1 LLANO ISD SCHOOL BOARD MEETING January 2016

2 LLANO ELEMENTARY AREAS A & C STUCTURAL STEEL AND EXTERIOR WALLS ARE IN PLACE INSTALLATION OF HVAC DUCT WORK IS ON- GOING ELECTRICAL AND PLUMBING ROUGH-IN IS ALSO ON-GOING

3 LLANO ELEMENTARY AREAS A & C OVERHEAD FIRE SPRINKLER PIPING IS BEING INSTALLED FIRE PROOFING OF THE STRUCTURE HAS BEEN COMPLETED SHEATHING AND WATER PROOFING OF THE EXTERIOR WALLS IS NEARING COMPLETION MASONS HAVE BEGUN LAYING BLOCK AND BRICK

4 LLANO ELEMENTARY AREAS A & C THE ELECTRICAL TRANSFORMER AND SWITCH GEAR HAS BEEN INSTALLED ROOFING OF BOTH AREAS IS ON-GOING HVAC IN THE GYMNASIUM IS COMPLETE CABINETS IN THE PRE-K/K WING WERE REPLACED DURING THE HOLIDAY BREAK

5 LLANO JR. HIGH SCHOOL MASONS HAVE TOPPED OUT THE BLOCK FOR THE GYMNASIUM THE ELECTRICAL TRANSFORMER AND SWITCH GEAR HAS BEEN INSTALLED AND CONDUIT IS CURRENTLY BEING INSTALLED ACROSS THE ROOF TOP THE CONCRETE FOR SECOND FLOOR OF THE NEW CLASSROOM WING WAS PLACED DURING THE HOLIDAY BREAK

6 LLANO JR. HIGH SCHOOL MECHANICAL, ELECTRICAL AND PLUMBING ROUGH-IN CONTINUES AT THE NEW GYM AND CLASSROOM WING INTERIOR WALLS IN THE OLD AG SHOP AREA ARE NEARING COMPLETION MECHANICAL, ELECTRICAL AND PLUMBING ROUGH-IN AT THE OLD AG SHOP AREA IS ALSO NEARING COMPLETION

7 LLANO JR. HIGH SCHOOL NEW VCT TILE WAS INSTALLED IN THE CAFETERIA DURING THE HOLIDAY BREAK EPOXY FLOORING IN THE SNACK BAR, CAFETERIA OFFICE AND THE BACK ENTRY TO THE KITCHEN WAS INSTALLED URING THE HOLIDAY BREAK THE SERVING LINE IN THE SNACK BAR AREA WAS ALSO REPLACED DURING THE HOLIDAY BREAK

8 PACKSADDLE ELEMENTARY IMPROVEMENTS TO PES ARE SUBSTANTIALLY COMPLETE ADDITIONAL FENCING AROUND THE BUS FUELING AREA IS FORTHCOMING ADDITIONAL LIGHTING OF THE BUS PARKING AREA IS BEING CONSIDERED

9 BASEBALL & SOFTBALL COMPLEX THE BASEBALL & SOFTBALL FACILITIES ARE SUBSTANTIALLY COMPLETE AND THE CERTIFICATE OF OCCUPANCY HAS BEEN RECEIVED PUNCH LIST ITEMS ARE BEING ADDRESSED FIELD LIGHTING HAS BEEN MEASURED AND MEETS OR EXCEEDS INDUSTRY STANDARDS ADDITIONAL FILL IN CERTAIN AREAS TO MINIMIZE EROSION IS BEING CONSIDERED

10 LLANO ELEMENTARY TIME LINE AREAS A & C AT LLANO ELEMENTARY ARE SCHEDULED TO BE COMPLETE THE FIRST WEEK OF JUNE RELOCATION OF THE CONTENTS OF THE MAIN BUILDING WILL BE MOVED THE FIRST PART OF JUNE WITH DEMOLITION OF THE BUILDING SCHEDULED FOR THE SECOND AND THIRD WEEK OF JUNE REPLACEMENT OF THE FLOORING IN THE PRE-K/K WING IS SCHEDULED TO BEGIN IN EARLY JUNE SUBGRADE PREP AND SITE UTILITIES FOR AREA B WILL TAKE PLACE IN JUNE FOUNDATION AND BUILDING CONCRETE FOR AREA B ARE SET TO BEGIN THE FIRST OF JULY

11 LLANO ELEMENTARY TIME LINE STRUCTURAL STEEL FOR AREAS B IS SCHEDULED TO BE COMPLETE MID-AUGUST FRAMING, SHEATHING AND MEP ROUGH-IN OF AREA B WILL BEGIN THE FIRST OF AUGUST AND CONTINUE TO MID-OCTOBER FINAL COMPLETION OF AREA B IS ANTICIPATED TO BE LATE NOVEMBER OCCUPANCY OF AREA B IS TO TAKE PLACE IN DECEMBER

12 LLANO JR. HIGH SCHOOL TIME LINE EXTERIOR METAL FRAMING AND SHEATHING IS SCHEDULED TO BEGIN IN THE NEXT WEEK WATERPROOFING OF THE BLOCK AT THE GYMNASIUM WILL CONTINUE FOR THE NEXT 3-4 WEEKS DRY-IN OF THE NEW ADDITION IS SCHEDULED FOR THE SECOND OR THIRD WEEK OF FEBRUARY MEP ROUGH-IN WILL CONTINUE THROUGH THE FIRST OF MARCH

13 LLANO JR. HIGH SCHOOL TIME LINE INTERIOR METAL FRAMING AND SHEETROCK IS SCHEDULED TO BEGIN IN FEBRUARY AND CONTINUES THROUGH THE END OF MARCH GYM FLOORING IS SCHEDULED TO BE INSTALLED IN APRIL COMPLETION OF THE NEW ADDITION IS ANTICIPATED TO BE MID-JUNE

14 LLANO JR. HIGH SCHOOL TIME LINE INTERIOR RENOVATIONS FOR THE NEW LIFE SKILLS ROOM AND STUDENT RESTROOMS WILL BEGIN THE FIRST OF JUNE AND BE COMPLETE THE SECOND WEEK OF AUGUST FURNITURE IN THE EXISTING BUILDING WILL BE MOVED THE FIRST WEEK OF JUNE REPLACEMENT OF THE VINYL FLOOR TILE AND CARPET IN THE LIBRARY AND ADMINISTRATION AREA WILL BEGIN THE SECOND WEEK OF JUNE

15 LLANO HIGH SCHOOL TRANSPORTATION & MAINTENANCE INTERIOR RENOVATIONS TO THE LHS AG SHOP ARE STILL BEING REVIEWED DESIGN OF THE MULTI-PURPOSE FACILITY AT LHS HAS BEEN REVIEWED WITH PEMB MANUFACTURES AND MODIFICATIONS TO THE STRUCTURE ARE BEING CONSIDERED DESIGN OF THE TRANSPORTATION & MAINTENANCE HAS ALSO BEEN REVIEWED WITH PEMB MANUFACTURES AND MODIFICATIONS TO THE STRUCTURE ARE BEING CONSIDERED