1 RICS information paper RICS professional information, UK Overview of a 5D BIM project 1st edition 1

2 Acknowledgments RICS would like to thank the following for their contributions to this information paper: Authors Andrew Turner MRICS (Henry Riley LLP) Joe Edwards (Henry Riley LLP) Contributors Rob Cox (Henry Riley LLP) Paul Curran MRICS (Henry Riley LLP) Chris Donachie MRICS (Henry Riley LLP) Matt Haines MRICS (Henry Riley LLP) Steve Hodson (Henry Riley LLP) Gil Newby MRICS (Henry Riley LLP) Emma Sellick MRICS (Henry Riley LLP) This information paper is independent of Autodesk, Inc., and is not authorised by, endorsed by, sponsored by, affiliated with, or otherwise approved by Autodesk, Inc. Autodesk, the Autodesk logo and Revit are registered trademarks or trademarks of Autodesk, Inc., and/or its subsidiaries and/or affiliates in the USA and/or other countries. Published by the Royal Institution of Chartered Surveyors (RICS) Parliament Square London SW1P 3AD UK No responsibility for loss or damage caused to any person acting or refraining from action as a result of the material included in this publication can be accepted by the authors or RICS. Produced by the Commercial Property working group of the Royal Institution of Chartered Surveyors. ISBN TBC Royal Institution of Chartered Surveyors (RICS) Copyright in all or part of this publication rests with RICS. No part of this work may be reproduced or used in any form or by any means including graphic, electronic, or mechanical, including photocopying, recording, taping or web distribution, without the written permission of RICS or in line with the rules of an existing licence. 2

3 Contents Acknowledgments... 2 RICS information papers 4 1 Introduction Project details Key problems identified, process and solution pre-tender Understanding the role of the quantity surveyor in relation to 5D BIM Lack of 5D case studies Level of detail and level of information Agreeing on an execution plan Naming protocols Agreement of data drops with the design team Objects and naming conventions Use of NRM Automatic quantification and understanding of costing software Object detail versus cost detail Coordination and benchmarking with the client s existing cost model Coordination of design detail Importance of quality assurance Tender inclusions Post-tender review Mid-tender interview feedback Tender analysis and contractor engagement Contractor feedback Issues encountered Lessons learnt Starting a BIM journey Use of NRM in a BIM environment Tender period: next steps Information (BIM) Manager and next steps for the quantity surveyor Glossary 22 Bibliography

4 RICS information papers This is an information paper. Information papers are intended to provide information and explanation to RICS members on specific topics of relevance to the profession. The function of this paper is not to recommend or advise on professional procedure to be followed by members. It is, however, relevant to professional competence to the extent that members should be up to date and have knowledge of information papers within a reasonable time of their coming into effect. Members should note that when an allegation of professional negligence is made against a surveyor, a court or tribunal may take account of any relevant information papers published by RICS in deciding whether or not the member has acted with reasonable competence. This information paper is believed to reflect case law and legislation applicable at its date of publication. It is the member's responsibility to establish if any changes in case law or legislation after the publication date have an impact on the guidance or information in this document. Document status defined RICS produce a range of professional guidance and standards products. These have been defined in the table below. This document is an information paper. Type of document Definition Status Standard International Standard Practice Statement An international high level principle based standard developed in collaboration with other relevant bodies Mandatory RICS statement practice Document that provides members with mandatory requirements under Rule 4 of the Rules of Conduct for members Mandatory Guidance RICS Code of Practice Document approved by RICS, and endorsed by another professional body/stakeholder that provides users with recommendations for accepted good practice as followed by conscientious practitioners Mandatory or recommended good practice (will be confirmed in the document itself) RICS Guidance Note (GN) Document that provides users with recommendations for accepted good practice as followed by competent and conscientious practitioners Recommended practice good RICS Paper (IP) Information Practice based information that provides users with the latest information and/or research Information explanatory commentary and/or 4

5 1 Introduction Through consultation with RICS, Henry Riley LLP was invited to write an information paper based on its experience of 5D building information modelling (BIM) throughout 2012 and 2013, with particular focus on a project in which an RICS New rules of measurement: Order of cost estimating and cost planning for capital building works (NRM 1) pricing document based on quantification from a BIM model was issued for tender. Henry Riley LLP has been active in the BIM environment since 2011 and has continued to further its understanding of BIM, with a particular focus on cost management. For Henry Riley the journey was slow-going due to various factors which are reviewed within this information paper, but through perseverance toward its goal to be able to automate a quantified BIM model in conjunction with cost databases, Henry Riley managed to develop its learnings and produce its first NRM BIM tender pricing document. This information paper overviews a Henry Riley 5D BIM project delivered during the procurement stage, as described in PAS :2013 Specification for information management for the capital/delivery phase of construction projects using building information modelling (BSI, 2013) (Figure 2: The information delivery cycle). This information paper is split loosely into chronological sections documenting the project from outset to issue of an NRM BIM tender and tender analysis stage. Note that this information paper has been written to help small to medium enterprises (SMEs) starting or having recently started their BIM journey (please refer to for more information). This information paper tries to minimise BIM jargon where possible to help new BIM adopters. However, where technical terms have been used please see the glossary for definitions and for further details on BIM terminology refer to PAS 1192:2, a free downloadable copy of which can be found on 5

6 2 Project details Henry Riley was appointed as the project quantity surveyor on this project by a key client and worked closely with them over 18 months to help develop their BIM strategy, processes and protocols. As such it was a learning experience for all involved, with the skills and expertise of those involved developing along the way. Key details of the project: Mixed-use new build. Brownfield site. JCT Design and Build contract. Client standard amendments. Client Employers Information Requirements (EIRs). Construction Industry Council (CIC) BIM Protocol. Design and build procurement. Tendering on stage 3/4 of 2013 RIBA digital Plan of Work. Design team included: o architect o structural engineer o mechanical and electrical designer/contractor; and o sprinkler designer Pricing document: NRM 1 formal cost plan 2. 6

7 3 Key problems identified, process and solution pre-tender Based on the experiences Henry Riley LLP gained over an 18-month period, the company was invited to be part of a BIM trial, working to a client standard BIM procedure, alongside other disciplines. Henry Riley s role was to produce a pricing document for detailed tender analysis, but using a design and build procurement method. Prior to commencing this project a number of issues had been noted when working within a BIM environment. The issues concerned included: understanding the role of the quantity surveyor in relation to 5D BIM a lack of 5D case studies the level of detail and level of information agreeing on an execution plan naming protocols agreement of data drops with the design team objects and naming conventions use of NRM automatic quantification and understanding of costing software object detail versus cost detail coordination and benchmarking with the client s existing cost model coordination of design detail the importance of quality assurance; and tender inclusions. Each of the issues identified posed their own risks and needed to be overcome in order for a successful tender pricing document to be produced. 3.1 Understanding the role of the quantity surveyor in relation to 5D BIM It is important to understand how the role of the quantity surveyor could change or adapt in the future; this is because the direction of the industry is still being defined and developed in line with level 2 and 3 principles of BIM. Henry Riley took the approach to develop a number of themes associated with 5D BIM: quantification from models, including automatic updated quantification once rules for sectors, clients and pricing methods have been established using NRM standards in conjunction with BIM models (noting client-specific requirements where necessary) library management: o o applying rate libraries to the quantified information; and creating cost databases per sector or client the ability to file share with design team and contractors alike; and improved benchmarking capability o o moving away from detailed measurement and spending more time on improving value; and understanding where value can be improved and understanding this earlier in the project timeline, ensuring savings can be achieved through the design development. 7

8 If these points can be achieved, it enables a serious discussion about the Government Construction Strategy efficiency stretch of 20 per cent. It is clear that 20 per cent of waste can be saved during construction if the designs used do not contain inherent clashes that could be prevented. However, the industry could also be able to save 20 per cent on the pre-tender period, not in terms of fees, but in what is being designed and its associated outturn cost, as a project s design principles become leaner at tender and construction commencement. It appears that the future of quantity surveying in the short to medium term will be, much as it is now, with a quantity surveyor providing detailed estimates and pricing documents based on design information. There could be a shift away from detailed measurement by hand but this, at least in the short term, will be replaced by detailed quality assurance procedures to ensure the information is being interpreted correctly. Furthermore, the quality assurance role will become vital to the project team, as the quantity surveyor will be the first to use the information rather than calculate it and initially this will be a time-consuming role. Finally, a bigger expectation for the quantity surveyor is to drive the value decisions within the design teams and client because, with better benchmarking and analysis, the quantity surveyor will have the data to lead these conversations. Understand what 5D means to you and your clients. Understand how you can use the data available to improve your service level agreements. 3.2 Lack of 5D case studies Throughout the BIM journey to date there have not been many case studies available to read and review with either a 5D bias, or that contain clear quantity surveyor outputs. The various examples that do exist provide only a brief overview of what 5D could be but, for example, just being able to measure steelwork within a model is only part of a solution. For 5D practices to become the norm for quantity surveyors, the quantity surveyor role needs to be undertaken in its entirety within a BIM environment, and the industry needs case studies to demonstrate this. Through Henry Riley s BIM journey at the time of writing, the following projects had been undertaken: re-creating client cost models into a BIM cost database measuring and estimating project costs from BIM models agreeing negotiated contract sums based on design model output, incorporated within the chosen BIM cost software; and the issue of Henry Riley s first NRM BIM tender. In subsection 3, Level of detail and level of information, the experiences of Henry Riley to date are outlined, and the issues and problems faced are discussed in more detail, confirming what was achieved in trying to use NRM in a BIM environment. Keep sharing and collaborating experiences. BIM in isolation will not help the industry to learn and progress and as such it will only hold back your own ability to keep developing. Also note that BIM4SME wants to showcase SME case studies on their website; as such SMEs should look to collaborate with this resource. 8

9 3.3 Level of detail and level of information Designing to the correct level of detail (LOD) is a common problem that can be encountered consistently in BIM projects. Although LOD outputs to a specified graphical representation, it has a direct effect on the level of information provided (data), as the greater the number of graphical items, the more data are available when viewed within costing software. Prior to commencing any design the team should agree on a key set of principles. Understanding the relationship between the RIBA digital Plan of Work stages and NRM classification requirements is important when confirming what LOD is required. For example, at an early RIBA stage basic design and object parameters are required to produce a visualisation of a building and its associated cost, therefore a high LOD model could overcomplicate matters as this would show elements of the building as too numerous and detailed for that specific design stage. LOD takes on more significant importance for a design and build tender, as the level of information designed should be such that it can be developed by the tendering parties. For example, should a concrete slab be represented as a composite item (graphically and spatially) or with all associated elements shown separately concrete slab, floor finish, insulation, damp proof membrane, reinforcement and so on? Of course, it is possible to determine a lot of these quantities from a composite item, but if detail is required for each element then it should be modelled individually, but at the correct stage of the plan of work. It is therefore important to discuss what information is due to be produced with the design team and run through the structure and elements of the pricing document that is to be issued, so it is clear what LOD is required, based on the specifics of the project. Agree the procurement method and RIBA Plan of Work stage(s) and ensure a model is not designed beyond this point at each stage you are working to. The appropriate level of NRM formal cost plan can then be used consistently throughout the matching RIBA stage Agreeing on an execution plan Building on the LOD example in subsection 3.3, Level of detail and level of information, what is important is how this is defined within the execution plan. The execution plan is just as important to the quantity surveyor as it is to the other disciplines. From the point of view of a quantity surveyor it has been noted that the following key points are required within an execution plan: naming protocols: particular costing software will use the name of the objects to group like items for quantification; therefore, standard naming protocols must be agreed prior to commencement such that object names can be understood in plain language. Additionally they cannot change after this point, as it would make redundant the work the quantity surveyor will have put into the estimate/pricing document up to this point LOD versus RIBA Plan of Work versus NRM (see subsection 3.3, Level of detail and level of information) definition of a common data environment: in this project it was agreed that the transfer of model data between the team would take place via the client s own internet-based information portal definition of file format: consider which systems are used and which files can be opened. Expenditure on design licenses should be avoided where possible, particularly when the appointment is for a quantity surveyor only 9

10 file-exporting instructions: software vendors have guides on how files should be saved from design files to those that a quantity surveyor can open and use. Issue these documents and include them within the execution plan appendices; and amalgamated files and by discipline files: it is usually important that the designers understand that the quantity surveyor needs both of these file types and that, when 3D models are issued, they have checked all of the information included. Far too frequently files are issued with incomplete information (where layers are turned off etc.). (The lead designer or nominated person within the execution plan should ensure the amalgamated file is fully updated prior to issue.) KEY LEARNING Understand what information you require and in what format. Clearly state this and ensure it is captured within the execution plan Naming protocols Previous experience with other projects of considerably lower complexity and cost had highlighted the importance of setting up a robust naming protocol as early as possible and retaining it throughout the duration of the project. This is important for a number of reasons, not least to make analysing the model as straightforward as possible. Initially, upon receipt of 3D models that were not specifically optimised for costing, there was considerable difficulty in understanding what objects within the model were meant to represent. It is not always practicable, or necessary, to have a high level of visual detail within a model, as long as all the relevant information is present and clear. However, it was found that, where designers had used default family names for objects from when they were originally created (not necessarily from the design software packages), they were totally incoherent, and interrogation of the model itself proved difficult. This made identification time consuming and, in many cases, almost impossible. As such a standard naming protocol including plain language descriptions was agreed. Robust naming protocols did not only make identification of objects much simpler but are also key in creating a standard name for like objects, which is important to how quantities are taken off in a BIM environment. Within the software used by Henry Riley, links are created to the names of objects; this is analysed in more depth in subsection 3.7, Objects and naming conventions; however, the key point is that names must be kept the same for like objects so as not to quantify objects in the wrong sections of the estimate/pricing document and unnecessarily increase the time taken to audit the cost document. It is imperative that naming protocols be introduced and agreed upon as early as possible, so as to avoid abortive work. It is also important that protocols are followed as deviation can be costly to the programme in particular to the quantity surveyor. 3.6 Agreement of data drops with the design team Prior to commencing the project the client had already agreed a set of data drops against key milestones within their design and construction phases. These closely followed those identified within the CIC BIM Protocol document. This project was started without any BIM inputs and as such had already progressed beyond a number of data-drop stages. The design team therefore agreed to work to the last data drop stage prior to issuing the tender information. The drop required the design to be complete to RIBA digital Plan of Work (dpow)

11 stage 3; however, as the client was quite advanced in understanding its design requirements, what resulted was a design that was at minimum RIBA stage 3, but in areas such as engineering services design it contained more detail. As noted in subsection 3.3, Level of detail and level of information, for a quantity surveyor this poses a potential problem. Should the additional detail be ignored and measured and priced to the appropriate NRM stage or should the additional detail be included, such that part of the pricing document provides detail beyond the required level of information? For example, should all external walls be measured together and therefore rated together as one item, or should the various wall types be clearly identified and separate rates entered against each one? As Henry Riley was part of a trial and as both the client and contractor base were familiar with the specifications, the team decided to include all of the detail that was available. The belief was that the more detail provided to a contracting party, the more they are empowered to understand the information and pass on their most competitive tender prices. Understanding of client/cic BIM Protocol data drops is critical to aligning both RIBA Plan of Work and NRM pricing documents. 3.7 Objects and naming conventions Rather than permitting object naming to follow the typical conventions of the particular design practice responsible, or even to follow the standard families systems in design packages such as Autodesk Revit software products, it is important to agree at project inception how model objects will be named to allow them to be used most effectively by the whole design team. For the quantity surveyor this is particularly important as one of their key roles is in the collation and sorting of the data to form meaningful cost plans. From the quantity surveyor s perspective, agreeing to incorporate NRM descriptors into the BIM object parametrics at the BIM execution plan stage allows successive developments in the model to align cost comparisons through the cost plan stages as well as to benchmark costs across projects against data held in house. It has been noted that individual clients often require cost outputs to be presented in accordance with their own modelling preferences; object naming conventions should be agreed and adopted from the outset to enable this to happen. Once implemented successfully the process of extracting useable quantities is greatly simplified and cost models can be almost entirely automated. The quantity surveyor s value can then be maximised in interrogating the efficiency of the design with reference to the client s requirements. Objects should be created with all of the data users in mind, and the correct LOD and level of information should be understood and included to ensure that objects have maximum usability. 3.8 Use of NRM Previous work undertaken for this client had used a client-specific costing document. However, this document had a very high level of detail in a number of sections, similar to the level of detail required for the NRM formal cost plan 3, and a far lower level of detail in other sections. In particular issues were encountered with the mechanical and electrical services cost plan, as the mechanical and electrical documentation was highly detailed, and had each work package split by physical location. The issue of its detail became a problem when trying to incorporate it into the wider cost plan, which only allowed for a line item for each work package (see NRM1). Furthermore, the issue of costs being 11

12 split by location caused a problem with naming objects within the models, which in turn would have resulted in a cost plan that was too detailed. The aim was to work with industry standards and best practice and initially NRM formal cost plan 3 (NRM FCP 3) was to be incorporated to form the basis of the standard cost documentation. However, the lower detail of certain sections of the client s existing cost plan was prohibitive to a certain extent, particularly due to the fact that the client did not want BIM to have an effect on project timelines, and also because a number of existing objects would require significant alteration for use with FCP3 (increasing LOD and level of information). The decision was made to use NRM formal cost plan 2 (FCP 2) in order to meet the time constraints, the requirements of dpow 2013 and to test out the principles of putting together an NRM BIM tender. Where further detail was available, this was captured by creating an optional extra level to the cost plan, so that developed design could be quantified, and yet all of the NRM elemental detail was included as intended. An additional consideration in using an NRM cost plan was the ability to benchmark back to the clientspecific cost plan. The client had a system of coding costs so that each aspect of a project could be benchmarked back to a blueprint model cost. Therefore, moving to an industry standard cost plan meant incorporating these benchmarking codes. This became a key driver in adding extra detail to the NRM FCP2 template. Where a line item in FCP2 fell within two of the benchmarking codes, another level of detail was created below the line item in order to properly allocate costs and give a real reflection of the expenditure within each section. Understanding the object relationship with existing 2D cost model measurement techniques is key to developing a workable 3D cost model. 3.9 Automatic quantification and understanding of costing software The role of the quantity surveyor will adapt within the BIM environment. The largest difference will be the volume of detailed measurement by hand that is no longer required and will be replaced by automatic quantity take off. There are a number of software solutions that can be used for this; however, in this project it was considered shrewd to opt for software that not only had automatic take off, but also the ability to produce and link to costing documents within the same application. The chosen costing software groups quantities by the object s name and type. For example, if two doors or two lengths of wall are named exactly the same then the quantities or dimensions of those objects will be grouped in the same dimension group. This is why it is so important for robust naming protocols to be agreed, so that each object should be in its correct dimension group. Furthermore, the required parameters of each object should be included within that object, as agreed within the execution plan, so that, for example, each wall will have the wall area identifiable and not just the length of wall. This is also a key point for the quality assurance check: a quick review of the dimensions will show up any obvious errors. Another important factor is to be able to create a costing document within the software and import the quantities from the model and the rates from a database. In order to do this a library of cost items was created along with associated rates so that a priced document could be built. This links in with the cost detail and LODs agreed on in the execution plan. The costing software has provision to further interrogate ( drill down ) levels of a cost plan, revealing increasing detail. What this creates is an elemental breakdown of items with detailed measurement, rates and costs in a level beneath that breakdown. This also allows extra detail to be included that was not included within NRM formal cost plan 2, but was modelled for detailed requirements. 12

13 Once the cost plans have been established they allow for a quick update to the project costs, subject to a thorough quality assurance check. Quantities from the model and rates from the rate library are live linked to the costing document; as such, whenever the drawings are revised, so long as the naming protocol has been followed, the cost will automatically update. However, it should be noted that, as this was a tender document, and was issued with all zero rate values, actual tender figures are added back once they have been received as part of the return. Review multiple cost software platforms against your role as a quantity surveyor in conjunction with your practice and client requirements Object detail versus cost detail An important aspect to consider is how the designed objects integrate with the required cost detail. Taking the example of a concrete slab, if the costing document being used simply provides a line item for a slab there is little point in modelling a detailed build-up of all associated elements. However, planning for this requires collaboration to potentially save time in both the modelling and costing phase. Continuing with the slab example, if there is a detailed breakdown of all the elements specified combining the known depth and the area of the slab, one can calculate the volume of the slab and the other elements using the same object. Including more designed objects and detail than the costing document requires, possibly due to the requirements of other applications of the model, will almost certainly be less of an issue than not producing enough detail within the model to complete the required cost plan. These issues were noted with regard to internal doors; for example, where there are different specifications of doors there are not always enough families created to cover all of the different variances and associated costs. Where internal doors have been grouped into one family and type, including both single and double doors, these cannot be separately identified and therefore specific rates cannot be applied to these objects. The model then needs to be updated to reflect the difference in detail, which adds time to the overall process. This demonstrates the importance of getting the initial execution plan specifically the LOD and level of information correct in conjunction with the naming protocols agreed before the start of any design to avoid unnecessary delays, and particularly to let the design team have an understanding of the required costing detail before developing further objects. When the NRM formal cost plans become more widely used and object libraries become more developed this will be less of an issue, but while this process develops it will be key for the project team to be proactive. Decide the detail your pricing document will reflect at an early stage. It will be difficult to change this after design has begun, as it may require new objects to be created Coordination and benchmarking with the client s existing cost model The client Henry Riley was appointed by uses blueprint principles for design and cost, so they can benchmark and drive efficiencies within their business. Therefore, an added complication of working with this existing data had to be dealt with. Due to the detail of the existing cost model, it was felt that it was not appropriate to use the same detailed document for contractor pricing on a design and build procured project, where the existing contractor base was more familiar with producing simple cost tender returns. 13

14 It was agreed that using NRM as a standard was a suitable way to proceed for pricing, despite the contractor base not being familiar with it. Setting up the NRM database was straightforward within the costing software; however, there was the additional requirement of being able to benchmark back to the existing 2D cost database. The costing software has the ability to add extra detail against each cost line as required. Therefore, an additional column was added to the client s specific coding system. Once data were exported from the cost software to the external spreadsheet software, it was possible to sort the information and benchmark back to the client s existing cost database. Understand how you can utilise existing cost data with NRM and understand what capabilities your BIM cost software has to assist you with this to avoid manual benchmarking Coordination of design detail During the process of the design it is important that all of the designers collaborate towards an amalgamated design in order to avoid abortive work and to minimise clashes within the final model. As BIM is a collaborative process it is imperative that regular design coordination meetings take place, out of which an updated, clash-free, amalgamated model should be produced. The quantity surveyor, if they feel it beneficial, will carry out a quantity measure of each updated model and undertake a quality assurance check. It is important to run a quality assurance report that checks how the data have been used. This allows the quantity surveyor to provide specific feedback on naming protocols, LOD, level of information and any missing objects prior to the following coordination meeting, for incorporation within the designers models. This prevents delays towards the end of the design period as problems are identified earlier. BIM is a collaborative process, but due care and attention is required when amalgamating models and interpreting data Importance of quality assurance Quality assurance is likely to become even more important to the role of the quantity surveyor. The quantity surveyor now receives information, where previously they would collect the data themselves; this requires a robust quality assurance procedure for checking data accuracy, as information can very easily be miscommunicated within a model, as demonstrated at the RICS BIM Conference If the correct naming protocols and design standards have been met, then the quantity surveyor should receive a clash-free, coordinated and amalgamated model with no quantification errors. However, there have been examples of duplication of the same object by different disciplines, so the quantity surveyor should have a procedure in place to undertake some measurement checks, probably using the software s inbuilt measurement tools, as well as comparing key indicators such as roof area with floor area. A visual inspection of the module is key. 2 Good quantity surveyor software should have inbuilt reports that enable quality assurance checks to be carried out. Different software vendors have different levels of reporting capability from non-existent to detailed line-by-line reports. All quantity surveyors should try to work with the software vendors to continually improve these tools, as the quantity surveyor is the end user. 14

15 The costing software used by Henry Riley included a feature called a references report. This gave a line-by-line report of how the data had been used, detailing: a) where objects were modelled, but not used within the estimate/pricing document b) where objects were modelled and used within the estimate/pricing document and against what line of the report c) what lines within the estimate/pricing document had quantity information included against them; and d) what lines within the estimate/pricing document did not have quantity information against them. 3 Once it has been checked that the information has been utilised correctly, the final quality assurance check should be the same procedure that a quantity surveyor would undertake in a non-bim environment. Using the quantity surveyor s knowledge, expertise and benchmarking experience, the quantities, rates and project values should be analysed to ensure they are as expected. On the project in question, estimates had already been produced through the early stages of the project and as such Henry Riley was able to cross-check the quantities and outturn cost against these estimates to ensure the cost model was aligned. Where it was not aligned, it could be checked whether the BIM model had developed or contained any errors. Generally, it was noted that the model produced the information as expected. With this project, it was fortunate that existing cost and design information was available; however, it did not test the quality assurance procedures fully, as a BIM model had not been used from inception and a safety net of 2D designs and cost was in place. Review in-house quality assurance procedures and ensure they can work within model data outputs and associated cost software Tender inclusions Within the tender documents issued, additional BIM outputs from the various models produced were included. While it did not seem prudent to burden the contractors with additional expense during a tender period where they were already required to interpret information in a form that they had not previously received, it was important to obtain as much benefit from the trial as possible. As with most cost software, the software used in this project was able to export to other file types. Therefore, information was exported to external spreadsheet software so that amendments, additional information and rates could be applied by the contractors in a form familiar to them. In addition, a free viewer version of the project-specific pricing document that showed the relationship with the design model and the pricing schedule with quantities was issued. This file could not be edited by the contractor, but various layers within the model could be switched on and off, giving the contractor clear identification of how the various measurements had been built up when read in conjunction with the measurement descriptions. This meant that queries from the measurement could be resolved by the contractors themselves in the first instance. 15

16 By providing both the spreadsheet document and the free version of the pricing document, more detailed data were provided to the contractor, but without the expense of purchasing additional software or training. Other notable tender inclusions were: CIC BIM Protocol 3D models in design software format client-specific contract amendments, including specific BIM requirements; and client-specific BIM protocols and procedures using EIRS. Prior to starting the tender period, undertake a pre-qualification process with the potential tenderers to understand their capabilities and what software interfaces they can work with. 16

17 4 Post-tender review 4.1 Mid-tender interview feedback Two clear themes were identified during the mid-tender interviews: use of the BIM model; and having the correct tools and technologies. During the interviews with the various contractors it became evident that the contractor base was struggling to view and understand the 3D models. Requests for PDFs and hard-copy print outs were frequent; however, this was something that the project team were not prepared to issue, as it would defeat the purpose and intended outputs of this BIM tender trial. It should be noted that the contractors were pre-qualified and their BIM capability assessed. Based on the client s requirement to complete the build before Christmas 2014, the tender period was reduced to accommodate an earlier on-site start date. The reduced tender period put pressure on the contractors supply chains that were not in a position to view and interpret BIM data, hence the requests for the more traditional transfer of information. It was also clear during the mid-tender interviews that the various contactors did not possess the correct tools and technologies. An inability to use the various systems required proved a delay to understanding the data that was available to them. This, coupled with only basic in-house usability and expertise, meant the contractors found it difficult to fully understand and progress during the initial tender period. 4.2 Tender analysis and contractor engagement Three out of the five tenderers submitted a pricing document that broadly matched the document that was derived from the costing software and included in the tender documents. One of the other tenderers submitted only the summary sheet provided and only on request provided back up in the required form. The final contractor submitted the summary sheet provided with their own pricing document as back up. Of the three who followed the pricing document, only one used the majority of the quantities taken from the costing software and this, incidentally, was the contractor who offered the lowest price and was eventually appointed. As well as offering the lowest price and engaging most readily with BIM processes overall, the work packages that were modelled were where the winning contractor had the most competitive prices. Items of risk, which neither the BIM model or survey information could detail, were also priced more competitively by the winning contractor which had a contributory effect on the overall competitiveness of these work packages. At the time of writing there was not enough information to analyse how much of an impact the BIM aspect had on these prices, although it is anticipated that this analysis will be able to be carried out at the end of the project when all risks have been realised and all subcontract packages let. In terms of analysis of the tenders themselves, it was considered by the quantity surveyors that using the NRM pricing document made analysing the tenders simpler and more accurate. Furthermore, adding client cost codes throughout the document allowed easy benchmarking back to the client s previous pricing documents. 4.3 Contractor feedback The tender was met with mixed responses from the contractors. Generally speaking, those who had the highest price did not engage well with the BIM tender process. Specifically, these contractors did 17

18 not want to work solely with a 3D model, and without the provision of 2D drawings they struggled to effectively disseminate the information through their supply chain. This meant that an already tight tender period was effectively made shorter with delays in getting information out to the supply chain. In contrast, the feedback from the winning tenderer was far more positive. They fed back that they had used the same costing software to drive efficiency in the tender process. They were clearly the most heavily engaged with BIM, and therefore reaped more of the benefits it can afford. They were also the only tenderer to provide their own model or mention the costing software during the posttender interview. 4.4 Issues encountered While the NRM format worked well for the analysis of tenders, it was noted that the extra detail entered into formal cost plan 2 (FCP2) may not be best suited to a design and build (D&B) procurement route. It was considered that, while FCP2 works well for D&B, the detail closer to formal cost plan 3 (FCP3) is more appropriate for a traditional contract. As mentioned in subsection 4.2, Tender analysis and contractor engagement, only one contractor properly used the NRM template and quantities and even then extra lines were added where descriptions were not adequate, although this was expected to a degree. Another issue that was encountered was the time constraint that was placed on the tenderers. The tender period was already considered to be short, particularly for a BIM trial, but this was exacerbated by a number of changes throughout the tender period and, as a result of this, the work-in-progress design. In addition, the client changes meant that the previous library of information did not adequately cover the scope of the project and as such time was devoted to object creation and naming as opposed to design development. Therefore, it was found by the contractors that there were also a number of clashes in the models along with the unfinished design. 18

19 5 Lessons learnt 5.1 Starting a BIM journey The experience that Henry Riley gained through its BIM journey, and in particular in connection with this case study project, enabled the identification of some initial steps that it is believed allow a BIM novice to start their own BIM journey. 1. Working with BIM should be seen as undertaking the usual role of the quantity surveyor, but with better data. Therefore, the key to removing any fear of BIM is to gain experience in it. Quantity surveyors should begin to learn how to work with the new systems and data and undertake the tasks themselves. By learning and doing, a BIM novice will gain the experience they require. One method that was used to gain experience was to run a 5D exercise at the same time as a more traditional route, therefore avoiding making any mistakes along the way and being able to benchmark the progress in BIM. 2. Once the experience has been gained, this will bring confidence to both the individual and the wider organisation. With a greater degree of confidence the quantity surveyor will be able to ask questions of others, integrate with other systems and challenge methods of working and required outputs. Only by challenging what they are told, in conjunction with understanding their existing role, will they be able to maximise the BIM benefits that can be achieved 3. Once an organisation has the confidence to discuss and debate their BIM involvement the next steps are to work with others and engage their own supply chain. A key theme associated with working with BIM is collaboration, but if the supply chain used is not aligned with business objectives, then it will also prevent the business from fully realising its BIM benefits. 4. With a supply chain in place and increasing BIM knowledge within an organisation, the next step is to tell clients what is known, what can be done and how the organisation can help them on their BIM journey and ultimately save them time and money. Once these discussions are engaged in, progress can be benchmarked and the BIM journey can be analysed to see if it has achieved what it set out to do, and a return on investment can be evaluated. 5.2 Use of NRM in a BIM environment The use of NRM on this project was not without its difficulties. This project followed the design and build procurement method and, as such, a form of NRM 1 was utilised as a pricing document. It was felt this was a good way to proceed as it enabled quantities to be produced for the benefit of the contractor. This was an attempt to try and give confidence to the contractor that they were using accurate quantities which in turn could be passed to their subcontractors in the hope of more competitive rates. There can also be conflicts in the object nature of BIM designs versus the NRM structure that exists where like items can appear within different sections and not be grouped as objects. By working through the detail of this project and understanding what is possible, a more traditional method of procurement seems to lend itself to a BIM project. The design team could complete their full design package and a full NRM 2 quantity take-off could then be achieved. A review of the procurement method and level of NRM structure and quantity measure is clearly a debate that quantity surveyors and design teams need to engage with in today s BIM conversations and at the beginning of every new project. BIM has the opportunity to deliver more accurate quantities in less time; however, coordination of the information and accuracy of what is designed is a factor, and for the short to medium term adopting an approach of using NRM 1 for pricing documents may suit the current market place. 19

20 It was noted that, when using NRM for the basis of tender, the object naming did not always line up with the NRM categorisation for measurement. In order to make best use of the NRM method of measuring it was felt that naming protocols should have been worked through in line with NRM. By naming objects in this way the 3D models would have required more consideration for how objects were used and in turn result in fewer clashes. Any future naming of objects should be reviewed with the quantity surveyor prior to being created to ensure the data could be used to everyone s benefit. At the time of writing, level 2 BIM was still being finalised. It is therefore important that quantity surveyors are focused on the current requirements of level 2 BIM and provide feedback to help define its requirements once a final level 2 definition has been agreed upon. Currently level 2 is very design focused and quantity surveyors need to work with RICS to ensure cost-management processes are on the agenda. 5.3 Tender period: next steps Due to this being an early BIM trial, more time is needed for contractors to understand the processes required to submit a BIM tender. Despite the fact that a BIM prequalification questionnaire was sent out, the tenderers were not familiar with the specific requirements of this client. Furthermore, the prequalifying questionnaire did not ask about the tenderer s supply chain. In the future, all BIM prequalification questionnaires should ask if the supply chain is able to use BIM data; or, failing that, if the contractor has the capability to change the 3D models into 2D information for smaller suppliers. Additionally, more time and preparation needs to be allowed for the designers. It is imperative that the information is well developed when the tenders are issued. This means that, even if there are changes, objects are already available in the library rather than having to be created from 2D information. In time, more objects will be created from other schemes and the library content will improve; however, until this has been achieved, more time needs to be afforded for the design process. This extra time should also result in more detail being put into the models as well as fewer errors from a short modelling period and more time for better coordination, improving use of objects and reducing clashes. 5.4 Information (BIM) Manager and next steps for the quantity surveyor Within the industry there is a lot discussion about information/bim managers, including who should undertake this role, and what it involves. As highlighted in subsection 3.1, Understanding the role of the quantity surveyor in relation to 5D BIM, the project quantity surveyor on a BIM project becomes the first user of all of the data, which includes a requirement to audit the information. The quantity surveyor is therefore best placed to order the data in such a way that the information can be interpreted and used correctly. Although the lead designers have often taken on the role of the information manager, it is the quantity surveyors who find themselves in a position to review all of the disciplines output and provide feedback on the information produced, and additionally a review of the data will be from a functionality and usability perspective rather than a design perspective. As such the quantity surveyors are best positioned to undertake the role of information manager, including an audit role for quality assurance. As BIM develops further, as does the RICS BIM Management qualification, it is expected over the coming years that the quantity surveyor will have a prominent role to play across all BIM projects, providing the knowledge and value to support both clients and design teams alike, which in turn will support Peter Hansford s 2025 vision goals and targets of: PEOPLE an industry that is known for its talented and diverse workforce SMART an industry that is efficient and technologically advanced SUSTAINABLE an industry that leads the world in low-carbon and green construction exports GROWTH an industry that drives growth across the entire economy LEADERSHIP an industry with clear leadership from a Construction Leadership Council. 20

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company?

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company? Organisation Type The first national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed that 67% of the industry sample possessed confidence in their skills

More information

November Introduction. What was your role with the company? Has your business awareness and use of BIM advanced in the last twelve months?

November Introduction. What was your role with the company? Has your business awareness and use of BIM advanced in the last twelve months? November 2016 Executive Summary The second national survey to benchmark the level of Building Information Modelling (BIM) adoption in Ireland revealed that 76% (67% 2015) of respondents possessed confidence

More information

Asset Management Policy

Asset Management Policy Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset

More information

Chartered Project Professional (ChPP) Application Guidance

Chartered Project Professional (ChPP) Application Guidance Chartered Project Professional (ChPP) Application Guidance Helping you to understand, decide and prepare for the Chartered Project Professional (ChPP) standard Becoming a Chartered Project Professional

More information

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015

CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 CONSTRUCTION INDUSTRY COUNCIL Technical Seminar on Construction Procurement Selection of Consultants 27 November 2015 Background A Task Force established by CIC Comprising Government, Clients, Consultants,

More information

Level 5 NVQ Diploma in Management and Leadership Complete

Level 5 NVQ Diploma in Management and Leadership Complete Learner Achievement Portfolio Level 5 NVQ Diploma in Management and Leadership Complete Qualification Accreditation Number: 601/3550/5 Version AIQ004461 Active IQ wishes to emphasise that whilst every

More information

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK

THE KEY ELEMENTS OF QUANTITY SURVEYING WORK THE KEY ELEMENTS OF QUANTITY SURVEYING WORK A Presentation to the Institution of Surveyors of Uganda by Tom Joseph Mukasa BSc, MSc, MRICS, ICIOB, AISU 2016 1. The following are key elements (divided into

More information

Promoting better business outcomes through the use of BIM and digital technologies.

Promoting better business outcomes through the use of BIM and digital technologies. Promoting better business outcomes through the use of BIM and digital technologies. Introduction The Role of the BIM Manager Agenda 18:00 Introduction + BIM update by Mike Turpin, Innovating Futures 18:10

More information

SCSI BIM Submission to the Enterprise Ireland BIM Implementation Forum. June 2014

SCSI BIM Submission to the Enterprise Ireland BIM Implementation Forum. June 2014 SCSI BIM Submission to the Enterprise Ireland BIM Implementation Forum June 2014 Introduction Building Information Modelling (BIM) can improve the quality, reliability and efficiency of construction projects

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

Supply Chain Charter. A fresh perspective on building

Supply Chain Charter. A fresh perspective on building Supply Chain Charter A fresh perspective on building 1 1 CONTENTS One CHARTER POLICY STATEMENT Two WHAT WE EXPECT FROM OUR MEMBERS A. SUSTAINABILITY B. HEALTH & SAFETY MANAGEMENT C. QUALITY MANAGEMENT

More information

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER IN LEADERSHIP AND MANAGEMENT AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED IN LEADERSHIP AND MANAGEMENT The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering

More information

SQA Equality Strategy

SQA Equality Strategy SQA Equality Strategy 2013 17 Publication Date: April 2013 Publication Code: FE6577 Published by the Scottish Qualifications Authority The Optima Building, 58 Robertson Street, Glasgow G2 8DQ Lowden, 24

More information

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015

BIM 2016 and the NEC. Simon Rawlinson, 20 April 2015 BIM 2016 and the NEC Simon Rawlinson, 20 April 2015 Presentation overview Commercial requirements of BIM BIM and NEC Working Together Government requirements for a collaborative digital model Supporting

More information

ABERDEEN CITY COUNCIL

ABERDEEN CITY COUNCIL ABERDEEN CITY COUNCIL 1 Job Details Job Title: Chief Officer - Capital Job Profile No: Function: Resources Grade: CO SCP 34 Version Date: November 2017 Salary 81,504 2 Job Purpose This role is responsible

More information

Purpose This note describes in more detail what HMRC is doing to devise and run a limited trial for an improved compliance enquiry process.

Purpose This note describes in more detail what HMRC is doing to devise and run a limited trial for an improved compliance enquiry process. Single Compliance Process (SCP) Briefing Paper for Tax Agents Purpose This note describes in more detail what HMRC is doing to devise and run a limited trial for an improved compliance enquiry process.

More information

Single or multi-sourcing model?

Single or multi-sourcing model? Outsourcing 2007/08 Single and multi-sourcing models Anthony Nagle and Alistair Maughan, Morrison & Foerster www.practicallaw.com/8-380-6567 Once an organisation decides to outsource, one of its biggest

More information

RTC EDUCATION LTD T/A REGENT COLLEGE REGENT SKILLS TRAINING

RTC EDUCATION LTD T/A REGENT COLLEGE REGENT SKILLS TRAINING Commercial in Confidence RTC EDUCATION LTD T/A REGENT COLLEGE REGENT SKILLS TRAINING TMX Report Template V2 02.04.12 Contents 1. Organisation Information, Introduction and Overview... 1 2. Areas of Particular

More information

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER

AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED PROFESSIONAL ENGINEER AUSTRALIAN ENGINEERING COMPETENCY STANDARDS STAGE 2 - EXPERIENCED The Stage 2 Competency Standards are the profession's expression of the knowledge and skill base, engineering application abilities, and

More information

Expert Reference Series of White Papers. ITIL Implementation: Where to Begin

Expert Reference Series of White Papers. ITIL Implementation: Where to Begin Expert Reference Series of White Papers ITIL Implementation: Where to Begin 1-800-COURSES www.globalknowledge.com ITIL Implementation: Where to Begin Michael Caruso, PMP, DPSM Introduction The Information

More information

Cookham Wood and BIM: Practical Lessons Learnt Fiona Moore Cirrus Consultant Services 10 July 2014

Cookham Wood and BIM: Practical Lessons Learnt Fiona Moore Cirrus Consultant Services 10 July 2014 Cookham Wood and BIM: Practical Fiona Moore 10 July 2014 Topics Covered: Project Overview BIM Early Adopter Project: Why Cookham Wood and how we got involved Ministry of Justice (MoJ) and BIM Key Client

More information

BIDDING FOR BIM. CIF Bidding for BIM. September

BIDDING FOR BIM. CIF Bidding for BIM. September BIDDING FOR BIM CIF September 2017 www.cif.ie Document Control Sheet Client: Project Title: Document Title: Document No: Construction Industry Federation (CIF) Lean Construction, Building Information Modelling

More information

Quantity Surveying and Construction

Quantity Surveying and Construction Quantity Surveying and Construction August 2014 Pathway guide Published by: RICS, Parliament Square, London SW1P 3AD. All rights in this publication, including full copyright or publishing right, content

More information

Report to INFRASTRUCTURE SERVICES Committee for decision

Report to INFRASTRUCTURE SERVICES Committee for decision 15/247 Subject: Prepared by: Network Outcomes Contracts Dave Hadfield (General Manager - Tairāwhiti Roads) Meeting Date: 6 August 2015 Report to INFRASTRUCTURE SERVICES Committee for decision SUMMARY The

More information

BIC Task & Finish Working Groups Project Briefing Document. Project Name: Metadata Map. BIC Project Brief Metadata Map Version 1.0

BIC Task & Finish Working Groups Project Briefing Document. Project Name: Metadata Map. BIC Project Brief Metadata Map Version 1.0 BIC Task & Finish Working Groups Project Briefing Document Project Name: Metadata Map BIC Project Brief The Purpose of the BIC Project Brief The BIC Project Brief is required to enable necessary projects,

More information

Commercial Management in the Construction Industry

Commercial Management in the Construction Industry Unit 11: Commercial Management in the Construction Industry Unit code: A/504/4355 QCF level: 6 Credit value: 15 Aim This unit gives learners an understanding of the factors which determine the cost of

More information

SEWSCAP CONTRACTORS FRAMEWORK CONTRACTORS CONSULTATION REPORT. For RHONDDA CYNON TAF COUNTY BOROUGH COUNCIL. July Page 1.

SEWSCAP CONTRACTORS FRAMEWORK CONTRACTORS CONSULTATION REPORT. For RHONDDA CYNON TAF COUNTY BOROUGH COUNCIL. July Page 1. For RHONDDA CYNON TAF COUNTY BOROUGH COUNCIL July 2010 Page 1 Contents; 1.0 Aims and Objectives of Framework 5 1.1 SEWSCAP Contractors Framework Objectives 5 1.2 21 st Century Schools Objectives 6 1.3

More information

Finance Effectiveness How to free up your time to do more interesting things

Finance Effectiveness How to free up your time to do more interesting things Finance Effectiveness How to free up your time to do more interesting things Adrian Gilder and Aly Jamal Grant Thornton UK LLP 18 October 2017 Agenda What is Finance Effectiveness? Why undergo a transformation

More information

Qualification Specification 601/3691/1 icq Level 5 NVQ Diploma in Management and Leadership (RQF)

Qualification Specification 601/3691/1 icq Level 5 NVQ Diploma in Management and Leadership (RQF) Qualification Specification 601/3691/1 icq Level 5 NVQ Diploma in Management and Leadership (RQF) Qualification Details Title : icq Level 5 NVQ Diploma in Management and Leadership (RQF) Awarding Organisation

More information

Level 3 Diploma in Management. Qualification Specification

Level 3 Diploma in Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements 6 Support for candidates 6 Assessment 7 Internal quality assurance

More information

ASSESSMENT PLAN LEVEL 3 - SURVEYING TECHNICIAN APPRENTICESHIP

ASSESSMENT PLAN LEVEL 3 - SURVEYING TECHNICIAN APPRENTICESHIP ASSESSMENT PLAN LEVEL 3 - SURVEYING TECHNICIAN APPRENTICESHIP 1.0 Introduction The Surveying Technician Apprenticeship is designed as an entry level into surveying will typically take 2 years to complete.

More information

Devon and Cornwall Police May 2017

Devon and Cornwall Police May 2017 Interim Audit Report 2016/17 Devon and Cornwall Police May 2017 Contents The contacts at KPMG in connection with this report are: Darren Gilbert Director KPMG LLP (UK) Tel: 02920 468205 Darren.Gilbert@kpmg.co.uk

More information

Planning Construction Procurement. A guide to developing your procurement strategy

Planning Construction Procurement. A guide to developing your procurement strategy Planning Construction Procurement A guide to developing your procurement strategy First published October 2015 Revised October 2016 ISBN: 978-1-98-851707-0 (Online) New Zealand Government Procurement PO

More information

ISO whitepaper, January Inspiring Business Confidence.

ISO whitepaper, January Inspiring Business Confidence. Inspiring Business Confidence. ISO 31000 whitepaper, January 2015 Author: Graeme Parker enquiries@parkersolutionsgroup.co.uk www.parkersolutionsgroup.co.uk ISO 31000 is an International Standard for Risk

More information

Template for ToR for Transaction Advisory Services

Template for ToR for Transaction Advisory Services Template for ToR for Transaction Advisory Services Addendum 1 Prepared by Genesis Analytics 4 December 2013 PPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services

More information

DIFFERENTIATED STRATEGIC SOLUTIONS SAICE 15TH ANNUAL CONFERENCE ON COMPUTERS IN CIVIL ENGINEERING

DIFFERENTIATED STRATEGIC SOLUTIONS SAICE 15TH ANNUAL CONFERENCE ON COMPUTERS IN CIVIL ENGINEERING DIFFERENTIATED STRATEGIC SOLUTIONS SAICE 15TH ANNUAL CONFERENCE ON COMPUTERS IN CIVIL ENGINEERING THE BENEFITS OF MANAGEMENT INFORMATION SYSTEMS TO THE PROFESSIONAL PRACTICE By Dr James A Robertson PrEng

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

Level 4 NVQ in Business & Administration Units Rules of Combination

Level 4 NVQ in Business & Administration Units Rules of Combination Level 4 NVQ in Business & Administration Units Rules of Combination Level 4 NVQ Certificate in Business & Administration To achieve a Level 4 Certificate in Business & Administration, you must complete

More information

Procurement manual for activities funded through the National Land Transport Programme

Procurement manual for activities funded through the National Land Transport Programme Procurement manual for activities funded through the National Land Transport Programme NZ Transport Agency www.nzta.govt.nz Copyright information This publication is copyright NZ Transport Agency. Material

More information

Procurement Strategy period September 2012 September 2014

Procurement Strategy period September 2012 September 2014 National Library of Scotland Procurement Strategy period September 2012 September 2014 Aims This document aims to identify NLS strategy for the development and continued improvement of procurement systems,

More information

CDM 2015: The regulator s experience to date. Simon Longbottom Head of HSE Construction Sector. Thoughts for Conference and Beyond

CDM 2015: The regulator s experience to date. Simon Longbottom Head of HSE Construction Sector. Thoughts for Conference and Beyond Health and and Safety Executive Small Projects Differently CDM 2015: The regulator s experience to date Simon Longbottom Head of HSE Construction Sector APS Conference 14 th September 2016 Thoughts for

More information

Social Care Induction Framework for Wales Manager s Guidance This guidance is for those responsible for workers during an induction period

Social Care Induction Framework for Wales Manager s Guidance This guidance is for those responsible for workers during an induction period Manager s Guidance This guidance is for those responsible for workers during an induction period There are two sections in the Manager s Guidance: 1 - How to use the Framework 2 - How to assess against

More information

CONTRACTS MANAGER (BUILDING) THE COMPANY

CONTRACTS MANAGER (BUILDING) THE COMPANY THE COMPANY Farrans Construction is a long established UK Building and Civil Engineering company operating in various sectors within the UK and wider Europe. A subsidiary of CRH plc, Farrans Construction

More information

faster better Transforming the development of quality apprenticeship standards

faster better Transforming the development of quality apprenticeship standards faster better & Transforming the development of quality apprenticeship standards www.instituteforapprenticeships.org #Fasterbetter @IFAteched ...to improve access to high quality apprenticeships and technical

More information

2Beginning with BIM. Axiom Architects

2Beginning with BIM. Axiom Architects 2Beginning with BIM Axiom Architects jonathan reeves city perspectives 24 Chapter 2 the practice Since Axiom Architects was founded in 1986, the practice has grown from its origins in Lewes, East Sussex,

More information

AN INTRODUCTION TO TECHNICIAN REGISTRATION

AN INTRODUCTION TO TECHNICIAN REGISTRATION AN INTRODUCTION TO TECHNICIAN REGISTRATION GATSBY IS A FOUNDATION SET UP BY DAVID SAINSBURY TO REALISE HIS CHARITABLE OBJECTIVES. WE FOCUS OUR SUPPORT ON A LIMITED NUMBER OF AREAS: PLANT SCIENCE RESEARCH

More information

OECD STUDY ON SOCIAL AND EMOTIONAL SKILLS STUDY PROJECT MANAGERS ROLES, RESPONSIBILITIES AND RESOURCES

OECD STUDY ON SOCIAL AND EMOTIONAL SKILLS STUDY PROJECT MANAGERS ROLES, RESPONSIBILITIES AND RESOURCES OECD STUDY ON SOCIAL AND EMOTIONAL SKILLS STUDY PROJECT MANAGERS ROLES, RESPONSIBILITIES AND RESOURCES Table of contents Introduction... 1 Profile of Study Project Managers... 2 Indicative timeline...

More information

The Procurement Route Choices Toolkit

The Procurement Route Choices Toolkit Entering into the wrong type of contract can be expensive and lead to poor partnerships in service delivery. Local highway authorities typically start the process of procurement for highway maintenance

More information

Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017

Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017 1. Introduction: Innovate 2 Succeed Invitation to Tender External Evaluator - June 2017 1.1 Invitation to Tender This is an invitation to submit a tender to provide services ( Services ) to meet the requirements,

More information

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference:

Transformation Programme. Sourcing Workstream PROCUREMENT PLAN. Inland Revenue. 28/06/2013 v1.0 FINAL Reference: Inland Revenue Transformation Programme Sourcing Workstream PROCUREMENT PLAN Project Sponsor: Greg James Prepared by: Sourcing Team Date: 28/06/2013 v1.0 FINAL Reference: 2013050 Document Control File

More information

Voluntary code for a. self-financed housing revenue account

Voluntary code for a. self-financed housing revenue account Voluntary code for a self-financed housing revenue account CIPFA, the Chartered Institute of Public Finance and Accountancy, is the professional body for people in public finance. Our 14,000 members work

More information

The Q-Base code. The code aims to:

The Q-Base code. The code aims to: The Q-Base code A tool for SME s quality management: The New Zealand experience Paper for the 5th apec standards and conformance conference, 23-24 September 2004, santiago, chile presented by sirma karapeeva

More information

Procurement Guide Part 1

Procurement Guide Part 1 Procurement Guide Part 1 [Draft7_Part1_revB_Introduction_Aug12] P a g e 1 Draft7_Part1_revB_Introduction_Aug12 Procurement Guide Part 1 1.1 Introduction All projects consume goods and services as part

More information

All Party Parliamentary Group for Excellence in the Built Environment - Call for evidence

All Party Parliamentary Group for Excellence in the Built Environment - Call for evidence 20 January 2017 All Party Parliamentary Group for Excellence in the Built Environment - Call for evidence Inquiry into the impact of Brexit on future skills needs in the construction industry and the built

More information

MANAGE PROJECTS CANDIDATE RESOURCE WITH SIMULATED ONLINE BUSINESS ASSESSMENT BSBPMG510A

MANAGE PROJECTS CANDIDATE RESOURCE WITH SIMULATED ONLINE BUSINESS ASSESSMENT BSBPMG510A MANAGE PROJECTS CANDIDATE RESOURCE WITH SIMULATED ONLINE BUSINESS ASSESSMENT BSBPMG510A Precision Group (Australia) Pty Ltd 9 Koppen Tce, Cairns, QLD, 4870 Email: info@precisiongroup.com.au Website: www.precisiongroup.com.au

More information

CAN DO the. toolkit 2. RESOURCE 1: Can Do Toolkit 2. Funded by. MerthyrValleys. Quality Living Striving for Excellence Working Together

CAN DO the. toolkit 2. RESOURCE 1: Can Do Toolkit 2. Funded by. MerthyrValleys. Quality Living Striving for Excellence Working Together SMEfriendly procurement CAN DO the toolkit 2 Funded by MerthyrValleys H O M E S Quality Living Striving for Excellence Working Together RESOURCE 1: Can Do Toolkit 2 IMPORTANT: All three resources that

More information

James Cook University. Internal Audit Protocol

James Cook University. Internal Audit Protocol James Cook University Internal Audit Protocol Table of Contents A. Introduction 2 B. Management Consultation during the Annual Internal Audit Planning Process 2 C. Support Provided to QAO/External Auditor

More information

Approved Employer (AE) Programme Handbook

Approved Employer (AE) Programme Handbook Approved Employer (AE) Programme Handbook Contents Introduction Programme structure streams and levels of approval Approved Employer benefits Approved Employer criteria Applying for approval Your obligations

More information

Strategic approach to payment system reform: the South African experience

Strategic approach to payment system reform: the South African experience Strategic approach to payment system reform: the South African experience Philip J. Tromp Experience has taught us that introducing change in a country s payment system is not an easy matter. The reason

More information

Economic Incentives Key Insights

Economic Incentives Key Insights Key Insight #1 Health and safety capability is a journey and an employer s needs change over time Key Insight #2 Keeping people healthy and safe is good for business Key Insight #3 Growing the culture

More information

Unit: CPC 421 Manage contracts to achieve outcomes (Commissioning, Procurement and Contracting)

Unit: CPC 421 Manage contracts to achieve outcomes (Commissioning, Procurement and Contracting) Unit: CPC 421 Manage contracts to achieve outcomes (Commissioning, Procurement and Contracting) Key Purpose The key purpose identified for those working in commissioning, procurement and contracting is

More information

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019

Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 Invitation to Tender RGT Evaluation Framework Agreement, 2016 to 2019 26th May 2016 1. Purpose of this Invitation to Tender (ITT) 1.1. This invitation to tender is for appointment to a three-year framework

More information

5D BIM: Creating Cost Certainty and Better Buildings

5D BIM: Creating Cost Certainty and Better Buildings 5D BIM: Creating Cost Certainty and Better Buildings David Mitchell 1 Abstract This paper looks critically at where BIM implementation is on the pathway and sets out the opportunities that arise when 5D

More information

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note

GE/GN8640. Risk Evaluation and Assessment. Guidance on Planning an Application of the Common Safety Method on. Rail Industry Guidance Note GN Published by: Block 2 Angel Square 1 Torrens Street London EC1V 1NY Copyright 2014 Rail Safety and Standards Board Limited GE/GN8640 Method on Risk Evaluation and Assessment Issue One; June 2014 Rail

More information

DATE ADVERTISED: 05 SEPTEMBER 2017 VACANCY PROPERTIES UNIT: FACILITIES MANAGER X 3 (BUTTERWORTH, MTHATHA AND EAST LONDON)

DATE ADVERTISED: 05 SEPTEMBER 2017 VACANCY PROPERTIES UNIT: FACILITIES MANAGER X 3 (BUTTERWORTH, MTHATHA AND EAST LONDON) DATE ADVERTISED: 05 SEPTEMBER 2017 VACANCY PROPERTIES UNIT: FACILITIES MANAGER X 3 (BUTTERWORTH, MTHATHA AND EAST LONDON) GRADE 14: R 454 924 - R 556 018 (Total Cost to Company) The Properties Facilities

More information

Risks, Strengths & Weaknesses Statement. November 2016

Risks, Strengths & Weaknesses Statement. November 2016 Risks, Strengths & Weaknesses Statement November 2016 No Yorkshire Water November 2016 Risks, Strengths and Weaknesses Statement 2 Foreword In our Business Plan for 2015 2020 we made some clear promises

More information

Quality Management System Guidance. ISO 9001:2015 Clause-by-clause Interpretation

Quality Management System Guidance. ISO 9001:2015 Clause-by-clause Interpretation Quality Management System Guidance ISO 9001:2015 Clause-by-clause Interpretation Table of Contents 1 INTRODUCTION... 4 1.1 IMPLEMENTATION & DEVELOPMENT... 5 1.2 MANAGING THE CHANGE... 5 1.3 TOP MANAGEMENT

More information

Project phases II. Tendering-constructionoperation

Project phases II. Tendering-constructionoperation Project phases II. -constructionoperation Construction management 2. Lepel BME Department of Construction Technology and Management 04.03.2015 Project phases time Inception initiation Preliminary analysis

More information

End of Project Report : Newtown Secondary School

End of Project Report : Newtown Secondary School Resource Management Planning: Worked Example End of Project Report : Newtown Secondary School The template for this document is available at www.wrap.org.uk/node/13707 Document Owner Project Project Reference

More information

SAFETY MANAGEMENT SYSTEMS IMPLEMENTATION EVALUATION GUIDE

SAFETY MANAGEMENT SYSTEMS IMPLEMENTATION EVALUATION GUIDE Appendix 8 to Chapter 3 Form 100-12/59 AIRCRAFT OPERATIONS DIVISION CAA OF LATVIA SAFETY MANAGEMENT IMPLEMENTATION EVALUATION GUIDE PROCEDURES SPECIFICATIONS PS 024 AIR OPERATOR CERTIFICATION APP 3.8-1

More information

AMP 5 Excellence in Health & Safety Awards Excellence in Health and Safety Innovation

AMP 5 Excellence in Health & Safety Awards Excellence in Health and Safety Innovation AMP 5 Excellence in Health & Safety Awards 2011 Excellence in Health and Safety Innovation Table of Contents Introduction...3 1. Tangible Benefits to Health and Safety, Including Cost and Risk Reduction...4

More information

INTERNATIONAL ACCOUNTING EDUCATION STANDARDS BOARD STRATEGY AND WORK PLAN March 2017

INTERNATIONAL ACCOUNTING EDUCATION STANDARDS BOARD STRATEGY AND WORK PLAN March 2017 INTERNATIONAL ACCOUNTING EDUCATION STANDARDS BOARD STRATEGY 2017 2021 AND WORK PLAN 2017 2018 March 2017 Strategy 2017 2021 IAESB Strategy 2017 2021 The International Accounting Education Standards Board

More information

Report. Quality Assessment of Internal Audit at <Organisation> Draft Report / Final Report

Report. Quality Assessment of Internal Audit at <Organisation> Draft Report / Final Report Report Quality Assessment of Internal Audit at Draft Report / Final Report Quality Self-Assessment by Independent Validation by Table of Contents 1.

More information

REVIEW OF SCOTTISH PUBLIC SECTOR PROCUREMENT IN CONSTRUCTION

REVIEW OF SCOTTISH PUBLIC SECTOR PROCUREMENT IN CONSTRUCTION REVIEW OF SCOTTISH PUBLIC SECTOR PROCUREMENT IN CONSTRUCTION Guidance on the use of a baseline skillset for construction procurement 11 October 2017 Page 1 of 21 1. Introduction... 3 2. Extract from the

More information

A quick guide to equality and procurement for housing

A quick guide to equality and procurement for housing A quick guide to equality and procurement for housing A quick guide to equality and procurement What s in this guide? This guide is intended to provide important information about key legal requirements

More information

DECISION TO ACCREDIT

DECISION TO ACCREDIT DECISION TO ACCREDIT Determine the requirements of the regulator, legislation and customer s needs prior to deciding on the standard to implement. Process is based on the following: Top management s decision

More information

IAESB Strategy and Work Plan

IAESB Strategy and Work Plan International Accounting Education Standards Board April 2010 IAESB 2010 2012 Strategy and Work Plan International Accounting Education Standards Board International Federation of Accountants 545 Fifth

More information

Digital Content Strategy Focus Group Public Report

Digital Content Strategy Focus Group Public Report Digital Content Strategy Focus Group Public Report Prepared for UK Trade & Investment Mark Leaver - April 2010 CONTENTS Context Focus Group Content Strategic Recommendations Structural Issues p1 p1 p6

More information

SHL JobMatch JobMatch Plus Report. JobMatch Plus Report. Name Ms Joan Smith. Job / Position Relationship Manager

SHL JobMatch JobMatch Plus Report. JobMatch Plus Report. Name Ms Joan Smith. Job / Position Relationship Manager SHL JobMatch JobMatch Plus Report JobMatch Plus Report Name Ms Joan Smith Job / Position Relationship Manager Date 12 April 2012 EXECUTIVE SUMMARY This report tells you about Ms Joan Smith s potential

More information

Managing stakeholder interests: How to manage complex and competing expectations

Managing stakeholder interests: How to manage complex and competing expectations Managing stakeholder interests: How to manage complex and competing expectations Author(s): J.C King, P.L King Organisation: Environmental Strategies Pty Ltd Country: Australia Email: jacobking@environmentalstrategies.com.au

More information

Making the right choice: Evaluating outsourced revenue cycle services vendors

Making the right choice: Evaluating outsourced revenue cycle services vendors White Paper Making the right choice: Evaluating outsourced revenue cycle services vendors Optum www.optum.com Page 1 White Paper Managing resources at today s hospitals and health systems is an ongoing

More information

CIF BIM Guide Standards & Policies August 2017

CIF BIM Guide Standards & Policies August 2017 BIM Guide August 2017 www.cif.ie BIM Guide Document Control Sheet Client: Project Title: Document Title: Document No: Construction Industry Federation (CIF) Lean Construction, Building Information Modelling

More information

White Paper Microsoft SharePoint for Engineering Document Management and Control

White Paper Microsoft SharePoint for Engineering Document Management and Control www.cadac.com White Paper Microsoft SharePoint for Engineering Document Management and Control Microsoft SharePoint is a powerful platform for document management and project collaboration. Many project-driven

More information

Procurement Options for NZ Construction Contracts

Procurement Options for NZ Construction Contracts 1 P a g e Tool Box Resource Procurement Options for NZ Construction Contracts A wide variety of contract arrangements have evolved in NZ for use on construction contracts. The following describes the most

More information

NSW DIGITAL GOVERNMENT STRATEGY. digital nsw DRIVING WHOLE OF GOVERNMENT DIGITAL TRANSFORMATION DESIGNING IN OUR NSW DIGITAL FUTURE

NSW DIGITAL GOVERNMENT STRATEGY. digital nsw DRIVING WHOLE OF GOVERNMENT DIGITAL TRANSFORMATION DESIGNING IN OUR NSW DIGITAL FUTURE NSW DIGITAL GOVERNMENT STRATEGY digital nsw DRIVING WHOLE OF GOVERNMENT DIGITAL TRANSFORMATION DESIGNING IN OUR NSW DIGITAL FUTURE CONTENTS 1 MINISTER S FOREWORD 2 TRANSFORMATION IMPERATIVE 3 ROAD MAP

More information

Invitation to Tender. Development Legal Services. August 2015

Invitation to Tender. Development Legal Services. August 2015 Development Legal Services August Contents 1. Important notices... 3 1.1. Confidentiality... 3 1.2. Accuracy of information and liability of SLH... 3 1.3. Canvassing... 4 1.4. Non-collusion... 5 1.5. Copyright...

More information

BRITISH SIGN LANGUAGE (SCOTLAND) BILL

BRITISH SIGN LANGUAGE (SCOTLAND) BILL BRITISH SIGN LANGUAGE (SCOTLAND) BILL EXPLANATORY NOTES (AND OTHER ACCOMPANYING DOCUMENTS) CONTENTS As required under Rule 9.3 of the Parliament s Standing Orders, the following documents are published

More information

Unit 3: The Traditional Procurement Route

Unit 3: The Traditional Procurement Route Unit 3: The Traditional Procurement Route 3.1 Introduction This Unit briefly introduces the main features of the traditional procurement route as a widely used route that provides a good basis for examining

More information

Conducting privacy impact assessments code of practice

Conducting privacy impact assessments code of practice ICO lo Conducting privacy impact assessments code of practice Data Protection Act Contents Data Protection Act... 1 About this code... 3 Chapter 1 - Introduction to PIAs... 5 What the ICO means by PIA...

More information

RICS New Rules of Measurement Roadshow Introductory seminar

RICS New Rules of Measurement Roadshow Introductory seminar RICS New Rules of Measurement Roadshow Introductory seminar for the CIOB on 6 May 2010 Workshop and Seminar Introducing the RICS New Rules of Measurement Order of cost estimating and elemental cost planning

More information

Audit Committee, 20 March Internal Audit Report Stakeholder Communications. Executive summary and recommendations.

Audit Committee, 20 March Internal Audit Report Stakeholder Communications. Executive summary and recommendations. Audit Committee, 20 March 2014 Internal Audit Report Stakeholder Communications Executive summary and recommendations Introduction As part of the Internal Audit Plan for 2013-14 Mazars have undertaken

More information

Oracle Prime Projects Cloud Service

Oracle Prime Projects Cloud Service Oracle Prime Projects Cloud Service Oracle Prime Projects Cloud Service is a complete, cloud-first success platform for all stages of the project lifecycle. It empowers executives, project managers, and

More information

BIM and the Consultant / Client s Quantity Surveyor

BIM and the Consultant / Client s Quantity Surveyor BIM and the Consultant / Client s Quantity Surveyor Mark McKane MRICS, MSc, PGCF&HEd Lecturer in Quantity Surveying School of the Built Environment BSc (Hons) Quantity Surveying & Commercial Management

More information

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability

More information

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America)

Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) Appendix A: Outline of Construction Management Functions /Roles for each phase of the project (source: Construction Management Association of America) 108 Appendix B: Questionnaire 109 CONSTRUCTION MANAGEMENT

More information

The standard for extraordinary project professionals...

The standard for extraordinary project professionals... The standard for extraordinary project professionals... Association for Project Management Registered Project Professional RPP Competences RPP the standard for extraordinary project professionals from

More information

SAMPLE. Not for training purposes. Participant Workbook. TAEDES505 Evaluate a training program. 1 st Edition 2017

SAMPLE. Not for training purposes. Participant Workbook. TAEDES505 Evaluate a training program. 1 st Edition 2017 Participant Workbook TAEDES505 Evaluate a training program 1 st Edition 2017 Part of a suite of support materials for the TAE Training and Education Training Package Acknowledgement Innovation and Business

More information

STRUCTURAL ENGINEER S SERVICES SCOPE

STRUCTURAL ENGINEER S SERVICES SCOPE ROYAL BOROUGH OF GREENWICH STRUCTURAL ENGINEER S SERVICES SCOPE WOOLWICH CREATIVE DISTRICT PROJECT status: R1 purpose: For information version: 1.0 date: 07/03/2016 1 This version Authored by: name: Nick

More information

Final Report Evaluation of Translation Bureau Programs Volume 2: Translation and Other Linguistic Services Program

Final Report Evaluation of Translation Bureau Programs Volume 2: Translation and Other Linguistic Services Program 2012-603 Evaluation of Translation Bureau Programs Office of Audit and Evaluation January 21, 2014 Table of Contents MAIN POINTS... i INTRODUCTION... 1 PROFILE... 1 Background... 1 Authority... 2 Roles

More information

ADVANCED PROCUREMENT FOR UNIVERSITIES AND COLLEGES WRITTEN SUBMISSION

ADVANCED PROCUREMENT FOR UNIVERSITIES AND COLLEGES WRITTEN SUBMISSION ADVANCED PROCUREMENT FOR UNIVERSITIES AND COLLEGES Introduction WRITTEN SUBMISSION APUC is the Procurement Centre of (procurement) expertise and representative body for procurement matters for all of Scotland

More information