HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett

Size: px
Start display at page:

Download "HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #77 Douthit Hills Student Community, Clemson University Project Joe Jett"

Transcription

1 SAFETY» Total Man Hours Worked This Week: 18810» Total Man Hours on Project » Crafts On Project This Week: 22» OSHA Recordable Rate: 0 July 31, 2016 P a g e 1

2 CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued Buildings F and E.» Continued Setting IDU Units.» Continued Buildings G and F.» Continued Mechanical Buildings F and E.» Continued Installing Building G & F.» Continued Electrical Building F.» Continued Setting Building F.» Continued Hanging & Finishing Building G.» Continued Sanitary Building E.» Continued Curtain Building E.» Continued Interior Building E. Bldg. G Drywall Bldg. E MC Cable Bldg. F Mechanical Room SITE, HUB, & WEST ZONE» Continued Building C.» Continued Setting Underground Detention System.» Paved Daniel Square Entrance.» Poured Highway 93.» Continued HUB.» Began Building D.» Tied in Domestic and Building B.» Continued Chiller HUB Basement.» Continued Forming HUB Roof A and B.» Continued Roof Building A. HUB CMU Walls Supply and Return Pump July 31, 2016 P a g e 2

3 NEXT WEEK S ACTIVITIES East Zone» Continue Setting F.» Energize Switch Building G.» Continue Hanging and Finishing Building G.» Continue Setting IDU Building G.» Continue Sanitary Building E.» Continue Overhead Buildings E & F.» Continue Buildings E and F.» Continue Interior Building E.» Continue Buildings F & G.» Continue Building F.» Continue Main Trunk Building F.» Continue Domestic Water Building F. Bldg. A Stair Rails Bldg. B Precast Bldg. C Ductbanks SITE, HUB, & WEST ZONE» Continue Forming Sidewalks.» Pour Newman Rd.» Continue Roof Building A.» Continue HUB.» Continue Building D Foundations.» Pour Roof A and HUB.» Continue Building B.» Continue Building C.» Continue Underground Detention System. Highway 93 Highway 93 July 31, 2016 P a g e 3

4 MANPOWER TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Holder Construction Company General Contractor American Deep Foundation Auger Cast Piles Baker Roofing Sheathing and Shingles Brightview Landscape Development Hardscape & Landscape Carolina Fire Protection Sprinklers C&C Fence Site Fence Cowart Tree Mulch Tree Removal Davis Crane Erectors Pre-Cast Erection D.H. Griffin Tank Foundation Removal Gainesville Mechanical Ductwork Gill Plumbing Plumbing Gregory Electric Aboveground Electric Hutch-N-Son Early Site Work st Choice Glass Glass Johnson Controls Building Controls JBR Construction Early Site Work Johnsons Modern Electric Aboveground Electrical King Asphalt Asphalt Kone Elevators Labor Finders Labor Force Metro Power Underground Electrical Old North State Masonry Masonry Osteen Chill Water pipe Precision Concrete Pyramid Masonry Masonry R.E. Mclean Tank Tank Demo Reeves Young Site Grading & Utilities Rival Construction Inc. Concrete RJ Coogan Deck Installers Ruppert Landscaping Landscape/ Hardscape Sears Contract Drywall/Metal Trusses Silt Fence Installation Site Erosion Control July 31, 2016 P a g e 4

5 MANPOWER CONTINED TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Southern Mechanical Inc. Electrical/Plumbing Steel Toe Labor Force Tree South Arborist Upstate Curb Curb and Gutter Valley Farm Construction Tree removal/grading Waterproofing Specialties Waterproofing Total July 31, 2016 P a g e 5

6 WEATHER CURRENT WEEK Rain Days This Week = 0 Rain Days To Date = 52 SAFETY REVIEW LOG Douthit Hills Monthly OSHA Statistics Man-hours worked RCR/DART Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 0 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Cumulative Man-Hours RCR DART R July 31, 2016 P a g e 6

7 MANPOWER CHART Douthit Hills Workforce Reeves Grading Metro Power American Deep Foundations Davis Crane Erectors Old North State Masonry Pyramid Masonry Sears Contract Gainesville Mechanical 1st Choice Glass Precision Concrete Southern Mechanical Rival Construction Baker Roofing Holder July 31, 2016 P a g e 7