ENVIRONMENTAL MANAGEMENT PLAN

Size: px
Start display at page:

Download "ENVIRONMENTAL MANAGEMENT PLAN"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY TRUNG SON HYDROPOWER COMPANY LIMITED TRUNG SON HYDROPOWER PROJECT ENVIRONMENTAL MANAGEMENT PLAN (Draft) INFRASTRUCTURE CONSTRUCTION OF RESETTLEMENTS TRUNG SON HYDROPOWER PROJECT Prepared by: Thang Long Infrastructure Development JSC. (Infra-Thanglong) Ha Noi, July 2013

2 CONTENT 1. GENERAL INTRODUCTION Background EMP Purposes and Scope 6 2. SUB-PROJECT DESCRIPTION Resettlement sites Architectural Solutions Progress of subproject LEGISLATION BASIS Vietnamese Legislation Safeguard Policies of the World Bank THE MAIN ENVIRONMENTAL IMPACTS THE MITIGATION MEASURES THE EMERGENCY ACTION PLANS THE ENVIRONMENTAL MORNITORING PLAN The monitoring plan in compliance with the mitigation measures The environmental quality monitoring EMP IMPLEMENTATION REPORTING SYSTEM CAPACITY BUILDING ESTIMATED COST FOR EMP IMPLEMENTATION COMMUNITY CONSULTATION AND INFORMATION DISCLOSURE REFERENCES ANNEX Annex 1 Location of disposal sites Annex 2 - Minutes of community consultation Annex 3 TOR for Construction Supervision Consultant (CSC) Annex 4 Environmental Responsibilities of Contractor 66 2

3 LIST of TABLE Table 1: Summary of impacts Table 2: Environmental mitigation measure Table 3 : Chance finding procedure and emergency action plan Table 4: The mornitoring plan Table 5 : The environmental sampling program Table 6: The roles and responsibilities of the stakeholders in the EMP implementation progress Table 7: Requirement of mornitoring report Table 8: Propsed training program on EMP Table 9: Estimated cost for EMP implementation LIST of FIGURE Figure 1 Map of Resettlement Communes... 8 Figure 2 Resettlement site No Figure 3 Some existing photos of the resettlement site No Figure 4 Resettlement site No. 2& Figure 5 Some existing photos of the resettlement sites No. 2 & Figure 6 Plan of Resettlement Site No Figure 7 Some existing photos of the resettlement site No Figure 8 Report and monitoring outline for EMP implementation

4 ABBREVIATIONS DONRE EPC EMP EVN FS RCC TORs UXO WB PMU Department of Natural Resource and Environment Environmental Protection Commitment Environment Management Plan Vietnam Electricity Feasibility Study Roller Compacted Concrete Terms of References Unexploded ordnance the World Bank Project Management Unit 4

5 1. GENERAL INTRODUCTION 1.1 Background Trung Son Hydropower project shall be built on Ma river, in territory of Trung Son commune, Quan Hoa district, Thanh Hoa province with an installed capacity of 260MW and a mean annual electricity of GWh, which is a multi-purpose project providing power generation and flood control benefits. Proposed dam is about 40km from Lao PDR downstream, reservoir tail is about 10Km from the border. A roller compacted concrete (RCC) dam is 84.5 m in height with 513 m crest length. Full supply level is 160m. Total capacity of the reservoir is million m 3. Flood Control storage is 112 million m 3. The reservoir covering an area of Km2 will inundate a mixture of forest and agricultural land. Total estimated cost is US$ 386 million, of which there is an estimation of US$2.9 million for environment managing tasks (except for the tackled requirements which the bidders must follow) and US$35.1 million for compensation, resettlement and livelihood restoration for affected people. EVN has officially applied for a WB loan of USD330 million from IBRD. At present estimation, there is a total of about 10,591 people belonging to 2,327 households to be affected by the project as a whole. About 533 households shall be displaced. Of those, it is estimated that about 1,945 people of 486 households shall be affected by construction of access road, 7,012 people of 1,516 households shall be affected by construction of main dam and dam associated structures, reservoir, and reservoir upstream and downstream impacts. Households to be displaced due to the project impacts shall relocate to 4 planned resettlement sites. Resettlement site No.1 to be built in Trung Son commune, Quan Hoa district, Thanh Hoa province; Resettlement site No.2 - to be built in Muong Ly and Tam Chung communes, Muong Lat district, Thanh Hoa province; Resettlement Site No.3 to be built in Trung Ly commune, Muong Lat district, Thanh Hoa province; Resettlement Site No.4 to be built in Tan Xuan commune, Moc Chau district, Son La province. The Basic Design of such resettlement sites have been developed and approved by the Client. It is expected that after the completion of the detailed design, the construction period of resettlement sites is 12 months. An environmental screening was undertaken in line with the World Bank safeguards policy requirements and it showed that the World Bank s policies on Environmental Assessment 5

6 Procedure/ Regulations (OP/BP 4.01), Natural Habitats (OP/BP 4.04), Involuntary Resettlement (OP/BP 4.12) and Policy on Access to Information are triggered for the subproject. The implementation of the subproject would cause both negative and positive impacts to the subproject area. The negative impacts will occur during pre-construction, construction, and operation. However, these impacts are not significant, temporary, localized, and can be mitigated with available mitigation measures. The positive impacts will occur mostly during operation. Positive impacts will likely be significant and positive due to their long term nature at both the local and regional level. Therefore, the subproject is assessed as B environmental category. The Government s regulation on environmental assessment requires submission of an Environmental Protection Commitment (EPC) for the subproject. Three EPC reports were prepared and submitted to the District People s Committees of Quan Hoa, Muong Lat and Moc Chau in April The EPC report for Resettlement Site No.1 was approved by the People s Committees of Quan Hoa District under Decision No.233/UBND-TNMT dated 27/05/2013. The EPC report for Resettlement Site No.2 & 3 was approved by the People s Committees of Muong Lat District under Decision No.305/UBND-TNMT dated 22/05/2013. Regarding to resettlement site No.4 located in buffer zone of Xuan Nha natural reserved area, environmental and ecological impacts generated from the land-use s purpose changing and resettlement construction will be detailedly analyzed in an independent EIA prepared by another consultant. This report will be submitted to and approved by Appraisal Council of MONRE (as stipulated in Environmental Protection Law of GoV). Consulting firm for this assignment is being selected and the draft of report is intended to be completed by December, In addition to fulfilling the government requirements, an Environmental Management Plan (EMP) that complies with the World Bank OP 4.01 needs to be prepared for this subproject. 1.2 EMP Purposes and Scope Main purposes of EMP: (i) Present the mitigation measures to minimize the potential impacts generated during the phases of a project. (ii) Develop the environmental monitoring programs in order to control and evaluate the efficiency of the mitigation measures; (iii) Estimated cost to implement EMP. 6

7 EMP will also be in compliance with the Environmental Management Framework of the Trung Son Project, which is included in Annex K of the EMP of Trung Son hydropower project. Scope of EMP: This EMP is used to address impacts and mitigation measures to be implemented during the pre-construction, construction, and operation phases of the resettlement sites, including work items as follows: (i) Ground leveling; (ii) House construction; (iii) Construction of public works: Community house, Kindergartens, Primary school and houses for teachers; health care centre; (iv) Construction of internal roads, suspension bridge, ferry; (v) Construction of water supply system; (vi) Construction of electricity system; (vii) Construction of irrigation system; (viii) Land reclamation. 2. SUB-PROJECT DESCRIPTION 2.1 Resettlement sites Resettlement and Cultivation Areas No. 1, 2, 3 & 4 located in Trung Son commune of Quan Hoa district and Trung Ly, Tam Chung and Muong Ly communes of Muong Lat district, Thanh Hoa province and in Tan Xuan commune of Moc Chau district, Son La province (see Figure 1 below). 7

8 Figure 1 Map of Resettlement Communes MA RIVER DAMS 8

9 Resettlement site No. 1: * Geographical coordinate - Latitude: from20 34' 52" to 20 39' 01" North - Longitude: from ' 24" to ' 10" East * Geographical location The resettlement site No.1 is bounded by Son La province to the North and West, by sub-area No.14 and No.03 of Trung Son commune to the South and East. The Resettlement site No. 1 is constructed for settlement of 235 relocated households (including 27 spared land blocks for further demand up to 2014). As planned, the ground leveling will be implemented for only 208 households in 5 resettlement points as follows: - Co Pung village: 48 households; - Pa Pua village: 29 households; - Pom Chon village: 55 households; - Keo Dam village: 44 households; - To Xuoc village: 32 households; Co Pung resettlement point: With an area of 5.98ha, this point is about 1km from the existing Ta Ban village to the Northwest. Investment construction items in Co Pung resettlement point include 48 family houses, 01 community house of 60m 2, 01 kindergarten with 02 classrooms, 01 primary school with 03 classrooms, 02 single rooms for teachers and associated infrastructure system of internal road, water supply and electricity. Pa Pua resettlement point: With an area of 3.04ha, this point is about 0.5km from the existing Ta Ban village to the Northwest. Investment construction items in Pa Pua resettlement point includes 29 family houses, 01 community house of 60m 2, and other associated infrastructures system. Requirement for social service is provided by new one constructed in Co Pung resettlement point. Keo Dam resettlement point: With an area of 4.73ha, this point is about 01km from the existing Ta Ban village to the Southwest. Investment construction items in Keo Dam resettlement point include 44 family houses, 01 community house of 60m 2, 01 kindergarten with 02 classrooms, 01 primary school with 03 classrooms, 03 single rooms for teachers, and associated infrastructure system of internal road, water supply and electricity. 9

10 Pom Chon resettlement point: With an area of 7.19ha, this point is located on the hill top, surrounded by Quanh stream and Ma river, about 1km from Pom Chon resettlement point to the South. Investment construction items in Pom Chon resettlement point includes 55 houses, 01 community house of 60m 2 and associated infrastructure system. Social services is provided by new one system constructed in Keo Dam resettlement point. To Xuoc resettlement site: With an area of 3.28ha, this point is about 1km from existing Xuoc village to the Southwest. To Xuoc resettlement point includes 32 houses, 01 community house of 60m 2, 01 kindergarten with 01 classroom, 01 primary school with 02 classrooms, and infrastructure system of internal road, water supply and electricity. All the resettlement points are connected to the West Road of Thanh Hoa Province- a provincial road of western districts, which is under construction and completed by 2014 (see the details in Figure 2). 10

11 Figure 2 Location of Resettlement site No. 1 Resettlement points West Thanh Hoa Road Quanh Stream Ma River 11

12 Figure 3 Some existing photos of the resettlement site No. 1 The existing condition of land use in the resettlement sites Bamboo, cassava in the resettlement sites The existing road with high slope The existing section of West Road not constructed Ta Ban Stream Quanh Stream 12

13 Resettlement site No. 2: * Geographical coordinate - Latitude: 20 32' 14" to 20 34' 32" North - Longitude: ' 39" to ' 13" East * Geographical location The resettlement site No.2 is bounded by Son La province to the North, by Ma river to the South and on the East and the West by Muong Ly commune The Resettlement site No. 2 is planned for 112 households (including 12 standby land blocks for development by As planned, the ground leveling will be implemented for 100 households in 03 resettlement points as follows: - Nang village: 54 households; - Tai Chanh village: 35 households; - Lat village: 11 households; Nang village resettlement point: With an area of 6.23ha, this point is about 1.5km from the existing Nang village to the higher position. Nang village resettlement point includes 54 houses, 01 comunity house of 100m 2, 01 kindergarten with 02 classrooms, 01 primary school with 8 classrooms, 04 rooms for teachers, 01 health care centre, water supply and electricity system. Tai Chanh village resettlement point: With an area of 3.69ha, this point is about 200m from the former Tai Chanh village. Tai Chanh village resettlement point includes 35 houses, 01 comunity house of 60m 2, 01 kindergarten with 02 classrooms, 01 primary school with 03 classrooms, 02 rooms for teachers, water supply and electricity system. Lat village resettlement point: With an area of 1.43ha, this point is about 200m from the former Lat village. Lat village resettlement point includes 11 houses, 01 new health care centre, water supply and electricity system. 13

14 Resettlement site No. 3: * Geographical coordinate - Latitude: 20 31' 07" to 20 32' 27" North - Longitude: ' 54" to ' 13" East * Geographical location The resettlement site No.3 is bounded by Sub-are No. 58 and 55 of Trung Ly commune to the South and the East and on the West by sub-area No. 66 of Trung Ly commune, Muong Lat distrist. The Resettlement site No. 3 is planned for 41 households (including 6 standby land blocks for development by As planned, the ground leveling will be implemented for 35 households in 02 resettlement points as follows: - Lin village: 19 households; - To Chieng village: 16 households; Lin village resettlement point: With an area of 2.9ha, this point is about 1.5km from the existing Lin village. Lin village resettlement point includes 21 houses, 01 community house of 60m 2, 01 kindergarten with 02 classrooms, 01 primary school with 03 classrooms, 02 rooms for teachers and water supply and electricity system,. To Chieng village resettlement site: With an area of 1.44ha, this point is about 1km from the existing To Chieng village. To Chieng resettlement point includes 19 houses, and other social infrastructures to be shared with Lin resettlement point. 14

15 Figure 4 Resettlement site No. 2&3 Resettlement sites West Thanh Hoa Road Ma river 15

16 Figure 5 Some existing photos of the resettlement sites No. 2 &3 The existing condition of land use in the resettlement sites Bamboo, cassava in the resettlement sites Some locations with low density of vegetation cover ( resettlement site No.2) Existing school in Ban Nang Village Medical Station- Ban Nang village Existing market of Ban Nang village 16

17 Resettlement site No.4: * Geographical coordinate: - Latitude: 20 39' 0" North - Longitude: ' 14" East * Geographical location The resettlement site No.4 is bounded to the North by Xuan Nha commune, Moc Chau distrist, Son La province and by Trung Ly commune, Muong Lat distrist, Thanh Hoa province to the South, by Trung Son commune to the East and to the West by Chieng Xuan commune, Moc Chau distrist, Son La province. The Resettlement site No. 4 is constructed for settlement of 186 relocated households (including 16 spared land blocks for futher demand up to 2014), As planned, the ground leveling will be implemented for 170 households at 03 resettlement points as follows: - Tham Ton: 50 households; - Pom Hien - Suoi Non 1: 68 households; - Pom Hien - Suoi Non 2: 68 households; Tham Ton resettlement point: With an area of 9ha, this resettlement point is located on the right side of Tan Xuan road connecting Xuan Nha commune to Tan Xuan commune. Invesment construction items in Tham Ton resettlement point include 50 family houses, 01 community house of 100m2, 01 kindergarten with 02 classrooms, 01 primary school with 03 classrooms, 02 single rooms for teachers and associated water supply and electricity and internal road system. Pom Hien - Suoi Non #1 resettlement point: With an area of 18.9ha, this point is located in Dong Ta Lao village. Investment construction items in Pom Hien - Suoi Non #1 resettlement point include 68 family houses, 01 community house of 60m 2, 01 kindergarten with 02 classrooms, 01 primary school with 03 classrooms, 02 single rooms for teachers, and assoicated water supply and electricity and internal road system. Pom Hien - Suoi Non #2 resettlement point: With an area of 13.5ha, this point is located in Tay Ta Lao village. Investment construction items in Pom Hien - Suoi Non #2 resettlement point include 68 family houses, 01 community house of 60m2, 01 kindergarten with 02 classrooms, 01 primary school with 03 lassrooms, 04 single rooms for teachers and associated water supply and electricity and internal road system. 17

18 Figure 6 Plan of Resettlement Site No. Resettlement poits The planned reservoir bottom 18

19 4 19

20 Figure 7 Some photos on existing condition of the resettlement site No. 4 The existing Tan Xuan road Existing condition of Tham Ton resettlement site Existing vegetation coverage in defined position of Pom Hiến Non #2 Stream The existing land use in Pom Hien- Non #1 Stream resettlement sites The existing roads Ta Lao Stream 20

21 2.2 Architectural Solutions Residential land: the land blocks are arranged along the internal road. Each land block contains an area of 700m2, including m 2 of ground leveled for house construction and remains for garden land. Totally, there are 342 land blocks for relocated households allocated to resettlement sites No. 01, 02 and 03) and 202 land blocks allocated to resettlement site No. 04. Additionally, 61 spared land blocks are also prepared for future demands up to Living houses: Stilt house and one-floor house modes are designed availably to selection of relocated people. House is separated into two parts: (i) The main space with living room and bedroom; (ii) The auxiliary space is arranged to one side of house with one separated entrance. The total area of house alternatively is 25m² or 45m² or 65 m² deepened on number of member of relocated household. Community house: The selected design is a large stilt house with an auxiliary room under the main floor. Kindergartens: One shared space is arranged to two ages of child. Classroom contains (i) A room for kid activities, one dining room and one bedroom; (ii) The auxiliary space with corridors and one multi-purpose spare room and toilet and kitchen. 21

22 Primary classrooms: An one-floor classroom is designed with three separated rooms and associated windows and doors (see picture). Single room for teachers: One-foor mode is designed close to schools. Each house contains separated spaces included living room, bed room, kitchen and toilet. Health care centre: Functional areas is designed including (i) Emergency room; (ii) surgery room; (iii) Patient room; (iv) Warehouse; (v) Management room. Internal road, suspension bridge and ferry: The internal road system connected the resettlement points to the external road is designed as the Grade-B Standards for rural road with the total length of 7.69 km for resettlement sites No. 1, 2 &3 and km for resettlement site No. 4. Suspension bridge is designed with the length of 111m and width of 2.5m and access road in accordance with the standard for Grade B. Ferry is designed with the width of 3.5m and working water level varied from 150m to 160m. These two construction items is only prepared for resettlement point Suoi Non #1 (Resettlement site No 4). Water supply system: In each resettlement points, the water from targeted streams is conveyed to the centralized filter tank with capacity of 17m 3 /h. Treated water is delivered by D34-D42 steel pipes along internal road's sides to 2m 3 water tank of each household by PVC D27 plastic pipes. 22

23 2.3 Progress of subproject Subproject is divided to 08 packages with budgets and progress below: No. Code of Name of package Budget Bidding Constructi package (million VNĐ) time on time W-RE-01 Construction of resettlement site No.1 Quan Hoa district, Thanh Hoa province (ground leveling, internal road, public house and living house) 55,704 4th Quarter months 2 W-RE-02 Construction of resettlement site No.2 & 3 Muong Lat district, Thanh Hoa province (ground leveling, internal road, public house and living house) 36,577 1st Quarter months 3 W-RE-20 Construction of resettlement site No.4 Moc Chau district, Son La province (ground leveling, internal road, public house and living house) 102,823 3rd Quarter months 4 W-RE-04 Construction of water supply system for resettlement sites No.1, 2 & 3 Thanh Hoa 33,009 4th Quarter months

24 No. Code of Name of package Budget Bidding Constructi package (million VNĐ) time on time province 5 W-RE-21 Construction of water supply system for resettlement site No.4 Son La province 17,639 3rd Quarter months 6 W-RE-03 Construction of 35/0.4KV power line and substation and 0.4KV power line 38,066 3rd Quarter months 7 W-RE-05 Reclamation for agricultural cultivation in Thanh Hoa province 3,263 1st Quarter months 8 W-RE-06 Reclamation for agricultural cultivation in Son La province 1,430 3rd Quarter months 24

25 3. LEGISLATION BASIS The EMP is prepared in compliance with the environmental regulation of GoV and the environmental safeguard policy of the WB. 3.1 Vietnamese Legislation o The Law on Environmental Protection approved by the National Assembly of the Socialist Republic of Vietnam dated 29th November, 2005; o Decree No.29/2011/ND-CP dated 18th April, 2011 of the Government on strategic environmental assessment, environmental impact assessment and environmental protection commitment; o Circular No.26/2011/TT-BTNMT dated 18th July, 2011 of the Ministry of Natural Resources and Environment, detailing a number of articles of the Government's Decree No. 29/2011/ND-CP dated 18th April, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment; o Decree No. 149/2004/NĐ-CP dated 27th July, 2004 of the Government on granting license for water source utilization and operation, and use of water sources, discharge of water into water sources; o Decision No. 233/QĐ-TTg dated 18th October 2006 by Prime Minister approved the National Program for the Protection of Labor, labor safety, labor hygiene in Table 2.1: Vietnamese regulations on environmental NO NAME OF REGULATION Code 1 Land quality National technical regulation on the allowable limits of heavy metals in the soils 2 Land quality National technical regulation on the pesticide residues in the soils QCVN 03:2008 QCVN 15: National technical regulation on domestic water quality QCVN 14: Water quality - National technical regulation on surface water quality QCVN 08: Water quality - National technical regulation on underground QCVN 09:2008 water quality 6 National technical regulation on Industrial Wastewater QCVN 41: Acoustic National technical regulation on noise QCVN 26: National technical regulation on Vibration QCVN 27:

26 NO NAME OF REGULATION Code 9 Air quality National technical regulation on ambient air quality 10 Air quality - National technical regulation on hazardous substances in ambient air 11 Air quality - National Technical Regulation on Industrial Emission of Inorganic Substances and Dusts 12 Air quality - National Technical Regulation on Industrial Emission of Organic Substances QCVN 05:2009 QCVN 06:2009 QCVN 19:2009 QCVN 20: National technical regulation on the emission of health care QCVN 02:2008 solid waste incinerators 14 Radiation safety-basic signal related to ionization radiation TCVN 7468: Requirement to set up radiation immunity areas TCVN 7515: Guidance on radiation immunity areas TCVN 7516: Definition of status of radiation TCVN 7517: Safeguard Policies of the World Bank The Bank Operation Policy (OP) and Bank Procedure (BP): Environmental Assessment Procedure/ Regulations (OP/BP 4.01) Natural Habitats (OP/BP 4.04) Involuntary Resettlement (OP/BP 4.12) Policy on Access to Information. 26

27 4. THE MAIN ENVIRONMENTAL IMPACTS An environmental impact assessment is an assessment of the possible positive or negative impact that a proposed project may have on the environment, together consisting of the environmental, social and economic aspects. To identify and evaluate the impacts of any one project, there are various methods commonly used for environmental impact assessment such as checklist method; matrix method; and cost-benefit analysis method. In this part of report, the checklist method is applied which is widely used and generally sufficient for small-scale projects having Category B classification. The construction of the subproject will mainly caused impacts on land acquisition, increased levels of dust, air pollution, and wastes. However, these impacts are not significant, temporary and localized and can reduce by mitigation measures. Table 1: Summary of impacts No. Impacts Manigtude Duration Description of impact Pre-construction stage Impacts assessment 1 Land acquisition Medium Permanent As master plan, total area of resettlement sites is 4,357ha (see table). Of which, area for construction of infrastructure and houses is ha (1.86%), the land reclamation for agricultural cultivation is ha (3.21%). Existing forest area assigned to household management is 4, ha (94.93%). Medium and mitigable Resettlement site Affected area (ha) Site No Site No.2& Site No.4 2,739 Total 4,357 The affected vegetation is mainly planted bamboos, distributed in Co Pung, Pa Pua, Pom Chon, Keo 27

28 No. Impacts Manigtude Duration Description of impact Dam points (Resettlement No. 1), Nang village point (site No.2), Tai Chanh, Lin villages (site No.3) and Suoi Non (site No.4). Other areas are predominantly uncultivated land with shrubs and grasses. Impacts assessment 2 Impact on Subproject affected household Medium Permanent The resettlement sites are constructed in agricultural and planted forest land. There is not any household needs to be relocated and no resettlement is required. Number of affected households is 357. Compensation plan will be prepared and implemented by the project owner. Resettlement site Numbers of affected households Site No Site No.2&3 123 Site No Total 357 Medium 3 Accident related UXO to None None Mine clearance was completed at all resettlement sites by Company No36 - Ministry of Defence (through contract No 03/2013/HĐKT-TĐTS and No 04/2013/HĐKT-TĐTS); None 4 Impact on historical and cultural properties Construction stage 5 Loss of vegetation None None The resettlement sites are selected to avoid crossing any historical and cultural properties such as pagodas, churches. No cultural and historical site is affected by the sub-project. During soil excavation, if there will be found any underground historical or cultural valuable object, the contractor shall follow Chance Find Procedures Medium Permanent The construction activities potentially created impact on vegetation coverage include site clearance for agricultural cultivation (about 140 ha) and ground leveling for resettlement construction (81 ha). 28 None Medium and mitigable

29 No. Impacts Manigtude Duration Description of impact coverage Residential and infrastructural Resettlement site area (ha) Land Reclamation Area (ha) Impacts assessment 6 Threats to flora and fauna Site Site 2& Site Total Affected vegetation is mainly planted bamboos and cassava, which have economic value rather than ecological one. Normally, life cycle of bamboo from growing to cultivated time is about five years. The newly developed areas are also used for bamboo planting and/or agricultural cultivation that helps to compensate the loss of green coverage in each project area. minor temporary All resettlements sites are located in uncultivated land and/or planted forest (mainly bamboo) with low bio-diversity but high vegetation coverage. Through community survey, there is only some popular animals such as bird, rodent and reptiles that can be found in these areas. There is not any sign of endangered species. Moreover, daily activities of local people such as transportation, agricultural cultivation, bamboo planting and even hunting prohibit the widespread of these animals. However, the construction activities such as site clearance, ground leveling and noise from construction equipment and vehicles and the operation of worker s camps can generate impacts to the local habitats. The impact mainly happens in the beginning time of construction (about 3 months from commencement) and needs to have suitable mitigation measures. Minor 29

30 No. Impacts Manigtude Duration Description of impact 7 Dust Medium temporary Dust mainly sourced from (i) construction site and (ii) routes of transporting construction materials (cement, sand, stone, steel, brick, etc.) and excavated soil and construction waste to disposal sites. Most of the resettlement sites are separated to the existing residential areas with distance varied from 1km to 3km. The existing green coverage is quite good. Dust mainly generates during the ground leveling and road construction (about 3 months) and significantly reduces during house construction. Impacts assessment medium and mitigable For the transportation routes, based on assessment of construction material demand, the number of truck mobilized is estimated as follow: Resettlement site Material waste (basic design) Number of truck Time Site No.1 9,900 tons 2-10 trucks/ day 12 months Site No.2 6,000 tons 2-6 trucks/ day 12 months Site No.3 7,800 tons 2-8 trucks/ day 12 months Site No.4 10,000 tons 2-10 trucks/ day 12 months With just around ten vehicle/truck predominantly operated in the first 3 months of construction stage, the impact is evaluated as minor, temporary and mitigated by contractor s measures. However, 03 positions including Nang village and Tai Chanh Junior School (Site No.2) and Ta Lao village (Site No.4) located on road sides are directly exposed to dust and needs to have effective mitigation measures. There is no new quarry and borrow pit required to be opened. All construction material will be provided by local suppliers and/or from existing quarries/borrow pits that newly opened for the 30

31 No. Impacts Manigtude Duration Description of impact Trung Son main project. All these quarries/borrow pits have to be licensed and strictly managed by local authorities. Impacts assessment 8 Noise and Vibration 9 Erosion/lan dslide Medium Temporary Noise and vibration are mainly generated from the ground leveling, road construction and material transportation. All resettlement sites are quite isolated to existing residential areas. With only a few vehicles operated daily, the impact is evaluated as minor, temporary and mitigated by contractor s measures. However, there are 02 sensitive points located along the transportation route including Tai Chanh Junior School (Site No.2) and Ta Lao Junior School (Site No.4). Suitable mitigation measures are required to be applied. Minor Temporary Construction activities such as ground leveling on hill s slope can create risk of landslide and/or erosion, especially in rainy season; There are some key factors related to landslide/erosion assessment, included: Geological Characteristics: medium and mitigable minor Resettlement No.1 located on edq layer with thickness varied from 0,5 to 3m strongly weathered soil thickness >3m strongly weathered rock. Slope is greater than 25% and groundwater is quite limited and stable geology. Resettlement site No.2&3 located in granite stone and hard granite biotit. The slope is higher than 25% and there is no sign of shallow groundwater presented. Resettlement site No.4 located on the silt layer of high organic matter with thickness varied from 0.3 to 0.5m and followed by layer of clay and limestone which are highly resistant to water penetration. 31

32 No. Impacts Manigtude Duration Description of impact Impacts assessment Climatic Characteristics The rainy season usually begins from May to September. The rainfall is uneven with monthly average rainfall is around 133mm; Regarding to the resettlement site No.4, heavy rain occur from April to September with monthly average rainfall is a little higher than other areas (around 200mm/month); 10 Surface water pollution As natural condition of stable geological foundation and high vegetation coverage as well as medium rainfall associated with the suitable design as GoV standard, impact related to landslide/erosion is minor and mitigable. Medium Temporary Pollution from construction sites Run-off water from construction sites and/or waste water from worker camps possibly create impact to the surrounding water sources (see in table below). The worker s camps at one resettlement points with around 30 people will be located close to construction site with minimum distance to the water sources of 100m. With such a distance, solid waste and waste water still have chance to entering into water bodies and have to be managed sufficiently. Medium and mitigable Location Stream Name (width) Distance to the construction site Xuoc Village (Site No. 1) Nang Village (Site No.2) Unknown creek (<1m) Run through the construction site Nang Stream (6-8m) About 200m 32

33 No. Impacts Manigtude Duration Description of impact Ta Lao Village Tà Lào Stream (6-8m) (Site No.4) Creek at Tà Lào Village(<1m) About 100m About 150m Impacts assessment 11 Solid waste generated Regarding to construction of resettlement site No.4, the suspension bridge and ferry are constructed over the Quanh Stream with the width varied from 15 to 20m). This water of stream is quite abundant and at good quality. The bridge abatement is build on land and there is no construction activities conducted in the stream. The scope of work for ferry construction is also small. The impact on water quality is evaluated as minor. Pollution from material transportation routes Most of the transportation routes such as West Road and Co Luong road located far from all water sources. There is only one internal road of Nang village (resettlement site No.2) crossed Nang stream at the connection point of Nang and Tai Chanh Village with no bridge and dam. Existing stream has a high flow (with width of 6m) and good water quality and mainly used for irrigation purpose. As estimated, about 02 to 05 vehicles are daily operated during construction. Chance for material from transported vehicles dropping into stream is quite limited but still required to be managed properly. Medium Temporary The estimate of excavated soil volume from ground leveling is presented as table below: Location The estimated excavated soil (m3) Resettlement Site No.1 34,876 Resettlement Site No.2 73,000 Resettlement Site No.3 18,438 Medium and mitigable 33

34 No. Impacts Manigtude Duration Description of impact Resettlement Site No.4 68,600 Impacts assessment Total 194,914 Design consultant, PMU and local authority have worked together to define suitable areas which have average transportation distance of less than 1km and sufficient storing capacity. These disposal sites can be used for agricultural cultivation after project completed. Some high slope position are built stone embankment with a height of 1-2m to avoid erosion/landslide in rainy season. Consequently, list below presents the selected sites: For resettlement site No.1: 03 disposal sites located at Co Pung, Pa Pua and Pom Chon resettlement point, along existing West Road. For resettlement site No.2: 01 disposal site located between Nang and Tai Chanh Village For resettlement site No.3: 01 disposal site located between To Chieng and Lin Village and 01 disposal site located at Lat village. For resettlement site No.4: 06 disposal sites are located along the existing road 12 Domestic waste Medium Temporary The subproject is implemented in 12 months. The peak construction time lasts 8-9 months, and the remaining time is reserved for ground leveling. It is expected to have 80 workers involved in the construction of each resettlement site. These workers will establish their camps on site. Workers can be locally selected, so each camp will have about workers. In resettlement sites, auxiliary facilities such as sanitary bathrooms and toilets will be built for workers. 34 Medium and mitigable

35 No. Impacts Manigtude Duration Description of impact Impacts assessment 13 Impact on current infrastructu re system All waste discharged from camps is mainly domestic solid waste which can cause environmental pollution. However, the discharged waste is mainly packing, leftover food, etc. with a small amount (each camp will generate 40kg waste per day). Minor Temporary The transportation of material to construction site and excavated soil to disposal site possibly create impact to the existing technical infrastructure system of local people such as local road, electric poles, water conveyed pipes of households. Minor Water pipes: the construction activities will not affect to existing water sources or conveying system of local residents. Electricity: Most of construction of resettlement areas are isolated to the existing residential areas. However, there are some electric poles located right on the roadside that can be impated during material transportation. Road: New internal road will be constructed for resettlement points and then connected to main roads such as West Thanh Hoa and Tan Xuan Roads (linked Tan Nha to Tan Xuan communes). Currently, these main road is already asphalted with 6m in wide (Tan Xuan road) or being constructed (West Thanh Hoa). The impact on road damage during transportation is minor. 14 Conflict between constructio n worker and local people Minor Temporary The presence of immigrated workers possibly creates several social issues such as social vices (like prostitution, gambling, Drugs etc.) and unhygienic situation around the worker's camp as well as cultural conflict with local residents. Most of ethnic people at the resettlement sites are Thai, Muong, H Mong. They have the own cultural habit and customs, but not closed to surrounding areas. Many construction activities are being implemented in project areas. The immigrated workers are supposed to be easily integrated with local community. For manual work, the contractor can hire 35 Minor

36 No. Impacts Manigtude Duration Description of impact the local labor (about 30-40% of construction labor). This impact is minor and temporary. Impacts assessment 15 Health and safety Operation stage Medium Temporary Labor accidents might happen during construction commencement stage if the safety issues are not well considered. The leading safety hazards on site are falls from height, motor vehicle crashes, excavation accidents, electrocution, machines, and being struck by falling objects. Some of the main health hazards on site are asbestos, solvents, noise, and manual handling activities. Construction work in these areas is not allowed under bad weather condition such as strong wind, mist, or nighttime, etc. Traffic accident can be happened when construction trucks/vehicle run through residential areas and or crowed places like school, market. Medium and mitigable 16 Impact to habits and customs of local people 17 Dust, noise and traffic accident Minor Temporary According to the public consultation, most of residents agreed with the design modes of resettlement sites. Houses in new resettlement sites are designed with the same architectural structure as the existing one. Additionally, with much better construction material, the new houses are expected to withstand climate disasters such as high wind, heavy rain and storm. Along the road, the similar house design contribute to create beautiful landscape of area. Besides, the sub-project will also provide sufficient infrastructures such as electricity, water supply and hygienic toilets and each resettlement point (30-50 households) will have a community house for public activities. It is expected that it will takes short-time for relocated people being familiar with new location. Minor Permanent After project completed, the internal road will only be used by local people (mostly motorbike or walking). All roads are concreted with the width of 2.5 to 3m and warning signs arranged around sensitive points such as kindergarten, school, health care center in order to minimize risk of traffic accidents. 36 Minor Minor

37 No. Impacts Manigtude Duration Description of impact Impacts assessment Trade activities in resettlement area are still limited with only 01 or 02 trucks weekly come to procure agricultural product and/or bamboo. Impact of dust and noise is not considerable. The maximum number of household in one resettlement point is 68. As practice, each household will generate 2 kg solid waste per day. Annually, one resettlement site can generate around 50 ton of domestic solid waste. Different to domestic waste from urban areas, waste in remote area is rich of 18 Solid waste and waste water. Minor Permanent biodegradable matter that can be buried and/or used as natural fertilizer. As current customs of ethnic group, solid waste are normally collected in digged hole in their own garden. In short-term, this solution is acceptable. In future, centralized dumping site for each one resettlement point should be considered for better management of domestic waste. Minor Waste water from household will be collected to small canals and to main drains along the road. Sewage from toilet will be directly penetrated into soil. With very low density of population, this method is environmentally acceptable and widely applied to almost all remote/mountainous areas. 19 Health and Environme ntal Sanitation Positive Permanent The positive change of environmental and living conditions of local people is presented in table below: Infrastructure Before the project After the project Water supply - Simple pipe for collecting water directly from stream/creek to households - The water storage is not hygienic. - Each household has its own water tank. - The centralized water storage with filtering system for treatment. Positive Electricity - Small scale hydrogenerator for each - Power is provided by national electricity grid. 37

38 No. Impacts Manigtude Duration Description of impact household. - Unsafety and low capacity of electricity. - Safety and stable power system. Impacts assessment Drainage - Natural drainage. - Concreted canal/culvert system. Toilet - Temporary, unsanitary. - Standard toilet 20 Conflict in water use Traffic road - Mainly pathway - All concreted roads with traffic signs. None None Irrigation water is required for new terraced paddy fields. Suitable water sources have been defined through site survey and public consultation. Water from existing streams is collected and conveyed to the field by pipe system. With very high vegetation cover on large catchment area, water is quite abundant and sufficient for both irrigation and domestic uses purposes. As a result, there is no conflict in water use. None 38

39 5. THE MITIGATION MEASURES Table 2: Environmental mitigation measure No. Impacts Mitigation Measures Implementation Unit Pre-construction stage 1 Land acquisition Implement measures defined in the Subproject Resettlement Plan PMU Construction stage 2 Loss vegetation cover 3 Threats to flora and fauna + All vegetation outside the limit of earthworks to be clearly marked and defined on-site by temporary fencing or marking + Site clearance in a forested area is subject to permission from Department of Agriculture and Rural Development. + The application of chemicals for vegetation clearing is not permitted. + Restore the vegetation in the reclaimed areas. + Prohibition of hunting and fishing. + Burning for vegetation clearing is not permitted + No area of potential importance as an ecological resource should be disturbed unless there is prior authorization from CSC, who should consult with PMUs, and the relevant local authorities. This could include areas of breeding or feeding of birds or animals, fish spawning areas, or any area that is protected as a green space. Contractor Contractor 39

40 No. Impacts Mitigation Measures Implementation Unit 4 Dust + Spray water on the road surface in case of high dust concentration or when complaint of residents raised. Contractor + At the project location route through residential areas (Nang village and Tai Chanh Junior School (Site No.2) and Ta Lao village (Site No.4), it is required to have sprinkler regularly used before construction vehicle passed. + Construction vehicles shall comply with speed and carried load limits + Material loads shall be suitably covered during transportation + Develop the suitable construction diagram and measures for reducing the construction time and plan clearance for material gathering. 5 Air pollution + All vehicles must comply with Vietnamese regulations controlling allowable emission limits of exhaust gases. Contractor + Vehicles in Vietnam must undergo a regular emissions testing and get certified named: Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT. + There should be no burning of waste or construction materials or cleared vegetation on site. + Cement processing plants should be located far from residential areas. 6 Noise and vibration + Ensure the maintenance periodically of construction vehicles and equipment. Contractor + Avoid noises of construction equipment/vehicle during nonworking time. + Construction vehicles shall comply with speed and carried load limits + Community announcement about the details of construction plan. 40

41 No. Impacts Mitigation Measures Implementation Unit 7 Erosion/landslide + Abate the soil erosion and maintain the soil slope during excavation time. Contractor + Avoid clearing activities during the rainy season. + Installation waste-trapping screens in drainage ditches; + Storm building drains for the construction to avoid local inundation of water in heavy rain. + Dredging sediment and deposit. 8 Water pollution + The Contractor must be responsible for compliance with the relevant Vietnamese legislation relevant to wastewater discharges into watercourses. Contractor + Installation of the private toilets for worker camps including mobile and standard toilets. + Temporary drainage system for water drainage, bin for waste collection.. + Waste water collection system with filter- tank. + Waste water storage for workers. + Prohibition of discharging waste into the residential and construction areas. + Regularly collect solid waste into the prescribed waste areas. + Before construction, all necessary wastewater disposal permits/licenses and/or wastewater disposal contract have been obtained. + At completion of construction works, wastewater collection tanks and septic tanks shall be safely disposed or effectively sealed off. 9 Solid waste + Frequently tidy up dropped waste from the construction site to the disposal sites Contractor 41

42 No. generated Impacts Mitigation Measures Implementation Unit + Procurement of the waste collection equipment at the camps 10 Traffic management 11 Impact on public social infrastructure + With the hazardous waste, establish the collection system to store temporarily around the construction sites, after that transport to the local hazardous waste treatment suppliers. + Build the hygienic toilets at each worker 's camp.. + Negotiate with residents and local authority to arrange the comfortable accommodation for workers. + Regular collection and transportations of waste, garbage to the prescribed location. + Reuse non hazardous waste such as debris of cut trees, brick, rock etc. + Prior to construction, carry out consultations meeting with local government and community + Installation of lighting at night must be done if this is necessary to ensure safe traffic circulation. + Place signs around the construction areas to facilitate traffic movement, provide directions to various components of the works, and provide safety advice and warning. + Employing safe traffic control measures, including road/rivers/canal signs and flag persons to warn of dangerous conditions (if necessary). + Avoid material transportation for construction during rush hour. + Signpost shall be installed appropriately in roads where necessary (especially 02 positions including Tai Chanh Junior School (Site No.2) and Ta Lao Junior School (Site No.4) located along the transportation route are more sensitive) + Awareness of machinery operator and supervise construction practice + Supervise excavation/leveling works to ensure that waste soil is transported to designated areas 42 Contractor Contractor

43 No. Impacts Mitigation Measures Implementation Unit 12 Cultural/Social conflicts, increasing risk of HIV/AIDs 13 Worker and public Safety + Compensate for any damage of house, road and other social service system + Disclose construction plan and methods + Introduce environmental code of practice developed in the main project to regulate worker s behavior. + Encourage contractor to hire local labor when possible + Extend the current communication campaigns on HIV/AIDs under the main project s health program to resettlement construction workers. + Develop, apply and monitor the implementation of workplace safety regulations including safety measures. + Provide protective equipment for workers and enforce the usage + Restrict unauthorized access to construction sites + Design bridges to ensure safe access at both ends + Ensure connection between the main road and roadside facilities to avoid accidents for vehicles, particularly bicycles and motorbikes + Install and maintain lighting for use at night and signboards when carrying out construction works on waterway + Set and implement limits on height of construction material loads on vehicles such as bricks, pipes + Worker allocation to site transportation or during loading/unloading of bulky materials and equipment + The contractor shall provide safety measures as installation of fences, barriers warning signs, lighting system against traffic accidents as well as other risk to people and sensitive areas 43 Contractor Contractor Contractor

44 No. Impacts Mitigation Measures Implementation Unit 14 Communication with local communities about Subproject environmental issues 15 Workforce, camp and site management + Blasting activities should be implemented within the designated time and local people shall be informed prior to blasting. + Storage, transport, use and destroy of industrial explosive materials shall be strictly follow the guidelines in Decree No 39/2009/NĐ dated on 23 April 2009 of the Govemment on Industrial Exploisive Materials and the National Technical Regulation QCVN 02:2008/BCT on guidelines in storage, transport, use and destroy of industrial explosive materials + Maintain open communications with the local government and concerned communities; + Disseminate project information to affected parties (for example local authority, enterprises and affected households, etc) through community meetings before construction commencement. + Provide a community relations contact from whom interested parties can receive information on site activities, project status and project implementation results. + Provide technical documents and drawings to PC s community, especially a sketch of the construction area and the EMP of the construction site. + Notification boards shall be erected at all construction sites providing information about the project, as well as contact information about the site managers, environmental staff, health and safety staff, telephone numbers and other contact information so that any affected people can have the channel to voice their concerns and suggestions. + Workers camps will be located at least 100 m away from schools and health care centers and not be located on steep slopes. The workforce shall be provided with safe, suitable and comfortable accommodations and safe portable water. They have to be maintained in clean and sanitary conditions. + Site offices, worker camps, mixing stations, and workshops shall be located NOT within 100m from any 44 Contractor Contractor

45 No. Impacts Mitigation Measures Implementation Unit water courses, 500 meters of existing residential area. + Engineers and workers shall register their temporary residence with the local authority. + Contractor should sign committeemen with local authorities on keeping of security and social safety on subproject s areas. + Allocate officer to be the Contractor s Workplace Safety and Environment Officer responsible for environmental and safety issues including training for workers. + Septic tank toilets must be provided at all construction camp areas where there will be concentration of labor. + First aid boxes shall be provided in each construction camp site. Operation stage 16 Traffic accident - Maintain the traffic sign board system Local authority 17 Solid waste and waste water pollution - Conduct IEC campaign to local residents on traffic regulation + Set the collection bin for separating organic waste at each household + Control outlet of drain along road to avoid directly discharging into water bodies and/or cultivation areas. + Conduct IEC campaign to raise awareness and practice of local residents on hygienic behaviors. + Operation and maintenance of drainage system, water supply system as well as toilet. Local authority 18 Water use's conflict + Define the protected area of water sources Local authority 45

46 No. Impacts Mitigation Measures Implementation Unit management + Animal breeding, chemical pouring around water sources is not permitted 46

47 6. THE EMERGENCY ACTION PLANS Table 3 : Chance finding procedure and emergency action plan TT Risks Activities Responsibilities 1 Discover antiques during excavation time - The contractor needs to protect the site and report to the CSC/PMU and local museum/culture management institution. - Bring them to the museum/culture management institution. Determine to continue the construction work or stop for investigation. The director of Cultural and Information Department and the director of the provincial museum have responsibility for the subsequent processing steps of the founded antiques in Article 21 of Decree No. 92/2002, guiding the implementation of the Law on Cultural Heritage Contactor CSC Contractor Contractor Relevant institutions 2 Discover the place of historic interest during the excavation time 3 The residents complain about the environmental problems from the construction activities Protect the scene and report to the local authority. Determine who have responsibility, where and how to deal with and suggest the next action. Handle the problems immediately if possible Record Discuss with the project owner/ local authority where the problem occurred 4 Accident at work Perform first aid if possible and pick the victim up to the nearest hospital if necessary Protect the scene and make a sign Take the minutes of incident. Contractor Relevant institutions. Contractor Contractor, PMU and local authority Workers/people who attend the scene Contractor Contractor and local community 5 Detect unexploded landmines Protect the scene Report to the local authority Contact to the most suitable military unit for help Contractor Contractor/ authority. local 47

48 7. THE ENVIRONMENTAL MORNITORING PLAN 7.1 The monitoring plan in compliance with the mitigation measures Potential impact Monitoring methods Table 4: The mornitoring plan Time Signs compliance Monitoring Unit 1 Accident related UXO to Check documents During the design stage Prior to the contractor is appointed to the construction site Sign the contract Complete the work. PMU Independent Monitoring (6 months) 2 Destroy trees and vegetation Observe vegetation tree covers the and Before construction site clearance Weekly, during the construction clearance time Agrarian floor. Keep vegetation far from the construction site PMU Contractor Construction monitoring The independent monitoring (6 months) 3 Local inundation Observe the actual drainage/ sewerage process After the heavy rains During extensive excavation the Good drainage surface No stagnant water on the construction site Construction monitoring Independent monitoring (6 months) 4. Generate waste 5 Noise and dust Monitoring the generated waste and waste treatment Interview Monitoring dust level in the construction site weekly Clearance of construction site Monthly Daily, during the extensive excavation, concrete and construction 48 Cover waterproof for the trash. Prohibition of disposing waste to the construction site Announce to the local authority Cover trucks Limited dust level on the construction roads and site. PMU Construction monitoring Independent monitoring (6 months) PMU Construction monitoring Independent monitoring

49 Potential impact Monitoring methods Time Signs compliance Monitoring Unit process implementation No complaint about dust and noise. (6 months) 6 Water pollution 7 Cultural/soci al conflict Increased risk of HIV/AIDs 8 Increase the threats of hunting and consuming wild animals 9 Protect the cultural resource Monitoring the construction site, surface drainage in water storage areas Interview workers and local residents. Monitoring workers in the construction site Control the food and worker camps Monitoring local residents Twice a week Monthly Weekly, especially weekend and holiday Monitoring During the excavation implementation Create the drainage system and draining hole/ sediment trap Cover and embank oil and fuel storage areas No trace of oil/fuel leakage on the ground. Communication campaign to prevent the risk of HIV/AIDs for workers at the resettlement sites Hire local workers for manual working implementation Not keeping wild animals in camp No hunting equipment in camp No report of wild animal consumption. Application of Revealed Treatment Process Construction monitoring Construction monitoring Independent monitoring (6 months) Construction monitoring Independent monitoring (6 months) Construction monitoring Independent monitoring (6 months) 10 Landslide/ Erosion Stability slope of Monitoring of soil transportation and threats from construction site, especially from excavation area. Occurrence of excavation process Weekly at construction site, where vegetation is not recovered Prevent the slope erosion during excavation time Cultivated lands at construction sites are re-planned. Construction monitoring Independent monitoring (6 months) 49

50 Potential impact Monitoring methods Time Signs compliance Monitoring Unit 11 Safety for worker 12 Safety for community 13 Capacity to approach of users to the infrastructur e/ resource Require protection clothing workers labor for monitoring the construction site, material and stone pits, during and after implementation of blasting work monitoring the impacts with the infrastructure/ existing resource 14 Risk on fire monitoring fuel and oil storage areas 15 Interrupted the approach or destroy the cultivated monitoring the cultivated land around the construction area Within 2 weeks, since the contractor has been mobilized to the construction site weekly Weekly during construction time Before and during blasting time Before the implementation of electric provided. Weekly Daily Weekly After complete excavation stage Develop the safety rules at work Workers with labor protection clothing such as gloves, boots, hard hats, etc at work Set warning signs at construction site Guard before and during the exploded time Including construction lighting system Guider is available for traffic when the trucks go out or loading and unloading time Training the safety electric usage for ethnic The effected local authority and residents receive the notice and agree about water supply progress for construction and in case of temporary interruption. Make driveways necessary. more if Set warning fires at the fuel and oil storage areas The combustible source must be far away from fuel and oil storages at least 100m Not allowed to load/unload or discharge waste, building materials at cultivated land Construction monitoring Independent monitoring (6 months) Construction monitoring Independent monitoring (6 months) Construction monitoring Independent monitoring (6 months) Construction monitoring Independent monitoring (6 months) Construction monitoring Independent monitoring 50

51 Potential impact Monitoring methods Time Signs compliance Monitoring Unit land area (6 months) 16 Health risk related to asbestos cement material monitoring resettlement activity. the During the resettlement time Residents wear the face mask when loading/unloading roofs made by asbestos cement. Construction monitoring Independent monitoring (6 months) 17 Control the transmissio n of the disease Check the real activity of contractor about the detail design. During the resettlement construction time. Construct the sanitation and drainage systems. Set the lips and holes for water tanks. PMU Construction monitoring Independent monitoring (6 months) 7.2 The environmental quality monitoring Beside mornitoring contractor's compliance on mitigation measures implementation, an environmental quality monitoring/sampling will be implemented during project performance (see table 5 below) 51

52 Table 5 : The environmental sampling program No. Observation items Pre-construction Construction Operation I Air quality 1. Parameter TSP, PM10, Noise 2. Frequency One time during 6 Per 6 months One time for the months after first operation year. construction 3. Location II Resettlement site No. 1 2 points: on the planned West Thanh Hoa Road, near Co Pung and To Xuoc Points Resettlement site No. 2 3 points: Lat, Nang and Tai Chanh Village Resettlement site No. 3 2 points: Lin and To Chieng Village Resettlement site No. 4 3 points: Tham Ton, Suoi Non 1 and Suoi Non Applied Environmental Standard QCVN 05:2008/MONRE QCVN 26:2010 / MONRE; Surface Water Quality 1. Parameter T, ph, DO, TSS, BOD5, COD, oil and grease, Coliform 2. Frequency One time within 6 one time per six One time within the months prior to months the first year of construction pilot operation. commencement 3. Location Resettlement site No. 1 Resettlement site No. 2 Resettlement site No. 3 Resettlement site No Applied Environmental Standard 1 point: Tà Ban Stream 1 point: Nang Stream 1 point: To Chieng (Ta Buôn) Stream 1 point: Quanh Stream QCVN 08:2008/MONRE; 52

53 8. EMP IMPLEMENTATION In order to ensure the EMP implementation operate effectively, environmental management system is defined with involvement of related agencies (see figure 8). WB EVN PMU Trung Sơn Independent Monitoring Consultation Construction monitoring monitoring Report Information interchange Contractor Local authority Community Figure 8 Organization chart of environmental management system (EMS) During detailed design stage, EMP requirement have to be integrated into assignment.. During the bidding and contract negotiation process, contractors have to review all the responsibilities and assigned task of contractor related to environmental mitigation measures and make commitment to comply with the regulations. Cost estimate for mitigation measure is encouraged to be done clearly. In the construction phase, Construction Supervision Consultant (CSC) have responsibility to conduct on-site monitoring on agreed mitigation measures implemented by Contractors (see Terms of reference in Appendix 3) The roles and responsibilities of the stakeholders during EMP implementation process are summarized in the following table: 53

54 Table 6: The roles and responsibilities of the stakeholders in the EMP implementation progress Stakeholders Responsibilities Sub-project 's stage 1. Trung Son PMU Contracting with the consultant to conduct 2. Feasible study consultant the environmental screening and EMP preparation for the sub-project. monitoring to ensure that the suitable mitigation measures are applied for the technical designs, bidding documents, construction contracts and construction monitoring. Arrange enough the resource including staffs and budget for the EMP implementation and monitoring of the sub-projects. The general monitoring to ensure the EMP compliance. Incorporation of mitigation measures on the technical design documents and construction contract and construction supervision. Cost estimate for environmental mitigation measures. 3. Contractor Ensure sufficient budget allocated to 4. Construction supervision consultant (CSC) 5. Independent monitoring consultant implementation of environmental mitigation measures by incorporated it into financial proposal and contract. Implement all the mitigation measures as agreed daily conduct on-site monitoring on health, safety and environmental issues as defined in EMP Conduct monitoring on effectiveness of EMP implementation Conduct sampling program Prepare report submitted to the WB and relevant agencies FS preparation Detailed design Construction Pilot operation FS preparation Bidding construction Construction Pilot operation and 54

55 6. The local authorities 7. The relocated households Facilitate to: Community consultation during the detailed design (if available) Conduct community based monitoring system on environmental impacts Participate in monitoring on environmental issues generated from construction activities - Detailed design Construction 9. REPORTING SYSTEM Table 7: Requirement of mornitoring report No. From To Report Frequency 1 The contractor PMU Monthly 2 Construction supervision consultant PMU Monthly 3 PMU Local authorities In required 4 Independent monitoring consultant PMU, WB Once per six months 5 PMU Trung Son Hydro Power Company Limited Once per six months 6 Trung Son Hydro Power Company Limited WB, EVN Once per six months 55

56 10. CAPACITY BUILDING Table 8: Propsed training program on EMP No. Contents Time Cost estimate 1 Training on labour safety and mitigation One time before Included in measures for the construction workers construction construction commencement contract 2 Training on EMP implementation and monitoring for staffs of PMU Annually Included in training program of main project 3 Training on community based monitoring for local authorities and representatives of affected people of 5 communes One time before construction commencement VND Total ESTIMATED COST FOR EMP IMPLEMENTATION Table 9: Estimated cost for EMP implementation No. Items Before construction Construction Operation 1 The mitigation This cost is This cost is counted The local environmental measures counted in the in the contract with and sanitation management contract with the the contractor cost. design consultant 2 Environmental quality monitoring of CSC Included in contract of CSC 3 Independent monitoring consultant included sampling VND 56

57 program 3 Capacity building cost In general training fee of Trung Son Hydropower Project AMOUNT: VND 57

58 12. COMMUNITY CONSULTATION AND INFORMATION DISCLOSURE No. Location for consultation Day and Time Attended members List of participated local authorities and representatives of households Summarize the issues as discussed/mentioned 58

59 13. REFERENCES 1 Basic design for the resettlement sites of Trung Son Hydropower Project. 2 Approval of the basic design for the resettlement sites of Trung Son Hydropower Project issued by Trung Son Hydropower Company Limited 3 Resettlement Plan report 4 EIA and EMP reports for Trung Son Hydropower Project (main project) 5 SESIA for Trung Son Hydropower Project. 14. ANNEX 59

60 14.1 Annex 1 Location of disposal sites The disposal location of resettlement No. 1 60

61 61 The disposal location of resettlement site No. 2, 3

62 The disposal location of resettlement site No. 2, 3 62