Katie Harkless Project Manager-Replacement Washington Gas

Size: px
Start display at page:

Download "Katie Harkless Project Manager-Replacement Washington Gas"

Transcription

1 Cast Iron Renewal Techniqueses Katie Harkless Project Manager-Replacement Washington Gas

2 Washington Gas Overview Serve D.C. and adjoining areas in MD and VA Approximately 1.2M customers 22 gate stations, 2 peak shaving plants, and 1 storage field 2

3 WG Cast Iron Piping DC 428 miles MD- 75 miles VA 17 Miles Total cast iron = 520 miles Replace 5-6 miles annually

4 WG Cast Iron Renewal Techniques Liners Cured-in-place liner U-liner Joint sealants Internal joint sealants External joint sealants Insertion Plastic insertion

5 WG Cast Iron Renewal Techniques Cured- In-Place Liner C d I Pl Li Cured-In-Place Liners WG primarily uses on 12 and larger diameters due to thicker pipe wall Example project Anacostia river rehab project Used liner because wanted to directionally drill but couldn t obtain permit from National Park Service. Remediated 1800 (2-900 lengths)

6 Cured-In-Place Anacostia River Rehab Project Cured-in-place process Disconnect pipe Clean pipe Pre-lining inspection (CCTV) Lining process Post-lining inspection Pressure test Activate the line

7 Anacostia River Rehab Project Background of the Project 16-inch cast iron pipes leaking under river Winter 2009 Replace Option Drill new lines Install new lines through Anacostia Park Complete line replacement Rehabilitation Options Insertion Lining selected as best option

8 River Crossing Location

9 Project Design Concerns Concerns related to depressurizing i of the main and possible water infiltration Double lining considered, first lining to stop water infiltration & second dfor gas carrier Obtaining Permits from Parks Dept Working from Vault Side without dismantling the vault Environmental issues related to dewatering of park side pit

10 Pipeline Inspection Depressurizing i of fthe First tleg of ftwin 16-Inch 16I main Phase I Consideration was given to live camera inspect while simultaneously lowering the gas pressure to witness any water infiltration ti WGL opted not to live camera inspect and depressurized first leg of twin main The pipeline after depressurizing was almost completely dry with only the first two cast iron joints weeping a little water

11 Cured-in-place Lining Technology

12 Pipeline Before Cleaning to Final Product

13 Camera Inspection Working from the park side of the project, the first camera inspection of the pipeline revealed a clean main, except for the last 100ft or so before the drip The debris found was sand like, the amount of debris became greater the closer it came to the drip valve Debris Drip

14 Blast Hose from Vault Side

15 Pipeline Cleaning

16 Cleaning Process

17 Filling the Drip Valve Drip filling Methodology Inserted 2-14-Inch pigs into the bottom of the drip Inserted 90ft of 2-Inch PVC pipe Camera Mixed and poured adhesive into 2-Inch pipe and fill drip (27 Cans used) Observed process through camera 2-14 Pigs

18 Lining Process

19 Lining Process Concrete Vault Sub Station Side Pressure Drum Direction of Lining Drip filled with 2-Pigs & Adhesive Park Side With Steel Sheeting Box

20 Lining Process

21 Clearance Concerns Important: For every two feet (2ft) of additional cover, top of main, The cut-out section of space between the mains MUST increase By one additional foot (1ft) for example, a pipe with 6 feet (6ft) of Cover requires a 7 foot (7ft) cut-out 2-Foot 6ft Section 4FT cover Section to be Lined Utility Requirement 1-Foot

22 Clearance Requirements Side View Pressure Drum 4ft Approx 40ft Long Including Trucks Direction Of Lining 1ft Approx 10-12ft12ft Long

23 Consequences of Misalignment Misalignment at the inversion point creates unsupported liner within the rehabilitated pipeline and a Spot Repair is required after curing Unsupported liner liner Unsupported liner Not enough Space to properly Align hose fitting

24 Loading the Lining

25 Inversion Cone Being Connected to Liner

26 Lining

27 Line Complete Valve Cast iron Joint Half/Pig to support Liner Liner was installed and held pressure PPM maintained positive pressure all night and next day to allow adhesive proper time to fully cure Re-pressurized and tested pipeline Cut open fish mouth valve position Liner Adhesive filled Drip Starline-1000

28 Pipeline Lining Completed

29 Other Challenges - Flooding

30 Other Challenges Freezing and Blizzard

31 Area Restored Liner Project Complete

32 WG Cast Iron Renewal Technique- Other Liners U-liner Internal sealing technique used in the late 1990 s U shaper liner that expands in pipe Useful on straight pipe with no service connections Remediated about 1000 of main

33 WG Cast Iron Renewal Techniques Internal Joint Sealant I t l j i t l t Internal joint sealants Only plausible on 16 diameter and up More cost effective than external joint sealant because don t have to excavate every joint Projected savings of up to 60% over conventional repair methods Example project Embassy Row internal sealing rehab Remediated about 3,300 of 20 cast iron main

34 WG Cast Iron Renewal Techniques Embassy Row Internal Sealing Rehab History of bell and spigot joint leakage Main in good condition Pipe wall thickness =.71 thickness Less expensive than direct bury 11 customer included Embassy residences Textile museum Large homes

35 WG Cast Iron Renewal Techniques Embassy Row Internal Sealing Rehab Sequence of Work Temporarily transfer services to low pressure main Install new 2 main - transfer services Excavations Gas stop-offs Disconnects Internal sealing Air test main Reconnect pipe segments Stop-off to reconnect last segments Service transfers Additional work

36 WG Cast Iron Renewal Techniques Embassy Row Internal Sealing Rehab Mass Ave 24 th St 23 rd St X Phelps Pl X X X X X X X X S ST Fla Ave X Stop-off (7 x 8 ) X - Disconnect (7 x 20 ) X Entry/Exit (7 x 10 )

37 WG Cast Iron Renewal Techniques Georgetown Internal Sealing Rehab Internal Sealing Seals Nitrile rubber Steel retaining bands Process Internal inspection/count Clean/grout joints Put seals and bands in place Expand steel bands Air test each seal Crews worked inside 20 main for 7 days

38

39

40

41 Construction

42 WG Cast Iron Renewal Techniques Embassy Row Internal Sealing Rehab Return To Service Air test at 25 psig for 1 hour Return to pressure at 5-psig increments Leak survey between increments

43 WG Cast Iron Renewal Techniques External Joint Sealant E t l j i t l t External joint sealants Same concept as encapsulation kit Considered a repair, not a renewal Not used for mass replacement, but more for big diameter joint repairs Not as cost effective as internal joint sealants

44 WG Cast Iron Renewal Techniques Plastic Insertion Plastic Insertion Used mostly for small, 8 and below diameter Have done some 16 diameter Convert LP to MP after insertion Practice is to purge before insertion, so not done on live gas Complete about 5 miles of replacement annually using the insertion method

45 Questions?

GAS UTILITY TECHNOLOGY UPDATE

GAS UTILITY TECHNOLOGY UPDATE GAS UTILITY TECHNOLOGY UPDATE NORTHEAST GAS ASSOCIATION 2013 FALL CONFERENCE ULC ROBOTICS www.ulcrobotics.com Who is ULC? We work with energy and utility companies to face infrastructure, technical and

More information

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS 1109.1 DESCRIPTION: ITEM NO. 1109 SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS 1. Installation of sanitary sewer lateral stub outs in sanitary sewer mains serving areas where service did not previously

More information

North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show. Dallas, Texas March 20-24, 2016 WM-T3-01

North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show. Dallas, Texas March 20-24, 2016 WM-T3-01 North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show Dallas, Texas March 20-24, 2016 WM-T3-01 A Comprehensive Understanding of ASTM F3097-15 Standard Practice for Installation

More information

SECTION XXXX POLYMER CONCRETE PUMP STATIONS

SECTION XXXX POLYMER CONCRETE PUMP STATIONS SECTION XXXX POLYMER CONCRETE PUMP STATIONS PART 1 GENERAL 1.1 SUMMARY A. This specification shall govern for the furnishing of all work necessary for installation of polymer concrete pump stations to

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Vacuum Excavation Services. vacuum excavation. services

Vacuum Excavation Services. vacuum excavation. services Vacuum Excavation Services vacuum excavation services Saving time and money is no small feat. In the U.S., the gas industry spends over a billion dollars a year on pipeline rehabilitation. The conventional

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

Inland Pipe Rehabilitation. August 17 OAWWA Canton, OH

Inland Pipe Rehabilitation. August 17 OAWWA Canton, OH Inland Pipe Rehabilitation August 17 OAWWA Canton, OH Presentation Agenda Introduction to IPR IPR Products & Services RS Technik by HammerHead Advanced CIPP Process Spartanburg, SC project review IPR Overview

More information

ENCAPSEAL Safe-T-Seal Advanced Technology External Sealing ENCAPSEAL. Safe-T-Seal. advanced technology external sealing

ENCAPSEAL Safe-T-Seal Advanced Technology External Sealing ENCAPSEAL. Safe-T-Seal. advanced technology external sealing ENCAPSEAL Safe-T-Seal Advanced Technology External Sealing ENCAPSEAL Safe-T-Seal advanced technology external sealing When it comes to leaks, we ve got the problem sealed. Safe-T-Seal Encapsulant ENCAPSEAL

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

SECTION 806 MANHOLE REHABILITATION

SECTION 806 MANHOLE REHABILITATION SECTION 806 MANHOLE REHABILITATION 806-1 DESCRIPTION: This specification consists of all work, materials, labor and equipment required for manhole rehabilitation for the purpose of eliminating infiltration

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 1413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

ITEM NO SLIPLINING SANITARY SEWERS

ITEM NO SLIPLINING SANITARY SEWERS ITEM NO. 1100 SLIPLINING SANITARY SEWERS 1100.1 DESCRIPTION: Sliplining is accomplished by pulling or pushing liner pipe into existing sewers by use of mechanical or hydraulic equipment. Once in place,

More information

SECTION 813 SEWER FLOW CONTROL

SECTION 813 SEWER FLOW CONTROL SECTION 813 SEWER FLOW CONTROL 813-1 DESCRIPTION: Sewer flow control is a set of methods to adjust the flow in the sewer system to allow for inspection, maintenance, repair or replacement. This is accomplished

More information

EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: PLUMBING SECTION: SANITARY WASTE AND VENT PIPING

EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: PLUMBING SECTION: SANITARY WASTE AND VENT PIPING ICC-ES Report PMG-1273 Reissued 01/2018 This report is subject to renewal 01/2019 EVALUATION SUBJECT: HAMMERHEAD CURED-IN- PLACE PIPE (CIPP) LINING SYSTEM DIVISION: 22 00 00 PLUMBING SECTION: 22 13 16

More information

SECTION VI SANITARY SEWERS

SECTION VI SANITARY SEWERS SECTION VI SANITARY SEWERS VI-1. DESIGN GUIDELINES Sewer collection lines and appurtenant structures within the jurisdiction of City of Paso Robles shall be constructed in accordance with plans prepared

More information

WATER LINE IN TUNNELS

WATER LINE IN TUNNELS Section 02517 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Handling, transporting, and installing water line in primary liner tunnels, including invert cleanup and blocking and water line in casings that

More information

Proper Planning & Analysis Results in a Focused, Cost Effective Pipeline Rehab Project Andrew Costa

Proper Planning & Analysis Results in a Focused, Cost Effective Pipeline Rehab Project Andrew Costa Proper Planning & Analysis Results in a Focused, Cost Effective Pipeline Rehab Project Andrew Costa Vice President of Sales, East Region Aegion Corporation WHAT TO EXPECT Front End Planning & Early Stage

More information

Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation

Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Mokapu CIPP Case Study & Innovations in Trenchless Technologies for Wastewater System Rehabilitation Presented by Mike York, Insituform Technologies, Inc. Trenchless v. Dig and Replace What is CIPP? Developed

More information

CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE

CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE CITY OF ODESSA SPECIAL SPECIFICATIONS ITEM 1000 GLASS-FIBER REINFORCED POLYESTER (FRP) REHAB/REPLACEMENT MANHOLE 1000.1 DESCRIPTION These specifications shall govern the furnishing of glass-fiber reinforced

More information

195LiquidsCatalog.

195LiquidsCatalog. 195LiquidsCatalog www.energyu.org www.midwestenergy.org 195 Abnormal Operating Conditions... 3 195-0060 General Abnormal Operating Conditions (CT60)... 3 195-0000 Documentation & Reporting... 3 195-0403

More information

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated.

A. This Section includes sanitary waste and vent piping inside the building and to locations indicated. SECTION 221316 SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

SECTION SANITARY SEWER SYSTEM

SECTION SANITARY SEWER SYSTEM SECTION 02731 SANITARY SEWER SYSTEM PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Sanitary sewer system including necessary accessories indicated on drawings and specified in this section. Contractor

More information

SECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS

SECTION SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS SECTION 02530 - SANITARY SEWERAGE PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

1.02 RELATED WORK: Refer to the following sections for related work:

1.02 RELATED WORK: Refer to the following sections for related work: SECTION 5100 - SANITARY SEWER MAIN PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of sanitary sewer mains and services. Topics include permits and fees, record drawings, pipe materials,

More information

192GasCatalog.

192GasCatalog. 192GasCatalog www.energyu.org www.midwestenergy.org 192-Abnormal Operating Conditions... 4 192-0101 Characteristics and Hazards of Natural Gas... 4 192-0201 Gas Detection and Alarm System Maintenance...

More information

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE SECTION 308 BORING AND JACKING PART 2 MATERIALS 2.2 STEEL CASING PIPE E. Casing pipe length shall conform to City of Meridian Standard Drawing SW1 Casing Length Requirements. 2.4 CARRIER PIPE SKIDS A.

More information

Section WATER LINE IN TUNNELS

Section WATER LINE IN TUNNELS PART 1 GENERAL 1.01 SUMMARY Section 02517 This Section includes handling, transporting, and installing water line in primary liner tunnels, including invert cleanup and blocking and water line in casings

More information

Assessing Salem s Oldest Transmission Main for Seismic Resiliency

Assessing Salem s Oldest Transmission Main for Seismic Resiliency Assessing Salem s Oldest Transmission Main for Seismic Resiliency ASSESSING AND DEVELOPING OPTIONS TO REDUCE VULNERABILITY OF AGING CRITICAL INFRASTRUCTURE Presented by Troy Bowers, PE Jeff Jones, PE PROBLEM

More information

ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES 853.1 DESCRIPTION: This item shall govern the construction of FRP sanitary sewer complete in place and the material therein,

More information

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details

Changes for the. TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details Changes for the 2017 TOHOPEKALIGA WATER AUTHORITY Standards, Specifications and Details The following changes are made to the existing standards and details to clarify or improve existing information.

More information

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant Massachusetts Water Resources Authority Presentation to MWRA Board of Directors Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant March 12, 2014 On-Site Thermal/Power Plant Built in

More information

Large Diameter Pipe Bursting

Large Diameter Pipe Bursting Water Research Foundation Large What Pressure is Pipe Pipe Structural Bursting? Rehabilitation Conference Metropolitan Water District - 700 North Alameda, Los Angeles -January 20, 2016 Large Diameter Pipe

More information

1. C-478 Specification for Precast Reinforced Manhole Sections. 2. D-3034 Specification for Polyvinyl Chloride (PVC) Pipe.

1. C-478 Specification for Precast Reinforced Manhole Sections. 2. D-3034 Specification for Polyvinyl Chloride (PVC) Pipe. SECTION 33 30 00 - SANITARY SEWER PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for furnishing and placing sanitary sewer pipe, laterals, stubs, and appurtenances. The pipe

More information

CITY OF BRANSON MUNICIPLE CODE Chapter 18 BUILDINGS AND BUILDING REGULATIONS ARTICLE V. RESIDENTIAL CODE

CITY OF BRANSON MUNICIPLE CODE Chapter 18 BUILDINGS AND BUILDING REGULATIONS ARTICLE V. RESIDENTIAL CODE CITY OF BRANSON MUNICIPLE CODE Chapter 18 BUILDINGS AND BUILDING REGULATIONS ARTICLE V. RESIDENTIAL CODE Sec. 18-103. - International Residential Code. (a) Adopted. The International Residential Code,

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

Todd Eising, PE, Utilities Section Manager Environmental & Water Resources Department, City of Folsom

Todd Eising, PE, Utilities Section Manager Environmental & Water Resources Department, City of Folsom Todd Eising, PE, Utilities Section Manager Environmental & Water Resources Department, City of Folsom Sean Maguire, PE, Project Manager Kennedy/Jenks Consultants Cindy Preuss, PE, Senior Project Manager

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES

San Antonio Water System Standard Specifications for Construction ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES ITEM NO. 853 SANITARY SEWER GLASS-FIBER REINFORCED POLYESTER (FRP) MANHOLES 853.1 DESCRIPTION: This item shall govern the construction of FRP sanitary sewer complete in place and the material therein,

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.PROV 602 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF ELECTRICAL CHAMBERS TABLE OF CONTENTS 602.01 SCOPE 602.02 REFERENCES 602.03 DEFINITIONS

More information

SECTION FACILITY SANITARY SEWERS

SECTION FACILITY SANITARY SEWERS SECTION 22 13 13 FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL

SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL SECTION C1 DUCTILE IRON PIPE AND FITTINGS GENERAL This section covers the furnishing and installation of ductile iron water pipe, fittings, thrust restraint and pipe disinfection. Ductile Iron Pipe MATERIALS

More information

UNDERGROUND TECHNOLOGY. Product Update. By Frank Russo

UNDERGROUND TECHNOLOGY. Product Update. By Frank Russo UNDERGROUND TECHNOLOGY Product Update By Frank Russo FULL POWERED SYSTEMS MOUNTED ON A 25,950 POUND GVWR (NON-CDL) CHASSIS 1,100 SCFM Vacuum system Filtration System that never needs Cleaning or Maintenance

More information

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS

ARTICLE 26 UTILITY LINE INSTALLATION REQUIREMENTS UTILITY LINE INSTALLATION REQUIREMENTS Index 26.01 JACK AND BORE OPERATIONS 26.02 PRESSURE PIPE RESTRAINT 26.03 PRESSURE CONNECTION BACK TO TABLE OF CONTENTS Section 26.01 JACK AND BORE OPERATIONS 26.01.01

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

CONSTRUCTION PROCEDURE

CONSTRUCTION PROCEDURE ARTICLE X CONSTRUCTION PROCEDURE Section 1001 General Construction Specifications Sewers shall be constructed in accordance with the requirements of the latest editions of the "State of Ohio, Department

More information

Transmission Pipeline Opportunities. Advancing Project Development in India through Public Private Partnerships

Transmission Pipeline Opportunities. Advancing Project Development in India through Public Private Partnerships Transmission Pipeline Opportunities Advancing Project Development in India through Public Private Partnerships 22 23 February, 2007 Pipeline Maintenance and Repair: Agenda Methane Losses from Pipeline

More information

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections.

SANITARY SEWERS. B. Construct or relocate building sanitary sewer services, stubs, and connections. SANITARY SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sanitary Sewer Gravity Mains B. Sanitary Sewer Force Mains C. Sanitary Sewer Services 1.02 DESCRIPTION OF WORK A. Construct sanitary sewer gravity

More information

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS

FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS FOX METRO WATER RECLAMATION DISTRICT MANHOLE / SEWER PIPE MATERIALS AND INSTALLATION SPECIFICATIONS MATERIALS 1. PIPE & FITTINGS Rev: 3/26/18 Pipe and fittings used in sanitary sewer construction shall

More information

Key I/I Reduction Plan Components

Key I/I Reduction Plan Components MARCH 24, 2015 Brad D. Werner, P.E. Key I/I Reduction Plan Components Understanding of the Collection System Developing solid Ordinances and Policies Long-Range Plan Development Capital Project Implementation

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

SECTION 8 SEPARATION OF LINES

SECTION 8 SEPARATION OF LINES SECTION 8 SEPARATION OF LINES 8.01 INDEX 8.01 INDEX 8.02 PURPOSE 8.03 DEFINITIONS 8.04 SEWER SEPARATION 8.05 NON-POTABLE SEPARATION 8.06 REFERENCES 8.02 PURPOSE This section states the requirements and

More information

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa).

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water (30 kpa). SECTION 221313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

PIPE AND FITTINGS. Submit product information sheet for joint restraint system to be used.

PIPE AND FITTINGS. Submit product information sheet for joint restraint system to be used. PIPE AND FITTINGS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Pipe B. Fittings C. Special Fittings D. Pipeline Accessories 1.02 DESCRIPTION OF WORK Construct water mains and building service pipes. 1.03

More information

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water

More information

Corrosion Rate Monitoring in Pipeline Casings. Jamey Hilleary Elecsys Corporation 846 North Mart-Way Ct. Olathe, KS, USA

Corrosion Rate Monitoring in Pipeline Casings. Jamey Hilleary Elecsys Corporation 846 North Mart-Way Ct. Olathe, KS, USA Corrosion Rate Monitoring in Pipeline Casings Jamey Hilleary Elecsys Corporation 846 North Mart-Way Ct. Olathe, KS, 66061 USA Jerry DeWitt Enbridge Energy Partners 1500 West Main St. Griffith, IN 46319

More information

Fiber Reinforced Cured-in-Place Rehabilitation Under an Interstate

Fiber Reinforced Cured-in-Place Rehabilitation Under an Interstate Fiber Reinforced Cured-in-Place Rehabilitation Under an Interstate UCT Conference - February 2017 Presented By Chantal Evans Representing Owner Jonathan Stathis/Cedar City Owner and owner issues Cedar

More information

Fully Structural Renewal of 39-inch PCCP Water Transmission Main with Swagelining and HDPE

Fully Structural Renewal of 39-inch PCCP Water Transmission Main with Swagelining and HDPE Caribbean Water & Wastewater Conference 2015 Topic: Water & Wastewater Pipeline Rehabilitation, Trenchless Technology Fully Structural Renewal of 39-inch PCCP Water Transmission Main with Swagelining and

More information

Geopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure

Geopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure Geopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure Dwight Silva Business Development Manager IPR, Great Lakes Geopolymers: Structural Rehabilitation Solution

More information

Service Lateral Rehabilitation Using Cured-In-Place-Pipe (CIPP)

Service Lateral Rehabilitation Using Cured-In-Place-Pipe (CIPP) THE TOTAL SOURCE Service Lateral Rehabilitation Using Cured-In-Place-Pipe (CIPP) Brendan Doyle BLD Services, LLC Introduction Intent, to provide information on: Lateral preparation Lateral CCTV Inspection

More information

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015

Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings. Clean & Safe Drinking Water Workshop. Wednesday, March 25, 2015 Innovation in Joint Restraint Systems for PVC Pressure Pipe and Fittings Clean & Safe Drinking Water Workshop Wednesday, March 25, 2015 Thrust forces Gasketed joints are made to seal and not to restrain,

More information

CONSTRUCTION PRODUCT MARKETING

CONSTRUCTION PRODUCT MARKETING CONSTRUCTION PRODUCT MARKETING You Have Infrastructure Needs. We Have Infrastructure Solutions. OVERVIEW Construction Product Marketing, LLC, offers a unique combination of Product Knowledge, Engineering

More information

STANDARD SPECIFICATIONS SECTION JACKED CASING

STANDARD SPECIFICATIONS SECTION JACKED CASING STANDARD SPECIFICATIONS SECTION 02315 JACKED CASING PART 1 - GENERAL A. Description Tunneling method by jacked casing, directional drilling, or a tunnel boring machine, for highway, railroad, creek, and

More information

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water.

A. Gravity-Flow, Nonpressure, Drainage-Piping Pressure Rating: 10-foot head of water. SECTION 22 1313 - FACILITY SANITARY SEWERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Assessment Methods For Large Diameter Water & Sewer Pressure Pipelines

Assessment Methods For Large Diameter Water & Sewer Pressure Pipelines Assessment Methods For Large Diameter Water & Sewer Pressure Pipelines Procrastinator s Workshop Thursday, December 12, 2013 Presented by: Michael J. Livermore Midwest Regional Manager Solutions for Sustainable

More information

Sullivan Lake Cold Water Intake. Pend Oreille PUD No. 1 of Pend Oreille County, WA

Sullivan Lake Cold Water Intake. Pend Oreille PUD No. 1 of Pend Oreille County, WA Sullivan Lake Cold Water Intake Pend Oreille PUD No. 1 of Pend Oreille County, WA April 7, 2016 Project Location Sullivan Lake Project Location Pend Oreille River Sullivan Lake Project Team Project Team

More information

An Innovative Solution for the Repair of the Sepulveda Feeder By: Michael McReynolds P.E. 1

An Innovative Solution for the Repair of the Sepulveda Feeder By: Michael McReynolds P.E. 1 An Innovative Solution for the Repair of the Sepulveda Feeder By: Michael P.E. 1 Abstract In January 1998, a routine inspection of the Sepulveda Feeder revealed that the 3.81 meter (150 ) diameter prestressed

More information

Advances in Condition Assessment Technologies for Pipelines

Advances in Condition Assessment Technologies for Pipelines Advances in Condition Assessment Technologies for Pipelines March, 2012 Cliff Jones Wachs Water Services Condition Assessment All pipes/ pipe materials leak All pipes can break 1 in 10 leaks will result

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Installation Guide. PrivacyShield Outdoor Enclosure

Installation Guide. PrivacyShield Outdoor Enclosure Installation Guide PrivacyShield Outdoor Enclosure Table of Contents 1.0 Introduction... 2 2.0 Materials, Delivery & Tools... 2 3.0 Layout and Post Locations. 3 4.0 Foundations... 5 5.0 PVC Installation....

More information

Specification Guidelines for Testing and Sealing Lateral Connections and Lateral Service Lines in Sanitary Sewer Systems

Specification Guidelines for Testing and Sealing Lateral Connections and Lateral Service Lines in Sanitary Sewer Systems Specification The information contained in the document is property of Avanti International. Avanti offers the following verbiage as a technical reference to assist in the creation of specifications for

More information

NEW CONTRACT STRUCTURE LEADS TO OPTIMUM SEWER REHABILITATION PROGRAM

NEW CONTRACT STRUCTURE LEADS TO OPTIMUM SEWER REHABILITATION PROGRAM John Monro Interflow Pty Limited Abstract: NEW CONTRACT STRUCTURE LEADS TO OPTIMUM SEWER REHABILITATION PROGRAM Being the region s largest Water Corporation, Sydney Water maintains an extensive program

More information

PIPELINE CONDITION ASSESSMENT & CLEANING DEVIL IS IN THE DETAILS CITY OF DE SOTO, KANSAS RAW WATER MAIN

PIPELINE CONDITION ASSESSMENT & CLEANING DEVIL IS IN THE DETAILS CITY OF DE SOTO, KANSAS RAW WATER MAIN PIPELINE CONDITION ASSESSMENT & CLEANING DEVIL IS IN THE DETAILS CITY OF DE SOTO, KANSAS RAW WATER MAIN Lisa S. Douglas, PE Division Manager Water Services Ace Pipe Cleaning, Inc. CASE STUDY OVERVIEW HISTORY

More information

Service Lateral Rehabilitation

Service Lateral Rehabilitation THE TOTAL SOURCE Service Lateral Rehabilitation Jacob Trapani BLD Services, LLC Introduction Intent, to provide information on: Lateral rehabilitation Sealing options Studies have shown that 40% to 70%

More information

SECTION XXXXX CHEMICAL GROUTING

SECTION XXXXX CHEMICAL GROUTING SECTION XXXXX CHEMICAL GROUTING PART 1 -- GENERAL 1.01 SCOPE OF WORK A. Provide all labor, materials, accessories, equipment, and tools required for the rehabilitation, infiltration reduction, and root

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS

DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS DUCTILE IRON PIPES AND FITTINGS DETAILED PRODUCTS SPECIFICATIONS General All Materials shall be EN, ISO or equivalent standard and shall be supplied from approved manufacturers. According to the International

More information

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems.

This section includes materials and installation of ductile-iron pipe and fittings for potable and recycled water systems. NORTH MARIN WATER DISTRICT STANDARD SPECIFICATIONS SECTION 15056 DUCTILE-IRON PIPE AND FITTINGS PART 1 GENERAL 1.01 DESCRIPTION This section includes materials and installation of ductile-iron pipe and

More information

INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS

INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS 1 of 5 8/1/2013 2:10 PM INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS Project Location and Description Glen Mayberry, Project Manager Roy F. Weston, Houston, TX The project is in

More information

3 TM Scotchkote TM Spray in Place Pipe 269 Coating. Case Study: Syracuse, New York

3 TM Scotchkote TM Spray in Place Pipe 269 Coating. Case Study: Syracuse, New York 3 TM Scotchkote TM Spray in Place Pipe 269 Coating Case Study: Syracuse, New York Client: City of Syracuse Department of Water 101 North Beech Street Syracuse, NY 13210 Contact: Eric Murdock, P.E. Chief

More information

SANITARY WASTE AND VENT PIPING

SANITARY WASTE AND VENT PIPING SECTION 15420 - SANITARY WASTE AND VENT PIPING PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY

DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY North American Society for Trenchless Technology (NASTT) NO-DIG 2005 Orlando, Florida April 24-27, 2005 DISPUTING THE MYTH OF INFLOW AND INFILTRATION REMOVAL EFFICIENCY Keith Cheek, Manager of Water Distribution

More information

PIPE REHABILITATION. Comply with Division 1 - General Provisions and Covenants, as well as the following:

PIPE REHABILITATION. Comply with Division 1 - General Provisions and Covenants, as well as the following: PIPE REHABILITATION PART 1 - GENERAL 1.01 SECTION INCLUDES A. Sliplining Pipe B. Cured-in-place Pipe Lining C. Deformed/Reformed Pipe Lining D. Folded/Formed Pipe Lining E. Spot Repairs by Pipe Replacement

More information

COMPOSITE WRAP FOR NON-LEAKING PIPELINE DEFECTS

COMPOSITE WRAP FOR NON-LEAKING PIPELINE DEFECTS Lessons Learned From Natural Gas STAR Partners COMPOSITE WRAP FOR NON-LEAKING PIPELINE DEFECTS Executive Summary Composite wrap is a permanent, cost-effective pipeline repair technology, suitable for non-leaking

More information

Wastewater Capital Projects Management Standard Construction Specification. 9.0 Pipe Testing, Inspection and Acceptance

Wastewater Capital Projects Management Standard Construction Specification. 9.0 Pipe Testing, Inspection and Acceptance CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 9.0 Pipe Testing, Inspection and Acceptance 9.1 General In addition to any other

More information

SECTION STORM DRAINAGE

SECTION STORM DRAINAGE SECTION 02720 STORM DRAINAGE PART 1 - GENERAL 1.01 WORK INCLUDED A. Trenching and other excavation. B. Ground water control. C. Pipe bedding. D. Installation of storm drains and appurtenances. E. Installation

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Daytona Beach Pier Building Renovation Jun 2010

Daytona Beach Pier Building Renovation Jun 2010 SECTION 15150 - SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation

SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 2004 Specifications CSJ 1062-04-047 SPECIAL SPECIFICATION 5787 Manhole Rehabilitation 1. Description. Repair, rehabilitate, or replace deteriorated, leaking, or structurally unsound existing sanitary sewer

More information

Beacon Hill Water & Sewer District Standard Specifications

Beacon Hill Water & Sewer District Standard Specifications Beacon Hill Water & Sewer District Standard Specifications STEP Sewer Systems Including: Design Criteria Standard Construction Drawings REVISED JANUARY 2012 Alternative sewer systems must meet the requirements

More information

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore Cured-in-Place Pipe (CIPP) for Pressure Pipe Presented by: Mike Moore CIPP Proven Technology Introduced over 45 years ago Most used trenchless technology for the rehabilitation of gravity flow pipeline

More information

Pipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam

Pipe User Group. Tuesday March 14, Walnut Creek, CA. Matt Wassam Pipe User Group Tuesday March 14, 2017 Walnut Creek, CA Matt Wassam 720-333-4500 Agenda AWWA M-28 liner definitions brief overview What information is required to bid a project? Technology Overview Transmission

More information

I&I Mitigation: Rehabilitation of Sewer Laterals and Sealing the Collection System

I&I Mitigation: Rehabilitation of Sewer Laterals and Sealing the Collection System I&I Mitigation: Rehabilitation of Sewer Laterals and Sealing the Collection System Rick Gage, Vice President of Sales Mike Czipar, Vice President of Business Development Discussion Points Mainline CIPP

More information

SPECIAL SPECIFICATION 5256 Cured-In-Place Pipe (Sanitary Sewer)

SPECIAL SPECIFICATION 5256 Cured-In-Place Pipe (Sanitary Sewer) 2004 Specifications CSJ 0912-71-657 SPECIAL SPECIFICATION 5256 Cured-In-Place Pipe (Sanitary Sewer) 1. Description. Furnish and install cured-in-place pipe. A. Resin-impregnated flexible tubes inserted

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 22 1316 - SANITARY WASTE AND VENT PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01

More information

Bruce Power Pipeline Assessment Workshop. May 31, 2018

Bruce Power Pipeline Assessment Workshop. May 31, 2018 Bruce Power Pipeline Assessment Workshop May 31, 2018 Pure Technologies Over 30 years of experience in pressure pipe assessment and management Provided inspection, assessment, and management of thousands

More information