1 Application for Prior Environmental Clearance (EC) (See Paragraph 6 tification dated14 th September 2006) as amended to EIA tification, 2006 issued vide S.O. 3067(E) on dt Basic Information Item Details 1. Name of the project/s Area acre (16.194ha) for river sand/morrum mining at gata no. 267,268, khand no.03 Village- Kyotra, Jalaun (U.P) 2. S.. in the schedule 1(a) 3. Proposed capacity/area/length /tonnage to be handled/ command area/lease area/ number of wells to be drilled 4 New/Expansion New 5 Existing capacity/area etc. NA(New Mine) Tehsil-Kalpi, District- Proposed Production 1,61,940 m 3 Per Annum or 2,91,492, TPA ( at Tonnage Factor of 1.8) 6. Category of the project i.e. A or B As per EIA tification dated , as amended on and this project falls under Category B (Sub-category B2 7. Does it attract the general condition? If NA yes, please specify. 8. Does it attract the specific condition? If yes, please specify. 9. Location Area acre ( ha) for river sand/morrum mining at Gata no. 267,268, khand no.03 Village- Kyotra, Tehsil-Kalpi, District- Jalaun(U.P) Point Latitude Longitude A 25 52'5.62 N 79 47'9.00 E B 25 52'3.92 N 79 47'20.78 E C 25 51'50.46 N 79 47'24.74 E D 25 51'53.33 N 79 47'7.15 E Plot/Survey/Khand. Khand no. 03 Gata no. 267,268 Village Tehsil District State 10. Nearest railway station/airport along with distance in kms. Kyotra Kalpi Jalaun Uttar Pradesh Aata Railway Station Km NW Farrukhabad Airport (approx km N) F1-1

2 11. Nearest town, city, district Headquarters along with distance in Km Nearest Town Kalpi, approx km N Nearest city Jalaun approx Km NW 12. Village Panchayats, ZillaParishad, Village Panchayat- Village Kyotra, Tehsil- Municipal Corporation, Local body Kalpi, District- Jalaun, Uttar Pradesh Pin code- (complete postal address with telephone nos. to be given) 13. Name of the applicant Prop. Sri Suresh Chandra Gupta 14. Registered Address R/O- 60,Ganesh Bazaar Jhansi,Distt-Jhansi,U.P 15. Address for correspondence: R/O- 60,Ganesh Bazaar Jhansi,Distt-Jhansi,U.P Name Prop. Sri Suresh Chandra Gupta Designation (Owner/Partner/CEO) Address Owner Pin Code Telephone. - R/O- 60,Ganesh Bazaar Jhansi,Distt-Jhansi,U.P Fax Details of Alternative Sites examined, if any. Location of these sites should be As it is specific project site, no alternate site is proposed shown on a topo sheet. 17. Interlinked Projects other interlinked projects 18. Whether separate application of t Applicable interlinked project has been submitted? 19. If yes, date of submission t applicable 20. If no, reason. t Applicable 21. Whether the proposal involves approval/ clearance under: if yes, details of the same and their status to be given. (a) The forest (Conservation) Act, 1980? (b) The wildlife (Protection) Act, 1972? (c) The C.R.Z. tification, 1991? 22. Whether there is any Government order/policy relevant/ relating to the site? 23. Forest land involved (hectares) Forest area involved The proposed does not involve approval/clearance under the said Acts & tification The area has been granted in favour of applicant vide letter no.843/khanij-mmc-30(e-tender/2018 dated 27 January 2018 for a period of five years, attached as Annexure-1 & 2. F1-2

3 24. Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? (a) Name of the Court (b) Case. (c) Orders/directions of the Court, if any and its relevance with the proposed project. litigation or court case is pending against the proposed project. (I) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) / 1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) 1.2 Clearance of existing land, vegetation and buildings? quantities /rates, wherever possible) with It is Government land. Due to mining activities This there will be slight changes in topographical features because proposed mining confined to river bed only. other area disturbed. Proposed mine is a part of river bed with sand reaches. Sand/Morrum mining will be done up to a restricted depth in river bed or as per approved Mining Plan. The activity will take place on the river bed. The excavated sand/morrum from mine lease area will be naturally replenished with the flow of water. Mining will be restricted to the allotted area only keeping the shores unaffected, thus does not involve any change in existing topography or land use. The area is non forest waste land, not covered with any vegetation. 1.3 Creation of new land uses? LOI is issued dated 27/01/2018 vide letter no. 843/Khanij-MMC-30(E-tender/2018). The project does not involve any creation of new land use. 1.4 Pre-construction investigations e.g. bore houses, soil testing? t Applicable 1.5 Construction works? t Applicable 1.6 Demolition works? t Applicable 1.7 Temporary sites used for construction works or housing of construction Temporary working office will be maintained at site. This will be temporary structure and F1-3

4 / workers? 1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations 1.9 Underground works including mining or tunneling? quantities /rates, wherever possible) with can easily shift one side to another side as and when required. civil work is required in the mine lease area. Only sand/morrum mining will be done 1.10 Reclamation works? reclamation measures will be adopted at site except leveling of river bed after Extraction of Sand/Morrum from river bed level. River itself replenishes with sediment carried during monsoon season Dredging? t Applicable 1.12 Offshore structures? t Applicable 1.13 Production and manufacturing processes? 1.14 Facilities for storage of goods or materials? 1.15 Facilities for treatment or disposal of solid or liquid effluents? 1.16 Facilities for long term housing of operational workers? The mining operation will be carried out by opencast method and about 1,61,940 cum./annum of sand/morrum will be excavated. t Applicable t Applicable Most of the workers will be employed from local village. Hence, housing facilities are not involved During operation phase there will be increased to present traffic there is no proposal for construction of new roads, rail routes New road, rail or sea traffic during construction or operation? 1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing The project does not involve any closure or transport routes or infrastructure diversion of existing transport routes or leading to changes in traffic infrastructure leading to changes in traffic movements? movements New or diverted transmission lines or t Applicable pipelines? 1.21 Impoundment, damming, culverting, There would be no construction laborers realignment or other changes to the inhabit at site thus there will be very less or hydrology of watercourses or no generation of solid waste is anticipated. aquifers? 1.22 Stream crossings? Most of the workers will be employed from local village. Hence, housing facilities are not involved F1-4

5 / 1.23 Abstraction or transfers of water form ground or surface waters? 1.24 Changes in water bodies or the land surface affecting drainage or run-off? 1.25 Transport of personnel or materials for construction, operation or decommissioning? 1.26 Long-term dismantling or decommissioning or restoration works? 1.27 Ongoing activity during decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either temporarily or permanently? 1.29 Introduction of alien species? t applicable 1.30 Loss of native species or genetic t applicable diversity? 1.31 Any other actions? t applicable quantities /rates, wherever possible) with The water requirement for the operational workers is met by private tankers from nearby dugwell/borewell. It is estimated that approx. 60 local labors are hired from nearby villages;. Total water requirement will be KLD. Proposed sand /Morrum mining will be done scientifically, and systematically as per mining rules in the allotted Gata only which unaffecting adjoining areas up to a depth of 3 mbgl, thus the changes in water bodies and the land surface are not expected. Excavation of sand will be done by manually/semi-mechanized. Tractors-trolley, Dumpers & JCB may be used as per requirement to collect the river Sand/morrum with prior permission of authority long-term dismantling or decommissioning or restoration works are involved t applicable. It is estimated that approx 60 laborers will be employed locally from nearby areas; The influx of the people will be temporary and positive (in terms of employment). 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): Information/checklist 2.1 Land especially undeveloped or agricultural land (ha) / quantities /rates, wherever possible) with Undeveloped, unfertile Govt. Land. LoI is awarded in favor of the proponent by the District Magistrate and also directed the proponent to get Environmental clearance certificate from MoEF. LoI is issued dated F1-5

6 Information/checklist 2.2 Water (expected source & competing users) unit: KLD / quantities /rates, wherever possible) with 27/1/2018 vide letter no.843/khanij-mmc- 30(E-Tender/2018) for further action towards execution of lease KLD through Tankers 0.60 KLD For drinking (for LPC KLD for Dust 2 lts/ SQM for 1200 mts road) 2.14 KLD for Green Belt) 2.3 Minerals (MT) Only sand /Morrum will be extracted. Proposed quantity:1,61,940 m 3 (2,91492MT) in lease period. 2.4 Construction material River Sand, aggregates, sand / soil (expected source MT) 2.5 Forests and timber (source MT) t applicable 2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW) 2.7 Any other natural resources (use appropriate standard units) construction activity will take place on the site. Since mining activity will be carried out in day time only, and no housing facility for laborers is proposed. Thus no electricity or any fuel for energy is required. Solar panel will be used for site office & Road side t applicable 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. / 3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by changing living conditions? Mining shall be carried out manually/ Semi -mechanized (drilling & blasting not required) & shall be loaded manually/using machines in to tippers/tractor trolleys & dispatched to market. It is proposed Open cast Mining project does not cause any changes in occurrence of disease or affect disease vectors. The proposed project will provide employment to skilled as well unskilled labour from the nearby villages and will also provide business opportunities in the area. F1-6

7 3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes t applicable This will help in socio economic development and increasing the living standard of the people from nearby villages. There are no sensitive areas like school, hospital are present in the vicinity of excavation site that are vulnerable to be affected. 4. Production of solid wastes during construction or operation or decommissioning (MT/month) / 4.1 Spoil, overburden or mine wastes Minor minerals will be excavated /extracted from the allotted gatas only and transported directly to the potential domestic/local markets; hence no waste generation is anticipated. Some time topsoil found as overburden which scraped separately. 4.2 Municipal wastes (domestic and or commercial wastes) 4.3 Hazardous wastes (as per Hazardous t applicable Waste Management Rules) 4.4 Other industrial process wastes t applicable 4.5 Surplus product t applicable 4.6 Sewage sludge or other sludge from t applicable effluent treatment 4.7 Construction or demolition wastes t applicable Very small amount of municipal waste will be generated; however collection bins will be provided for the same and will be disposed off as per MSW Rule, Redundant machinery or equipment Mining will be done manually/semimechanized Only PUC vehicle will be allowed in mining activities. 4.9 Contaminated soils or other materials t applicable 4.10 Agricultural wastes t applicable 4.11 Other solid wastes t applicable 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) / F1-7

8 5.1 Emissions from combustion of fossil fuels from stationary or mobile sources / During operational phase there may be vehicular exhaust emissions by movement of vehicles which will be minimized by using well maintained and PUC certified vehicles in the mining lease area. 5.2 Emissions from production processes Some fugitive emission during mining and transport activities. 5.3 Emissions from materials handling including storage or transport 5.4 Emissions from construction activities including plant and equipment 5.5 Dust or odours from handling of materials including construction materials, sewage and waste Dust emission is anticipated from handling and transportation of materials which will be minimized by water sprinkling on haulage road and through tarpaulin cover on transportation vehicles. t applicable 5.6 Emissions from incineration of waste t applicable 5.7 Emissions from burning of waste in t applicable open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources t applicable 6. Generation of ise and Vibration, and Emissions of Light and Heat: 6.1 From operation of equipment e.g. engines, ventilation plant, crushers / 6.2 From industrial or similar processes t applicable 6.3 From construction or demolition t applicable 6.4 From blasting or piling t Applicable 6.5 From construction or operational traffic 6.6 From lighting or cooling systems t applicable 6.7 From any other sources t applicable There may be minor emissions in the form of dust during mining of Sand/Morrum. Generation of noise can be anticipated from operation of transportation vehicles on the Working site. Well maintained (PUC) trucks and tractors will be used which will be mitigate the effect of noise pollution Operational traffic may contribute in noise generation. Proper maintenance of vehicles will reduce the impact. F1-8

9 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: 7.1 From handling, storage, use or spillage of hazardous materials 7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) 7.3 By deposition of pollutants emitted to air into the land or into water / 7.4 From any other sources t applicable 7.5 Is there a risk of long term build up of pollutants in the environment from these sources? t applicable Mobile toilet will be used for collection of sewer and which will be managed by portable toilet at site. Water sprinkling will be done on haulage roads for suppression of dust which will be generated by vehicular movement. t applicable 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment 8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances / 8.2 From any other causes t applicable 8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? storage is proposed at site, material will directly transported to the market. The proposed mining area is a slightly undulated, river bed land which falls in seismic zone II, where chances of severe earth quakes are very low. In order to further safeguard the disasters described under the column, mining activities will be carried out in the day time and in the lean period (dry season) only. 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality / F1-9

10 9.1 Lead to development of supporting facilities, ancillary development or development stimulated by the project, which could have impact on the environment e.g.: Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) extractive industries supply industries other 9.2 Lead to after-use of the site, which could have an impact on the environment 9.3 Set a precedent for later developments 9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects / Improve socio-economic status of villages around mine area Benefits to local people due to employment Improvement in educational facilities Provision of health facilities supporting infrastructure is required since the site has good connectivity with local roads, and highways SH km (N). Also the laborers will be hired locally thus no permanent or temporary housing is required at site. Since it is an open cast excavation, arrival of monsoon every year will replenish the excavated site. Hence there will be no change in land use pattern. t applicable The project will cause positive, long term impact. (III) Environmental Sensitivity Areas Name/ Identity 1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests. 3 Areas used by protected, NO important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration Aerial distance (within 15 km) of proposed project location boundary There is no protected area. Betwa River. Proposed for river bed mining activity Jalalpur Reserve Forest 1.64 Km SE t applicable F1-10

11 Areas Name/ Identity 4 Inland, coastal, marine or underground waters 5 State, National boundaries t applicable 6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Aerial distance (within 15 km) of proposed project location boundary t applicable (SH-91) Approx km in N direction from the project site. 7 Defense installations t Within 15 km of the project site. 8 Densely populated or built-up area Nearest Town Kalpi, approx km N 9 Areas occupied by sensitive Primary schools and temples are present. in man-made land uses (hospitals, vill- Basrehi 2.15 km in NW direction from schools, places of worship, the project site. District Hospital Jalaun is community facilities) situated km towards rth West 10 Areas containing important, high quality or scarce resources(ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) direction from the project site. The project site locates on river bed of Betwa River. thing specific The area under study falls in Zone-II, according to the Indian Standard Seismic Zoning Map. F1-11

12 I hereby give undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost. Date: Place: (Signature of the Proponent with Name and Full Address) Prop. Sri Suresh Chandra Gupta R/o- 60, Ganesh Bazaar Jhansi,Distt-Jhansi,U.P F1-12