AIA 2009 BIM AWARDS. Category B: Design/Delivery Process Innovation Using BIM
|
|
- Arnold Griffith
- 6 years ago
- Views:
Transcription
1 Introduction AIA 2009 BIM AWARDS Category B: Design/Delivery Process Innovation Using BIM Project: UNIVERSITY OF COLORADO - DENVER HEALTH SCIENCE CENTER RESEARCH COMPLEX II Owner s Statement Architect s Statement Contractor s Statement Effective Project Team Coordination The ReadClash Story Better Planning with 4D Simulation Design and Construction Team VDC Coordination Assembly Instructions for Construction - Steel Assembly Instructions for Construction - Concrete 3D Coordination of MEP and Fire Protection Owner Integration Project Summary
2 INTRODUCTION Virtual Design and Construction (VDC): A collaborative process incorporating both design and construction input through the use of Building Information Models (BIM), CPM schedules and cost estimates to create a virtual building prototype prior to construction. The University of Colorado-Denver Health Sciences Center (UCDHSC) Research Complex 2 (RC2) project is an 11 story, 540,000 square-foot biomedical research facility located in Aurora, Colorado on the UCDHSC Anschutz Medical Campus. RC2 is the second biomedical research building on the campus following RC1, built on an adjacent site a few years earlier by a different general contractor and designed by the same architectural firm. The RC2 project provided a rare opportunity to compare the use of VDC processes on a new building to a very similar project built without substantial use of these technologies. The proposed use of VDC technology and processes on RC2 was a key factor in the owner s selection for the project team. The project team s goals for the use of BIM and VDC on RC2 were to improve our customer experience, enhance productivity, optimize the project schedule, and to provide effective collaboration among the project team members from the start of design through construction. The VDC processes that allowed the construction team to achieve these goals were Integrated Work Planning for concrete placement, 4D Visualization, and 3D MEP Coordination. The design team leveraged BIM on the RC2 project to enhance the design process and the models were shared as part of the process. The use of BIM and VDC then continued during the project with the generation of assembly instruction models to facilitate construction.
3 OWNER S STATEMENT The University of Colorado Denver Research 2 project at the Anschutz Medical Campus has been a pleasure and one of the most successful projects we ve had. The CM/GC, the architect and the University worked as a well integrated team to deliver the project. Delivering state-of-the art research programs is a process reflective of conducting the research itself; rapidly evolving, financially challenging, emotionally rewarding. The process is involved and involving, given a community which is naturally inquisitive and tirelessly consent driven; there is little to the process that isn t under scrutiny. Success in this environment requires experience as well as calm, professional conduct. And foremost, an ever-present focus on the needs of the client and program. It s a process that demands self-less execution. The CM/GC s willingness and drive to embrace new computer technologies for coordination and scheduling places them ahead of other general contractors. Their commitment and foresight in requiring the subcontracting trades to also work with the same new technologies is a benefit to both the project and to the construction industry in general. We feel that the general contractor has measured up to the demands placed upon them by our culture and our needs, let alone the external challenges brought on by market dynamics. We absolutely couldn t be more pleased with your leading of the construction services team for Research Complex 2.
4 ARCHITECT S STATEMENT RC1 was a successful project by all conventional standards -- on schedule, on budget, full program achieved, happy users and client. RC2 went beyond successful into the realm of outstanding. One factor contributing to the difference was that the programmatic similarity between the two projects allowed the first to serve as a mock-up for the second. The team had the opportunity to interview the RC1 users at all levels to fine tune the concept, program and construction. A second, perhaps more important factor related to the use of 3D modeling throughout the process on RC2. The full design team modeled RC2 starting early in the design process. The model was used by the contractor as soon as they were on board for early project cost and schedule analyses. Collision detection was done by the design team initially on small repetitive portions of the project, then on larger zones and floors, and finally on the entire project. As the fast track project progressed, bid documents were issued in 2D but the 3D design model accompanied each bid package. The contractor and the primary subs made the model their own and with each succeeding document issue, they used the design team s updated model to update their own. Multiple coordination sessions were held between the design team member disciplines and the construction subs, each time using the 3D model as the primary tool for understanding and resolving issues. The most complex portion of the project was the interstitial mechanical level above a subterranean vivarium. The contractor expanded the design model to include every trade and every service element. Meetings between the design and construction team often included members of the client s facilities group to assure access and maintenance issues were suitably addressed. The positive impacts of the 3D modeling were many. Previously unforeseen problems occurred in the model and on the viewing screen rather than in physical conflicts. The overall project construction schedule was substantially foreshortened because of minimized conflicts, shared data, and the ability to study sequence issues in the model. And a true sense of collaboration was developed between all participants -- design team members, contractor and subs, client and ultimate users, and the facilities personnel who actually operate and maintain the project. RC2 went beyond successful into the realm of outstanding.
5 CONTRACTOR S STATEMENT Research Complex II is one of those great projects where not only did the project execute successfully with a happy customer, early completion, under budget, high quality, and a very strong safety record, but the team enjoyed the project from start to finish. This overwhelming success was the result of strong collaboration of the team from the day of our award to the start of research in the completed building. We were selected as the CM/GC under a competitive fee and qualifications process in the summer of 2003 where we committed to utilize our building expertise coupled with our recent BIM/VDC experience on a number of other high profile projects. With construction not planned to start until late 2005 and the acknowledged complexity of the $200 million project, the entire team was committed to research tools that would lead to dramatic process improvement. After developing BIM/VDC processes in 1997, our company was and is committed to pushing our projects to advance the use of innovative tools to improve project outcomes and deliver better projects for our customers. The team took this goal to heart and implemented a collaborative model based process from the start of preconstruction. Because this commitment was made in 2003, some of the BIM tools utilized by the team were truly pushing the capabilities of the available technology and are less sophisticated than the tools we use today. What stands out from this project is the process change that occurred within all of the team members and the measured results that the project experienced. Everyone involved with the Research Complex II project is extremely proud of our accomplishments and have used all of the lessons learned to enhance our projects today. What does stand out out from this this project is is the the process process change change that that occurred occurred within within all of the all of team the members team members and the and measured the measured results results that the project experienced.
6 Effective Project Team Coordination One of the leading factors in the success of the RC2 project was that all team members came to the table clearly understanding that if the project was to be successful, early participation and coordination with all design team members was essential. During the early stages of Design Development, all members of the design team were brought together and the team quickly agreed on a language that the electronic design files would speak. Common layering strategies, coordinated base points, and an open model sharing philosophy were determined to be critical for proper collision detection and reporting. ARCHITECT Autodesk ADT 2006 NavisWorks v5 Design Model d Manager M age OWNER CM C / GC Autodesk ADT 2006 NavisWorks v5 Construction t u Model Manager M age The architect managed the consultants in the creation of the BIM and acted as the design model manager. The architect s model provided exterior skin and interior architecture 3D information The consultants models provided 3D design information for their respective disciplines The architect performed early 3D coordination using Navis- Works JetStream The design models provided the design intent information that was then transferred to the construction team DESIGN TEAM RENDERING MEP STRUCTURAL ENGINEERS ENGINEERS Autodesk ABS 2006 RAMCAD /ADT 2006 STRUCTURAL DESIGN MODEL GC - CONCRETE STEEL SELF PERFROM SUBCONTRACTOR ADT 2006 CIS/2 & TEKLA MECHANICAL ELECTRICAL SUBCONTRACTOR SUBCONTRACTOR ABS 2006 / CADDUT ABS 2006 FIRE PROTECTION SUBCONTRACTOR ABS 2006 ARCHITECTURAL DESIGN MODEL MEP DESIGN MODEL
7 The ReadClash Storyy The general contractor s experience with BIM on previous projects, specifically the use of NavisWorks JetStream during 3D MEP Coordination, encouraged the design team to implement the software as part of their coordination workflow. JetStream allowed the model manager to combine models from all disciplines and find collisions between the various systems, which might otherwise have gone unnoticed using traditional coordination methods. The need to better visualize the data produced by JetStream was identified. Collaboration between the architect and general contractor resulted in the commissioning of new proprietary software called ReadClash. ReadClash permitted the conflict issues found using NavisWorks JetStream to be easily located within the AutoCAD environment, the native design software used by all disciplines on the project. This allowed even non-technical team members to work with the entire team in coordinating the complex Mechanical and Structural systems. ReadClash was used for early design coordination between the structural and MEP engineers. During the pre-construction and construction phases, the use of ReadClash became standard process for conflict and resolution tracking for the contractor. CLICK ON IMAGE ABOVE TO VIEW READCLASH ANIMATION
8 Better Planning with 4D Simulation The general contractor used a multi-tiered approach to scheduling, which involved studying installation scenarios, communicating the results to the subcontractors, and tracking material procurement and delivery. 4D visualization, created by linking a 3D model with a CPM schedule, enabled the construction team to actively participate and provide instantaneous feedback on the schedule throughout the life of project. The 4D process was led by a construction team project scheduler using NavisWorks Timeliner software. The 4D visualization was used in pre-planning coordination meetings to avoid field conflicts between subcontractors scheduled to work in adjacent areas. The 4D process tracked the installation of critical systems required for the on-schedule completion of the building, including structural, building enclosure, and interior construction. With the early integration of the construction team in the 4D process, the project was able to benefit from the accurate placement of concrete and structural systems, which mitigated the opportunities for re-work. The successful use of BIM as a planning tool allowed the construction team to increase productivity, enhance communication amongst the project team and deliver RC2 two months earlier than originally planned. CLICK ON IMAGE ABOVE TO VIEW 4D ANIMATION
9 Design and Construction Team VDC Coordination Early selection of the general contractor permitted it to engagement of a design-assist role early in the project. In addition to its standard portfolio of pre-construction, estimating and constructability review services other projects which were under construction by the general contractor, provided invaluable lessons learned. These experiences were conveyed to the design team and subcontractors, and remote site visits were arranged to assist in the development of a protocol for the use of BIM on the project The contractor leveraged its pre-construction experience and provided direct feedback to the design team based on discoveries that its virtual coordination process uncovered. This level of early engagement increased the number of pre-construction and constructability questions (and subsequent solutions) well in advance of the actual construction activities. The resulting number of construction-phase Requests For Information (RFI) was significantly lower when compared to the RC1 project Pre-coordination Post-coordination
10 Assembly Instructions for Construction - Steel 1 2 The design team BIM was delivered to the contractor at the end of the design phase and the contractor became the steward of the new construction BIM. The general contractor and subcontractors added constructability information and a greater level of detail to this means and methods model. Sets of 2D shop drawings or assembly instructions for various phases and disciplines of construction were ultimately derived from the construction BIM. 3 STEEL DESIGN AND FABRICATION: The structural steel analysis model from the engineer was exported and used by the steel detailer/fabricator. A 3D model was exported from the steel fabrication model to integrate with other construction models for virtual coordination. The fabrication model was then used to develop structural steel shop drawings. The structural steel was fabricated off-site and delivered per the project steel erection schedule. 4
11 Assembly Instructions for Construction - Concrete 1 2 GENERAL CONTRACTOR SELF-PERFORMED CONCRETE WORK: The process began with a base 3D building model and added layers of information (i.e. structural steel, embeds, MEP sleeves and other design considerations). The construction team used a quality control method to review the data with all related disciplines. The composite 3D model was distilled and translated into an installation drawing for use by the concrete crew. The information provided is an accurate, single-source set of instructions and eliminates the risk of using incomplete or uncoordinated drawings. The IWP process on RC2 contributed to a 74% reduction in RFI s during earthwork and foundation installation when compared to the RC1 project. 4 3 The 3D process was instrumental in identifying coordination conflicts prior to work proceeding in the field. This guaranteed the plan to be accurate and the work uninterrupted, allowing the field to have very predictable safety, quality and schedule -Contractor Superintendent 5
12 3D Coordination of MEP and Fire Protection The general contractor led the virtual MEP coordination process by compiling a composite 3D model of the various MEP systems prior to fabrication and installation. The contractor also added important structural and architectural elements to the model to increase its accuracy and usability for construction coordination. By serving as the model manager and integrator, the general contractor was able to facilitate solutions to model clashes between trades that were in the best interest of the project. RFI s were submitted with 2D/3D media attachments derived from the BIM, providing quick and exact explanations of the issues. Combined with a proposed solution, proven through 3D modeling, the RFI response time of the design team was reduced and trial-and-error in the field all but eliminated. A further result was increased pride in the work by the subcontractors, who were included in the resolution process. The ReadClash and NavisWorks JetStream applications allowed each subcontractor to use their native AutoCAD plug-in software to generate accurate, coordinated 3D MEP models. The models could then be carried downstream to their CNC fabrication machinery to prefabricate their systems. The high degree of fabrication accuracy resulted in a simplified, error-free installation. As a result of the VDC processes implemented on RC2, the electrical subcontractor had the least amount of re-work they ever observed in the field. The mechanical subcontractor estimated a 50% reduction in labor and 50% reduction in schedule from the use of VDC. Building as modeled Building as modeled Building as constructed Building as constructed Building as modeled Building as constructed
13 Owner Integration The owner s facilities team was engaged throughout the 3D MEP coordination process. Their involvement helped to ensure that all MEPFP system equipment would be easily accessible for future maintenance purposes. The initial coordination work resulted in the complete elimination of field changes related to improving or increasing access. This feat would have been virtually impossible without the collaboration of those involved and the technology to facilitate the process. The initial 3D MEP investigation of the Vivarium (animal research facility) level prompted the owner to request the generation of BIM-derived animation sequences of the mechanical areas. This process and presentation allowed for a better understanding of the complex mechanical room, and resulted in a redesign of the catwalk systems to accommodate the required servicing of equipment. CLICK ON IMAGE ABOVE TO VIEW THE VIVARIUM WALKTHROUGH AS PLANNED = AS BUILT
14 Project Summary The use of VDC by the project team resulted in an overall reduction of RFI s when compared to the RC1 project. The resulting reduction in RFI and change order administration costs offset the cost of BIM/VDC. The 4D simulation was a key component in visually communicating the aggressive CPM schedule. By leveraging VDC, particularly 4D Simulation, the construction team completed the RC2 project two months early; six months ahead of RC1! An independent research student from the University of Colorado found the following impact from the use of VDC: An increase in RFI s during preconstruction due to VDC review of design resulted in the reduction of construction RFI s by 74% during the foundation phase and by 47% during the steel erection phase. RC2 experienced a 37% reduction in coordination RFI s. RC2 experienced a 32% reduction in coordination change orders The mechanical subcontractor estimated a 50% reduction in labor and 50% reduction in schedule from the use of VDC. The construction model has continued to be used since the completion of the project. The owner engaged the contractor to assist in studying move/add/change requests by the building users. The construction BIM facilitated the investigation of how to programmatically change areas that were already constructed. The facilities management team received construction model CAD files representing 90% of the as-built conditions to use in their management of the facility. A NavisWorks model with hyperlinks to an Excel spreadsheet equipment list was also provided to the facilities management team. Virtual Design and Construction on the UCDHSC Research Complex 2 project achieved the team goals of enhancing productivity, optimizing the project schedule, providing effective collaboration, and improving the customer experience.
FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF
ARCHITECTURE & BUILDING ENGINEERING AEC COLLECTION EBOOK FIVE WAYS YOUR MOVE TO A BIM WORKFLOW PAYS OFF Get started > 01 02 03 04 05 DELIVER HIGHER- QUALITY WORK OPERATE MORE EFFICIENTLY EXPAND YOUR BILLABLE
More informationThe benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM
Page 1 of 5 The benefits of reinventing the wheel BIM AND IPD BRING FUNDAMENTAL CHANGES TO ROLES IN A STRUCTURAL ENGINEERING FIRM By Rick Oehmcke, S.E. Not that many years ago, few structural engineers
More informationRealizing Complex Design Through BIM The Louisiana State Museum and Sports Hall of Fame
The Louisiana State Museum and Sports Hall of Fame Location: Natchitoches, Louisiana Category: A: BIM Excellence Type: New Construction Site Area: 36,500 sq. ft. GSF Total: 27,000 sq. ft NAA Total: 18,900
More informationBIM Checklist. Introduction
Introduction This Building Information Modeling (BIM) Checklist is intended to be used as a guide for project stakeholders who are looking to implement BIM/VDC in a design-build project. Since integration
More informationBIM Design & Construction Requirements. Follow-up Seminar. September 10,
BIM Design & Construction Requirements Follow-up Seminar September 10, 2009 www.indiana.edu/~uao/iubim.html Opening Comments Two years ago Indiana University began the process of embracing the use of Building
More informationBenefits of Employing BIM on Unique Designs: Art Gallery of Alberta. Bob Walker Ledcor Construction Limited Edmonton, Alberta May 2011
Benefits of Employing BIM on Unique Designs: Art Gallery of Alberta Bob Walker Ledcor Construction Limited Edmonton, Alberta May 2011 The Evolution of the new Art Gallery of Alberta Ledcor Construction
More informationDESIGN + BUILD CONSTRUCTION
DESIGN + BUILD CONSTRUCTION The Power of Design and Construction Traditional construction methodology is changing. Under the traditional approach, design and construction services are split into separate
More informationBIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders
BIM enhances structural analysis regardless of project size By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders MARCH 2013 BIM enhances structural analysis regardless of project size By Jeffrey Yoders
More informationContracted Scope ABC of the Carolinas Excellence in Construction Awards Carolinas HealthCare System CMC Kitchen Healthcare.
Contracted Scope Provide a detailed description of your scope for this project. Responses should include: type of construction; size of project; contract value; length of project; and percentage of labor
More information- DATA REQUIREMENTS BIM
UHS BIM Protocol S E C T I O N 1 - DATA REQUIREMENTS BIM authoring software: The design team is required to use parametric BIM authoring software for creation of models that include all geometry, physical
More informationRFP Feasibility Design Services: Clinical Education & Assessment Center Expansion Questions & Answers: February 13 th, 2018
Question & Answer: #1 The RFP calls for a survey of the building to gain a comprehensive understanding of the existing building, utilities, building systems, occupancies and all existing conditions as
More informationBIM for Contractors: Kickin It Off the Right Way
BIM for Contractors: Kickin It Off the Right Way David Epps Manager Building Information Modeling Holder Construction Company John Mack VDC / BIM Dept. Manager Herrero Contractors, Inc. John Mack VDC /
More informationPandya Paragkumar U Civil Engineering Graduate Student Lamar University
BUILDING INFORMATION MODELING AND SUSTAINABILITY Pandya Paragkumar U Civil Engineering Graduate Student Lamar University Dr.Enno Ed Koehn, P.E., F.ASCE Professor, Civil Engineering Department Lamar University
More informationBIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER
PROJECT NAME BIM EXECUTION PLAN PROJECT INFORMATION CLIENT PROJECT NAME PROJECT NUMBER XX XXXXX XX XXXXX XXXXXXXXXXXXXXXXXXXXXXXXX DATE XXXXXXXX 2016 PROJECT LOCATION & ADDRESS XXXXX, XXXXX. INTRODUCTION...
More informationA Design Dress Rehearsal Before Building
The Luk Hoi Tong Co., Limited A Design Dress Rehearsal Before Building Office: Proposed Office Redevelopment of 31 Queen s Road Central Location: Central, Hong Kong Type: Commercial Scheduled Time of Completion:
More informationUtilizing BIM technology has major advantages for construction that save
C HAPTER6 BIM for the Construction Industry 6.0 EXECUTIVE SUMMARY Utilizing BIM technology has major advantages for construction that save time and money. An accurate building model benefits all members
More informationMethodist Hospital for Surgery Addison, Texas. CLIENTS Methodist Health System Private Physician Consortium SRP Medical Medica Development
Team First: A Case Study Discussing the Benefits of Team Collaboration and Building Information Modeling on the Design and Construction of a Physician-Owned Surgery Hospital Impacted by Federal Health
More informationGETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams
GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability
More informationWorking with roof consultants can be beneficial, but there are
30 www.professionalroofing.net JULY 2013 During the 2013 International Roofing Expo, I moderated an NRCA panel that explored the relationships between roofing contractors and roof consultants. Although
More informationFACILITIES CONFERENCE
FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity
More informationGIS + BIM = Integrated Project Penn State
524 GIS + BIM = Integrated Project Delivery @ Penn State David E. GOLDBERG, Robert J. HOLLAND and Scott W. WING 1 Introduction In 2007, at the American Society of Landscape Architects Conference in San
More information1/4/2014. Alternative Project Delivery Methods 1. Agenda
Steven. C. Thweatt Assistant Vice Chancellor Facilities Management University of Colorado @ Boulder Steven.thweatt@colorado.edu Introduction Fun in the air More Fun in Chattanooga Licensed Architect Georgia
More information1.0 ABOUT THE NU GUIDELINES
Construction Policies & Procedures Northeastern University Guidelines for Capital Project Design & Implementation.0 ABOUT THE NU GUIDELINES This document is intended to describe in a comprehensive manner
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 01 3100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
More informationState of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements. Version 1.0
State of Tennessee Office of the State Architect {TN OSA) Building Information Modeling {BIM) Requirements Version 1.0 April 22, 2013 Table of Contents 1. Introduction...... 1 1.1. Mission of the TN OSA
More informationACE AGE Awards Submission 2017 Entry Form Category: Contractor: Project Name: Project Description: Solutions of Special Projects:
ACE AGE Awards Submission 2017 Entry Form Category: 8 Best Building Project General Contractor (Under $10 Million) Contractor: PCL Construction Services, Inc., Megan Oldham, mmoldham@pcl.com Project Name:
More informationBuilding Information Modeling to Facilities Information Management and Beyond
Building Information Modeling to Facilities Information Management and Beyond Meghan Ruffo, Thomas Koltoniak, & Geoffrey Coon Carolinas HealthCare System Join the conversation #AU2016 Class summary Carolinas
More informationAchieving Results Through Genuine Leadership
Achieving Results Through Genuine Leadership T R A I N I N G Facing tough issues and aggressive goals, top organizations win by preparing genuine leaders who live out the mission and values of the organization.
More informationDesign/ Build. Engineering Services. Construction MECHANICAL SYSTEMS SOLUTIONS
Design/ Build & Construction Engineering Services MECHANICAL SYSTEMS SOLUTIONS Your single source for building MEP systems Effective building construction and the supporting mechanical, electrical and
More informationPrinciples of Schedule Contingency Management
Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation
More informationStepping into Variable Height Retaining Walls
Stepping into Variable Height Retaining Walls Eric Cylwik Sundt Construction, Inc. CR 2499 - Mechanically-stabilized earth (MSE) walls are inherently complex shapes; smoothly curving in all 3 dimensions
More information2O2O Customer Success Story
Teknion Wows the Design World with More Sophisticated Wood and Casegoods Innovative beautiful design, grounded in principles of quality and durability, are primary values at international office furniture
More informationPhysical or Virtual? : Effectiveness of virtual mockups of building envelope systems
Physical or Virtual? : Effectiveness of virtual mockups of building envelope systems Minjung Maing 1 Introduction. Within the building design to construction process, mockups of some form will be used
More information2017 AGC ACE Awards Category 6: Specialty Contractor: Project Name:
2017 AGC ACE Awards Category 6: Best Building Project, Subcontractor, $6-$10M Specialty Contractor: Sturgeon Electric Company, Inc. Project Name: Denver Health Support Services Building at 601 Broadway
More informationExhibit B - A/E Scope of Services (General Contracting Project) State of Ohio Professional Services Agreements for Public Facility Construction
- State of Ohio Professional Services Agreements for Public Facility Construction TABLE OF CONTENTS ARTICLE 1 - BASIC SERVICES... 1 ARTICLE 2 - PROGRAM VERIFICATION STAGE... 2 ARTICLE 3 - SCHEMATIC DESIGN
More informationPlease comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. LEVERAGING VIRTUAL DESIGN &
More informationCurrent Status of Building Information Modeling (BIM) Adoptability in the U.S. Electrical Construction Industry
Fifth International Conference on Construction in the 21 st Century (CITC-V) Collaboration and Integration in Engineering, Management and Technology May 20-22, 2009, Istanbul, Turkey Current Status of
More informationCarolinas HealthCare System Case Study Collaborate Bid Build (CB 2 ) A Different Approach to Project Delivery
Carolinas HealthCare System Case Study Collaborate Bid Build (CB 2 ) A Different Approach to Project Delivery Carolinas HealthCare System Case Study Behavioral Health Davidson, NC Project Team Carolinas
More informationINOVA Office Building I. Adolfson & Peterson Construction. Keri Burson:
INOVA Office Building I Adolfson & Peterson Construction Keri Burson: kburson@a-p.com; 303-363-7101 Category #9 Best Building Project General Contractor ($10 - $40 Million) Why this project should win
More informationOHSU/PSU/OSU COLLABORATIVE LIFE. SCIENCES BUILDING and OHSU SKOURTES TOWER THIS IS OUR STORY.
OHSU/PSU/OSU COLLABORATIVE LIFE SCIENCES BUILDING and OHSU SKOURTES TOWER PORTLAND, OR GREAT PROJECTS ARE EXECUTED BEST WHEN THE OWNER-ARCHITECT-CONTRACTOR TEAM DEVELOPS A HIGH LEVEL OF TRUST AND COLLABORATION
More informationTexas Health Resources, Methodist Alliance Hospital, Fort Worth, Texas. Hospital; 188,000 s.f. $46.5m 58 beds with growth potential of 300 beds
Seminar Objectives 1) IPD and its impact on team behavior 2) Lean and its role in a collaborative process. 3) Pre-Fabrication 4) How Lean, BIM and collaborative processes impact project value. The Project
More information4D Modeling: Applications and Benefits
4D Modeling: Applications and Benefits Martin Fischer Assoc. Prof., Stanford University Director, CIFE Founder, Common Point Technologies, Inc. The big idea: Build virtually before building in reality.
More informationSynchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study
89 Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3
More informationWindows Server 2003 migration: Your three-phase action plan to reach the finish line
WHITE PAPER Windows Server 2003 migration: Your three-phase action plan to reach the finish line Table of contents Executive summary...2 Windows Server 2003 and the big migration question...3 If only migration
More informationSmartPlant Spoolgen for Fabrication and Construction
WHITE PAPER SmartPlant Spoolgen for Fabrication and Construction Fast and Accurate Spool and Erection Isometrics Contents 1. Introduction... 1 1.1. For the Owner Operator... 2 1.2. For the EPC... 2 1.3.
More informationBIM ADOPTION AND IMPLEMENTATION FOR ENGINEERING & CONSTRUCTION INDUSTRY PRACTICES
BIM ADOPTION AND IMPLEMENTATION FOR ENGINEERING & CONSTRUCTION INDUSTRY PRACTICES ARIEF RAHMAN BIM MANAGER PP Construction & Investment INDONESIA M: +62 8128858162 W: www.pt-pp.com www.pt-pp.com AGENDA
More informationAbout us. 5D Initiative
PRESS RELEASE The 5D Initiative enters into a process of more intensive cooperation with Autodesk, Bentley, CCT, RIB and Tekla in order to develop new BIM software solutions that fit needs of European
More informationREQUEST FOR PROPOSAL. Construction Management Services Not at Risk
REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk
More informationBIM Deliverables Guide for Masonry Contractors Volume II
BIM Deliverables Guide for Masonry Contractors Volume II Contributors: Mike Madone Mountain Masonry LLC Austin Norberg and Justin Wenger Seedorf Masonry Mike Kinateder KMI Construction Ed Davenport Davenport
More informationCareers List Professional Careers in Construction
Careers List Professional Careers in Construction Architect Designs buildings, including the preparation of detailed construction drawings and specifications, and advises on their construction. May specialize
More informationBronx Mental Health Redevelopment Project
Bronx Mental Health Redevelopment Project Residential Village Bronx Campus Transitional Living Residences, Haven House Horizon House, and Studio Apartments BIM Orientation December 20, 2012 1 Bronx Mental
More informationSeattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices
Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district
More informationCRC-CI Project EP National BIM Guidelines and Case Studies
CRC-CI Project 2007-002-EP National BIM Guidelines and Case Studies Tom Fussell - Team Leader Executive Director and Chief Architect, QLD Department of Public Works Scott Beazley - Project Manager BIM
More informationWestinghouse Electric Company Nuclear Power Engineering Campus. Final Proposal. Mark Speicher
Westinghouse Electric Company Nuclear Power Engineering Campus Final Proposal Mark Speicher Advisor: Dr. David Riley December 15 th, 2009 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 ANALYSIS ONE: LEED...
More informationScope of Work Bid Package C-4 - West Polished Concrete
Scope of Work Bid Package C-4 - West Polished Concrete CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,
More informationViewpoint Construction Software Vista 6.14 Product Enhancement Brief
P a g e 1 Viewpoint Construction Software Vista 6.14 Product Enhancement Brief Packed with new enhancements, Vista 6.14 is easier to use, performs better, and now lets you work anywhere there is a Wi-Fi
More informationCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.
More informationPORTLAND PUBLIC SCHOOLS HUMAN RESOURCE SERVICES AND DELIVERY
PORTLAND PUBLIC SCHOOLS HUMAN RESOURCE SERVICES AND DELIVERY January 2013 Overview Portland Public School District (the District or PPS) contracted with AKT to create a new vision and values for their
More informationFor Service and Specialty Contractors
For Service and Specialty Contractors Introducing Sage 300 Trade Specialty Designed Especially for the Unique Needs of Service and Specialty Contractors At Sage, we know that service and specialty contractors
More informationTEACHING BUILDING INFORMATION MODELLING IN AN ARCHITECTURAL SCHOOL
F. Madeo and M. A. Schnabel (eds.), Across: Architectural Research through to Practice: 48 th International Conference of the Architectural Science Association 2014, pp. 421 432. 2014, The Architectural
More informationBack to Where We Once Belonged FM Global s road to SlimBIM
Back to Where We Once Belonged FM Global s road to SlimBIM By Thomas A. Gay Assistant Vice President FM Global - Engineering Plan Services Past Chair Board of Direction buildingsmart alliance Vice Chair
More informationMANAGEservices. Managed Services for Integrated Projects
MANAGEservices Managed Services for Integrated Projects Transform Your Project Delivery Capabilities with ProjectWise MANAGEservices Bentley can provision, manage, monitor and support its industry-leading
More informationNetModeler. NetModeler Concept
Single 3D Building Model Based Project Collaboration Over the Internet Petri Kokko, Enterprixe Software Ltd. Concept HVAC & E Engineer Prefabricators General Contractor Sub-Contractors and Suppliers Structural
More informationBuilding Information Modeling (BIM) Execution Plan
10/19/2017 for [Stanford Project Name] [Stanford Project Number] Developed by [Primary A/E] TABLE OF CONTENTS USE OF THE BIM EXECUTION PLAN... 3 1. PROJECT INFORMATION... 3 2. PROJECT SCHEDULE AND MILESTONES...
More informationBEST PRACTICE COLLABORATION
WHITE PAPER BEST PRACTICE COLLABORATION Executive Summary The architecture, engineering and construction (AEC) industry was once almost synonymous with inefficiency and conflict, and was generally regarded
More informationMultiple-Prime Top 10 Concerns Especially when
Multiple-Prime Top 10 Concerns Especially when There have been many articles written about the benefits of multiple-prime contracting as a successful delivery method alternative for Public Owners especially
More informationdeveloper.* The Independent Magazine for Software Professionals Automating Software Development Processes by Tim Kitchens
developer.* The Independent Magazine for Software Professionals Automating Software Development Processes by Tim Kitchens Automating repetitive procedures can provide real value to software development
More informationA Structured Approach to Minimum Cost Recovery Scheduling
A Structured Approach to Minimum Cost Recovery Scheduling Chris Carson, PSP Project Controls Manager Alpha Corporation Norfolk, Virginia Email: chris.carson@alphacorporation.com Background Project management
More informationCategory: 3 Meeting the Challenge of a Difficult Job GC Contractor: The Beck Group Project Name: The Royal Gorge Bridge and Park Visitor Center
Category: 3 Meeting the Challenge of a Difficult Job GC Contractor: The Beck Group Project Name: The Royal Gorge Bridge and Park Visitor Center The 10-mile-long Royal Gorge is narrow, steep and one of
More informationIV.E.8 - BIM Standards
Contents 1. General... 3 1.1. Strategy & Objective... 3 1.2. Road Map... 4 2. Process... 7 2.1. Start... 7 2.2. Plan... 9 2.3. Execute... 12 2.4. Monitor... 14 2.5. Close-out... 16 3. Execution... 19 3.1.
More informationPlease comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at
Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at http://www.leanconstruction.org/usage.pdf when using this file. Thank you. Welcome to the 5 th Meeting
More informationAutodesk and the UK BIM Level 2 Mandate
Autodesk and the UK BIM Level 2 Mandate BIM Level 2 Mandate The UK Cabinet Office is in the midst of a multi-year effort to reform the way in which the UK government procures construction helping to ensure
More informationMore than 135 years of delivering landmark projects around the world
Company Profile More than 135 years of delivering landmark projects around the world About Us Drake & Scull International PJSC (DSI) is a regional market leader delivering world class quality projects
More informationScott M. Francis, P.E., PSP
Scott M. Francis, P.E., PSP LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Scott M. Francis,
More informationLEVEL I PREQUALIFICATION DOCUMENTS
Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,
More information...becoming a builder when a man s handshake was more important than a written contract, it was only natural to name his company...
...becoming a builder when a man s handshake was more important than a written contract, it was only natural to name his company... JOE E. WOODS, INC. GENERAL CONTRACTING The tradition of fairness, reliability,
More informationExperiencing Interoperability of BIM in a Stadium Project in China
Experiencing Interoperability of BIM in a Stadium Project in China Cheng Zhang 1, Bo Liu 2, Guobin Gong 3 1) Lecturer, Department of Civil Engineering, Xi an Jiaotong-Liverpool University, Suzhou, Jiangsu,
More informationConsensusDocs. Catalog. Updated Docs Inside
ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even
More informationContinuing Education Credits
Recent Developments in (IPD) for NECA Members October 14, 2013 9:00-9:50 AM Following this session, you will be able to: Explain the concept and structure of an IPD project. Identify the issues and risks
More information9, FRANCE USA JAPAN CATIA
CATIA for Yacht Dedicated zone for your graphic band images. The challenges The yachting industry is caught in a fierce crosswind: while the Small Boat market is facing increasingly stiff competition on
More informationDesign Build - Project Delivery Model Trends
Drag picture to placeholder or click icon to add Drag picture to placeholder or click icon to add Drag picture to placeholder or click icon to add Design Build - Project Delivery Model Trends Sean M. Collins,
More informationWhite Paper Microsoft SharePoint for Engineering Document Management and Control
www.cadac.com White Paper Microsoft SharePoint for Engineering Document Management and Control Microsoft SharePoint is a powerful platform for document management and project collaboration. Many project-driven
More informationSECTION QUALITY REQUIREMENTS
SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.
More informationFacilities Planning and Construction (FP&C)
Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:
More informationCustomer FIRST for Avantis PRiSM Program Guide
Customer FIRST for Avantis PRiSM Program Guide Best-in-class Software Maintenance, Support and Services Leverage the Full Value of your Avantis PRiSM Software 02 About Schneider Electric and Avantis PRiSM
More informationAbington Memorial Hospital Abington, PA. Project Description
Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project
More informationDaily Report Module for Construction Management Information System
Daily Report Module for Construction Management Information System Yan-Chyuan Shiau, Wen-Chian Wang Chung-Hua University, Department of Construction Engineering 30 Tung-Shiang, Hsin-Chu, Taiwan, 300, R.O.C.
More informationFacilities Management
Facilities Management October 6, 2017 THIS PAGE INTENTIONALLY LEFT BLANK University of South Florida BIM Guidelines and Standards Page 2 of 30 BIM Guidelines and Standards Table of Contents SECTION 1:
More informationSounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build
When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits
More informationO10 BIM for specialist sub-contractors and trades BIM IN PRACTICE
O O10 BIM for specialist sub-contractors and trades O BIM IN PRACTICE O O10 BIM for specialist sub-contractors and trades Contributors: Dominik Holzer, AEC Connect Sumit Oberoi, AMCA Philip Shanks, Jackson
More informationTurner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project.
EXHIBIT N - Lean Production Planning System and Innovation Turner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project. Production Planning
More informationgrowth automation productivity vision Sapphire Collateral Valuation Management
CASE STUDY How Appraisal Automation is Driving One of America s Largest Homebuilders Get the full story of how one of America s largest homebuilders enhanced productivity and strengthened quality controls
More informationBIM Pilot Getting Started Guide. next
BIM Pilot Getting Started Guide What is BIM? Framework for implementing a BIM pilot project Driven BIM leadership Getting started with your BIM pilot project Moving to BIM can seem like a daunting task.
More informationFebruary Purlins Framing Engineering Dry Lining Cable Management. voestalpine Metsec plc
February 2016 voestalpine Metsec plc www.metsec.com CORPORATE BROCHURE A BRIEF INTRODUCTION voestalpine Metsec plc is the UK s leading manufacturer of cold roll formed steel sections and profiles. Founded
More informationBuilding information modeling (BIM) The holistic view by Siemens. Unrestricted Siemens Switzerland Ltd 2016
Building information modeling (BIM) The holistic view by Siemens siemens.com/bim Construction projects are faced with numerous challenges Unbudgeted costs Unreliable schedule Insufficient quality Environmental
More information3D Virtual Master Campus Planning and Management
3D Virtual Master Campus Planning and Management Dr. Thomas Furlani Charles Hixon Best Practices The Eastern Regional Association of Physical Plant Administrators (ERAPPA) is a Registered Provider with
More informationDesign Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright
Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development
More informationTHE INDUSTRY STANDARD
THE INDUSTRY STANDARD Private i is the clear tool of choice for private capital investors worldwide. Choose Private i and join hundreds of endowments and foundations, pension and sovereign wealth funds,
More informationProject Procurement Considerations in This Market. October 14, 2016
Project Procurement Considerations in This Market October 14, 2016 Overview Thank you for being here! Introduction About QBS Colorado Project Delivery Methods Market Information Federal & State Information
More informationCASE STUDY GOVERNMENT. Metropolitan Council. Managing Project Risks through the Establishment of Effective Project Controls. e-builder.
CASE STUDY e-builder.net Patrick Watz, AECOM s Project Manager By having those processes structured it has helped us streamline things, and give us visibility into where a process is. ABSTRACT This paper
More information