1 SAFETY» Total Man Hours Worked This Week: 6254» Total Man Hours on Project: » Crafts On Project This Week: 7» OSHA Recordable Rate: 0 February 14, 2016 P a g e 1

2 CURRENT CONSTRUCTION ACTIVITIES EAST ZONE.» Continued interior wall Building G.» Continued Grout/Caulk of Building F.» Continued Building E.» Continue Building E.» Continued Plumbing Building G.» Continue Window Frame Building G. Window Building G SITE & WEST ZONE» Completed Domestic Water HUB Utility Yard» Installed Grease HUB Utility Yard.» Installed East Parking Lot.» Completed Auger Cast Building B.» Continued Storm Line West Spine.» Continued Ductbank West Zone. Plumbing Building G February 14, 2016 P a g e 2

3 NEXT WEEK S ACTIVITIES EAST ZONE» Continue Precast Building E.» Continue Building E.» Continue Window Frame Building G.» Begin Prep for 4th floor Topping Building F.» Begin Roof Building F.» Continue Exterior Bldg. G.» Begin Ice & Water Bldg. G.» Continue Brick Relief Bldg. G. HUB Building Pad Prep SITE & WEST ZONE Grease HUB Utility Yard» Begin chipping Pile HUB.» Begin Footings and HUB.» Begin East Parking Lot.» Continue Storm Line West Spine» Begin Ductbank HUB Utility Yard.» Set Manholes 4 E&C.» Continue Domestic HUB Utility Yard.» Continue Wire Parking Lot Lights.» Continue Racking Manholes. February 14, 2016 P a g e 3

4 MANPOWER TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Holder Construction Company General Contractor American Deep Foundation Auger cast piles Baker Roofing Sheathing and Shingles C&C Fence Site Fence Cowart Tree Mulch Tree Removal Davis Crane Erectors Pre-Cast Erection D.H. Griffin Tank Foundation Removal Gainesville Mechanical Plumbing Hutch-N-Son Early Site Work st Choice Glass Glass JBR Construction Early Site Work King Asphalt Asphalt Labor Finders Labor Force Metro Power Underground Electrical Osteen Chill Water pipe Precision Concrete R.E. Mclean Tank Tank Demo Reeves Grading Site Grading & Utilities RJ Coogan Deck Installers Ruppert Landscaping Landscape/ Hardscape Sears Contract Drywall/Metal Trusses Silt Fence Installation Site Erosion Control Southern Mechanical Inc. Electrical/Plumbing Tree South Arborist Upstate Curb Curb and Gutter Valley Farm Construction Tree removal/grading TOTAL February 14, 2016 P a g e 4

5 WEATHER CURRENT WEEK Rain Days This Week = 0 Rain Days To Date = 40 SAFETY REVIEW LOG Man-hours worked Douthit Hills Monthly OSHA Statistics RCR/DART Mar- Apr-15 May Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Man-Hours Worked RCR DART R February 14, 2016 P a g e 5

6 MANPOWER CHART Douthit Hills Workforce Reeves Grading Metro Power American De ep Foundations Davis Crane Erectors Sears Contract Gainesville Mechanical 1st Choice Glass Precision Concrete Southern Me chanical Baker Roofing Holder February 14, 2016 P a g e 6