BID ADDENDUM NO. 1 COVER SHEET. All Bidders of Record. Seamus Doran, Project Manager. DATE: June 29, 2017

Size: px
Start display at page:

Download "BID ADDENDUM NO. 1 COVER SHEET. All Bidders of Record. Seamus Doran, Project Manager. DATE: June 29, 2017"

Transcription

1 CAPITAL PLANNING & CONSTRUCTION 505 Ramapo Valley Road, Mahwah, NJ Phone (201) Fax (201) BID ADDENDUM NO. 1 COVER SHEET TO: FROM: All Bidders of Record Seamus Doran, Project Manager DATE: June 29, 2017 RE: Ramapo College of New Jersey Topken Language Lab RCNJ Project No C The attached Addendum is issued for the purpose of amending certain requirements of the bid and is hereby made part of and incorporated in full force as part of the Contract Documents. Unless hereinafter specifically noted or specified otherwise, all work shall conform to the applicable provisions of the Contract Documents. ******************************************************* BIDDERS OF RECORD ARE REQUIRED TO SIGN THIS ADDENDUM BELOW AND INCLUDE A COPY OF THE COMPLETE ADDENDUM WITH THE BID SUBMISSION TO ACKNOWLEDGE RECEIPT OF THIS DOCUMENT. RECEIVED BY: DATE: COMPANY: Enclosure Addendum No. 1 dated June 29, 2017

2 RAMAPO COLLEGE OF NEW JERSEY TOPKEN LANGUAGE LAB ADDENDUM NO.1 Dated June 29, 2017 This addendum is hereby made part of the Project Manual and Drawings dated June 15, The Project Manual and Drawings shall be supplemented or amended as specified herein. This Addendum contains changes to the requirement of the Project Manual. Such changes shall be incorporated into the Contract Documents and shall apply to work with the same meaning and force as if they had been included in the original Documents. Whenever this Addendum modifies a portion of a paragraph of the Project Manual, the remainder of the paragraph affected shall remain in force. The conditions and terms of the basic Specifications shall govern work described in this Addendum unless specifically amended by this Addendum. Whenever the conditions of work, and the quality or quantity of materials, or workmanship are not fully described in this Addendum, the conditions of work and other related requirements included in the basic Specifications for similar items of work shall apply to the work described in this Addendum. If no similar items of work are included in the basic Specifications, the best quality of material and workmanship shall apply and all work shall be subject to the written acceptance of the Architect. RESPONSE TO CONTRACTOR QUESTIONS: GENERAL BIDDING INSTRUCTIONS DEMOLITION ARCHITECTURAL MECHANICAL RAMAPO COLLEGE OF NEW JERSEY ADDENDUM NO. 1 TOPKEN LANGUAGE LAB PAGE 2 OF 3 JUNE 29, 2017

3 RE-ISSUED REVISED DOCUMENTS The following revised documents are issued as part of this addendum and shall be incorporated into the bid documents: I. CONSTRUCTION DOCUMENT SPECIFICATIONS 1. SPECIFICATION SECTION CONTRACTOR CHANGE ORDER PROPOSAL FORM Replace section with revised section dated June 29, II. ARCHITECTURAL DRAWING SHEETS END OF ADDENDUM NO. 1 RAMAPO COLLEGE OF NEW JERSEY ADDENDUM NO. 1 TOPKEN LANGUAGE LAB PAGE 3 OF 3 JUNE 29, 2017

4 PRE-BID MEETING MINUTES DATE: June 22, 2017 PROJECT: Topken Language Lab RE: Pre-Bid Meeting Minutes 1. Introductions a. Ramapo College of New Jersey Owner Represented by: Seamus Doran, Project Manager Steve Sondey, Purchasing b. SDR Architecture Architect Represented by: Steven DeRochi, Architect 2. Pre-Bid Conference a. Ensure all forms are filled out completely and properly to avoid possible protests from other bidders. b. Mandatory Bids will only be opened from firms listed on the sign-in sheet c. Minutes Minutes will be distributed as part of Addendum No Bid Dates a. June 29, :00 NOON: Last day for questions / requests for approval b. June 30, 2017: Addendum #1 issued c. July 12, :00 PM: BIDS DUE 4. Bid Documents a. Documents are available for download at 5. Bid Proposal Documents a. Bid Cover Sheet b. Proposal Form c. Non-Collusion Affidavit Form d. Stockholder Disclosure Form e. Agreement of Surety f. Bid Security Form g. NJ Public Works Registration Certificate of the Bidder and subcontractors h. NJ DPMC Notice of Classification and Uncompleted Contracts Form of the Bidder and subcontractors i. Proof of Insurance (Limits as defined in the General Conditions j. Plumbing and Electrical licenses 6. Bidder Qualifications a. Bidder must be NJDPMC pre-qualified in either Trade Codes 006, 0008, or 009 b. Bidder must have a current Public Works Contractor Registration certificate c. Bidder must have a valid business registration certificate on file with the Division of Revenue d. Bidder must not be engaged in investment activities in Iran RAMAPO COLLEGE OF NEW JERSEY June 22, 2017 Topken Language Lab Page 1 of 2 Pre-Bid Meeting Minutes RCNJ Project No C

5 e. Insurance coverage as specified in the general conditions 7. Project Overview a. Steven DeRochi provided an overview of the project scope. 8. Costs paid for by the College a. NJDCA plan review and permit costs b. Onsite field quality testing consultants 9. Questions 10. Site Walk-through RAMAPO COLLEGE OF NEW JERSEY June 22, 2017 Topken Language Lab Page 2 of 2 Pre-Bid Meeting Minutes RCNJ Project No C

6 Ramapo College of New Jersey RCNJ Project No C Project - Topken Language Lab Change Request No. Date: CONTRACTOR CHANGE ORDER PROPOSAL FORM Contractor Name: Address: Telephone No.: SECTION A: DETAILED DESCRIPTION OF THE WORK: SECTION B: SELF PERFORMED WORK 1. Total Labor (from Labor Worksheet) $ Total Material (from Material Worksheet) $ Total Equipment (from Equipment Expense Proposal) $ Subtotal (total lines 1 through 3) $ Contractor's Mark-up Combined Overhead and Profit (10% of line 4) $ SELF PERFORMED WORK TOTAL (Total lines 4 and 5) $0.00 PM REVISIONS SECTION C: SUBCONTRACTOR WORK (From Subcontractor's Proposal - provide subcontractor proposal forms) 7. Names of Subcontractors: Base Cost Only 10% Markup A. $0.00 B. $0.00 C. $0.00 D. $ TOTAL SUBCONTRACTORS' PROPOSALS $0.00 $ General Contractor's 5% Markup on Subs' Cost (per General Conditions) $ SUBCONTRACTOR TOTAL $0.00 SECTION D: CONTRACTOR'S REQUESTED TOTAL 11. AMOUNT REQUESTED (Total lines 6 and 10) $0.00 Signature of Contractor's Authorized Representative Date Print Name Print Title SECTION E: PROJECT MANAGER'S REVIEW I have reviewed the labor hours, material quantities and equipment and (check one): no exceptions are taken to this Proposal. see comments noted on proposal or below. By: Project Manager Date Contractor Change Order Proposal Form

7