Budget Estimate Basic Tenant Improvement

Size: px
Start display at page:

Download "Budget Estimate Basic Tenant Improvement"

Transcription

1 Building work rules, conditions and insurance: 1. Review the work rules. If they are not available no budget should be provided. 2. Hours available for construction 3. Insurance requirements 4. Entities to add to insurance policy 5. Keys available for tenant space 6. Utility room access Plans and permits: 1. Is an as-built plan available? Digital or paper? 2. Who will complete preliminary space planning? 3. Are architectural drawings required with an architects stamp? 4. How many plan pages will be required to get a permit? 5. How many plan pages will be required to build the project? 6. Are product submittals required? 7. Which municipality has jurisdiction for issuing the permit? 8. How much is the permit fee and how many inspections are required? Masking and dust control: 1. Are adjacent spaces occupied? Is there a demising wall to the structure? 2. Does the tenant space have exterior access? Direct, ramp, stairs or elevator? 3. Does the tenant space have interior access? Elevator, freight elevator, stairs or hallway? 4. Is negative air flow required during construction? 5. Is an infectious disease control plan required? 6. What existing finishes to remain need to be protected during construction? 7. Is daily vacuuming or mopping of common areas necessary? Demolition: 1. Use the preliminary floor plan to determine demolition work. 2. Walls 3. New openings and access holes 4. Outlets, switches and lighting to be removed 5. Existing return air grills and supply air grills 6. Cabinetry and counters 7. Doors, windows and trim 8. Flooring and base 9. Toilets, sinks, urinals, drinking fountains, drains and piping 1 of 8 6/29/2012

2 Demolition: (continued) 10. Soffits 11. Stairs, elevators and ramps 12. Accessories 13. Appliances 14. Equipment 15. Furniture 16. Other Concrete: 1. What type of floor is in the space? Is it a slab on grade, post tensioned concrete, structural slab, coffered poured in place or lightweight concrete? 2. Is x-ray imaging or ground penetrating radar required? 3. How thick is the concrete? 4. How many square feet of concrete will be removed? 5. How many core drilled holes are required? 6. Is wall cutting required? 7. Is a demolition hammer required? 8. Is heavy equipment required? 9. How many cubic yards of concrete will be required to patch the concrete removed? Is testing required? Framing: 1. Lineal feet of walls to build and wall layout 2. Steel studs: gauge, spacing, size and height 3. Black track 4. Flex track 5. Fire treated door and window bucks 6. Strapping, blocking, bracing, brackets and fasteners 7. Structural walls, Soffits, architectural details, reception walls and partitions 8. Final wall cover inspections Plumbing: 1. Wall hung sinks and faucets 2. Counter top sinks and faucets 3. Toilets and urinals 2 of 8 6/29/2012

3 Plumbing: (continued) 4. Drinking fountains 5. Dishwashers, ice machines and refrigerators 6. Washing machines 7. Mop sinks, floor drains and floor sinks 8. Restaurant sinks 9. Back flow preventer 10. Venting and roof patching 11. Schematic drawing, permit and inspections Electrical: 1. General purpose outlets 2. Quad outlets 3. Computer outlets 4. Printer/copier outlets 5. Equipment outlets 6. Retail storefront outlets 7. Switches, dimmers, timers and clocks 8. Energy conservation and occupancy switching 9. Drop in florescent light fixtures 10. Surface mount light fixtures and pendant lighting 11. Recessed light fixtures and track lighting 12. Mud rings and pull strings for data and phone locations 13. Imaging equipment, X-ray equipment, Hand dryers, Dishwashers, coffee pots, microwaves, refrigerators, freezers and ice machines 14. Emergency exit lighting with battery backup. 15. Automatic entry hardware 16. Plans, Permit and Inspections 17. Other - HVAC equipment, Signs, Compressors, lab equipment and Vacuum pumps HVAC: 1. Plenum return air or ducted return air 2. Relocate diffusers 3. Relocate return air grills 4. Rework existing system or install new system? 3 of 8 6/29/2012

4 HVAC: (continued) 5. Server room system required? 6. Are engineered drawings required? 7. What are the power requirements for new equipment? 8. Design review, plans, permits and inspections Sprinklers: 1. Does the space have a fire sprinkler system? 2. Do sprinkler heads need to be relocated or added to maintain coverage? 3. Do sprinkler heads need to be upgraded to quick response sprinkler heads? 4. How many sprinkler heads need to be added or modified? 5. If additional heads are required is there enough water pressure and volume to accommodate the additional heads? 6. Will the fire alarm system need to be upgraded due to new work? 7. Are engineered drawings required for permits? 8. Plans, permits and inspections. 9. Other Fire Alarm: 1. Will the fire alarm system need to be upgraded for the new wall plan? 2. How many devices will need to be relocated? 3. How many devices will need to be added? 4. Are circuits available for new devices at the main panel? 5. Is there a flow switch installed at the fire sprinkler system? 6. Plans, permits and inspections. Drywall: 1. Do any new walls penetrate the ceiling grid? 2. Do the new walls need to be built to the structure above the grid? 3. How many square feet of new drywall is required? 4. Are any walls fire rated? 5. Do any of the walls need insulation or acoustical drywall? 6. Do any of the new walls need leaded drywall for sound or x-ray? 7. Will patching be required for existing walls? 8. How will drywall be loaded into the space? Window, elevator, stairs or direct? 9. Will a fastener inspection be required? 4 of 8 6/29/2012

5 Painting and wall finishes: 1. Masking 2. Prepare walls and hard lid for paint 3. Prime new drywall and patches 4. Apply 2 coats of main color to drywall and hard lid. 5. Apply 2 coats of semi-gloss at restrooms 6. Apply 2 coats of eggshell to accent walls 7. Color matching and test samples 8. Door and window trim Painting and wall finishes: (continued) 9. Plastic laminate, FRP or tile at restrooms 10. Wall coverings 11. Wall panels 12. Touch up 13. Clean up 14. Other Ceiling tile and grid: 1. How high is ceiling grid above the finished floor? 2. New grid and tile 3. Repair or replace existing tile and grid? 4. Insulation 5. Seismic upgrade or building code upgrade? 6. Wires for other trades 7. Wall bracing 8. Soffits 9. Inspections Doors and trim: 1. Door type 1 Size and material for door and frame 2. Door type 2 Size and material for door and frame 3. Window kits 4. Fire rated doors 5. Offsite finishing and color matching 6. Delivery 5 of 8 6/29/2012

6 Doors and trim: (continued) 7. Expedited production 8. Side windows 9. Fire rated glass in window kits 10. Storefront doors 11. Automatic entry doors 12. Other Door Hardware: 1. Hinge type, size and color 2. Passage lever handles 3. Keyed lever handles 4. Store room function lever handles 5. Privacy lever handles 6. Deadbolts 7. Electric latches 8. Keypad lever handles 9. Door closers 10. Automatic entry system for ADA access 11. Kick plates 12. Hold opens magnetic and manual 13. Master keyed system 14. Other Hardware: 1. Grab bars 2. Towel dispenser 3. Toilet Paper dispenser 4. Facial tissue dispenser 4. Soap dispenser 5. Mirror 6. Recessed garbage can 7. Shelves and hooks 8. Partitions and privacy panels 9. Other 6 of 8 6/29/2012

7 Cabinetry and Counters: 1. Reception counter and transaction top 2. Lunchroom cabinetry and counters 3. Exam room cabinetry and counters 4. Workstations 5. Storage room shelving 6. Display fixtures 7. Vertical partitions 8. Other Flooring: 1. Floor preparation and underlayment 2. Carpet 3. Vinyl and coving 4. Ceramic tile 5. Vinyl composition tile 6. Wood flooring or simulated wood flooring 7. Entry mats 8. Transitions 9. Rubber base 10. Sealing and waxing Miscellaneous: 1. Window treatments and window film 2. Janitorial and clean up 3. Debris removal and solid waste fees 4. Recycling 5. LEED certification 6. Roof patching 7. RF locating for sewer drains 8. Florescent tube disposal 9. Appliances 10. Security system 11. Data, phone, audio and video systems 12. Furniture moving 7 of 8 6/29/2012

8 General conditions: 1. Elevator, freight elevator, loading dock, stairs, hallway or direct access 2. Parking 3. Utilities 4. Site security 5. Project manual 6. Project duration 7. Occupied or vacant space 8. Construction hours of operation 9. Project supervision 10. Other Not included: 1. Acoustical, structural and radiation engineering 2. Tenant signage 3. Tenant equipment and fixtures 4. Equipment rentals 5. Common area hallway ADA upgrades 6. Common area restroom ADA upgrades 7. Hazardous material testing 8. State and local taxes 9. Other Disclaimer This checklist is provided to help you review your budget. It is a starting point but it is not intended to cover every conceivable situation. Using experienced advisors should always be considered before you sign any lease or commit to any outlay for tenant improvements. 8 of 8 6/29/2012

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM)

SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) SPACE TYPE: PHYSICAL FITNESS (EXERCISE ROOM) Construction Criteria The unit costs for the Physical Fitness Center (Exercise Room) space type are based on the construction quality and design features in

More information

Davis Frame Co., Inc. Construction Budget Considerations

Davis Frame Co., Inc. Construction Budget Considerations Davis Frame Co., Inc. Construction Budget Considerations ITEM BID 1 BID 2 BID 3 MISCELLANEOUS COSTS Surveying Building Permit Engineering Fees Interest on Construction Loan Property Taxes Hazard & Liability

More information

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS STANDARD FEATURES LIST Foundation Concrete walls 4 concrete floor slab Interior basement unfinished Standard nine foot foundation walls

More information

MODULAR BUILDING SPECIFICATIONS

MODULAR BUILDING SPECIFICATIONS Use Group A - Assembly B Business E Education I - Institutional Construction Type Type II Non Combustible Type V - Wood Floor 12 Outrigger Frame with Cross members Frame: 12 Perimeter Steel Main Beams

More information

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com

Edouard AVANT GROVE U I C U I C. Modern Living Made Easy uichomes.com Edouard Modern Living Made Easy uichomes.com - new construction - 3 stories + full basement - 4 bedrooms - 2.5 baths - 2,380 s.f. call 314.881.2333 or e-mail sales@uicstl.com PLAN NTS DECK 13' 0" X 12'-0"

More information

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES If your home or business incurred damage, the engineering department, in conjunction with the Flood Mitigation Officer, will

More information

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows:

SECTION (Master Template Final-05) ELECTRICAL BOXES. A. Provide boxes for electrical equipment and wiring devices as follows: SECTION 16130 (Master Template Final-05) ELECTRICAL BOXES PART 1 GENERAL 1.01 SECTION INCLUDES A. Provide boxes for electrical equipment and wiring devices as follows: 1. Wall and ceiling outlet boxes.

More information

Estimate Form for Bathroom Design and Installation

Estimate Form for Bathroom Design and Installation Estimate Form for Bathroom Design and Installation Name: Home Address: City: State: Phone (Home): Phone (Office): Phone (Office): Phone (Office): Phone (Jobsite): Jobsite Address: City: State: By: Hereafter

More information

CHARTRES COURT Washington Avenue Houston, Texas ChartresCourtHouston.com CHARTRES COURT LLC

CHARTRES COURT Washington Avenue Houston, Texas ChartresCourtHouston.com CHARTRES COURT LLC CHARTRES COURT 713-868 - 7226 5023 Washington Avenue Houston, Texas 77007 ChartresCourtHouston.com CHARTRES COURT LLC Features Open floor concept living/dining with spacious island kitchen Great master

More information

Demolition Plan A1 A3. Scale: 3/32" = 1'-0" Arch. Men N.I.C. Elev. Lobby. Stairs N.I.C. N.I.C. Women N.I.C. Issued for Tender.

Demolition Plan A1 A3. Scale: 3/32 = 1'-0 Arch. Men N.I.C. Elev. Lobby. Stairs N.I.C. N.I.C. Women N.I.C. Issued for Tender. inc. 400-7 avenue edmonton, alberta, canada tr y t: (780) 48 47 f: (780) 48 00 e: lesnider@shaw.ca 4 door to North Common Corridor doors to door to F. H. C. Men Women ELEC/TEL UP Stairs DN F. H. C. DN

More information

Bureau of Indian Affairs

Bureau of Indian Affairs Bureau of Indian Affairs Office of Facilities Management and Construction JUSTICE / DETENTION FACILITIES SPACE TEMPLATES Table of Contents BUREAU OF INDIAN AFFAIRS JUSTICE DETENTION FACILITIES SPACE TEMPLATES

More information

DESIGN AND CONSTRUCTION STANDARDS. Section 2: Standards for Specific Categories of Work. Laboratory Standards

DESIGN AND CONSTRUCTION STANDARDS. Section 2: Standards for Specific Categories of Work. Laboratory Standards Laboratory Standards These criteria include general planning guidelines. They are intended for use of Designers during the design phases of the project. Planning Assumptions Overview In order to maximize

More information

3D Home Improvement and Inspection Services, Inc

3D Home Improvement and Inspection Services, Inc Property Inspection Report Cover Page ABC Disney Lane, Winter Garden FL, 34787 Inspection prepared for: John Doe Inspection Date: 7/15/2010 Time: 11:00 am Age: 6 Years Size: 3,378 LSF / 4,427 TSF Weather:

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

Division 09 FINISHES TABLE OF CONTENTS

Division 09 FINISHES TABLE OF CONTENTS Division 09 FINISHES TABLE OF CONTENTS 09 1000 GENERAL... 3 A. RELATED SECTIONS... 3 B. MAINTENANCE OF FINISHES... 3 C. PUBLIC AREAS... 3 D. CUTTING AND PATCHING... 3 E. CLEANING... 3 F. RECOMMENDED FLOORING

More information

Kelly Village Apartments 3118 Green Houston, Texas 77020

Kelly Village Apartments 3118 Green Houston, Texas 77020 Kelly Village Apartments 3118 Green Houston, Texas 77020 Houston Housing Authority J. Allen Management Managing Agent Scope for Kelly Village Unit #1125 Overall Scope: Demolition, Renovation, and Restoration

More information

SECTION TOILET COMPARTMENTS. A. Section Metal Fabrications: Concealed steel support members.

SECTION TOILET COMPARTMENTS. A. Section Metal Fabrications: Concealed steel support members. SECTION 10155 TOILET COMPARTMENTS PART 1 GENERAL 1.1 SECTION INCLUDES A. Plastic laminate partitions. 1.2 RELATED SECTIONS A. Section 05500 - Metal Fabrications: Concealed steel support members. B. Section

More information

Facility Improvements

Facility Improvements CA-SI-01 ACCESSIBLE PARKING STALL ADDITIONS CA-SI-07 BASEBALL & SOFTBALL INFIELD IMPROVEMENTS Additional parking stalls and signage needed for disabled individuals and to meet ADA requirements. Installation

More information

THE CONSTRUCTION SUPERVISOR

THE CONSTRUCTION SUPERVISOR City of Aurora Building Inspections 15151 E Alameda Pkwy Aurora, CO 80012 (303) 739-7420 THE CONSTRUCTION SUPERVISOR When a building permit has been issued for any construction within the City, the Supervisor

More information

1. Unified Facilities Criteria - Design: General Building Requirements (UFC ).

1. Unified Facilities Criteria - Design: General Building Requirements (UFC ). 1. GENERAL GUIDANCE REGARDING DESIGN A. Commissary facilities are Department of Defense (DoD) projects, and as such must be constructed in accordance with the following criteria, codes, and standards.

More information

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good. EAST LYME HIGH SCHOOL Located at 30 Chester Field Road, East Lyme, Connecticut 06333, the High School s original structure was built in 1967. An addition and alterations occurred in 1973. The building

More information

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING

Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING Green Remodeling Illustrations GREEN REMODELING ILLUSTRATIONS GREEN BUILDING GUIDELINES FOR HOME REMODELING WWW.STOPWASTE.ORG New Addition Consider the following green remodeling options in a new addition.

More information

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW

HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW HERMIT S REST GRAND CANYON NATIONAL PARK BUILDING CODE REVIEW 27 September 2007 prepared by: J. CHRIS EVANS ARCHITECT 3220 E. Terra Alta Blvd. No. 9 Tucson, Arizona 85716 520.319.8835 evansarch@hotmail.com

More information

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018)

BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) BASEMENT FINISH PERMIT AND BUILDING CODE REQUIREMENTS (REVISED 3/6/2018) PERMIT SUBMITTAL CHECKLIST: Signed and completed Building Permit application form. A separate Electrical permit is required from

More information

FACILITIES MAINTENANCE WORKER

FACILITIES MAINTENANCE WORKER FACILITIES MAINTENANCE WORKER Summary Statement: Under supervision, is responsible for performing routine building maintenance tasks and assisting Building Maintenance Supervisor with the performance of

More information

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS St. Louis County Department of Public Works Division of Code Enforcement HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS This guide is intended to provide the homeowner or contractor with the

More information

New Homes Starting at $124,900

New Homes Starting at $124,900 Chicora New Homes Starting at $124,900 New Homes - The Best Locations - The Right Price Sales & Marketing By: Keller Williams New Homes Division www.newhomesatmyrtlebeach.com Chicora C & R Builders, with

More information

COLONIAL PLANS. 708 North Street US Highway Route 1 Houlton, Maine (207)532,2444

COLONIAL PLANS. 708 North Street US Highway Route 1 Houlton, Maine (207)532,2444 COLONIAL PLANS 8US Highway Route 1 Hancock, Maine 04640 1(877)767 0664*(207)667 0664 708 North Street US Highway Route 1 Houlton, Maine 04730 (207)532,2444 DEXTER COLONIAL 28 X 34 1904 SQ. FT. DEXTER COLONIAL

More information

University of Toronto Cleaning Specifications

University of Toronto Cleaning Specifications Revised/Updated February 1-2013 University of Toronto Cleaning Specifications AREA TYPE Task To Be Completed Frequency Main Entrance 1 Clean both sides of door glass including side lights. Daily & 2 Clean

More information

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet

Total Building Area: 1964 Construction 30,140 square feet 1976 Construction 36,787 square feet 66,927 square feet FLANDERS ELEMENTARY SCHOOL Located at 167 Boston Post Road, East Lyme, Connecticut the school s original structure was built in 1964 and replaced the Central Office Building as the elementary school. Two

More information

Basement Renovation Guide For Residential Dwellings

Basement Renovation Guide For Residential Dwellings 1 Development Services Department Building Permit & Inspection Services Basement Renovation Guide For Residential Dwellings This document is a guide for home owners and does not cover all possible conditions.

More information

Highland Park. Exceptional Interiors (cont.) Green Technology. Designer Kitchen Features. Distinctive Exterior Features

Highland Park.  Exceptional Interiors (cont.) Green Technology. Designer Kitchen Features. Distinctive Exterior Features unit 2 HOMES 650 Mill Valley Parkway 2332 Sq.Ft. 3-Car 4/3 $542,800 6 Mt. Shasta Views 643 Mill Valley Parkway 2332 Sq.Ft. 3-Car 4/3 $552,800 8 Mt. Shasta Views Under construction 945 Rollingview Raised

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-09 06 00 (May 2009) Change 1-11/13 ----------------------------- Preparing Activity: USACE Superseding UFGS-09 06 90 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

RETAIL TENANT TECHNICAL CRITERIA VERSION 2 MAY 2015

RETAIL TENANT TECHNICAL CRITERIA VERSION 2 MAY 2015 RETAIL TENANT TECHNICAL CRITERIA VERSION 2 MAY 2015 CONTENTS INTRODUCTION 4 PROJECT PLANS 7 BELOW GRADE ZONES WEST STREET 13 TRANSPORTATION HUB 21 WALL STREET 33 2 WTC 43 ABOVE GRADE ZONES 3 WTC 47 4

More information

EVENT 29: November 15, 2017 THE DO-DOs AND DON Ts OF TOILET ROOM DESIGN

EVENT 29: November 15, 2017 THE DO-DOs AND DON Ts OF TOILET ROOM DESIGN EVENT 29: November 15, 2017 THE DO-DOs AND DON Ts OF TOILET ROOM DESIGN THE DO-DOs AND DON Ts OF TOILET ROOM DESIGN - CREDIT(S) EARNED ON COMPLETION OF THIS COURSE WILL BE REPORTED TO AIA CES FOR AIA MEMBERS.

More information

Element Z General Design Requirements Room Standards

Element Z General Design Requirements Room Standards Toilet Room Guidelines PART 1 - GENERAL 1.01 OVERVIEW A. This document provides design and construction criteria for public/patient, and staff toilet rooms at (Owner). PART 2 - DESIGN CRITERIA 2.01 GENERAL

More information

CODE COMPLIANCE PLAN REVIEW PROCEDURES

CODE COMPLIANCE PLAN REVIEW PROCEDURES CODE COMPLIANCE PLAN REVIEW PROCEDURES 1. All construction for state agencies on state-owned or state leased-purchased properties or facilities are to submit design documents for code compliance plan reviews

More information

standard features Power Exhaust Fans w/light - Both Baths GFCI Receptacles Upgrade Light Fixture - Bath 1 Vanity - Per Lav GFCI Receptacles

standard features Power Exhaust Fans w/light - Both Baths GFCI Receptacles Upgrade Light Fixture - Bath 1 Vanity - Per Lav GFCI Receptacles 2017 standard features INTERIOR Cornice w / Full Length Drapes Panels-Main Living Areas only Shaw Moxie Carpet with Pad and Tack Designer Select Congoleum No Wax Vinyl Flooring 8 Flat Ceilings Throughout

More information

Typical Finished Basement Details

Typical Finished Basement Details Albemarle County, Virginia Typical Finished Basement Details Based on the 2012 Virginia Residential Code Finished basements must be constructed in conformance with these details. For requirements, details

More information

PeachStone Capital, Inc. Atlanta s Hard Money Lender When timing is everything, we close! Hard Money Loan Property Worksheet Checklist

PeachStone Capital, Inc. Atlanta s Hard Money Lender When timing is everything, we close! Hard Money Loan Property Worksheet Checklist Hard Money Loan Property Worksheet Checklist Please complete ALL requested information. Incomplete applications will NOT be reviewed! Fully executed purchase and sale agreement including all exhibits,

More information

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities Division 1 Requirements Design and Construction Quality Campus Master Plans Texas Tech University System Operating and Building Maintenance Project Administration Historically Underutilized Business (HUB)

More information

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

SECTION BASIC ELECTRICAL MATERIALS AND METHODS SECTION 26 05 05 BASIC ELECTRICAL MATERIALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the limited scope construction materials and methods for application with electrical installations as follows:

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours

General Conditions 39,522 5, ,292 26,050 75,921 1, Labor hours Basic Edition Standard Estimate Report Page 1 Name 1000 General Conditions 1107 Professional Consultant 10 Surveying 1.00 day 600.000 /day 600 - - - - - - 600 Professional Consultant 600 600 8.00 hours

More information

LASALLE - BACKUS EDUCATION CAMPUS

LASALLE - BACKUS EDUCATION CAMPUS INITIAL YEAR BUILT 1957 BUILDING AREA 63,000 SF CURRENT PROGRAM CAPACITY 406 ENROLLMENT 2008 349 WARD 4 PROPOSED PROGRAM CAPACITY 425 Site Plan LASALLE - BACKUS - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION

More information

A. Submit the following in addition to the standard requirements.

A. Submit the following in addition to the standard requirements. SECTION [13120] OMNIFLEX 300 MODULAR WALL SYSTEM SECTION 1 GENERAL 1.01 SECTION INCLUDES A. This Section specifies all requirements necessary to furnish and install a complete modular wall system including,

More information

Considering Modular Buildings for Your Space Needs?

Considering Modular Buildings for Your Space Needs? Considering Modular Buildings for Your Space Needs? Consider This Design of Space: What will you be using the building for? How many square feet of space per person is reasonable? Code Requirements*: (building

More information

2014 Commercial Plan Submittal Checklist

2014 Commercial Plan Submittal Checklist City of Aurora Public Works Department AURORA PUBLIC SCHOOLS AND CHERRY CREEK PUBLIC SCHOOLS 2014 Commercial Plan Submittal Checklist Permit Center 15151 E. Alameda Parkway, Ste 2400 Aurora, CO 80012 303-739-7420

More information

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule "C"

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule C OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS Schedule "C" Building Code All Ready To Move (RTM) Homes are built according to the Alberta Building Code and National Building Code. Please note that

More information

MISSOURI DEPARTMENT OF TRANSPORTATION ATTACHMENT G FACILITIES EXPECTATION FORM

MISSOURI DEPARTMENT OF TRANSPORTATION ATTACHMENT G FACILITIES EXPECTATION FORM MISSOURI DEPARTMENT OF TRANSPORTATION ATTACHMENT G FACILITIES EXPECTATION FORM Note: This list should be used as a guide and not considered all inclusive. The offeror should use due diligence for any items

More information

TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX

TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ FAX TOWNSHIP OF LOGAN 125 MAIN STREET, PO BOX 314 BRIDGEPORT, NJ 08014 856-467-3626--- FAX 856-467-9260 Application for Certificate of Occupancy for Change of Occupancy Pursuant to Chapter 119 of the Township

More information

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210)

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210) Quality Inspection 8618 London Heights San Antonio, TX 78254 Phone: (210) 240-0476 PRE DRYWALL INSPECTION REPORT Prepared For: DELETED (Name of Client) Concerning: DELETED, San Antonio, TX 78258 (Address

More information

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements 700 Paris Ave. PO Drawer 9 Port Royal, SC 29935 Application for Permit - P O Drawer 9, Port Royal South Carolina Permit

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

Delta Zeta Sorority House Renovation Scope of Work

Delta Zeta Sorority House Renovation Scope of Work PROJECT: Delta Zeta Renovation Alpha Sigma Chapter 749 West Jefferson St. Tallahassee, FL 32304 Delta Zeta Sorority House Renovation Scope of Work This renovation scope is based on plans drawn by 4m Design

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

INTERIOR ENVIRONMENT

INTERIOR ENVIRONMENT CHAPTER 12 INTERIOR ENVIRONMENT > SECTION 1201 GENERAL 1201.1 Scope. The provisions of this chapter shall govern ventilation, temperature control, lighting, yards and courts, sound transmission, room dimensions,

More information

Qualifying Process for Handyman Online Qualifying Questions. Name: Street Address: City: State: Zip Code. Home Phone: Cell Phone: Address:

Qualifying Process for Handyman Online Qualifying Questions. Name: Street Address: City: State: Zip Code. Home Phone: Cell Phone:  Address: Qualifying Process for Handyman Online Qualifying Questions Please type in your answers and email to info@pittsburghsbestremodeling.com or print out this form and write in your answers and fax to 412-829-1664

More information

OVERHEAD SERVICE DISTRIBUTION

OVERHEAD SERVICE DISTRIBUTION OVERHEAD SERVICE DISTRIBUTION Overhead Service Carriers Our service distribution solutions have been designed to be compatible with a wide range of furniture and fume hood products, allowing you to create

More information

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies MasterFormat LEVEL TWO NUMBERS AND TITLES Introductory Information 00001 Project Title Page 00005 Certifications Page 00007 Seals Page 00010 Table of Contents 00015 List of Drawings 00020 List of Schedules

More information

PREP + INSULATION. DISCLAIMER: These tools are for illustrative purposes only and

PREP + INSULATION. DISCLAIMER: These tools are for illustrative purposes only and PREP + INSULATION HOME ENERGY UPGRADES What every contractor needs to know. Copyright 2012 Advanced Energy. All Rights Reserved 103 HOME ENERGY UPGRADES Prep + Insulation Contents Air sealing is a challenging

More information

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5 Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey 01-2320 sqft.spf] Page 1 of 5 PREPARATION PRELIM PERMITS & FEES Building Permit 1 each 2200.00 _ 2200.00

More information

Modular Wood Framing Goes Vertical

Modular Wood Framing Goes Vertical Modular Wood Framing Goes Vertical By: Troy Bean, P.E., S.E. DCI Engineers January 2013 The Wood Products Council is a Registered Provider with. Credit(s) earned on completion of this program will be reported

More information

CENTRAL GREAT PLAINS SERIES

CENTRAL GREAT PLAINS SERIES CENTRAL GREAT PLAINS SERIES 1 2 MADE FOR LIVING A heritage of excellence. Atlantic Homes has been providing families with quality homes for generations. With a unique combination of state-of-the-art manufacturing

More information

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection SECTION 13090 RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13090-1 LOW INTENSITY RADIATION PROTECTION

More information

6 Bears and a Goat Brewery - Phase I

6 Bears and a Goat Brewery - Phase I Abbreviations 417 William Street Project Address 1140 International Parkway, Virginia 22406 Agency with Jurisdiction Stafford County, VA Tenant Area 9,975 SF- gross Vicinity Map Code Data Applicable Code

More information

Seal Harbor Development 1 Nagog Park Acton, MA 01720

Seal Harbor Development 1 Nagog Park Acton, MA 01720 Seal Harbor Development 1 Nagog Park Acton, MA 01720 Specifications for Ocean Mist Villages Foundation and Concrete Floors Footings All footings are constructed and poured with 3000 lb mix, continuous

More information

Building Inspection Report

Building Inspection Report Building Inspection Report Sample Commercial Inspection Report Inspection Date: Prepared For: Prepared By: Professional Property Inspection Consultants 4857 Winterset Drive Columbus, OH 43220 (614) 459-5941

More information

OFFICE OF EDUCATIONAL FACILITIES FLORIDA BUILDING CODE SECTION 423 APPLICATION MATRIX

OFFICE OF EDUCATIONAL FACILITIES FLORIDA BUILDING CODE SECTION 423 APPLICATION MATRIX 423.1 Scope: Public educational facilities 423.2 Public schools and community colleges general requirements 423.2.1 Owner 423.2.2 Exemption from local requirements 423.2 Code enforcement 423.3.1 School

More information

Training Certification Categories

Training Certification Categories Training Certification Categories Residential Residential Building Inspector structures are free from hazardous structural conditions and comply with the UCC. Duties include inspection of footings and

More information

RESIDENTIAL BUILDING REQUIREMENTS

RESIDENTIAL BUILDING REQUIREMENTS RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell

More information

ELEMENTS COLLECTION 1

ELEMENTS COLLECTION 1 ELEMENTS COLLECTION 1 2 MADE FOR LIVING A heritage of excellence. Atlantic Homes has been providing families with quality homes for generations. With a unique combination of state-of-the-art manufacturing

More information

BUILDING CODES & DESIGN CRITERIA

BUILDING CODES & DESIGN CRITERIA BUILDING CODES & DESIGN CRITERIA Adopted Building Codes: 2006 International Building Code (IBC) 2006 International Residential Code (IRC) 2006 International Mechanical Code (IMC) 2006 International Plumbing

More information

Cheldelin Middle School

Cheldelin Middle School Facility Information Address: 987 NE Conifer Blvd Corvallis Site Size: Building Area: Construction Date: Improved Parking: Grade Levels Served: Regular Classrooms: Portable Classrooms: Sept. 2007 Enrollment:

More information

The facility is approximately 439,350 square feet, located on a acre parcel on Wood Dale Road in Wood Dale, Illinois. 439,350 Square Feet

The facility is approximately 439,350 square feet, located on a acre parcel on Wood Dale Road in Wood Dale, Illinois. 439,350 Square Feet 1.0 DESIGN SPECIFICATIONS 1.1 Size of Building and Tract: The facility is approximately 439,350 square feet, located on a 21.86-acre parcel on Wood Dale Road in Wood Dale, Illinois. 1.2 Size of Building

More information

Features & Amenities. EXTERIOR FINISHES COMMUNITY FEATURES

Features & Amenities.  EXTERIOR FINISHES COMMUNITY FEATURES Features & Amenities COMMUNITY FEATURES EXTERIOR FINISHES WARRANTY COVERAGE Located in the heart of Troy along the east side of Rochester Road, between Wattles and Long Lake Roads Easy access to I-75 and

More information

Hansen Pole Buildings Planning Guide. Toll Free / Toll Free FAX

Hansen Pole Buildings Planning Guide. Toll Free / Toll Free FAX Hansen Pole Buildings Planning Guide Toll Free 866-200-9657 / Toll Free FAX 866-200-9658 While we strive to earn your business, whether you purchase from us or not, we would hope you would utilize this

More information

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS **************************************************************************

(August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS-02 42 91 (May 2010) ------------------------- Preparing Activity: USACE Nontechnical Title Revision (August 2015) UNIFIED FACILITIES GUIDE SPECIFICATIONS SECTION TABLE

More information

Fairfax County, Virginia

Fairfax County, Virginia Fairfax County, Virginia Typical Finished Basement Details Based on the 2009 International Residential Code CONTENTS General Requirements... 2 Emergency Escape and Rescue... 2 Wall Construction... 3 Floor/ceiling

More information

Telecommunication Spaces

Telecommunication Spaces Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137

More information

New Homes Forestbrook Road. Yes, it s INCLUDED!

New Homes Forestbrook Road. Yes, it s INCLUDED! Sugar Mill is a Covenant Restricted Community. New Homes Forestbrook Road Yes, it s INCLUDED! Granite Countertops Ceramic Tile Kitchen Floors Front Brick Accents Upgraded Kitchen Cabinets Ceramic Tile

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information

Section HIGH-TENSION Stretched-Fabric Wall Systems SoftWalls, Inc.

Section HIGH-TENSION Stretched-Fabric Wall Systems SoftWalls, Inc. P a g e 1 PART I. GENERAL 1.01 Scope A. Furnish and install SoftWalls HIGH-TENSION Acoustical & Tackable Stretch Fabric Systems B. Related Work Specified Elsewhere: 1.Preparation of a smooth, flat and

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

The Ultimate Home Value with Quality,

The Ultimate Home Value with Quality, The Ultimate Home Value with Quality, Durability & Flexibility in Design Chesapeake Bay Limited Series Homes 21 S. Groffdale Road Leola, PA 17540 (800) 406-1062 or (717) 656-2381 Fax (717) 656-0316 www.eagleriverhomes.net

More information

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011

UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 UNIVERSITY OF ARIZONA CONSTRUCTION AND RENOVATION PERMITTING PROCEDURE ADOPTED: JULY 2011 CONTENTS A. PURPOSE B. DESIGNATED RESPONSIBILITIES C. DEFINITIONS D. PROJECT SUBMITTAL PROCEDURE E. REQUIREMENTS

More information

Velma F Thomas Early Childhood Center

Velma F Thomas Early Childhood Center Facility Assessment Summary This report summarizes the findings of a facility assessment completed on the date noted in the document footer below. Assessors rate each facility feature and system by visual

More information

3. Has a hazardous materials survey been completed for the project to identify any potential contaminates? Answer: Yes.

3. Has a hazardous materials survey been completed for the project to identify any potential contaminates? Answer: Yes. 1. Page A401 details 3, 4, 5 show storefront sections, but no storefront specification exists. Can this be provided? Answer: This frame these sections apply to is to be changed to hollow metal. Delete

More information

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application

CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application CITY OF CAMDENTON OFFICE OF THE BUILDING OFFICIAL Commercial Building & Architectural Review Permit Application DATE: / / PERMIT # REQUEST FOR: NEW BUILDING ADDITION REMODEL PLUMBING ONLY ELECTRIC ONLY

More information

Seasons Business Center New Construction!

Seasons Business Center New Construction! Seasons Business Center New Construction!...Seasons Business Center Stow, Ohio 114,188 SF of High Bay Space 32 Clear Height 80 480 ESFR Sprinklers Tax Abatement Available 8 Reinforced Concrete Floor 271

More information

SIDEWALK & RAILING REPLACEMENT BOARD OF ED BUILDING

SIDEWALK & RAILING REPLACEMENT BOARD OF ED BUILDING PROJECT: 25 E 5 S SALT LAKE CITY, UTAH 84111 CODE ANALYSIS APPLICABLE CODES 675 E. 5 S. Suite 4 DFCM PROJECT NUMBER: 182782 DFCM CONTRACT NUMBER: 18793 STRUCTURAL ENGINEER: REAVELEY ENGINEERS + ASSOCIATES

More information

CONSTRUCTION TRADES LABORATORY September 30, 2010

CONSTRUCTION TRADES LABORATORY September 30, 2010 CONSTRUCTION TRADES LABORATORY September 30, 2010 I. PROGRAM REQUIREMENTS Refer to the project-specific Schedule of Spaces for student stations, square footage, and for any requirements that may differ

More information

Dear Home Owner: Certificate Holder: Mr. xxxxxx Unit yyyyyy 3410 N. Lake Shore Drive Chicago, IL ADDITIONAL INSURED LANGUAGE:

Dear Home Owner: Certificate Holder: Mr. xxxxxx Unit yyyyyy 3410 N. Lake Shore Drive Chicago, IL ADDITIONAL INSURED LANGUAGE: Dear Home Owner: For your information, construction work can be done in the unit Monday through Saturday, during the hours of 8:00 am to 6:00 pm. Deliveries and equipment must be taken through the back

More information

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF WELDED SYSTEM PART 1 GENERAL 1.1 SECTION

More information

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations Project Update Project Update September 8, 2006 January 06, 2010 Project Manager Project Manager Anibal Caussade Dennis Bonny Field Coordinator Field Coordinator Bud Ball Paul Friel Project Budget Project

More information

BID SPECIFICATIONS FOR CLEANING & MAINTENANCE SERVICES FOR CITY OF ZION

BID SPECIFICATIONS FOR CLEANING & MAINTENANCE SERVICES FOR CITY OF ZION BID SPECIFICATIONS FOR CLEANING & MAINTENANCE SERVICES FOR CITY OF ZION The City of Zion is requesting bids for cleaning and maintenance services to be performed at: Zion City Hall, 2828 Sheridan Road,