1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Azerbaijan Highway 2 (P094488) Operation Name: Highway 2 (P094488) Project Stage: Implementation Seq.No: 14 Status: ARCHIVED Last Modified : Country: Azerbaijan Approval FY: 2006 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Azeryolservis JSC Key s Board Approval 17-Jan-2006 Original Closing 28-Feb-2011 Planned Mid Term Review Last Archived ISR 14-Feb-2011 Effectiveness 09-Aug-2006 Revised Closing 28-Feb-2014 Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) The main project development objective is to reduce road transport costs and improve access, transit and road safety within Azerbaijan's East-West and North- South corridors, through upgrading some sections of the Alat-Masalli road of the Baku-Iran highway (M3) and rehabilitating the Baku-Shamakhi road (M4). Has the Project Development Objective been changed since Board Approval of the Project? No Component(s) losure Authorized Public Disclosure Authorized Component Name Upgrading sections of the M3 highway between Alat and Masalli and Rehabilitation of the M4 road Baku-Shamakhi and key access roads. Provision of technical assistance, training and goods to support MoT's and RTSD's strengthening, RTSD road maintenance capacity and Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Component Cost Implementation Status Overview Disbursement ratio under the Second Highway Project reached the 40 percent mark (US$ 273 million out of US$675 million). It is estimated that additional US$40-45 million will be disbursed by the end of June 2011 (i.e., 47 percent). The Government is planning to request the Bank to consider additional financing for the Project to cover financing gap for the construction of the 62km Section 3 of M3 Alat-Masalli road Page 1 of 10

2 Results Project Development Objective Indicators Transit time from Alat to Masalli 180' Works are completed only on 31km of M3, South of Alat. Saving in transit time was not measured yet. 80' 31-Dec-2012 Vehicle operating cost from Alat to Masalli 100% Works are completed only on 31km of M3, South of Alat. VOC savings are yet to be measured via HDM4. Estimated completion date for sections 1C,2 and Kur river bridge. The contract for Section 3 is not signed yet. 88% 31-Dec-2012 Transit time from Baku to Shamakhi 150' 31-Dec ' Rehabilitation of the road is now completed. The 110 minutes is an estimate. Transit time will be measured during the year Estimated completion date for sections 1C,2 and Kur river bridge. The contract for Section 3 is not signed yet. 100' 30-Apr-2011 Page 2 of 10

3 Vehicle operating cost from Baku to Shamakhi 100% 31-Dec-2005 Rehabilitation of the road is almost completed, but the measurement is not done yet. 90% 01-Jan-2011 Decline in the percentage of road accidents in the project roads 0% 31-Dec-2005 Works are underway so no reductions in accidents are measured yet. Nonetheless, it is worth mentioning that no accident related tothe civil works occurred during construction so far. 30% 01-Feb-2014 Transit time from Ujar to Kurdamir Custom Indicator Minutes Apr-2011 Rehabilitation of the road is completed. The 42 minutes is an estimate that needs to be checked during site survey during year Page 3 of 10

4 Vehicle operating cost from Ujar to Kurdamir Custom Indicator Percentage Rehabilitation of the road is completed, but the measurements have not been made yet Apr-2011 Transit time from Tagiyev to Sahil Custom Indicator Minutes Rehabilitation of the road is expected to finish by December Apr-2012 Vehicle operating cost from Tagiyev to Sahil Custom Indicator Percentage Rehabilitation of the road is expected to finish by December Apr-2012 Transit time from Hajigabul to Bahramtapa Custom Indicator Minutes Rehabilitation is going to start. Thus no benefit yet. 31-Dec-2013 Page 4 of 10

5 Vehicle operating cost from Hajigabul to Bahramtapa Custom Indicator Percentage Rehabilitation is about to start. Thus no benefit yet Dec-2013 Increased travel frequencies for villagers in the Hajigabul-Bahramtapa region Custom Indicator Percentage 01-Jan-2009 Rehabilitation of the Rehabilitation of the road is not started yet. Procurement is ongoing Dec-2013 Average increase in farmgate prices of key commodities in Hajigabul- Bahramtapa region Custom Indicator Percentage 01-Jan-2009 Rehabilitation of the road is not started yet. Procurement is ongoing Dec-2013 Intermediate Results Indicators Number of km upgraded for Alat-Astara 0 31 Construction of 31km section is completed Dec-2012 Page 5 of 10

6 Number of km rehabilitated for Baku-Shamakhi Apr-2011 Number of km rehabilitated for Kurdamir-Ujar Custom Indicator Kilometers Works are completed Apr-2011 Number of km rehabilitated for Tagiyev-Sahil Custom Indicator Kilometers 01-Jan Apr-2012 Number of km rehabilitated for Hajigabul-Bahramtapa Custom Indicator Kilometers 01-Jan-2009 Works about to start Dec-2013 Page 6 of 10

7 Number of km rehabilitated for connecting roads Custom Indicator Kilometers 01-Jan-2009 Design of connecting roads is completed. Procurement will take place in Summer Feb-2014 Preparation of the revised Road law No yes The revised Road Law was prepared and submitted to the government. 31-Dec-2008 Number of km of roads data introduced in the RDB Custom Indicator Kilometers About 12400km of roads have been surveyed through videologging Jul-2012 Number of people trained in the use of RDB Custom Indicator Number On-the-job training is provided for staff of ARS and local staff of contractor Jul-2012 Page 7 of 10

8 Preparation of new geometric and structural design standards No new standards ongoing Consultant started assignment in January Aug-2011 Development of new civil engineering curriculum No new curriculum 01-Jan-2008 cancelled 31-Dec-2011 The assignment is canceled because of the lack of performance of the consultant. This assignment is transferred to another projectfinanced by the Bank (public investment capacity building project). Development of Road Safety Strategy No new strategy 01-Jan-2008 draft available The draft strategy is being reviewed by ARS 30-Jun-2013 Development of Road Master Plan No Road Master Plan 01-Jan-2008 ongoing 23-Dec-2010 Consultant service going to start. 30-Apr-2012 Page 8 of 10

9 Preparation of the new norms for maintenance Data on Financial Performance (as of 21-Apr-2011) Financial Agreement(s) Key s No new norms ongoing The consultant is deployed and has issued inception report. 31-Aug-2011 Project Loan No. Status Approval Signing Effectiveness Closing P IBRD Effective 17-Jan May Aug Feb-2013 P IBRD Effective 29-Apr Dec Apr Feb-2013 P IBRD Effective 24-Jun Jul Oct Feb-2014 P IDA Effective 24-Jun Jul Oct Feb-2014 Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IBRD Effective USD P IBRD Effective USD P IBRD Effective USD P IDA Effective USD Disbursement Graph Page 9 of 10

10 Key Decisions Regarding Implementation Disbursement under the project is now up to par. About 40 percent of the proceeds have been paid and disbursement is expected to reach 47 percent by June Recent award of civil works contracts will allow this trend to last. The quality of civil works is satisfactory. The MoTC and the ARS (in charge of implementation) need to make sure that the supervision firms and the contractors for the sections 1C and 2 of M3 Alat-Masalli and R6 Tagiyev - Sahil road (Baku bypass) are performing. At present, the contractors for M3 does not deploy fast enough and the contractor for R6 is behind schedule by about half a year. Restructuring History There has been no restructuring to date. Related Projects P Highway 2 - Additional Financing, P Second Additional Financing Highway II Page 10 of 10