1 THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main Contract works will commence when the Main Contractor is formally appointed and the contract is let. A standstill period may be the required and for information on this refer to diagrams in the following procedure notes: Refer to procedures FGH2 Prepare ITT (OJEU) and FGH3 tender below OJEU 2. PURPOSE The purpose of starting the Main Contract works is to commence and complete the works in accordance with the contract drawings and specifications, within programme and budget. 3. PROCEDURE The key actions in starting the Main Contract works are as follows: Appoint the Main Contractor and let the contract After the Standstill period (if required), set up the pre-start meeting Issue the production information Hand over the site to the Main Contractor to prepare for construction The Design Team leader (normally the Architect) will administer the contract and monitor the works. The contract is a legally-binding commitment between the Contractor and the client to deliver the project. The architect administers this contract impartially between both parties (client and contractor). 3.1 PROJECT MANAGEMENT TEAM ROLE The role of the Project team at this stage is to act as the Client Representative for the duration of the contract. As part of this, they will report to the Project Board at regular intervals, both by Project Board meetings and Project Board reports (in months where there is no meeting). Other responsibilities include: Confirming that the construction phase Health and Safety plan is sufficiently developed to allow possession of site and start of works this is a client duty under the CDM regulations and the Project team may be assisted in this by the CDM coordinator Page 1 of 6

2 Ensuring contract documents are prepared, issued to the Main Contractor, signed and filed Arranging handover of site to Main Contractor and confirming that the necessary insurances are in place Ensuring all legal documents are in place (collateral warranties, performance bonds etc.) Ensuring that the necessary statutory approvals are in place prior to works starting (planning permission, building warrant etc.) Reviewing the Main Contractor s construction schedule and method statements; comparing this against the project master programme Ensuring that a programme of site meetings is set up and documented Managing the Change Control Procedure and authorising change orders as required Monitoring overall funding, cash flow and variations (in liaison with the QS) Ensuring that payments are made promptly in accordance with the contract requirements Ensuring that the Health and Safety file is being maintained Ensuring that the Design Team and any other relevant consultants are undertaking the necessary site inspections Anticipating and resolving problems before they develop as well as establishing mechanisms for dealing with any claims should they arise. Managing the handover process at completion of the works. 3.2 DESIGN TEAM AND QS ROLES Design Team: The role of the Design Team is normally to monitor the construction of the project. This will include: Providing production information Reviewing working drawings being provided by Specialist Sub-contractors Responding to site queries raised by contractors Inspecting the works to ensure compliance with the drawings and specifications, insofar as this can be determined by visual inspection Inspecting the works to ensure an acceptable quality standard has been achieved The structural engineer will have a general duty of care to ensure the erection of the structural frame is proceeding in a safe manner as well as any other components that are subjected to stress, forces or loadings The Design Team is not responsible for the following: The work of any other consultant engaged directly by the University Managing the Main Contractor s programme of works or organising the work on site Contract Administrator: The Design Team leader (the architect) is normally the Contract Administrator and this will be clarified in the Design Team conditions of appointment. Page 2 of 6

3 The Contract Administrator (CA) acts as the formal point of contact between the Project Team and the Main Contractor; the CA will arbitrate on contractual issues and issue the following: Design information Variations Instructions on standards of work and working methods Interim payment and other certificates The Certificate of Practical completion Snagging lists The Certificate of Making Good Defects Quantity Surveyor: The QS is responsible for the following: Measuring the value of work completed by the Main Contractor Agreeing variations through the Change Control Procedure Agreeing monthly valuations with the Main Contractor Agreeing the final account with the Main Contractor In addition to this, the QS has a duty to the University (usually through the Project team) to report on and manage the financial aspects of the construction budget of the project. Such reports are presented to the Project Board through the reports and the Project Board meetings 3.3 MAIN CONTRACTOR ROLE On taking over the site, the Main Contractor is responsible for: Appropriate insurance of the site and the works Mobilising all labour, subcontractors, materials, equipment and plant in order to execute the construction works in accordance with the contract documents and the agreed project programme. Ensuring that the works are completed in compliance with the building contract, Statutory requirements and Health and Safety requirements Day-to-day supervision of the project build Notifying any expected problems or the potential for delay. 3.4 PRE-START MEETING The Design Team leader has responsibility for compiling the pre-start meeting agenda, chairing the meeting, taking minutes and distributing them. Consequently the Project team and the Design team leader require to set the date for the pre-start meeting and discuss and agree the agenda items. Invitees include the Main Contractor (and subcontractors if appropriate), Design Team, other Consultants, the Project team and members of the Project Team (as appropriate). The purpose of this meeting and typical agenda is as follows. However, it is the Design Team s responsibility to draw up and issue the pre-start meeting agenda and obviously this may vary from that indicated. Page 3 of 6

4 Item Title and Content Lead by 1. Introductions: Introduce and welcome all representatives who will regularly attend site progress meetings Clarify their roles and responsibilities Note any specialist consultants appointed directly by the University, e.g. for quality control or commissioning Give project overview and outline University objectives Distribute Project Directory and describe its function 2. Environmental, Health and Safety: Confirm / agree / undertake the following: Notification of the HSE Hand over the Health & Safety Plan and agree procedure for the Health and Safety file Site inductions, H&S information, name of H&S representative 3. Administration: Agree the following: Meetings schedule Communications Liaison with Project team Liaison with third parties Publicity 4. Contract: Confirm current status of production information Hand over any outstanding production information, including and variations. Review situation re: issue of any other important information Request contractor s insurance documents for immediate inspection Request performance bonds (if applicable), warranties, CIS certification etc 5. Costs and budget: Confirm the following: Contract Sum Provisional Sums Procedure for valuations and payment certificates 6. Programme and Progress: Confirm / agree the following: Contract period / duration, with dates of possession and completion Overall master programme Key packages and lead in times Construction programme Key milestones Progress reporting Information required 7. Change Control Procedure: Note procedure for the following: Project team CDM-C Contract Administrator / Design Team leader Contract Administrator /Design Team leader QS Contractor Page 4 of 6

5 Item Title and Content Lead by CCPs Instructions Document Control 8. Standards of Workmanship / Materials / Design: Note procedure for the following: Contractor s Quality System Standards of workmanship and materials Design approval / comments Samples M&E coordination 9. Statutory Consents and third parties: Note status of the following: Planning Building Warrant Environmental Agencies Third Parties 10. Review of site & employer s site requirements: Clarify the following: Site Ownership and boundaries Condition of site and previous use Constraints on use of site Neighbour issues Overview of the following site requirements: Condition survey Conditions of entry to site / signing in and passes Induction procedures Working hours Emergency procedures and contacts Permit procedures Waste monitoring 11. Site Services: Clarify the following: Site telephone Electricity Water Disruption or connection to existing services Other required 12. Contractor s site organization: Clarify the following: Contractor s accommodation requirements Site access, security, fencing etc Parking Site vehicles and any special requirements Control of mud / dust / noise etc. Fire precautions Deliveries to / from site Name boards / signage Contractor s Site Representative(s) Emergency contacts Contractor / Clerk of Works / Design Team / Project Team as appropriate Design leader Project Team Project Team Page 5 of 6 Team Contractor and others as required

6 Item Title and Content Lead by Notifications of the accidents / H&S and Asbestos regulations etc Location of future meetings 13. Completion and handover procedures 14. Any other business (client, contractor, consultants) 15. Date of next meeting 3.3 PROJECT BOARD MEETINGS The Project Team should outline the requirements for attendance at Project Board meetings and note what is expected from the Design Team, QS, other Consultants and the Main Contractor. Refer to procedure note AB1 Establish Project Board and User Groups 4. OUTPUT An efficient and trouble free start of Main Contract works, all contacts and procedures clarified and a programme of site meeting established Page 6 of 6

ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY

ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE HANDOVER TO UNIVERSITY THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 5 LAST MODIFIED 2 December 2010 DATE PRINTED RIBA stages JK JK 5 ISSUE CERTIFICATE OF PRACTICAL COMPLETION AND INITIATE

More information

FIDIC Contracts. Training Course in English language. May, 25-26, Two days course on:

FIDIC Contracts. Training Course in English language. May, 25-26, Two days course on: FIDIC Contracts Training Course in English language May, 25-26, 2018 Two days course on: FIDIC Module 4 - FIDIC Contracts Management and Administration FIDIC 99 EDITIONS ESSENTIALS FOR WORKING IN INTERNATIONAL

More information

JOB DESCRIPTION. Surveyor Stockbridge Village. CESP (Community Energy Saving Programme) Delivery Team Villages Housing

JOB DESCRIPTION. Surveyor Stockbridge Village. CESP (Community Energy Saving Programme) Delivery Team Villages Housing JOB DESCRIPTION POST: SECTION: RESPONSIBLE TO: Surveyor Stockbridge Village CESP (Community Energy Saving Programme) Delivery Team Villages Housing CESP Project Manager / Head of Asset Management Objectives

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering Design and construct Superseding (in part) NZS 3910:2003 NZS 3916:2013 COMMITTEE REPRESENTATION This Standard was prepared

More information

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE The purpose of the health and safety questionnaire is to provide Clients with assurances that all companies on

More information

Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation

Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation Mini Tender Questionnaire for Subcontractors Section B involves a questionnaire oriented around the provision of key

More information

Registered as a Scottish Charity - No. SC Job Description

Registered as a Scottish Charity - No. SC Job Description Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Salary: Reports To: Neighbourhood Maintenance Surveyor Assets and Investment Selkirk Grade 8, salary

More information

Box Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments

Box Clever Consulting. Executive Summary Project Report. June Strand Plaza. Liverpool. for. Primesite Developments Box Clever Consulting Executive Summary Project Report June 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 06/07/17 Strand Plaza - Liverpool Status Report @ End of

More information

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1.

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1. PROBUILD SUBCONTRACTOR QUALITY MANAGEMENT GUIDE Section Two Project Specific Quality Management Plans Version No 1. PREFACE This document has been developed to assist subcontractors to meet Probuild s

More information

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management

COSBEDMO19 - SQA Unit Code FM75 04 Manage project completion and handover in built environment design management Manage project completion and handover in built environment design Overview This unit applies to designers who are engaged in projects at site level at the handover stage and who are responsible for completing

More information

Procedure for Stage 8 Post Project Evaluation. Procedure No. 017

Procedure for Stage 8 Post Project Evaluation. Procedure No. 017 Procedure for Stage 8 Post Project Evaluation Procedure No. 017 Print Name Title Date Prepared by C Hanratty CATSO 16 th Feb 05 Reviewed by Corporate Authorisation J.G. MacNamara J.G. MacNamara T.S.O.

More information

Managing Contractors (Scotland)

Managing Contractors (Scotland) Managing Contractors (Scotland) University Health and Safety Policy Author: Health & Safety Services 1 Managing Contractors Procedures (Scotland) to support University Health and Safety Policy CONTENT

More information

Filey Town Council Council Offices 52A Queen Street Filey North Yorkshire YO14 9HE TEL:

Filey Town Council Council Offices 52A Queen Street Filey North Yorkshire YO14 9HE TEL: JOB DESCRIPTION TOWN CLERK/RESPONSIBLE FINANCIAL OFFICER The Town Clerk will be the Proper Officer of the Council and as such is under a statutory duty to carry out all the functions, and in particular

More information

Appendix C Having used FIDIC 99 as the basis for identifying the modifications made within the analyzed contracts, it was necessary to understand the

Appendix C Having used FIDIC 99 as the basis for identifying the modifications made within the analyzed contracts, it was necessary to understand the Appendix C Having used FIDIC 99 as the basis for identifying the modifications made within the analyzed contracts, it was necessary to understand the differences between FIDIC 87 and FIDIC 99. The below

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT:

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT: A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V.2 10.5.17) PROJECT: Oakdale Primary School, Peterborough Extension, Refurbishments and Associated Works.

More information

PRACTICE NOTES FOR QUANTITY SURVEYORS

PRACTICE NOTES FOR QUANTITY SURVEYORS PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong

More information

Quantity Surveying and Construction

Quantity Surveying and Construction Quantity Surveying and Construction August 2014 Pathway guide Published by: RICS, Parliament Square, London SW1P 3AD. All rights in this publication, including full copyright or publishing right, content

More information

Level 6 NVQ Diploma in Construction Site Management (Construction)

Level 6 NVQ Diploma in Construction Site Management (Construction) Level 6 NVQ Diploma in Construction Site Management (Construction) Qualification Specification ProQual 2014 Contents Page Introduction 3 The Qualifications and Credit Framework (QCF) 3 Qualification profile

More information

ESTATES DEPARTMENT Health & Safety Manager

ESTATES DEPARTMENT Health & Safety Manager ESTATES DEPARTMENT Health & Safety Manager Job reference number: 205-17 Job Description Post Title Health & Safety Manager Grade 7 Responsible to Responsible for Liaises with Head of Estates (RCM) N/A

More information

Protocol for Consultation with Trade Union Safety representatives.

Protocol for Consultation with Trade Union Safety representatives. Protocol for Consultation with Trade Union Safety representatives. Introduction The purpose of this protocol is to outline the arrangements within the School for consulting and cooperating with Trade Union

More information

Urzgan Rural Access Program

Urzgan Rural Access Program 00083939 Urzgan Rural Access Program Rehabilitation of Gravel Road from Surkhliz to Chinartu, Ch. (18+000-27+000)km in Urzgan Province of Afghanistan Lot 3 United Nations Office for Project Services (

More information

Job Profile QUANTITY SURVEYOR (QS-GB-N14)

Job Profile QUANTITY SURVEYOR (QS-GB-N14) Job Profile QUANTITY SURVEYOR (QS-GB-N14) Job Title Reporting to No. Reports Business Unit Location Contract Type Salary Additional Benefits Quantity Surveyor Commercial Manager / Managing Quantity Surveyor

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 09.03.2016 Project phases time Inception initiation Preliminary analysis

More information

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients December 2008 Contents Page Contents...2 Introduction...3 The Process Flowchart...4 Project Registration: Step 1...5

More information

Box Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments

Box Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments Box Clever Consulting Executive Summary Project Report July 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 05/08/17 Strand Plaza - Liverpool Status Report @ End of

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

Unit: CPC 421 Manage contracts to achieve outcomes (Commissioning, Procurement and Contracting)

Unit: CPC 421 Manage contracts to achieve outcomes (Commissioning, Procurement and Contracting) Unit: CPC 421 Manage contracts to achieve outcomes (Commissioning, Procurement and Contracting) Key Purpose The key purpose identified for those working in commissioning, procurement and contracting is

More information

Establish health and safety requirements

Establish health and safety requirements 16. 1for Establish health and safety requirements projects The Health and Safety at Work Act (Section 2 (2) (a)) requires that employers should provide and maintain plant and systems of work that are,

More information

Path Construction Project Checklist

Path Construction Project Checklist Paths for All Factsheet 5.7 Updated: May 2015 Original version: 2002 Path Construction Project Checklist This factsheet provides a quick checklist of all the main points and issues to consider when carrying

More information

Asbestos Management Plan

Asbestos Management Plan Health and Safety Services Asbestos Management Plan Policy, Organisation and Arrangements Sean Callaghan Issue number 2 April 2013 Contents Contents 1.1. Introduction... 4 1.2. Policy Statement... 4 2

More information

Project Management Techniques

Project Management Techniques ALUMASA QATAR Project Management Techniques A project is usually one time effort. Although similar work may have been done previously, every project has its own features and therefore is of non-repetitive

More information

DATE ADVERTISED: 05 SEPTEMBER 2017 VACANCY PROPERTIES UNIT: FACILITIES MANAGER X 3 (BUTTERWORTH, MTHATHA AND EAST LONDON)

DATE ADVERTISED: 05 SEPTEMBER 2017 VACANCY PROPERTIES UNIT: FACILITIES MANAGER X 3 (BUTTERWORTH, MTHATHA AND EAST LONDON) DATE ADVERTISED: 05 SEPTEMBER 2017 VACANCY PROPERTIES UNIT: FACILITIES MANAGER X 3 (BUTTERWORTH, MTHATHA AND EAST LONDON) GRADE 14: R 454 924 - R 556 018 (Total Cost to Company) The Properties Facilities

More information

WORK PLACEMENT AGREEMENT

WORK PLACEMENT AGREEMENT WORK PLACEMENT AGREEMENT Thank you for choosing a Ravensbourne student for work placement. We hope the placement experience will be positive and that you will want to work with us on a continuing basis.

More information

Managing health and safety in construction

Managing health and safety in construction Managing health and safety in construction Construction (Design and Management) s 2007 Approved Code of Practice Managing health and safety in construction Health and Safety Construction (Design and Management)

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17 Quality Manual DRAFT Page 1 of 17 Document Acceptance and Release Notice This is Revision A1 of the East Coast Designer Builders Quality Manual. The Manual is a managed document. For identification of

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

CHAS Assessment Standards

CHAS Assessment Standards CHAS Assessment Standards Section 1 - All Prosecutions or Enforcement Notices The Supplier has provided details of any enforcement notices or prosecutions served on them in the last three years by the

More information

Site Safety Plus. Site Management Safety Training Scheme (SMSTS) Course appendix G

Site Safety Plus. Site Management Safety Training Scheme (SMSTS) Course appendix G Site Safety Plus Site Management Safety Training Scheme (SMSTS) Course appendix G 1. Introduction 2. Aims and objectives 3. Entry requirements 4. Assessment 5. Delegate numbers 6. Course duration and attendance

More information

East Riding of Yorkshire Council Corporate Health and Safety Policy

East Riding of Yorkshire Council Corporate Health and Safety Policy East Riding of Yorkshire Council Corporate Health and Safety Policy Lead Directorate and Service: Corporate Resources - Human Resources, Safety Services Effective Date: June 2016 Date Due for Review: June

More information

ASBESTOS MANAGEMENT PLAN. July Document Version: 1

ASBESTOS MANAGEMENT PLAN. July Document Version: 1 July 2017 Document Version: 1 Document Control Document ID: Put: \root directory \path here Version No. Date Revision Details Author Endorsed Approved 1.0 28 th July 2017 VLD AM SW Page 2 FOREWORD The

More information

CDM-C Guidance. Five or more employees. Health and Safety 1. CMD-C Guidance Notes V

CDM-C Guidance. Five or more employees. Health and Safety 1. CMD-C Guidance Notes V CDM-C Guidance Five or more employees Health and Safety 1 CONTENTS INTRODUCTION...4 Further reading / additional resources...4 QUESTION 1: POLICY AND ORGANISATION...5 Guidance...5 What you need to provide...6

More information

GENERAL TERMS AND CONDITIONS OF SERVICE CONTRACTS OF DRUKARNIA ELLERT SP. Z O.O. (hereinafter: the Printing House) 1 Definitions

GENERAL TERMS AND CONDITIONS OF SERVICE CONTRACTS OF DRUKARNIA ELLERT SP. Z O.O. (hereinafter: the Printing House) 1 Definitions GENERAL TERMS AND CONDITIONS OF SERVICE CONTRACTS (hereinafter: GTC) OF DRUKARNIA ELLERT SP. Z O.O. (hereinafter: the Printing House) 1 Definitions Contract a contract whereby the Customer orders the production

More information

Tender Document and Specifications for Council Property Assorted Painting and Decorating between Parks and Recreation and Contractor.

Tender Document and Specifications for Council Property Assorted Painting and Decorating between Parks and Recreation and Contractor. Tender Document and Specifications for Council Property Assorted Painting and between Parks and Recreation and Contractor. CONTRACT 2014-02 November 2014 CONTENTS Instruction to Tenderers... 3 Foreword

More information

CANDIDATE BRIEF. Student Intern - Building Surveyor, Facilities Directorate

CANDIDATE BRIEF. Student Intern - Building Surveyor, Facilities Directorate CANDIDATE BRIEF Student Intern - Building Surveyor, Facilities Directorate Salary: Grade 3 ( 16,654 p.a.) Reference: FDEST1108 Closing date: 1 March 2018 Interviews: 15 March 2018 12 month fixed term:

More information

NEC3 Engineering & Construction Contract Role of the Project Manager

NEC3 Engineering & Construction Contract Role of the Project Manager NEC3 Engineering & Construction Contract Role of the Project Manager Ian Hedley BSc (Hons) MRICS MACostE MAPM Wednesday 17 th September 2014 Ramada Encore, Haydock 1 Aims Background to NEC Contracts Identify

More information

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN Revision Date Nature of Revision Prepared by Approved by 1 July 2014 Approved Plan Jon Fahie This, the University

More information

Quality Assurance Manual

Quality Assurance Manual Quality Assurance Manual Current Electrical is committed to leading the market in satisfying customer needs by providing versatile and innovative electrical and control solutions We take pride in the ability

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 04.03.2015 Project phases time Inception initiation Preliminary analysis

More information

CIVIL ENGINEERING CONTRACT ADMINISTRATION AND CONTROL

CIVIL ENGINEERING CONTRACT ADMINISTRATION AND CONTROL CIVIL ENGINEERING CONTRACT ADMINISTRATION AND CONTROL By the same author Civil Engineering Quantities, Third Edition Civil Engineering Specification, Second Edition Building Quantities Explained, Third

More information

Construction (Design and Management) Safety Guidance Document

Construction (Design and Management) Safety Guidance Document Construction (Design and Management) Safety Guidance Document Lead Directorate and Service: Corporate Resources - Human Resources, Safety Services Effective Date: April 2011 Contact Officer/Number Garry

More information

Project Manager Facilities and Development

Project Manager Facilities and Development Date: September 2015 Job Title : Project Manager Department :, Waitemata DHB & & Facilities Management, Auckland DHB Location : Primarily based at North Shore Hospital campus and other WDHB / ADHB facilities

More information

Nomination and Remuneration Committee Charter

Nomination and Remuneration Committee Charter Charter Nomination and Remuneration Committee Charter Myer Holdings Limited ACN 119 085 602 Myer Holdings Limited PO Box 869J Melbourne VIC 3001 Australia Telephone +61 3 8667 6000 www.myer.com.au Nomination

More information

JOB DESCRIPTION. Contract Supervisor. Contract Co-ordinator. Liaison Officers

JOB DESCRIPTION. Contract Supervisor. Contract Co-ordinator. Liaison Officers JOB SCRIPTION JOB TITL: RSPONSIBL TO: PARTMNT/ SCTION: IRCT RPORTS: Contract Supervisor Contract Co-ordinator Asset & Investment irectorate Liaison Officers SALARY ( ): Grade 9 PURPOS OF TH ROL To assist

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

The safe management and control of Temporary Works

The safe management and control of Temporary Works The safe management and control of Temporary Works What are TW s? The HSE describe Temporary Works (TW s) as; an engineered solution that may include any structure, provision for access, item or technique

More information

Occupational Health and Safety Management Manual v2.2

Occupational Health and Safety Management Manual v2.2 Occupational Health and Safety Management Manual v2.2 Written: February 2013 Author: David Seymour, Director of Operations Co Author: Mathew Sprake, Operations Manager Approved: Board of Directors 1. Introduction

More information

Tender Document and Specification

Tender Document and Specification Tender Document and Specification for Council Property Assorted Painting and Decorating between Parks and Recreation and Contractor CONTRACT 2014-02 March 2014 CONTENTS Instruction to Tenderers... 3 Foreword

More information

UNIVERSITY OF SUNDERLAND STANDING ORDERS TENDERING AND CONTRACT PROCEDURES

UNIVERSITY OF SUNDERLAND STANDING ORDERS TENDERING AND CONTRACT PROCEDURES UNIVERSITY OF SUNDERLAND STANDING ORDERS TENDERING AND CONTRACT PROCEDURES Finance and Development Committee Revised February 2010 UNIVERSITY OF SUNDERLAND STANDING ORDERS ON TENDERING AND CONTRACT PROCEDURES

More information

Custom Home Building Proposal

Custom Home Building Proposal Custom Home Building Proposal Scroll down to read the first part of this sample. When purchased, the complete sample is 20 pages long and is written using these Proposal Pack chapters: Cover Letter, Title

More information

28.00 Project Briefing & Procurement

28.00 Project Briefing & Procurement 28.00 Project Briefing & Procurement 28.01 Generally A new building marks a significant investment in the future of the University. For many years hence it will reflect the changing role of the University

More information

Volunteer Placement Scheme Policy

Volunteer Placement Scheme Policy Policy NECA promotes and encourages the participation of Volunteers in all areas of its work. NECA recognises the different but equally valuable contribution of Volunteers in complementing the work of

More information

Designer and CDM Co-ordinator Guidance

Designer and CDM Co-ordinator Guidance Designer and CDM Co-ordinator Guidance Fewer than five employees Health and Safety 1 CONTENTS INTRODUCTION...5 Further reading / additional resources...5 Note to suppliers...6 QUESTION 1: POLICY AND ORGANISATION...8

More information

C D M R e g u l a t i o n s

C D M R e g u l a t i o n s C D M R e g u l a t i o n s 2 0 1 5 CDM Consultancy - Support for Client - Principal Designer - Principal Contractor c l a r i t y t h r o u g h s i m p l i c i t y Reducing the risk to health and safety

More information

Supply to Rancho De Viti Investments Corporation at Maranitawa - Ba (Scheme No. G52/07)

Supply to Rancho De Viti Investments Corporation at Maranitawa - Ba (Scheme No. G52/07) MR 96/2015 Supply to Rancho De Viti Investments Corporation at Maranitawa - (Scheme No. G52/07) Notes: 1. Safety Plan to be included in tender bid. 2. Lineman and Trainee Lineman/Line worker Certificate

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts)

Commencement of Works vs commencement of Works Program (FIDIC Rainbow Conditions of Contracts) Volume (5) Number (8) August 2015 J. Appl. Environ. Biol. Sci., 5(8)55-69, 2015 2015, TextRoad Publication ISSN: 2090-4274 Journal of Applied Environmental and Biological Sciences www.textroad.com Commencement

More information

ESTATES SERVICES. Soft Landings An Introduction

ESTATES SERVICES. Soft Landings An Introduction ESTATES SERVICES Soft Landings An Introduction 2013 Capital Projects - Context Capital projects have responsibility for all new major build and refurbishment projects A major project is a project with

More information

Designer and CDM Co-ordinator Guidance

Designer and CDM Co-ordinator Guidance Designer and CDM Co-ordinator Guidance Five or more employees 1 CONTENTS INTRODUCTION...4 Further reading / additional resources...4 QUESTION 1: POLICY AND ORGANISATION...5 Guidance...5 What you need to

More information

ROYAL COLLEGE OF ART JOB DESCRIPTION. Programme Manager. Director of Buildings and Estates. Background

ROYAL COLLEGE OF ART JOB DESCRIPTION. Programme Manager. Director of Buildings and Estates. Background ROYAL COLLEGE OF ART JOB DESCRIPTION Title: Directorate: Responsible to: Programme Manager Buildings and Estates Director of Buildings and Estates Background The Royal College of Art is the only entirely

More information

ISO 9001:2015 ISO 14001:2015 OHSAS

ISO 9001:2015 ISO 14001:2015 OHSAS JSM Group Management System Manual January 2017 ISO 9001:2015 ISO 14001:2015 OHSAS 18001:2004 National Electricity Registration Scheme (NERS) Fleet Operators Recognition Scheme (FORS) Issue & Amendment

More information

Education Infrastructure Service. Asbestos Management Process

Education Infrastructure Service. Asbestos Management Process Education Infrastructure Service Asbestos Management Process Version 9 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by

More information

UNIVERSITY OF LINCOLN JOB DESCRIPTION

UNIVERSITY OF LINCOLN JOB DESCRIPTION UNIVERSITY OF LINCOLN JOB DESCRIPTION JOB TITLE DEPARTMENT LOCATION Health and Safety Assistant Health and Safety Department Brayford Pool JOB NUMBER HS1006 GRADE 4 DATE June 2017 REPORTS TO Head of Health

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

GreenSquare Job Description Job Title

GreenSquare Job Description Job Title GreenSquare Job Description Team Technical Manager GreenSquare Construction Job Family & level Location Construction Level 6 Swindon Date updated June 2015 JE Score Organisational Structure Reports to

More information

MEMBERSHIP APPLICATION FORM

MEMBERSHIP APPLICATION FORM MASTER BUILDERS BUILD BETTER MEMBERSHIP APPLICATION FORM General / Commercial Contractor Housing Contractor Trade Contractor Trade Supplier Service Provider Affiliate Member Master Builders Association

More information

BISHOP GROSSETESTE UNIVERSITY. Document Administration

BISHOP GROSSETESTE UNIVERSITY. Document Administration BISHOP GROSSETESTE UNIVERSITY Document Administration Document Title: Document Category: Sickness Absence Policy and Procedure Policy and Procedure Version Number: 2 Status: Reason for development: Scope:

More information

Job Application Form

Job Application Form Post Applied for: Date: Job Application Form Please complete this form fully using black ink or type. Please ensure that all sections are completed and that any gaps in the employment history are recorded

More information

CASUAL EMPLOYEE TERMS & CONDITIONS OF EMPLOYMENT

CASUAL EMPLOYEE TERMS & CONDITIONS OF EMPLOYMENT CASUAL EMPLOYEE TERMS & CONDITIONS OF EMPLOYMENT Belljax Pty Ltd as Trustee for Jeden Trust T/A Midwest Labour Pool 1. The Terms and Conditions in this document form the basis for casual employment with

More information

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy.

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy. Bowmer Kirkland & Kirkland & Accommodation Health & Safety Policy December 2013 www.bandk.co.uk Index Policy Statement Page 3 Interaction of Health and Safety Responsibilities Page 5 Organisation Page

More information

Trethowans LLP. Recruitment Agency Preferred Supplier List (PSL) Invitation to Tender

Trethowans LLP. Recruitment Agency Preferred Supplier List (PSL) Invitation to Tender Trethowans LLP Recruitment Agency Preferred Supplier List (PSL) Invitation to Tender 1. Tender Process 1.1. Trethowans LLP ( Firm ) is providing this Invitation to Tender ( ITT ) to various interested

More information

Occupational Health and Safety/Risk Officer. Enquiries: Human Resources Officer APPLICATIONS

Occupational Health and Safety/Risk Officer. Enquiries: Human Resources Officer APPLICATIONS POSITION DESCRIPTION Position Title: Occupational Health and Safety/Risk Officer Position No.: 432 Position Status: Business Unit: Division: Permanent Full Time Organisation Development Governance Date

More information

THIS IS THE HEALTH AND SAFETY POLICY STATEMENT OF GLASGOW KELVIN COLLEGE

THIS IS THE HEALTH AND SAFETY POLICY STATEMENT OF GLASGOW KELVIN COLLEGE THIS IS THE HEALTH AND SAFETY POLICY STATEMENT OF GLASGOW KELVIN COLLEGE Document Control Information Reviewed by the Strategic Management Team: April 2017 of Next Review: April 2018 Approved by the Board

More information

Registered as a Scottish Charity - No. SC Job Description. Grade 8, Salary commences 25,339 per annum

Registered as a Scottish Charity - No. SC Job Description. Grade 8, Salary commences 25,339 per annum Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Salary: Reports To: Asset Safety Officer Assets and Investment Selkirk Grade 8, Salary commences

More information

Division: Planning and Regulation Job Grade: JG4A

Division: Planning and Regulation Job Grade: JG4A Position Title: Position Number: 3032 Division: Planning and Regulation Job Grade: JG4A Unit: Building and Environmental Health Award base: 35 Hours Unit Leader: Manager Building and Environmental Health

More information

Verify Category A Audit Content

Verify Category A Audit Content Verify Category A Audit Content V10.0 Achilles Group Limited, 2014. All rights reserved. Objective The objective of this document is to provide suppliers who have registered for a Verify Category A (V10.0)

More information

Office Base Amiens Street Dublin 1 Moving to Northbank House, Upper Sherriff Street, Late 2016

Office Base Amiens Street Dublin 1 Moving to Northbank House, Upper Sherriff Street, Late 2016 Role: Property Surveyor Office Base 63-66 Amiens Street Dublin 1 Moving to Northbank House, Upper Sherriff Street, Late 2016 (With travelling expected across the East Region) Job Title Reporting to Contract

More information

GreenSquare Job Description Job Title Technical Project Manager Grade Team

GreenSquare Job Description Job Title Technical Project Manager Grade Team GreenSquare Job Description Job Title Technical Project Manager Grade Team Location GreenSquare Construction Swindon Date updated June 2015 JE Score Organisational Structure Reports to Technical Manager.

More information

Manage Deliverables - Construction Step 6 February 2015

Manage Deliverables - Construction Step 6 February 2015 Manage Deliverables - Construction Step 6 February 2015 1 Construction Phase Step 1: Needs Development Step 2: Scope Development Step 3: Selection of Design Team Step 4: Design Phase Step 5: Selection

More information

Corporate Social Responsibility Policy Statement

Corporate Social Responsibility Policy Statement Health and Safety Policy Statement Environmental Policy Statement Corporate Social Responsibility Policy Statement Organisation and Arrangements Created Oct 2012 BT/WS Issue 21, Sept 2017 BT/AT Page 1

More information

Quality Assurance Agreement

Quality Assurance Agreement Quality Assurance Agreement between Preh GmbH, Schweinfurter Strasse 5-9, 97616 Bad Neustadt an der Saale, Germany Preh, - hereinafter referred to as the Customer and, - hereinafter referred to as the

More information

FACT SHEET CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2015 THE PROPERTY PROFESSIONALS AUGUST 2016

FACT SHEET CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2015 THE PROPERTY PROFESSIONALS AUGUST 2016 MANAGEMENT) REGULATIONS forget the Legal Helpline ( members only) uk/uksi//51/pdfs/ uksi_0051_en.pdf CONTEXT The Management) (CDM) Regulations came into force on 6 April and replace the 2007 Regulations.

More information

Capability health procedure for academic support staff

Capability health procedure for academic support staff Capability health procedure for academic support staff Policy The School's policy in relation to sickness absence is to support employees by paying sick pay and investigating absence in conjunction with

More information

Attendance. Employee Policy HR Consult. 1. Policy Statement

Attendance. Employee Policy HR Consult. 1. Policy Statement Attendance 1. Policy Statement Employee Policy HR Consult We value the contribution our employees make to our success and high attendance levels are vital to us continuing to achieve high levels of performance.

More information

FIDIC for PRACTITIONERS TRAINING COURSES Entitled. Module: FIDIC Subcontract

FIDIC for PRACTITIONERS TRAINING COURSES Entitled. Module: FIDIC Subcontract Nestor Bildungsinstitut GmbH Nestor-FIDIC Federation of International Consulting Engineers FIDIC for PRACTITIONERS TRAINING COURSES Entitled Module: FIDIC Subcontract 17 th September 18 th September 2015

More information

Scottish Borders Housing Association

Scottish Borders Housing Association Registered as a Scottish Charity - No. SC030751 Job Description Job Title: Department/Section: Location: Neighbourhood Assistant Customer Services SBHA Head Office Salary: Grade 11 18,281 Reports To: Neighbourhood

More information

Welcome to the Wage Subsidy Orientation. Presenter: Tara Brant Wage Subsidy Case Manager

Welcome to the Wage Subsidy Orientation. Presenter: Tara Brant Wage Subsidy Case Manager Welcome to the Wage Subsidy Orientation Presenter: Tara Brant Wage Subsidy Case Manager Today s Agenda Overview of the program and requirements Examples of how the program works Marketing the program to

More information