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration; provide and manage
NAVSEA STANDARD ITEM ITEM NO: 009-60 DATE: 17 JAN 2013 CATEGORY: I 1. SCOPE: 1.1 Title: Schedule and Associated Reports for Availabilities Over 9 Weeks in Duration; provide and manage 2. REFERENCES: 2.1
More informationLONG INTERNATIONAL. Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA
Richard J. Long, P.E., Andrew Avalon, P.E., PSP and Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax:
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT APPROVED: PROCEDURE NO.: 015 DATE: 08I'4I09 TITLE: CONSTRUCTION
More informationThe IEC61508 Senior Manager's hymn sheet
The IEC61508 Senior Manager's hymn sheet A few key points for those Managers overseeing applications that use the IEC61508 group of standards by The 61508 Association SAFETY INSTRUMENTED SYSTEMS are too
More informationApplication & Management of CPM Schedules
Application & Management of CPM Schedules Matthew Milliet James Construction Group, LLC 2009 Louisiana Transportation Conference Session 60 Project Scheduling DISCLAIMER The following is intended to outline
More informationNAVSEA STANDARD ITEM. 1.1 Title: Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage
NAVSEA STANDARD ITEM ITEM NO: 009-111 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage 2. REFERENCES:
More informationNAVSEA STANDARD ITEM. 1.1 Title: Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage
NAVSEA STANDARD ITEM ITEM NO: 009-111 DATE: 18 NOV 2016 CATEGORY: I 1. SCOPE: 1.1 Title: Schedule and Associated Reports for Availabilities 9 Weeks or Less in Duration; provide and manage 2. REFERENCES:
More informationSECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS]
SECTION 01 32 00.1 CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS] Note: This section is intended to include general procedural requirements for the preparation, submittal and updating
More informationPMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep
PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT PMP Exam Prep PROJECT SCHEDULE MANAGEMENT Page 223 Schedule Management Process : Contains 6 of the 49 total processes Plan Schedule Management Define
More informationBA /14/2010. PSU Problem Solving Process. The Last Step 5. The Last Step 8. Project Management Questions PLAN IMPLEMENT EVALUATE
1 3 BA 301 Fall 2010 Chapter 6 Achieve BA 301 Research & Analysis of Business Problems 4 The Last Step 5 PLAN IMPLEMENT EVALUATE 6 The Last Step 8 Project Management Questions PLAN IMPLEMENT EVALUATE Project
More informationLATE PLANTING DECISIONS WITH CROP INSURANCE: DECISION GUIDELINES FOR MICHIGAN FARMERS IN SPRING 2011
Staff Paper LATE PLANTING DECISIONS WITH CROP INSURANCE: DECISION GUIDELINES FOR MICHIGAN FARMERS IN SPRING 2011 Roger Betz, David B. Schweikhardt, J. Roy Black, and James Hilker Staff Paper 2011-06 June
More informationNEGOTIATION STRATEGIES
NEGOTIATION STRATEGIES Colin P. Stevenson Stevenson Whelton MacDonald & Swan LLP LSUC Primer on Mediation April 5, 2016 INTRODUCTION 1. This paper deals with negotiation strategies at a commercial mediation.
More informationManaging the Risk of Delayed Completion in the 21 st Century. A Summary Report
Managing the Risk of Delayed Completion in the 21 st Century A Summary Report Acknowledgements The CIOB is grateful to all respondents who gave their time and effort in completing the survey. We would
More informationINFORMATION SYSTEM PROJECT MANAGEMENT
SUBJECT : Information System Project Management INFORMATION SYSTEM PROJECT MANAGEMENT TOPIC: Information systems in business context SESSION 2 Session 2 SUBJECT: Information System Project Management TOPIC:
More informationDate Advances Declines Net Advance AD Line
AUTHOR The subjective works of WD Gann from the early part of the twentieth century are not normally associated with one of the modern pillars of twenty first century Technical Analysis, Market Breadth.
More informationProject Time Management
Project Time Management Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules. Describe how project managers use
More informationModern Systems Analysis and Design Seventh Edition
Modern Systems Analysis and Design Seventh Edition Jeffrey A. Hoffer Joey F. George Joseph S. Valacich Managing the Information Systems Project Learning Objectives ü Explain the process of managing an
More informationScheduling. Adapted from John Musser
Scheduling Adapted from John Musser Today Network Fundamentals Gantt Charts PERT/CPM Techniques WBS Review Types: Process, product, hybrid Formats: Outline or graphical organization chart High-level WBS
More informationINTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING CONTENTS
INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING (Effective for audits of financial statements for periods beginning on or after December 15, 2004) CONTENTS Paragraph Introduction...
More informationProject Time Management
Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing
More informationChapter 7. A closer look at. overhead costs
Chapter 7 A closer look at overhead costs What are overhead costs? s For product costing, these are indirect product costs s For responsibility costing, these are indirect costs of responsibility areas
More informationNEPAL STANDARDS ON AUDITING AUDIT SAMPLING AND OTHER SELECTIVE TESTING PROCEDURES
NSA 09 NEPAL STANDARDS ON AUDITING AUDIT SAMPLING AND OTHER SELECTIVE TESTING PROCEDURES CONTENTS Paragraphs Introduction 1-5 Definitions 6-15 Audit Evidence 16-20 Risk Considerations in Obtaining Evidence
More informationSystems for Strategic Management and Support
University of Pisa MSc in Computer Engineering Systems for Strategic Management and Support LECTURE 12 http://www.iet.unipi.it/m.cimino/ssms/ Mario G.C.A. Cimino Department of Information Engineering COURSE
More informationComputing Descriptive Statistics Argosy University
2014 Argosy University 2 Computing Descriptive Statistics: Ever Wonder What Secrets They Hold? The Mean, Mode, Median, Variability, and Standard Deviation Introduction Before gaining an appreciation for
More informationChapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it
Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it Header1 Project control can be reduced to two basic components: Monitoring and control Construction
More informationCPM in Construction Management transition from 7 th to 8 th Edition. James J. O Brien Fredric L. Plotnick
CPM in Construction Management transition from 7 th to 8 th Edition James J. O Brien Fredric L. Plotnick Introduction to CPM is Still Required Chapter 1. Introduction to CPM Planning and Scheduling 3 1.1
More informationAdministrative Exemption
Federal Guidelines Administrative Exemption To qualify for the administrative employee exemption, all of the following tests must be met: - The employee must be compensated on a salary or fee basis (as
More informationRisk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results
Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12,
More informationOperations Management, 11e (Heizer/Render) Chapter 3 Project Management. Section 1 The Importance of Project Management
Instant download and all chapters Test Bank Operations Management 11th Edition Jay Heizer, Barry Render https://testbankdata.com/download/test-bank-operations-management-11thedition-jay-heizer-barry-render/
More informationINTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF SELECTIVE TESTING PROCEDURES CONTENTS
INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF SELECTIVE TESTING PROCEDURES (Effective for audits of financial statements for periods ending on or after July 1, 1999, but contains
More informationCOST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL
SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,
More informationProject Planning & CPM Scheduling using MS Project. APWA NorCal 2018 Annual Conference
Project Planning & CPM Scheduling using MS Project APWA NorCal 2018 Annual Conference What is Planning? Planning: A determination of the what, how, where and by whom ; the tasks that need to be completed
More informationA FRAMEWORK FOR DEVELOPING AN ARTS EDUCATION POLICY
A FRAMEWORK FOR DEVELOPING AN ARTS EDUCATION POLICY by D. Paul Schafer and the York Region District School Board This statement is designed to provide information on the development of an arts education
More informationMeeting Project Schedule Compliance Standards. PT&C EVM Practice Lead
Meeting Project Schedule Compliance Standards Michael Nosbisch, CCC, PSP PT&C EVM Practice Lead PT&C Overview Our mission is to help clients reduce program risk through application of sustainable business
More informationFor the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.
For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com
More informationDocument No: SB002-P3 Revision No: Last Updated: April
BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and
More informationOffice of Human Resources. Maintenance Planner - CA3115
Office of Human Resources Maintenance Planner - CA3115 General Statement of Duties Performs full performance professional work to prepare, plan, schedule, and estimate facility capital projects including
More informationBest practices in demand and inventory planning
whitepaper Best practices in demand and inventory planning WHITEPAPER Best Practices in Demand and Inventory Planning 2 about In support of its present and future customers, Aptean sponsored this white
More informationSECTION CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationIndex. Note: Page numbers in italics refer to Figures; those in bold to Tables.
Note: Page numbers in italics refer to Figures; those in bold to Tables. absolute / hard logic, 267 acceleration, 354 5 activity centred approach, 37 activity selection at contract stage, 97 levels of
More informationCambridge International AS & A Level Computer Science
Topic Support Guide Cambridge International AS & A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationInformation Technology Project Management, Seventh Edition
Information Technology Project Management, Note: See the text itself for full citations. Understand the importance of project schedules and good project time management Discuss the process of planning
More informationSchedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
More informationBox Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments
Box Clever Consulting Executive Summary Project Report July 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 05/08/17 Strand Plaza - Liverpool Status Report @ End of
More informationThe Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove
Improved Project Control Through Scheduling January 24, 2014 The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit
More informationScheduling Challenges in the Industrial Construction Sector
Scheduling Challenges in the Industrial Construction Sector Carol Bolstad, President, Senior Planner Scheduling & Information Services, Inc. carol.bolstad@1sis.com www.1sis.com Agenda Scheduling Practices
More informationSchedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
More informationEstimating and Scheduling
Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques
More information2.0 SCHEDULE DEVELOPMENT
Filed: 0-0- Exhibit D Tab Page of 0 0 0 PROGRAM SCHEDULE.0 OVERVIEW The ability to validate, integrate, oversee and ultimately to retain control over the program schedule is one of the key factors that
More informationSeven Principles for Performance
Seven Principles for Performance Measurement What is excellent performance measurement really based on? by Stacey Barr introduction There are seven principles which are the criteria that define excellence
More informationProject Time Management
Project Time Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Adapted from Managing Information Technology Projects, Schwalbe Learning Objectives Define activities as the basis
More informationPROJECT DESIGN GUIDE D08 QUALITY CONFORMANCE
PDG PROJECT DESIGN GUIDES D08 PROJECT DESIGN GUIDE D08 QUALITY CONFORMANCE Project Name: Name Project No.: Number Date Document No.: PDG-PDG-PRO-D08.0 Date Created: 22 nd May 2010 Date Revised: Last edited
More informationImplementing Resource Scheduling Techniques
Implementing Resource Scheduling Techniques A Guide for Planners and Scheduler s Presented 26 th November 2009 at Park Regis Hotel, Brisbane for Tonkin Corporation Micro Planning International Asia Pacific
More informationSAMPLE. AACE International Recommended Practice No. 14R-90
E 14R90 SA M PL RESPONSI BI LI TYANDREQUI RED SKI LLSFORAPROJ ECTPLANNI NG ANDSCHEDULI NG PROFESSI ONAL AACE International Recommended Practice No. 14R-90 RESPONSIBILITY AND REQUIRED SKILLS FOR A PROJECT
More informationIAASB Main Agenda (December 2009) Agenda Item. Engagements to Compile Financial Information Issues and IAASB Task Force Proposals I.
Agenda Item 3-A Engagements to Compile Financial Information Issues and IAASB Task Force Proposals I. Objective 1. The objective of this Paper is to consider significant issues to be addressed in the revision
More informationUK ROOFING SECTOR WORKFORCE DEVELOPMENT STRATEGY
UK ROOFING SECTOR WORKFORCE DEVELOPMENT STRATEGY 2017-2021 UK ROOFING SECTOR WORKFORCE DEVELOPMENT STRATEGY A REPORT, BUILT UPON EXTENSIVE RESEARCH, SHOWING HOW SUPPORTING THE ROOFING SECTOR WILL OPEN
More information12/26/2013. Sharif University of Technology. Session#11. Instructor. Class time. Course evaluation. International Campus Kish
International Campus Kish Sharif University of Technology Session#11 Instructor Omid Fatahi Valilai, Ph.D. Industrial Engineering Department, Sharif University of Technology Email: Fvalilai@Sharif.edu,
More information