1 Motorways of the Sea Forum Brussels, 16 th of June 2017

2 Vitalijus Trakšelis Project manager, small scale LNG 16 June, 2017 Introduction to Blue Baltics project

3 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 3

4 KN an oil product and LNG terminal operator Traditional business Focus for strategic expansion development, construction and operations of LNG terminals 50+ years of oil product terminal operations Klaipeda LNG terminal based on FSRU Independence LNG reloading and bunkering station under construction in Klaipeda State fuel reserves terminal LNG transport and bunkering vessel project for the Baltic Sea LNG terminal development and Advisory services MoS Corridor Forum 4

5 Klaipeda LNG terminal Key facts Terminal started its operations in Jan m3 of LNG storage 4 bcm / year regasification capacity Third party access New opportunities Energy security for the Baltics states and for Finland and Poland Opportunity for market players to import gas from the global market Diversified supplies and entrance to new regas markets Break-bulking possibilities for new small-scale LNG markets Klaipėda MoS Corridor Forum 5

6 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 6

7 BLUE BALTICS LNG infrastructure facility deployment in the Baltic Sea Region Lithuania: AB Klaipėdos nafta (Coordinator of the Action) LNG Hub for the Baltic Sea Region SE Klaipeda State Seaport Authority Upgrade of the jetty to provide services for LNG operations Germany: Uranos Vermögensverwaltungs GmbH & Co. KG LNG Mobile Multifunctional Refilling Station (LNG MMRS / maritime bunker vessel) deployment Estonia: Alexela Energia AS Mobile L-CNG bunkering and fuelling infrastructure Sweden: AGA AB Upgrade of the LNG Terminal in Nynäshamn for reloading and bunkering operations MoS Corridor Forum 7

8 BLUE BALTICS LNG infrastructure facility deployment in the Baltic Sea Region Key facts for the BLUE BALTICS project Project partners 5 Project duration 01/03/ /06/2019 Total eligible project costs Uranos Vermögensverwaltungs GmbH & Co. KG AB Klaipedos nafta AGA AB KSSA Klaipeda State Seaport Authority Alexela Energia AS EU funds received Uranos Vermögensverwaltungs GmbH & Co. KG AB Klaipedos nafta AGA AB KSSA Klaipeda State Seaport Authority Alexela Energia AS 47,6 m EUR 23,3 m EUR 12,5 m EUR 4,7 m EUR 4,6 m EUR 2,6 m EUR 15,0 m EUR 7,3 m EUR 4,1 m EUR 1,5 m EUR 1,4 m EUR 0,8 m EUR MoS Corridor Forum 8

9 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 9

10 Natural gas supply chain in Klaipeda MoS Corridor Forum 10

11 HEKLA Klaipėda LNG Infrastructure Facility Deployment Eligible costs EU support 15 m EUR 4,5 m EUR Some of the technical parameters of the LNG reloading station Volume of LNG storage tanks (from appr. January 2018) 5 x m 3 LNG Loading/Unloading facility (ship-station-ship) LNG bunkering facility Number of truck loading bays Station s annual technological capacity 2 bays m 3 LNG MoS Corridor Forum 11

12 BLUE BALTICS AB Klaipėdos nafta Klaipėda LNG Reloading Station Additional equipment on the FSRU LNG equipment on the jetty Firefighting equipment - Purchase of the active firefighting system (delivery of the equipment preliminary on August 2017) Removal / cleaning of contaminated soil - In m3 contaminated soil was replaced by m3 clean soil 2 technical studies completed (Hazard and Operability studies, Operational procedures for STS reloading operations) Saddles ordered and delivered Further equipment will be purchased (if needed) Process equipment (LNG hose tower / reels and/or loading arms, auxiliary equipment for operation etc. Firefighting equipment (firefighting tower to cover LNG loading equipment, water curtains to cover 110 meter of jetty etc MoS Corridor Forum 12

13 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 13

14 BLUE BALTICS SE Klaipeda State Seaport Authority Upgrade of the jetty to provide services for LNG operations Geological examination works and EIA completed Technical jetty construction solutions completed Technical design study for reconstruction of jetties ongoing Jetty reconstruction (about 220 m) - foundation for process equipment (drain system / impounding basin for spilled LNG), - works that include installation of mooring equipment and dredging works (- 15 m) etc MoS Corridor Forum 14

15 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 15

16 BLUE BALTICS Uranos Vermögensverwaltungs GmbH & Co. KG LNG Mobile Multifunctional Refilling Station (LNG MMRS / maritime bunker vessel) deployment Tornio Ora Gavle Pori Ust-Luga Nyneshamn A joint venture by Nauticor and KN will charter a LNG bunkering vessel to supply: Risavika Lysekil Nauticor LNG bunkering clients Truck loading station in Klaipeda Klaipeda Satellite LNG terminals in the Baltic Sea Gate Swinoujscie Existing Planned MoS Corridor Forum 16

17 Advantages of the MMRS design Design High maneuverability Innovation in refueling technology Innovation in refueling technology - Based on a long-term study funded by the EU, called LNG Masterplan - TEN-T Project 2012-EU S. - Two azimuthing thrusters aft, two bow thruster forward. Thrusters allow for 360 rotation within 2 minutes - Good sea keeping capability for coastal and seagoing operation (DP2 maintains vessel position automatically) - Target is to operate the vessels without pilot and tugs - A range from dock side to 28 m above waterline - Transfer system operating port and starboard - Usage of innovative cryogenic breakaway couplings - zero emission of methane to the environment - Prevent spillage - Connects and disconnects under pressure - Natural Gas is cooled down on shore to -162 C to liquefy to LNG - Ambient head input causes the release of gas which can not be vented to the atmosphere - This gas process will allow for the fast transfer of LNG to a wide range of receiving tanks without venting gas to the atmosphere Klaipėda LNG terminal LNG supply route (approx. 7 km) LNG reloading/bunkering station Existing oil product terminal MoS Corridor Forum 17

18 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 18

19 BLUE BALTICS AGA AB m3 LNG storage tank Upgrade of the LNG Terminal in Nynäshamn for reloading and bunkering operations A truck loading station with two bays for loading trucks with LNG MoS Corridor Forum 19

20 Enabling ship loading at AGA LNG terminal in Nynäshamn Storage tank - Additional submerged cryogenic pump - Needed piping for pumping LNG from the tank to the jetty Site - Site will not be enlarged Jetty - New marine loading arm for bunker ships - Modification of present loading arm and gas return connection - Additional fire fighting equipment - Civil reinforcements Bunker ships - Capacity ships max tons and max ship length of 160 m - Expected bunker ship capacity on average 130 m3 - Expected loading time at jetty about 1 hour for ships MoS Corridor Forum 20

21 Index 1. KN and Klaipėda LNG terminal 2. Introduction to Blue Baltics 3. Blue Baltics: KN 4. Blue Baltics: KSSA 5. Blue Baltics: Uranos 6. Blue Baltics: AGA 7. Blue Baltics: Alexela MoS Corridor Forum 21

22 BLUE BALTICS Alexela Energia AS 1 LCNG fueling station 14 LNG containers 1 mobile LNG bunkering station Image not available yet - Project completed - 1 container ordered and already delivered - 1 container additional to be ordered for LCNG fueling station during containers to be used for the mobile LNG bunkering station, to be ordered when mobile bunkering station is ordered - Proposals received - Preferred solution selected - Order of equipment to be made when customer sign contracts MoS Corridor Forum 22

23 BLUE BALTICS Preliminary timeline 2016 Oct Grant Agreement signed 2016 Dec Uranos LNG MMRS ship building contract signed 2017 May Alexela: Mobile LCNG fuelling station completed 2018 Dec Alexela: Mobile LNG infrastructure delivered and deployed 2019 March Uranos: LNG bunkering vessel deployed 2019 Jun KSSA / KN: Reconstruction of Jetty completed Mar Start of the Blue Baltics project 2017 Feb KN: Basic design for fire protection at Klaipeda LNG reloading station completed 2017 Oct AGA: Technical studies completed for the LNG terminal in Nynäshamn 2018 Dec KN: Upgrade of LNG infrastructure completed 2018 Dec AGA: Upgrade of infrastructure completed and deployed 2019 Jun 30 End of the Blue Baltics project MoS Corridor Forum 23

24 Thank you! Vitalijus Trakšelis Project manager, small scale LNG 16 June, MoS Corridor Forum 24