1 Sustainability Practices that Work Oregon School Board Association Sustainable Schools Conference January 27-28, 2010 Portland Public Schools Nancy Bond, Hood River School District Liz Whitmore Opsis Architecture Alec Holser, Gerding Edlen Renee Loveland

2 Fostering Sustainability in Schools Portland Public Schools Nancy Bond

3 Resource Conservation Specialist Reduce utility budget Change behavior Develop policy In 10 years, my work has saved Portland Public Schools more than $7.5 million

4 Today s presentation Utility bill review Energy conservation Solid waste management Stormwater management Interdepartmental collaboration Green building occupant education

5 Utility Bill Review Watch for: Correct rate schedule Unwarranted fees (late fees, service charges) Spikes Misread meter? Leak? Irrigation? Bad behavior? Billing system malfunction?

6 Leak Credit Normal = ~ $2,000 Previous bill = $8,116 Credit = $4,241.19

7 Irrigation Previous = $6,500 Current = $18,605 Service Date = July

8 Billing system meltdown Normal = $4,439 Not normal = $234,897

9 Correcting Utility Errors Internally, work with: Accounts Payable - watch bills Maintenance staff - alert to leaks Also work with utility service provider: Correct rate schedule Get credit for leaks, overcharges And watch for: Double billing That it s your property That it s a current account

10 Utility Bills: Review Watch for trends = opportunity to change behavior Monthly Electricity Use for Buckman 40,000 30,000 20,000 kwh 10, /05 04/05 07/05 10/05 01/06 04/06 07/06 10/06 01/07 04/07 07/07 10/07 Electricity Use 01/2005 thru 12/2007 Annual Trend

11 Energy Conservation Power Patrol Focus on behavior change

12

13 Energy Challenge Compare kwh to previous year (Jan Mar) Goals: Reduce energy consumption Teach students about environmental impact of different energy sources Teach students how to reduce energy consumption in schools and at home Educational outreach deliverables: Classroom presentations, assembly, signs, posters schools participate

14

15

16 Energy Challenge Results 2008 savings = $5,003 = 4% 2009 savings = $5,851 = 6.5%

17 Waste Reduction and Recycling District wide recycling program Oregon Green Schools certification program State-wide program: 3 levels of certification Focused on behavior change Includes recycling, buying recycled, energy conservation PPS has 28 certified Oregon Green Schools (2 premier and 5 merit schools with 11 in the application process)

18 PermanentwareTrays PPS discards more than 20,000 polystyrene trays per day $14,000 grant to purchase 2500 trays for 9 schools

19 Results Saved nearly $6,000 in avoided disposal costs No measurable increase in electricity or water/sewer costs Plan to roll out districtwide beginning 2010

20 Stormwater Management More than $1 million/year in stormwater fees Goals: Reduce stormwater in pipes Gain Clean River Rewards stormwater credits Create educational opportunities for students, staff, community

21 Stormwater Management Astor School Rain Garden

22 davinci Arts Middle School

23

24 Mt. Tabor Middle School

25

26 Results More than $54,000 in retroactive credit More than $60,000 annually on-going Clean River Rewards credits

27 Interdepartmental Collaboration Nutrition Services Trays Fork it Over! 62 tons in 5 years Warehouse Textbooks, surplus donations Procurement Buy recycled Surplus office supplies web page

28 BESC Green Team Educational Outreach and Process Change Bi-monthly electronic green tips to all BESC PPS employees Answer queries from employees Bulletin board celebrating sustainability projects in district

29 BESC Green Team BESC Green Team includes volunteers from 11 departments Energy, solid waste projects Promoting one garbage can per department Custodians replace plastic bag only when soiled Water dispenser/glasses for Board Night audit Turned off BESC fans after 6 p.m. (saves $31,346/yr) Set sleep function on some computers, copiers and printers

30 Results: Real savings (since Dec 2008): $31,346/yr achieved Potential savings: additional $12,700/yr identified from these initiatives

31 Two big successes Night survey - Finance (28 computers) District-wide change on copier settings: to sleep after 5 minutes, saves $150,000/yr

32 Green Building - Partnerships Rosa Parks Housing Authority of Portland owns property Boys and Girls Club shared space and utilities Result: LEED Gold school for fraction of cost

33 Evans-Harvard High Performance Classroom at davinci Arts MS

34 Partners Construction Team: SRG Partnership Inc.: Architect Todd Hess Building Company: General Contractor PBS Engineering: Project Management Funding Partners: Oregon Department of Energy City of Portland - Green Investment Fund davinci Arts Middle School - school fund raising Business Energy Tax Credit (OR Dept of Energy) Mark Edlen - personal gift Bonneville Environmental Foundation Energy Trust of Oregon Plus 32 other donors!

35 Education goals How to: Use building as designed Maintain the building Use building as teaching tool Connect occupants with their built and natural environments

36

37 Sustainable Behavior in Schools Start with easy stuff Identify and nurture your champions Engage all levels in the organization Foster partnerships Celebrate successes!

38 Thank you! Questions? Nancy Bond ext 4279

39 Integrating Learning Outcomes in the Sustainable Design Process Hood River School District Liz Whitmore Opsis Architecture Alec Holser

40 Hood River School District Bond Projects 7 schools $16 million dollars Renovations / Additions/ Energy Upgrades/ Seismic Upgrades

41 Hood River Middle School Music/Science Center LEED Platinum Net-Zero

42 Cultural Resource

43 Historic School Context

44 Existing Science Program

45 Defining a Sustainable Vision Eco Charrette TAG Program

46 Defining a Sustainable Vision Eco Charrette TAG Program

47 LEED Path to Net Zero International Living Building Institute

48 Hood River Middle School Music/Science Center LEED Platinum Goals Sustainable Sites : open space, stormwater management, reduce heat island effect Water Efficiency: low water landscaping, efficient fixtures Energy & Atmosphere: 67% energy use reduction Materials & Resources: recycle construction waste, use recycled/regional/rapidly renewable materials Indoor Environmental Quality: daylight and views, increased ventilation, enhanced thermal comfort

49 Hood River Middle School Music/Science Center Platinum Goals Sustainable Sites : open space, stormwater management, reduce heat island effect Water Efficiency: low water landscaping, efficient fixtures Energy & Atmosphere: 67% energy use reduction Materials & Resources: recycle construction waste, use recycled/regional/rapidly renewable materials Netzero: Produce as much energy as the building consumes 33% energy production Indoor Environmental Quality: daylight and views, increased ventilation, enhanced thermal comfort

50 Net Zero Goals Net zero water Rainwater collection and storage Efficiency of use, Treatment for use On site wastewater and storm water treatment Net zero energy Reduce use through efficiency measures Produce energy through renewable technologies (solar and wind power)

51 Energy Trust Netzero Pilot Program Early design assistance Technical assistance Premium installation incentives Performance verification incentives

52 Board Concerns Allocation of resources/$ to meet needs of entire District Administration Equality of projects across the District Additional costs to achieve LEED Platinum and Net Zero Fiscal responsibility of using tax payer s $ Equality of program delivery between the two middle schools in HR Waiting for Bids to make final decision

53 Positive Aspects Doing the Right Thing (energy efficiency, sustainability, reducing carbon footprint, community leadership) Creating a Living Building as a teaching tool (incorporating curriculum and supporting existing environmental science program) Net Zero Achievement Incentives Energy Trust Pathway to Net Zero Pilot Program

54 Science and Music Center Library

55 National Historic Register Building as a Cultural Resource

56 Project Site

57

58

59 Hood River Middle School Music/Science Center Science and music center New elevator/ improved exiting Music and Science / Environmental Learning Center / ADA Life Safety Upgrades

60 Net Zero Water Bioswale Stream Roof Collection

61 Hood River Middle School Music/Science Center

62 Hood River Middle School Music/Science Center

63 64 Points = LEED Platinum

64 Integrated Design

65 Energy Efficiency: R-15 Under-slab Insulation

66 Energy Efficiency: Radiant Flooring

67 Energy Efficiency: ICF/Brick Walls & Triple Glazing for Thermal Mass, Cultural Context

68 Use of Existing Resources: Reuse of Existing Building

69 Energy Efficiency: Displacement Ventilation, CO2 Sensors, preheated air with Transpired Solar Collector under PV panels

70 Energy Efficiency: R-38 Roof Insulation

71 Energy Efficiency: Daylighting Monitor/Skylights

72 Community & Site Connection: Greenhouse

73 Community & Site Connection: Amphitheater

74 Energy Efficiency: Energy Model

75 Building as a Teaching Tool

76 Hood River Middle School Music / Science Center Annual End Use Energy Baseline Building Use: -247,100 KBTU/Yr LEED Platinum Building Use: -105,020 KBTU/Yr Netzero Building Generation: Solar Wall Photovoltaic Array Wind Demonstration 22,300 KBTU/Yr 121,800 KBTU/Yr 1,700 KBTU/Yr = 145,800 KBTU/Yr + 40,780KBTU/Yr

77 Hood River Middle School Costs Energy Efficiency Measures: $57,640 Renewable Energy Systems: $227,000 Total Added Cost: $284,640 ETO Efficiency Incentives: $15,000 ETO Renewable Incentives: $45,000 BETC LEED Platinum Incentive: $13,600 BETC Photovolatic Incentive: $80,400 Total Incentives: $154,000 Total Net Added Cost: $130,640

78 Hood River Middle School Music / Science Center Simple Payback Total Building Costs $1,573,142 hard costs Net zero Building Added Renewable Energy Costs $130,640 / $6,565 per year (annual cost savings) = year payback Simple payback is based on current energy costs

79 ESCO Projects: McKinstry Energy Services Updating lighting to more energy efficient fixtures and layout Updating major mechanical systems (e.g., boilers, heating, ventilation systems) Only 3 steam heating systems, to be tested for efficiency Installing new trash compactor Installing a complete control system to aid in strategic scheduling and controls All systems to be commissioned to ensure visibility of savings and results

80 McKinstry Estimated Savings Estimated Utility Rebates from Energy Trust of Oregon, BPA, and existing SB1149 accrued funds $536,430 Estimated Business Energy Tax Credit $135,521 Total estimated annual energy savings $195,017 By implementing these building improvements, CO2 emissions will be reduced by 2,412,589 pounds annually, which is equivalent to removing 162 cars from the road or planting 330 acres of trees.

81 Energy Savings Guarantees Where McKinstry has direct control, it is prepared to guarantee any portion of a project. Where McKinstry does not have direct control (such as burn hours associated with lighting), McKinstry is prepared to work with the district to devise a method of Measurement and Verification (M&V), which will provide the highest degree of assurance that the energy cost savings exist.

82 Food and Conservation Science Food, Energy, Water, Waste

83 Garden Flow Energy What is it? Where does it come from? Production Issues Independent production Conservation measures Energy budget (net zero) Passive solar Solar hot water Choices Harness human energy Commerce Enthusiasm Increase in health/productivity Water Cycles and Patterns Quality and Quantity Catchment Storage Movement Conservation Sense of Place Change over time : Human ability to effect change : Belonging : Pride in job well done : Sense of wonder and joy : Demonstration to others : Wellspring of ideas : Observation inspiration : Relationship with land : Beauty Waste Compost Recycling Raw/real food Reduction of transport Grown nutrients/fertilizer Food Nutrition Exercise Slow food Inclusion/infusion into curriculum Relation to culture Availability Awareness Sense of caring From The Permaculture Classroom by Michael Becker

84 Public/Private Process to Sustainable Systems Implementation Gerding Edlen Renee Loveland

85 Sustainable Practices that Work OHSU Center for Health and Healing Sustainable Systems Implementation Oregon School Board Association Conference Post Occupancy Evaluation (October January 2009) 27 28, 2010

86 Sustainable Systems Implementation GESS Overview GESS is a wholly-owned subsidiary of Gerding Edlen Development Company, LLC Specializing in program management of facility enhancement programs Developer -led comprehensive retrofit services from assessment through implementation Managing large complex projects on-time and on-budget Structuring innovative financing options including public-private transactions with varied capital sources such as tax credits, utility incentives, debt, and equity Pioneering an interactive systems approach Integrated Resource Optimization TM - that targets multiple resources: energy, water and waste Utilizing multiple strategies: efficiency, distributed generation (e.g. solar) and site improvement Optimizing system interactivity: integration of the building, site and central plant facilities 86

87 Sustainable Systems Implementation Systematic and Comprehensive Process Work with client to develop common understanding of financial constraints, building use, systems and occupancy Set strategic program goals Manage re-commissioning process Measure progress and savings Performance Assurance Re-asses strategic goals Site Visit Utility data review and baselining Interviews with facilities staff Qualitative features review Infrastructure review Vendor bid and selection process Manage renovation and retrofit projects to specified scope, on budget and on schedule Minimize disruption to ongoing operations Preliminary report Prioritize tactical projects needed to achieve strategic goals First cost, incentive and financial analysis review Scope tactical projects, finalize budget and construction schedules Submit for state, local and utility incentives as part of financing package Secure third party investors if required Prepare vendor Selection Process 87

88 Sustainable Systems Implementation Integrated Resource Optimization TM Optimize Building & Site Performance to Maximize Economic Value and Resource Efficiency Integrate building, central plant & site systems (highly interactive but often not properly integrated) Building efficiency + distributed generation (e.g., in-building efficiency & site solar supply) Focus on energy, water, waste and human comfort Optimize Operations & Maintenance BUILDING CENTRAL PLANT SITE SYSTEMS & Co-Gen PV/Solar Water 88

89 Sustainable Systems Implementation Integrated Resource Optimization TM Optimize Building & Site Performance to Maximize Economic Value and Resource Efficiency Integrate building, central plant & site systems (highly interactive but often not properly integrated) Building efficiency + distributed generation (e.g., in-building efficiency & site solar supply) Focus on energy, water, waste and human comfort Optimize Operations & Maintenance BUILDING CENTRAL PLANT SITE SYSTEMS & Co-Gen PV/Solar Water 89

90 Sustainable Systems Implementation Financing Options Traditional Financing Mechanisms Use of Multiple Capital Sources to Leverage Capital Budgets State/Federal tax credits and utility incentives Performance Contracting Enables Self-Supporting Debt Leverage resource (energy, water, etc.) savings and operational savings to service debt Guaranteed maximum costs, open book construction cost reconciliation, guaranteed savings and guaranteed performance Innovative Financing Mechanisms Third-party tax equity financing for distributed generation projects PACE Property Assessed Clean Energy City of County forms a special tax district to issue bonds; property tax assessments are used to finance debt eeppa Energy Efficiency Power Purchase Agreement Modeled around the market value of untapped energy efficiency Commercial application in development phase Sustainable Outsourcing Schools Facility Conference Management Portland / Plant Public Operations Schools I Hood River School District I Opsis Architecture I Gerding Edlen90

91 Sustainable Systems Implementation Maximize the Impact of Available Funds Financial Benefits Leverage capital budget 3 5x Maximize savings / efficiencies across all resources Create more cost savings to support program financing Maximize use of available State and Federal incentives Federal Tax Incentives ARRA 14% Funds 2% Capital Budget 24% State Tax Incentives 17% Self Supporting Debt, Private Party Guarantee 39% Utility Incentive 4% Deliver larger financial returns and resource conservation faster SOURCES OF FUNDS 91

92 Case Study: Portland Community College, Sylvania Campus PROJECT OVERVIEW 757,817 square feet of building stock 12 buildings + central plant on 122 acre campus Current energy consumption: $1,586,000/yr ; $2.09/sf Focus on energy, water and waste PROJECT GOAL First Net Zero Community College Interim 50% energy efficiency goal FRAMEWORK BASED ON PCC s E6 PRINCIPLES Efficient and Effective Use of Project Funds Energy generation Energy Conservation Environmental Stewardship Employment Stimulus Education to Prepare Workers for Green Jobs 92

93 Case Study: Portland Community College, Sylvania Campus E6/NET ZERO ASSESSMENT Outlined measures and costs associated with a full net zero package Also outlined six other packages that can build upon each other for incrementally greater savings Gap analysis relative to LEED certification NET ZERO PACKAGE Building energy and water efficiency improvements 2 MW solar array Closed-loop Geothermal System 1.1 MW Waste-to-Energy Fuel Cell Site Water Measures - Wastewater Treatment and Reuse; Rainwater Harvesting; Stormwater Treatment PHASE I PROJECT Building energy and water efficiency improvements 1.1 MW Generator at Central Plant 70% energy cost savings 57% carbon footprint reduction LEED Certification 93

94 Case Study: Portland Public Schools PROJECT OVERVIEW 9 Schools ~500,000 square feet of roofing 757 kw solar array Current electrical energy consumption: $313,418/yr PROJECT SCOPE CM/GC for re-roofing of 9 schools Solar developer for thin-film solar installation 8-yr. Power Purchase Agreement Energy efficiency upgrades pending stimulus funding PROJECT COST $17.3 million Solar installation added no additional cost to the overall project ENERGY SAVINGS $57,800 Annually 18% Overall Energy Cost Savings District-Wide CO 2 REDUCTION 159,621 lbs/year JOB CREATION 260 Green Jobs 94

95 Sustainable Practices that Work OHSU Center for Health and Healing Sustainable Systems Implementation Oregon School Board Association Conference Post Occupancy Evaluation (October January 2009) 27 28, 2010

96 Questions?