1 ENVIRONMENTAL MONITORING REPORT Project Number: January 2018 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian Development Bank

2 SEMI-ANNUAL ENVIRONMENTAL MONITORING REPORT Period January June 2017 Project Number: Loans 3161/8286-VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Executing Agency: EVN Hanoi City Prepared by Hanoi City Power Corporation, Electricity of Vietnam for Asian Development Bank

3 ABBREVIATIONS ADB B&C documents CEMP CSC DPMB EMP EVNHANOI: EVNHCMC: HCMC IEE JV: OHL: PCC: PIC: RoW UGC: UXO: Asian Development Bank Bidding and Contract documents Contractor Environmental Management Plan Contractor Safeguard Consultant Development Project Management Board Environmental Management Plan Ha Noi Power Corporation Ho Chi Minh City Power Corporation Ho Chi Minh City Initial Environmental Examination Joint Venture Over Head Line Power Construction Company Project Implementation Consultant Rights of Way Underground cable Unexploded Ordnance CURRENCIES (Rate of exchange of 28March. 2016) Currency Unit VND $1.00 = 22,355 VND NOTE In this report, "$" refers to US dollars unless otherwise stated. This Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the terms of use section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the ADB does not intend to make any judgments as to the legal or other status of any territory or area.

4 Table of Contents 1 INTRODUCTION Project Background Report Purpose Project implementation progress MONITORING MANAGEMENT SYSTEM AND MONITORING METHODOLOGY Monitoring Management System Monitoring methodology Document review of Monitoring Compliance with EMPs by CSC Site visit Compliance with ADB loan covenants and applicable government laws, regulations and requirements Compliance with ADB loan covenants Compliance with the environmental requirements of the Government of Vietnam Incorporation of Environmental Requirements into Project Contractual Arrangements Summary of Environmental Mitigations and Compensation Measures Implemented during the Construction Phase Environmental Mitigation Measures Implemented Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Thuong Tin-Thanh Oai Transmission Line Expansion of Thuong Dinh 110KV substation Connecting line to 220 kv Son Tay Substation Main findings from site visit Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Thuong Tin-Thanh Oai 210 KV transmission line Expansion of Thuong Dinh S/S (110kV) - E kV line to 220kV Son Tay S/S EMP Performance Status Summary of Environmental Mitigations and Compensation Measures Implemented during the Operation Phase SUMMARY OF ENVIRONMENTAL EFFECT MONITORING Monitoring location and frequency Applicable Standards Ambient air quality standard Waste water quality standard Surface water quality standard Soil quality standard Monitoring result Ambient air quality... 42

5 7.3.2 Surface water quality Soil quality Key Issues Identified Issues identified between January and June Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Thuong Tin - Thanh Oai transmission line Expansion of Thuong Dinh 110KV substation Connecting line to 220 kv Son Tay Substation Issues from previous report (June-December 2016) COMPLAINTS CONCLUSION AND RECOMMENDATION Conclusions Recommendation...50 Appendix A: Summary of the environmental requirements in EMP/IEE and in B&C documents.. 1 Appendix B: Photos of Site Visit Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Thuong Tin - Thanh Oai transmission line... 6 Appendix C: Environmental Effect Monitoring results Air quality in front of control centre of Son Tay substation on 13 March Air quality at Safety corridor of over head line at Dong Phuong Yen commune, Chuong Mi district of Phu Nghia substation and transmission line on 10 January Air quality at Dam of Tich river, Can Huu commune, Quoc Oai district of Phu Nghia substation and transmission line on 10 January Air quality at worker camp Phu Nghia 110kV substation of Phu Nghia substation and transmission line on 10 January Air quality at 220kV Xuan Mai substation of Phu Nghia substation and transmission line on 12 April Air quality at Safety corridor of over head line at Dong Phuong Yen commune, Chuong Mi district of Phu Nghia substation and transmission line on 12 April Air quality at Dam of Tich river, Can Huu commune, Quoc Oai district of Phu Nghia substation and transmission line on 12 April Air quality at worker camp of Phu Nghia 110kV substation of Phu Nghia substation and transmission line on 12 April Air quality at K1, K2, K3, K4, K5, K6, K7, K8, K9, K10, K11, K12, K13, K14 of Thuong Tin- Thanh Oai 110kV transmission line on 25 Jul Air quality in front of expansion control centre of Expansion Thuong Dinh 110kV substation on 13 March

6 11. Air quality in front of expansion control centre of Expansion Thuong Dinh 110kV substation on 12 July Surface water at NM1, NM2, NM3, NM4, NM5, NM6 of Thuong Tin- Thanh Oai 110kV transmission line on 12 July Soil quality at field around Son Tay substation on 27 March Appendix D: Official Letter from Hanoi DPMB to the contractors of (i) Rehabilitation of Son Tay 110KV substation; (ii) Phu Nghia substation and connecting line; (iii) Thuong Tin-Thanh Oai Transmission line; (iv) Expansion of 110kV Thuong Dinh substation E1.5; and (v) Son Tay 110kV transmission line (26 Nov 2016) Official Letter from Hanoi DPMB to the contractors of 110kV line to 220kV Son Tay subsation (ST-W01), Phu Nghia substation and connecting line (110kV) (PN_W01-L01, PN_W01_L02), T/L (110kV) from Thuong Tin substation to Thanh Oai (TTTO-W01) (19 Dec 2016)...25

7 LIST OF TABLES TABLE 1: LIST OF SUBPROJECTS WITH IEE STATUS... 9 TABLE 2: THE SCOPE OF 06 CIVIL WORKS PACKAGES OF 5 SUBPROJECTS...10 TABLE 3: CONSTRUCTION PROGRESS OF SUBPROJECTS...12 TABLE 4: ENVIRONMENTAL MONITORING STAKEHOLDER S RESPONSIBILITIES...18 TABLE 5: ESTABLISHED MONITORING SYSTEM AMONG RELEVANT STAKEHOLDERS...19 TABLE 6: STATUS OF LOAN COVENANT COMPLIANCE...22 TABLE 7: THE GOVERNMENT ENVIRONMENTAL REQUIREMENTS AND COMPLIANCE LEVELS...23 TABLE 8: EMP COMPLIANCE STATUS OF ONGOING CIVIL WORK PACKAGES...30 TABLE 9: EMP COMPLIANCE STATUS OF COMPLETED SUBPROJECTS...37 TABLE 10: ENVIRONMENTAL EFFECT MONITORING PARAMETERS, LOCATION AND FREQUENCY OF 5 SUBPROJECTS STATED IN IEES...39 TABLE 11: STATUS OF ENVIRONMENTAL MONITORING ANALYSIS...40 TABLE 12: AMBIENT AIR QUALITY STANDARD...41 TABLE 13: WASTE WATER QUALITY STANDARD...41 TABLE 14: SURFACE WATER QUALITY STANDARD...41 TABLE 15: SOIL QUALITY STANDARD...42 TABLE 16: MONITORING RESULT FOR AIR QUALITY OF REHABILITATION OF SON TAY 110KV SUBSTATION (Q1 2017)...42 TABLE 17: LOCATION OF AIR QUALITY MONITORING OF PHU NGHIA SUBSTATION AND CONNECTING LINE...42 TABLE 18: MONITORING RESULT FOR AIR QUALITY OF PHU NGHIA SUBSTATION AND CONNECTING LINE...43 TABLE 19: LOCATION OF AIR QUALITY MONITORING OF THUONG TIN- THANH OAI TRANSMISSION LINE...43 TABLE 20: MONITORING RESULT FOR AIR QUALITY OF THUONG TIN- THANH OAI 110KV TRANSMISSION LINE (Q2 2017)...44 TABLE 21: AIR QUALITY MONITORING RESULT FOR EXPANSION OF THUONG DINH 110KV SUBSTATION (Q1, Q2 2017)...45 TABLE 22: MONITORING RESULT FOR SURFACE WATER QUALITY OF PHU NGHIA SUBSTATION (MONTHLY 2017)...45 TABLE 23: LOCATION OF SURFACE WATER QUALITY MONITORING OF THUONG TIN- THANH OAI TRANSMISSION LINE...45 TABLE 24: MONITORING RESULT FOR SURFACE WATER QUALITY OF THUONG TIN- THANH OAI TRANSMISSION LINE (Q2 2017)...46 TABLE 25: MONITORING RESULT FOR SOIL QUALITY OF SON TAY 110KV SUBSTATION...46 TABLE 26: ISSUES IDENTIFIED DURING THE PREVIOUS MONITORING PERIOD AND SOLUTION...48 TABLE 26: IDENTIFIED ISSUE AND ACTION REQUIRED...52 LIST OF FIGURES FIGURE 1: ENVIRONMENTAL MANAGEMENT SYSTEM...17 FIGURE 2: LOCATION OF AIR QUALITY MONITORING OF PHU NGHIA SUBSTATION AND CONNECTING LINE...43 FIGURE 3: LOCATION OF AIR QUALITY MONITORING OF THUONG TIN- THANH OAI TRANSMISSION LINE...44 FIGURE 4: LOCATION OF SURFACE WATER QUALITY MONITORING OF THUONG TIN- THANH OAI TRANSMISSION LINE...46

8 1 INTRODUCTION 1.1 Project Background 1. The Asian Development Bank (ADB) has approved Loan 3161/8286-VIE:1 Ha Noi and Ho Chi Minh City Power Grid Development Sector Project to strengthen the capacity and reliability of the power infrastructure in Ha Noi and Ho Chi Minh City through the rehabilitation and development of the 220 kilovolt (kv) and 110 kv grid. Hanoi Power Corporation (EVN HANOI) and Ho Chi Minh City Power Corporation (EVN HCMC), which are respectively responsible for the power supply in Ha Noi and Ho Chi Minh City, are the executing agencies. The project s impact will be that growth in national electricity demand is met in a sustainable manner, and the outcome will be improved reliability and efficiency of electricity supply in Ha Noi and Ho Chi Minh City. 2. The project s outputs, categorized into four distinct groups to enable more focused monitoring of project performance, are the development and/or rehabilitation of: (i) four core substation and transmission line subprojects in Ha Noi, (ii) four core substation and transmission line subprojects in Ho Chi Minh City, (iii) up to 19 noncore substation and transmission line subprojects in Ha Noi, and (iv) up to eight 2 noncore substation and transmission line subprojects in Ho Chi Minh City. 1.2 Report Purpose 3. This report presents the results of the environmental management performance and internal monitoring activities for period of January- June The report covers the following: - Status of compliance with ADB environmental loan covenants and with the environmental requirements of the Government of Vietnam during the report period. - Status of implementation of the environmental mitigation measures during the report period of January- June 2017, under construction five subprojects (Sơn Tay s/s, Phu Nghia s/s, Thuong Tin- Thanh Oai T/L, Thuong Dinh s/s, Son Tay T/L) based on the EMP requirements included in disclosure IEEs - Recommending measures to mitigate the negative impacts on the environment for the construction phase. - Monitoring results during operation phase of 5 subprojects namely: (i) Construction of Noi Bai airport S/S (110kV); (ii) Mo Lao S/S (110kV) and 110kV Branches; (iii) Chem - Tay Ho T/L (220kV); and (iv) Thanh Xuan S/S (110kV). 1.3 Project implementation progress 4. As stated in the approved IEE, the independence environmental monitoring consultant will not be mobilised to conduct environmental monitoring. Thus, the monitoring tasks have been assigned for Construction Supervision Consultant (CSC), Hanoi Development Project Management Board (DPMB) with support of Project Implementation Consultant (PIC). This monitoring focus on monitoring implementation of environmental protection measures of the construction contractors. The status of internal environmental monitoring system as well as preparation of national EIAs and IEEs and construction states are summarized in Figure 1. 1 The funds are from ADB s ordinary capital resources (OCR) and ASEAN Infrastructure Fund (AIF). 2 There were nine suprojects proposed in the original list, but one (11kV Cat Lai An Khanh power line) was withdrawn in 2017.

9 Table 1: List of subprojects with IEE status Subproject DoNRE EIA Approval IEE Construction started Construction completed EVN HANOI A: Core Project 1 Rehabilitation of Son Tay S/S (110kV) Nov-14 May-16 Apr-17 2 Rehabilitation and upgrade of Phuong Liet S/S (110kV) Nov-14 Disclosed in Jan 2014 (Q4 2017) not yet 3 Rehabilitation and upgrade of Tran Hung Dao S/S (110kV) Nov-14 (Q4 2017) not yet 4 Construction of Noi Bai airport S/S (110kV) Aug-13 Disclosed in Dec 2013 May-15 Apr-16 B: Non-Core Project 1 Mo Lao S/S (110kV) and 110kV Branches Oct-13 Disclosed in Jun 2014 Dec-15 Jun-16 2 Chem - Tay Ho T/L (220kV) Mar-14 Disclosed in Jun 2014 Dec-14 Aug-15 3 Thanh Xuan S/S (110kV) Jan-15 Disclosed in Jun 2015 Dec-15 Jun-16 4 Expansion of Thuong Dinh S/S (110kV) - E1.5 Jun-15 Disclosed in Jun 2015 Dec-16 Jul-17 5 Phu Nghia S/S (110KV) and 110KV line Jan-15 Disclosed in Mar 2016 Aug-16 Aug-17 6 T/L (110kV) from Thuong Tin S/S to Thanh Oai Aug-14 Disclosed in Apr 2016 Sep-16 Apr-17 7 Rehabilitation of 110KV bay - Tia S/S - E10.4 Not Required* Disclosed in Aug 2016 (Q3 2017) not yet 8 110kV line to 220kV Son Tay S/S Apr-16 Disclosed in Nov 2016 Dec-16 Jul-17 9 Thanh Cong - Thuong Dinh UGC (110 kv) Apr-15 Disclosed in Mar 2017 (Q2 2017) (Q4 2017) 10 Construction of Tay Ho - Yen Phu UGC (110 kv) Apr-15 Disclosed in May 2017 (Q4 2017) not yet 11 New building 110kV Ba Vi S/S Jun Apr 2017 (expected) (Q3 2017) (Q4 2017) 12 New building 110kV Sai Dong Industrial combinations (Sai Dong 2) Not yet June 2017 (expected) (Q4 2017) (Q4 2017) kV line to Sai Dong Industrial combinations S/S Not yet June 2017 (expected) (Q4 2017) (Q4 2017) 14 New building 110kV Tay Ho Tay S/S and line Not yet May 2017 (expected) (Q1 2018) not yet 15 New building 110kV Phung Town and line Not yet May 2017 (expected) (Q1 2018) not yet 16 New building 110kV Ngoc Hoi and line Not yet Aug 2017 (expected) (Q2 2018) not yet 17 TL (110kV) Thuong Tin S/S - Quat Dong S/S - Tia S/S Not yet Aug 2017 (expected) (Q2 2018) not yet New building 110kV Chuong My and line 110kV Thanh Oai - Chuong Not yet Aug 2017 (expected) (Q2 2018) not yet 18 My kV line from North An Khanh to South An Khanh Not yet Sep 2017 (expected) (Q2 2018) not yet * EIA is not required for "Rehabilitation of 110KV bay - Tia S/S - E10.4" by DONRE. Environmental Protection Plan will be submitted to District Environment Natural Resource Division before the construction starts.

10 5. The construction progress during the reporting period and to-date for each of the sub-projects is described below. During the first semi-annual period 2017, the construction activities are taking place in 5 subprojects: i) Rehabilitation of Son Tay 110KV substation-e1.7; ii) Phu Nghia 110KV substation and 110KV line; and iii) Construction of 110kV line from Thuong Tin 500 / 220kV substation supplying electricity to Thanh Oai 110kV, iv) Expansion of Thuong Dinh S/S (110kV) - E1.5, v) 110kV line to 220kV Son Tay S/S. Particularly, Rehabilitation of Son Tay 110kV Substation- E1.7, Phu Nghia s/s and Thuong Tin- Thanh Oai TL subproject have been continuing from the second semi annual period 2016; two other have been started in January The scope of each contract package and its implementation period is summarized in Table 2. Subproject 1. Rehabilitati on of 110kV Son Tay S/S 2.Phu Nghia 110KV substation and 110KV line 3.Constructi on of 110kV line from Thuong Tin 500 / 220kV substation supplying electricity to Thanh Oai 110kV Table 2: The Scope of 06 civil works packages of 5 subprojects Contract Start Scope Contractor package Date ADB- Rehabilitation of 110kV Son Tay JV Pico- o. HNPC- substation, all the civil work will Hanoi ST-W01: carry out inside the substation development Civil work only. investment for and electricity rehabilitee services s Son Tay Company substation ADB- HNPC- PN-W01- L01: Constructi on of substation ADB- HNPC- PN-W01- L02: Constructi on of OHL ADB- HNPC- TT-TO- W01 : Constructi on of OHL Construction of new Phu Nghia 110kV substation in lot KT-01 of Phu Nghia Industrial Zone, Phu Nghia commune, Chuong My district, Hanoi, on an area of 6.110m 2. This is part of Phu Nghia Industrial Zone which does not require land acquisition and clearance. Construction of new Phu Nghia- Xuan Mai 110kV transmission line of km long with an acquired area of 256,355 m 2 ; and two 110kV feeder bays at vacant 110 kv distribution yard of 220kV Xuan Mai, in Thach Hoa commune, Quoc Oai District, Ha Noi City Construction of new 110kV transmission line consists of building thirteen (13) towers with total length of overhead line is km. The new 110kV transmission line has the departure point: 110kV busbar of 500kV Thuong Tin substation, located at Van Phu commune Thuong Tin district, Hanoi city to arrival point is busbar of 110kV Thanh Oai substation, located at Kim Bai town, Thanh Oai district, Hanoi city Completi on date Mar 2016 Jun % completed IDC Sep 2016 Jun % completed INCO Sep 2016 Jun % completed Sông Đà Joint Stock Company 11 Oct 2016 Jun % completed 10

11 Expansion of Thuong Dinh 110kV substation - E kV line to 220kV Son Tay Substation ADB- HNPC- TD-W01: Constructi on of substation ADB- HNPC- NRST- W01 Thuong Dinh 110kV station was built and energized on December 2012 in an area of 4,844.16m2. It currently operates with 03 transformers of a total capacity of 166MVA. This subproject will install 02 additional 63MVA power transformer on an expansion area of approximately 2,705.6m 2. The whole expansion is made on part of Thuong Dinh Warehouse that is managed by National Power Transmission Corporation The subproject Construction of 110kV transmission line from the 500/200kV Thuong Tin substation to the 110kV Thanh Oai substation consist of construction of a new 110kV transmission line which consists of 13 towers with total length of overhead line is km. The new 110kV transmission line goes through nine (8) communes/town in two (2) Thuong Tin and Thanh Oai districts, Hanoi city. The departure point is from the 500/200kV Thuong Tin Substation at Van Phu commune (Thuong Tin district) and arrival point at the 110kV Thanh Oai Substation in Kim Electricity Construction Joint Stock Company No. 1 Vietnam Electricity Construction Joint Stock Company (VNECO) Jan 2017 Jun % completed Jan 2017 Jun % completed Bai town (Thanh Oai district) JV = Joint Venture, OHL = Over Head Line, PCC = Power Construction Company, UGC = Under Ground Cable 6. Works on all packages PN-W01, TD-W01 and NRST-W01 are now moving forward and ST- W01, TT-TO-W01 have been operating since June Until June 2017, the completed work items include three packages namely PN-W01, TD-W01 and NRST-W01 with a working progress of 98%, 95% and 70% respectively. Works on these three packages are proposed to complete in July The monthly construction progress of five ongoing subprojects (Son Tay s/s, Phu Nghia s/s, Thuong Tin- Thanh Oai T/L, Thuong Dinh s/s and Son Tay T/L) is summarized in Table 3. 11

12 Contract package Son Tay s/s PN-W01- LO1: Construction of substation Table 3: Construction Progress of subprojects Physical progress January, Fitted the scaffolding, Plasted the concrete beam and outward wall of control centre. February, Installed medium voltage cubicles, protection and control cubicles inside control centre. - Installed septic tank and drain pipe of substation - Painted the control centre March, Installed curb in front of substation - Completed installing septic tank within the substation - Building the cable trench in going T2 transformer. - Rip-rap for switch yard. - Digging and laying down the 22kV underground cable feeder namely 472, Connecting secondary cable inside AC, DC, PP-1, CP-T1, ACCU cubicles. - Fixing the terminal box of 02 connection cubicles - Testing the 24kV cubicle - Laying down communication cable April, Carryout the site acceptance test to 171, 131 bays, C41 bar and T1 transformer; - Connecting medium feeders, capacitor bank to new control centre. May, The substation starts operating June, The substation under operation January, 2017 Building the surounding brick wall for store of substation; Filling sand for lobby of control centre; Building wall for out door cable trench; Fixing electrical equipment on their support selves. February, 2017 Completed installing all supporting selves for outdoor electrical equipment; Installing control centre s roof; Paving function room of control centre; Building outdoor cable trenches and installing cable rack of trenches; Casting the switch yard. March, 2017 Connecting all part of earthing system of toilete and control center to the earthing system of substation; Casting concrete slab of out door cable trenchs; Installing Circuit breaker, Current transformer, Voltage transformer; Installing pooctich bar, lightening protection of substation; Paving tiled for roadway's pavement inside the substation; Building and plastering the parterre along with the roadway within the boundary of substation. April, 2017 Installing caparcitor banks for substaion; Testing for current transformer and voltage transformer; Rip-rapping for swith yard. Installing fire protection system. May,

13 Contract package PN-W01- LO2: Construction of Overhead line Physical progress Installing 22kV and 35kV distribution cubicles inside control center and control and protection cubicles; Installing 110kV outdoor equipment, 24kV and 35kV caparcitor bank; Laying down and connecting power cable and secondary cables inside control center; Painting curbs of roadway inside substation; Testing and adjusting secondary board of electrical equipment. June, 2017 Testing and adjusting for 110, 35, 22kV electrical equipment ; Installing Pantograph disconnector for 112 bay; Carrying out acceptance for control and protection board of 171, 172, 131, 132, TC C41, C42, C31, C32 bays. January, 2017 Completed drilling of 50/53 electric pile foundations Completed casting base for 50/53 electric pile foundations Completed casting for 48/53 electric pile foundations Completed installing 43/53 Electrical pile foundations February, 2017 Completed drilling of 51/53 electric pile foundations Completed casting base for 51/53 electric pile foundations Completed casting for 51/53 electric pile foundations Completed erecting 24/53 Electrical piles. March, 2017 Completed drilling of 53/53 electric pile foundations Completed casting base for 52/53 electric pile foundations Completed casting for 52/53 electric pile foundations Completed erecting 48/53 Electrical piles. Laying cable on the electrical piles from electrical pile No.05 to 06. April, 2017 * 110kV Phu Nghia transmission line Completed drilling of 53/53 electric pile foundations Completed casting base for 53/53 electric pile foundations Completed casting for 53/53 electric pile foundations Completed erecting 52/53 Electrical piles. Laying cable on the electrical piles from electrical pile No.02 to 06, No.07-08, 15-25, 29-33, 39-41, 42-43, * 220kV Xuân Mai Substation part Erecting the formwork and casting foundation for support self of electrical equipments within the 220kV Xuan Mai substation. May, 2017 * 110kV Phu Nghia transmission line Completed drilling of 53/53 electric pile foundations Completed casting base for 53/53 electric pile foundations Completed casting for 53/53 electric pile foundations Completed erecting 53/53 Electrical piles. Laying cable on the electrical piles which total length is 6.766m/11.821m. * 220kV Xuân Mai Substation part Completing support self of electrical equipments for additional out going bay; Carried out acceptance test for electrical equipments for new out going bay. June, 2017 * 110kV Phu Nghia transmission line 13

14 Contract package Thuong Tin- Thanh Oai Thuong Dinh s/s Physical progress - Laying cable on the electrical piles from electrical pile No. 43 to 49; * 220kV Xuân Mai Substation part - Installing primary electrical equipments for 176 outgoing bay in 220kV Xuân Mai substation; January, 2017 Completed digging of 40/51 electric pile foundation; Completed casting base for 39/51 electric pile foundation; Completed casting for 38/51 electric pile foundation; Installing formwork, casting and installing anchor bolt for 38/51 electrical pile foundation; Backfilling for 35/51 electrical pile foundation; Completed installed the whole electric pile for 31/51 position. February, 2017 Completed drilling of 52/53 electric pile foundation; Completed casting base for 51/53 electric pile foundation; Completed casting for 51/53 electric pile foundation; Completed installed whole electrical pile for 24/53 tower. March, 2017 Completed digging of 51/51 electric pile foundation; Completed casting base for 51/51 electric pile foundation; Completed casting for 49/51 electric pile foundation; Installing formwork, casting and installing ancho bolt for 49/51 electrical pile foundation; Backfilling for 44/51 electrical pile foundation; Completed installed the whole electric pile for 44/51 position; Laying down the electrical cable on electrical pile from tower No. 23 to 51. April, 2017 Complete erecting all 51/51 electrical piles and laying down overhead line on all electrical tower; Completed plastering all 51/51 electrical pile's foundations. May, 2017 Going on operation June, 2017 Going on operation January, 2017 Breaking down the brick wall of store inside the substation; Digging fire protection water storage reservoir and oil fault exhausted reservoir February, 2017 Casting first floor and installing formwork second floor of control centre; Casting foundation for T1 transformer and installing the formwork for supporting selves of outdoor electrical equipments; Building the surrounding brick wall of substation; Installing the steel skeletons for anti fire water storage reservoir and oil fault exhausted reservoir; Completed installing all drain septic. March, 2017 Casting inward wall of underground floor; Pumping concrete for stair of underground and first floor; Building brick wall for first floor; Casting foundation for T1 transformer and 16 supporting selves of outdoor electrical equipment of T6 outgoing bay; Casting 17/29 supporting selves of electrical equipment of T5 bay; 14

15 Contract package Connecting line to 220 kv Son Tay SS Physical progress Building the surrounding brick wall of substation which length is 60m, completed two beam of substation's gate; Completed plating inward wall of oil fault exhausted reservoir; Installing earthing system of substation with 12/40 earthing rods and connecting 518/1500m earthing wire; Completed plasting 20m of 110kV cable trench and 65m of secondary cable trench. April, 2017 Plastering outward wall of control centre; Painting ceiling of first floor; Plastering second floor of control centre; Casting foundation of supporting selves for electrical equipment; Installing earthing system inside the substation; Backfilling T5 and T6 bays. May, 2017 Installing door for control centre; Installing foundation of supporting poles for disconnector inside substation; Installing cable rack for outdoor cable trenches; Installing draining system; Installing 110kV electrical equipment (i.e. circuit breaker, disconnector). June, 2017 Installing fire protection equipment; Completing roadway inside the substation; Testing 110kV, 22kV electrical equipment; Laying down secondary cable inside cable trenches; Connecting all 22kV distribution cubicles. January, 2017 Digging 04/19 electrical pile foundation; Completed casting base for 02/19 electric pile foundation; Installing steel skeletons for electric pile foundations; Testing sample of steel for making foundation of subproject. February, 2017 Completed drilling of 13/19 electric pile foundation; Completed casting base for 10/19 electric pile foundation; Completed casting for 07/19 electric pile foundation; Installation steel skeletons, casting foundations and installing anchor bolt for 06/19 electrical piles; Soil backfilling for 02/19 electrical piles. March, 2017 Completed drilling of 18/19 electric pile foundation; Completed casting base for 17/19 electric pile foundation; Completed casting for 17/19 electric pile foundation; Installation steel skeletons, casting foundations and installing anchor bolt for 15/19 electrical piles; Soil backfilling for 14/19 electrical piles completed erecting the whole electrical piles for 10/19 tower. April, 2017 Completed drilling of 19/19 electric pile foundation; Completed casting base for 19/19 electric pile foundation; Completed casting for 18/19 electric pile foundation; Installation steel skeletons, casting foundations and installing anchor bolt for 18/19 electrical piles; 15

16 Contract package Physical progress Soil backfilling for 18/19 electrical piles. Completed erecting the whole electrical piles for 16/19 tower. May, 2017 Completed drilling of 19/19 electric pile foundation; Completed casting base for 19/19 electric pile foundation; Completed erecting whole electrical piles for 18/19 electric towers; Lay down overhead line on electrical piles from tower No.6-7, 8-9, 10-13, , , (Ha Dong- Son Tay 110kV Transmission line); Preparing for connecting at terminal box of 220kV Son Tay substation. June, 2017 Completed drilling of 19/19 electric pile foundation; Completed erecting whole electrical piles for 18/19 electric towers; Lay down overhead line on electrical piles for whole route except from tower No , MONITORING MANAGEMENT SYSTEM AND MONITORING METHODOLOGY 2.1 Monitoring Management System 8. As stated in the approved IEE, the independence environmental monitoring consultant will not be mobilised to conduct environmental monitoring. Thus, the monitoring tasks have been assigned for Construction Supervision Consultant (CSC), HANOI DPMB with supported by Project Implementation Consultant (PIC). This monitoring focus on monitoring implementation of environmental protection measures of the construction contractors. The status of internal environmental monitoring system could be summarized in Figure 1. The detail description of Environmental monitoring responsibilities of each stakeholder is presented in Table 4. 16

17 Figure 1: Environmental management system 17

18 Table 4: Environmental monitoring Stakeholder s responsibilities Stakeholder Responsibilities Status of compliance Hanoi Establish an Environment Unit led by an Hanoi DPMB established an Development Environmental Staff to implement EMP tasks Environment and Social Unit which Project Manage, implement and supervise the is led by a vice director of DPMB Management compliance of the EMP and any conditions and consists of Head of Technical Board (DPMB) for approval, including the supervision of and Supervisory, one safeguard construction and operation of all Board staff expert staff, and some other DPMB and Contractor Evaluate the performance of EMP and conduct revisions, or suspension of staff who are assigned for each subproject to be responsible for environmental issues such as operations in cases of violating the supervision of EMP conditions of the EMP, which can cause implementation, its monitoring and serious impacts on the local community. coordination with relevant Ensure the effective communication and dissemination of content and requirements in EMP to the Contractor. Assist the Contractor in implementing subplans Supervise EMP performance Report EMP performance to EVN, ADB by semi-annual environmental monitoring report Prepare summary reports on Project s environmental activities upon request Brief the Project s information in community meetings Ensure continuing communication with local communities and fulfil commitments to facilitate for community consultations during project life. stakeholders. Construction Supervision Consultant (CSC) (which has one Construction safeguard consultant) Project Implementation Consultant (PIC) Prepare and implement Environmental Supervision Plan during construction phase Approve the Environmental Monitoring Plans (during construction phase) prepared by contractors, and supervise their implementation Report on any incidents or non-compliances of EMP to DPMB Ensure adequate education and training to all staff related to environmental supervision Provide recommendations on EMP performance to DPMB Assist EVN/DPMB in reviewing detailed design for the subproject to ensure mitigation measures being incorporated. Assist EVN/DPMB for monitoring and evaluation of safeguards compliance Maintain close coordination with HANOI DPMB s Environment Unit throughout the project life. One CSC, who oversees EMP compliance monitoring as well as construction work and engineering, was assigned for 5 ongoing civil work packages respectively. S/he prepared an Environmental Supervision Plan right after they signed the contracts with the HANOI DPMB, and reviewed Environmental Monitoring Plans prepared by contractors. These plans are prepared under the instruction of HANOI DPMB and approved by HANOI DPMB. Hanoi DPMB mobilized project implementation consultant to support IEE preparation and provide trainings and conduct site inspection 18

19 Stakeholder Responsibilities Status of compliance Work with HANOI DPMB to provide education and training for awareness building on safeguards issues Contractor Local authority and community Prepare an Environmental Monitoring Plan Keep records and necessary data as required in EMP and submit to Construction Supervision Consultant Ensure that workers are informed of purposes of EMP and aware of necessary measures to implement EMP Participate in monitoring EMP implementation Yes, 6 contractors of ongoing civil work packages have assigned 6 environmental officers to be in charge of environmental management 9. Monitoring system has been established among relevant stakeholders of ongoing subprojects to ensure internal monitoring of EMP compliance (Table 5). Environmental officer Ha Tuan Minh Yes Table 5: Established Monitoring system among relevant stakeholders Agency Project Management Board of Hanoi Power Development Nguyen Duc Ninh Nhu Xuan Quang Tran Kieu Ngoc Nguyen Van Hai Nguyen Thi Loan Project Implementation consultant Phu Nghia substation Nguyen Thanh Contractor - Power Engineering Construction Tung, Nguyen Huu Joint Stock Company Tuan Contractor - Machine Engineering Joint Stock Nguyen Van Hien Company CSC - Vietnam electrical construction consultant Le Van Thiep service JSC. Phu Nghia overhead connecting line Package No. ADB-HNPC-PN-W01-L01 ADB-HNPC-PN-W01-L02 ADB-HNPC-ST-W01 ADB-HNPC-NRST-W01 ADB-HNPC-TTTO-W01 ADB-HNPC-TD-W01 ADB-HNPC-PN-W01-L01 ADB-HNPC-PN-W01-L02 HANOI DPMB-PN-TVGS Nguyen Van Ky Contractor - Power construction JSC No.1 ADB-HNPC-TTTO-W01 CSC - Vietnam electrical construction consultant HANOI DPMB-TTTO- Le Van Thiep service JSC. TVGS Thuong Tin- Thanh Oai TL Nguyen Van Loc Contractor - Song Da 11 JSC ADB-HNPC-TTTO-W01 CSC - Joint venture Infrastructure Technical & HANOI DPMB-TTTO- Le Van Thiep Electricity construction Investment consultancy TVGS JSC and Electric power design survey JSC Rehabilitation of Son Tay 110KV substation Nguyen Van Tai Contractor Industrial construction JSC ADB-HNPC-ST-W01 Le Van Thiep CSC - Joint venture Infrastructure Technical & Electricity construction Investment consultancy JSC and Electric power design survey JSC HANOI DPMB-ST-TVGS Connecting line to 220 kv Son Tay SS Le Thanh Nha Vietnam Electricity Construction Joint Stock Corporation (VNECO) ADB-HNPC-NRST-W01 19

20 Environmental officer Le Van Thiep Agency CSC - Vietnam electrical construction consultant service JSC. Package No. HANOI DPMB-NRST- TVGS Thuong Dinh SS Lai Thi Nhu Contractor Power construction JSC No.1 ADB-HNPC-TD-W01 Le Van Thiep CSC - Joint venture Infrastructure Technical & Electricity construction Investment consultancy JSC and Electric power design survey JSC HANOI DPMB-TD-TVGS 2.2 Monitoring methodology 10. The EMP compliance monitoring has been conducted through: i) reviewing the completed monthly EMP compliance forms of CSCs for each civil work package; ii) Site inspection by HANOI DPMB (weekly); iv) environmental effect monitoring; and iv) Random site inspection by PIC, at least twice per year Document review of Monitoring Compliance with EMPs by CSC 11. All documents related to environmental management of the project are collected and reviewed to understand the performance of mitigation measures through its documentation. The reviewed documents include: internal monitoring reports of contractors of ongoing civil work packages, site inspection of CSC for every ongoing civil work packages, contractor environmental management plans (CEMP) and biding and contract documents. The Monthly reports on EMP compliance of contractors are done through site inspection of CSC for every ongoing civil work packages. Monitoring form aided by the monitoring checklist were prepared based on detail described mitigation measures, as per stated in EMPs, proposed in Annex C. The effectiveness of a contractor s environmental management of a particular impact item is evaluated subjectively using the following rating criteria: 1 Very good: all required measures are conducted 2 Good: main measures are conducted 3 Medium: some measures conducted 4 Weak: few measures conducted 5 Very weak: few measures conducted Site visit 12. Site visit has been conducted by HANOI DPMB (weekly). The PIC visits construction site at least two times every year. During this report period, PIC has conducted site visit on 18 April 2017 to random check performance of contractors on the site, check the location of worker camps, interview workers. 3 Compliance with ADB loan covenants and applicable government laws, regulations and requirements 3.1 Compliance with ADB loan covenants 13. As required, all safeguard environmental schedule stated on Loan Covenant need to strictly complied with, the list of environmental loan covenants and the level of compliance of Loan 3161/8286 is presented in 20

21 14. Table 6. 21

22 Table 6: Status of Loan Covenant Compliance ADB Environmental loan covenants Schedule 4, Para. No. 7 The Borrower shall ensure that the Executing Agencies do not award any Works contract which involves environmental impacts until:(a) The Ministry (or its Department, as the case may be) of Environment and Natural Resources has issued an environmental certificate approving the IEE relevant to the Subproject; and (b) the Executing Agencies have incorporated the relevant provisions from the EMP into the Works contract related to the Subproject. Schedule 4, Para. 10 The Executing Agencies shall recruit the individual consultants for preparation of safeguard documents, financial and economic analyses, technical specifications, bidding documents and bid evaluation reports in accordance with procedures acceptable to ADB for recruiting individual consultants. Schedule 5, Para. No. 3 The Borrower shall cause the Executing Agencies to ensure that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with (a) the Borrower's applicable laws and regulations relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the IEE, the EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report. Schedule 5, Para. No 8 The Borrower shall cause the Executing Agencies to make available necessary budgetary and human resources to fully implement the EMP and the RP. Schedule 5, Para. No 9 The Borrower shall cause the Executing Agencies to ensure that all bidding documents and contracts for Works contain provisions that require contractors to: (i) comply with the measures relevant to the contractor set forth in the IEE, the EMP and the RP and any corrective or prevent active actions set forth in a Safeguards Monitoring Report; (ii) make available a budget for all such environmental and social measures; and (iii) provide the Executing Agencies with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise Status of compliance Not complied with. EIA and IEE reports were prepared and approved as requirements of Vietnamese regulation and ADB s requirements respectively, and EMP is included in bidding documents of issued civil packages (namely: PN-W01-L01, PNW01-L02, TTTO-W01, ST-W01, NRST-W01). However, the bidding documents of Rehabilitation of Son Tay 110KV substation, Phu Nghia substation and connecting line and Thuong Tin-Thanh Oai Transmission line did not specifically mention the requirement of environmental effect monitoring required by the IEEs. Being complied with Hanoi DPMB has recruited Project Implementation Consultant (PIC) as well as Construction Supervision Consultant (CSC) for supporting in revising/preparing environmental reports and supervising in environmental mitigation measures Being compliance with - The compliance status of the Borrower's applicable laws and regulations relating to environment, health and safety is explained in Section IEEs, and semi-annual monitoring reports have been submitted to ADB for approval and disclosure; - Daily monitoring at site is conducted by supervisor consultants and supervisor contractors; - EMP included in biding documents of PN-W01-L01, PN- W01-L02, TTTO-W01, ST-W01, TD-W01, NRST-W01) civil constructs. The compliance monitoring system has been taken place as noted above. Being compliance with - The budget for EMP implementation will be available by project owner and contractors - The environmental staff of contractor, project owner as well as PIC are assigned to support and inspect EMP implementation Not complied with The bidding documents of PN-W01-L01, PN-W01-L02, TTTO- W01, ST-W01, TD-W01, NRST-W01) civil constructs and contracts for Works contain provisions that require contractors to comply with mitigation measures stated in IEE; make budget available and inform the Executing Agencies any unanticipated environmental, resettlement issues. However, the bidding documents of Rehabilitation of Son Tay 110KV substation, Phu Nghia substation and connecting line and Thuong Tin-Thanh Oai Transmission line did not specifically mention the requirement of environmental effect monitoring required by the IEEs. 22

23 ADB Environmental loan covenants during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the RP. Schedule 5, Para. No 10 (e) The Borrower shall cause the Executing Agencies to do the following: (a) submit semimanual Safeguards Monitoring Reports to ADB until the Project completion and disclose relevant information from such reports to the affected persons and to ADB web site promptly upon submission; (b) if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the RP, as applicable, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMP, and the RP promptly after becoming aware of the breach. Schedule 5, Para. No 26 For any Works supported under the Project, the Borrower shall ensure that the Executing Agencies will not issue a notice to proceed with such Works, until it has been confirmed in writing that the related construction site is free and clear from any unexploded ordnance. Status of compliance Being complied with - unanticipated environmental impacts and corrective action is a part in environmental monitoring reports; - as reported in monitoring reports, there were no unanticipated environmental impacts identified; - As confirm from Hanoi Development Project Management Board (DPMB), there are not large changes in projects which could create adverse impacts on environment; - Semi-annual Environmental Monitoring reports are submitted to ADB (first monitoring period: July-December 2015) - All civil works on the site complied with ADB requirements - This monitoring report will be disclosed on ADB website; the important sections of the monitoring reports like conclusion (problem findings) and recommendation will be translated into Vietnamese and distributed to contractors for implementation of corrective actions and placed at construction sites. If affected people are interested in, they can read it. Being complied with The Project Owner has sent a letter to the Hanoi Capital Military Command to get recommendation for UXO clearance for every subproject. If the Hanoi Command request for UXO clearance, this is always done before subproject construction. For 3 subprojects monitored in this report, UXO was required by Hanoi Capital Military Command and the UXO clearance was conducted before construction starts. 3.2 Compliance with the environmental requirements of the Government of Vietnam 15. The status of compliance with Government Environmental requirements are presented in Table 7. Table 7: The Government Environmental requirements and compliance levels No. Government Environmental requirements Compliance levels Legal documents on environment protection 1 Environmental Protection Law No.55/2014/QH13 of the 13 th National Assembly, the 7 th Session, passed on 23 Jun 2014 and put into force from 1 Jan Decree No. 18/2015/ND-CP dated 14 Feb 2015 of the Government on Regulating Strategic Environmental Assessment, Environmental Impact Assessment and Environmental Protection Commitment; Fully complied with All environmental protection requirements are fulfilled, such as preparation of EIA report, implementation of mitigation measures. Being compliance with EIAs have been prepared and approved for all subprojects as per regulation stated in the Decree, before the civil works start. 23

24 No. Government Environmental requirements Compliance levels 3 Decree No.38/2015/ND-CP dated 24 Apr 2015 issued by the GOV on waste and wasted materials management. 4 Circular No.36/2015/TT-BTNMT dated 30 June 2015 issued by the MONRE regarding the hazardous wastes management. 5 Circular No.27/2015/TT-BTNMT dated on 29 May 2015 on strategic environmental assessment, environmental impact assessment, and environmental protection plan. 6 Circular No. 31/2016/TT-BTNMT dated 14 October 2016 of the Ministry of Natural Resources and Environment regarding environmental protection for industrial clusters, concentrations of businesses, service providers, trade villages, production, commercial and service establishments Legal documents on electricity 1 Decree No.14/2014/ND-CP dated 26 Feb 2014 promulgated by the GOV regarding the detailed regulation on the implementation of the Electricity Law on electric safety, put into force from 15 Apr Circular No.31/2014/TT-BCT dated 2 Oct 2014 issued by the Ministry of Industry and Trade (MOIT) regarding the detailed regulation on some contents of electrical safety. Other relative legal documents: 1 Decree No. 45/2013/ND-CP dated 10 May 2013 of the GOV regarding the detailed regulation on some articles of the Labor Code on working hours, rest hours, occupational safety and occupational hygiene. 2 Circular No.22/2010/TT-BXD dated 2 Dec 2010 issued by the Ministry of Construction (MOC) regarding the regulation on labour safety during the project construction process. 3 Decision No.3733/2002/QD-BYT issued by the Ministry of Health dated 10 Oct 2002 regarding the promulgation of 21 labour hygiene standards, 5 principles and 7 labour hygiene measurements. Environmental Standards and Regulations Being compliance with Solid waste is properly collected and disposed at Xuan Son city licenced landfill site by Hanoi urban Environmental Company, who signed a disposal contract with contractors Being compliance with Hazardous waste is collected and treated separately during construction phase at Xuan Son and Nam Son landfill sites by Son Tay and Hanoi urban Environmental Company. Being compliance with EIAs have been prepared and approved for all subprojects following the guidance in the Circular and approved by relevant authorities before construction started It is complying with Mitigation measures for environmental impacts are implemented in general. It is complying with All safety regulations on ROW distances, UGC safety regulations etc. are strictly followed. It needs to be improved The regulated working hours, rest hours, occupational safety and occupational hygiene are followed in general but need improvement. It needs to be improved All workers must wear working protection facilities and trained on safety regulation at construction site It needs to be improved The labour hygienic conditions are relatively followed but needs improvement. It is complying with The impact mitigation measures are applied to meet the labour standard. 24

25 No. Government Environmental requirements Compliance levels 1 QCVN 05:2013/BTNMT - National technical regulation on ambient air quality; It is complying with The impact mitigation measures are applied to meet the standard on ambient air quality. Water is sprayed when the dust is visible at construction site. All trucks transporting construction material are covered by canvas, etc. 2 QCVN 26:2010/BTNMT - National technical regulation on noise. It is complying with. The impact mitigation measures are applied to meet the standard on noise. Constructor avoids operating machine, equipment creating big noise during rest time of local people. 3 QCVN 08-MT:2015/BTNMT - National technical regulation on surface water quality. 4 QCVN 07:2009/BTNMT - National technical regulation on hazardous waste thresholds. 25 It is complying with. The impact mitigation measures are applied to meet the standard on surface water quality. Hazardous wastes are gathered at one place and disposed by regulated unit which is Son Tay Urban Environmental Company. It is complying with. The impact mitigation measures are applied to meet the standard on hazardous waste. Hazardous waste is gathered at one place and disposed by regulated unit which is Hanoi Urban Environmental Company. 16. The environmental requirements of the Government of Vietnam are followed by HANOI DPMB and Constructors in general, but some improvements are required for full compliance. 4 Incorporation of Environmental Requirements into Project Contractual Arrangements 17. The environmental consideration has been incorporated into the subproject documents such as the EMP/IEE and the bidding and contract (B&C) documents of PN-W01-L01, PN-W01-L02, TTTO- W01, ST-W01, TD-W01, NRST-W01 as stated in Appendix A. 18. In these B&C documents, the content of the potential environmental impact and proposed mitigation measures for construction period in the EMP chapter in IEE and the emergency respond plan are included. 5 Summary of Environmental Mitigations and Compensation Measures Implemented during the Construction Phase 19. During this report period, 6 construction packages of 5 subprojects, namely: Son Tay substation (1 package), Phu Nghia substation and connecting line (2 packages), Thuong Tin Thanh Oai transmission line (1 package), Son Tay TL (1 package), Thuong Dinh Substation (1 package) are under construction. The monthly site inspection was conducted by the environmental officer of the HANOI DPMB. The Construction supervision consultant monitor at construction site every day.

26 5.1 Environmental Mitigation Measures Implemented 20. The environmental mitigation measures implemented at the five subprojects are as follows: Rehabilitation of Son Tay 110KV substation 21. Son Tay substation is built in a closed area within a surrounding wall. Warning signs and barriers around work areas were erected. Site could only be accessed with permission of contractor. The construction activities are conducted inside the substation area. Thus, the environmental impact, such as, dust and noise to residential areas is negligible. Building materials are gathered in the substation area, therefore it does not create dust and does not make traffic obstructs. The excavated area was limited to the area needed for construction only. There is no clearance of vegetation and other facilities outside the construction area. The contractor has applied dust control measures: covered truck transporting construction material; surrounded construction site by a fence. The work generating big noise is implemented at daylight hours only. Oil and fuel from machinery was collected and disposed to Son Tay landfill, which is licensed site for solid waste treatment/disposal. All fuel storage areas were securely fenced and provided with oil and water separators. All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to Son Tay landfill. The workers are supplied on-site with potable water Phu Nghia substation and connecting line 22. Sites are located inside the subproject area so that they do not interfere with the welfare or social cohesion of surrounding communities. There is no clearance of vegetation and other facilities outside the construction. Contractor s storage facilities have been surrounded by a security fence. Excavated material is disposed of outside and away from the work area to Xuan Son licensed landfill site. The contractor has applied dust control measures: covered truck transporting construction material; made fence surrounding construction site; covered construction material piles etc. The work generating big noise is implemented at daylight hours only. It is expected that an amount of construction wastewater of m 3 /day is generated from construction of Phu Nghia substation. Construction wastewater is preliminary treated by the sediment hole before discharging into surrounding water bodies. The wastewater quantity is small, the negative impact is negligible. Oil and fuel from machinery was collected and disposed to Xuan Son licensed and regulated site; All fuel storage areas were securely fenced and provided with oil and water separators. 23. Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to Xuan Son licensed landfills 24. Contractor has provided workers safety equipment potable water, sanitary toilet, washing and showering facilities, medical and first aid facilities. Regarding the community/worker health and safety, warning signs and barriers around work areas were erected. Site could only be accessed with permission of contractor. Visitors were warned against site hazards to avoid possible accident. Workers have been educated on the social problems and measures of preventing HIV/AIDS Thuong Tin-Thanh Oai Transmission Line 25. Sites are located in the rice field so that they do not interfere with the welfare or social cohesion of surrounding communities. The contractor has applied dust control measures: covered truck transporting construction material. The work generating big noise is implemented at daylight hours only. Construction wastewater is preliminary treated by sedimentation in the excavated hole before being pumped to surrounding rice field. However, the wastewater quantity is small, and the receiving water bodies are rice field that does not require high water quality standard. Therefore, the negative impact is negligible. All waste oil and oil filters were collected and if possible recycled, otherwise to be disposed to the regulated area. No solid waste is disposed at the surrounding area. All fuel storage areas were securely fenced and provided with oil and water separators. Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 26

27 26. Contractor has provided workers with safety working environment, No drugs or alcohol on-site. Before construction, workers need to be introduced and explained site safety procedures. Regarding the community/worker health and safety, site could only be accessed with permission of contractor. Visitors were warned against site hazards to avoid possible accident. Workers have been educated on the social problems and measures of preventing HIV/AIDS Expansion of Thuong Dinh 110KV substation 27. Thuong Dinh substation is expanded on part of Thuong Dinh warehouse that is managed by National Power Transmission Corporation. Warning signs and barriers around work areas were erected. Site could only be accessed with permission of contractor. The construction activities are conducted inside the Thuong Dinh warehouse area. Thus, the environmental impact, such as, dust and noise to residential areas is negligible. Building materials are gathered in the substation area, therefore it does not create dust and does not make traffic obstructs. The excavated area was limited to the area needed for construction only. There is no clearance of vegetation and other facilities outside the construction area. The contractor has applied dust control measures: covered truck transporting construction material; surrounded construction site by a fence. The work generating big noise is implemented at daylight hours only. Oil and fuel from machinery was collected and disposed to Xuan Son landfill, which is licensed site for solid waste treatment/disposal. All fuel storage areas were securely fenced and provided with oil and water separators. All waste oil and oil filters were collected and if possible recycled, otherwise to be disposed at specific area for hazardous waste treatment and disposal in Xuan Son landfill. The workers are supplied on-site with potable water Connecting line to 220 kv Son Tay Substation 28. The 110kV connection line starts from the 110kV bay of the 220 kv Son Tay SS and terminate at the separated connection of the existing 110 kv TLs. The connection line traverses Thanh My and Xuan Son communes of Son Tay Town, and mainly passes through paddy fields, rain-fed crop growing area, and low hills in line with the master plan of the satellite urban area of Son Tay. The contractor has applied dust control measures: covered truck transporting construction material. The work generating big noise is implemented at daylight hours only. Construction wastewater is preliminary treated by sedimentation in the excavated hole before being pumped to surrounding rice field. However, the wastewater quantity is small, and the receiving water bodies are rice field that does not require high water quality standard. Therefore, the negative impact is negligible. All waste oil and oil filters were collected and if possible recycled, otherwise to be disposed to the regulated area. No solid waste is disposed at the surrounding area. All fuel storage areas were securely fenced and provided with oil and water separators. Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 29. Contractor has provided workers with safety working environment, No drugs or alcohol on-site. Before construction, workers were introduced and explained site safety procedures. Regarding the community/worker health and safety, site could only be accessed with permission of contractor. Visitors were warned against site hazards to avoid possible accident. Workers have been educated on the social problems and measures of preventing HIV/AIDS. 5.2 Main findings from site visit 30. During this report period, PIC conducted site visit on 14 April 2017 to random check performance of contractors on the site of all five subprojects under construction: i) Rehabilitation of Son Tay 110KV substation-e1.7; ii) Phu Nghia 110KV substation and 110KV line; and iii) Construction of 110kV line from Thuong Tin 500 / 220kV substation supplying electricity to Thanh Oai 110kV, iv) Expansion of Thuong Dinh S/S (110kV) - E1.5, v) 110kV line to 220kV Son Tay S/S. 31. The main findings from site visit could be summarized as below: Rehabilitation of Son Tay 110KV substation The good points: 27

28 - Son Tay substation has been nearly completed. The machine installation activities are conducted inside the substation area. Thus, the environmental impact, such as dust and noise to residential areas is negligible. The equipment area is surrounded by safety string to warn outside people enter the dangerous area (Appendix B -Photo 1) - The safety regulation board is in place (Appendix B -Photo 2) - The washing/bathing place for workers is quite neatly (Appendix B -Photo 4) - No complaints from surrounding residents about the environmental problems caused by the project Problems to overcome On site - Water stagnant at a road section; construction of cable trench is not done section by section. This can cause dust generation and run-off with soil particles (Appendix B -Photo 5) - Some workers are not using personal protective equipment while working (Appendix B -Photo 6) Worker camps - Temporary accommodation of workers is not tidy. Kitchen area is not hygienic. - Garbage is collected but disposed directly into the surrounding area (Appendix B -Photo 7) - Temporary toilet is placed near the kitchen without solid door. Around the toilet there is a lot of solid waste (Appendix B -Photo 8) Phu Nghia substation and connecting line The good points: - The working safety regulations are illustrated in the working safety board and substation is surrounded by high wall with the sign to prohibit local people entering the substation s construction site (Appendix B -Photo 9 and 10) - Building materials are gathered inside the construction area, therefore no dust and traffic obstructs are generated (Appendix B -Photo 11) - No complaints from surrounding residents about the environmental problems caused by the subproject Points to overcome - An uncompleted trench without cover could cause accident at nigh time (Appendix B -Photo 12) - Workers not fully use personal protective equipment while working (Appendix B -Photo 13, 14) Thuong Tin-Thanh Oai 210 KV transmission line The good points: - The tower foundations are constructed on the rice field. No residential area at distance 500m from the tower excavation. The environmental impacts on the communities such as dust, noise, water are negligible. - No complaints from surrounding residents about the environmental problems caused by the subproject Points to overcome - The earth filled tower foundation is not properly compacted. This can cause soil erosion after heavy rain (Appendix B -Photo 15) - Solid waste is still remained at construction site (Appendix B -Photo 16) Expansion of Thuong Dinh S/S (110kV) - E1.5 The good points: - Workers camps are built in the premises of the transformer station, kitchen is relatively clean. - No complaints from surrounding residents about the environmental problems caused by the subproject 28

29 Points to overcome - The solid waste is not collected and disposal properly kV line to 220kV Son Tay S/S The good points: - Workers rent houses at the surrounding area, no wastewater and solid waste is discharged into the surrounding environment. - No complaints from surrounding residents about the environmental problems caused by the subproject Points to overcome - Workers not fully use personal protective equipment while working 5.3 EMP Performance Status 32. The EMP compliance monitoring results based on the reviewing of CSC site inspection forms (see annex C) and site inspection of Hanoi DPMB and PIC is summarized in Table 8. 29

30 Table 8: EMP Compliance Status of Ongoing Civil Work Packages EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay Establishment of contractor s facilities (camps, offices, quarries, concrete batching areas etc.). Demarcation and clearing of RoW and ancillary facilities 3: Medium - Son Tay substation is built in a closed area with surrounding wall. The construction activities are conducted inside the substation area. Thus, the environmental impact, such as dust, noise to residential areas is negligible - Building materials are gathered in the substation area, therefore it does not create dust and do not make traffic obstructs - [Not improved from the previous monitoring period] The workers camp is not tidy. Kitchen is not hygienic. 1: Very good - The subproject site is bounded by fence. No clearance of vegetation and other facilities is needed. 1: Very Good - Sites are located inside the subproject area so that they do not interfere with the welfare or social cohesion of surrounding communities. - Contractor s storage facilities are surrounded by a security fence. 3: Medium - The subproject site is bounded by high wall. - An uncompleted trench without cover could cause accident at nigh time 1: Very Good - Sites are located the rice field so that they do not interfere with the welfare or social cohesion of surrounding communities. 1: Very Good - Vegetation has been cleared at the excavated tower foundation only, Therefore the vegetation at other non- 2: Good - Thuong Dinh substation is expanded on part of Thuong Dinh warehouse. The construction activities are conducted inside the Thuong Dinh warehouse area. Thus, the environmental impact, such as dust, noise to residential areas is negligible - Building materials are gathered in the substation area, therefore it does not create dust and do not make traffic obstructs - The workers camp is quite tidy. They buy lunch and use the toilet of existing substation so the domestic waste is not much. 1: Very good The subproject site is bounded by fence. No clearance of vegetation and other facilities is needed. 1: Very Good - Sites are located the rice field so that they do not interfere with the welfare or social cohesion of surrounding communities. 2: Good Vegetation has been cleared at the excavated tower foundation only, Therefore the vegetation at other non-construction place is protected 30

31 EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay Preparation of site: excavation, removal and disposal of unusable (incompetent) materials Dust management Noise and vibration 1: Very good - The excavated area was limited to the area needed for construction only. - Excavated material was stored at construction site then being transported and disposed at Xuan Son licensed landfill. 3: Medium - The contractor has applied dust control measures: covered truck transporting construction material; made fence surrounding construction site; - Construction of cable trench is not done section by section. This can cause dust generation and run-off with soil particles 1: Very good - The work generating big noise is implemented at daylight hours only. - No clearance of vegetation and other facilities is needed. 1: Very good - The excavated area was limited to the area needed for construction only. - Excavated material was stored at construction site then being transported and disposed at Xuan Son licensed landfill. 1: Very good - The contractor has applied dust control measures: covered truck transporting construction material; made fence surrounding construction site; covered construction material piles etc. 1: Very good - The work generating big noise is implemented at daylight hours only. construction place is protected 1: Very good - The excavated area was limited to the area needed for construction only. 2: Good - The contractor has applied dust control measures: covered truck transporting construction material; - However, the filled soil at tower foundation was not properly compacted. This would generate dust when strong wind blows 1: Very good - The work generating big noise is implemented at daylight hours only. 1: Very good - The excavated area was limited to the area needed for construction only. - Excavated material was stored at construction site then being transported and disposed at Xuan Son licensed landfill. 1: Very Good - The contractor has applied dust control measures: covered truck transporting construction material; made surrounding construction site; fence 1: Very good - The work generating big noise is implemented at daylight hours only. 1: Very good - The excavated area was limited to the area needed for construction only. - Excavated material was stored at construction site then being transported and disposed at Xuan Son licensed landfill. 2: Good - The contractor has applied dust control measures: covered truck transporting construction material; - However, the filled soil at tower foundation was not properly compacted. This would generate dust when strong wind blows 1: Very good - The work generating big noise is implemented at daylight hours only. 31

32 EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay Waste water from construction site Waste water from worker camps - Noise is managed not to exceed 55dBA at boundary of any residential area between 6hr and 21h00 and 45 dba between 21h00 and 06h00; 1: Very Good - No wastewater generated at the construction site. - Oil and fuel from machinery was collected and disposed to Xuan Son landfill site. 4: Weak - [Not improved from the previous monitoring period] Temporary toilet is placed near the kitchen. Wastewater (estimated about 2.4 m 3 /day from 30 workers) is not preliminary treated before disposed to - Noise is managed not to exceed 55dBA at boundary of any residential area between 6hr and 21h00 and 45 dba between 21h00 and 06h00; 1: Very Good m 3 /day of construction wastewater is generated from construction of Phu Nghia substation. Construction wastewater is preliminary treated by the sediment hole before discharging into surrounding water bodies - Oil and fuel from machinery was collected and disposed to Xuan Son landfill site 1: Very Good - Wastewater is preliminary treated by settling chamber. The wastewater quantity is small (about 2.4 m 3 /day from 30 workers; source: IEE), the negative impact is negligible. - Noise was managed not to exceed 55dBA at boundary of any residential area between 6hr and 21h00 and 45 dba between 21h00 and 06h00; 1: Very Good - Construction wastewater is preliminary treated by sedimentation in the excavated hole before being pumped to surrounding rice field. - Oil and fuel from machinery was collected and disposed to Xuan Son landfill site. 1: Very Good - Wastewater is preliminary treated by wastewater treatment system (septic tanks) before discharging into water bodies. The wastewater quantity is small (about 2.6 m 3 /day from 40 workers; source: IEE), the Noise is managed not to exceed 55dBA at boundary of any residential area between 6hr and 21h00 and 45 dba between 21h00 and 06h00; 1: Very Good - No wastewater generated at the construction site. Oil and fuel from machinery was collected and disposed to Xuan Son landfill site. 2: Good - Workers use the toilet of existing substation and not cooking meal so the waste water is collected to the existing drain system of substation. Noise was managed not to exceed 55dBA at boundary of any residential area between 6hr and 21h00 and 45 dba between 21h00 and 06h00; 1: Very Good - Construction wastewater is preliminary treated by sedimentation in the excavated hole before being pumped to surrounding rice field. Oil and fuel from machinery was collected and disposed to Xuan Son landfill site. 1: Very Good - Wastewater is preliminary treated by wastewater treatment system (septic tanks) before discharging into water bodies. The wastewater quantity is small (about 2.6 m 3 /day from 40 workers; source: IEE), the 32

33 EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay surrounding bodies. water negative impact is negligible. - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills negative impact is negligible. - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills Prevention of soil erosion on construction site. 1: Very Good No soil erosion occurred 1: Very good No soil erosion occurred 4: Week Soil erosion may occur from improperly compacted tower foundation 1: Very Good No soil erosion occurred 1: Very Good No soil erosion occurred Disposal of domestic solid waste 3. Medium [Not improved from the previous monitoring period] Domestic solid waste is not collected and disposed properly 3: Medium [Not improved from the previous monitoring period] Domestic solid waste is collected but disposed directly into the surrounding area 3: Medium Solid waste is disposed at the surrounding area. 3. Medium Domestic solid waste is not collected and disposed properly 1: Very Good Domestic solid waste is collected and disposed properly. Storage and handling of fuel and lubricants 1: Very Good - All fuel storage areas were securely fenced and provided with oil and water separators. Fuel hoses and shut off valve to be locked. - Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 1: Very Good - All fuel storage areas were securely fenced and provided with oil and water separators. Fuel hoses and shut off valve to be locked. - Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 1: Very Good - All fuel storage areas were securely fenced and provided with oil and water separators. Fuel hoses and shut off valve to be locked. - Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 1: Very Good - All fuel storage areas were securely fenced and provided with oil and water separators. Fuel hoses and shut off valve to be locked. - Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 1: Very Good - All fuel storage areas were securely fenced and provided with oil and water separators. Fuel hoses and shut off valve to be locked. - Fuel was stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. 33

34 EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay Workplace health and safety - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills 3: Medium - Contractor has abided: Vietnamese Labor Code as amended 2002 as follow: - Provided workers be with safety working environment - [Not improved from the previous monitoring period] However, some workers are not using personal protective equipment while working - Not allow drugs or alcohol on-site; - The workers are provided on-site with Potable water for drinking - Prepared work safety regulation for each activity - Before execution, workers are introduced and explained site safety procedures. - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills 3: Medium - Contractor has abided: Vietnamese Labor Code as amended 2002 as follow: - Provided workers be with safety working environment - Erect warning signs and barriers around work areas - Not allow drugs or alcohol on-site; - Control noise and dust provided all workers with safety equipment appropriate for the task they are employed. - The workers are supplied on-site with: Potable water for drinking, sanitary toilet, washing and showering facilities. - Prepared work safety regulation for each activity - Before execution, workers need to be - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills 3: Medium - Contractor has abided Vietnamese Labor Code as amended 2002 as follow: - Provided workers be with safety working environment - Not allow drugs or alcohol on-site; - Before execution, workers were introduced and explained site safety procedures. - However, some workers do not wear safety equipment appropriate for the task they are employed. - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills 1: Very Good - Contractor has abided: Vietnamese Labor Code as amended 2002 as follow: - Provided workers be with safety working environment - Not allow drugs or alcohol on-site; - The workers are provided on-site with Potable water for drinking - Prepared work safety regulation for each activity - Before execution, workers are introduced and explained site safety procedures. - Provided medical and first aid facilities together with a person qualified in first aid. - All waste oil and oil filters was collected and if possible recycled, otherwise to be disposed of to landfills 3: Medium - Contractor has abided Vietnamese Labor Code as amended 2002 as follow: - Provided workers be with safety working environment - However, workers did not fully use personal protective equipment while working - Not allow drugs or alcohol on-site; - Before execution, workers were introduced and explained site safety procedures. 34

35 EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay - Provided medical and first aid facilities together with a person qualified in first aid. introduced and explained site safety procedures. - Provided medical and first aid facilities together with a person qualified in first aid. - However, some workers do not wear safety equipment appropriate for the task they are employed. - An uncompleted trench without cover could cause accident at night time Chance discovery of archaeological and cultural sites No chance of discovery of archaeological and cultural sites. No chance of discovery of archaeological and cultural sites. No chance of discovery of archaeological and cultural sites. No chance of discovery of archaeological and cultural sites. No chance of discovery of archaeological and cultural sites. Public access to site 1: Very Good - Warning signs and barriers around work areas were erected. - Site could only be accessed with permission of contractor. - Visitors were warned against site hazards to avoid possible accident 1: Very Good - Warning signs and barriers around work areas were erected. - Site could only be accessed with permission of contractor. - Visitors were warned against site hazards to avoid possible accident 1: Very Good - Site could only be accessed with permission of contractor. - Visitors were warned against site hazards to avoid possible accident 1: Very Good - Warning signs and barriers around work areas were erected. - Site could only be accessed with permission of contractor. Visitors were warned against site hazards to avoid possible accident 1: Very Good - Site could only be accessed with permission of contractor. Visitors were warned against site hazards to avoid possible accident 35

36 EMP Requirements Rehabilitation of Son Tay 110KV substation Phu Nghia substation and connecting line Compliance Attained Thuong Tin-Thanh Oai Transmission line Thuong Dinh Substation Connecting line to 220 kv Son Tay Community and worker health and safety 3: Medium - No issue with Community health and safety - [Not improved from the previous monitoring period] However, the toilet, washing and showering facilities for workers are very poor. 3: Medium - Workers have been educated on the social problems. and measures of preventing HIV/AIDS; - Workers are provided, safe water and hygienic bathing and cooking; - First aid, medicines are available at site and camps for workers; - Workers have not fully use labor protecting equipment and wear them during working time 3: Medium - Workers have been educated on the social problems. and measures of preventing HIV/AIDS; - First aid, medicines are available at site and camps for workers; - [Not improved from the previous monitoring period] The safety tape should be hang around the holes dug for tower foundation to prevent people fall into a pit at night 2: Good - No issue with Community health and safety. The toilet, washing and showering facilities for workers are in place from existing substation. 3: Medium - Workers have been educated on the social problems. and measures of preventing HIV/AIDS; - First aid, medicines are available at site and camps for workers; - The safety tape should be hang around the holes dug for tower foundation to prevent people fall into a pit at night 36

37 6 Summary of Environmental Mitigations and Compensation Measures Implemented during the Operation Phase The High Voltage Grid Company under EVN Hanoi, that manages operation of substations and transmission lines, is conducting the environmental monitoring on hazardous solid waste, accident cases, health and safety. The monitoring results are submitted to DONRE and kept at the office for occasional inspection by DONRE. The summary of the monitoring results is in Table 9. Table 9: EMP Compliance Status of Completed Subprojects No. EMP Requirement Noi Bai ss Mo Lao ss Chem-Tay Ho ss Thanh Xuan ss Came into operation April 2016 June 2016 August 2015 June 2016 in: 1 Occupational health and safety regulations and guidelines of MoLISA should be applied to operations of substation or transmission line Ensure substation pr operty is adequately fenced with clearly visable danger warning signs to keep public out. Ensure transmission line towers are marked with clearly visable danger warning signs to keep public out. (For substation) Store and handle transformer fluids and other hazardous materials according to international procedures and standards The substation under control of High Voltage Grid Company, under EVN HANOI. All the workers carry out the control of substation and transmission line are use safety equipment during working hours, thus no accident occurred during operating phase. All gates of substation always be lock, to ensure no outside come in without allowance of substation s caption. Guest can go in substation only if they were training on electricity safety process of EVN HANOI. The substation under control of High Voltage Grid Company, under EVN HANOI. All the workers carry out the control of substation and transmission line are use safety equipment during working hours, thus no accident occurred during operating phase. All gates of substation always be lock, to ensure no outside come in without allowance of substation s caption. Guest can go in substation only if they were training on electricity safety process of EVN HANOI. The transmission line under control of High Voltage Grid Company, under EVN HANOI. All the workers carry out the control of transmission line are use safety equipment during working hours, thus no accident occurred during operating phase. The substation under control of High Voltage Grid Company, under EVN HANOI. All the workers carry out the control of substation and transmission line are use safety equipment during working hours, thus no accident occurred during operating phase. N/A to transmission line All gates of substation always be lock, to ensure no outside come in without allowance of substation s caption. Guest can go in substation only if they were training on electricity safety process of EVN HANOI. N/A to substation N/A to substation Transmission line towers are marked with clearly visible danger warning signs to keep public out. All hazardous waste during operating of substation has been storing in enclose room and they will transmission to hazardous license land fill. All hazardous waste during operating of substation has been storing in enclose room and they will transmission to hazardous license land fill. N /A to substation N/A to transmission line All hazardous waste during operating of substation has been storing in enclose room and they will transmission to hazardous license land fill. 37

38 7 SUMMARY OF ENVIRONMENTAL EFFECT MONITORING 7.1 Monitoring location and frequency 33. Environmental effect monitoring should be conducted in line with the national regulation and as required in IEE. The required monitoring aspects are: noise and air quality (for all 5 subprojects), surface water quality (for 4 subprojects, except rehabilitation of Son Tay 110KV substation) and soil quality (only for two subprojects Rehabilitation of Son Tay 110KV substation and Thuong Tin - Thanh Oai transmission line). The requirement of environmental effect monitoring stated in IEEs of 5 ongoing subprojects are summarised in Table Three subprojects namely (Rehabilitation of Son Tay 110KV substation, Phu Nghia substation and connecting line, and Thuong Dinh Substation) have conducted monitoring during construction phase until operation phase at 2017 Q1 and Q However, for Thuong Tin- Thanh Oai, environmental effect monitoring was not conducted during the construction stage (from September 16 and ended in April 2017), but only for one time in 2017 Q2 during the operation stage, because tower foundations are installed mainly at agricultural land where now residential area is located and no water sources exist nearby. In addition, the construction time of each tower is short (about one month), thus the environmental impact on each tower location is negligible. After first environmental effect monitoring as required by Vietnamese regulation (frequency of one time during construction phase) contractors stopped conducting monitoring since budget located for environmental effect monitoring is based on Government requirement only. 36. The environmental effect monitoring is not required for Son Tay TL subproject, so this one was conducted one time only during pre-construction phase. 37., and the status of environmental monitoring analysis of each subproject is summarized in Table

39 Environmental aspects/ monitoring frequency Noise and Air quality Affected surface water quality Analysis of contaminated soil quality Table 10: Environmental Effect Monitoring parameters, location and frequency of 5 subprojects stated in IEEs Rehabilitation of Son Phu Nghia substation Thuong Tin - Thanh Oai Connecting line to Thuong Dinh SS Tay 110KV substation and connecting line transmission line 110kW Son Tay SS Dust, CO, NOx, SOx, Dust, CO, NOx, SO2, dust, CO, NOx, SOx, dust, CO, NOx, SOx, dust, noise (by visual Parameter noise - Noise noise noise observation) Location At substation site At SS site and TL At TL site (14 locations) At substation site At TL site Quarterly during Quarterly during Quarterly during Quarterly during Quarterly during Frequency construction periods construction periods construction periods construction periods construction periods TSS, oil and TSS, oil and grease, BOD5, TDS, grease, BOD5, TDS, Parameter Not required TSS, oil and grease TP, TN (by visual TP, TN (by visual observation) observation) Location Frequency Parameter Location Frequency Heavy metals (As, Cd, Pb) Area surrounding substation Once time at start of excavations construction sites including worker camps Monthly Not required At TL site (8 locations) Quarterly during construction periods (heavy metals (As, Cd, Pb, Hg, Mn), hydrocarbons At sites where contaminated soil is suspected Quarterly during construction periods TSS, oil and grease, BOD5, TDS, TP, TN (by visual observation) Not required construction sites including worker camps Monthly Not required 39

40 Core subprojects New development of Noi Bai Airport 110kV Substation and associated 110 kv line Table 11: Status of Environmental Monitoring Analysis 2015 Q Q2 Done on 15 June 2015 Q3 Done on 14 Sep 2015 Q4 Done on 21 Dec 2016 Q1 Done on 11 March 2016 Q2 Operation (from Apr) 2016 Q Q Q Q2 Operating Operating Operating Operating Rehabilitation of Son Tay 110KV substation Not yet due Not Not Done on 13 Conducted Conducted March Rehabilitation and upgrading of E12 Tran Hung Dao 110 kv Substation Rehabilitation and upgrading of E13 Phuong Liet 110 kv Substation None Core Chem - Tay Ho 220kV transmission line Not yet due Done on 19 Jun Operation (from Aug) Operation (from June) Operating Operating Operating Operating Operating Operating Operating 110 kv Mo Lao Substation and connection line Not yet due Done on 13 Done on 10 Mar Jun 3 Operating Operating Operating Operating 110 kv Tay Ho Tay SS and connection line Increasing capacity of T2 transformer, rehabilitation of 110 kv bay- Tia substation E Installation of new transformer T3, E1.20 Thanh Xuan 110 kv SS Not yet due Done on 11 Mar Expansion of E5 110 kv Thuong Dinh SS Not yet due Done on 9 Jun Operating Operating Operating Operating Done on 13 Mar Done on 10 Jan Phu Nghia substation and connecting line Not yet due Not Conducted New development of 110 kv Ba Vi SS kv Tay Ho - Yen Phu Underground Cable Line (UGC) New development of 110 kv Phung Town SS and connecting line New development of 110 kv Ngoc Hoi SS and connecting line kv Thanh Cong Thuong Dinh UGC Done on 12 July Done on 12 Apr 110 kv transmission line from 500/220 kv Thuong Tin SS to Thanh Oai Not yet due Not Not Done on 12, Conducted Conducted 25 Jul Connecting line to 220 kv Son Tay SS Not required Not required 110 kv Transmission line from 500 kv Thuong Tin SS to E1.34 Quat Dong and E10.4 Tia substations New development of 110 kv Chuong My (1x40 MVA) SS and 110 kv Thanh Oai- Chuong My transmission line kv Bac An Khanh-Nam An Khanh Transmission line New development of 110 kv Sai Dong 2 (Industrial park Sai Dong) SS kv Connecting line to Sai Dong Upgrading of E10.7 Thach That 110 kv SS The IEE requires quarterly monitoring of noise, ambient air quality, surface water quality and soil quality (Table 11), however, only surface water quality was monitored in this period. 40

41 7.2 Applicable Standards Ambient air quality standard 38. The permitted values for air parameters, National technical regulation on ambient air quality QCVN 05:2009/BTNMT, are presented in Table 12. Table 12: Ambient Air quality standard No. Parameters Unit Standard QCVN 05:2009 BTNMT (per hour) Remark 1 TSP g/m Carbon Monoxide (CO) g/m Sulfur Dioxide (SO2) g/m Nitrogen Dioxide (NO2) g/m NOx g/m VOC g/m 3-7 PM10 dust g/m 3-8 Noise dba 70 QCVN 26:2010/BTNMT 9 Low frequency vibrant m/s QCVN 27:2010/BTNMT 10 Hight frequency vibrant m/s 2-11 Electric field A/m Waste water quality standard 39. National technical regulation on waste water quality QCVN 14:2008 BTNMT, 40:2011/BTNMT column B quality was applied for determining general waste water quality. The permitted values for wastewater parameters are presented in Table 13. Table 13: Waste water quality standard No. Parameters Unit Standard QCVN 14:2008 BTNMT, 40:2011/BTNMT column B 1 TSS g/m Chemical Oxygen Demand (COD) mg/l Biological Oxygen Demand (BOD5) mg/l 50 4 Total N mg/l 40 5 Total P mg/l 6 6 Total Coliform MPN/100ml Surface water quality standard 40. National technical regulation on surface water quality QCVN 08:2015/BTNMT was applied for determining general surface water quality. The permitted values are presented in Table 14. Table 14: Surface water quality standard No. Parameters Unit Standard QCVN 08:2015 BTNMT column B1, 03:2008/BTNMT 1 Dissolved Oxygen (DO) mg/l 4 2 TSS g/m COD mg/l 50 4 BOD5 mg/l 15 5 Conductivity S/m - 6 Iron (Fe) mg/l Zine (Zn) mg/l Arsenie (As) mg/kg dry soil Cadimium (Cd) mg/l

42 No. Parameters Unit Standard QCVN 08:2015 BTNMT column B1, 03:2008/BTNMT 10 Lead (Pb) mg/kg dry soil Crom (Cr) mg/kg dry soil Clo (Cl) mg/l Oil and Grease mg/l 1 14 Total Coliform MPN/100ml Soil quality standard 41. National technical regulation on soil quality QCVN 03MT:2015/ BTNMT is in Table 15. Table 15: Soil quality standard No. Parameters Unit Standard QCVN 03MT:2015/ BTNMT 1 Arsenic (As) mg/kg dry soil 15 2 Copper (Cu) mg/kg dry soil Zn mg/kg dry soil Cadmium (Cd) mg/kg dry soil 2 5 Lead (Pb) mg/kg dry soil Monitoring result Ambient air quality Rehabilitation of Son Tay 110KV substation 42. Environmental effect monitoring should have been conducted quarterly since May 2016 when the construction work started, however, sampling was taken only on 13 March 2017 so far. The monitored parameters are: Carbon Monoxide (CO); Sulphur Dioxide (SO2); CO2; NOx; PM10 dust; Noise, Low frequency vibrant; Electromagnetic field; TSP, in front of control centre. The monitoring results (Table 16) showed that all monitored air parameters are under allowable limits. Table 16: Monitoring result for air quality of Rehabilitation of Son Tay 110kV substation (Q1 2017) Parameter Monitoring Result QCVN 05 :2013 BTNMT 1. Carbon Monoxide (CO) , Sulfur6Dioxide (SO2) NOx PM10 dust Noise QCVN 26:2010/BTNMT 6. Low frequency vibrant QCVN 27:2010/BTNMT Phu Nghia substation and connecting line 43. Sampling for environmental effect monitoring was taken quarterly as requirement in IEE, on 10 January 2017 and 12 April The monitored parameters are: Carbon Monoxide (CO); Sulphur Dioxide (SO2); CO2; NOx; PM10 dust; Noise, Low frequency vibrant; Electromagnetic field; TSP at 4 locations (KK1, KK2, KK3, KK4) listed in Table 17, and Figure 2. The monitoring results (Table 18) showed that all monitored air parameters are under allowable limits. Table 17: Location of air quality monitoring of Phu Nghia substation and connecting line No. Locations KK1 At 220kV Xuan Mai substation KK2 Safety corridor of over head line at Dong Phuong Yen commune, Chuong My district KK3 Dam of Tich river, Can Huu commune, Quoc Oai district KK4 Worker camp of Phu Nghia 110kV substation 42

43 Figure 2: Location of air quality monitoring of Phu Nghia substation and connecting line Table 18: Monitoring result for air quality of Phu Nghia substation and connecting line Locations No QCVN 05 :2013 Parameter KK1 KK2 KK3 KK4. BTNMT Q 1 / 1 7 Q2/17 Q1/17 Q2/17 Q1/17 Q 2 / 1 7 Q1/17 Q2/17 1. Carbon Monoxide (CO)- 12,50 15,50 18,80 12,80 18,20 15,60 11,30 8,900 (µg/m 3 ) , Sulfur6Dioxide (SO2)- (µg/m 3 ) NOx- (µg/m 3 ) PM10 dust- (µg/m 3 ) Noise -DcB QCVN 26:2010/BTNMT 6. Low frequency vibrant -DcB QCVN 27:2010/BTNMT Thuong Tin- Thanh Oai 110kV Transmission line 44. Ambient air quality monitoring should have been conducted quarterly since September 2016 when the construction work started, however, there is only one sample was conducted on 25 July 2017 during the operation stage (cf. paragraph 38). The 14 monitored locations are listed in Table 19 and Figure 3. The monitoring results (Table 20) showed that all monitored air parameters are under allowable limits. Table 19: Location of air quality monitoring of Thuong Tin- Thanh Oai transmission line No. K1 K2 K3 K4 K5 Locations At start point of transmission line at Thuong Tin 500kV substation Near electrical pole G01 Near National Mental Hospital No1 At Tien Phong trade village, Tien Phong commune Nam Vang Ltd, Co, Tien Phong commune 43

44 No. K6 K7 K8 K9 K10 K11 K12 K13 K14 Locations Lang hamlet, Tien Phong commune Rice field at Du Du 1 hamlet, Thanh Thuy commune Near electrical pole G06, Tam Da hamlet, Thanh Van commune Near electrical pole G07, Quan Nhan hamlet, Thanh Van commune Near electrical pole G08, Bui Xa hamlet, Thanh Van commune Near water pumping substation on the Hoa Binh river, Kim Bai town Near electrical pole G09 Near electrical pole G10 West of Thanh Oai substation Figure 3: Location of air quality monitoring of Thuong Tin- Thanh Oai transmission line Table 20: Monitoring result for air quality of Thuong Tin- Thanh Oai 110kV Transmission Line (Q2 2017) No. Parameter Locations QCVN 05 :2013 K1 K2 K3 K4 K5 K6 K7 K8 K9 K10 K11 K12 K13 K14 BTNMT 1. Carbon Monoxide (CO)- 4,6 4,5 5,2 5,5 5,9 5,7 5,2 4,8 4,5 4,4 5,2 4,9 5,5 5,1 (µg/m 3 ) , Sulfur6Dioxide (SO2)- (µg/m 3 ) NOx-(µg/m 3 ) Noise -DcB QCVN 26:2010/BTNMT Expansion of Thuong Dinh 110KV substation 45. Sampling for environmental effect monitoring was taken quarterly (on 13 Mar 2017 and 12 July 2017) at the substation site in accordance with the IEE. The monitoring results (Table 21) showed that all monitored air parameters are under allowable limits. 44

45 Table 21: Air quality Monitoring result for Expansion of Thuong Dinh 110kV substation (Q1, Q2 2017) No. Parameter Q1/2017 Q2/2017 QCVN 05 :2013 BTNMT 1. Carbon Monoxide (CO) (µg/m 3 ) 18,000 15,900 30, Sulfur6Dioxide (SO2) (µg/m 3 ) NOx (µg/m 3 ) PM10 dust- (µg/m 3 ) Noise QCVN 26:2010/BTNMT 6. Low frequency vibrant QCVN 27:2010/BTNMT Locations in front of expansion control centre Connecting line to 220 kv Son Tay Substation The dust and noise parameters have been monitored during quarter 1 and by visual observation. The result showed no sign of dust and noise is at acceptable level Surface water quality 46. During this monitoring period (January June 2017), environmental effect monitoring of surface water is required for one subproject: Thuong Tin - Thanh Oai transmission line only (Table 10) Phu Nghia substation and connecting line 47. Surface water quality monitoring has been conducted monthly since January 2017, though only visual observation is required by the IEE. The monitored parameters are: Total suspended Solid (TSS); Chemical Oxygen Demand (COD); Iron (Fe); Zinc (Zn); Arsenic (As); Oil and Grease; at Cuu Khe canal near Phu Nghia substation. The monitoring results (Table 22) showed that all monitored surface water parameters are under the allowable limits. Table 22: Monitoring result for surface water quality of Phu Nghia substation (Monthly 2017) No Parameters Locations QCVN 08 Cuu Khe canal near Phu Nghia substation :2015/BTNMT (column Jan/17 Feb/17 Mar/17 Apr/17 May/17 Jun/17 B1),03:2008/BTNMT 1. COD TSS Fe Zn As Oil Thuong Tin - Thanh Oai transmission line 48. Surface quality monitoring should have been conducted quarterly since September 2016 when the construction work started, however, there is only one sample was conduct on 12 Sep 2017 during the operation stage (cf. paragraph 38) at 8 locations listed in Table 23 and Figure 4. The monitoring results (Table 23) showed that all monitored surface water parameters are under the allowable limits. Table 23: Location of surface water quality monitoring of Thuong Tin- Thanh Oai transmission line No. NM1 NM2 NM3 NM4 NM5 NM6 Locations At canal near Thuy Ung bridge, Van Phu commune Near Chiec bridge, cross Nhue river, Tien Phong commune Canal at Nhan Hien hamlet, Hien Giang commune Canal at Tam Da hamlet, Thanh Van commune Canal at Quan Nhan hamlet, Thanh Van commune Canal at Bui Xa hamlet, Tam Hung commune 45

46 NM7 NM8 Near Dia Muoi bridge, Hoa Binh river, Kim Bai town Phuong Vi river, East corner of Thanh Oai substation Figure 4: Location of surface water quality monitoring of Thuong Tin- Thanh Oai transmission line Table 24: Monitoring result for surface water quality of Thuong Tin- Thanh Oai transmission line (Q2 2017) N o Parameters Locations Cuu Khe canal near Phu Nghia substation QCVN 08 :2015/BTNM T (column B1),03:2008 /BTNMT NM1 NM2 NM3 NM4 NM5 NM6 NM7 NM8 1. COD TSS Fe Oil Soil quality Remark 49. During this monitoring period (January June 2017), environmental effect monitoring of soil quality was conducted for one subproject, which is rehabilitation of Son Tay 110KV substation Rehabilitation of Son Tay 110KV substation 50. The sample was taken on 27 March 2017 at substation construction site. The monitored parameters are: Arsenic (As); Cadmium (Cd); Lead (Pb). The monitoring results (Table 25) showed that all monitored soil parameters are under the allowable limits. Table 25: Monitoring result for soil quality of Son Tay 110kV substation No Parameters Monitoring Result QCVN 03MT:2015/BTNMT (agricultural land) 1. Arsenic (As) Cadmium (Cd) Lead (Pb)

47 8 Key Issues Identified 8.1 Issues identified between January and June It was found that the bidding document of five subprojects; (i) Rehabilitation of Son Tay 110KV substation; (ii) Phu Nghia substation and connecting line; (iii) Thuong Tin-Thanh Oai Transmission line; (iv) Expansion of 110kV Thuong Dinh substation E1.5; and (v) Son Tay 110kV transmission line did not specifically mention the requirement of environmental effect monitoring required by the IEEs. EVN HANOI issued official letter to the contractor on 19 December 2016 (Appendix D of the previous monitoring report 4 ), notified the contractors of the requirement, and requested them to conduct environmental effect monitoring accordingly. The Environmental effect monitoring in line with the national regulation EIA and the monitoring plan in each subproject IEE were conduct by every subproject, except Thuong Tin- Thanh Oai transmission line (Chapter 7.1). 52. The main points of environmental performance monitoring for the five subprojects are summarized as follows: Rehabilitation of Son Tay 110KV substation On site - Construction of cable trench is not done section by section. This can cause dust generation and run-off with soil particles - Water stagnant at a road section; construction of cable trench is not done section by section. This can cause dust generation and run-off with soil particles - [Not improved from the previous monitoring period] Some workers are not using personal protective equipment while working Worker camps - [Not improved from the previous monitoring period] Temporary toilet is placed near the kitchen. Wastewater (estimated about 2.4 m 3 /day from 30 workers) is not preliminary treated before disposed to surrounding water bodies; - [Not improved from the previous monitoring period] Domestic solid waste is not collected and disposed properly; - [Not improved from the previous monitoring period] The toilet, washing and showering facilities for workers are very poor Phu Nghia substation and connecting line - An uncompleted trench without cover could cause accident at nigh time - [Not improved from the previous monitoring period] Domestic solid waste is collected but disposed directly into the surrounding area - Workers not fully use personal protective equipment while working Thuong Tin - Thanh Oai transmission line - The filled soil at tower foundation was not properly compacted. This would generate dust when strong wind blows - Solid waste is disposed at the surrounding area - Some workers do not wear safety equipment appropriate for the task they are employed. - [Not improved from the previous monitoring period] The safety tape should be hang around the holes dug for tower foundation to prevent people fall into a pit at night Expansion of Thuong Dinh 110KV substation - Domestic solid waste is not collected and disposed properly

48 8.1.5 Connecting line to 220 kv Son Tay Substation - The filled soil at tower foundation was not properly compacted. This would generate dust when strong wind blows - Workers did not fully use personal protective equipment while working - The safety tape should be hang around the holes dug for tower foundation to prevent people fall into a pit at night 8.2 Issues from previous report (June-December 2016) 53. When the site visit was conducted on 17 November 2016 during the previous monitoring period, some environmental problems were identified, and it was found that EMP of subproject was not always followed. EVN HANOI issued an official letter to the contractors and CSCs on 26 November 2016 (Appendix D of this report), to remind contractors of the EMP requirements and request them to settle all backlog issues on each site, and give them one week to address all. After one week, the CSC at each site reported to Environment Officers of EVN HANOI all the last issues were solved. Then Environment Officers of EVN HANOI inspected sites and confirmed that. Table 26: Issues Identified during the previous monitoring period and solution Issues Location Targets/Solutions Issue Closed/problem solved Absence of environmental effect monitoring Rehabilitation of Son Tay 110KV substation; Phu Nghia substation and connecting line; Thuong Tin- Thanh Oai transmission line; Thuong Dinh Substation and Connecting line to 220kW Environmental effect monitoring conducted Second quarter 2017 Absence of environmental monitoring during the operation phase Son Tay substation 110 kv Mo Lao Substation and connection line Installation of new transformer T3, E1.20 Thanh Xuan 110 kv SS Rehabilitation of Son Tay 110KV substation The workers camp is not Worker camp tidy. Kitchen area has not been so hygienic. The soil pile next to the construction area was not covered. This would generate dust when strong wind blows Domestic solid waste is not collected and disposed properly The toilet, washing and showering facilities for workers are very poor. On site Worker camp Worker camp 48 Environmental monitoring conducted Workers camp and kitchen need to be clean up. Excavated soil need to be covered by plastic cloth before transporting to the disposal site Garbage need to be collected and transported to Xuan Son landfill The toilet, washing and showering facilities for Second quarter 2017 Confirmed to be solved in December However, workers do not clean the kitchen frequently, and the same problem was found again for several times. Confirmed to be solved in December However, the same problem was found again for several times. Confirmed to be solved solved in December However, the same problem was found again for several times. Confirmed to be solved in December 2016 except toilet door remained the same

49 Issues Location Targets/Solutions Issue Closed/problem solved workers should be upgraded to be more hygienic Some workers do not wear safety equipment appropriate for the task they are employed On site Phu Nghia substation and connecting line - The subproject On site information board has no phone number of the units involved or the hotline telephone number for people to contact if there are complaints, Workers should wear safety equipment The subproject information board should complement the phone number of the units involved or the hotline telephone number for people to contact if there are complaints, Confirmed to be solved in December 2016 Confirmed to be solved in November 2016 Kitchen area does not meet the requirements on environmental sanitation - Domestic solid waste is collected but disposed directly into the surrounding area The toilet, washing and showering facilities for workers are very poor. Worker camp On site and Worker camp Worker camp Thuong Tin-Thanh Oai transmission line The excavation area was not On site warning tape around to prevent workers from falling into the pit in the evening. Excavated material is placed On site around the excavated area which could fall into the excavated hole and generate dust The kitchen should be cleanup to meet hygienic condition Domestic solid waste should be collected and properly disposed The toilet, washing and showering facilities for workers should be upgraded to be more hygienic The warning tape need to be located around the hole dug at the construction site Excavated material should be stored tidily around the excavated area to avoid soil falling into the excavated hole and generating dust Confirmed to be solved in December 2016 Confirmed to be solved in December However, the same problem was found again for several times. Construction site was completed in December 2016 before the problem was solved. Construction site was completed in November 2016 before the site visit on 17 April It has been solved in November However, the same problem was found again for several times. Benton is tested on the soil ground. Some workers do not wear safety equipment appropriate for the task they are employed On site On site Benton should be tested on the container then brought out when finished. Do not through away into rice field Workers should wear safety facilities when working It has been solved in November 2016 It has been solved in November COMPLAINTS 54. No complaints regarding environmental issue in the period between July and December

50 10 CONCLUSION AND RECOMMENDATION 10.1 Conclusions 55. The compliance with requirements during construction phase is generally good. Almost all impact mitigation measures have been implemented. 56. The main environmental issues of the five subprojects are related to: - Hygienic condition of worker camp: Kitchen and toilet are not clean - Management of construction and domestic solid waste: domestic solid waste and construction solid waste were not properly collected and disposed - Workers use of working protective facilities - Protective measures for community safety. 57. These environmental issues occurred over the last 6 months (July-December 2016). When the site visit was conducted on 17 November 2016 during the previous monitoring period, some environmental problems were identified, and it was found that EMP of subproject was not always followed. EVN HANOI issued an official letter to the contractors and CSCs on 26 November 2016 (Appendix D of this report), to remind contractors of the EMP requirements and request them to settle all backlog issues on each site, and give them one week to address all. After one week, the CSC at each site reported to Environment Officers of EVN HANOI all the last issues were solved. Then Environment Officers of EVN HANOI inspected sites and confirmed that. 58. The environment issues were mitigated after inspection by Hanoi DPMB environmental staff and PIC. However, these problems continued to occur in this six months (Jan-June 2017) and are being remediated immediately after reminders of the environmental inspection team. 59. These problems continue to occur indicates the environment officers of EVN Hanoi did not inspect construction site frequently, and they, together with CSCs and EOs of constructors on each site, should enforce workers follow strictly the requirements of environmental protection. 60. All subprojects have no complaints from residents living surrounding the subproject area on the environment issues Recommendation 61. Based on the main environmental issues of the five subprojects stated in conclusion section and detailed in section 8 for each subproject, the corrective actions/solution as well as required closed date for each issue is presented in 50

51 62. Table 27. Environment officers of EVN Hanoi should inspect construction site more often, and CSCs and EOs of constructors on each site should enforce workers to follows EMP. Since the stated environmental issues are common and easily to be corrected/mitigated, hence the closed date is taken immediately or one/two weeks after PIC visit. The inspection was conducted one/two weeks later by Hanoi DPMB environmental officer or PIC to confirm the implementation of mitigation measure being done. All the environmental issues identified in this monitoring period were addressed by May

52 Table 27: Identified Issue and action required Issues Location Targets/Solutions Proposed Closed date Rehabilitation of Son Tay 110KV substation Construction of cable trench is not done section by section. This can cause dust generation and run-off with soil particles On site Constructor should complete one section before starting other section to prevent dust generation and runoff with soil particles Water stagnant at a road section; construction of cable trench is not done section by section. [Not improved from the previous monitoring period] Some workers are not using personal protective equipment while working [Not improved from the previous monitoring period] Temporary accommodation of workers is not tidy. Kitchen area is not hygienic [Not improved from the previous monitoring period] Domestic solid waste is not collected and disposed properly [Not improved from the previous monitoring period] The toilet, washing and showering facilities for workers are very poor. On site Water stagnant at a road section should be drained; construction of cable trench should be done section by section to avoid dust generating and accident occurred. On site Workers should wear safety equipment while working. Environment officers of EVN Hanoi together with CSCs and EOs of constructors on each site should enforce workers follow strictly the requirements of environmental protection Worker camp Temporary accommodation of workers and kitchen area should be cleaned to be more hygienic. Worker camp Worker camp Garbage need to be collected and transported to Xuan Son landfill The toilet, washing and showering facilities for workers should be upgraded to be more hygienic May 2017 Constructor finished the undone sections then starts the new section May 2017 Constructor drained and finished the undone sections then starts the new section April 2017 Workers were wearing the personal protective equipment right after PIC reminder April 2017 The workers camp and kitchen area were cleaned one week after PIC visit April 2017 Constructor collected and disposed to Xuan Son landfill one week after PIC visit May 2017 The toilet, bathing facilities was upgraded two weeks after PIC visit Phu Nghia substation and connecting line An uncompleted trench On site without cover could cause accident at nigh time [Not improved from the previous monitoring period] Domestic solid waste is collected but disposed directly into the surrounding area Workers not fully use personal protective facilities while working On site Worker camp An uncompleted trench should be covered or complete as soon as possible to avoid accident at nigh time Domestic solid waste should be transported and disposed at regulated place by Son Tay URENCO Workers should fully use personal protective facilities while working Environment officers of EVN Hanoi together with CSCs and EOs of constructors on each site should enforce workers follow strictly the April 2017 (Right after PIC visit) April 2017 The construction site was cleaned up right after PIC visit April 2017 Workers were wearing the personal protective equipment right after PIC warning 52

53 Issues Location Targets/Solutions Proposed Closed date requirements of environmental protection Thuong Tin-Thanh Oai transmission line The earth filled tower foundation is not properly compacted. This can cause soil erosion after heavy rain Solid waste is still remained at construction site Some workers do not wear safety equipment appropriate for the task they are employed. [Not improved from the previous monitoring period] The holes dug for tower foundation is without safety tape could make people falling into a pit at night On site On site On site Expansion of Thuong Dinh 110KV substation Domestic solid waste is not On site collected and disposed properly The earth filled tower foundation should be properly compacted to avoid soil erosion after heavy rain Solid waste should be cleaned up from the construction site Workers should fully use personal protective equipment while working Environment officers of EVN Hanoi together with CSCs and EOs of constructors on each site should enforce worker follow strictly the requirements of environmental protection The safety tape should be hang around the holes dug for tower foundation to prevent people fall into a pit at night Domestic solid waste should be collected and disposed properly through Hanoi URENCO April 2017 (Right after PIC visit) May 2017 The construction site was cleaned up two weeks after PIC visit April 2017 Workers were wearing the personal protective equipment right after PIC warning April 2017 (Right after PIC visit) April 2017 The construction site was cleaned up one week after PIC visit Connecting line to 220 kv Son Tay Substation The filled soil at tower On site foundation was not properly compacted. This would generate dust when strong wind blows Solid waste is disposed at the surrounding area. Workers did not fully use personal protective equipment while working The holes dug for tower foundation is without safety tape could make people falling into a pit at night On site Onsite On site The filled soil at tower foundation should be properly compacted to prevent generating dust when strong wind blows Solid waste should be disposed in Xuan Son landfill site Workers should fully use personal protective equipment while working Environment officers of EVN Hanoi together with CSCs and EOs of constructors on each site should enforce worker follow strictly the requirements of environmental protection The safety tape should be hang around the holes dug for tower foundation to prevent people fall into a pit at night April 2017 (Right after PIC visit) May 2017 Solid waste was disposed in Xuan Son landfill site two weeks after PIC visit April 2017 Workers were wearing the personal protective equipment right after PIC warning April 2017 (right after PIC visit) 53

54 APPENDIXES APPENDIX A: SUMMARY OF THE ENVIRONMENTAL REQUIREMENTS IN EMP/IEE AND IN B&C DOCUMENTS... 1 APPENDIX B: PHOTOS OF SITE VISIT... 4 APPENDIX C: ENVIRONMENTAL EFFECT MONITORING RESULTS... 7 Appendix A: Summary of the environmental requirements in EMP/IEE and in B&C documents Environmental issues Establishment of contractor s facilities (camps, offices, quarries, concrete batching areas etc.). Demarcation and clearing of RoW and ancillary facilities Preparation of site: excavation, removal and disposal of unusable (incompetent) materials Dust management Noise and vibration Waste water to construction site Environmental requirements in the EMP/IEE - Sites are located so that they do not interfere with the welfare or social cohesion of surrounding communities - Site is limited to reduce unnecessary clearing of vegetation. - Sanitary soakage areas from offices and camps to be sited so that effluent is treated. - No discharge of grey water or sewage allowed to surface water systems. - Workshops to be provided with oil and water separators. - Fuel storage areas not to be located within 20m of watercourse. - Contractor s storage facilities may need to be surrounded by a security fence. - Concrete batching areas to be provided with bunds to control movement of runoff to waterways. - Define the 22m RoW width. - Identify trees to be removed within the RoW and arrange to get approval for remove. - Limit area to be cleared - Identify areas with any significant vegetation - Areas to be defined by a clear boundary. - Clearing boundaries need to be shown to machinery operators. - Cleared vegetative material to be offered to communities for use as fuel wood or - If an impediment to work may otherwise be disposed of by clean burning fires. - Limit area to be excavated. - Topsoil to be removed and stored for re-use. - Excavated material to be disposed of outside and away from the work area. - At completion of work dumping areas to be re-top soiled and revegetated. - When dust is carried towards residential areas or becomes problematic on-site, the contractor is to apply dust control measures; - If particular noisy work is implemented, the work may need to be limited to daylight hours. - Noise not to exceed 55dBA at boundary of any residential area between 6hr and 21h00 and 45 dba between 21h00 and 06h00; - Not allow to discharge waste water directly to water body surrounding the site ; In B&C documents All environmental requirements in the EMP/IEE have been integrated into the B&C documents and the CEMP of NB-W01, NB- W02, MLAO- W01, MLAO- W02, TX-W01, ST-W01, NRST-W01, PN-W01, TTTO-W01, TD-W01. Appendix - 1

55 Environmental issues Prevention of soil erosion on construction site. Disposal of site waste Storage and handling of: fuel and lubricants Community Safety from increased vehicle movements Workplace health and safety Chance discovery of archaeological and cultural sites Clearance and rehabilitation of Construction sites and removal of contractor s facilities. Environmental requirements in the EMP/IEE - Make a discharging canal surrounding the foundation holes to collect runoff water to reduce its turbidity before discharging it into water body surrounding the site ; - Not allow to drop oil and fuel from machinery to site; - Apply soil conservation and erosion protection technologies. - Avoid operating machinery in adverse ground conditions. - Protect and vegetate newly excavated areas as soon as possible - All waste materials to be collected and sorted into two categories (i). those that can be recycled and - (ii) those that need to go to an approved landfill site for disposal; - All fuel storage areas should be securely fenced and provided with oil and water separators. Fuel hoses and shut off valve to be locked. - Fuel should be stored in properly sealed containers. Regularly check its locks to prevent fuel from running over to environment. - All refueling to be done at least 20 m away from waterways by trained personnel - All waste oil and oil filters to be collected and if possible recycled, otherwise to be disposed of to landfills - The contractor needs to train refueling personnel in these procedures. The contractor has to develop an accidental spill handling action plan - All vehicles need to be properly maintained and operated in accordance with transportation laws. - All loads should be properly secured and fugitive loads to be covered. - Drivers are fined if ignore safety requirements. - Contractor should abide: Vietnamese Labor Code as amended 2002 as follow:. - Provided workers be with safety working environment - Erect warning signs and barriers around work areas - Not allow drugs or alcohol on-site; - Control noise and dust provided all workers with safety equipment appropriate for the task they are employed. - The workers are to be supplied on-site with: Potable water, sanitary toilet, washing and showering facilities. - Prepared work safety regulation for each activity - Before execution, workers need to be introduced and explained site safety procedures. - Provided medical and first aid facilities together with a person qualified in first aid. - Chance discoveries should be notified to the SO who will report to the EO of HANOI DPMB. EO would advise on procedure for dealing with chance discoveries. - All solid waste should to be removed from sites and disposed in approved landfills. - All contaminated soil should be removed. - All sites must be rehabilitated and restored to original condition. - Drainage should be re-established. - Those activities should be included as part of final inspection before payment made. In B&C documents Appendix - 2

56 Environmental issues Public access to site Community and worker health and safety Environmental requirements in the EMP/IEE - Erect warning signs and barriers around work areas. - Site can only be accessed with permission of contractor. - Visitors are to be warned against site hazards to avoid possible accident - Promulgate, educate workers on the social problems. Implement measures of preventing HIV/AIDS; - Provide good daily life conditions for workers in camps in terms of sanitation, safe water and cooking; - Worker s camps shall be constructed in a high places and - Local workers should be hired for normal works; - Equip workers with labor protecting equipment and force them to wear during working time. - Provide means of first aid, medicines at site and camps for workers; - Ensure sanitation in worker s camps. Provide dust bin to collect wastes; - Prohibit hunting and trading wild animals; EO = Environmental Officer of HANOI DPMB, SO = Safeguard Officer of HANOI DPMB. In B&C documents Appendix - 3

57 Appendix B: Photos of Site Visit 1. Rehabilitation of Son Tay 110KV substation (Photos were taken in April 2017) Photo 1: The substation is nearly completed. The equipment area is surrounded by safety string to warn onsite people enter dangerous area Photo 2. Safety regulation board is in place Photo 3. The clean water is provided to daily use of workers Photo 4. The washing/bathing place for workers is quite neatly Photo 5. Water stagnant at a road section; construction of cable trench is not done section by section Photo 6. Some workers are not using personal protective equipment while working Photo 7. Solid waste at the camp site Photo 8. Temporary toilet is placed near the kitchen without solid door Appendix - 4

58 2. Phu Nghia substation and connecting line Photo 9. Working safety board at construction site Photo 10. The high wall to prevent local people entering the substation s construction site Photo 11. Building materials are gathered inside the construction area Photo 12. An uncompleted trench without cover could cause accident at night time Photo 13. Workers wear safety equipment but without helmet Photo 14. Workers wear safety equipment but without boots Appendix - 5

59 3. Thuong Tin - Thanh Oai transmission line Photo 15. The excavation area was not warning tape around, excavated soil is not covered by canvas. Photo 16. Solid waste is still remained at construction site Appendix - 6

60 Appendix C: Environmental Effect Monitoring results 1. Air quality in front of control centre of Son Tay substation on 13 March 2017 Appendix - 7

61 2. Air quality at 220kV Xuan Mai substation of Phu Nghia substation and transmission line on 10 January 2017 Appendix - 8

62 2. Air quality at Safety corridor of over head line at Dong Phuong Yen commune, Chuong Mi district of Phu Nghia substation and transmission line on 10 January 2017 Appendix - 9

63 3. Air quality at Dam of Tich river, Can Huu commune, Quoc Oai district of Phu Nghia substation and transmission line on 10 January 2017 Appendix - 10

64 4. Air quality at worker camp Phu Nghia 110kV substation of Phu Nghia substation and transmission line on 10 January 2017 Appendix - 11

65 5. Air quality at 220kV Xuan Mai substation of Phu Nghia substation and transmission line on 12 April 2017 Appendix - 12

66 6. Air quality at Safety corridor of over head line at Dong Phuong Yen commune, Chuong Mi district of Phu Nghia substation and transmission line on 12 April 2017 Appendix - 13

67 7. Air quality at Dam of Tich river, Can Huu commune, Quoc Oai district of Phu Nghia substation and transmission line on 12 April 2017 Appendix - 14

68 8. Air quality at worker camp of Phu Nghia 110kV substation of Phu Nghia substation and transmission line on 12 April 2017 Appendix - 15

69 9. Air quality at K1, K2, K3, K4, K5, K6, K7, K8, K9, K10, K11, K12, K13, K14 of Thuong Tin- Thanh Oai 110kV transmission line on 25 Jul 2017 Appendix - 16

70 Appendix - 17

71 10. Air quality in front of expansion control centre of Expansion Thuong Dinh 110kV substation on 13 March 2017 Appendix - 18

72 11. Air quality in front of expansion control centre of Expansion Thuong Dinh 110kV substation on 12 July 2017 Appendix - 19

73 12. Surface water at NM1, NM2, NM3, NM4, NM5, NM6 of Thuong Tin- Thanh Oai 110kV transmission line on 12 July 2017 Appendix - 20

74 Appendix - 21

75 13. Soil quality at field around Son Tay substation on 27 March 2017 Appendix - 22

76 Appendix D: 1. Official Letter from Hanoi DPMB to the contractors of (i) Rehabilitation of Son Tay 110KV substation; (ii) Phu Nghia substation and connecting line; (iii) Thuong Tin- Thanh Oai Transmission line; (iv) Expansion of 110kV Thuong Dinh substation E1.5; and (v) Son Tay 110kV transmission line (26 Nov 2016) This letter was issued to notice the contractors of the environment monitoring requirement and request them to settle all backlog issues on each site. (see para 56 for explanation) Appendix - 23

77 Appendix - 24

78 2. Official Letter from Hanoi DPMB to the contractors of 110kV line to 220kV Son Tay subsation (ST-W01), Phu Nghia substation and connecting line (110kV) (PN_W01-L01, PN_W01_L02), T/L (110kV) from Thuong Tin substation to Thanh Oai (TTTO-W01) (19 Dec 2016) This letter was issued to notice the contractors of the environment monitoring requirement and request them to conduct environmental effect monitoring (see para 50 for explanation) Appendix - 25