1 LNG Calibration Facility Metrology for LNG workshop 19 th May 2015, Brøndby, Denmark Oswin Kerkhof (VSL), Marina Safonova (IMS Group)

2 Contents Part I (Oswin Kerkhof, VSL) LNG Calibration Facility (flow and composition) Background Research goals Functional & Metrological Design Requirements Part II (Marina Safonova, IMS Group) Engineering and Fabrication capabilities Process Description

3 Building traceability for LNG flow metering A three step approach 5-25 m 3 /h kg/min 5 200/400 m 3 /h /3200 kg/min Primary Standard Completed, EMRP project Mid-scale standard Sufficient for Small Scale LNG Project in progress m 3 /h Full scale facilities

4 Primary LNG mass flow standard operated and validated in 2013 at Gasunie Peakshaver

5 Next Step - LNG Calibration Facility Medium sized Flow & Composition

6 Location Rotterdam Maasvlakte, the Netherlands

7 Research Goals

8 FLOW MEASUREMENTS 1. Validating the uncertainty of flow standard Mass flow kg/min => Target uncertainty 0,15%* Volume flow m 3 /h => Target uncertainty 0,20%* * Requires further reducing measurement uncertainty of primary standard down to 0,10%

9 FLOW MEASUREMENTS 2. Investigate performance of at least two types of mass flow and volume flow standards Readings as a function of flow, pressure, temperature Extrapolation functions (to what respect is a water calibration representative for LNG use of a flow meter?) Installation effects (different flow profiles, near boiling conditions, )

10 COMPOSITION MEASUREMENTS Validating the uncertainty of composition standard Cross validation with reference liquefier(s) Uncertainty target: 0,2% on calorific value

11 Design Requirements FUNCTIONAL DESIGN REQUIREMENTS METROLOGICAL DESIGN REQUIREMENTS DESIGN STANDARDS

12 FLOW STANDARD General Traceable to primary standard No boil-off, venting of methane to air minimized Control parameters Flow Rate m 3 /h ( kg/min) Expandable to 400 m 3 /h Line pressure 1 10 barg(g) Temperature -123 to -175 C (1 to 20 C below boiling point) Composition Measurable (Mustang system), not controllable

13 FLOW STANDARD Production performance Capacity 1 Meter under Test (MuT) per day Schedule of MuT 1 6 (expandable to 8 ) US/DS piping 40D upstream, 8D downstream Calibration of two meters in series possible Types of MuT Coriolis, USM, Turbine, dp-type, Vortex and other

14 FLOW STANDARD Metrological design rules LNG velocities are low to avoid flashing / bubbles. No double bends out of plane (swirl!), no straighteners (delta-p!) Temperature measurement at the position of flow meters better than 0,1 C Smallest possible interconnected volumes to avoid in- and expiratory effects during calibration time window

15 FLOW STANDARD Same magnitude as gas at atmospheric conditions!

16 COMPOSITION STANDARD Special design sampler (subcooled conditions) Vaporization at conditions above critical pressure Gas Chromatograph Sampling flow rate at 7,5 ml/min (LNG) / 5 l/min (gas) Connectable to small volume reference LNG (liquefier system NPL and/or Effectech) Connectable to LNG calibration loop

17 Sponsors and Project Partners

18 Engineering & Fabrication by IMS Group IMS Group, LLP 18

19 IMS Group Metrology Project Engineering and Management Highly rated by FPAL/Achilles professional buyers community Dedicated fabrication shops in UK & Russia Support project life cycle from concept to Commissioning Serve both onshore and offshore oil and gas sectors around the world World-wide collaboration in measurement product development Leading Metrology System Integrator ISO 9001, and accredited, VSL CMC Certified (prover calibration), NMI IMS Group, LLP

20 Core Services Conceptual and Front End Engineering for all Core Products and related Sites EPC (Engineer, Procure, Construct) Metering and Allocation Sites for Natural Gas, Crude Oil and Hydrocarbon Fuels Technical Audits and Modernization of Fiscal Metering Systems, Pipeline Surge Protection and Water Hammer. Maintenance of Field Metering and Automation Equipment including Central Control Systems Metrological Services, including Calibration & Verification of Field Meters (P, T, Flow, Density, Viscosity), Approvals and Procedures IMS Group, LLP

21 Engineering and Fabrication OGS, Swansea, UK 1200m² Carbon Steel Workshop 300m² Stainless Steel Workshop 2400m² Assembly Workshop 2, 3.2, 7.5, 8 & 20 tonne cranes Flow Calibration Rig: 1800m²/h OGS, Ely, UK 1000m² Assembly Workshop 250m² R & D Workshop Flow Characterisation Loop Multiphase Test Loop Assembly and Testing of Supervisory System Control Panels Assembly and Testing of Analyser Houses and Cabinets Assembly of USM, Helical Turbine Meters IMS Group, LLP

22 Fabrication OGSB Kaliningrad, Russia Territory: 3.0 hectare Location: Kaliningrad, Russia, Free Economic zone Office space: 1,670 sq. m. Workshop space: sq. m. Warehouse: 900 sq.m., heated Certified NDT Laboratory ISO 9001:2008 certified Equipment: 3.5, 5, 12 & 20 ton overhead cranes Flow calibration rig Shot-blasting chamber Painting chamber Welding Equipment («ARGUS LIMITED»)

23 Inspection & Testing ALL Our FACTORIES perform the following Quality testing Visual Inspection Magnetic Particle Inspection Dye Penetration Inspection Positive Material Identification Radiographic Testing Ultrasonic Testing Hydrostatic testing Pneumatic testing Leak testing Paint inspections Flow testing

24 Facility Objective Phase 2: m3/hr Phase 1: m3/hr IMS Group, LLP Page 24

25 Main Equipment IMS Group, LLP Page 25

26 The Test Loop IMS Group, LLP Page 26

27 Annual Calibration IMS Group, LLP Page 27

28 LNG Calibration Facility Thank you for your attention