1 1 Security of supply in the region, closure of Ignalina nuclear power plant, building of new nuclear power plant in Lithuania Lietuvos energija AB 05/10/2007 Tallinn

2 Content of presentation: 2 security of supply in the region; closure of Ignalina nuclear power plant; new nuclear power plant in Lithuania.

3 The importance of regional interconnections Ensuring security of supply in the Baltic region Integration of the Baltic power systems into the EU IEM Possibility to install efficient big units 3

4 Planned new interconnections Estonia Finland (ESTLINK II) Lithuania Sweden (SWEDLIT) Lithuania Poland (LITPOLLINK) 4

5 Progress 5 ESTLINK project completed in 2006 SWEDLIT feasibility study will be completed in OctoberNovember The study is financed by TSOs Lietuvos energija AB and Svenska Krafnat Upgrading of LITPOLLINK interconnection s study was completed in July The Project Development Company will be established in October 2007

6 Production Consumption NORDEL NORDEL (+) Exp. (-) Imp. LT LV EE Zviedrija Sweden ESTLINK 350 MW Norvēģija Norway Integrated Baltic and CIS energy system Igaunija Estonia Latvija Latvia Russi Krievija a Lietuva Lithuania Dānija (TWh) Somija Finland Baltkrievija Belorus Poland Polija UCTE/ CENTRAL Europe Ukraina Ukraine Vācija Germany Čehija Czech

7 New NPP Production Consumption (+) Exp. (-) Imp. NORDEL NORDEL Zviedrija Sweden LT LV Capacity 1500 MW Annual production 11 TWh Somija Finland ESTLINK 350 MW Norvēģija Norway SWEDLIT EE MW Igaunija Estonia Latvija Latvia (TWh) Integrated Baltic and CIS energy system Russia Krievija Lietuva Lithuania Dānija Import TWh Belorussia Baltkrievija Polija Poland UCTE/ CENTRAL Europe LITPOLLINK 1000 MW Ukraina Ukraine Vācija Germany Čehija Czech New coal PP Capacity 400 MW

8 Development of the grid 330 KV in Lithuania Plavinu HPP Jelgava Grobinia PP Telšiai SwedLit Šiauliai LATVIJA Daugavpils Panevėžys Klaipėda Ignalinos AE Utena Polockas 330 kv Jurbarkas Belorusskaja Jonava Sovietskas Kaunas Neris Smorgonys BALTARUSIJA Kruonio HAE RUSIJA Vilnius 330 kv Lietuvos E Alytus Nuolatinės srovės intarpas 400 kv Mątki Elk Gardninas LE NKIJA Narew Mo lodečnas 8

9 BALTIC POWER SYSTEM 9

10 The closure of Ignalina NPP Unit I was shut down in December 2004 The closure of Unit II is scheduled in 2009 The Ignalina NPP can be substituted by the Lithuanian PP, but this power plant has to be upgraded to meet environment requirements 10

11 Electricity production in Lithuania Nuclear Thermal Hydro Other

12 Installed generating capacities and forecast in Lithuania Fuel Nuclear: Ignalina Thermal: Elektrėnai (condensing) Vilnius CHP Kaunas CHP Mažeikiai CHP Others Hydro: Kaunas HPP Kruonis PSPP Small scale HPP totally Other renewables: Wind Others Total generation Total without hydro and wind Daily demand Peak demand nuclear Gas, HFO, orimulsion Gas, HFO Gas, HFO HFO MW

13 Prerequisites for a new nuclear power plant To implement the National Energy Strategy and with regard to the energy policy strategy of the European Union. To develop energy sector and to ensure energy safety of Lithuania. To assure secure supplies of energy from diverse, secure, sustainable energy sources which do not emit gases causing the greenhouse effect. To substitute the power generation sources which will be lost as a result of decommissioning of Ignalina nuclear power plant. To protect the essential interests and national security of the Republic of Lithuania. 13

14 NNPP project milestones up to now LT Government adopted LT Parliament passed Signed on Approved and presented to the LT Government Communiqué Signed on MoU Feasibility Study Steering Committee LE, LV, EE Heads Communiqué LT, LV, EST Prime Ministers Signed on Law on NPP 14 Prepared on EIA* program Lietuvos energija LT Government LT Parliament LT and PL Prime Ministers *EIA Environmental Impact Assessment

15 Law on NNPP 15 Main objectives and principles: Decision in principle to construct a new nuclear power plant in Lithuania; Formation of the National Investor; Establishment of the Project Development Company (PDC), the members of the PDC, their rights and obligations, the criteria's for the members invitation and selection.

16 Legislative Initiatives 16 - Law on Enterprises and Facilities of Strategic Importance to National Security and Other Enterprises Important for Ensuring National Security - Amended Law on Nuclear Energy - New Regulation for the Licensing of Activities in the Field of Nuclear Energy (in progress) - New Law on Nuclear Safety - Other legislative changes in line with the Law on New NPP

17 Environmental impact assessment In the EIA the impacts of a new NPP of at most 3400 MW is evaluated Two alternative locations within the territory of the current Ignalina NPP are assessed All commercially available and technically feasible plant types will be taken into consideration INLET Alternative site 1 Alternative site 2 OUTLET 17

18 Preparation works of the Project 18 Completion of the Environmental Impact Assessment Finalisation selection of the site for the Project Detail planning procedures and formation of the land plot Carrying out of full ground condition surveys at the site Conducting of the amended Feasibility Study Selection of preferred technologies for the Project Preparation of the procurement strategy Preparation of Bid Information Specification, establishment of evaluation criteria and methodology and organization for selecting a construction contractor for the Project Coordination of draft bid invitation and specification with regulatory authorities Establishment of long term policy on storage and disposal of radioactive waste and spent fuel Carrying out of cooling water modelling and other required studies Preparation of human resource strategy Preparation of information technologies strategy

19 Strategic partnership 19 Based on MoU, LE, LvE and EE have prepared the Feasibility Study MoU foresees, that parties should agree on next steps On July LE submitted the Project Development Agreement to LvE, EE and PSE for review Project Development Agreement establishes Project development and cooperation principles: identifies required preparation works empowers a single point of responsibility for implementing required preparation works provides mechanics for cost sharing increases flexibility to move the Project forward secures consensus based decision making process