1 Community Meeting Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If you have questions or comments, please ask one of our representatives. Thank you for attending!

2 BluEarth Renewables BluEarth Renewables US LLC is the US affiliate of BluEarth Renewables LP. BluEarth Renewables brings together extraordinary people with the power to change the future by delivering renewable energy to the power grid every day. We are a leading, power producer that develops, builds, owns and operates wind, hydro and solar facilities across North America. Our portfolio includes 325 MW net (565 MW gross) of nameplate capacity in operation and under construction and over 1,000 MW under development. For more information, visit bluearthrenewables.com Our Portfolio Solar Wind Hydro Development Construction Offices

3 Regional Overview An overview of existing and proposed wind energy projects in the region. 77 TB FLATS \\PDCCITRDSGIS2\Projects_4\InterMountainWind\LuckyStarWindProject_00301_18\Figures\Misc\LocationMaps\Fig_RegionalWindProjects.mxd; User: 35015; Date: 10/17/ DUNLAP SEVEN MILE HILL EKOLA FLATS TWO RIVERS BOSWELL SPRINGS Medicine Bow Hanna 287 MEDICINE BOW 30 LUCKY STAR 72 TWO RIVERS Rock River MCFADDEN RIDGE Elk Mountain 80 FOOTE CREEK 13 HIGH PLAINS LUCKY STAR 34 Land Status Bureau of Land Management Lucky Star Wind Project Two Rivers Ranch Existing Projects Casper 25 Private Projects Under Review State U.S. Forest Service Medicine Bow Rock River 80 Source: Albany County 2018, Carbon County N 2 1:450,000 4 Miles Laramie Cheyenne Medicine Bow Regional Wind Projects

4 Lucky Star Wind Project Project Description We are planning to submit local and state permit applications required to construct and operate the Lucky Star Wind Project across two private ranches in Carbon and Albany Counties, Wyoming. Permits required for the project include Conditional Use Permits from the counties as well as an Industrial Siting Council (ISC) Permit from the Wyoming Department of Environmental Quality. Project Details Location Point of Interconnection Project Area Expected Capacity Preliminary Site Plan South of Highway 30 and Medicine Bow Aeolus substation 78,000 acres 500 MW Up to 100 wind turbines on Medicine Bow River Ranch and up to 200 wind turbines on Lookout Ranch *Estimated The Project is being developed by Lucky Star Wind, LLC, a wholly owned subsidiary of BluEarth Renewables US LLC.

5 Two Rivers Wind Project Project Description We are planning to submit local and state permit applications required to construct and operate the Two Rivers Wind Project across two private ranches in Carbon and Albany Counties, Wyoming. Permits required for the project include Conditional Use Permits from the counties as well as an Industrial Siting Council (ISC) Permit from the Wyoming Department of Environmental Quality. Project Details Location North of Highway 30 and Medicine Bow Point of Interconnection Freezeout substation Project Area Expected Capacity Preliminary Site Plan 19,500 acres 280 MW Up to 80 wind turbines on Two Rivers Ranch and up to 20 wind turbines on Medicine Bow River Ranch *Estimated The Project is being developed by Two Rivers Wind LLC, a wholly owned subsidiary of BluEarth Renewables US LLC.

6 Project Plans Aeolus Substation Legend Two Rivers Wind Project Substation Lucky Star Wind Project Electrical Trunk Line Met Tower Transmission Line Project Road Collection Line Met Tower Access Route Land Status Bureau of Land Turbines Management Two Rivers I Private Two Rivers II State Two Rivers III U.S. Forest Service Two Rivers IV 487 Lucky Star Freezeout Substation :325, Miles Albany County Medicine Bow Carbon County Two Rivers Wind Project 30 Lucky Star Wind Project Two Rivers Wind Project Wilcox di Me -M Bow cine Rock River 1 d cfadden R McFadden Lucky Star Wind Project Sem inoe Dam Garrett Aeolus Substation Freezeout Substation Hanna Medicine Bow Albany County 48 7 Carbon County \\PDCCITRDSGIS2\Projects_4\InterMountainWind\TwoRiversRanch_WindProject\Figures\Notifications\Fig_1_ProjectLocation.mxd; User: 35015; Date: 10/18/ Sinclair Wa lc ott Wilcox 72 Roc k River 30 Elk Mountain McFadden 34 Bos ler Wy oming Sara toga 12 Ryan Park Riv erside 13 0 Centennial 11 La ramie 30 N Two Rivers and Lucky Star Wind Projects

7 Two Rivers Wind Project Construction Schedule We anticipate that construction would begin on Two Rivers I, II and III, followed by phase IV. Construction would begin with road improvements, road construction, and geotechnical investigations and would be followed by construction of foundations, the electric collection systems, and installation of wind turbine generators. The preliminary site plan consists of two substations, electrical collector systems and roads, and a kv transmission line to the point of interconnection Regulatory & Permitting Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Engineering & Design Procurement Start Construction - Roads, laydowns & foundations Substation & Electrical Collector System Transmission Infrastructure WTG Delivery & Erection Testing & Commissioning Commercial Operation Date

8 Lucky Star Wind Project Construction Schedule Construction would begin with road improvements, road construction, and geotechnical investigations and would be followed by construction of foundations, the electric collection systems, and installation of wind turbine generators. The preliminary site plan consists of two substations, electrical collector systems and roads, and a 230 kv transmission line to the point of interconnection Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Regulatory & Permitting Ongoing since August 2018 Engineering & Design Procurement Start Construction - Roads, laydowns & foundations Substation & Electrical Collector System Transmission Infrastructure WTG Delivery & Erection Testing & Commissioning Commercial Operation Date

9 Community Benefits The Lucky Star and Two Rivers wind projects will bring benefits to the local community through additional long-term tax revenue, employment during construction and operations, and boosts to the local economy with the procurements of goods and services. Two Rivers Lucky Star Fiscal Benefits & Tax Revenue Cost of Construction $364 million $650 million Material Cost $262 million $468 million Local & State Sales Taxes $15 million $27 million Lifetime Property Tax $30 million $48 million Wind Energy Production Tax $30 million over 30-year project life $60 million over 30-year project life Employment Benefits Construction Employment Up to 170 Up to 250 Average Monthly Wage (Construction) $3,800 / worker $3,800 / worker Operations Employment Up to 10 Up to 14 Average Monthly Wage (Operations) $3,360 / worker $3,360 / worker

10 Permits & Coordination We are actively coordinating with local, state, and federal authorities to minimize any disturbance to the environment that may come as a result of construction and operation of the Projects, to obtain the appropriate environmental permits, and to develop species-specific survey and conservation plans, as necessary. Some of the following items are required, and some are voluntary commitments worked on in coordination with federal, state, and local authorities: Wyoming Department of Environmental Quality, Industrial Siting Council Section 109 Permit Carbon and Albany County Conditional Use Permits for a Wind Energy Conversion System County Road Use Agreements Eagle Conservation Plan and Eagle Take Permit from U.S. Fish and Wildlife Service Bird and Bat Conservation Strategy Monitoring Plan for Wyoming Game and Fish Department US Army Corps of Engineers Clean Water Act Section 404 Permit Pre-Construction Permits (e.g. Wyoming Department of Environmental Quality Large Construction General Permit)

11 Environmental Studies Pre-construction wildlife surveys are being conducted consistent with the U.S. Fish and Wildlife Service Land-based Wind Energy Guidelines. We are coordinating extensively with state and federal environmental agencies to gather all necessary baseline data to permit the project. Meetings with the Wyoming Game and Fish Department and U.S. Fish and Wildlife Service have been initiated to determine the level of baseline survey information needed and coordination will continue. The following environmental studies have been completed, are currently underway, or are planned to be completed for the Projects: Site Characterization anticipated completion Nov Avian Use/Eagle Point Count Surveys ongoing through summer 2020 Raptor Nest Surveys ongoing through summer 2020 Eagle Activity/Flight Path ongoing through summer 2020 Sage Grouse Lek Surveys ongoing through spring 2020 Bat Acoustic Monitoring anticipated completion 2020 White Tailed Prairie Dog Colony Mapping anticipated completion summer 2019 Big Game Fixed Routes anticipated completion summer 2020 Wetland/Waters of the U.S. Delineations desktop review initiated, anticipated completion 2019 Ecological Site Description Mapping anticipated completion 2018 Cultural Resource Surveys anticipated completion 2019 Erosion Potential Assessment anticipated completion 2018 Sensitive Wildlife Species surveys planned for 2019

12 Two Rivers Wind Project Project Timeline Environmental Surveys & Agency Coordination Signed wind lease Meteorological tower erected Initiate surveys & agency coordination Environmental assessment for BLM right of way Post construction surveys Industrial Siting Council Jurisdictional meetings Permit application and hearings County & Local Government Engagement Local government meetings Conditional use permits and hearings Public Engagement BluEarth acquired projects Information meetings Ongoing community investment Project Construction Pre-construction permits Begin construction. Turbine delivery and installation Commercial operations

13 Lucky Star Wind Project Project Timeline Environmental Surveys & Agency Coordination Initiate surveys & agency coordination Meteorological tower erected Environmental assessment for BLM right of way Post construction surveys Industrial Siting Council Jurisdictional meetings Permit application and hearings County & Local Government Engagement Signed wind lease Local government meetings Conditional use permits and hearings Public Engagement BluEarth acquired projects Information meetings Ongoing community investment Project Construction Pre-construction permits. Begin Construction. Turbine delivery and installation Commercial operations

14 Thank you for attending! Please fill out a comment form and provide your feedback on the two proposed projects. If you would like to receive updates, please provide us with your name and contact information. bluearthrenewables.com/tworivers bluearthrenewables.com/luckystar projects@bluearth.ca