ENVIRONMENTAL MANAGEMENT PLAN

Size: px
Start display at page:

Download "ENVIRONMENTAL MANAGEMENT PLAN"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION TRANSMISSION EFFICIENCY PROJECT (TEP) ENVIRONMENTAL MANAGEMENT PLAN DONG ANH 220KV SUBSTATION SUBPROJECT (Final) Prepared by POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 1 March 2014

2 TEP - Dong Anh 220 kv Substation Environment Management Plan TABLE OF CONTENTS 1. INTRODUCTION POLICY, REGULATIONS, AND ADMINISTRATIVE FRAMEWORKS Government Regulations: World Bank Safeguard Policies SUBPROJECT DESCRIPTION Objectives of the Subproject Scope of the Subproject Location of Subproject Subproject Main Work Volume Main Activities Before and During Construction Subproject Implementation Schedule and Total Investment BASELINE DATA Geographical Location and Population Topography and Geology Hydro- Meteorological Characteristics Land use Environmental baseline data Socio-economic status of the project area Protected areas, natural reserves, sensitive areas, cultural property, historical monument, temple and pagoda in the project area POTENTIAL IMPACTS MITIGATION MEASURES EMP IMPLEMENTATION ARRANGEMENTS EMP Implementation Reporting Requirements MONITORING PROGRAM

3 TEP - Dong Anh 220 kv Substation Environment Management Plan 8.1. Objectives INSTITUTIONAL DEVELOPMENT ACTIVITIES COST ESTIMATION FOR EMP IMPLEMENTATION PUBLIC CONSULTATION Public consultation Annex 1: Environmental Specifications for the Contractor LIST OF TABLES Table 3.1. Main construction quantity of the subproject... 9 Table 3.2. List of primary construction material Table 5.1. Impact of the subproject Table 6.1. Impact mitigation measures for environment Table 7.1. Institutional Arrangement for Subproject s EMP implementation Table 8.1. Environmental Monitoring Plan Table 9.1. Cost estimation for capacity building in EMP implementation (*) Table Summary of cost estimation for implementation of EMP ABBREVIATION AMB : North Power Project Management Board EVN : Vietnam Electricity SIMC : Safeguard Independent Monitoring Consultant EMP : WB : World Bank NPT : National Power Transmission Corporation PFF : Preventing and fighting fire 2

4 TEP - Dong Anh 220 kv Substation Environment Management Plan PTC1 : Power Transmission Company No.1 PECC1 : Power Engineering Consulting Joint stock Company No. 1 TEP : Transmission Efficiency Project VND : Vietnam Dong USD : U.S.Dollar EMF : Electromagnetic Field GOV : Government of Vietnam HV : High voltage LV : Low Voltage MONRE : Ministry of Natural Resources and Environment PCBs : Polychlorinated Biphenyls PMU : Project Management Unit (under the AMB) 3

5 TEP - Dong Anh 220 kv Substation Environment Management Plan 1. INTRODUCTION The subproject: Dong Anh 220kV Substation is one of the subprojects that will be implemented in Phase I of the Transmission Efficiency Project (TEP) funded by the World Bank. The subproject will be implemented in Lien Ha and Thuy Lam communes of Dong Anh district, Hanoi city. The implementation of the subproject is in line with the City Power Development Master Plan (CPDMP) to meet the growing electricity demand load and power system in the Northeast area of Hanoi city. The activities of subproject include construction of a new 220kV substation and construction of 1,453m of 22kV power line supplying auxiliary power for the substation. These activities may cause negative impacts on the local environment and communities during pre-construction, construction, and operation phases. To ensure the potential negative impacts are identified and mitigated during the subproject implementation and in compliance with the policy on environmental assessment of the World Bank (OP/BP 4.01), an (EMP) of the subproject has been prepared in accordance with the guidelines provided in the Environmental and Social Management Framework (ESMF) of the TEP project. The EMP includes the following contents: an introduction, the main legal framework, the subproject description, the environmental background, potential positive and negative impacts, proposed mitigation measures, and implementation arrangements. It also includes an Environmental Codes of Practice (ECOP) prepared for the subproject. The EMP will be incorporated into the bidding documents and construction contracts, as well as a scope for environment quality monitoring. A Resettlement Plan (RP) has also been prepared for the subproject and presented separately. The Government s regulation on EA requires submission of an Environmental Impact Assessment (EIA) Report for the subproject. The EIA report has been prepared and submitted to Hanoi Department of Natural Resources for appraisal and approval. 2. POLICY, REGULATIONS, AND ADMINISTRATIVE FRAMEWORKS 2.1. Government Regulations: The following national laws and regulations are applied for subproject: - Law on Protection of the Environment No. 52/2005/QH11 passed by the National Assembly on November, 29 th, 2005 regulates the obligations of individuals, organizations in protecting environment. - Law on Water Resource No. 17/2012/QH13 enacted June 21, Land Law No. 13/2003/QH11 dated November 26, 2003, and the new Land Law No. 45\2013\QH13 dated November 29, 2013 which will take effect on July 1, Construction Law No. 16/2003/QH11 dated November 26, Labor law No. 35-L/CTN dated 23rd Jun 1994, with some amendment under Document No. 84/2007/QH11 by the National Assembly. - The Law of Cultural Heritage No. 28/2001/QH10 promulgated on June , with some amendment in 2009 by the National Assembly (No. 32/2009/QH12). - Law on Fire Prevention and Fighting No. 27/2001/QH10 dated June 29, Law on electricity No. 28/2004/QH11 dated December 3, Decree of Government No. 80/2006/ND-CP dated 9 August 2006 on guidance for implementation of Law on Protection of the Environment. POWER ENGINEERING CONSULTING JS COMPANY No.1 1

6 TEP - Dong Anh 220 kv Substation Environment Management Plan - Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating strategic environmental assessment, environmental impact assessment and environment protection commitment. - Decree No.106/2005/ND-CP dated August 17th, 2005 on implementation guidelines for some items stipulated in the Electricity Law on protection of high voltage electrical networks. - Decree No. 81/2009/ND-CP dated October 12, 2009 on some corrections and additions of Decree No.106/2005/ND-CP dated August 17th, 2005 on implementation guidelines for some items stipulated in the Electricity Law on protection of high voltage electrical networks. - Decree No. 117/2009/ND-CP dated December 31, 2009 on sanction of violations in the field of environmental protection. - Decree No. 59/2007/ND-CP dated April 9, 2008 on solid waste management. - Decree 174/2007/ND-CP dated November 29, 2007 of GOV on environmental protection charges for solid wastes. - Decree No. 98/2010/ND-CP of the Government dated 21 September 2010 on detailing the implementation of some articles of the Law on Cultural Heritage and the Law amending and supplementing some articles of Law on cultural heritage. - Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending some Article of Decree No.106/2005/ND-CP dated 17 August, Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree No.29/2011/ND-CP dated 18 April, Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to toxic waste management. - Circular No. 03/2010/TT-BCT dated January 1, 2010 on some rules on safe protection of high voltage grids. - Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on management and pollution prevention and exposure to PCBs. - The main applicable National Technical Regulations include: QCVN 05: 2009/BTNMT: National technical regulation on ambient air quality; QCVN 27:2010/BTNMT: National technical regulation on vibration; QCVN 26:2010/BTNMT: National technical regulation on maximum noise limit in public and residential areas; QCVN 08: 2008/BTNMT - national technical regulation on surface water quality; QCVN 09: 2008/BTNMT - national technical regulation on ground water quality; QCVN 01: 2009/BYT- national technical regulation on drinking water quality; QCVN 02: 2009/BYT- national technical regulation on domestic water quality; QCVN 06: 2009/BTNMT air quality specified maximum allowable concentrations of certain hazardous substances in ambient air; QCVN /BTNMT: National technical regulation on domestic wastewater; QCVN 40:2011/BTNMT: National technical regulations on industrial wastewater; QCVN 03:2008/BTNMT: National technical regulation on permissible limits of heavy metals in soils; QCVN 07:2009/BTNMT National Technical Regulation on Hazardous Waste Thresholds; QCVN 01:2008/BCT National technical regulation on safety principles in working with transmission lines and electrical equipment. - Other relevant sector technical regulation and standards. POWER ENGINEERING CONSULTING JS COMPANY No.1 2

7 TEP - Dong Anh 220 kv Substation Environment Management Plan 2.2. World Bank Safeguard Policies An environmental and social screening of the subproject was undertaken in line with the OP 4.01 and it showed that the World Bank s policies on Environmental Assessment (OP/BP 4.01), and Involuntary Resettlement (OP/BP 4.12) will be triggered for the subproject. The screening has also resulted in categorizing the subproject as a Category B project. In addition, the Bank s requirements on public consultation and information disclosure will need to be followed. Environmental Assessment (OP/BP 4.01): Environmental Assessment (EA) is an umbrella policy for the Bank s safeguard policies. The overarching objective is to ensure that Bank-financed projects are environmentally sound and sustainable, and that decision-making is improved through appropriate analysis of actions and of their likely environmental impacts. The EA process is intended to identify, avoid and mitigate potential impacts of Bank operations. EA takes into account the natural environment (air, water, and land); human health and safety; social aspects (involuntary resettlement, indigenous peoples, and physical cultural resources); and transboundary and global environmental aspects. EA considers natural and social aspects in an integrated way. This subproject triggers OP 4.01 because it involves the construction and operation of a high-voltage substation and connecting overhead transmission lines, requiring the identification, mitigation and monitoring of potential adverse environmental and social impacts. As required by OP 4.01, the subproject prepared an EIA and an EMP that meet the Government s and the World Bank s safeguards requirements. By the TEP appraisal, the subproject draft EIA and EMP were disclosed locally at the project site and the Bank s InfoShop in Washington DC on January 24, 2014 as required by OP 4.01 and the Bank s policy on access to information. The final EIA and EMP were disclosed locally at the subproject sites, at the InforShop, and the Vietnam Development Information Center on April 18, Involuntary Resettlement (OP/BP 4.12) The Involuntary Resettlement policy seeks to prevent severe long-term hardship, impoverishment, and environmental damage to the affected peoples during involuntary resettlement. OP 4.12 applies whether or not affected persons must move to another location. The Bank describes all these processes and outcomes as involuntary resettlement, or simply resettlement, even when people are not forced to move. Resettlement is involuntary when the government has the right to expropriate land or other assets and when affected people do not have the option to retain the livelihood situation that they have. This policy is triggered because the subproject it would have impacts involving the temporary and permanent involuntary taking of land and the loss of structures and assets associated with the land for the construction of the substation and the associated connecting line. By appraisal, the subproject has prepared and disclose the raft RP locally at the project site and the Bank s InfoShop in Washington DC on January 24, The RP includes the measures to ensure that displaced people are: (i) informed about the options regarding resettlement; (ii) consulted and offered alternative resettlement choices; and (iii) provided with effective compensation and livelihood restoration. The final RP was disclosed locally at the subproject sites, at the InforShop, and the Vietnam Development Information Center on April 18, World Bank Group Environmental, Health, and Safety Guidelines POWER ENGINEERING CONSULTING JS COMPANY No.1 3

8 TEP - Dong Anh 220 kv Substation Environment Management Plan World Bank-financed projects should also take into account the World Bank Group Environmental, Health, and Safety Guidelines 1 (known as the "EHS Guidelines"). The EHS Guidelines are technical reference documents with general and industry-specific examples of Good International Industry Practice. The EHS Guidelines contain the performance levels and measures that are normally acceptable to the World Bank Group and are generally considered to be achievable in new facilities at reasonable costs by existing technology. The environmental assessment process may recommend alternative (higher or lower) levels or measures, which, if acceptable to the World Bank, become project- or site-specific requirements. This subproject should conform the Environmental, Health, and Safety Guidelines for Electric Power Transmission and Distribution and the General EHS Guidelines. 3. SUBPROJECT DESCRIPTION 3.1. Objectives of the Subproject The objectives of the proposed subproject are to: i) meet the load growing electricity demand of Hanoi city power system especially load of the Northeast of Hanoi city; ii) create power links between Northeast of Hanoi city and neighboring provinces, distributing power capacity, avoiding overloading of the transformers at the station in the area, thereby ensuring safety and reliable operation of power network in Hanoi city; iii) reduce power loss in entire power network, enhancing effectiveness of electricity generation of EVN Scope of the Subproject Dong Anh 220kV Substation shall be built with capacity of 2 x 250MVA and space land for installation of additional transformer No.3 at the substation. In the first time, install 01 transformer AT1-250MVA put into operation in The second transformer shall be expected to be installed in the period of The transformer of AT3 shall be installed after Dong Anh 220kV substation shall be built suitably with following period size and taking into account the link with 500kV switchgear of the next stage. The entire area of the 220kV Dong Anh subproject is approximately 49,819.38m 2. The construction activities include: i) construction and installation for outdoor civil work (transformer foundation, tower and conductor brace, cable trench system, supporting pole and equipment foundation etc.; ii) function house service for management and operation (bay housing and control housing 220kV and 110kV, pumping station for fire-fighting) 22kV connectionline; and iii) construction of 30 m of access road to the substation Location of Subproject The substation: Dong Anh 220kV substation construction in this stage is proposed to be constructed and in consideration with coupling with the 500kV switchyard in later stage. An area of Dong Anh 220kV substation is 49, m 2, (land occupied area of 500kV switchyard in later stage is 29, m 2 ) in paddy field, of Bieu Khe village, Thuy Lam commune and Ha Phong village, Lien Ha commune, Dong Anh district, Hanoi city. The substation borders the residential area of Huong Tram village Thuy Lam commune to the North; the communal road of Xuan Non - Thuy Lam communes to the East; the rice paddy to the South, further as 1 The EHS Guidelines can be consulted at POWER ENGINEERING CONSULTING JS COMPANY No.1 4

9 TEP - Dong Anh 220 kv Substation Environment Management Plan residential area of Ha Phong village in Lien Ha commune, and the Dong Anh Soc Son existing 110kV connection line to the West. The subproject site was approved by Hanoi city People s Committee via Document No. 3431/UBND-CT dated 11/05/2011 and by Hanoi Architecture - Planning Department via document No. 4130/QHKT-HTKT dated 14/12/2010. Total acquired land for the substation is: 49, m 2 Substation ground: Substation ground will be designed to ensure that ground level will be higher than flood level. Existing ground level is: 5.1m. Maximum historic flood level in 2008 in substation area is: 5.54m An average level of the ground after leveling is: 6.8m Substation area near the irrigation channel system so drainage is very good. The subproject location is illustrated in the map below: POWER ENGINEERING CONSULTING JS COMPANY No.1 5

10 TEP - Dong Anh 220 kv Substation Environment Management Plan Figure 1: The Dong Anh 500/220kV subproject location POWER ENGINEERING CONSULTING JS COMPANY No.1 8

11 TEP - Dong Anh 220 kv Substation Environment Management Plan Number of project affected households 112 households (440 people) Total area land required Temporary = 0 m 2 Permanent = 49, m 2 Agricultural land required Temporary = 0 m 2 Permanent = 49,819.38m 2 Residential land required Temporary = 0 m 2 Permanent = 0 m 2 Industrial land required Temporary = 0 m 2 Permanent = 0 m 2 Other land required (Forestry land and hill land) Temporary = 0 m 2 Permanent = 0 m Subproject Main Work Volume Table 3.1. Main construction quantity of the subproject No. Project components Unit Qty Notes I Civil works 1 Ground leveling Vegetation soil excavation m 3 15,942.1 Embanking sand to substation foundation m 3 113,218.7 Embanking soil to substation foundation m 3 8, Foundation excavation, embankment - Soil excavation m 3 24, Soil embankment m 3 14, Asphalted concrete road m 2 7, Concrete work - Local placed concrete m 3 5, Precast concrete m Steel works - Steel for concrete ton Local galvanized steel ton Electric welded steel ton Construction, paving - Construct brick wall m Coating wall, floor m 2 14, Paving m 2 2,067,8 (Source: Adjusted FS of 220kV Dong Anh substation, PECC1, 12/2013) POWER ENGINEERING CONSULTING JS COMPANY No. 1 9

12 TEP - Dong Anh 220 kv Substation Environment Management Plan Table 3.2. List of primary construction material No. Project components Unit Qty Notes 1 Cement kg 1,819,669.7 Loss calculated 2 Coarse yellow sand m3 3, Aggregate - Aggregate 1x2 m3 2, Aggregate 2x4 m3 1, Rounded steel < 18 kg 184, Shaped steel kg 17, Timber formwork m Brick piece 510, Source: Adjusted FS of 220kV Dong Anh substation,12/ Main Activities Before and During Construction Main Activities Before and During Construction Activities before construction: - Acquiring land for tower foundation construction, conducting compensation and allowances for land damages and assets on land for site clearance. - Constructing auxiliary facilities (worker camps, stockpiles, material storage yards). - Mobilization of workers. - Temporary land acquisition partly along roadside for storing material and equipment. - Set-up of domestic water supply for the domestic and construction needs Activities during construction: - Construction of substation: + Foundation excavation. + Transportation of material and equipment to the site. + Set-up of pillars and substation equipment. - Construction of transmission line: + Foundation excavation. + Transportation of material to the site. + Set-up of poles installation of line components. - Main materials and equipment to be used: + Cement, sand, stone, iron, pole, porcelain, mixing station, cranes, etc: bought in the locality, transported to the subproject site by road Transportation Material and equipment supply Material and equipment supply will be determined in detail in later phase, depending on the state budget disbursement and the subproject bidding method. Two sources are expected: - Material and equipment supply by the subproject owner. - Material and equipment supply by the contractor. Long distance transportation For material and equipment supplied by the project owner: + Long distance transportation of such material and equipment will be undertaken using specialized trucks. Such trucks will be selected in accordance with the requirements provided in the contract. POWER ENGINEERING CONSULTING JS COMPANY No. 1 10

13 TEP - Dong Anh 220 kv Substation Environment Management Plan + Long distance transportation from the subproject owner warehouse to the site will be undertaken using ton trucks and loading and unloading will be done using 5-ton cranes. For materials and equipment supplied by the contractor: + Electric poles will be transported using Kawaz trucks, using 5-ton cranes for loading and unloading. + Supporting frames and accessories will be transported using 5-ton trucks with manual loading and unloading. + Cement and steel will be transported using 5-12 ton trucks with manual loading and unloading. + Stone and sand will be transported using 5-12 ton dump trucks. Intermediate transportation - Materials and equipment stored at the site such as cables, insulators, accessories, breakers, capacitors, power meters, meter boxes and cement will be transported to the construction sites using non-motorized vehicles and manual handling. Manual handling All materials and equipment will be transported to the construction site manually. The distance will be determined case by case Emplyoment and Workers Camps Temporary warehouse, camp used for construction works are planned to be built in an unused of substation ground (reserved area, road etc.). Area of temporary camps is taken according to number of worker working in construction site. These temporary camps include: camp for accommodation, camp for administration, camp for public activities. The labor demand is determined by the volume of work, construction method and the current labor norms. In the construction phase is expected to be apporoximately 150 people participating in construction Subproject Implementation Schedule and Total Investment Subproject Implementation Schedule Based on the requirements of power supply and capacity of the subproject owner, the subproject timeline is scheduled as follows: No. Implementation schedule Time 1 Preparation of Technical Design and professional reports Dec Preparation of Bidding Document 1st Quarter Preparation of Construction Drawing for part not related to equipment 2nd Quarter Project commencement 3rd quarter Preparation of construction Drawing part related to equipment 4th Quarter Connection, operation 2nd Quarter 2015 POWER ENGINEERING CONSULTING JS COMPANY No. 1 11

14 TEP - Dong Anh 220 kv Substation Environment Management Plan Total Investment Total investment breakdown is indicated in the table below: - Cost of civil work 141,939,873,000 Cost for equipment 143,416,798,000 - Cost for compensation, clearance& resettlement 36,369,507,000 Cost for project management 3,718,914,000 Cost for Engineering, Investment 14,186,706,000 Others 25,540,411,000 Ccontingencies 93,986,334,000 Total investment: 459,158,544,000 POWER ENGINEERING CONSULTING JS COMPANY No. 1 12

15 TEP - Dong Anh 220 kv Substation Environment Management Plan 4. BASELINE DATA 4.1. Geographical Location and Population The 220kV substation subproject will be located on the paddy rice land area belonging to the communes of Thuy Lam and Lien Ha, Dong Anh district, Hanoi city. Dong Anh district is the gateway to the west of Hanoi with a total natural land area of 18,230 ha, divided into 23 administrative communes and 1 town including 156 villages and 62 wards, and with a population of about 331,000 people. Dong Anh district has favorable natural conditions for economic and social development, and significant transportation advantages facilitating good and trade exchange between Hanoi and the north eastern provinces. The district administratively borders Soc Son district to the north; Bac Ninh province and Gia Lam district to the East; Hong River to the south; and Vinh Phuc province on the west Topography and Geology Topography As mentioned above 220kV Dong Anh is proposed to be located on paddy field so geomorphologic terrain on the region is rather flat, it belongs to accumulation plain terrain type. Topographical grade: Topography of III grade. Geology Geology in the region comprises of soil layer: Clay, blended clay, originated from quaternary formation. Physo-geological phenomena Earthquakes According to earthquake zoning map in Vietnam created by the Geo-physics Institute under National Technology and Natural Science in 1995, it is found that in the proposed site for substation, the earthquake up to grade 7 may occur. Substation is located on river/marine sedimentation terrain, engineering geological condition is rather complicated. The phenomena can occur, such as sliding to foundation wall, swampy in shallow field. Suitable solution shall be applied to foundation to ensure long-term stability Hydro- Meteorological Characteristics Meteorology Dong Anh 220kV Substation is located entirely in an area affected by climate and hydrological regime of Hong and Ca Lo river basin, which basically belongs to the tropical climate region with cold winter and hot humid summer heavy rain. The average wind speed in the area is about 2.1m/s with the prevailing west, southeast, and east directions from April to September and north and northwest directions from October to March. The yearly average temperature is 23.6 o C. Maximum temperature is up to 42.8 o C, and often occurs in May and lowest temperature is 2.7 o C, and often occurs in January. The yearly average humidity is about 82%, with the highest level of 100%, and the lowest possible level of below 16%. POWER ENGINEERING CONSULTING JS COMPANY No. 1 13

16 TEP - Dong Anh 220 kv Substation Environment Management Plan The annual average rainfall in the region is relatively high reaching 1611 mm. The rainy season begins in May and ends in October. The average number of rainy days in a year are about days. The number of average thunderstorms per year at the substation site is 58.6 days. In order to determine the lighting region partition in the area of the 22kV transmission line supplying electricity to the station, using the lightning observation data of Lang station. thunderstorms could occur any day, month in year but mostly in the summer especially in the afternoon from 13h to evening, maximum thunderstorm month is from May to September coincide with high rainfall; time occur thunderstorm is 1 2h, having thunder. From November to March is period of monsoon activity, there is little thus thunderstorm in the period, about 2 3 days per month. Hydrology: The flow regime of the Red River system is divided into two distinct seasons, dry season and flood season. The dry season lasts from November to May next year. The total volume of water in the dry season accounts for 20 30% of the annual flow. The driest time occurs in January, February, and March with a total water volume of about % of the annual flow. The flood season starts from June to October. The total water volume in flood season accounts for 70 80%. August is the month with the largest flow accounting for 19 23% of the total annual flow. The river and stream water levels seasonally affect the substation site, resulting in dry rice fields during the dry season. In the flood season (rainy season), the infield rain and heavy flood in the rivers cause flooding in the fields, especially in the July, August, and September. A historical rain in August 1971 in the Red River area and a heavy rain happened in October November 2008 caused flooding in many parts in Ha Noi. However, Dong Anh 500kV substation and the connecting line will be constructed on elevated land sites of Lien Ha and Thuy Lam communes, thus would only affected by flooding by rain. The flooding level is from m and lasts for a few days Land use Dong Anh district has the natural land area of 18,230 ha, including agricultural land of 10,015 ha, making up 54.76%; the remainder is of specialized land, urban, unused and forestry land. Distribution of land use in the Dong Anh district No. Land type Area (ha) Land rate (%) 1 Agricultural land 10, Annual crop land 9, Perennial crop land Aquaculture land Specialized land 3, Residential land 2, POWER ENGINEERING CONSULTING JS COMPANY No. 1 14

17 TEP - Dong Anh 220 kv Substation Environment Management Plan 4 Unused land 2, Forestry land 5, Total 18, Environmental baseline data (Source: Statistic Yearbook of Dong Anh district - Quality of air, noise and vibration Air quality in the district is very different areas. However, the project is located in arable agricultural land, population density and traffic are not high. Overall, air quality in the project region have not contaminated, thus the health of people living the region is insured, all of criterias (CO, SO2, CO, noise, and vibration) are in the allowable limit of National Technical Standard. Water quality Surface water sources in the region is diversity on population level. Water quality is quite good in the Red rivers but it is polluted in main river Nhue river, Kim Nguu river which is playing the role of the region sewerage. In general, water and underground quality in the project is quite good, through evaluating the analysis result of water sample in and adjacent the project and compared with the national standards found that most the criteria are located in allowable limit, only Coliforms and Fe are higher than allowable standard. Therefore, to meet domestic use purposes, underground water should be treated to reject metal before using in domestic purposes. Soil quality Most of the heavy metals in soil at the survey area have lower value and within the allowable limits. Soil in the project area is agricultural land to plant rice, this proved that soil quality at the project is quite good, not polluted by heavy metal. Location of the subproject is in an open area, air is very clean. There are no industrial, handicraft activities in the area. There is no observed pollution in term of water, air and soil. People are living in surrounding area of the subproject site. Main land use pattern in the site is rice field. No forest is presented in the area. There are no wild animals in the subproject area, except for such species as small frog, mouse, small snakes and intersects Socio-economic status of the project area Dong Anh district has an advanced economic growth rate, which has 17.4% for many years. Commercial and service activities are increasingly developing towards a modern civilized society. Many new areas are formed such as Thang Long industrial and Nguyen Khe industrial zones that have contributed to the creation of nearly jobs for local labors. The agricultural sector continues to be a strong investment area and interest of the district, with high level of total investment. Restructuring plants and animals having high economic value has been a focus. The poverty rate reduces by 2%. The district focuses on the development of culture, especially social goals of education. In recent years, the district maintains the right scale of education, quality of key and comprehensive education of the district are maintained, striving to maintain universal POWER ENGINEERING CONSULTING JS COMPANY No. 1 15

18 TEP - Dong Anh 220 kv Substation Environment Management Plan primary education, secondary and high schools (reached 90-95%), 100% of teachers at all levels reached standards. Public health, family population and children are of attention of the authority, especially on building national standard communal health with 100% of communes having medical doctors Protected areas, natural reserves, sensitive areas, cultural property, historical monument, temple and pagoda in the project area. The project is located in an area of agricultural land. There are no any natural reserve area, sensitive area, cultural property, historical monument, temple and pagoda in the project area. The district has no natural reserve areas, national parks. In the the Thuy Lam commune, has Sai temple is 5km far from the subproject. 5. POTENTIAL IMPACTS The subproject would contribute to meeting the demand load and power safety in Hanoi city and thereby bring about significant socioeconomic benefit. Apart from such benefits, the subproject may also result in environmental and socioeconomic impacts which are adverse to the local conditions. The environmental screening of the subproject indincates that it is eligible for financing considering that the subproject would not involve possible high risk and would not create potential adverse impacts on (a) critical natural habitats and/or protected area including proposed protected areas; (b) loss or damage to cultural property, including sites having archeological (prehistoric), paleontological, historical, religious, cultural and unique natural values, graves and graveyards; (c) water regime, particularly water flow and water quality; and (d) local traffic. The implementation of the subproject would mainly cause land acquisition, increased dust generation, air pollution, domestic waste, and health and safety issues due to construction activites and electrical magnetic field. However, these impacts are not significant, temporary, localized impacts with available mitigation measures. Only OP 4.01 and OP 4.12 are triggered for this subproject. The potential negative impacts of the subproject are identified in table 5.1 and could be minimized by applying the proposed mitigation measures developed for the subproject which is described in Table 6.1 of Section 6. POWER ENGINEERING CONSULTING JS COMPANY No. 1 16

19 TEP- Dong Anh 220kV Substation Table 5.1. Impact of the subproject Impact/issues Significance of impact Duration of impact - THE PRE-CONSTRUCTION AND CONSTRUCTION PHASES Impact description Effect of land acquisition Medium Short-term and Long-term - The substation and connection line would be located in the rice fields of 110 households of Thuy Lam commune and Lien Ha commune, Dong Anh district, Hanoi city. Of these, 16 affected households belong to Thuy Lam commune. The number of affected household in Lien Ha commune are expected about 94 households (according to the Resettlement Plan report, PECC1, 2013), households would lose their land permanently. - 47,953.71m 2 of agricultural land would be permanently acquired. This land is located in communes of Thuy Lam and Lien Ha. - No household would need to be relocated because of the subprojects. - Land acquisition would have adverse impacts on income and livelihood of the affected households. Impacts of land acquisition are described in detail in the subproject Resettlement Plan, PECC1, 2013). - In addition, 120 m 2 of inter-field concrete irrigation ditch, 1120 m 2 of inner-communal concrete road and m 2 of inner-commune earth road land are also permanently affected. This would pose some difficulties for agricultural activities at the rice field and traffic in the area. Temporary permanent acquisition and Medium Short- term Long-term Total land acquisition of the subproject is as follows: Land Unit Permanent affected Temporary affected 1. Substation land Paddy field m 2 47, Inner field irrigation ditch m POWER ENGINEERING CONSULTING JS COMPANY No. 1 17

20 TEP- Dong Anh 220kV Substation Impact/issues Loss of vegetation due to land clearance for Dong Anh substation Erosion or sediment generation caused by earthworks Significance of impact Small Duration of impact Short tem Long term land Impact description Inner-field concrete road land m Inner-commune earth road land m Total m 2 49, Ground for substation and connection line is used to be rice fields. This area is rice cultivate land of Bieu Khe and Ha Phong s village households of Thuy Lam and Lien Ha communes. Vegetation near the subproject comprises grass and shrubs at the time of survey (June, 2013) this area has been harvesting. Medium Short-term - Project areas have flat, not through rivers and streams - The earthworks of the project include: + Digging foundation holes: 15, m 3 soil. + Backfilling foundation holes: 113, m 3 sand and 10, m 3 soil. (according to adjusted FS of the 220kV Dong Anh substation) - Activities of construction and excavation only happen in a short time at foundation holes and are prioritized to be done in dry season. - The project will apply successive construction method. Therefore, risk of soil erosion is at low level, so there is no risk of erosion, landslides. Air pollution and dust generation Medium Short term - Exhaust gases such as SO x, NO x, CO from the operating transportation vehicles and power generators would have potential impacts of degrading air quality in the subproject area and the health of workers and local communities. - Dust is generated from soil excavation and substation site leveling work, especially in dry season. The affected people will be the workers and the inhabitants around the project area. POWER ENGINEERING CONSULTING JS COMPANY No. 1 18

21 TEP- Dong Anh 220kV Substation Impact/issues Significance of impact Duration of impact Impact description Noise and vibration Contamination of water and soil by hazardous waste - Dust is also generated by means of transport of materials and plants during the construction of the subproject. The affected people will be road users and local communities along the route of construction material transportation on the National road No.3 especially entering road to substation (Lien Ha Thuy Lam inter-commune road). - Given the small number of vehicles mobilized for the subproject, short time of construction, and far location of the Bieu Khe village residential area (about 200m), the impact of air and dust pollution on workers and communities can be assessed as medium and can be mitigated. Small Short-term - Operation of transportation vehicles, site grading and piling machines, and power generators can cause noise and vibration affecting households along the national No.3 especially along Lien Ha Thuy Lam inter-commune road and at subproject construction sites. However, this impact is small because it the related activities would only occur during the construction phase and can be easily mitigated. Medium Short-term - Oil spill from vehicles and construction machines can affect quality of soil and water, especially in rainy season. This leakage oil can affect surrounding area by run off rainwater. - Transformer oil or oil having PCBs might also be leakage to the environment due to accidents. However, oil having PCBs to be used at substation are prohibited by the national regulation. - The operation of the substation will use some chemicals available in such equipment as battery, insulating oil, grease oil and etc., but in small quantities. Effects on Medium Short-term - Discharging of construction waste and domestic waste can make adverse effects to environmental to medium environment quality. quality by discharging of construction waste and term - Excavation is planned to do in dry season. Excess soil will be reused to fill in the poles foundation. Thus there will be no soil, sand left after the subproject implementation. - During construction stage, construction waste will be collected, sold and discharge POWER ENGINEERING CONSULTING JS COMPANY No. 1 19

22 TEP- Dong Anh 220kV Substation Impact/issues Significance of impact Duration of impact Impact description domestic waste appropriately (backfilling). Domestic waste will be collected or treated in on-site treatment system. However, it is necessary to implement a efficient management plan to ensure all of wastes are colleted and treated obey the regulation. Public health and Medium Short-term - There are some storehouses and grounds need to be built temporary in order to contain safety effects to medium materials and equipments. Construction camp will be built for workers. from construction camps, materials storehouse and ground term - Construction camp and materials storehouses can affect the health and safety of local inhabitants and workers by unsafe keeping of construction materials and equipments and the conflict between workers and local inhabitants especially residents in Thuy Lam and Lien Ha communes. - Workers will be from the locality; the construction camp will include rest room and arranged in substation area; all of construction equipments and materials will be placed in appropriate places which are fenced around. Therefore, the conflict between workers and local inhabitant s and impacts on public health and safety are at low level. Arising conflicts between construction workers and local residents. Local road degradation due to construction activities and Small Short-term - Focusing large number workers of construction activities (150 people in maximum) shall cause a risk in conflict between the worker and the local residents. The subproject implementation is expected to be completed in short period about 12 months. However, the contractors will mainly use local workers for jobs suitable and worker will be chosen from the skilled ones in the region so this impact is minor and be able to minimize. Medium Short-term - The subproject site is near Lien Ha Thuy lam asphalte commune road route, National Road No. 3; it is very advantageous in construction materials transportation. - These roads are well-processed foundation and are covered by thick layer of bitumen. In addition, level of transportation activities is not high, transporting oversize and overload POWER ENGINEERING CONSULTING JS COMPANY No. 1 20

23 TEP- Dong Anh 220kV Substation Impact/issues Significance of impact Duration of impact Impact description materials equipments should be followed existing regulation and responsible authorities to ensure transportation safety for people and existing infrastructure system. Hence, the impact of the local road degradation is at low level. existing regulation and responsible authorities to ensure safety for people and existing infrastructure system. However, if not transportation weight is not well managed, the impact of the local road degradation would be moderate. OPERATION PHASE Exposure to electromagnetic field (EMF) levels exceeding the standard. Interference with radio, TV or other communications. Effects on public health and safety, including voltage hazard Fire hazard due to oil leakage Medium Long-term - If not properly designed and constructed the substation and the connection lines would have adverse impact on worker and community health. Based on the calculation and existing substation 220kV show that, the EMF level is under standard. The Dong Anh 220kV substation was designed to conform to safety standard. Safety regulation will also be applied strictly by workers when operating substation. No impact No impact - The location of the project is far away from the radio communication works. Medium Long term - In design stage, all safety measurements were considered. However, voltage hazard and effects on safety of local inhabitants and operation workers can in case of no conform to safety regulation. Medium Long term - Fire hazard can be caused from cooling oil leakage or transformer problems. However, this effect is minimized since the substation has oil-collected pit and fire safely equipments. POWER ENGINEERING CONSULTING JS COMPANY No. 1 21

24 TEP- Dong Anh 220kV Substation Impact/issues Pollution due to leakage oil and hazardous materials Significance of impact Duration of impact Impact description Medium Long term - Leakage oil from transformers can affect adversely on environmental quality. In order to prevent the impact on the environment quality due to leakage oil, oil-collected pit will be installed. Oil collected pit has concreted cover and prevented from leaking, also be equipped with an automatic water pump. Oil collected tank is arranged in locations convenient for the collection of the transformer (V = 90m 3 ) in capacity (equivalent 78tons of oil) to ensure 100% volume of oil discharge from transformer will be obtained when there is a problem. - The project does not use cooling oil that contains PCBs and hazardous materials Noise from substation operation Impact due to waste water and domestic solid waste of operation workers Problems of grid, accident at work during operation management. Small Long term - The transformer will be manufactured according to regulations with noise level under 70dBA at 30m of distance. It will also be installed complying technical requirements to reduce the noise to operation. Besides, the project locates in paddy field. Thus, impact of the noise is insignificant. Small Long term - In the operation stage, the substation does not discharge any of hazardous wastes. Domestic waste water from daily activities of operation workers will be treated by a septic tank before discharging the environment. Domestic solid waste will be collected and discharged through waste collected system of the local. Therefore, impact on the environmental due to waste discharge is small. Medium Long term - In activities of management, operation, repair and maintenance of the subproject, problems of grid and accident can occur in case workers do not conform to safety and operation regulations. POWER ENGINEERING CONSULTING JS COMPANY No. 1 22

25 6. MITIGATION MEASURES Table 6.1. Impact mitigation measures for environment Environment al and social issues Mitigation measures Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures Engineering design phase 1.Engineeri ng design - Select an optimal alternative to minimize land acquisition, avoid causing the existing vegetable covers and trees and structures. - Strictly follow electrical and fire safety requirements of the related regulations. Relevant technical regulations and standards Employer: EVNNPT AMB NPMB By appraisal authority Pre-construction phase 1. Land acquisition - Careful site-survey, consultation with the affected local communities and authorities to choose optimal solutions for the location substation and auxiliary facilities to minimize land acquisition. - Compensate for land acquisition and damages strictly in accordance with the RPF of the TEP project and the Resettlement Plan of the subproject. At the land acquisition site of Bieu Khe village. - Decree No. 69/2009/ND- CP. - Cicular No.14/2009/TT- BTNMT EVNNPT PMU Local authority Local authorities and the affected people - Construction phase 1. Dust generation - The Contractor is responsible for compliance with relevant Vietnamese legislation with respect to ambient air quality. - The Contractor shall implement dust suppression measures (e.g. water spray vehicles, covering of material stockpiles, etc.) as required; - Construction vehicles shall comply with speed limits and haul distances shall be minimized. - Material loads shall be suitably covered and secured during At the constructio n site Along Lien Ha Thuy Lam transportati on road QCVN 05:2009/BTNM T: National technical regulation on ambient air quality Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 23

26 Environment al and social issues Mitigation measures transportation to prevent the scattering of soil, sand, materials or dust. - The Contractor shall be responsible for any clean-up resulting from the failure by his employees or suppliers to property secure transported materials. - Exposed soil and material stockpiles shall be protected against wind erosion and the location of stockpiles shall take into consideration the prevailing wind directions and locations of sensitive receptors. - Dust masks should be used where dust levels are excessive. Locations for mitigation measures route Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures 2. Air pollution - All vehicles must comply with Vietnamese regulations controlling allowable emission limits of exhaust gases. - Vehicles in Vietnam must undergo a regular emissions check and get certified named: Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT. - There should be no burning of waste or construction materials or cleared vegetation on site. At the constructio n site. Along Lien Ha Thuy Lam transportati on road route. Nearest residential area. TCVN : Road vehicles. maximum permitted emission limits of exhaust gages. QCVN 05:2009/BTNM T. National technical regulation on ambient air quality. Contractor PMU Compliance reported by CSC 3. Noise and vibration - The contractor is responsible for compliance with the relevant Vietnamese legislation with respect to noise and vibration. - All vehicles must have appropriate Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT; to avoid exceeding At the constructio n site. Lien Ha Thuy Lam - QCVN 26:2010/BTNM T: National technical regulation on Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 24

27 Environment al and social issues Mitigation measures noise emission from poorly maintained machines. - Construction will be carried out during daylight hours. If it is necessary to carry out some works at night or weekends, the affected local community must be informed sufficiently in advance. - Avoiding or minimizing transportation though or material processing near community areas. Locations for mitigation measures road route. Residential areas surrounding the subproject Applicable National Regulations, Standards noise - QCVN 27:2010/BTNM T: National technical regulation on vibration. Responsible party Verification required to determine effectiveness of measures 4. Water pollution - The Contractor must be responsible for compliance with the relevant Vietnamese legislation relevant to wastewater discharges into watercourses. - Portable or constructed hygienic toilets must be provided on site for construction workers. Wastewater from toilets as well as kitchens, showers, sinks, etc. shall not be discharged directly to any water body. - Wastewater over standards set by relevant Vietnam technical standards/regulations must be collected in a conservancy tank and removed from site by licensed waste collectors. - Using techniques as berming or diversion during construction to limit the exposure of disturbed sediments to moving water. - Before construction, all necessary wastewater disposal permits/licenses and/or wastewater disposal contract have been obtained. - At completion of construction works, wastewater collection tanks and septic tanks shall be safely disposed or effectively sealed off At the foundation constructio n site. At worker s camp (location of receiving points for wastewater discharge). - QCVN 09:2008/BTNM T: National Technical Standard on underground water quality. - QCVN 14:2008/BTNM T: National technical regulation on domestic wastewater - QCVN 24:2009/BTNM T: National technical regulation on industrial wastewater. Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 25

28 Environment al and social issues Mitigation measures Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures 5. Drainage and sedimentati on control - The Contractor shall follow the detailed drainage design included in the construction plans, intended to prevent storm water from causing local flooding or scouring slopes and areas of unprotected soil resulting in heavy sediment loads affecting local watercourses. - Ensure drainage system is always maintained cleared of mud and other obstructions. - Areas of the site not disturbed by construction activities shall be maintained in their existing conditions. - Earthworks, cuts, and fill slopes shall be properly maintained, in accordance with the construction specifications, including measures such as installation of drains, use of plant cover. - To avoid sediment-laden runoff that could adversely impact watercourses, install sediment control structures where needed to slow or redirect runoff and trap sediment. Sediment control structures could include windrows of logging slash, rock berms, sediment catchment basins, straw bales, storm drain inlet protection systems, or brush fences. At foundation constructio n site of substation and power line. At drainage system site serve for the subproject. - TCVN 4447:1987: Earth works- Codes for construction - Decree No. 22/2010/TT- BXD on regulation of construction safety. - QCVN 08:2008/BTNM T: National technical regulation on the quality of surface water Contractor PMU Compliance reported by CSC 6.Managem ent of stockpiles, and construction ranges - All locations to be used for disposal of construction excavation and stockpiles must be previously identified in the approved construction specifications. Sensitive sites such as scenic spots, areas of natural habitat, areas near sensitive receptors, or areas near water should be avoided. - An open ditch shall be built around the stockpile site to intercept wastewater. - Stockpile topsoil when first opening of the substation and power towers and use it later to restore the area to near natural conditions. At disposal site and stockpiles Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 26

29 Environment al and social issues Mitigation measures - If landowners are affected by use of their areas for stockpiles, they must be included in the project resettlement plan. - All stones and the needed filling materials must be bought at licensed sources Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures 7. Solid waste - Before construction, a solid waste control procedure (storage, provision of bins, site clean-up schedule, bin clean-out schedule, etc.) must be prepared by Contractors and it must be carefully followed during construction activities. - Before construction, all necessary waste disposal permits or licenses must be obtained. - Measures shall be taken to reduce the potential for litter and negligent behavior with regard to the disposal of all refuse. At all places of work, the Contractor shall provide litter bins, containers and refuse collection facilities. - Solid waste may be temporarily stored on site in a designated area approved by the Construction Supervision Consultant and relevant local authorities prior to collection and disposal by a licensed waste collector for disposal at government-approved sites. - Waste storage containers shall be covered, tip-proof, weatherproof and scavenger proof. - No burning, on-site burying or dumping of solid waste shall occur. - Recyclable materials such as wooden plates for trench works, steel, scaffolding material, site holding, packaging material, etc shall be collected and separated on-site from other waste sources for reuse, for use as fill, or for sale to reprocessing to companies with legitimate operating permits. - If not removed off site, solid waste or construction debris shall be At constructio n site. - Decree No. 59/2007/ND-CP on solid waste management. - Circular No. 12/2011/TT- BTNMT on hazardous waste management. Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 27

30 Environment al and social issues Mitigation measures disposed of only at sites identified and approved by the Construction Supervision Consultant and included in the site specific measures. Under no circumstances shall the contractor dispose of any material in environmentally sensitive areas, such as in or close to watercourses. Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures 8.Hazardou s wastes - Hazardous waste of any kind shall be disposed of at an approved appropriate landfill site and in accordance with the national legislative requirements. The Contractor shall obtain needed disposal certificates. - The removal of asbestos-containing materials or other toxic substances shall be performed and disposed of by specially trained and certified workers. - Used oil and grease shall be removed from site and sold to an approved used oil recycling company. - Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles and machinery shall be collected in holding tanks and removed from site by a specialized oil recycling company for disposal at an approved hazardous waste site. - Used oil or oil-contaminated materials that could potentially contain PCBs shall follow procedures provided in the ESMF to avoid any leakage or affecting workers. The local DONRE must be contacted for further guidance. - Relevant agencies shall be promptly informed of any accidental spill or incident. - Tender documents will prohibit procurement of equipment containing PCBs. At constructio n site. - Decision No. 23/2006/QD- TNMT with list of hazardous substance - Circular No. 12/2011/TT- BTNMT on management of hazardous substance Contractor PMU Compliance reported by CSC 9.Workforc e, Camps - The workforce shall be provided with safe, suitable and comfortable accommodations and safe portable water. They have to be maintained in clean and sanitary conditions. At worker camp site. - Decree No.12/2010/TT- BXD concering Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 28

31 Environment al and social issues and Site Managemen t Mitigation measures - Site offices, worker camps, mixing stations, and workshops shall be located NOT within 100m from any water courses, at least 500 meters of existing residential area. - Engineers and workers shall register their temporary residence with the local authority. - Allocate officer to be the Contractor s Workplace Safety and Environment Officer responsible for environmental and safety issues including training for workers. - Septic tank toilets must be provided at all construction camp areas where there will be concentration of labor. - First aid boxes shall be provided in each construction camp site. Locations for mitigation measures Applicable National Regulations, Standards regulation on construction safety. Responsible party Verification required to determine effectiveness of measures 10.Disruptio n of vegetative cover - The Contractor shall prepare a Clearance, Vegetation and Restoration Management Plan for prior approval by the Construction Engineer, following relevant regulations. The Clearance Plan shall be approved by Construction Supervision Consultant and followed strictly by Contractor. Areas to be cleared should be minimized as much as possible. - The stripped topsoil shall be stockpiled in areas agreed with the Construction Supervision Consultant for later use in re-vegetation and shall be adequately protected. - The application of chemicals for vegetation clearing is not permitted. - Prohibit cutting of any tree unless explicitly authorized in the revegetation clearing plan. At the revegetation site - Law on Environmental Protection No.52/205/QH1 1. Contractor PMU Compliance reported by CSC 11.Traffic managemen t - Before construction, carry out consultations with local government and community and with the traffic police. - Significant increases in number of vehicle trips must be covered in a construction plan previously approved. Routing, especially of heavy At constructio n site Along - Law on traffic and transportation No.23/2008/QH Contractor NPMB Local authorities and POWER ENGINEERING CONSULTING JS COMPANY No. 1 29

32 Environment al and social issues Mitigation measures vehicles, needs to take into account sensitive sites such as schools, hospitals, and markets. - Installation of lighting at night must be done if this is necessary to ensure safe traffic circulation. - Place signs around the construction areas to facilitate traffic movement, provide directions to various components of the works, and provide safety advice and warning. - Employing safe traffic control measures, including road signs and flag persons to warn of dangerous conditions. - Passageways for pedestrians and vehicles within and outside construction areas should be segregated and provide for easy, safe, and appropriate access. Locations for mitigation measures connection line route Applicable National Regulations, Standards 12. Law on construction No.16/2003/QH 11. Decree No. 22/2010/TT- BXD on regulation of construction safety. Responsible party Verification required to determine effectiveness of measures communities 12.Restorati on of affected areas - Disposal areas, site facilities, workers camps, stockpiles areas, working platforms and any areas temporarily occupied during construction of the project works shall be restored using landscaping, adequate drainage and re-vegetation. - Start re-vegetation at the earliest opportunity. Appropriate local native species of vegetation shall be selected for the planting and restoration of the natural landforms. - Spoil heaps and excavated slopes shall be re-profiled to stable batters, and grassed to prevent erosion. - All affected areas shall be landscaped and any necessary remedial works shall be undertaken without delay. - Trees shall be planted at exposed land and on slopes to prevent or reduce land collapse and keep stability of slopes. - Soil contaminated with chemicals or hazardous substances shall be removed and transported and buried in waste disposal areas. At temporary occupied site. - Law on Environment protection No.52/2005/QH 11. Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 30

33 Environment al and social issues Mitigation measures - Restore all damaged inter-filed irrigation canals, inter-field roads, and inter-communal roads caused by the subproject activities to their original state (site specific measures) or better. Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures 13. Worker and public Safety - Contractor shall comply with all Vietnamese regulations regarding worker safety. - Prepare and implement action plan to cope with risk and emergency and aid service at construction site. - Training workers on occupational safety regulations. - Ensure that ear pieces are provided to and used by workers who must use noisy machines such as piling, mixing, etc., for noise control and workers protection. - Install fences, barriers, dangerous warning/prohibition site around the construction area which showing potential danger to public people (such as unfinished power pole foundation, high risk electrical shock areas, etc.). - The contractor shall provide safety measures as installation of fences, barriers warning signs, lighting system against traffic accidents as well as other risk to people and sensitive areas. At the constructio n site - Decree No. 22/2010/TT- BXD concerning regulation on construction safety. - Instruction No.02/2008/CT- BXD on safe and sanitation issues in construction agencies. Contractor PMU Compliance reported by CSC 14.Commun ication with local communitie s - Maintain open communications with the local government and concerned communities; the contractor shall coordinate with local authorities (leaders of local wards or communes, leader of villages) for agreed schedules of construction activities at areas nearby sensitive places or at sensitive times (e.g., religious festival days). - Disseminate project information to affected parties (for example local authority, enterprises and affected households, etc) through community meetings before construction commencement. - Provide a community relations contact from whom interested parties At the constructio n site - Decree No. 73/2010/ND-CP on administrative penalization security and society issues Contractor PMU Compliance reported by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 31

34 Environment al and social issues Mitigation measures can receive information on site activities, project status and project implementation results. - Monitor and address community concerns and information requirements as the project progresses. - Respond to telephone inquiries and written correspondence in a timely and accurate manner. - Inform local residents about construction and work schedules, interruption of services, traffic detour routes and material transportation routes, as appropriate. - Notification boards shall be erected at all construction sites providing information about the project, as well as contact information about the site managers, environmental staff, health and safety staff, telephone numbers and other contact information so that any affected people can have the channel to voice their concerns and suggestions. Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures 15.Chance find procedures - If the Contractor discovers archeological sites, historical sites, remains and objects, including graveyards and/or individual graves during excavation or construction, the Contractor shall: - Stop the construction activities in the area of the chance finds. - Delineate the discovered site or area. - Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities or sensitive remains, a night guard shall be arranged until the responsible local authorities or the Department of Culture and Information takes over. - Immediately notify the Construction Supervision Consultant and the subproject owner who in turn will notify responsible local or national authorities in charge of the Cultural Property of Viet Nam. - Contact the relevant local or national authorities who would be in At the constructio n site. Along connection line - Law on Cultural Heritage (2002). - Decree No 98/2010/ND-CP dated 21/10/2010 on guideline to implement Cultural Heritage Law. Contractor, supervising consultant cooperates to implement Cultural Information Department Contractor, NPMB and local Relevant local authorities POWER ENGINEERING CONSULTING JS COMPANY No. 1 32

35 Environment al and social issues Mitigation measures charge of protecting and preserving the site before deciding on subsequent appropriate procedures. This would require a preliminary evaluation of the findings to be performed. The significance and importance of the findings should be assessed according to the various criteria relevant to cultural heritage; those include the aesthetic, historic, scientific or research, social and economic values. - Ensure decisions on how to handle the finding be taken by the responsible authorities. This could include changes in the layout (such as when finding an irremovable remain of cultural or archeological importance) conservation, preservation, restoration and salvage. - If the cultural sites and/or relics are of high value and site preservation is recommended by the professionals and required by the cultural relics authority, the subproject s owner will need to make necessary design changes to accommodate the request and preserve the site. - Decisions concerning the management of the finding shall be communicated in writing by relevant authorities. - Construction works could resume only after permission is granted from the responsible local authorities concerning safeguard of the heritage. - These procedures must be referred to as standard provisions in construction contracts, when applicable. Locations for mitigation measures Applicable National Regulations, Standards Responsible party Authority Verification required to determine effectiveness of measures - Operation phase Exposure of substation worker to EMF and - Existing national law and technical regulations and standards should be strictly followed by operation and maintenance staff to ensure safe limits for EMF are not exceeded. - Evaluate potential exposure to the public against the reference levels developed by the International Commission on Non-Ionizing At central control room. At the - Decree No. 106/2005/ND- CP, dated August 17th, 2005 by the Operation and Management unit NPMB POWER ENGINEERING CONSULTING JS COMPANY No. 1 33

36 Environment al and social issues risk of electrical shock Mitigation measures Radiation Protection (ICNIRP) or the IEEE. - If EMF levels are confirmed or expected to be above the recommended exposure limits, application of engineering techniques should be considered to reduce the EMF produced by power lines, substations, or transformers. Examples of these techniques include: i) Shielding with specific metal alloys; ii) Burying transmission lines; and iii) Increasing height of transmission towers. - Specifically Worker hours will be limited in accordance with WHO: - EMF Intensity (kv/m) - Admissible exposure time (min) - Up to No limits - - Up to Up to Up to 10 - >25 Prohibited Locations for mitigation measures transformer site. Applicable National Regulations, Standards GOV. - Decree No. 81/2009/ND-CP dated October 12th, 2009 by the GOV. - QCVN 01:2008/BTC: National technical regulation on Electric safety. Responsible party Verification required to determine effectiveness of measures Fire hazard due to accident - Comply with the national law and regulation on fire prevention and fight extinguishing. - Prepare an emergency preparedness plan for fire hazard control. - Equip the substation with enough number of fire extinguishers. - Frequently examine equipment to detect and repair fire hazard. - Train operation staff on fire prevention and fire control. At substation site. - Law on Fire Prevention and Fighting No. 27/2001/QH10 dated June 29, Operation and Management unit NPMB Pollution due to oil spill and oil leakage from - Build an appropriate emergency oil spill tank as required by the regulation. - Set up a maintenance program in order to timely detect any risk of oil spill or oil leakages. - Train the operation staff for dealing with oil spill and leakages, At oil storehouse site - Circular No.12/2011/TT- BTNMT on hazardous waste management. Operation and Management unit NPMB POWER ENGINEERING CONSULTING JS COMPANY No. 1 34

37 Environment al and social issues substation Mitigation measures especially in emergencies case. Locations for mitigation measures Applicable National Regulations, Standards Responsible party Verification required to determine effectiveness of measures Noise from substation operation - Adopt low noise generating standard electrical equipment in the bidding and contractual documents. - Frequently check and maintain equipment, repair damages (If any) that can increase noise generation. - Install natural barrier (such as trees) to absorb and minimize noise. At transformer site - QCVN 26:2010/BTNM T: National technical regulation on noise QCVN 27:2010/BTNM T: National Technical regulation on vibration. Operation and Management unit NPMB Domestic waste water and solid waste - Installed septic tanks to treat domestic waste water at all working stations. - Implement a 3Rs plan for reducing, recycling, and reusing solid waste. - Sign a contract with a local environment and sanitation licensed company to collect solid waste generated at the substation. At water discharge system of the station. - QCVN 14:2008/BTNM T: National technical regulation on domestic wastewater - Decree No.59/2007/ND -CP on the management of solid waste. Operation and Management unit NPMB POWER ENGINEERING CONSULTING JS COMPANY No. 1 35

38 7. EMP IMPLEMENTATION ARRANGEMENTS Proper environmental management during construction requires the involvement of several stakeholders and agencies, each with different roles and responsibilities including: NPT, PMB, DONREs (Provincial Department of Natural Resources and Environment) of Hanoi city, the Contractors, the Construction Supervision Consultant, and local communities. To ensure effective implementation of the EMP, the following actions will be carried out during the implementation of the subproject: a) During the detailed design and tender documentation making - During the detailed design of technical specifications and preparation of bidding contract documents for each contract, the technical design consultant will incorporate into these bidding and contractual documents the parts of the EMP specific to that contract, as well as the specific measures identified in the EMP. - In preparing the bidding and contract documents, make an effort to ensure that the contractors are aware of the safeguard obligation and commit to comply. The environmental specifications in Annex 1 needs to be included in the bidding and contractual documents b) During the course of preconstruction and construction PMU will assign the Construction Supervising Consultant (CSC) and/or field engineer to be responsible for supervision of safeguard performance of contractor on a daily basis. A generic Terms of Reference (TOR) is provided in Appendix 2, CSC and/or field engineers will carry out, but not limited to, the following tasks: - Before the commencement of the construction, confirm that all compensation for land and facilities are provided and relocation and/or land acquisition/donation has been completed. - Review and approve Site (SEMP) to be prepared by contractor before the commencement of the construction. - Closely supervise the implementation of the EMP throughout the construction period. - Confirm the compliance with the agreed environmental plan and inspect any damages incurred by the contractor. If necessary, prepare an order to compensate/restore the construction sites as specified in the contracts. Contractor safeguard performance will be included in the subproject progress report. The role and responsibilities of relevant parties in the implementation of EMP are described in the following table: Table 7.1. Institutional Arrangement for Subproject s EMP implementation Community/ agencies Project Implementing Agency: NPT Responsibilities - NPT will be responsible for overseeing the project implementation including ESMF implementation and environmental performance of the project. - The NPMB will be responsible for monitoring the subproject implementation, including environmental compliance of the project. PMB will have the final responsibility for ESMF implementation and environmental performance of the subproject during both the construction POWER ENGINEERING CONSULTING JS COMPANY No. 1 36

39 Community/ agencies Project Implementing Agency: PMBs Environmental Unit EU (EU) under NPMB Construction Supervision Consultant (CSC) and/or Field Engineer Contractor and operational phases. Responsibilities - The NPMB is responsible for fostering effective coordination and cooperation between contractor, local authorities, and local communities during construction phase. PMB will be assisted by the environmental staff, and CSC/or field engineer. - Specifically NPMB will: i) closely coordinate with local authorities in the participation of the community during subproject preparation and implementation; ii) monitor and supervise EMP implementation including incorporation of EMP into the detailed technical designs and bidding and contractual documents; iii) ensure that an environmental management system is set up and functions properly; iv) be in charge of reporting on EMP implementation to NPT and the World Bank. - In order to be effective in the implementation process, PMBs will establish an Environmental Unit with at least an environmental staff to help with the environmental aspects of the project. - The EU is responsible for monitoring the implementation of WB s environmental safeguard policies in all stages and process of the subproject. Specifically, this unit will be responsible for: i) reviewing the subproject EIAs and EMPs prepared by consultants to ensure that they follow the project ESMF and meet the government and the Bank requirements; ii) helping NPMB incorporate EMPs into the detailed technical designs and civil works bidding and contractual documents; iii) helping PMB incorporate responsibilities for EMP monitoring and supervision into the TORs, bidding and contractual documents for CSC; iv) providing relevant inputs to the consultant selection process; v) reviewing reports submitted by the CSC; vi) conducting periodic site checks; vii) advising PMB on solutions to environmental issues of the project; and viii) preparing environmental performance section on the progress and review reports to be submitted to NPT, the Bank, and the local authorities if requested. - The CSC will be responsible for routine supervising and monitoring all construction activities and for ensuring that Contractors comply with the requirements of the contracts and the EMP. The CSC shall engage sufficient number of qualified staff (e.g. Environmental Engineers) with adequate knowledge on environmental protection and construction project management to perform the required duties and to supervise the Contractor s performance. - The CSC also assists PMB in reporting and maintaining close coordination with the local community. - Based on the approved EMP and environmental specifications/requirements in the bidding and contractual documents, the Contractor is responsible for establishing a site-specific EMP for each construction site area, submit the plan to the NPMB and CSC for review and approval before commencement of construction. In addition, it is required that the Contractor get all permissions for construction (traffic control and diversion, excavation, labor safety, etc. before civil works) following current regulations. - The contractor is required to appoint a competent individual as the contractor s on-site Safety and Environment Officer (SEO) who will be POWER ENGINEERING CONSULTING JS COMPANY No. 1 37

40 Community/ agencies Local community Mass organizations Province and District People s Committees (PPCs/DPCs), Provincial DONRE Responsibilities responsible for monitoring the contractor s compliance with the EMP requirements and the environmental specifications. - Take actions to mitigate all potential negative impacts in line with the objective described in the EMP. - Actively communicate with local residents and take actions to prevent disturbance during construction. - Ensure that all staff and workers understand the procedure and their tasks in the environmental management program. - Report to the NPMB on any difficulties and their solutions. - Report to local authority and NPMB if environmental accidents occur and coordinate with agencies and keys stakeholders to resolve these issues. - Community: According to Vietnamese practice, the community has the right and responsibility to routinely monitor environmental performance during construction to ensure that their rights and safety are adequately protected and that the mitigation measures are effectively implemented by contractors and the NPMB. In case of unexpected problems, they will report to CSC/PMB. - These organizations could play a role as a bridge between the PPC/DPC, communities, contractors, and NPMB by assisting in community monitoring. - Mobilizing communities participation in the subproject, providing training to communities. - Participating in solving environmental problems if any. - Oversee implementation of subprojects under recommendations of DONRE and NPMB to ensure compliance of Government policy and regulations. - DONRE is responsible for monitoring the compliance with the Government environmental requirements EMP Implementation Reporting Requirements The safeguard performance will be included in the subproject and Project progress reports. NPMB with assistance from the CSC will include safeguard performance at subproject level to NPMB periodically. At the project level, NPT will prepare safeguard performance report twice per year for submission to the World Bank describing the Project progress and compliance with the ESMF and other safeguard requirements.the reporting requirements are described in Table 7.2 below. Table 7.2. Reporting Procedures Report Prepared by Submitted to Frequency of Reporting 1 Contractor to the Employer PMB Once before construction commences and monthly thereafter 2 Construction Supervision NPMB Weekly and monthly POWER ENGINEERING CONSULTING JS COMPANY No. 1 38

41 consultant (CSC) 4 Community Monitoring NPMB When the community has any complaint about the subproject safeguards implementation 5 PMBs NPT Six-monthly 6 NPT WB Six-monthly NPMB reports on environmental performance/compliance of the subproject should be included in the progress report submitted to the NPT before each project implementation support mission and must include sufficient information on: i) preparation and disclosures of environmental safeguards instruments for subprojects; ii) incorporation of new subproject EMPs in the bidding and contractual documents; iii) monitoring and supervision of EMP implementation by the contractor, the construction supervision engineer, and the NPMB; iv) any challenges in safeguard implementation, solutions, and lessons learned. 8. Monitoring Program 8.1. Objectives It is essential to design the monitoring program and monitoring frequency appropriately to be able to demonstrate both the overall performance of the subproject works as well as the short- term impact due to peak construction activities. More specifically, as the integral and critical part of the EMP, the environment monitoring program should have the following objectives: Determine the actual extent of the impacts. Control impacts which are generated from construction process and mentioned in the EMP. Check and supervise implementation of environmental protection solutions during construction based on EMP. Suggest mitigation measures in case of unexpected impacts. Suggest to the related parties to coordinate with central and local environmental organizations to solve any pending issues that might arise relating to environmental protection under the scope of the subproject. Assess the effect of mitigation measures in pre-construction, construction and operation stages and recommend for improvement. The environmental monitoring plan is described in Table 8.1 below. POWER ENGINEERING CONSULTING JS COMPANY No. 1 39

42 Table 8.1. Environmental Monitoring Plan Impact Monitored parameter Monitored point Pre-construction and construction Phase I. Vegetation cover - Clearance technique clearance or cutting - Disposal of cut-down down trees trees. I I. Rural roads in the project region, especially along Lien Ha Thuy Lam road III. Surface water quality, sedimentation and erosion - All heavy tonnage vehicles on the local roads - Road surface situation, damage level and density of vehicles and people participating in traveling activities. - Not excavate while it is raining - Water drainage system, and construction and domestic sewage collection system at jobsite and rented house of worker. - Level of flora clearance and subproject of slope stabilization - At substation site - In a centralized place for processing. - Along the traffic road National No.3, and especially in Lien Ha Thuy Lam intercommune road route. - Surface water near the foundation construction site of substation and power line. - Water drainage are in the worker s camping site, stockpiles.. (location of receiving points for wastewater discharge). Monitoring method Timing/ frequency of monitoring - Observation - From beginning to the last moment. - Observation and consultation with local residents. Observation - Weekly basis when material is transported to the region. - During the construction time. -During and after heavy rain Responsibility -Contractor -Construction supervising consultant - Contractor, -Construction supervising consultant -Contractor, -Construction supervising consultant Verification Compliance report by CSC Compliance report by CSC Compliance report by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 40

43 Impact Monitored parameter Monitored point IV. Dust and air pollution - Checking the efficiency of the operation permission and its deadline date of construction equipment and machines. - Checking the spraying measure (reducing dust) at the material transportation roads Cover for material during transportation process - Checking woker s domestic waste collection. - Concentration of air pollutants: total dust, SO2, NOx, CO V. Noise - Noise by machinery - Local resident response to noise from the construction process VI. Sanitation situation at the construction site, including the hygiene of workers camps - Garbage, waste water at the construction site and workers tents - If the tents have been supplied clean water and had sanitary latrines. - Along transportation road - Material gathering points for construction of subproject - Residental areas surrounding the subproject area. - At the construction location of tower foundation. - At worker s camp Monitoring method - Observation - Survey equipment - Consultation with local residents - Visual inspection Observing Timing/ frequency of monitoring - Before material transportation trucks start in hot, dry and windy days -During activities that may result in high noise level; Complaints by local residents - Every week, when official acceptance of work Responsibility -Contractor, -Construction supervising consultant -Contractor, -Construction supervising consultant -Contractors -Construction monitoring consultant Verification Compliance report by CSC Compliance report by CSC Compliance report by CSC POWER ENGINEERING CONSULTING JS COMPANY No. 1 41

44 Impact Monitored parameter Monitored point - Collection of solid wastes at the construction site and at the worker s tent areas. - Disposal method Monitoring method Timing/ frequency of monitoring Responsibility Verification VII. Safety of workers and local presidents - Minutes about training in labors safety for workers. - Conditions for living activities of worker. - Labor protection equipment, warning signs and compliance with regulation on labor safety of workers. - At the construction site. - At the worker s camp - Inspection - Checking the construction diary of the contractor - Every month - Contractors - Construction monitoring consultant Compliance report by CSC Operation Phase I. Electrical field and magnetic field III. Danger of High-voltage electricity to health and electric safety for workers and - Electrical field and magnetic field - Frequency of TL inspection and maintenance. - Labor safety equipment providing - At the transformer site, central control room. - At the local people s houses near to substation. Electrical field and magnetic field measuring equipment. - 1 time/6 month. - When there are some complaints of local people - The substation site Observation 1 time/03 month PTC1 POWER ENGINEERING CONSULTING JS COMPANY No. 1 42

45 Impact Monitored parameter Monitored point local residents. for worker. - Safe distance of substation Monitoring method Timing/ frequency of monitoring Responsibility Verification POWER ENGINEERING CONSULTING JS COMPANY No. 1 43

46 9. INSTITUTIONAL DEVELOPMENT ACTIVITIES + EVN's training: Internal training course on how to monitor EMP and how to report environmental results as part of quarterly and annual project reports. + Training of PTC1: The following training will be provided for the environmental staffs and some people of local authority. + Safety training: Regular training on safety issues related to the distribution network maintenance; +Monitoring and reporting of environmental management plan for stakeholders of the Project s district or communes: The training will give guidance to the local stakeholders about the participation of local peoples during implementation of EMP. The training will also include the methodology for site observation and monitoring check sheet filling. Table 9.1. Cost estimation for capacity building in EMP implementation (*) Type of training Number of students Duration of training Starting date/ending date (for each student) Venue of training (Domestic or Abroad) Institute or organization to provide training Cost estimate (VND) Environmental Management Training Course of EVN s training days Before subproject implementation Training location is chosen by EVN (in Hanoi city) EVN combines with specialized organization. 05 persons x 03 days x 1,000,000 VND 15,000,000 VND Seminar of environmental management (training of PTC1) days Before subproject implementation, after finish Environmental Management Training Course Training location is chosen by PTC1 (in Hanoi city or others). PTC1 combines with specialized consultant 15,000,000 Training Course Contractor for days Before subproject implementation Location will be selected by NPT or by contractor. Contractor combines with NPT and consultant 15,000,000 Total 45,000,000 (*) Cost for environmental management training is held by EVN for TEP project. The cost estimated above is used for the 220kV Dong Anh substation. POWER ENGINEERING CONSULTING JS COMPANY No 1 48

47 10. COST ESTIMATION FOR EMP IMPLEMENTATION Table Summary of cost estimation for implementation of EMP No. Items Implementation cost (VND) 1 Mitigation measures (*) Construction phase - The costs is covered in the contract with construction contractor. Operation phase - Cost in covered in the operation cost of Transmission Company No1. (PTC1) 2 Environmental monitoring during construction stage (conducted by the CSC) (*) 3 Supervision cost for environmental supervisor of PMU 1person/month x 8,000,000VND/person x 12 month = 96,000,000 Included in management cost of the project of AMB The cost is covered in running cost of subproject operating unit 4 Capacity building (training cost) 45,000,000 5 Total 141,000,000 POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 51

48 11. PUBLIC CONSULTATION Public consultation Activity 1: During survey and consultation for agreement of the 220kV Dong Anh station subproject, the subproject s engineering consultancy notified local authorities at levels regarding the subproject (scale, objectives and signification of the subproject). Activity 2: Surveying, investigating field, establishing environmental impact assessment and the EMP of the subproject were conducted. After surveying and investigating, and having enough data on the subproject s impacts. The Consultant (on behalf of the Employer) held meeting dated from 15/10/2013 with local authorities of Thuy Lam commune of Dong Anh district, Hanoi city and 06/12/2013 with local authorities of Lien Ha commune of Dong Anh district. The Consultant presented the following issues: + Subproject description: location of the project, and the necessary of the subproject construction; + Potential impacts on environment caused by the subproject; + Mitigation measures against negative impacts. Summarization of attendees s opinions: + Agree with the project investment policy. + Agree with potential impact on environment caused by the project and mitigation measures against negative impacts on the environment and society. + Recommendation: the remaining land area of Bieu Khe village field should be recovered for the project. (Minutes of the public consultation meeting are enclosed in appendix 2). Information disclosure The draft EMP was disclosed at the CPC office of commune of Thuy Lam commune and Lien Ha commune, Dong Anh district, Hanoi city in Vietnamese version The Vietnamese and English draft EMP was disclosed at the Vietnam Development Information Center at No. 63, Ly Thai To St, Hanoi City and the WB s Info Shop in Washington DC on January 24, The final EMP was disclosed locally at the subproject sites, at the InforShop, and the Vietnam Development Information Center on April 18, POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

49 Table 12.1: Summary on pubic environmental consultation meetings N0. Subproject Location, date and time consultation meeting 1 220KV Dong Anh substation - Office of CPC Thuy Lam commune Dong Anh district. - Date October, No. of Participant Representative of attended local authority and HHs 10 person 1. Representatives of CPC Nguyen Huu Tuu - Chairman of CPC. Ngo Thi Bon - Chairman of Fatherland Front. 2. Representatives of others 3. Representatives of PECC1 (consultant) Summary of discussed issues and concerns Comment of attended representatives - Agree with the project investment policy. - Agree with potential impact on environment caused by the project and mitigation measures against negative impacts on the environment and society. How concerns were taken into account or why not 2 - Office of CPC Lien Ha commune Dong Anh district - Date December, person 4. Representatives of CPC Le Xuan Thuy Deputy Chairman of CPC. 5. Ngo Van Quyen - Chairman of Fatherland Front. 6. Representatives of others 7. Representatives of PECC1 (consultant) - Agree with the project investment policy. - Agree with potential impact on environment caused by the project and mitigation measures against negative impacts on the environment and society. POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

50 Annex 1: Environmental Specifications for the Contractor The environmental management requirements in construction of the subproject have been established and presented clearly in the EMP (indicate the specific section of the EMP here). The Contractor need to carefully read and fully understand all requirements included in the contractor s bid: (Insert the name of the Civil Works Package here) of the subproject. I. Overview In order to avoid negative effects into the environment and local community, as well as minimizing damaging impacts to the environment during the construction and operation stages of the resettlement sites, Contractor and workers are required to observe the mitigation measures as mentioned below: - for the Project. - The technical specifications, procedures and the most popular practices are presented in this annex. II. Overall requirements of Contractor for environmental management Contractor need, in in line with the requirements of the EMP, to include, but not limited the following responsibilities: - Be in compliance with the current national legal regulations on environmental management. - Work in scope of requirements in the contract and the conditions in the bidding documents. - Assign the representative of the construction team to participate in the site inspection operations by the PMB, CSC or the DONRE as well as implement all corrective actions to overcome the environmental issues as guidance provided by the Construction Supervision Consultant (CSC). - Provide and update information for PMB about any activities, assignments that can contribute or continue to cause the significant harmful impacts into the environment. - In case of instruction by the CSC and PMB, the Contractor must stop the construction activities that causes adverse impacts, also propose and conduct the environmental remedial actions and implementation other construction methods (if required) to minimize the negative environmental impacts. - Establish and maintain an Environmental and Safety Unit, which consists of Construction team leader or Vice- team leader and Safety and Environmental Officer (SEO) with the purpose of receiving and dealing with the complaints, objections, argument and displeased of the local community caused by the construction operation. SEO is responsible to record all of complaints, resolve methods and results into the complained register. The register need to keep at the construction office and available for review by the supervision engineer and PMB. III. Responsibilities of Contractor in EMP implementation: The construction Contractor has responsibility in compliance with the technical specifications of the EMP, (name of the subproject to be inserted here) and national environmental management regulations, including but not limited the following items: i) The mitigation measures presented in relevant section of the EMP(indicate the specific section of the EMP here) and prepare budget for implementing the mitigation measures. POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

51 ii) Based on EMP, Contractor developed a detail Site for addressing the construction related impacts. The SEMP includes the following components: - Management Plan for worker camps. - Management Plan of the overall construction operation. - Plan for management and storage of construction materials (including the dangerously chemicals) - Solid waste and waste water management plan (including construction and household waste) - Plan for management and mitigation of noise and dust. - Plan for management and mitigation of impacts to vegetation and wild animals. - Plan for environmental landscape restoration - Healthy and safety ensuring plan at the construction. - Erosion and soil aggrandizement controlling plan. - Safety plan during the construction stage and training for workers about environmental management and community relations. - Rules and regulations about living activities of staffs and workers at the construction sites. - Emergency Problem Treatment Plan. - Management and Monitoring Plan for Report Process. The detail measure of plan need to satisfy the following requirements: to implement the particular mitigation measures: who implement (people, team, etc), how to implement (labours, machines, equipment, etc.) and the cost. This plan shall be completed and submitted to the CSC for review and approval before start of the construction. The Contractor will: a) ensure that at least one supervisor is available in compliance with EMP before and during the construction time. b) ensure that all of the construction activities will be approved in document of the relevant authorities. c) ensure that all of staff and workers understand through their process and duties. d) be in compliance with requirements about the environmental management monitoring and reporting in EMP and inform to PMB about the difficulties and solutions. e) Inform to the local authority and PMB in case of environmental problems and co-ordinate with the relevant institutions and stakeholders for resolving. IV. Safety and Environmental Officer of Contractor: Each contractor will nominate a Safety and Environmental Officer (SEO) to work full-time at the construction site. Requirements for a SEO include an undergraduate degree in Environmental Major, at least 3 years of working experience in environmental management, training and monitoring at the infrastructure construction project. Additionally, SEO should have a good knowledge about Vietnamese Environmental Legal Regulations and has participated to the labor safety and sanitation training class that organized by Department of Labour- Invalids and Social Affairs and have the labor safety and sanitation certificate. SEO have the responsibilities for implementing and managing EMP of Contractor. Tasks of SEO will include, but not limit the following activities: POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

52 i) Training and developing environmental awareness for workers of Contractor within 2 weeks after the contractor is mobilized. The training is repeating every six months. The additional trainings will be implemented under the guidance of Environmental Supervision Engineer. ii) Conduct the internal environmental monitoring at the site to check the construction activity implementation of contractors, equipment and implementation methods to manage the environmental pollution and evaluate the efficiency of the mitigation measures into the environmental impacts. iii) Internal monitoring the implementation of environmental mitigation measures and in compliance of contractors with the environmental protection measures to prevent and control pollution; the committed requirements in the contract; guidelines of the contractor(s) on environmental improvement, environmental awareness and also proactive measures to prevent pollution. iv) Conduct an investigation and propose the mitigation measures for the contractor(s) in case of incompliance/ infringe the EMP; monitoring and implementing the environmental mitigation measures. v) Evaluate the success of the EMP implementation to estimate effectively the cost and adequacy of the implemented mitigation measures. vi) Survey after receiving the complaint, thence evaluate and select the corrective actions. vii) Conduct the additional monitoring activities, based on the concrete guidelines of the monitoring engineer and/ or PMB; and viii) Contact and implement all activities under the co-ordination or guidance of the Contractor Leader, Environmental Supervision Engineer, Supervision Engineer, PMB, representatives of the provincial environmental management offices, local authority about all of environmental problems if necessary. ix) Establish the regularly reports for the environmental implementation of the civil works package. x) All of the internal monitoring as well as other activities of SEO should be documented and updated frequently in the environmental implementation monitoring diary of Contractor. This diary is used for normally checking by the CSC to evaluate the effectiveness of mitigation and the work of SEO. V. Monitoring the environmental implementation of Contractor: The PMB will sign a contract with the Consultant to carry out the task of CSC. The CSC will apply the environmental and monitoring activities of the package as indicated in Appendix 2. The environmental monitoring engineer of construction/execution monitoring Consultant is responsible to monitor daily the implementation of measures, in order to minimize environmental impact and safety of the Contractor. The construction monitoring Consultant will carry out the following main tasks: Before the construction stage, make sure that all of the compensation process for land, works on land and relocation and/ or recovery/ donation of land as well as the clearance of landmines and UXO have been completed. Review and approve the SEMP for implementing the EMP by Contractor before the construction operation. POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

53 During the construction process, monitoring closely the compliance with implementing of the environmental and safety mitigation measures. Confirm the compliance with the EMP of Contractor and check any negative effect or damage caused by the contractor. If necessary, establish a request statement for contractor to compensate/ restore the construction site, as provided in the contract. The implementation of environmental management issues of the Contractor shall be mentioned in the progress report of the sub-projects. VI. Compliance Framework: a) The contractors are not allowed to implement the construction activities, including preparation of construction within the project scope in advance the detail SEMP for implementation of the EMP are reviewed and approved by the construction supervision consultant and environmental official of the Client. b) The PMB is mandatory to ensure that the Contractor in compliance with the contract provision including compliance with EMP and the detail implementation plan of EMP. In case of incompliance with EMP, Client will require the Contractor to bring out the suitable measures. c) In order to ensure in compliance with the environmental standards of the sub- project, PMB is allowed to hire the third party to solve the problems in case the Contractor could not implement the remedies on time, leading to the negative effects into the environment, as follow: - For small infringements (such as minor impact/ damage, temporary and repairable), PMB or the representative of PMB (the CSC) will notify the Contractor to correct the problems as required in the EMP within 48 hours after receiving the official report. If the mistakes are satisfactorily repaired during that time, no more action should be undertaken. Supervision consultants have the right to extend more 24 hours in the limited time for recovery, under the conditions that the Contractor has implemented activities but not completed the prescribed time, due to irresistible conditions that mentioned in the contract. - For major violations, it is required about 72 hours for repairing, the PMB through the CSC will announce the violation and require the Contractor to rectify the problems within the prescribed time by their budget. If the Contractor fails to complete corrective work according to the specified time, they will be punished by financial punishment (cost punishment is calculated by the cost of remedying damage) - According to the evaluation of the CSC, if the Contractor fails to resolve the problems in environmental management or the contractor conduct reparing unsatisfactorily within the specified period of time (48 hours or 72 hours), the investors have the capacity to arrange for another contractor (third-party) to implement the suitable measures and deduct money for this task from the contract with the contractor in the next payment. POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

54 APPENDIX 2 TOR FOR CONSTRUCTION SUPERVISION CONSULTANT Overview The Construction Supervision Consultant will be the provider of engineering services ( Services ) to ensure the effective implementation of the Sub-project EMP. Scope of Services: General services as provided by the Construction Supervision Consultant are checking and inspecting construction activities to ensure that the mitigation measures set forth in the Subproject EMP shall be accurately taken and adverse impacts on the environment shall be mitigated. On behalf of PMU, the Construction Supervision Consultant shall fulfill the following tasks: - Execute site inspection on a regular basis; - Consider the implementation situation of environmental protection measures stated in the EMP and Contract Documents; - Consider efficiency of environmental mitigation measures and environmental implementation of the Project; - If necessary, take account of acceptability in terms of environmental aspect of construction method (for temporary and permanent works), relevant design plannings and submittals. When necessary, the Construction Supervision Consultant shall look for and recommend the least impact plan on the environment in consultation with the designer, the Contractor and PMU; - Appraise the survey results about any nonconformity to the environmental quality and efficiency of remedial measures; and - Provide regular feedback audit results to the contractor s Chief Engineer according to the ECOP and site-specific mitigation measures; - Instruct the Contractor to execute the remedial actions within the prescribed schedule and carry out additional supervision if necessary, in accordance with requirements and sequence of the Contract in case there are any nonconformities and complaints; - Instruct the Contractor to implement actions to mitigate impacts and comply with the EMP procedures as requested in case the nonconformity/inconsistency is identified; - Instruct the Contractor to stop the actions which cause adverse impacts and/or the Contractor s failure to implement requirements of the EMP / carry out remedial actions. - For the contracts, it will be required to set forth EMP on site (SEMP), the Construction Supervision Consultant shall consider the last time and make a recommendation via all the environmental plans at site which are likely to affect the environment. This task includes but not limits to: dredging areas, borrowed pits and dumping site areas, camping area of workers. The Construction Supervision Consultant shall consider and approve SEMP as submitted by the Contractor. If finding that these plans do not comply with the EMP, EIA or RAP, the Construction Supervision Consultant shall co-ordinate with PMU and the Contractor to propose a reasonable measures or remediation. - Settlement of complaints: The complaints about environmental violation such as noise, dust, traffic safety and etc. from the local people will be received by the Contractor s site POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

55 staff. The site superintendent or his deputy of the Contractor and the Construction Supervision Consultant shall have to settle and achieve the solution for such complaints. The Construction Supervision Consultant shall be provided with a copy of such complaints and certify that these complaints are settled by the Contractor in a proper manner, which is similar to the related matter as identified in the site inspection. - Certification of monthly payment: The Construction Supervision Consultant shall certify monthly payments for the related activities on the environment performed by the Contractor. - Report: The Construction Supervision Consultant shall prepare the following written reports: o Report on nonconformities every two weeks o Report on monthly summaries including issues and main findings from review and construction activities o To the end of the Project, the Construction Supervision Consultant shall prepare a final report which summarizes main findings in its work, a number of violations, solution and etc. as well as provide consultations and guidance s on the implementation form of such tasks in future. POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

56 Appendix 3.1: Example of report template for monitoring of EMP implementation (Used for reports by contractor) Project name: Project location: Contractor name: Initial or monthly report: Date of report: No. Impact Mitigation measure taken Comment Construction phase 1 Surface water pollution 2 Noise and vibration level 3 Soil erosion 4 Air pollution 5 Impacts on agriculture land due to temporary land acquisition 6 Local traffic interruptions 7 Existing road damage 8 Solid waste from excavation 9 Remained soil management 10 Environmental impacts by workers 11 Conflict between workers and local residents 12 Disease spreading between workers and local residents 13 Health and safety 14.. Reported by : Title : Address : Telephone : POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

57 Appendix 3.2: Example of environmental performance monitoring report (Applying for monthly report of the Construction Supervision Consultancy submitting to the Subproject Management Board of AMB/PTC1 and SIMC) Project name: Project location: Province: District: Commune: Monthly report (Yes/No): Quarterly Report to EVN (Yes/No): Quarterly Report to the WB (Yes/No): SIMC report (Yes/No): Date of report: No. Parameter Assessment of Consultant/ community complaints Comments/ Recommendations During Construction Amount of cut down vegetation in the 1 subproject site. Noise level around construction sites 2 and adjacent residential areas. Dust, exhausts released from machines, machines, and construction activities on 3 material transportation roads and the subproject site. Tree cutting and access roads 4 management and control. Solid waste and site cleaning up after 5 the construction. Workers' sanitation facilities and 6 safety management. 7 Increased levels of traffic. 8 Status of application of safety measures. 9 Construction material management. Operational status of the treatment system 10 and waste collection. During operation The safety of the electrical system, signs 1 and accident frequency from the power. Equipment fire fighting and rescue 2 capabilities. Ability from leak from the oil sumps into 3 the environment. 4 Noise levels to operation transformers. The operation of the collection system 5 and the treatment of domestic waste. Report prepared by: Position: Position: POWER ENGINEERING CONSULTING JOINT-STOCK COMPANY No. 1 52

58 APPENDIX 4: DRAWING OF THE PROJECT LOCATION

59 APPENDIX 5: STATUS IMAGE OF THE PROJECT AREA The proposed substation and connection line site Lien Ha Thuy lam inter-commune road Vegetation image in the subproject