DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340
|
|
- Joy Johnston
- 6 years ago
- Views:
Transcription
1 DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. The General provisions of the contract, including GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS AND DIVISION I, GENERAL REQUIREMENTS apply to the work specified in this section. B. DEFINITIONS 1.02 DESCRIPTIONS 1. Heavy Duty Concrete Floor Manufacturer: A-H EMERY Aggregate Topping as manufactured by Anti-Hydro International, Flemington, NJ, 08822, (908) A. Work includes: Furnish all necessary materials, labor and equipment required to install heavy duty topping. B. Related work specified elsewhere: 1. Cast-in-Place Concrete, see Section Reinforcing steel, see Section Integral Hardener, see Section Concrete Finishing, see Section Concrete Curing, see Section Joint Sealants, see Section QUALITY ASSURANCE A. Manufacturer's Qualifications 1. Obtain heavy duty floor topping materials from a single manufacturer with a minimum of twenty-five (25) years of experience providing materials of the type specified in this section. 1
2 2. The heavy duty floor topping manufacturer shall provide a representative who will instruct the applicator's crew on the proper techniques of applying the heavy duty floor topping. B. Applicator's Qualifications 1.04 GUARANTEE 1. Installation shall be performed by a concrete contractor with not less than years of satisfactory experience in the application of the type of system as specified in this section, and shall be approved by the manufacturer of the heavy duty floor topping. A. The contractor shall furnish the manufacturer's standard maintenance guarantee of the heavy duty concrete floor topping for a period of five years after installation. This maintenance guarantee includes the bond and hard, non-dusting qualities of the floor. Not included are damage due to Acts of God or other elements beyond the scope of protection of this system. B. The integral hardening manufacturer shall review the proposed concrete mix design for all concrete containing integral hardening admixture and shall submit, in writing, acceptance of proposed mix. C. The contractor shall notify the heavy duty concrete floor topping manufacturer seven working days prior to system placement. D. Anti-Hydro International shall furnish daily inspections and reports of each day's placement furnished to the architect and/or engineer. The cost of the inspections is to be borne by the contractor SUBMITTALS A. Product Data 1. Submit manufacturer's technical data on specified products of the heavy duty concrete floor topping. 2
3 2. Submit a letter from the manufacturer certifying compliance with the requirements of sections 2.01.B and 2.01.C of this specification. 3. Submit independent test data using X-ray diffraction or other accepted method on EMERY aluminum oxide and ferric oxide contents. 4. Submit a list of three installations where this system has been in use for five years or greater. 5. Submit a specimen copy of the Daily Inspection Report and Five Year Maintenance Guarantee MATERIAL DELIVERY, HANDLING AND STORAGE A. Primary system materials shall be delivered in the manufacturer's undamaged, unopened containers. Each container shall be clearly marked with the following: 1. Product name 2. Manufacturer's name 3. Lot/Batch numbers B. Provide equipment and personnel to handle the materials by methods which prevent damage. C. The contractor shall promptly inspect all direct jobsite deliveries to assure that quantities are correct and that materials comply with requirements and are not damaged. D. The contractor shall be responsible for all materials furnished by him, and he shall replace, at his own expense, all such material that is found to be defective in manufacture or that has become damaged in transit, handling or storage. E. Store materials in accordance with manufacturer's instructions, with seals and labels intact and legible. Maintain temperatures within the required range. Do not use materials which have been stored for a longer period of time than the manufacturer's maximum recommended shelf life. All materials containing portland cement or 3
4 1.07 JOB CONDITIONS other hydrating powders are to be kept dry until use to prevent damage. A. During material application, care should be exercised to comply with the temperature and humidity limitations of the materials used as defined by the manufacturer. PART 2 - MATERIALS 2.01 PRODUCTS A. Concrete Base Slab: For concrete materials, see Section 03300, Cast-In-Place Concrete and provide additional items as required by this section. 1. Concrete base shall have a maximum of 3% air content. Do not use air entraining admixtures. 2. Concrete mix shall contain a minimum of 5.6 bags of Type I portland cement per cubic yard and not more than 32 gallons of total liquid. Add "ANTI-HYDRO" Integral Admixture at the rate of 1.5 gallons per cubic yard. 3. Do not use fly ash, cement substitutes or slag cement in mix design. B. Integral Hardening Admixture: "ANTI-HYDRO" Integral Hardening Admixture. The integral hardening admixture shall conform to the following requirements: 1. The admixture shall have a twenty year history of successful use in similar applications. 2. The admixture shall have been tested by an independent testing laboratory according to ASTM C-501 and shown to increase abrasion resistance of a 4000 psi concrete by 75%, minimum over a control mix without the admixture. 3. The admixture shall increase compressive strength of the concrete mix design at 28 days by 5%, 4
5 minimum a control mix of the same design without the admixture. 4. The admixture shall have been tested by an independent testing laboratory in accordance with ASTM E and shown to reduce water vapor transmission by one-half, minimum, over a control mix without the admixture and shall produce concrete with a perm rating of 0.04, minimum. C. Topping Aggregate: A-H EMERY, size A1, as manufactured by Anti-Hydro International, conforming to the following requirements: 1. Emery aggregate shall conform to Corps of Engineers CE-204 and shall consist of not less than 58% aluminum oxide and 24% ferric oxide. 2. Emery aggregate shall not be effected by freezing, moisture or cleaning compounds. 3. Emery aggregate shall be tested for conductivity and shall have a value of not more than 6.0 x 10-5 ohm-cm at room temperature. 4. Emery aggregate shall be crushed, factory graded, polyhedral in form and shall conform to the following gradation: Sieve Size %Retained 3/8 2-3 # # # # # #100 Trace D. A-H EMERY A1 PREMIX 1. A-H EMERY Aggregate shall be supplied "premixed", proportioned at the rate of 300 pounds of A-H EMERY 5
6 aggregate, 94 pounds of Type I portland cement, and workability agents. 2. A-H EMERY A1 PREMIX shall be mixed using clean equipment. Mixing liquid shall consist of "ANTI- HYDRO" integral floor hardener added with the mixing water. Use in accordance with the manufacturers' recommendations. NOTE TO SPECIFIER: SECTION 2.01 E.1. / Optional System E. A-H EMERY A1 AGGREGATE END OF NOTE. 1. A-H EMERY Aggregate shall be mixed at the site at the rate of 300 pounds of A-H EMERY Aggregate to 94 pounds of Type I portland cement. Mixing liquid shall consist of 1 quart "ANTI-HYDRO" Integral Hardening Admixture and not more than 4 gallons of total mixing liquid per bag of cement. 2. Compressive strength shall be tested in accordance with ASTM C-109 and shall produce minimum compressive strengths as below: 1 Day 6,000 psi 3 Days 8,000 psi 28 Days 14,000 psi 3. Flexural strength shall be tested in accordance with ASTM C-293 and shall produce minimum flexural strengths as follows: Flexural Strength: 7 Days 1,000 psi 28 Days 1,600 psi F. Bonding Agent: A-H EPOXY BONDING #125 or "ANTI-HYDRO" SLUSH COAT admixture, as manufactured by Anti-Hydro International. 6
7 G. Curing: A-H 3 WAY SEALER AIM as manufactured by Anti- Hydro International, consisting of a liquid type membrane-forming curing compound complying with ASTM-C- 309, Type I, Class A. Moisture loss not more than grams per square centimeter when applied at 200 square feet per gallon. H. Joint Sealant: Saw cut joints shall be filled with A-H GROOVE & CRACK FILLER #250, elastic type modified epoxy filler, per Section. I. Materials for this specification are based on products of Anti-Hydro International and terminology used may include reference to manufacturer's proprietary product. Such reference shall be construed only as establishing the quality of material and workmanship to be used under this section and shall not be construed as limiting competition. PART 3 - EXECUTION 3.01 CONCRETE PLACEMENT A. For concrete base slab placement, see Section 03300, and provide additional items required by this section SLAB SUB-BASE 1. Concrete base shall be placed at 3" maximum slump. 2. Add integral hardening admixture to the mixing water or to the partially mixed concrete and continue mixing for an additional 30 revolutions at mixing speed. A. The base to receive the concrete slab for the heavy duty concrete floor finish shall be well drained, uniformly well compacted and free of frost and foreign materials. The base shall be damp but free of standing water. B. No concrete shall be placed on wet or soggy ground without first laying and compacting a bed of broken stone or gravel of adequate thickness to prevent the mud from mixing with the concrete. 7
8 3.03 CONCRETE BASE SLAB A. NEW CONCRETE BASE SLAB 1. Place concrete base slab between screed points to minimize handling. Concrete shall be placed and screeded using proper tools and equipment to prevent segregation. Use square tipped shovels to move concrete into place; do not use rakes. 2. Surface of base must be textured before concrete achieves final set. Texturing is done by cutting ribs in the surface with a coarse wire broom. The presence of laitance on the hardened base slab shall not be permitted. Water cure only. B. EXISTING CONCRETE BASE SLAB 1. Clean, and prepare existing concrete floor slabs with scarifying, shotblast, or waterblast equipment to a sufficient depth beyond the point of any contamination and loose materials. 2. Remove debris from jobsite. Powerwash the prepared surface to remove loose material. Cover base slab with polyethylene sheets if the topping application is delayed for more than 48 hours or the base slab is subject to debris or contamination from other trades APPLICATION OF TOPPING A. Surface Preparation: The concrete base slab shall be cleaned, dampened and treated with a slush coat consisting of 1 part "ANTI-HYDRO" Admixture, 3 parts water and enough Type I portland cement to make a creamy slurry. 1. Scrub slush coat into base surface with a stiff broom and place topping while slush coat is still wet. 8
9 B. Follow manufacturers instructions for epoxy bonding application. C. Topping: Mix topping as specified under section , and in accordance with manufacturer's instructions. D. Emery topping shall be straight edged or rolled level, immediately followed by bull floating or "darbying" for secondary leveling and compaction FINISHING A. After the topping has been allowed to stiffen (sustain foot pressure with no greater than 1/4" indentation), the first floating operation shall start. After completion of this operation, the topping shall be allowed to stiffen further. A second floating operation shall be done perpendicular to the first float. B. For subsequent trowelings, the blades of the power trowel shall be slightly tilted to produce a hard, smooth, finished surface free from chatter marks or blemishes. For further burnishing, continue troweling operation JOINTS A. Control Joints 1. Control joints shall be spaced in accordance with ACI Standard Concrete Floor and Slab Construction. All joints in base concrete must be carried through the topping. 2. Control joints shall be saw cut a minimum of 1/4 of the thickness of the concrete base slab and 2/3 the thickness of the A-H EMERY Topping. Cuts must be made as soon as the concrete or topping can be cut without raveling the edge, but not more than 24 hours after finishing. 3. Joints shall be filled with A-H GROOVE & CRACK FILLER #250, elastic type modified epoxy joint 9
10 filler per Section, at a minimum of 28 days after concrete placement. B. Construction Joints 1. Construction joints shall be keyed or doweled for load transfer as shown on the drawings. Construction joint edges in the topping should be compacted with a small radius edging tool. 2. Joints shall be filled with A-H GROOVE & CRACK FILLER #250, elastic type modified epoxy joint filler per Section, at a minimum of 28 days after concrete placement CURING AND PROTECTION A. The base Concrete and topping should be wet cured for a minimum of seven days in accordance with the provisions of ACI 302.1R-30, Section 8.1. B. As soon as the topping has been finished according to the provisions of section 3.05 of this specification, apply A-H 3 WAY SEALER AIM at the rate of square feet per gallon. Allow to dry and immediately flood the topping with water. Cover with wet burlap and polyethylene. Maintain wet cure for a period of 7 days, minimum. C. Concrete base and topping shall not be placed in temperatures over 80 deg. F, in the direct rays of the sun, or are exposed to drying winds. Care should be taken to prevent water loss. Erect wind barriers, finish the concrete promptly and start wet curing immediately. D. Floor topping should not be subjected to traffic during the 7 day water curing period. If the slab is to be subjected to heavy traffic during the first two weeks, it should be protected by plywood sheets or planking QUALITY CONTROL TESTING DURING CONSTRUCTION 10
11 A. Quality control testing of base concrete shall conform to the requirements of Section 03300, "Cast In Place Concrete," section B. Quality control testing of EMERY aggregate topping shall conform to the requirements of this section. C. The Owner will employ an inspector and testing laboratory approved by the Architect/Engineer to perform tests and to submit test reports to the local authorities, Owner, Architect, Engineer and Contractor. D. Sampling and testing for quality control during placement of topping may include the following, as directed by Owner's inspector. E. Compressive Strength of Hydraulic Cement Mortars: ASTM C Emery Aggregate Topping Temperature: Test hourly when air temperature is 50 degrees Fahrenheit and below, and when 80 degrees Fahrenheit and above; and each time a set of compression test specimens are made. 2. Compressive Strength Tests: ASTM C , one set (6 cubes 2" x 2" x 2") for each 3 cubic yards of EMERY aggregate topping placed for each day's pour; two specimens tested at 3 days, two specimens tested at 7 days, and two specimens tested at 28 days. Mold and store cubes for laboratory cured test specimens. 3. Strength level of cubes will be considered satisfactory if averages of sets of strength test results equal or exceed specified compressive strength, and no individual strength test result falls below specified compressive strength by more than 85%. F. Test results will be reported in writing to Architect, Structural Engineer and Contractor within 24 hours after tests. Reports of compressive strength tests shall contain the project identification name and number, date 11
12 3.09 JOB COMPLETION REV.8/14 HDCFT.DOC of topping placement, name of concrete testing service, location of topping batch in structure, and design compressive strength at 28 days. A. The Heavy Duty Floor Topping manufacturer shall inspect the completed hardened floor according to the manufacturer's guarantee provisions. The contractor shall correct all defects to meet this specification and those of the EMERY topping manufacturer. B. Clean up all debris, excess materials and equipment and remove from site. C. Guarantee paperwork must be processed within 60 days from the date of substantial completion. END OF SECTION 12
SECTION SITE CONCRETE
SECTION 321313 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting
More informationSECTION MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS
SECTION 09699 MOISTURE RESISTANT/WATER-PROOF FLOORING ADHESIVE FOR CONCRETE SLABS PART 1 GENERAL 1.1 SECTION INCLUDES A. Testing and application of systems for the reduction of moisture resistant or water-proof
More informationPART 1 - GENERAL. Section Cast-in-Place Concrete 1.3 REFERENCES
CSI SECTION 32 13 13 CONCRETE PAVING 32 01 26 RIGID PAVING REHABILITATION DOT APPROVED PRODUCTS LIST OR SPECIAL PROVISIONS Very Early High Strength, Low Shrinkage, Powder Polymer-Modified Concrete Overlay
More informationMay 8, 2017 ADDENDUM #1. IFB Resin Floor System For Highway Department Central District Building
May 8, 2017 ADDENDUM #1 IFB 17-082 Resin Floor System For Highway Department Central District Building Addendum #1 is being issued to offer an alternate resin flooring system. 096700 FLUID-APPLIED FLOORING
More information1.1 Related Work Specified in Other Sections (Delete if Not Applicable):
NOTE TO SPECIFIER: Concrete Resurfacing (Broom Finish) System provides an economical alternative to the removal and replacement of existing concrete. This system creates a flexible and durable finish that
More informationKOSTER AMERICAN CORPORATION
Section 09699 PART 1 GENERAL Water Vapor Emission Control Systems 1.1 RELATED DOCUMENTS A. Drawings, documents, and general provisions of the Contract, including, but not necessarily limited to, General
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SECTION INCLUDES A. The Contractor shall furnish all work and materials, including cement, sand and coarse aggregate, water, admixtures, curing
More informationSPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN
SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN 1. SUMMARY A. Work includes: 1. Pavement removal, topsoil stripping, and site grading for concrete slab.
More informationFundamentals of Concrete
Components Cement Water Fine Aggregate Coarse Aggregate Fundamentals of Range in Proportions Advantages of Reducing Water Content: Increased strength Lower permeability Fundamentals of Increased resistance
More informationA. Drawings and general provisions of the contract, including General and Supplementary Conditions, apply to this section.
SECTION 03 01 30 MAINTENANCE OF CAST-IN-PLACE CONCRETE SECTION 03 01 40 MAINTENANCE OF PRECAST CONCRETE SECTION 03 01 50 MAINTENANCE OF CAST DECKS AND UNDERLAYMENT SECTION 03 01 60 MAINTENANCE OF GROUTING
More informationINDUSTRY RECOMMENDATION EXTERIOR CONCRETE FLATWORK
INDUSTRY RECOMMENDATION for EXTERIOR CONCRETE FLATWORK Prepared by Ohio Concrete Inquires regarding this document may be addressed to: Ohio Concrete 2600 Corporate Exchange Dr., Ste. 165 Columbus, OH 43231
More informationBy CTS Cement Manufacturing Corp.
CSI SECTION 03 60 00 GROUTING 03 62 00 NON-SHRINK GROUTING 03 62 13 NON-METALLIC NON-SHRINK GROUTING High Flow, Non-Metallic, Multi-Purpose, Cementitious, Non-Shrink Grout EDITOR NOTE: The following guideline
More informationNarrow Modular Pavers (NMP) for Sand-Set Installations
The following specification refers to the Stepstone, Inc. product known as: Narrow Modular Pavers (NMP) for Sand-Set Installations Narrow Modular Pavers are part of the California Architectural Paver line
More informationSECTION CONCRETE PAVING SLABS SET IN MORTAR
SECTION 32 14 13.16 CONCRETE PAVING SLABS SET IN MORTAR (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs mortared to a concrete base and grouted joints
More informationBIO-AQUIFER STORM SYSTEM
BIO-AQUIFER STORM SYSTEM Specifications for Construction PART 1 GENERAL 1.01 SECTION INCLUDES A. Providing labor, materials, tools and equipment to furnish and install a permeable concrete paving stone
More informationSECTION EPOXY FLOORING SYSTEMS
SECTION 09800 EPOXY FLOORING SYSTEMS PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationA. ASTM C 150 Standard Specification for Portland Cement. B. ASTM C 595 Standard Specification for Blended Hydraulic Cements.
TECHNICAL SPECIFICATIONS SEWER MANHOLE REHABILITATION SYSTEM WITH A PROTECTIVE CEMENT LINER AND HIGH BUILD EPOXY COATING (As Provided by Standard Cement Materials) FOREWORD The following specification
More informationCELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES
PART 1: SCOPE CELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES 1.1 An Approved Celcore Applicator shall furnish all labor, materials and supervision
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish
More informationfor Mortar-Set Concrete Tiling Installations
The following specification refers to the Stepstone, Inc. product known as: Large Scale CalArc Pavers for Mortar-Set Concrete Tiling Installations Large Scale CalArc Pavers are part of the California Architectural
More informationSECTION COMMON WORK RESULTS FOR CONCRETE SSPECIALTY COATINGS
SECTION 03 05 00 COMMON WORK RESULTS FOR CONCRETE 09 97 00 SSPECIALTY COATINGS Weld Crete ************************************************************************************************************************
More informationCRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING
Guide Specification CRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING COORDINATE WITH DRAWINGS: Show location and extent of stabilized aggregate surfacing. Show details required at adjoining
More informationSECTION EPOXY TERRAZZO
SECTION 09402 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to
More informationSECTION RESINOUS FLOORING or SECTION QUARTZ FLOORING
SECTION 09 67 23 RESINOUS FLOORING or SECTION 09 67 26 QUARTZ FLOORING PART 1 - GENERAL 1.1 SUMMARY (Specification writer shall add, delete or amend, as deemed necessary) A. Provide all labor, materials,
More informationITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS
ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown
More informationKolorines Glass Mosaic Tiles Project Specification
Kolorines Glass Mosaic Tiles Project Specification SUGGESTED SPECIFICATION Glass Mosaic Tile Installation for Swimming Pools NOTES TO SPECIFIER: 1. Specify PremiumPlus Thin-Set mixed with CustomFlex Additive
More informationPAVING SLABS ON A CONCRETE BASE
SECTION 32 14 13.16 PAVING SLABS ON A CONCRETE BASE (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs on a sand bed over concrete for pedestrian applications.
More informationUFGS (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-07 16 19 (January 2007) ---------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-07 16 19 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More information1.2 Reference Standard: NOFMA - National Oak Flooring Manufacturers Association Grading Standards.
WOOD FLOORING GENERAL INFORMATION 1.1 This section applies to factory finished wood strip flooring. 1.2 Reference Standard: NOFMA - National Oak Flooring Manufacturers Association Grading Standards. 1.3
More informationDIVISION 03 CONCRETE CONCRETE Maintenance of Concrete
DIVISION 03 CONCRETE 03 00 00 CONCRETE 03 01 00 Maintenance of Concrete 03 01 10 Maintenance of Concrete Forming and Accessories 03 01 20 Maintenance of Concrete Reinforcing 03 01 23 Maintenance of Stressing
More informationB. Related Sections: 1. Division 07 Section "Joint Sealants" for sealing of expansion, contraction, control, and isolation joints in tile surfaces.
SECTION 093000 - CERAMIC TILE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationEngine Bay Floors Floor Resurfacing 4000
Engine Bay Floors Floor Resurfacing 4000 P.O. Box 341 Macungie, PA 18062 610.530.7710 800.573.9198 www.enginebayfloors.com 1.1 SUBMITTALS Flooring Specification SECTION 1 GENERAL A. Product Data: Submit
More informationSECTION TILING
SECTION 09 30 00 TILING PART 1 - GENERAL 1.1 SUMMARY A. Section includes tile as indicated on new surfaces and as specified. 1.2 SUBMITTALS A. Samples: 1. Submit samples of colors and sizes of tile. B.
More informationSeptember 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE
September 1, 2003 CONCRETE MANUAL 5-694.800 5-694.810 GENERAL SPECIAL TYPES OF CONCRETE 5-694.800 In the general use of the word concrete, the idea implied is the conventional placement of the material
More informationConstruction Standard Specification Section Exposed Aggregate Concrete. Exposed Aggregate Concrete
Construction Standard Specification Section 03351 Exposed Aggregate Concrete Exposed Aggregate Concrete Part 1 GENERAL 1.01 Summary A. Section includes: Exposed Aggregate Concrete produced through the
More informationA. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.
SECTION 033000 - PART 1 - GENERAL 1.1 SUMMARY A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes. B. Related
More informationSUPER-KRETE SPECIFICATION S-1 EXISTING CONCRETE SURFACE PREPARATION SECTIONS ; /19; ;
SUPER-KRETE SPECIFICATION S-1 EXISTING CONCRETE SURFACE PREPARATION SECTIONS 01 71 16; 02 25 16/19; 03 01 30; 0716 16 SUPER-KRETE International, Inc. This product guide specification is written according
More informationSECTION ARCHITECTURAL CAST STONE
PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 047200 ARCHITECTURAL CAST STONE A. RELATED DRAWINGS All drawings, to include supplemental drawings, instructions and conditions of this contract. B. RELATED
More informationB. All work of the section shall comply with the conditions of the contract, the drawings and any special conditions forming a part of the contract.
SPECIFICATIONS PART ONE - GENERAL ------------------------------------------------------------------------ 1.01 General Description A. The Cementitious capillary waterproofing materials specified herein
More informationPERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960
STUC-O-FLEX PERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960 PART 1 - GENERAL 1.01 DESCRIPTION Provide all labor, materials and equipment necessary
More informationSECTION UTILITY MANHOLES AND STRUCTURES
SECTION 33 05 14 UTILITY MANHOLES AND STRUCTURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Precast reinforced concrete manholes and structures with tongue-and-groove joints with masonry transition
More informationA. The scope of this standard includes recommendations for the specification of cast-in-place concrete.
PART 1: GENERAL 1.01 Scope of Standard A. The scope of this standard includes recommendations for the specification of cast-in-place concrete. 1.02 Related Standards A. Structural Systems (currently The
More informationTILE TILE
09300 - TILE 09300-1 PART ONE: GENERAL 1.1 Description TILE 1.1.1 Work of this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance with the requirements
More informationprospec.com Concrete Repair & Restoration
prospec.com Concrete Repair & Restoration Table of Contents Product Portfolio 3 Product Enhancements 4 Product Selection Matrices 5 Construction Grout & Precast Non-shrink grouts C-1107 Construction Grout
More informationConstruction Standard Specification Section Exposed Aggregate Concrete
Construction Standard Specification Section 03351 Exposed Aggregate Concrete Part 1 GENERAL 1.01 Summary A. Section includes: Exposed Aggregate Concrete produced through the use of a chemical surface retarder
More information1. Rapid Set Cement. 2. Methods of preparation. 3. How to stage a job site. 4. Installation Mix, place, finish. 5. Coloring the TRU.
1. Rapid Set Cement 2. Methods of preparation 3. How to stage a job site 4. Installation Mix, place, finish 5. Coloring the TRU natural TRU Rapid Set is NOT Portland Cement Rapid Set is a Calcium Sulfoaluminate
More informationTECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &
TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS Financial Project ID 429140-1-52-01, 429140-2-52-01 & 428267-1-52-01 The official record of this Technical Special Provision is the electronic file signed
More informationSECTION HYDRAULIC CEMENT UNDERLAYMENT
ARDEX GUIDE SPECIFICATION ARDEX Underlayment HC 100 High-Capacity Self-Leveling and V1200 Self-Leveling Flooring Underlayment Cement-based Self-Leveling Underlayment for use with ARDEX ARDIFLO System SECTION
More informationITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)
ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED) 275.1. Description. This Item shall govern for treating subgrade, new and/or existing base [with or without asphaltic concrete pavement (ACP)], or
More informationFIVE STAR PRODUCTS, INC. (800)
FIVE STAR PRODUCTS, INC. www.fivestarproducts.com (800) 243-2206 Page 1 of 11 DESIGN-A-SPEC GUIDELINES FIVE STAR RS ANCHOR GEL CONTENTS PART A - GENERAL CONDITIONS PART B - MATERIAL SPECIFICATIONS PART
More informationBest Management Standards / Specifications. For Concrete Slab Raising. Prepared in conjunction with the Concrete Repair Association
For Concrete Slab Raising Prepared in conjunction with the Concrete Repair Association DETAILED SPECIFICATIONS 1. Description: 2. Slab Raising: These specifications cover the furnishing, boring, drilling,
More informationIt s in the Pour Gla-Zit does so much for all types of new concrete projects no Pour should be without it. Gla-Zit.com
It s in the Pour Gla-Zit is a unique liquid, added to cement for waterproofing/densifying concrete masonry and Ready-Mix product. Add Gla-Zit as the last material, mix for three (3) minutes and Pour. Gla-Zit
More informationARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound
ARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound SECTION 03 01 30 MAINTENANCE OF CAST-IN-PLACE CONCRETE
More informationCEMENTITIOUS CRYSTALLIZING WATERPROOFING PART 1 GENERAL
CEMENTITIOUS CRYSTALLIZING WATERPROOFING PART 1 GENERAL 1.1 SECTION INCLUDES A. Cementitious crystallizing waterproofing for interior/exterior walls and floor slabs with nonactive leaks. B. Cementitious
More informationPRODUCT SPECIFICATIONS
PART 1 GENERAL 1.01 SUMMARY A. Section Includes: High density cast resin architectural products, including columns, panels, caps, bases, trim elements and balustrade systems. Specifier Note: Article below
More informationSECTION 3300 CAST-IN-PLACE CONCRETE
SECTION 3300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 DESCRIPTION A. This Section includes furnishing materials and installation of cast-in-place concrete as indicated on the Drawings and/or specified
More informationEditing notes to assist users are separated from specification text by rows of asterisks. Delete these notes prior to final printing.
SECTION 09635 LIMESTONE FLOORING This guide specification has been prepared by TexaStone Quarries LLC to assist design professionals in the preparation of a specification section covering cut limestone
More informationSection Polished Concrete Finishing. Vexcon
SS 105 5-16 Section 03 35 43 Polished Concrete Finishing Specifier Note: This product guide specification is written according to the Construction Specifications Institute (CSI) 3-part format. This section
More informationA. Section includes hydraulic-cement-based, polymer-modified, self-leveling underlayment for application below interior floor coverings.
SECTION 03 54 16 - HYDRAULIC CEMENT UNDERLAYMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
More informationSTANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL
STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL 1. SCOPE 2. DESIGN 3. MATERIALS 4. CONSTRUCTION 5. METHOD OF MEASUREMENT AND PAYMENT SCOPE This Specification sets out requirements for the design,
More informationConcrete. Chapter 10 Properties of Fresh Concrete. Materials of Construction-Concrete 1. Wikipedia.org
Wikipedia.org Concrete Chapter 10 Properties of Fresh Concrete Materials of Construction-Concrete 1 What is Concrete? Concrete is a composite material that consists of a cement paste within which various
More informationSIKALASTIC-152 EXTERIOR WATERPROOFING MEMBRANE. Product. Scope. Appraisal No. 811 [2013] Appraisal No. 811 (2013) Amended 28 August 2017
SIKALASTIC-152 EXTERIOR WATERPROOFING MEMBRANE Amended 28 August 2017 BRANZ Appraisals Technical Assessments of products for building and construction. Sika (NZ) Ltd PO Box 19 192 Avondale Auckland 1746
More informationColoured Mineral Dry Shake Floor Hardener
Construction Product Data Sheet Edition: 27/02/2013 Identification no: 02 08 03 04 001 0 000013 Version: GCC Coloured Mineral Dry Shake Floor Hardener Product Description is a one part, pre-blended, coloured
More informationFlorock Seamless Flooring Systems
Architectural Specification FloroCrete RT Rake/Trowel Urethane Mortar 3/16-1/4 (4.5-6.0 mm) Floor Resurfacing System Part 1: General 1.01 System Description A. System I Skid-Resistant Finish Resurfacing
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS
USACE / NAVFAC / AFCEC / NASA UFGS-03 37 13 (November 2009) ----------------------------- Preparing Activity: USACE Superseding UFGS-03 37 13 (April 2006) UNIFIED FACILITIES GUIDE SPECIFICATIONS References
More informationSECTION Pedestrian Traffic Coatings{PRIVATE } 1.1 SUMMARY (Specification writer shall add, delete or amend, as deemed necessary)
Guide Specification MiraFlex II For Plywood Decks Pedestrian Deck and Waterproofing System (Specification writer shall choose the most appropriate section that applies to a given scope of work, including
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular
More information2018 Flooring Specification - Tile Set Method TECTURA DESIGNS CEMENT TERRAZZO TILES
2018 Flooring Specification - Tile Set Method 09300 TECTURA DESIGNS CEMENT TERRAZZO TILES PART 1 - GENERAL 1.1 INTRODUCTION A. Tectura Designs, Terrazzo Tiles are to be installed following the tile setting
More informationGUIDE SPECIFICATION
GUIDE SPECIFICATION 09 64 33.01 940 Centre Circle, Suite 1000 Altamonte Springs, FL 32714 Telephone: 407-260-9910 Fax: 407-260-9933 Toll Free: 800-800-5247 Web Site: http://www.kahrs.com This Guide Specification
More informationPacific Polymers Elasto-Deck BT Guide Specification
1 07141-1 August 2016 Pacific Polymers Elasto-Deck BT Guide Specification SECTION 07141 FLUID APPLIED WATERPROOFING 2 07141-2 August 2016 Pacific Polymers Elasto-Deck BT Guide Specification SECTION 07141
More informationPRODUCT GUIDE SPECIFICATION
PRODUCT GUIDE SPECIFICATION Specifier Notes: This product guide specification is written according to the Construction Specifications Institute (CSI) 3-Part Format, including MasterFormat, SectionFormat,
More informationSPECIFICATION GUIDELINE
SPECIFICATION GUIDELINE Environmental Stoneworks Corporate Office 6300 East Stapleton Drive South Denver, CO 80216 Phone (303) 309-3040 Fax (303) 309-3059 www.estoneworks.com Environmental Stoneworks specification
More informationGuide to Improving Specifications for Ready Mixed Concrete
NRMCA Publication 2PE004 Guide to Improving Specifications for Ready Mixed Concrete 2015 National Ready Mixed Concrete Association All rights reserved NRMCA Publication 2PE004 Guide to Improving Specifications
More informationSECTION EPOXY TERRAZZO
SECTION 09 66 23.16 EPOXY TERRAZZO THIS GUIDE SPECIFICATION HAS BEEN PREPARED BY THE NATIONAL TERRAZZO AND MOSAIC ASSOCIATION, INC., AND IS DISTRIBUTED FOR USE BY ITS MEMBERS AND DESIGN PROFESSIONALS.
More informationTolerances- Section
Tolerances- Section 346-6.4 Do not add water to delivered concrete when it is within the target Range for slump 1 346-6.4 Tolerances: Meet the following tolerances from target values for plastic concrete
More informationSECTION RESINOUS MATRIX TERRAZZO FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 09 66 23 - RESINOUS MATRIX TERRAZZO FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationSECTION ROOF PEDESTAL PAVER SYSTEM
SECTION 07 76 00 ROOF PEDESTAL PAVER SYSTEM ************************************************************************************************************************ Edit entire master to suit project requirements.
More informationTechnical Memorandum No. MERL Quality Management Plan Guidance for Concrete used for Construction of Significant Features
Quality Management Plan Guidance for Concrete used for Construction of Significant Features 1. 2. U.S. Department of the Interior Bureau of Reclamation Technical Service Center Denver, Colorado August
More informationSECTION A. American Society for Testing and Materials (ASTM):
hp.seal-krete.com 306 Gandy Rd., Auburndale, FL 33823-2723 800.323.7357 863.967.1535 fax:863-965.2326 Seal-Krete High Performance Epoxy-Shell WB 50 Product Specification GUIDE SPECIFICATION SECTION 09725
More informationGUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410
GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific
More informationA. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):
SECTION 31 32 13.16 CEMENT STABILIZATION PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section pertains to the specifications for cement stabilization of sandy or silty soil and consists of pulverizing, addition
More informationITEM P-631 REFINED COAL TAR EMULSION WITH ADDITIVES, SLURRY SEAL SURFACE TREATMENT
9/30/2009 AC 150/5370-10E ITEM P-631 REFINED COAL TAR EMULSION WITH ADDITIVES, SLURRY SEAL SURFACE TREATMENT 631-1.1 GENERAL. This item shall consist of a mixture of refined coal tar emulsion, mineral
More informationLS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION
LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION A. Section Includes B. References C. Quality Assurance D. Submittals E. Delivery, Storage and Handling F. Environmental Conditions G. Summary H. Concrete
More informationSECTION INTERLOCKING CONCRETE PAVERS
SECTION 23 14 13 INTERLOCKING CONCRETE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for concrete paver applications in the U.S. for concrete pavers and bedding sand over a compacted
More informationApplication Instructions for Keystone Kool Deck on Existing Concrete
Application Instructions for Keystone Kool Deck on Existing Concrete REQUIRED MATERIALS Keystone Kool Deck PTA Bonding Agent Water 20 Mesh Marble Sand White Portland Cement OPTIONAL TOOLS Mortex Pattern
More informationDECORATIVE EXTERIOR FINISHING
System Guide Specification for Super-Krete Stain and Seal System S-9550 SECTION 03 35 00 Concrete Finishing and SECTION 09 93 13 Exterior Staining and Transparent Finishing DECORATIVE EXTERIOR FINISHING
More informationConstruction. SikaTop 111 Plus. Application Instructions. Sika Corporation
SikaTop 111 Plus Application Instructions SikaTop 111 Plus Two-component, polymer-modified, portland cement based. Fast-setting, screed mortar. Performance repair mortar for horizontal repairs and form
More informationInternational Polished Concrete Institute November 2006 Toll Free (866) Website
International Polished Concrete Institute November 2006 Toll Free (866) 421-9550 Website www.ipcionline.org E-mail info@ipcionline.org SECTION 03365 POLISHED CONCRETE FLOOR SYSTEM PART 1 GENERAL 1.1 SECTION
More informationKinds of Mortars. Mortar. Specifying Mortar. Proportion Specifications. M a S o N w O r K. Specification for Mortar Cement
ASTM C9 ASTM C44 ASTM C270 ASTM C780 ASTM C329 ASTM C586 Mortar Specification for Masonry Specification for Aggregate for Masonry Mortar Specification for Mortar for Unit Masonry Method for Preconstruction
More informationCITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS
CONCRETE SIDEWALKS AND DRIVEWAYS PART 1 DESCRIPTION OF WORK The work to be done under this section of the Specifications and the accompanying plans consists of all labor, material, and equipment necessary
More information***********************************************************************************
AQUAFIN-2K/M Two-Component Cement-based Acrylic-based Waterproofing GUIDE AQUAFIN, Inc. SPECIFICATION PART 1 - GENERAL 1.1 SECTION INCLUDES SECTION 07 16 14 ACRYLIC MODIFIED (FLEXIBLE) CEMENTITIOUS WATERPROOFING
More informationFiber Reinforced Tile and Stone Mortar
, ANSI A 118.4, ANSI A 118.11 ARDEX X 77 MICROTEC Fiber Reinforced Tile and Stone Mortar The most advanced technology ideal for large format porcelain tile installations,exterior or interior, floor or
More informationCW 3615 RIPRAP TABLE OF CONTENTS
December 2014 SPECIFICATION CW 3615 R4 CW 3615 RIPRAP TABLE OF CONTENTS 1. GENERAL CONDITIONS... 1 3. DESCRIPTION... 1 5. MATERIALS... 1 5.1 General... 1 5.2 Rock... 1 5.3 Random Stone Riprap... 1 5.4
More informationProject Address: Name of Person Completing Form:
Statement of Inspections This form is provided as a way to list aspects of the project that require special inspection and testing in accordance with IBC Sections 107.1, 1704, and 1705 and define duties
More information1. Cast-in-place concrete is specified in Section
SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record
More informationApplication Specification:
Application Specification: GW-15-UBU-HD April 2014 Supersedes 5/13 PART 1 - GENERAL 1.1 SUMMARY Division 07 18 16: GACOFLEX POLYURETHANE ELASTOMERIC COATING SYSTEM FOR VEHICULAR TRAFFIC DECKS AND RAMPS
More informationMunicipality of Waterville Public Sidewalk Repair Policy
Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by
More information1. Decks, balconies, and sun porches 2. Walkways, ramps, and stairways 3. Patios and courtyards
SECTION 07185 TRAFFIC MEMBRANE PART 1 GENERAL 1.1 SECTION INCLUDES A. Traffic membrane, consisting of welded seam PVC waterproofing, over f following surfaces: 1. Decks, balconies, and sun porches 2. Walkways,
More informationINSULATED CONCRETE MASONRY UNITS Section 04220
INSULATED CONCRETE MASONRY UNITS Section 04220 PART 1 GENERAL 1.01 Summary A. Section Includes 1. Insulated masonry wall units (CMU's) 2. Decorative insulated masonry wall units 1.02 SUBMITTALS A. Samples:
More informationCHATTANOOGA, TN Last Updated: 04/12/17. NOTE TO SPECIFIER: Be sure to obtain the latest version of this Guide Specification.
NOTE TO SPECIFIER: Be sure to obtain the latest version of this Guide Specification. This Guide Specification is not a completed document ready for use. It must be edited (i.e., deleting, adding, or modifying
More information