Advance Notice June 27, Cougar Ridge and Sunset Elementary Schools Change Order #7 Crawford
|
|
- Melvin Turner
- 5 years ago
- Views:
Transcription
1 Advance Notice June 27, 2018 Cougar Ridge and Sunset Elementary Schools Change Order #7 Crawford Action to be taken: I move the board approve the Cougar Ridge and Sunset Elementary Schools Change Order #7 from Cornerstone General Contractors, Inc., in the amount of $455, plus $45, WSST for a total of $501, Each proposal request listed on the attached Change Order No. 7 has been reviewed by the District Construction Coordinator for the project. Cost proposals were reviewed and reduced where possible and as proposed represent an equitable charge for the scope of work involved. CI037 CI041 CI048 CI050 CI051 CI052 CI065 CI072 CI074 CI075 CI077 CI079 CI082 CI086 CI090 CI097 CI098 CI104 CI106 CI108 CI111 CI115 CI117 CI118 CI1015 CI1018 CI024 CI026 CI032 CI036 CI039 CI042 CI044 CI051 CI062 Revise downspout connections. When demo and excavation was complete, conditions did not match original drawings. Interior finish changes requested by Owner. Add hallway soffit to match existing. Add tackable vinyl wallcovering as directed by Owner. Additional electronic access controls as directed by Owner. Reception finishes revised by Owner. Loading dock column to provide easier loading/access to existing door. Move dry sprinkler line due to and conflicts. Miscellaneous structural changes due to. Provide concrete wall cover at loading dock due to relocation of loading dock. Remove skylight, repair dry-rotted joists and replace roofing as directed by Owner. Move existing electrical to accommodate new heat pumps due to discrepancies in original drawings. Added Glue Lam Beam at Northeast entry. Revise wall flashing to expose Glu Lam Beam and provide watertight seal at top of masonry. Revise corridor 120 finishes to blend with existing finishes and detailing. Align roof system with outriggers to avoid need for hot tar roofing and resulting construction odors. Revise ductwork due to ceiling duct conflicts; existing duct lower than shown. Additional 2-hour firewall per Code Inspector. Change alum sill flashing to sheet metal due to product not being available. Provide beam connection due to connection missing on shop drawings. Demo SAGE room ceiling to accommodate installation of heat pump and replace ceiling. Revise area of ceiling incorrectly shown alternate on drawings. Route chiller piping overhead to replace the existing leaking underground piping per Owner. Additional steel and connections per submittal review comments. Add steel support at screen wall not shown on drawings. Add structural tie-in at Grid 21 due to connections not shown. Add tackable wall covering to hallways and classrooms per Owner. Revise kitchen catwalk due to insufficient detail on structural Revise expansion joint detail to cover inconsistent gap at existing building due to original construction inaccuracy. Revise roof detail and dimensions at existing loading dock overhang. Construct and insulate new roof pony walls for seismic joint redesign per Owner Envelope Consultant to enhance waterproofing detail. At kitchen, revise framing and structural detailing. Additional steel joist revision per shop drawing review. Change smooth to fluted CMU at base of wall. Furr existing wall in Commons due to unforeseen condition.
2 Advance Notice June 27, 2018 Cougar Ridge and Sunset Elementary Schools Change Order #7 Crawford (Continued from previous page) Original Contract Sum (without $15,215, WSST) Original Contract Total including $16,736, WSST Previous Contract Total including $17,791, change orders and WSST Change Order # 7 $455, % WSST $45, Total Change Order #7 $501, Revised Contract Total $18,293, The revised contract total is within the project budget. Steve Crawford will be available to answer any questions the board may have regarding this recommendation. Please scroll down to view Cougar Ridge and Sunset Elementary Schools Change Order #7 (3 pages).
3 CHANGE ORDER #07 PROJECT: Combined Cougar Ridge and Sunset Elem Schools Cougar Ridge Elementary School Sunset Elementary School th Ave SE 4229 W Lake Sammamish Parkway SE Bellevue, WA Bellevue, WS OWNER: Issaquah School District 656 NW Holly Street Issaquah, WA INITIATION DATE: 6/20/2018 ARCHITECT S PROJECT NO.: #16991 & TO: Cornerstone General Contractors North Creek Parkway, #115 Bothell, WA ARCHITECT: BASSETTI ARCHITECTS 71 Columbia Street, Suite 500 Seattle, WA CONTRACT FOR: General Construction CONTRACT DATE: Aug 1, 2017 You are directed to make the following changes in this Contract: CGC # Ref # Description Cost Project CI037 RFI-87 (E) Downspout Connection Conflicts due to $22, CRES CI041 CCD05 Interior Finishes Changes ($2,515.00) CRES CI048 ASI06 Add Hallway Soffit to match existing aesthetic $2, CRES CI050 CCD23 Add Vinyl Wallcovering as directed by Owner $92, CRES CI051 CCD09 Access Controls added as directed by Owner $48, CRES CI052 CCD10 Reception finishes changed as directed by Owner $1, CRES CI065 CCD15 Loading Dock Column Move due to existing door clearances needed $15, CRES CI072 Move Dry Sprinkler Line due to unforeseen $3, CRES conditions CI074 CCD18 Misc Structural Changes not shown on drawings $5, CRES CI075 CCD19 Conc wall cover at loading dock to deal with CI077 CCD21 Remove Skylight, repair dry-rotted joists as directed by Owner CI079 RFI-167 Move Elec to accommodate new Heat Pumps, $8, CRES $30, CRES $9, CRES CI082 RFI-176 Added GLB at Northeast Entry $4, CRES CI086 RFI-172 Masonry top of wall Flashing to emphasize Glu Lam Beam $10, CRES CI090 Corridor 120 finishes to tie new to existing $2, CRES CI097 Align Roof System with Outriggers to avoid roofing kettle, avoiding construction smell impact $3, CRES CI098 RFI-125 Ceiling Duct Conflicts, existing duct lower than $1, CRES
4 Combined Cougar Ridge and Sunset Elem Schools CO #7 Project Number : & intended CI099 CCD29 UC lighting in Health 103 added as directed by Owner CI104 RFI Hour Fire Wall clarification due to drawing ambiguity CI106 Change Alum Sill Flashing to Sheet Metal due to product not being available CI108 RFI-109 Request Beam Connection due to connection missing on drawings CI111 Demo SAGE Room Ceiling to accommodate installation of Heat Pumps $2, CRES $2, CRES $5, CRES $4, CRES $4, CRES CI115 Ceiling Install Incorrectly Designated as Alternate $2, CRES CI117 PR-01 Route Chiller Piping Overhead to replace the existing failing underground per Owner direction CI118 Submittal # $50, CRES Added Steel Per Submittal Review Comments $1, CRES CI015 RFI-49 Steel Support At Screen Wall not shown on drawings $13, SES CI018 RFI025 Structural Tie-in at Grid 21 due to connections not shown CI024 CCD-08 Add wall covering to hallways and classrooms per direction per Owner CI026 RFI-74 Kitchen Catwalk Revisions due to insufficient detail on structural $21, SES $34, SES $3, SES CI032 RFI-76 Expn Joint Gap Issue due to existing building not $6, SES built accurately CI036 RFI-89 Roof Detail and Dimensions at F & 17.2 $1, SES CI039 RFI-92 Construct and Insulate Roof Pony Walls for seismic joint redesign due to Owner Envelope Consultant $21, SES CI042 RFI-106 Kitchen Facade Framing structural detailing $2, SES CI044 RFI-10.1, RFI-15, ASI-03 Detailing Steel Joist Revision due to shop drawing review $7, SES CI051 Change Smooth to Fluted CMU at base of wall $1, SES CI062 CCD17 Furr Existing Wall in Commons due to unforeseen conditon $5, SES Total $455, Not valid until signed by both the Owner and Architect. Signature of the Contractor indicates his agreement herewith, including any adjustment in the Contract Sum or Contract Time. \\2K12FILE1\Projects\JOBS\ISD Sunset ES\L Construction Admin\L04 Change Orders\CO 07\CO 07.docx Page 2 of 3
5 Combined Cougar Ridge and Sunset Elem Schools CO #7 Project Number : & The original (Contract Sum) (Guaranteed Maximum Cost) was $15,215, Net change by previously authorized Change Orders $959, The (Contract Sum) (Guaranteed Maximum Cost) prior to this Change Order was $16,174, The (Contract Sum) (Guaranteed Maximum Cost) will be (increased) (decreased) (unchanged) $455, by this Change Order The new (Contract Sum) (Guaranteed Maximum Cost) including this Change Order will be $16,630, The Contract Time will be (increased) (decreased) (unchanged) by 0 days The Date of Substantial Completion as of the date of this Change Order therefore is 8/17/2018 Bassetti Architects P.S. 71 Columbia Street, Suite 500 Seattle, WA Cornerstone General Contractors North Creek Parkway, #115 Bothell, WA Issaquah School District 656 NW Holly Street Issaquah, WA Date: 6/20/2018 Date: Date: \\2K12FILE1\Projects\JOBS\ISD Sunset ES\L Construction Admin\L04 Change Orders\CO 07\CO 07.docx Page 3 of 3