1 Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited smi.investment.limited@gmail.com Date : August, 2016

2 Executive Summary The Monthly Progress Report is prepared for providing information about the progress of Sano Milti Khola Hydropower Project, Ramechhap (3 MW). It will contain the information about the project activities and achievement of the preceding month along with the work plan for the particular month. This report will be issued in the first week of every month. Major project activities will be highlighted.

3 1.0 Background The Sano Milti Khola Small Hydroelectric Project (3 MW) is run-off-river type hydropower project proposed along the Sano Milti Khola in Ramechhap and Dolkha District of Janakpur Zone. The project area lies within Fulasi VDC of Ramechhap district and Melung VDC of Dolkha District. Sano Milti Khola Hydropower Ltd. holds the survey license for this project. The boundary co-ordinates of the project are E to E and N to N. Sano Milti Khola Hydroelectric Project has been promoted by SM Investment Ltd (SMI). SMI is basically a collective effort of Nepalese in South Korea to invest in Sano Milti Khola Small Hydroelectric Project. 2.0 Project Development Milestones S No Date Milestone /04/28 BS Survey License Issued in the name of Mr Ram Bdr Tamang /03/07 BS DoED extended the Date of Survey License of 3000 kw in the name of Sano Milti Khola Hydropower Pvt. Ltd upto 2071/02/25 BS /01/05 BS Ministry of Energy approved the ToR of Sano Milti Khola Hydropower Project /05/05 BS DoED extended the date of Survey License up to 2072/02/25 BS /02/24 BS Ministry of Energy approved the IEE Report and at the same day the approved IEE Report was submitted in DoED /02/24 BS Registered application to obtain Generation License /03/10 BS Grid Connection Agreement with NEA /01/13 BS Power Purchase Agreement with Power Trade Department/NEA /02/09 Agreement with Thodung/Waiba & Lama JV for Civil Construction Works /07/01 Generation License Issued by Department of Electricity Development

4 3.0 Project Description 3.1 Location & Access The project site is about 175 km away from Kathmandu, the capital city of Nepal. Manthali, the nearest trade center or town is about 22 km away towards south from the project site. Another nearest town is Charikot which is about 37 km away towards north. The powerhouse site of the project is 3 km far from the Milti Dobhan accessible by the graveled road Charikot Kirnetar Manthali Road. The proposed intake site is located on Milti Khola at about 6 km upstream from the confluence of Milti Khola and Tamakoshi River at the boundary of Melun and Phulasi VDC. The forebay location at Aimantar Village can be reached by constructing about 4.5 km road section from Milti Dobhan. Similarly, the headworks site can be made accessible by excavating about 3 km long track along the Milti Khola from the Milti Dobhan.

5 3.2 Project Layout Map Project Layout Plan

6 3.3 General Features of the Project Name of River : Sano Milti Khola Nearest Town : Manthali of Scheme : Run-of-River Gross Head : 216m Net Rated Head : Installed Capacity : 3.0 MW Average Annual Energy after Outage : GWh 1. Hydrology Catchment Area Mean Annual Discharge Design Discharge (at Q40 PoE) Riparian Release Design Flood Discharge Average Annual Precipitation 2. Diversion Weir of Weir Length of Weir Crest Elevation : 55 km2 : 2.17 m3/s : 1.7 m3/s : 0.09m3/sec : 277m3/sec (100 yr. flood) : 1650mm : Concrete Weir : 26 m : El m 3. Intake Structure : Side intake Size : (1.50 m x 0.80 m) Nos : 2 (Two) 4. Gravel Flushing structure Length Size (Depth) Width Nos : Surface, rectangular type : 11 m : 1.3 m to 2.50 m : 1.60 m : 2 (Two) 5. Desanding Basin : Surface, rectangular type, Concrete No. of Bays : Double Length : 29 m Wide : 3.50 m Total Depth (Including Hopper) : 2.21 to 3.15 Particle size to be settled : 0.20 mm :

7 6. Headrace Canal Length Wide Height : Concrete (Rectangular) : 2191 m : 1.50 m : 1.0 m 7. Forebay Surface Area : 153 m 2 (Length 17 m x Width 4 m) Volume : m 3 Bed Level : m Gate : Sluice Gate 8. Penstock Pipe : Steel Total Length : m Diameter : 0.90 m Material/Thickness : Structural Steel, 10 mm to 18 mm Bifurcation Length : 9.0 m m Bifurcation Diameter : 0.70m 9. Powerhouse Size (L x W) Height Turbine Axis Level 10. Tailrace Section Total length Size Tail Water Level : Surface : 32 m x 14 m : m : m : RCC Structure (Buried) : Rectangular : m : 0.85 m x 2.0 m : m 11. Turbine : Horizontal Axis Pelton No of unit : 2 (Two) Rated Output Capacity Per unit : 1500 kw Rotational Speed : 750 rpm Efficiency : 88.15% 12. Governor : Electric-electronic Adjustment for Speed Drop : Between 0 to 10%

8 13. Generator : Synchronous, 3 Phase No. of Units : 2 (Two) Rated Output Capacity per Unit : 1700 kva Power Factor : 0.85 Voltage : 6600 V Frequency : 50 Hz. Efficiency : 95% 14. Transformer : Three Phase, Oil Immersed Nos of Units : 2 (Two) Rated Capacity per unit : 1700 kva Voltage Ratio : 11/33 kv Efficiency : 99% 15. Transmission Line Voltage Level Length From To : 33 kv : 5 km : Powerhouse : NEA Kirnetar Substation

9 4.0 Construction Schedule:

10 5. Project Progress 5.1 Coordination with District Forest Office Site Visit for verification of trees at the project site was made by District Forest Office Team. Detail Report was prepared and all the necessary documents has been forwarded to Department of Forest, Kathmandu. After the review, the document will be forwarded to Ministry of Forest and Soil Conservation. DFO Team Members (Site Inspection) 5.2 Meeting with the Banks Document Review is under process in the banks. Meetings and discussions are being regularly held for finalization of the financial closure at the earliest. 5.3 Factory Visit in China (Electromechanical Suppliers) Technical Team of Chairman and Project Manager had made the visit to China for identifying some of the prominent electromechanical suppliers of China with strong presence in Nepalese

11 market. Factory along with other infrastructures were reviewed to prepare a roster of potential and reliable E/M Suppliers. Further technical discussions with the suppliers are scheduled to be held in the project office.

12 5.4 Issuance of Generation License Generation License of Sano Milti Khola Hydropower Project has been issued by Department of Electricity Development on 1st Kartik, Sano Milti Khola Hydropower Ltd holds the license for Sano Milti Hydropower Project from 2073/06/09 to 2108/06/ Joint Survey/Investigation of Headrace Section Joint Team of Design Consultants (Gorkha Hydro & Engineering P Ltd), Technical Consultants(TAC Hydro Engineers P Ltd), Civil Contractors and SMKHL Team had made a thorough investigation at the site along with the Geologists. Detail report will be provided by the consultant team after Tihar regarding the field inspection along with their recommendations.

13 Monthly Work Plan November S No Description May Remarks Week 1 Week 2 Week 3 Week 4 1 Follow up Tree Cutting Approval Dept of Forest/GoN 2 Inauguration at Site 3 Access Road Works Site Visit 4 Document Revision for Loan Processing (Bank) 5 Meeting with Electromechanical Suppliers at Office (Ktm) 6 Joint Survey (Headrace Section)