8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation

Size: px
Start display at page:

Download "8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation"

Transcription

1 8Re: Northern Access 2016 Project Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation Dear Mr. Horey and Mr. Hoover, Mr. Bradden Horey Mr. Brent Hoover P.E. Project Management National Fuel Gas 6363 Main Street Williamsville, NY, Mott MacDonald Group Limited (Mott MacDonald) has prepared this opinion letter at the request of National Fuel Gas Supply Corporation (National Fuel) to summarize the feasibility and significant geotechnical risks associated with a Direct Pipe crossing of Ischua Creek at Milepost 62.4, as part of the Northern Access 2016 Pipeline Project. The opinions presented in the document are those of Mott MacDonald based on available information for the Northern Access 2016 Pipeline Project and are subject to change, if additional information is provided. I. Executive Summary As discussed herein, it is Mott MacDonald s professional opinion that the Direct Pipe Method is not suitable for this crossing for several reasons. Canal Place 520 South Main Street Suite 2457 Akron OH United States of America T +1 (330) First, the Direct Pipe method is a relatively new form of trenchless technology, and is primarily completed in soils lacking gravels, cobbles, and boulders (conditions anticipated under Ischua Creek) for small diameter installations of less than 30 inches. To allow for proper excavation of cobbles and boulders, a 42-inch diameter microtunnel boring machine (MTBM) would likely be required. Second, for the Ischua Creek crossing, the required installation length is greater than 1,000 feet (the recommended limit of this technology per the equipment manufacturer), and thus would require a larger diameter installation (likely 42-inch diameter pipe) than the proposed 24-inch diameter pipeline for the Northern Access 2016 Pipeline Project. However, if National Fuel decided to install a 42-inch diameter pipe for the Ischua Creek crossing, the installation of such an oversized pipe would create an unpiggable pipeline, as multi-diameter inspection pigs that can navigate a diameter change from 24" to 42" are not proven or commercially available. Additionally, while a larger diameter casing pipe could be installed to house the 24-inch diameter pipeline, cathodic protection issues may occur. Third, soils with gravel percentages of 93 percent have been identified under Ischua Creek, which can present significant risk and challenges to the MTBM and the overall installation process, such as the risk of stalling during the proposed crossing and an increase in the potential for annulus collapse and surface subsidence issues. Fourth, on the north side of the proposed crossing, a mixed-face condition of bedrock and soil may exist, further increasing subsidence and sinkhole risks. These risks are associated with over-excavating of the soil materials as the MTBM encounters the bedrock materials. 8Re: Northern Access 2016 Project Page 1 of 6

2 Finally, in the event the MBTM is unable to excavate through a nested cobble zone or boulder, the excavation of a rescue pit would be needed down to the front of the machine in order to clear the obstruction. Depending on where this occurred along the alignment, an excavation from the surface to the MBTM would be a very substantial excavation with very significant surface disturbance. This would negate any environmental benefit that a trenchless method otherwise affords. Given that the Ischua Creek crossing is in very close proximity to a USDA Conservation Easement, National Fuel has inquired about entry and surface disturbance inside of the easement, but has been advised that no entry or surface disturbance is permitted. Each of the aforementioned risks is discussed is greater detail in Section II below. II. Ischua Creek Direct Pipe Feasibility Evaluation and Associated Geotechnical Risks A. Direct Pipe Installations are Not Suitable for 24-inch Crossings As noted above, the Direct Pipe Method is a relatively new form of trenchless technology, and is used primarily for large diameter installations (greater than 30-in pipe diameter), especially in soils containing gravels, cobbles and possibly boulder, which are expected to be encountered under Ischua Creek. Direct Pipe installations for pipe diameters of less than 42 inches are limited to favorable ground conditions (lacking gravel and cobble deposits) and to installation lengths less than 1,000 feet, per equipment manufacturer recommendations. Larger diameter MTBMs can complete longer drive/installation lengths than smaller machines. This is related to the size of the drive motors and other components (such as a cutter wheel equipped with a larger number of disc cutters) that can be incorporated into larger diameter machines. For MTBM installations with diameters less than 42 inches, the achievable installation length in good ground conditions is typically less than 1,000 feet. For larger diameter machines, installation lengths upwards of 3,000 feet have been achieved in favorable ground conditions (soils lacking significant gravel, cobble, and/or boulder percentages). Based on the site constraints for the Ischua Creek Crossing, the required installation length of a Direct Pipe installation is over 1,000 feet. Additionally, for installations in gravels and cobbles, which are expected to be encountered under Ischua Creek, the minimum MTBM diameter is recommended by the manufacturer to be at least 42 inches. For the MTBM to be able to crush down particles it encounters, the particles must be able to pass through the cutter wheel and into the crushing chamber. Depending on rock strength and frequency, the high range for boulder size crushing is typically 30 percent of the outer diameter of the cutter wheel while the low range is 20 percent. For a 24-inch installation, the largest particle that can be consumed by the MTBM is approximately 4.8 inches, which represents a small cobble. To allow for excavation of larger sized particles, a larger diameter installation would be required. For example, a 42-inch diameter MTBM would be able to process a medium-sized cobble up to 8.4 inches in diameter. Page 2 of 6 To allow for excavation of even larger sized particles, the cutter wheel of the MTBM would need to be equipped with disc cutters to break down these larger particles into smaller pieces such that they can pass through

3 the cutter wheel and into the crushing chamber for further break down. However, cutter wheels with sufficiently sized disc cutters are limited to machines of 42 inches in diameter and larger. Additionally, even if National Fuel decided to install a 42-inch diameter pipe for the Ischua Creek crossing, the installation of such an oversized pipe would create an unpiggable pipeline, as multi-diameter inspection pigs that can navigate a diameter change from 24" to 42" are not available. National Fuel must meet the requirement under DOT 49 CFR that " each new transmission line and each replacement of line pipe, valve, fitting, or other line component in a transmission line must be designed and constructed to accommodate the passage of instrumented internal inspection devices". In addition, National Fuel, under DOT 49 CFR 192 Subpart O, is required to perform a baseline assessment of High Consequence Areas on a transmission pipeline and a reassessment minimally every seven (7) years thereafter. National Fuel utilizes In-Line Inspection as its assessment method to meet this requirement for new pipelines. Further, while a larger diameter casing pipe could be installed to house the 24-inch diameter pipeline inside of it, this situation would create numerous potential problems associated with the insertion process and would also pose serious potential for problems with protecting the 24- inch pipeline from corrosion. National Fuel has indicated that it follows industry best practices, which include not using casing/carrier pipe designs due to the potential for electrical shorts between the two pipes. Given the length of the bore, insulators would be problematic and can become disconnected from the carrier pipe, potentially resulting in a direct short. A non-corrosive environment must also be maintained within the casing to compensate for the inability of cathodic protection to reach the cased carrier pipe. Over time, any entry of groundwater to the interior of the casing may result in creation of a corrosive environment and possibly electrolytic communication between the carrier pipe and casing. Once complete isolation between the casing and the carrier pipe is compromised by the entry of water, the casing itself may become part of the cathodic protection circuit, placing additional demand on the protective system, providing unpredictable impact to the pipe within the casing, and suppressing the effectiveness of cathodic protection on uncased pipe adjacent to the cased segment. Because the installation of the 24-inch pipeline within a larger diameter casing pipe would have the aforementioned long term safety implications, such a design has been eliminated from consideration. B. Geotechnical Conditions under Ischua Creek Page 3 of 6 The geotechnical conditions for the Ischua Creek crossing are summarized in the geotechnical report entitled Geotechnical Drilling and Exploration Report Proposed Northern Access 2016 Pipeline HDD Crossing at Ischua Creek (Report) by Urban Engineers of New York, D.P.C. dated March 2016 and revised in July 2016, a copy of which is attached hereto for reference. As depicted in the Report, the anticipated geotechnical conditions include soils overlying bedrock materials. The soils include four (4) distinct soil units including gravel and sand with little to some silt and clay, clayey silt and sand with trace to little gravel, clay and silt with little to some sand and trace gravel, and gravel with trace to some clayey silt and sand. The soils containing gravel are observed to exist with thicknesses up to 100 feet and occur at the ground surface and at various depths below the ground surface (up to at least 175 feet below ground surface on the south side of the Ischua Creek crossing). Grain

4 size distributions completed on selected soil samples indicate gravels with compositions up to 93 percent of the soil by weight. Cobbles were noted at various depths in all of the boreholes. The bedrock material located beneath the soil layers includes interbedded sandstone and shale bedrock. C. The Anticipated Geotechnical Conditions Under Ischua Creek Leads to a Greater Risk of Stalling During Installation Soils with high percentages of gravels, cobbles and/or boulders (as noted in the Report) can present significant challenges to the operation and advancement of the MTBM. Large quantities of gravel and cobbles can choke or stall out the machine. High percentages of gravels and cobbles can also cause significant wear to the cutting tools and crushing chamber. In these soils, the operator is required to control the amount of gravels and cobbles that enter the crushing chamber at any one time to prevent the MBTM from exceeding its torque capabilities and stalling while in the process of crushing multiple pieces of gravel and cobble particles at the same time. Per the Report, soils with gravel percentages of 93 percent have been identified under Ischia Creek. This high percentage of gravel leads to a greater stalling risk for the proposed crossing. The risk associated with stalling of the MTBM includes the potential need to back out the MTBM machine and inability to support the surrounding ground as the pipe string and MTBM are removed from the ground. In soils with a high percentage of gravels and cobbles, the lack of a supporting presence to the surrounding soils leads to collapse of the overlying materials and increased potential for sinkhole and subsidence development. The removal of the pipe string and MTBM to clear a blockage also increases the abrasion that will occur on the product pipe s protective coatings, increasing the risk of damage as the pipe is forced to travel an additional length through the ground. D. Nested Cobbles Would Likely be Encountered During the Direct Pipe Installation, Which Have the Potential to Require Significant Excavation Along the Pipeline Alignment if Unable to be Cleared Page 4 of 6 While cobbles were not sampled during the geotechnical investigations due to size restrictions of the standard penetration test sampler, cobbles are inferred to exist since this area is in the Allegheny Plateau of New York, which was heavily glaciated during the Pleistocene Era. Known large cobbles exist in this area developed during that Era and should be expected along the drill path alignment. While cobbles on their own do not pose a significant risk to a Direct Pipe installation, where multiple cobbles exist (known as nested cobbles ), the MTBM is likely to experience great difficulty advancing forward through these materials. When the machine is not capable of excavating through the nested cobble zone, a rescue pit is needed to be excavated down to the front of the machine to clear the obstruction. Excavation requires direct access along the alignment. An obstruction could be encountered anywhere along the drill path, including in a wetland or stream, thus leading to significant potential resource impacts if excavation in these areas becomes necessary. The excavation area would need to be large enough to unearth the MBTM and free and provide ingress/egress for the required machinery. While pulling back from the excavation face with the MTBM can be attempted to dislodge the obstruction, this may not be able

5 to clear the obstruction. In addition, attempting to pull back from the excavation face may result in collapse of the overlying ground materials increasing settlement, subsidence, and sinkhole risks. E. Boulders and Cobbles Encountered During Pipe Have the Potential to Cause Significant Over Excavation and Associated Risks The ability to break down large boulders is highly dependent upon the type of cutters incorporated into the cutter wheel and the ability of the soil mass to hold/grip the boulder in place to allow the cutters to break down the larger particle into smaller pieces. If the soil mass does not have sufficient strength to keep the boulder in place, the boulder will tend to be pushed in front of the MBTM. This can lead to serious issues associated with over excavation, significant line and grade deviations and the requirement for a rescue shaft to break up the boulder. If the cobble or boulder were to fall out of the excavation face and accumulate on the bottom of the cutter wheel, the machine may try to ride up on top of the object causing significant deflections. These deflections can increase the risk of over bending the pipe during an installation. In terms of strength, MTBMs are reportedly capable of crushing materials with unconfined compressive strengths up to 200 MPa (30,000 psi). However, large quantities of materials with strengths above 130 MPa (20,000 psi) can significantly damage the cutters, cutter wheel, and/or crushing cone. Furthermore, in the event the MBTM is unable to excavate through a nested cobble zone or boulder, the excavation of a rescue pit would be needed down to the front of the machine in order to clear the obstruction. This requires a significant excavation from the surface to provide direct access along the drill alignment, so as to reach machine depth. While pulling back from the excavation face with the MTBM may be possible to dislodge the obstruction, it may not clear the object resisting forward progress. As noted above, attempting to pull back from the excavation face has the potential to result in collapse of the overlying ground materials, increasing settlement risks along the entire bore path. Given that the Ischua Creek crossing is in very close proximity to a USDA Conservation Easement, National Fuel has inquired about entry and surface disturbance inside of the easement. However, National Fuel has been advised that no entry or surface disturbance is permitted. F. Mixed-face Conditions Pose Significant Risks to a Direct Pipe installation. The term mixed-face condition refers to a mixture of either boulders and other soil constituents or bedrock and other soil constituents. Mixed-face conditions require the use of MTBMs equipped with appropriate cutters consisting of a mixture of disc cutters and soil tooling. As stated earlier, the requirement for disc cutters is limited to installations of 42 inches and larger. Page 5 of 6 If a MTBM encounters a mixed-face condition, over-excavation of the softer soils can occur as the MTBM slowly breaks down a larger sized particle or bedrock materials. The over-excavation of softer materials can lead to the development of sinkholes and large surface settlements. Thus, Direct Pipe installations should never be used at the interface of soil and bedrock, such as the mixed-face condition of soil and bedrock materials which may exist on the north side of the Ischua Creek crossing.

6 III. CONCLUSION In summary, it is Mott MacDonald s opinion that significant geotechnical risks exist for a Direct Pipe crossing of Ischua Creek associated with the high percentage of coarse grained gravels and cobbles observed at various depths beneath the ground surface on the south side of the crossing, potential for mixed-face conditions, and the inability to excavate the ground materials with a 24-inch installation. Due to these risks, a Direct Pipe crossing of Ischua Creek is deemed to carry a significant to extreme risk of failure. Regards, Glenn Duyvestyn Vice President T (330) C (216) glenn.duyvestyn@mottmac.com Page 6 of 6

2 3 4 Jacking Shaft Ground Surface Reception Shaft Microtunneling Process Jacking Shaft Ground Surface Reception Shaft Microtunneling Process Jacking Shaft Ground Surface Reception Shaft Microtunneling

More information

GEOTECHNICAL BASELINE REPORTS APPLYING THE GUIDELINES TO MICROTUNNELING

GEOTECHNICAL BASELINE REPORTS APPLYING THE GUIDELINES TO MICROTUNNELING The North American Society (NASTT) and the International Society for Trenchless Technology (ISTT) International No-Dig Show 2009 Toronto, Ontario Canada March 29 April 3, 2009 Paper A-2-04 GEOTECHNICAL

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations

More information

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 WM-T5-01 Problems Realized with Contractor-Proposed Pilot Tube Auger Boring Rebecca

More information

WARNING DO NOT BID ON THIS PROJECT

WARNING DO NOT BID ON THIS PROJECT WARNING DO NOT BID ON THIS PROJECT Nick H. Strater, P.G., Associate, Brierley Associates, Bedford, NH Brian C. Dorwart, P.E., P.G., Sr. Consultant, Brierley Associates, Bedford, NH For projects advertised

More information

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995 2013 ASCE Agenda Introduction Difficult Ground Microtunneling in Difficult Ground Craig Camp July 31, 2013 Microtunneling Characteristics (NASTT) Earth pressure balancing Hydrostatic pressure balancing

More information

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing

More information

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS 4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS This section discusses the geology, soils, seismicity, hazardous materials, and subsurface obstructions along Flower Street, and evaluates their potential

More information

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Earth Boring Co. Limited Trenchless Since 1947 Founded in Streetsville

More information

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TM1-T2-03 Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

More information

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject 56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea

More information

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Introduction Purpose Provide engineers and owners

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

What do you mean we can t do HDD?

What do you mean we can t do HDD? Clark Public Utilities Salmon Creek Crossing What do you mean we can t do HDD? Presented by Matt Hickey, PE Murray, Smith & Associates, Inc. and Russ Knutson, PE Clark Public Utilities Project Team Clark

More information

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA Miranda Roman D. *, LaFaso Edward Iseki, Inc. 7518 Carroll Road, San Diego, Calif. 92121-2402 USA This paper will discuss the

More information

For NGTL to file calculation of operating condition on pull back stress analysis.

For NGTL to file calculation of operating condition on pull back stress analysis. NOVA Gas Transmission Ltd. Exhibit No. B85 National Energy Board Hearing Order GH-001-2014 Undertaking U-10 Submitted November 25, 2014 Response to Undertaking given by Mr. Trout to Chairman Vergette at

More information

Report of Exploratory Test Pits

Report of Exploratory Test Pits Report of Exploratory Test Pits UNF Transportation Projects Stockpile Investigation Osprey Ridge Road Extension Jacksonville, Florida CSI Geo Project No.: 71-17-135-20 Arcadis Project No.: JK017002.0001

More information

August 15, 2006 (Revised) July 3, 2006 Project No A

August 15, 2006 (Revised) July 3, 2006 Project No A August 15, 2006 (Revised) July 3, 2006 Project No. 01-05-0854-101A Mr. David Reed, P.E. Protean Design Group 100 East Pine Street, Suite 306 Orlando, Florida 32801 Preliminary Soil Survey Report Polk Parkway

More information

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133 GEOTECHNICAL EXPLORATION AND ENGINEERING SERVICES REPORT CONDUCTED FOR: Immokalee Stormwater Master Plan Implementation Immokalee, Collier County, Florida PREPARED FOR: Mr. Marc Stonehouse, P. E. Project

More information

SPECIFICATION : BORING AND JACKING

SPECIFICATION : BORING AND JACKING SPECIFICATION 330524: BORING AND JACKING PART 1.0 GENERAL 1.1 DESCRIPTION 1.1.1 The work of this specification includes all labor, machinery, construction equipment and appliances required to perform in

More information

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River 3 rd Annual Rocky Mountain Regional No Dig Conference & Exhibition Westminster, CO November 8, 2012 David Bennett,

More information

Chapter A-10 GEOTECHNICAL ANALYSIS NORTH KANSAS CITY - LOWER (NATIONAL STARCH AREA)

Chapter A-10 GEOTECHNICAL ANALYSIS NORTH KANSAS CITY - LOWER (NATIONAL STARCH AREA) Kansas Citys, Missouri and Kansas Flood Damage Reduction Feasibility Study (Section 216 Review of Completed Civil Works Projects) Engineering Appendix to the Interim Feasibility Report Chapter A-10 GEOTECHNICAL

More information

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction

More information

penetrometer test (CPT) soundings were done to supplement the SPT data. Construction recommendations were made for most of the new buildings.

penetrometer test (CPT) soundings were done to supplement the SPT data. Construction recommendations were made for most of the new buildings. 2016 ASCE Ridge Branch Florida Section Project of the Year Grouted Pulldown Micropile foundation design for Four-story Building at Southeastern University, Lakeland, Florida Introduction and Project Description

More information

Take Me to the Other Side:

Take Me to the Other Side: Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Narrative Trenchless Feasibility Assessment for the Northern Access 2016 Project

Narrative Trenchless Feasibility Assessment for the Northern Access 2016 Project Narrative Trenchless Feasibility Assessment for the Northern Access 2016 Project Supplemental Information on Specific Streams of NYSDEC Concern and Statement of Project Compliance with New York State Water

More information

SHAFT CONSTRUCTION SECANT PILE

SHAFT CONSTRUCTION SECANT PILE by Rob jameson and eric lindquist feature story SECANT PILE SHAFT CONSTRUCTION Modern Tools and Techniques Allow Excavation to Depths Previously Considered Infeasible By Rob Jameson and Eric Lindquist

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Farmer, P.E. Hazen and Sawyer, P.C. Project Background City

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

CONDUCTED FOR: PREPARED FOR: 5 May 2016 YPC Project No. 16GY146

CONDUCTED FOR: PREPARED FOR: 5 May 2016 YPC Project No. 16GY146 GEOTECHNICAL EXPLORATION SERVICES REPORT CONDUCTED FOR: Collier Boulevard PREPARED FOR: Mr. Christopher L. Johnson Director of Land Development Stock Development, LLC Professional Circle, Suite 01 Naples,

More information

Geotechnical Exploration and Evaluation Report

Geotechnical Exploration and Evaluation Report Geotechnical Exploration and Evaluation Report Nassau Reclaimed Water Main From Radio Avenue to Harts Road Nassau County, Florida CSI Geo Project No.: 71-17-329-04 Client Project No.: JEA 09302-049-01

More information

Attachment A HDD Table Allegheny County

Attachment A HDD Table Allegheny County Attachment A HDD Table Allegheny County Drawing Name Drill Name County Township Drill Location Risk Assessment Level (Low / Medium / High) PA AL 0001.0000 RR.pdf CSX Railroad Allegheny Forward N: 40.230110

More information

IPC Company & DPI Presentation. February 2017

IPC Company & DPI Presentation. February 2017 IPC Company & DPI Presentation February 2017 WHO WE ARE OVERVIEW Innovative Pipeline Crossings Inc. (IPC) Founded in 2013, in Calgary Private Company Since July 2016 under new Management Supervisory Board

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo Moncton Watermain Relocation Moncton, New Brunswick TRS 2010 Dr Mark Knight University of Waterloo Presentation Outline Overview of the project Design and construction Issues Trenchless construction Lessons

More information

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing. SECTION 02221 TRENCHING, BACKFILLING AND COMPACTION PART 1 GENERAL 1.01 WORK INCLUDED A. Excavation for piped utility material. B. Provide necessary sheeting, shoring and bracing. C. Prepare trench bottom

More information

Pump Station Excavation

Pump Station Excavation Pump Station Excavation SPONSORED BY THE KIEWIT CORPORATION A capstone project for the The Department of Civil & Environmental Engineering in The Ira A. Fulton College of Engineering and Technology Brigham

More information

Design of pipeline installation. D-Geo Pipeline

Design of pipeline installation. D-Geo Pipeline Design of pipeline installation D-Geo Pipeline Design of pipeline installation D-Geo Pipeline General Pipelines are an important part of the underground infrastructure. They are the lifelines of our modern

More information

Appendix A - Vicinity Map Vicinity Map: Palm Beach Gardens City Hall Additions, 000 N Military Trail, Palm Beach Gardens, FL Proposed Location of Police Dept. Attached Addition Proposed Location of New

More information

A number of abbreviations and technical terms have been used in this guideline:

A number of abbreviations and technical terms have been used in this guideline: Page No: i CONTENTS 1.0 BACKGROUND 2 2.0 DEFINITIONS 2 3.0 INTRODUCTION 2 4.0 HORIZONTIAL DIRECTIONAL DRILLING GUIDELINE 2 4.1 HDD Process 2 4.2 HDD Methods 2 4.2.1 Pilot Bore 2 4.2.2 Reaming 2 4.2.3 Pullback

More information

Pipe Ramming with HDD. Presentation Outline

Pipe Ramming with HDD. Presentation Outline EXAMINING PIPE RAMMING DESIGN- A FORENSIC ANALYSIS OF A HIGH RISK PROJECT Kimberlie Staheli, Ph.D., P.E. Staheli Trenchless Consultants Seattle, WA, USA Presentation Outline Pipe Ramming State of the Art

More information

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded

More information

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E' North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show Orlando, Florida April 13-17, 2014 Paper MA-T4-02 Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA 14-3001 - Construct Bin Wall at HERD Eglin AFB, Florida MTEC Project Number 2014-101 November 10, 2014 Revised: January 5, 2015 Prepared For: Peterson Engineering,

More information

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 November 13, 2015 103IP3406 Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 Subject: Infiltration Testing Gates Road Valve Site Sunoco Pennsylvania Pipeline

More information

REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA

REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA AREHNA PROJECT NO. B-15-008 March 11, 2015 Prepared For: City of Tampa Stormwater Division 306 W. Jackson Street, 6N Tampa, Florida

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD) ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING

More information

WEF Collection Systems Conference Noble Gulch Trunkline Relocation Project: Implementation of a Multifaceted Trenchless Technology Program

WEF Collection Systems Conference Noble Gulch Trunkline Relocation Project: Implementation of a Multifaceted Trenchless Technology Program Noble Gulch Trunkline Relocation Project: Implementation of a Multifaceted Trenchless Technology Program Keith Corcoran, PE, Carollo Engineers Anne Prudhel, PE, Carollo Engineers ABSTRACT The Santa Cruz

More information

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU ABSTRACT MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU Christopher L. Windley, PE (McKim & Creed, Inc.)* Joshua P. Farmer, PE and Stephen D. Leitch, PE (Hazen & Sawyer, PC) *McKim

More information

CHANGE YOUR UNIVERSE S o i l - C e m e n t f o r B u i l d i n g F o u n d a t i o n s

CHANGE YOUR UNIVERSE S o i l - C e m e n t f o r B u i l d i n g F o u n d a t i o n s CHANGE YOUR UNIVERSE S o i l - C e m e n t f o r B u i l d i n g F o u n d a t i o n s Doug Hula, P.E. Gosling Czubak Engineering Sciences, Inc. Presentation Outline Introduction Overview Case Study Inspection

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

CC1602 Microtunneling

CC1602 Microtunneling CC1602 Microtunneling H.H. Sheikh Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E www.ictd.ae rachel@ictd.ae Course Introduction: Significant technical advances and increases in the utilization

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Milepost 210 to 218 Drainage Structure Pipe Jacking Creek County, Oklahoma July 1, 2016 Terracon Project No. 04165017 Prepared for: Benham Tulsa,

More information

Draft. Not yet Approved TABLE OF CONTENTS. Page

Draft. Not yet Approved TABLE OF CONTENTS. Page TABLE OF CONTENTS Page 5.0 1 5.1 1 5.2 1 5.3 1 5.4 1 5.5 1 5.6 1 5.7 1 5.8 MICROTUNNELING...1 5.8.1 SCOPE...1 5.8.2 PLANNING...1 5.8.2.1 Equipment Selection...2 5.8.2.2 Environmental Permitting...5 5.8.3

More information

Stage 4 Geotechnical Investigations Information Sheet

Stage 4 Geotechnical Investigations Information Sheet Stage 4 Geotechnical Investigations Information Sheet Geotechnical specialists will use a range of equipment to examine ground conditions by either excavating small shallow test pits of soil, using a mechanical

More information

Imperial s Sarnia Products Pipeline

Imperial s Sarnia Products Pipeline Imperial s Sarnia Products Pipeline Waterdown to Finch Project Community Information Session Imperial s Waterdown to Finch Project Important infrastructure to the Greater Toronto and Hamilton Area (GTHA).

More information

Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California

Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California TECHNICAL MEMORANDUM Preliminary Concepts for Soil-Bentonite Cutoff Wall Topock Compressor Station, Needles, California DATE: April 14, 2004 Pacific Gas and Electric Company (PG&E) is undertaking an expedited

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

Design of pipeline installation D-GEO PIPELINE

Design of pipeline installation D-GEO PIPELINE Design of pipeline installation D-GEO PIPELINE Design of pipeline installation D-GEO PIPELINE General Pipelines are an important part of the underground infrastructure. They are the lifelines of our modern

More information

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga,

More information

File No Supplemental November Geotechnical and Environmental Consulting Engineers

File No Supplemental November Geotechnical and Environmental Consulting Engineers Supplemental Information & Geotechnical Recommendations Proposed New Solar Valley Location B (East of Building No. 7) Cañada Community College 4200 Farm Hill Boulevard Submitted to: Mr. Peter Hempel Construction

More information

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING January 2007(Revision 1) Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK 1.04 CLASSIFICATION OF THE WORK 1.05 QUALITY ASSURANCE PART 2 PRODUCTS 2.01

More information

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities 1 Introduction This document, developed by the San Francisco Public Utilities Commission

More information

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 313430- PART 1 GENERAL 1.1 WORK INCLUDED A. Provide all equipment, material, labor and supervision to design and install Engineered Aggregate Piers for the soil reinforcement. Design shall rely

More information

BRADSHAW CONSTRUCTION CORPORATION

BRADSHAW CONSTRUCTION CORPORATION BRADSHAW CONSTRUCTION CORPORATION TUNNELING SPECIALISTS From a Contractor s Perspective Bradshaw s Experience 54 years as a tunneling contractor 26 years as a microtunneling contractor 25 years using conventional

More information

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety North American Society for Trenchless Technology (NASTT) NASTT s 216 No-Dig Show Dallas, Texas March 2-24, 216 TA-T5-3 Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic

More information

From the desk of G. A. Aaker, Jr., PE.

From the desk of G. A. Aaker, Jr., PE. SAMPLE CALCULATIONS TO DETERMINE THE REQUIRED MINIMUM WALL THICKNESS PER DOT 192 / ASME B31.8 FOR GAS TRANSMISSION AND DISTRIBUTION PIPING SYSTEMS 192.103 GENERAL Pipe must be designed with sufficient

More information

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 November 13, 2015 103IP3406 Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 Subject: Infiltration Testing Hopeland Road Valve Site Sunoco Pennsylvania Pipeline

More information

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii Reyn Hashiro 1, P.E., M. ASCE, Devin Nakayama 2, P.E. M. ASCE, and James Kwong 3, Ph.D., P.E., M. ASCE 1 Associate, Yogi Kwong

More information

ASCE PIPELINES 2015 CONFERENCE. Recap/Highlights by Bill Chavez, PUG Vice-Chairman Baltimore, MD August 23-26, 2015

ASCE PIPELINES 2015 CONFERENCE. Recap/Highlights by Bill Chavez, PUG Vice-Chairman Baltimore, MD August 23-26, 2015 ASCE PIPELINES 2015 CONFERENCE Recap/Highlights by Bill Chavez, PUG Vice-Chairman Baltimore, MD August 23-26, 2015 Microtunneling Technology Implemented for the Replacement of a 36-inch PCCP Force Main

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

REDUCING RISK AND VISITOR IMPACTS

REDUCING RISK AND VISITOR IMPACTS REDUCING RISK AND VISITOR IMPACTS Trenchless Solutions for Liberty Island Paul J. Mourt, PE Project Rules To Live By 1 Expect the Unexpected Do your homework 2 Risks need to be evaluated on every project

More information

Geotechnical Engineering Evaluation Campbell County Athletic Play Fields Campbell County High School South Campus Gillette, Wyoming

Geotechnical Engineering Evaluation Campbell County Athletic Play Fields Campbell County High School South Campus Gillette, Wyoming March 9, 2016 Proposal No. WYP16064 Campbell County School District Mr. Andy Mravlja 1000 W. 8 th Street Gillette, WY 82716 amravlja@ccsd.k12.wy.us RE: PROPOSAL Geotechnical Engineering Evaluation Campbell

More information

ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

ITEM NO. 824 SERVICE SUPPLY LINES (WATER) ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines installation and adjustment installed in accordance with these specifications and as directed

More information

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Michigan Department Of Transportation 3703F (11/06) SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006 Page 1 of 5 1 Materials 1.1 Pipe (a) Pipe shall be specifically designed and certified for microtunneling

More information

Geotechnical Investigations Water Main Construction

Geotechnical Investigations Water Main Construction Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine

More information

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River

Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River DEEP FOUNDATIONS 207 Case History: Value Engineering of Driven H-Piles for Slope Stability on the Missouri River W. Robert Thompson, III, 1 M.ASCE, P.E., Jeffrey R. Hill, 2 M.ASCE, P.E., and J. Erik Loehr,

More information

TECHNICAL NOTE HDPE Pipe and Utility Crossings

TECHNICAL NOTE HDPE Pipe and Utility Crossings TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER)

San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) San Antonio Water System Standard Specifications for Construction ITEM NO. 824 SERVICE SUPPLY LINES (WATER) 824.1 DESCRIPTION: This item shall consist of water service supply lines adjustment and installation

More information

SUPPORT OF TUNNELING WITH CHEMICAL GROUTING IN NEW JERSEY

SUPPORT OF TUNNELING WITH CHEMICAL GROUTING IN NEW JERSEY North American Society for Trenchless Technology (NASTT) No-Dig Show 2012 Nashville, TN March 11-15, 2012 Paper F-2-03 SUPPORT OF TUNNELING WITH CHEMICAL GROUTING IN NEW JERSEY Guy Dickes 1 1 Constellation

More information

August 3, 2018 TTL Project No Supplemental Test Borings Cleveland Bulk Terminal Cleveland, Ohio

August 3, 2018 TTL Project No Supplemental Test Borings Cleveland Bulk Terminal Cleveland, Ohio 1915 North 12 th Street Toledo, OH 43604-5305 T 419-324-2222 F 419-241-1808 www.ttlassoc.com August 3, 2018 TTL Project No. 1706701 Mr. Vito Melilli Coastal Engineer KS Associates, Inc. 260 Burns Road,

More information

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) PART 1 GENERAL 1.01 WORK INCLUDED SECTION 02360 / 31 34 30.13 ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) A. Provide all equipment, material, labor and supervision to design and

More information

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG.

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG. MEMORANDUM Levelton Consultants Ltd. 150-12791 Clarke Place Richmond, BC V6V 2H9 Canada Tel: 604 278-1411 Fax: 604 278-1042 E-Mail: rhillaby@levelton.com Web Site: www.levelton.com TO: STUART OLSON DOMINION

More information

Author(s) McCabe, Bryan; Reilly, Ciaran C.; Orr, Trevor L.

Author(s) McCabe, Bryan; Reilly, Ciaran C.; Orr, Trevor L. Provided by the author(s) and NUI Galway in accordance with publisher policies. Please cite the published version when available. Title Analysis of microtunnel jacking forces in alluvium and glacial till

More information

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014

APPENDIX F GEOTECHNICAL INVESTIGATION UPDATE CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 GEOTECHNICAL INVESTIGATION UPDATE. CITY OF SANTA CRUZ D RAFT EIR L A B AHIA H OTEL JANUARY 2014 October 5, 2013 Project No. SCR-0720 SANTA CRUZ SEASIDE COMPANY Craig French 911 Center Street, Suite B Santa

More information

Agenda for Today s Workshop

Agenda for Today s Workshop Agenda for Today s Workshop 10:00 to 10:45: Introduction Dr. Mo Najafi 10:45 to 11:15: Research and Testing Mr. Jwala Sharma 11:15 to 11:45: Cost Comparison Ms. Trupti Kulkarni 11:45 to 12:00: Lab Tour

More information

Concrete Pipe Jacking

Concrete Pipe Jacking Concrete Pipe Jacking Technical Brief CPAA Introduction Concrete pipe jacking is a method of installing pipelines without disrupting existing surface facilities or activities. Pipe jacking has been used

More information

June i TABLE OF CONTENTS

June i TABLE OF CONTENTS June 2005 - i - 05-526 TABLE OF CONTENTS SECTION PAGE 1.0 INTRODUCTION... 1 1.1 Purpose of the Investigation... 1 1.2 Description of the Project and Scope of Work... 1 1.3 Site Geology... 1 1.4 Site Description

More information

REPORT OF GEOTECHNICAL EXPLORATION KINLOCK FM REPLACEMENT NEW MANHOLE STRUCTURE JACKSONVILLE, FLORIDA ECS PROJECT NO A CLIENT ID: 0199

REPORT OF GEOTECHNICAL EXPLORATION KINLOCK FM REPLACEMENT NEW MANHOLE STRUCTURE JACKSONVILLE, FLORIDA ECS PROJECT NO A CLIENT ID: 0199 REPORT OF GEOTECHNICAL EXPLORATION KINLOCK FM REPLACEMENT NEW MANHOLE STRUCTURE JACKSONVILLE, FLORIDA ECS PROJECT NO. 3-6187-A CLIENT ID: 0199 Prepared for: JEA 1 West Church Street Jacksonville, Florida

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

Geotechnical Engineering Report

Geotechnical Engineering Report Geotechnical Engineering Report Turner Turnpike Widening Milepost 203 to 210 Drainage Structure Pipe Jacking Creek County, Oklahoma June 1, 2016 Terracon Project No. 04155197 Prepared for: Garver, LLC

More information

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE PART I - GENERAL 56.01 SCOPE: The Contractor shall furnish all labor, material, equipment and supplies and shall perform all work necessary for the

More information

Application for Underground Pipeline Crossing or Longitudinal of Railroad Property and or Track

Application for Underground Pipeline Crossing or Longitudinal of Railroad Property and or Track Wheeling and Lake Erie Railway Company Real Estate Department, 100 East First Street, Brewster, OH 44613 Application for Underground Pipeline Crossing or Longitudinal of Railroad Property and or Track

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information