SCARSDALE PUBLIC SCHOOLS Bond Project Planning

Size: px
Start display at page:

Download "SCARSDALE PUBLIC SCHOOLS Bond Project Planning"

Transcription

1 SCARSDALE PUBLIC SCHOOLS 2017 Bond Project Planning October 23, 2017

2 2017 Bond Project Planning - Overview 1) December 2014 Bond ( ) Work in this bond included for Heathcote, Edgewood, Middle School, High School, Quaker Ridge Roof and District-wide technology needs. Major work identified for Greenacres deferred for additional study and future bond projects. 2) Greenacres Feasibility Committee ( ) Engineering and Building Condition Studies compared to new building or a model program. Any work at Greenacres identified as only part of a larger scope of work. No formal recommendation made to the Board of Education regarding renovation or new building. Leaving the building as is (renovations only) was not an option that this committee favored. Focus of future discussion should be building conditions and educational adequacy.

3 2017 Bond Project Planning 3) Greenacres Feasibility Committee Re-convened ( ) Using same data factors, recommendations of the committee remained consistent with initial committee; focus on building conditions and educational adequacy. No recommendation is made in regards to expansion or new build however leaving the building as is (renovations only), once again, was not an option that this committee favored. 4) Building Conditions Survey (BCS) (Fall 2015) District undergoes NYSED mandated review of all District buildings. 5) Roof Master Plan Completed (Spring 2016) 6) Fields Master Plan Completed (Spring 2016)

4 2017 Bond Project Planning 7) Building Committees (Spring 2016) Meetings held at each building except at Greenacres due to feasibility committee work. Members at each building included administration, teachers, and parent representatives. The purpose of each committee was to identify and prioritize potential work in their building which would make a meaningful impact on the experience on building use by students, teachers, and community members. Building Condition items also thoroughly reviewed. Common priorities across the buildings included airconditioning, security vestibules, and food service solutions.

5 8) BBS Architects 2017 Bond Project Planning The District engaged BBS Architects in Feb for the planning, design, and construction phases for all upcoming capital projects, including a major renovation/replacement of an elementary school. They were charged with bringing an objective recommendation at all schools, including Greenacres. Studied and reviewed all previous work including: Building Conditions Survey (BCS) & Greenacres Feasibility Committee reports, Engineering reports & Building Committee priorities; and Roof Master Plan & Fields Master Plan. BBS engineering and architectural teams then analyzed each building in depth and prepared a BCS master list, which was combined with original BCS. All building schedules were studied and building tours and interviews with key personnel were conducted to gather a clear understanding of how each building functions in delivering instruction.

6 2017 Bond Project Planning Scope Development Formal presentations were made to the Board of Education: May 22, 2017 Presentation of all facility needs and some initial design enterprise solutions to address major issues. Renovation and expansion to Greenacres was formally recommended over new construction. June 12, 2017 Presentation of updated building Master plans based on feedback from the BOE, building committees, and community. Work at the Middle and High Schools recommended to be deferred for future committee study and development. July 6, 2017 Board of Education agrees to Administration s recommendations to move forward with project planning for the following: 1) District-wide facility needs focusing on roofs, building systems, electrical upgrades, code compliance and health & safety issues; 2) The addition or upgrading of security vestibules at all elementary buildings and the Middle School; and 3) The renovation and expansion of Greenacres Elementary School 4) In addition, to provide a final scope of a bond project at or near tax neutral (+/- $5 million).

7 2017 Bond Project Planning Scope Refinement Continued scope refinement since July based on: Continued study of the buildings Feedback from staff Feedback from the community Recommendations from the Greenacres Building Committee Study and recommendations from the District-wide Facilities Committee

8 Scarsdale Vision for Learning & Draft Scope Review Greenacres Spatial District-wide Facility Needs Security Vestibules

9 Scarsdale s Vision for Learning A Strategic Planning Journey (2008-present)

10 Scarsdale s Vision for Learning A Scarsdale Education for Tomorrow 2.0 It s not what you know, it s what you do with what you know. -Tony Wagner

11 Innovation occurs at the intersection of people, place & space.

12 Elementary Learning Spaces Manageable & Sustainable Child-centric Flexible Learning within every space: Whole class instruction Partner/collaborative work & feedback Presentation spaces Privacy spaces (small group, independent) Areas to showcase student ideas and work products

13

14 Classroom Spaces for Innovation

15

16 Common Spaces for Innovation

17 Greenacres as a Learning Commons Whole School Learning Participatory learning community Inquiry Problem & Project- Based Project Learning Discovery Learning Self-Directed Maker Experimental Collaboration Teacher as Researcher Tech Sandbox Professional Learning Adapted from The Elementary School Learning Commons: A Manual. David V. Loertscher and Carol Koechlin;; Learning Commons Press, 2015, ISBN:

18 SET 2.0

19 Bond Project Scope - Greenacres Spatial Needs GREENACRES - Spatial Needs Interior Reconstruction & Upgrades 7,662,701 Expansion 14,379,492 Casework, Technology & Equipment 1,275,834 Engineering & Site 3,102,913 Greenacres Building Committee Recommendations 3,674,408 Historic Renovation/Preservation Contingency 1,000,000 TOTAL GREENACRES SPATIAL NEEDS $31,095,348

20 2017 Bond Project Scope Review District-wide Facility Needs Components of District-wide Improvements (including Greenacres) Heating & Ventilation Roofs Boilers & Steam Traps Field & Site improvements Electrical upgrades Structural repairs ADA/Doors and Handrail compliances Flooring improvements Base Security Cameras installation Other Miscellaneous

21 2017 Bond Project Scope Heating & Ventilation The work identified in this area includes the installation of ventilation systems throughout the District. Not included in original BCS, but identified in further inspection of building by BBS. Does not address air conditioning. These are priority 1A or 1B items. Edgewood Installation of mechanical fresh air system. Fox Meadow - Installation of mechanical fresh air system. Greenacres Replacement of older unit ventilators. Heathcote Installation of mechanical air handler for the gym. Quaker Ridge Installation of mechanical fresh air system to 15 classrooms and other areas. Middle School Replacement of older unit ventilators. High School Replacement of older unit ventilators.

22 2017 Bond Project Scope Heating & Ventilation Facility Needs - Heating & Ventilation Edgewood 2,935,456 Fox Meadow 2,650,000 Greenacres 1,585,997 Heathcote 450,000 Quaker Ridge 1,140,000 Middle School 155,000 High School 3,330,000 TOTAL HEATING & VENTILATION $12,246,453

23 2017 Bond Project Scope Roofs The work identified in this area includes the replacement of certain roofs in the District within the next five years as identified by the Roof Master Study. Identified roofs are currently in fair condition, approximately 25+ years of age (as of 2017), and are out of warranty. The District currently budgets and spends $275,000 on annual upkeep of its roofs. All Roofs: Priority 3

24 2017 Bond Project Scope Roofs Facility Needs - Roofs Edgewood (2021) 377,076 Fox Meadow - Greenacres (2023) 911,006 Heathcote (2019) 2,412,384 Quaker Ridge (2021) 660,812 Middle School (2021 & 2022) 3,506,579 High School (2020) 1,739,028 TOTAL ROOFS $ 9,606,885

25 2017 Bond Project Scope Boilers & Steam Traps Many of the District s boilers were replaced as part of a District-wide project in the early 1990 s. These boilers were identified in the original Building Condition Study and on further review by BBS. They were elevated from a priority 3 to a priority 2 based on recent expensive annual repairs required to keep them operable. Steam traps are located in a few of the District s buildings as part of each building s heating system. They were all replaced as part of the District s Energy Performance Contract in 2009 and typically have a life of 7 years. Steam traps typically fail one at a time and not catastrophically.

26 2017 Bond Project Scope Boilers & Steam Traps Facility Needs - Boilers & Steam Traps Edgewood 550,000 Fox Meadow 575,000 Greenacres 550,000 Heathcote 400,000 Quaker Ridge - Middle School 250,000 High School 1,106,081 TOTAL BOILERS & STEAM TRAPS $ 3,431,081

27 2017 Bond Project Scope Fields & Site Work The work identified in this area includes the following: Edgewood & Fox Meadow Rectifies drainage issues at window well locations. Priority 3. Greenacres Site rehabilitation and development after expansion and drainage window well locations. Priority 3. Quaker Ridge Mitigate flooding at generator gates. Priority 3. Middle School Mitigates drainage issues, wall repair at bus driveway and fence replacement. Priority 3. High School Dean Field renovation per Fields Master Plan Priority 3. Non-building brick wall repairs. Priority 2

28 Dean Field 2017 Bond Project Scope Fields & Site Work Identified as part of previous budgets to receive upgrades. Further Master study identified Dean Field as the second highest priority field in need of improvements behind Butler field. Butler Field improvements are currently slated for the Budget. Ranking based on a review of programmatic, preservation of facilities, aesthetics of facilities, sustainability, community use etc., in comparison to other District-wide site and field improvement locations. Fields Master Study completed by landscape architect consultant and further reviewed by BBS landscape architects. Total Estimated Cost = $1,400,000

29 2017 Bond Project Scope Fields & Site Work Facility Needs - Fields & Site Work Edgewood 85,000 Fox Meadow 75,000 Greenacres 575,000 Heathcote - Quaker Ridge 20,000 Middle School 201,000 High School 1,629,500 TOTAL FIELDS & SITE WORK $ 2,585,500

30 2017 Bond Project Scope Electrical Upgrades Identified electrical upgrades as part of the Building Condition Survey and later confirmed or added to by BBS inspections. District-wide Replace older electrical panels in all buildings. Priority 3. Edgewood Utility transformer replacement. Priority 3. Emergency lighting improvements. Priority 2. Greenacres Upgrade fire alarm systems. Priority 1B/2. Middle School Additional electrical panels. BBS study only. Priority 3.

31 2017 Bond Project Scope Electrical Upgrades Facility Needs - Electrical Upgrades Edgewood 638,545 Fox Meadow 150,000 Greenacres 574,326 Heathcote 200,000 Quaker Ridge 150,000 Middle School 475,000 High School 100,000 TOTAL ELECTRICAL UPGRADES $ 2,287,871

32 2017 Bond Project Scope Building Structure The work identified in this area includes repairs to the main structure of the building. Middle School Repair water intrusion in Butler breezeway. Identified by District staff. Priority 3. Excavate and repair wall to stop water intrusion in boiler room. Priority 2. Rebuild brick masonry outside Cooper link corridor and various areas of tuck pointing around the building. Priority 2. High School IT workspace water intrusion, excavate & waterproof (110ft between stairwells). Priority 3. Other masonry repairs to the building. Priority 2.

33 2017 Bond Project Scope Building Structure Facility Needs - Building Structure Edgewood - Fox Meadow - Greenacres - Heathcote - Quaker Ridge - Middle School 575,000 High School 557,500 TOTAL BUILDING STRUCTURE $ 1,132,500

34 2017 Bond Project Scope ADA/Doors/Handrails All work identified by BBS during building inspections. All items listed as priority 1. Representative items district-wide include the following: Widening doorways where required to allow wheelchair access Installation of door openers where required Replacing non-compliant handrails Installation of handrails where required Replace doors with uneven leafs for ADA compliance where required Greenacres Installation of handicapped ramp to upper playground and handicapped playground station

35 2017 Bond Project Scope ADA/Doors/Handrails Facility Needs - ADA/Doors/Handrail Compliances Edgewood 210,000 Fox Meadow 120,000 Greenacres 299,600 Heathcote 66,000 Quaker Ridge 66,000 Middle School 452,500 High School 533,500 TOTAL ADA/Doors/Handrail Compliances $ 1,747,600

36 2017 Bond Project Scope Flooring Improvements Flooring improvements identified in the Building Condition Study and BBS inspections and recommendations as follows: Greenacres Replace all corridor fritz tile. Priority 3 VAT floor tile removal. Priority 3 High School Remediate floor deflection outside nurse s office. Priority 2.

37 2017 Bond Project Scope Flooring Improvements Facility Needs - Flooring Improvements Edgewood - Fox Meadow - Greenacres 539,135 Heathcote - Quaker Ridge - Middle School - High School 200,000 TOTAL FLOORING IMPROVEMENTS $ 739,135

38 2017 Bond Project Scope Security Improvements Installation of base security camera systems per recommendations of BBS and security consultants. Priority 2.

39 2017 Bond Project Scope Security Improvements Facility Needs - Security Improvements Edgewood 56,250 Fox Meadow 56,250 Greenacres 56,250 Heathcote 56,250 Quaker Ridge 56,250 Middle School 125,000 High School 187,500 TOTAL SECURITY IMPROVEMENTS $ 593,750

40 2017 Bond Project Scope Misc. Items Misc. items by building are as follows: Edgewood Repair/remove standpipe system. Priority 1A. Fox Meadow Repair/remove standpipe system. Priority 1A. Greenacres Extensive interior painting. Priority 3. Replace second floor lockers with wider doors. Priority 3. Corridor ceiling restoration. Priority 3. Relocate six drinking fountains. Priority 1. Heathcote Replace non safety and/or wire glass glazing at corridors. Priority 2. Quaker Ridge Water mitigation to stop flooding elevator shaft room. Priority 3. Middle School Replace ceiling tile in small gym. Priority 2.

41 2017 Bond Project Scope Misc. Items Facility Needs - Miscellaneous Items Edgewood 100,000 Fox Meadow 100,000 Greenacres 487,000 Heathcote 99,000 Quaker Ridge 30,000 Middle School 152,000 High School - TOTAL MISCELLANEOUS $ 968,000

42 2017 Bond Project Scope Facility Needs Totals Facilities Needs - Totals Edgewood 4,952,327 Fox Meadow 3,726,250 Greenacres 5,578,314 Heathcote 3,683,634 Quaker Ridge 2,123,062 Middle School 5,892,079 High School 9,383,109 TOTAL FACILITY NEEDS $ 35,338,775

43 2017 Bond Project Scope Security Vestibules Security Vestibules were discussed at building committee meetings and were designated as a high priority in addition to air conditioning. Security Vestibules add an extra layer of security at main entranceways and are recommended by the District s security consultant.

44 2017 Bond Project Scope Security Vestibules Security Vestibules - Totals Edgewood 42,176 Fox Meadow 42,176 Greenacres - (included with Greenacres spatial) - Heathcote 156,896 Quaker Ridge 156,896 Middle School 310,101 High School - TOTAL SECURITY VESTIBULES $ 708,245

45 2017 Bond Project Scope Draft Totals Bond Project Draft Scope Totals Facility Needs 35,338,775 Greenacres Spatial 31,095,348 Security Vestibules 708,245 TOTAL BOND PROJECT DRAFT SCOPE $ 67,142,368

46 2017 Bond Project Scope Draft Totals Bond Project Draft Scope Totals Facility Needs - Excluding Greenacres 29,760,461 Greenacres Project 36,673,662 Security Vestibules 708,245 TOTAL BOND PROJECT DRAFT SCOPE $ 67,142,368

47 2017 Bond Project Scope Draft Totals Facility Needs - by Priority Area Priority 1 716,600 Priority 1A 9,188,545 Priority 1B 2,061,453 Priority 2 5,387,831 Priority 3 17,984,346 TOTAL ALL PRIORITIES $35,338,775

48 COMMITTEE UPDATES Greenacres Building Committee Last week s meeting focused on drop-off and pick up logistics. District-wide Facilities Committee Last week s meeting continued to focus on air-conditioning. Committee agreed that air-conditioning instructional classroom spaces is a priority. Next discussion will focus on developing a recommendation for air conditioning in context of a full bond project recommendation.

49 2017 Bond Project Timeline October 23rd Board of Education Meeting Review of Current Scope Items November 6 th Public Forum November 13 th Board of Education Meeting Final Project Recommendations from Administration November 27 th Board of Education Meeting Adoption of Bond Resolution January 24th Residents Vote on Bond Proposition

50 APPENDIX

51 Greenacres Building Committee - Information Modular Classroom Costs Purchase Lease Bond Lease Budget Total Lease Modulars - 2 1,082, , , ,014 Modulars - 4 1,495, , ,058 1,001,597 Modulars - 6 1,920, , ,066 1,287,983