ADDENDUM 1. C. Bidders are requested to attach a copy of this Addendum to the Project Manual in their possession.

Size: px
Start display at page:

Download "ADDENDUM 1. C. Bidders are requested to attach a copy of this Addendum to the Project Manual in their possession."

Transcription

1 ADDENDUM 1 Renovations to Council Rock High School North Secured Entry 62 Swamp Road Newtown, PA To: For: Prepared For: ALL BIDDERS Renovations to Council Rock High School North Secured Entry 62 Swamp Road Newtown, PA Council Rock School District 30 North Chancellor Street Newtown, PA Date: March 5, 2014 Notice to all Contractors bidding the Renovations to Council Rock High School North Secured Entry project. This Addendum is to amend or clarify the Contract documents as follows: GENERAL A. This Addendum constitutes part of the Project Manual and Contract. Should conflict occur between the Project Manual and items in this Addendum or between Drawings and this Addendum, the Addendum shall govern. B. Work described in this Addendum shall be in accordance with Specifications for like items in remainder of building and complete with all labor and materials required. C. Bidders are requested to attach a copy of this Addendum to the Project Manual in their possession. D. Work affected by items in this Addendum shall be appropriately adjusted to accommodate these changes. E. Acknowledge receipt of this Addendum by inserting its number and date in the space provided in the Bid Form. Failure to do so may subject Bidder to disqualification. F. The agenda for Pre-Bid Meeting held on February 26 th, 2014 is attached to this addendum. G. The Sign-In Sheet for Pre-Bid Meeting held on February 26 th, 2014 is attached to this addendum. Council Rock School District Renovations to Council Rock ADDENDUM 1-1 Philadelphia, Pennsylvania High School North Secured Entry

2 Renovations to Council Rock High School North Secured Entry 62 Swamp Road Newtown, PA H. Pre-Bid Questions from meeting held on February 26 th, 2014 are included in this addendum. SPECIFICATIONS: Specification Section , Bid Form: REMOVE Bid Form for Contract Number 1 in entirety and REPLACE with revised Bid Form for Contract Number 1, General Construction. Reference attachments this Addendum Specification Section , Bid Form: REMOVE Bid Form for Contract Number 2 Plumbing Construction, Bid Form for Contract Number 3 HVAC Construction, Bid Form for Contract Number 4 Electrical Construction in their entirety from the Project Manual. This is a single prime General Construction contract only Specification Section , Summary of Work, Item 1.5, A: DELETE reference to 5 Prime Contractors in its entirety. This is a single prime General Construction contract only. DRAWINGS: Architectural 2.01 Drawing AD101 Demolition Plan. CLARIFY the demolition note to only apply to solid surface sill. See attached Sketch AD1-A Drawing A101 1/A101 Enlarged New Work Plan. ADD note Use bullnose CMU at jambs of door opening, at Door E Drawing A102 2/A201 Wall Section. CLARIFY the connection of 6 Box Beam to existing masonry. See note on attached Sketch AD1-A Drawing A102 3/A102 Wall Section and 4/A102 Wall Section. REVISE plastic laminate countertop to solid surface countertop. (Size and thickness as specified are acceptable.) Mechanical Plumbing Electrical 2.05 Drawing MPE-1 Reference Fire Protection Plan. ADD note advising Contractor of responsibilities regarding draining of system, filling, testing, etc. The contractor shall be responsible for draining of system, filling of system, provision of fire watch and notifying AHJ as required Drawing MPE-1 Reference General Notes. ADD note requiring the painting of any exposed conduits to match existing adjacent finishes. Council Rock School District Renovations to Council Rock ADDENDUM 1-2 Philadelphia, Pennsylvania High School North Secured Entry

3 Renovations to Council Rock High School North Secured Entry 62 Swamp Road Newtown, PA BIDDERS QUESTIONS: (Questions and response information through February 27 th, 5:00 PM. Further questions received will be incorporated as part of Addendum #2.) /24/14 Robert Marlin Question: The General Contractor s bid form has 2 alternates listed for the above referenced project and states to refer to Specification Section for a Full Description. I do not have that section in my bid documents. Please issue this spec. section with your next addendum. Response: The above listed alternates are a Bid Form error. There are no alternates for this project, and thus no required Specification Section See attached revised Bid Form for Contract Number 1 General Construction, which is included as part of this Addendum /26/14 Pre-Bid Meeting Question: Do the HVAC systems require reconfiguring? Response: Yes. There are no new fire alarm devices, but several existing must be relocated. Telecom must be rewired come from the IDF closet and sprinklers are to be relocated /26/14 Pre-Bid Meeting Question: Will the sprinkler system be able to be shut off during that work? Is there a testing certification required after installation? Response: Yes, arrangements will be made to drain the sprinkler system. No, there is not a hydrostatic testing requirement however contractor shall inspect all fitting, piping, heads etc. to confirm that there are no leaks /26/14 Pre-Bid Meeting Question: Does the job require premium work time? Response: No, premium time should not be required to complete the project on time. However, CRSD will accommodate as necessary so that the final completion date can be met /26/14 Pre-Bid Meeting Question: Will the building entrance be open/active during construction? Response: The entrance should be maintained as much as possible, but when work directly affecting the entrance is in progress, arrangements will be made to reroute visitors to another entrance/exit. Council Rock School District Renovations to Council Rock ADDENDUM 1-3 Philadelphia, Pennsylvania High School North Secured Entry

4 Renovations to Council Rock High School North Secured Entry 62 Swamp Road Newtown, PA /26/14 Pre-Bid Meeting Question: What is the project estimate? Response: The project estimate is $80, /26/14 Pre-Bid Meeting Question: Is there a special keying system? Response: Yes, CRSD uses Schlage keys and Glen LeSeur of Allegion is the hardware consultant /26/14 Pre-Bid Meeting Question: Who pays for the permit cost? Response: The district will purchase the general building permit for all trades. All other fees, licenses, etc. are the responsibility of the trade responsible for the same. The GC is to procure the building permit. ATTACHMENTS: General: Pre-Bid Meeting Agenda Pre-Bid Sign-in Sheet Specifications: Table of Contents Section Bid Form Drawings: AD1-A01 AD1-A02 END OF ADDENDUM NO. 1 Council Rock School District Renovations to Council Rock ADDENDUM 1-4 Philadelphia, Pennsylvania High School North Secured Entry

5

6

7

8

9 MEETING AGENDA CLIENT: PROJECT: COUNCIL ROCK SCHOOL DISTRICT COUNCIL ROCK HIGH SCHOOL NORTH Renovations to Council Rock High School North Secured Entry MEETING DATE: 26 February 2014 MEETING TIME: MEETING TOPIC: 3:00 PM Council Rock North High School Pre-bid Meeting 1. WELCOME AND PROJECT TEAM DESCRIPTION a. Introductions b. Issues discussed during pre-bid ARE NOT contractual unless affirmed in a formal addendum. c. Bid Due date Tuesday, March 18th, 2014 at 3:00 PM at the Council Rock School District, 30 North Chancellor Center, Newtown, PA BIDDING REQUIREMENTS a. One Prime Contractor: Contract 1 General Construction b. Forms to submitted with bids (3 copies of each) Bid form (acknowledge all addenda) Non-Collusion Affidavit Bid bond (10% of base bid sum) Performance bond (100% of base bid sum with Bond Rating of A- or better)- Submit following bid award Contractor Qualification Statement c. Bid opening is on Tuesday, March 18 th, 2014 at 3:00 PM at the Council Rock School District, 30 North Chancellor Street, Newtown, PA d. Prevailing Wage Reference front-end of specifications e. Steel Products Act- Supplement Instructions to Bidders f. Basis for award is low responsible/responsive bidder g. Bids irrevocable for 60 and 120 days per Act h. Bonds Bid Bond (10% contract amount) Performance / Payment Bond (100% of contract with A- or better rating) 161 Leverington Avenue, Suite 105 Philadelphia, Pennsylvania T: F:

10 i. Insurance Requirements See Article 11 of General Conditions A j. Pre-bid RFI process: - to Accept questions up through Tuesday, March 11 th, 2014 at 5:00 PM k. Last Addendum will be issued no later than three calendar days prior to bid 3. GENERAL ISSUES a. Criminal Background checks required (Criminal, Child Abuse and FBI) b. Form of contract is through AIA Document A General Conditions of the Contract for Construction c. Building Permit to be provided by Owner See Contract documents: Contractors are responsible for arranging all the inspections and securing all final approvals. 4. PROJECT SCHEDULE a. April 3 Board Meeting Acceptance of Bids and Notice To Proceed b. Mobilize within 10 days of Notice to Award for shop drawings, schedule development and logistics c. Substantial Completion is August 29, REVIEW OF PROJECT SCOPE OF WORK a. Power Point Presentation b. Additional site visits should be scheduled with Doug Taylor, Director of Operational Services dougtaylor@crsd.org 6. QUESTIONS 7. TOUR OF PROJECT SITE 8. CLOSE 161 Leverington Avenue, Suite 105 Philadelphia, Pennsylvania T: F:

11 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania TABLE OF CONTENTS REVISED ADDENDUM 1 VOLUME 1 Copyright DRAWING INDEX As Listed On Contract Drawings Cover Sheet DIVISION 00- BIDDING AND CONTRACT REQUIREMENTS Section Invitation to Bid Section Instructions to Bidders AIA Document A701 Section Supplemental Instructions to Bidders Section Background Checks Section Bid Form REVISED ADDENDUM 1 Section Bid Attachments Section Non-Collusion Affidavit of Contractor Section Agreement between Owner and Contractor AIA Document A Section Performance Bond AIA A312 Section Payment Bond AIA A312 Section General Conditions of the Project for Construction AIA Document A Section Prevailing Wages and Forms Section Construction Forms DIVISION 01 - GENERAL REQUIREMENTS Section Section Section Section Section Section Section Section Section Section Section Section Section Section Section Section Section Summary of Work Contract Modification Procedures Payment Procedures Coordination Project Meetings Construction Progress Documentation Submittal Procedures Safety Reference Standards and Definitions Basic Product Requirements Products Substitution Procedures Cutting and Patching Selective Demolition Cleaning Closeout Procedures Project Record Documents Warranties and Bonds TABLE OF CONTENTS Philadelphia, Pennsylvania TOC - Page 1 SGA Project:

12 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania Section Operation and Maintenance Data DIVISION 4 MASONRY Section Unit Masonry Assemblies DIVISION 6 - WOOD AND PLASTICS Section Miscellaneous Carpentry DIVISION 7 - THERMAL AND MOISTURE PROTECTION Section Joint Sealants DIVISION 8 - DOORS AND WINDOWS Section Section Section Aluminum Framed Entrances and Storefronts Finish Hardware Glazing DIVISION 9 - FINISHES Section Section Section Section Gypsum Board Systems Resilient Wall Base and Accessories Carpet Tile Painting DIVISION 12 - FURNISHINGS Section Institutional Casework DIVISION 28 ELECTRONIC SAFETY AND SECURITY Section Section Section Section Common Work Results for Electronic Safety and Security Conductors and Cables for Electronic Safety and Security Electronic Access Control and Intrusion Detection Video Surveillance END OF TABLE OF CONTENTS TABLE OF CONTENTS Philadelphia, Pennsylvania TOC - Page 2 SGA Project:

13 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania SECTION BID FORM BID FORM FOR CONTRACT NUMBER: 1 CONTRACT NAME: General Construction FOR Renovations to Council Rock High School North Secured Entry Newtown, PA Proposal of: (Name) (Address) (Telephone) (Contact Person) Council Rock School District 30 North Chancellor Street Newtown, PA In conformity with the Plans and Specifications as prepared by Schrader Group Architecture LLC, 161 Leverington Ave, Ste 105, Philadelphia PA 19127, after an examination of the site and the Bidding and Contract Documents, the undersigned submits this proposal and enclosed herewith a bond in an amount of not less than ten percent (10%) of the total of the hereinafter stated Base Bid, made payable to or indemnifying the Council Rock School District, 30 N. Chancellor Street, Newtown, PA , which it is understood will be held by the Owner, as security as provided in the Instructions to Bidders, if this proposal or any part thereof is accepted by the Owner, and the undersigned shall fail to furnish approved bonds and execute the Agreement within ten (10) days from the date of issuance of the award. Should the Owner fail to make an award on this project through no fault or failure on the part of the Bidder, then the Owner shall return said bid security. BID FORM Philadelphia, Pennsylvania Page 1 SGA Project:

14 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania It is hereby certified that the undersigned is the only person(s) interested in this proposal as principal, and that the proposal is made without collusion with any person, firm or corporation. The Bidder submits herewith, as such, a Non-Collusion Affidavit in accordance with the provisions of the Pennsylvania Anti-bid-Rigging Act of October 28, Bidder hereby agrees to execute the Agreement and furnish surety company bonds in the amount of one hundred percent (100%) of the Contract Price for the Performance Bond and Labor and Material Payment Bond, within ten (10) days after mailing by the Owner of notice of award, and to begin work with ten (10) days after date of Notice to Proceed. Bidder guarantees that, if awarded contract, he will furnish and deliver all materials, tools, equipment, tests transportation, secure all permits and licenses, do and perform all labor, supervision and all means of construction, pay all fees and do all incidental work, and to execute, construct and finish, in an expeditious, substantial and workmanlike manner, in accordance with the plans and specifications, to the complete satisfaction and acceptance of the Owner, for the Work of this Contract for the Renovations to Council Rock High School North Secured Entry project. It is understood that the Owner, reserves the right to reject any or all proposals, or part thereof, or items therein and to waive technicalities required for the best interest of the Owner. It is further understood that competency and responsibility of bidders will receive consideration before the award of the contract. A certified copy of the Contractor s Qualification Statement, AIA Document A-305 will be submitted as part of this bid. Bidders submit this proposal with the understanding that the work shall be substantially complete by the dates indicated in Supplemental Instruction to Bidders, Item 18, Time for Completion. The time for completion of the work of all contracts shall be considered as of the essence of this Contract. Liquidated Damages do apply to this Project and are further described in Supplemental Instructions to Bidders, Item 18C. The Contractor understands and agrees the TIME IS OF THE ESSENCE and that all schedule dates are minimum performance dates, notwithstanding anything to the contrary contained in the Contract Documents, should the progress of the Project be ahead of schedule dates, the Contractor agrees to coordinate and complete its Work in accordance with the actual Project Progress and the actual pace of the Project without additional compensation. The bidder agrees that he will not assign his bid or any of his rights or interests thereunder without the written consent of the Owner. In the event of a discrepancy between the verbiage (words) and numbers entered here below, the verbiage shall govern. Bid Withdrawal This proposal is submitted with the definite understanding that it will not be withdrawn for a period of sixty (60) days after Bids are due, or any authorized postponement thereof, except as provided by law (73 P.S. 1602, as amended). BID FORM Philadelphia, Pennsylvania Page 2 SGA Project:

15 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania THE BID, as called for, is submitted as follows: Item A. BASE BID: For all General Construction work complete, for the Renovations to Council Rock High School North Secured Entry project, as shown and specified in the Contract Documents, for the lump sum of: Dollars ($ ) Item B. UNIT PRICES Unit Prices shall include costs for furnishing and installing all materials, labor, tools, equipment, and other incidental necessary to complete the specified operation. Unit Prices will be used to ADD/DEDUCT the contract where appropriate. Schedule of Unit Prices: Unit Price #GC1 Provide a Laborer (Class 03) at the following Unit Price Unit Price #GC2 Provide a Carpenter at the following Unit Price $ per hour $ per hour Item C. ALLOWANCES Bidder agrees to include in the Base Bid Price, in addition to the Work shown on the Drawings and Specifications the following: Quantity Allowance 1: Ninety (90) hours of Unit Price GC1 work $ Quantity Allowance 2: Ninety (90) hours of Unit Price GC2 work $ TOTAL ALLOWANCE (INCLUDE IN BASE BID PRICE) $ BID FORM Philadelphia, Pennsylvania Page 3 SGA Project:

16 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania Name of Contractor ATTACHMENTS: The following Documents are attached and are made a condition of this Bid: a. Non-collusion Affidavit b. Bid Bond c. Contractor Qualification Statement ACCEPTANCE OF ADDENDA: In submitting this proposal, I have received and included in this bid, the instructions and information contained in the following Addenda: Addendum No. Dated SIGNATURES The Undersigned here certifies that this Proposal is genuine and not a sham, collusive or fraudulent or made in the interest of or in behalf of any person, firm or corporation not herein named; and that the Undersigned has not, directly or indirectly, inducted or solicited any bidder to submit a sham bid, or any other person, firm or corporation from bidding, and that the Undersigned has not, in any manner, sought by collusion to secure for himself any advantage over any other Bidder. (Individual Bidder) Seal WITNESS BID FORM Philadelphia, Pennsylvania Page 4 SGA Project:

17 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania Trading and doing business as Business Address: ** If a fictitious trade name is employed in the conduct of business, insert such name and complete appropriate, by deletion, the following sentence: The foregoing fictitious trade name (has) (has not) been registered under Pennsylvania Law. (Partnership Bidder) Seal WITNESS Seal Partner Seal Partner Seal Partner Business Address: ** If a fictitious or trade name is employed in the conduct of business, insert such name and complete, as appropriate, by deletion, the following statement: The foregoing fictitious or trade name (has) (has not) been registered under Pennsylvania law. BID FORM Philadelphia, Pennsylvania Page 5 SGA Project:

18 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania Complete, as appropriate, the following statement: The Partners constituting the Partnership are: (Corporate Bidder) *** (Name of Corporation) By: (Vice) President ATTEST: (Asst.) Secretary (Corporate Seal) Business Address: OR (If appropriate) (Name of Corporation) BID FORM Philadelphia, Pennsylvania Page 6 SGA Project:

19 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania WITNESS ***By: Authorized Representative Business Address: *** Complete, as appropriate, the following statement: The Corporation has been organized and is existing under the laws of the of (state/commonwealth) (state) END OF BID FORM BID FORM Philadelphia, Pennsylvania Page 7 SGA Project:

20 Renovations to Council Rock High School North Secured Entry Council Rock School District, Newtown, Pennsylvania THIS PAGE INTENTIONALLY LEFT BLANK BID FORM Philadelphia, Pennsylvania Page 8 SGA Project:

21 STAIR E121 RECEPTIONIST E114 SCHRADERGROUP Architecture, LLC LOBBY E102 S03 DEMO 0'-8" x 10'-0" SOLID SURFACE COUNTER 1 Drawing Title: DEMOLITION PLAN (AD101) Architecture Planning Programming 161 Leverington Ave Suite 105 Philadelphia, Pennsylvania T F COUNCIL ROCK HIGH SCHOOL NORTH SECURED ENTRIES 62 Swamp Rd, Newtown, PA FEBRUARY 28, /4" = 1'-0" DATE: SCALE: Drawing Number: AD1-A01

22 ALIGN GWB WITH FACE OF CMU BEYOND Drawing Title: 4" COLD-FORMED MTL 48" O.C., STAGGERED. ATTACH TO STRUCTURE ABOVE 5/8" GWB OVER 6" MTL STUD (18 16" O.C. W/ BATT INSULATION 6" (18 ga) COLD-FORMED BOX BEAM HEADER. PROVIDE FRAMING ANGLES AT EACH END FOR ATTACHMENT TO CMU W/ (2) 5/8" DIAMETER EXPANSION ANCHORS INTO CMU AND (6) SCREW FASTENERS INTO HEADER PER CLIP 1 SCHRADERGROUP Architecture, LLC WALL SECTION (2/A102) FEBRUARY 28, /4" = 1'-0" COUNCIL ROCK HIGH SCHOOL NORTH SECURED ENTRIES 62 Swamp Rd, Newtown, PA Architecture Planning Programming 161 Leverington Ave Suite 105 Philadelphia, Pennsylvania T F DATE: SCALE: Drawing Number: AD1-A02