Update on FCPS Construction/Renovation Projects. September 2015

Size: px
Start display at page:

Download "Update on FCPS Construction/Renovation Projects. September 2015"

Transcription

1 Update on FCPS Construction/Renovation Projects

2 Jessie Clark Middle -- Renovation Architect: General Contractor: Tate Hill Jacobs Architects Alliance Corporation GC Contract Sum: $18,041,500 Total Project Cost: $22,377,666 Change Orders to Date (18): $97,325 Scheduled Contract Completion Date: July 2015 % of Contract Completed: 92.24% Revised Completion Date per GC: October 2015

3 Jessie Clark Middle -- Renovation Rendering of Final Façade

4 Jessie Clark Middle -- Renovation Work Completed to Date: Completed paver installation at parent drop-off. Finished kitchen equipment utilities, energization and owner training. Turned over Cafeteria Area to JCMS for box lunch service. Completed loading dock concrete installation. Completed inspections for kitchen hood, HVAC and plumbing. Current Work Effort (September): Complete all power, data, PA and Technology Installations. Complete coping, downspouts and other roof components. Install handrail at loading dock. Complete landscaping at the front of the school. Correct all punch list inspection items.

5 Jessie Clark Middle -- Renovation Marquee Signage Installation Loading dock Corridor E

6 Jessie Clark Middle -- Renovation Cafeteria Kitchen Cafeteria Cafeteria

7 Squires Elementary -- Renovation Architect: General Contractor: JRA Architects D.W. Wilburn, Inc. GC Contract Sum: $12,166,000 Total Project Cost: $15,207,000 Change Orders to Date (5): $27,684 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 55.0% Revised Completion Date per GC: No Change

8 Squires Elementary -- Renovation Rendering of Final Façade

9 Squires Elementary -- Renovation Work Completed to Date: Area A has been turned over to the Owner (Phase 1). Area B new classroom wing grade beams and footings are complete (Phase 2). Area B interior building demolition has begun (Phase 2). Area B under slab plumbing has begun (Phase 2). Area B under slab electrical has begun (Phase 2). Current Work Effort (September): Area A punch list items to be completed / corrected (Phase 1). Area B new classroom wing stem walls to begin (Phase 2). Area B new classroom wing CMU walls to begin (Phase 2). Area B under slab plumbing to continue (Phase 2). Area B under slab electrical to continue (Phase 2).

10 Squires Elementary -- Renovation New Front Entry New Classroom Wing / Footings CMU Partitions CMU Wall Patching

11 Squires Elementary -- Renovation Under Slab Plumbing Under Slab Electrical Vapor Barrier EIFS on Gym Wall

12 New Elementary at Passage Mound Architect: General Contractor: Moody-Nolan Architects Griggs Enterprises, Inc. GC Contract Sum: $14,980,350 Total Project Cost: $19,478,511 Change Orders to Date (3): $80,778 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 15.76% Revised Completion Date per GC: No Change

13 New Elementary at Passage Mound Rendering of Final Façade

14 New Elementary at Passage Mound Work Completed to Date: Start Masonry Walls- Area B. Start and Complete Footer/Foundation Wall- Area C and Area D. Install Bar Joists- Area A. Dig and Install Domestic Water and Sanitary line. Install Gravel and Blacktop part of parking lot. Current Work Effort (September): Install Air Barrier- Area A & Area B. Install Insulation on Roof- Area A. Start Brick- Area A. Install Bar Joists & Decking- Area B. Install Gravel and Blacktop part of Parking lot (bus loop).

15 New Elementary at Passage Mound Site Towards Area B Lower Curb Cut CMU Walls Area A Air Barrier Progress

16 New Elementary at Passage Mound Cafeteria Roof Framing Area D Slab Work Air Barrier Installation Street View

17 New Elementary at Georgetown Road Architect: General Contractor: Clotfelter-Samokar Architects D.W. Wilburn, Inc. GC Contract Sum: $14,874,000 Total Project Cost: $19,848,291 Change Orders to Date (4): $23,801 Scheduled Contract Completion Date: July 2016 % of Contract Completed: 28.0% Revised Completion Date per GC: No Change

18 New Elementary at Georgetown Road Rendering of Final Façade

19 New Elementary at Georgetown Road Work Completed to Date: Site contractor continues to work on site subgrading. Contractor has completed concrete footings and foundation walls. Below slab interior sanitary piping completed. CMU in Area C is around 80% complete. CMU in Areas A & B is approximately 60%. CMU in Area D is approximately 10% complete. Electrical rough-in is on-going. Current Work Effort (September): Site contractor to continue grading parking lot for base and binder installation. Concrete floor slab installation will continue at the stage and mezzanines. Mezzanine decking and structural steel will continue. Joist installation in Area B will complete. Foam cavity insulation to begin in Area A, B & C. CMU installation will continue.

20 New Elementary at Georgetown Road Phase B Corridor Phase A Lobby Phase A Media Ctr. Mezzanine

21 New Elementary at Georgetown Road Front Elevation Cafeteria Slab Roof Structure Lobby at Gym

22 New High at Winchester Road Architect: General Contractor: Tate Hill Jacobs: Architects D.W. Wilburn, Inc. GC Contract Sum: $62,044,000 Total Project Cost: $81,511,696 Change Orders to Date (2): $637 Scheduled Contract Completion Date: July 2017 % of Contract Completed: 8.0% Revised Completion Date per GC: No Change

23 New High at Winchester Road Rendering of Final Façade

24 New High at Winchester Road Work Completed to Date: Access road work and parking lot blasting completed and building pad work will continue. Foundations in Areas B, C, E-3, E-4 will be completed and interior foundations will begin. ICF walls will continue in all areas with foundations installed. Under-slab electrical and plumbing complete in Area C; concrete slab poured. Current Work Effort (September): Foundations to be completed in Area E-2 and to begin in Area A. Area C ICF walls will have concrete to bearing height, steel joists beginning to be set, and CMU walls continuing. Area E-3 & E-4 slabs will be completed and under slab rough-ins will continue. Geothermal drilling will continue.

25 New High at Winchester Road Area C Slab Stem Walls Area A Building Pad ICF & IFAs

26 New High at Winchester Road IFAs and Slab Aux. Gym Slab Main Gym IFAs & CMU Walls IFAs & CMU Walls

27 Refunding Bond Sales Series 2015A and Series 2015B

28 Sold September 2, 2015 Series 2015A refunded Series 2010B Build America Bonds (BAB s) Series 2010B BAB s included an uncertain federal subsidy that had already been reduced from 35% to just over 32% Series 2015B refunded Series 2007 Series 2015A brought savings over $1.9 million -- average rate 2.75% compared with 2010B average rate 3.25% (based on original subsidy) Series 2015B brought savings of about $285, average rate 2.95% compared with 2007 average rate of 4.40%