UPDATED FORM I 433 TPD CALCINED PETROLEUM COKE PLANT WITH 9 MW COGENERATION OF POWER PROPOSED AT
|
|
- Kory Ball
- 5 years ago
- Views:
Transcription
1 UPDATED FORM I Of 433 TPD CALCINED PETROLEUM COKE PLANT WITH 9 MW COGENERATION OF POWER PROPOSED AT APSEZ, Atchutapuram, Visakhapatnam district, Andhra Pradesh By RAIN CALCINER LIMITED Prepared By B.S. ENVI-TECH (P) LTD Secunderabad NABET Accreditation : NABET/EIA/1316/RA002
2 FORM I
3 FORM 1 (As Per New tification of Mo.E.F dated vide SO 3067 (E)) BASIC INFORMATION S. Item Details 1 Name of the Project/s M/s. Rain Calciner Limited 2 S.. in the schedule 4(b) 3 Proposed capacity/ area/ length/ tonnage to be handled/ command area/ lease area/ number of wells to be drilled 4 New/ expansion/ modernization New 5 Existing capacity/ Area etc. t Applicable 6 Category of Project i.e A or B B 7 Does it attract the general condition? If yes please specify. 8 Does it attract the specific condition? If yes please specify. 9 Location Plot/ Survey/ Khasra Village Tehsil District State 10 Nearest railway station/ airport along with distance in Kms. 11 Nearest town, city, district head quarters along with distance in kms. 12 Village panchayaths, Zilla parishad, Municipal Corporation, Local body (Complete postal addresses with telephone nos to be given) 433 TPD Calcined Petroleum Coke Plant With 9 MW Cogeneration Of Power APSEZ, Atchutapuram, Visakhapatnam district, Andhra Pradesh Elamanchali 13 km Vishakapatnam 30 km APSEZ, Atchutapuram, Visakhapatnam district, Andhra Pradesh. 13 Name of the applicant M/s. Rain Calciner Limited 14 Registered address Rain Center, 34,Srinagar Colony, 15 Address for correspondence Hyderabad Name Designation (Owner /Partner/ CEO) Address A.S.Reddy Whole Time Director M/s. Rain Calciner Limited, Rain Center, 34,Srinagar Colony, Hyderabad Pin code E- mail a.s.reddy@raincarbon.com Telephone no Fax no Details of Alternative sites examined, if any location of these sites should be shown on a topo sheet. t Applicable
4 17 Interlinked projects t Applicable 18 Whether separate application of interlinked project has been submitted? 19 If yes, date of submission - 20 If no, reason - 21 Whether the proposal involves Nil approval/ clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation)Act, 1980 (b) The Wild Life (Protection)Act, 1972 (c) The CRZ tification, Whether there is any Government Order/ Policy relevant/ relating to the site? 23 Forest land involved (hectares) Nil 24 Whether there is any litigation pending against the project and/or land in which the project is propose to be set up? (a) Name of the court (b) Case (c) Orders/ directions of the court, if any and its relevance with the proposed project. Nil (I) ACTIVITY 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Details thereof (with S.. Information/Checklist / approximate quantities /rates, wherever possible) with source of information data 1.1 Permanent or temporary change The Special Economic Zone in land use, land cover or (SEZ) in Atchutapuram, topography including increase in Visakhapatnam is being intensity of land use (with respect developed by Andhra Pradesh to local land use plan) Industrial Infrastructure Corporation (APIIC). Rain Calciner Limited s proposed project will be one of the units within this SEZ. A land of Acres (17.5 Hectares) has been allotted for the project. 1.2 Clearance of existing land, ne vegetation and buildings? 1.3 Creation of new land uses? About Acres (17.5
5 1.4 Pre-construction investigations e.g. bore houses, soil testing? Hectares) in identified Special Economic Zone, meant for Heavy polluting units has been allotted for the project and this is converted into Industrial area. Engineering properties of the soil will be tested for structural design 1.5 Construction works? All the necessary infrastructural facilities along with the calcination plant will be installed 1.6 Demolition works? ne 1.7 Temporary sites used for construction works or housing of construction workers? 1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations 1.9 Underground works including During the construction stage, temporary site offices, accommodation for construction workers will be located within the premises. All the structures will be located above the ground and the construction activity does not involve much cut and fill activity ne mining or tunneling? 1.10 Reclamation works? ne 1.11 Dredging? ne 1.12 Offshore structures? ne 1.13 Production and manufacturing processes? The proposed Calcination process is based on Pot (Shaft) Calciner technology. Process Technology shall be obtained from a World renowned Agency. Green petroleum coke is conveyed from the raw material storage / unloading hoppers via belt conveyers to day bins feeding the coke to Pot Calciners for calcining. A part of the calcined coke is returned and mixed with input GPC depending on process parameters as well as required quality of CPC. Green coke in the pot calciner is indirectly heated up to around 1250 C by high temperature fume in the flue in order to
6 remove moisture and volatiles efficiently, improve real density, electrical conductivity and mechanical strength. Volatiles evolved during the process are introduced to the flue for complete combustion with the pre-heated air without any external fuel. CPC from pot calciner is indirectly cooled in chute with water jacket and is discharged at regular intervals. Part of the discharged CPC is diverted for mixing with the input GPC and major part of CPC is conveyed to calcined coke storage. CPC is dispatched from the plant in Bulk. Bag filter units are provided at all locations of GPC / CPC transfer to suppress the dust Facilities for storage of goods or materials? 1.15 Facilities for treatment or disposal of solid waste or liquid effluents? 1.16 Facilities for long term housing of operational workers? 1.17 New road, rail or sea traffic during construction or operation? The flue gases pass through the Waste Heat Recovery Boiler (WHRB) where steam is generated. The exit gases from the WHRB are vented to atmosphere through a stack. A Stand-bye Bye pass stack shall also be included in the Design. Required space has been considered in the layout for storage of Raw Material / Finished goods and also for the stores facility. ne Well established towns with good public transport facilities are available in not far-off locations. SEZ is being developed by Andhra Pradesh Industrial Infrastructure Corporation (APIIC) as a MULTI PRODUCT Manufacturing facility, housing
7 1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission lines or pipelines? 1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? many Industries. APIIC has established Industries by prospective Unit Owners. APIIC provides basic infrastructure amenities like Industrial/ Potable water / communication / Roads and other common facilities All infrastructures were already developed in the zone. ne ne ne 1.22 Stream crossings? ne 1.23 Abstraction or transfers of water ne from ground or surface waters? 1.24 Changes in water bodies or the land surface affecting drainage or run-off? ne 1.25 Transport of personnel or materials for construction, operation or decommissioning? Personnel will be transported to site in vehicles. Similarly, GPC has to be sourced from refineries that produce sponge Anode Grade Coke. Thus, GPC will be imported from reliable suppliers to meet the stringent quality standards and will be moved into the zone 1.26 Long-term dismantling or decommissioning or restoration works? 1.27 Ongoing activity during decommissioning which could have an impact on the environment? GPC will be sourced from various refineries mainly in rth America, South America, Middle East and Asia etc. ne ne
8 1.28 Influx of people to an area in either temporarily or permanently? The manpower requirement for regular operations is estimated to be about 150. During the Construction period, this figure may be higher. Hence influx of people will increase and locals will also be employed Introduction of alien species? ne Loss of native species or genetic ne diversity? 1.31 Any other actions? ne 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are nonrenewable or in short supply): S.. Information/checklist 2.1 Land especially undeveloped or agricultural land (ha) 2.2 Water (expected source & competing users) unit: KLD / Details thereof (with approximate quantities /rates, wherever possible) with source of information data The Special Economic Zone (SEZ) in Atchutapuram, Visakhapatnam was developed by Andhra Pradesh Industrial 2.3 Minerals (MT) ne Infrastructure corporation. About Acres developed land ( 17.5 Hectares) has been allotted for the project. The water consumption for the plant is about 1,440 m3 / day and the same will be met from public supply. As the present site is in SEZ & developed by APIIC, infrastructural requirements are being arranged by them. 2.4 Construction material stone, aggregates, sand / soil (expected source MT) 2.5 Forests and timber (sourc e MT) 2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW) 2.7 Any other natural resources (use appropriate standard units) Stone aggregate, cu.m Sand cu.m, cement tons etc.. shall be used during construction phase. ne Required Electrical energy requirement shall be met from power generated in Cogeneration plant. However, start-up power will be tapped from the AP Transco grid. -
9 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S.. Information/Checklist 3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by changing living conditions? 3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc., / Details thereof (with approximate quantities/rates, wherever possible) with source of information data Green petroleum Coke is the Raw Material for manufacturing Calcined Petroleum Coke. It is classified as carbonaceous material and is n-toxic in nature and does not fall under Hazardous chemical category. ne Social status of the people living in the vicinity will improve as a result of direct / indirect employment opportunities provided by the plant. ne 3.5 Any other causes ne 4. Production of solid wastes during construction or operation or decommissioning (MT/month) S.. Information/Checklist / Details thereof (with approximate quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine wastes ne 4.2 Municipal waste (domestic and or ne commercial wastes) 4.3 Hazardous wastes (as per Waste oil will be generated from Hazardous Waste the plant Management Rules) 4.4 Other industrial process wastes ne 4.5 Surplus product Incidental surplus product ie power will be supplied to grid/ wheeled to their sister concerns. 4.6 Sewage sludge or other sludge from effluent treatment ne
10 4.7 Construction or demolition ne wastes 4.8 Redundant machinery or t Applicable equipment 4.9 Contaminated soils or other ne materials 4.10 Agricultural wastes ne 4.11 Other solid wastes Gypsum which gets generated as a by-product will be used for cement plants/fal-g brick manufacturing units. 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Details thereof (with approximate quantities/rates, S.. Information/Checklist / wherever possible) with source of information data 5.1 Emissions from combustion of fossil fuels from stationary or The exhaust gases from the Pot Calciner Furnaces are sent to mobile sources Waste Heat Recovery Boilers (WHRB). The gases after heat recovery are vented to atmosphere through the stack. A stand-by byepass stack will also be included in 5.2 Emissions from production processes 5.3 Emissions from materials handling including storage or transport 5.4 Emissions from construction activities including plant and equipment 5.5 Dust or odours from handling of materials including the Design. Green coke in the pot calciner is indirectly heated up to around 1250 C by high temperature fume in the flue in order to remove moisture and volatiles efficiently, improve real density, electrical conductivity and mechanical strength. Volatiles evolved during the process are introduced to the flue for complete combustion with the pre-heated air without any external fuel. The coke at site is either in Day Bins or in Storage area. Both are fully covered and hence no fugitive dust is expected from these areas. Fugitive dust for short duration ne
11 construction materials, sewage and waste 5.6 Emissions from incineration of waste ne 5.7 Emissions from burning of ne waste in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other ne sources 6. Generation of ise and Vibration, and Emissions of Light and Heat: / Details thereof (with S.. Information/Checklist 6.1 From operation of equipment e.g. engines, ventilation plant, crushers 6.2 From industrial or similar processes 6.3 From construction or demolition approximate quantities/rates, wherever possible) with source of information data with source of information data The major noise generating sources are the Turbo-Generator, Fans and Compressors. The noise level from the STG proposed is likely to be about 85 db(a). ne ise levels of construction machinery will be there for short duration 6.4 From blasting or piling ne 6.5 From construction or Construction equipment - < 85 operational traffic db(a) 6.6 From lighting or cooling systems 6.7 From any other sources ne ise from Stand-by DG set / Air-conditioning equipment less than <70 db(a) 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Details thereof (with approximate quantities/rates, S.. Information/Checklist / wherever possible) with source of information data 7.1 From handling, storage, use or ne spillage of hazardous materials 7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) ne
12 7.3 By deposition of pollutants ne emitted to air into the land or into water 7.4 From any other sources ne 7.5 Is there a risk of long term build up of pollutants in the environment from these sources? ne 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment Details thereof (with approximate quantities/rates, S.. Information/Checklist / wherever possible) with source of information data 8.1 From explosions, spillages, fires etc from storage, handling, use ne or production of hazardous substances 8.2 From any other causes ne 8.3 Could the project be affected by natural disasters causing ne environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality Details thereof (with approximate quantities/rates, S.. Information/Checklist / wherever possible) with source of information data 9.1 Lead to development of ne supporting facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.)
13 housing development extractive industries supply industries other 9.2 Lead to after-use of the site, which could have an impact on the environment 9.3 Set a precedent for later developments ne ne 9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects ne (II) ENVIRONMENTAL SENSITIVITY Aerial distance (within 15 km.) S.. Areas Name/ Proposed project Identity location boundary 1 Areas protected under ne international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other ne water bodies, coastal zone, biospheres, mountains, forests 3 Areas used by protected, Pudimadaka for Olive important or sensitive species Turtles - 7 km of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or Bay of Bengal -3 km underground waters 5 State, National boundaries - ne 6 Routes or facilities used by the - ne - public for access to recreation or other tourist, pilgrim areas 7 Defence installations - ne - 8 Densely populated or built-up area ne -
14 9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) 10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Schools, hospitals & community facilities- Achuthapuram village - ne - - ne Pudi occassional Cyclones for
15
16 SPECIAL REQUEST The proposed project already obtained Environmental Clearance in 2009, vide SEIAA order.. SEIAA/AP/VSP-19/2009 dated as per SO 1533 tification dated 14 th September 2006, issued by SEIAA. The project is categorized as Category B project based on the threshold limits published in the tification requiring Environmental Clearance from SEIAA. And also, as it is proposed to be located in the Special Economic Zone identified by the Government Of Andhra Pradesh, (where already other industries exist). The project could not be implemented due to the poor market conditions and prevailing industrial scenario earlier. However, the demand for CPC has significantly increased in the last couple of years. Presently, there is a huge gap in demand and supply of CPC. Rain Calciner would like to utilize this opportunity and set up the proposed facility within an year of getting all necessary clearances. Rain Calciner Limited will be fast track project with a proposed investment of about Rs 200 crores and good employment opportunity which will contribute to the overall development of community around the project. Keeping the above in view, RCI requests the committee to Revalidate the Environmental Clearance for another two years.
APPENDIX I. (See paragraph-6) FORM 1
(I) Serial Number Basic Information Item APPENDIX I (See paragraph-6) FORM 1 Details 1. Name of the project/s Soapstone Mining (ML. 15/95) 2. S.. in the schedule B1- Mining of Mineral 3. Proposed capacity/area/length/tonnage
More informationFORM 1 BASIC INFORMATION S.NO.
FORM 1 BASIC INFORMATION S.NO. Item Details 1 Name of the Project M/s AVA Stones (P) Ltd, Director: Sri.Bimal Kumar Agarwal Colour Granite Mine. 2 S.. in the schedule 1(a) 3 Proposed capacity/ area/ length/
More informationAnnex F Scoping Checklist
Scoping Checklist Table F1: Scoping Checklist Table. Questions to be considered in Scoping /? Which Characteristics of the Project 1. Will construction, operation or decommissioning of the Project involve
More informationFORM I SUBMISSION TO STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, ANDHRA PRADESH. BY. Asst.Director of Mines and Geology, Rajamahendravaram
FORM I SUBMISSION TO STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, ANDHRA PRADESH. BY Asst.Director of Mines and Geology, Rajamahendravaram Ordinary Sand Land Details : Govt Land Extent : 3.9634 Ha. VILLAGE
More informationAPPENDIX I (See paragraph 6) FORM 1
APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information: S.. Item Details 1 Name of the project/s: M/s. Sri Lakshmi Enterprises 2 S.. in the schedule 1 (a) 3. Proposed capacity/area/length/tonnage to
More informationFORM-I for seeking clearance for project attracting CRZ notification
AnnexureIV FORM-I for seeking clearance for project attracting CRZ notification Basic information: SEA CLIFF RESORTS TOURISM PROJECT (.1682/A3/15/KCZMA/S&TD) Name of the Project: THE SEACLIFF Location
More informationAPPENDIX I. (See paragraph 6) FORM 1
APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information Name of the Project Size of the project (in terms of total area) CRZ classification of the area Expected cost of the project Contact Information
More informationAPPENDIX I. (See paragraph-6) FORM 1
(I) Serial Number Basic Information Item APPENDIX I (See paragraph-6) FORM 1 Details 1. Name of the project/s Soapstone, Red Ocher and China Clay (ML. 81/82) 2. S.. in the schedule 1 (a) - Mining of Mineral
More informationFORM 1 & 1 A. Palladium Grand II RESIDENTIAL & COMMERCIAL DEVELOPMENT. Palladium Grand II, S. No. 17/1A/2, Dhanori, Pune, Maharashtra
FORM 1 & 1 A Palladium Grand II RESIDENTIAL & COMMERCIAL DEVELOPMENT At Palladium Grand II, S. 17/1A/2, Dhanori, Pune, Maharashtra By M/s. Raojee Constructions FORM 1 Palladium Grand II RESIDENTIAL & COMMERCIAL
More informationM/s. Karthika Mines & Minerals Pvt.Ltd.-Colour Granite Quarry Ha. FORM - I
FORM - I (I) Basic Information S.. Item Details 1 Name of the project/s M/s.Karthika Mines & Minerals Pvt.Ltd. Colour Granite Quarry, 10.00 Ha. 2 S.. in the schedule 1 (B) 3 Proposed capacity Area-10.00
More informationMolvan- Chhamuchhal Group Gram Panchayat. Taluka- Mangrol, District- Surat. Ph. No
Serial Number FORM 1 (Application for Environment Clearance Certificate) Item 1. Name of the project/s 2. S. No. in the schedule 3. Proposed capacity/ area/ length/ tonnage to be handled/ command area/lease
More informationFORM 1. APPLICATION FOR OBTAINING ENVIRONMENTAL CLEARANCE VIDE PARA 6 OF S.O.1533 OF MOEF NOTIFICATION DATED 14 th SEPTEMBER 2006
FORM 1 APPLICATION FOR OBTAINING ENVIRONMENTAL CLEARANCE VIDE PARA 6 OF S.O.1533 OF MOEF NOTIFICATION DATED 14 th SEPTEMBER 2006 (I) Basic Information: S. Item Details 1. Name of the Project/s : Expansion
More informationFORM-I. 13. Name of Applicant District Collector Nasik 14. Registered Address Address : Collector Office, Nasik
FORM-I (I) Basic Information Item Details. 1. Name of the Project Proposal for Sand Quarry in Kas Village, Taluka Trimbakeshwar, District Nasik, State Maharashtra over an area of 1.5400 Ha at Damanganga
More informationForm -1. [Vide Notification dated 1 st December 2009] FOR PROPOSED. COSTAL ROAD AT DRONAGIRI, NAVI MUMBAI Precast RCC Bridges On Holding Ponds-
Project Name : Design and Construction of Precast Arch Bridges(3s.) on Holding Pond. 3A, 3 & 4 for Form -1 [Vide tification dated 1 st December 2009] FOR PROPOSED COSTAL ROAD AT DRONAGIRI, NAVI MUMBAI
More informationAPPENDIX I (See paragraph 6) FORM 1
APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information S. No Item Details 1 Name of the Project/s Sri A. Narasimulu 2 S. No in the Schedule 1(a) 3 Proposed capacity/area/length/tonnage to be handled/command
More informationSubmitted To State Expert Appraisal Committee (SEAC), State Environmental Impact Assessment Authority, Andhra Pradesh.
Application for Prior Environmental Clearance (Form 1) For Proposed Colour Granite Mine over an Extent of 3.000 Hectares, in Sy. : 143 of Bharthupuram village, Nandigam Mandal, Srikakulam District, Andhra
More informationAppendix I. Form 1 BASIC INFORMATION PAWA MASONARY STONE MINING PROJECT VILLAGE PAWA, TEHSIL DIDWANA, DISTRICT NAGAUR, RAJSTHAN
Appendix I Form 1 BASIC INFORMATION PAWA MASONARY STONE MINING PROJECT VILLAGE PAWA, TEHSIL DIDWANA, DISTRICT NAGAUR, RAJSTHAN AREA: 1.0 HECT (NON FOREST LAND) ML 219/1997 PRODUCTION CAPACITY: 50,000 TPA
More informationFORM I TERMS OF REFERENCE. For. QUARRY OF ROAD METAL (6.265 Ha) Sri K Kasi Raju. PROP: K.Kasi Raju
FORM I TERMS OF REFERENCE For QUARRY OF ROAD METAL (6.265 Ha) Of Sri K Kasi Raju PROP: K.Kasi Raju Extent: 6.265 Ha of Budawada (V), Chimskurthy (M), Prakasam (Dt), Andhra Pradesh (I) BASIC INFORMATION
More informationAPPENDIX I (See paragraph - 6) FORM 1
APPENDIX I (See paragraph - 6) FORM 1 (I) Basic Information S. Item Details 1 Name of the project Sarpanch, Gram Panchayat chando chando Sand Mine 2 S.. in schedule Category B, Project or Activity 1(a)
More informationAPPENDIX I (See paragraph 6) FORM 1 (Application for Environment Clearance)
(I) Basic Information APPENDIX I (See paragraph 6) FORM 1 (Application for Environment Clearance) Name of the Project: KRUTI ONELLA Sahyog Rekha Infraproject LLP Location / site alternatives Survey no.
More informationFORM 1 (As per new Notification of MoEF dated vide S.O 3067 (E))
FORM 1 (As per new tification of MoEF dated 01-12-2009 vide S.O 3067 (E)) (I) BASIC INFORMATION S.. Item Details 1. Name of the project/s M/s. S.L.N.S. Granites Mining of Colour Granite 4.90 Ha 2. S..
More informationApplication Forms for Prior Environmental Clearance as per Environmental Impact Assessment Notification dtd &
Application Forms for Prior Environmental Clearance as per Environmental Impact Assessment tification dtd 14-09-2006 & 01-12-09 To be submitted By SHRI SANJAY SINGH S/O SHRI MAHENDRA SINGH RATHORE To Madhya
More informationAPPENDIX - I (See paragraph 6) FORM 1
APPENDIX - I (See paragraph 6) FORM 1 (I) Basic Information Item Details 1 Name of the project/s M/S Jashnani Constructions Pvt. Ltd. Proposed residential building project at Shahapur, Thane 2 S.. in the
More informationSri.T.N.Balasubramanya
Sri.T.N.Balasubramanya (Earlier: M/s.Global Golden Rocks) Extent: 5 Ha Colour Granite Quarry Sy.No.65 of Lattigam Village, Nandigam Mandal, Srikalulam District, Andhra Pradesh UPDATED FORM-I FORM 1 (As
More information(Residential cum Commercial Project) APPENDIX I (See paragraph 6) FORM 1. Plot area: 37,039 m 2 Built up area: 1,11, m 2
(I) Basic Information APPENDIX I (See paragraph 6) FORM 1 Sr. Item 1 Name of the Project 2 S. number in schedule 8(a) 3 Proposed capacity/area/length/tonnage to be handled/command area/lease area/number
More informationUPDATED FORM I. SUBMISSION To Ministry of Environment & Forests & Climate Change, New Delhi. Prepared by. M/s. VIJAYNAGAR SUGAR PVT. LTD.
Annexure - III UPDATED FORM I For Amendment to Environmental Clearance (Environmental Clearance issued by MOEF vide. F.. J-11011/366/2007-IA-II (I) Dated, 15.04.2008.) SUBMISSION To Ministry of Environment
More informationAPPENDIX I (See paragraph 6) Form 1 (I) Basic Information
APPENDIX I (See paragraph 6) Form 1 (I) Basic Information Sr.. Item Details 1 Name of the Project/s Proposed expansion in Environment Clearance for Residential and Commercial project by Manikchand Kumar
More informationUPDATED FORM I, (Submitted to State Expert Appraisal Committee, Telangana)
UPDATED FORM I, (Submitted to State Expert Appraisal Committee, Telangana) Venkateswara Mines & Minerals (Earlier: Sri Bode Vijayasen Reddy), Kannaraopet Village, Nallabelli Mandal, JayashankarBhupalpally
More informationFORM 1. 8 Does it attract the specific condition? It yes, No Please specify 9 Location At Village Akurli, Akurli Road, Kandivali(E), Mumbai
FORM 1 (I) Basic Information Sr. Item Details. 1 Name of the Project WHITE CITY METAL 2 S.. in the Schedule 8 (b) 3 Proposed capacity/area /length/tonnage to Plot area: 45,800.00 sq.mt. be handled/command
More informationSand, Stone & Bajri Mining Project Applicant: Shri Ashish Kumar, M/s Ashish Stone Crusher. Form-1 FORM-1 SRUSHTI SEWA, NAGPUR 1
FORM-1 SRUSHTI SEWA, NAGPUR 1 FORM 1 (I) Basic Information S.. Item Details 1. Name of the project/s Sand, Stone and Bajri Mining Project 2. Serial. in the schedule 1(a) Mining of Mineral 3. Proposed capacity
More informationAPPENDIX I (See paragraph 6) FORM 1
(I) Basic Information APPENDIX I (See paragraph 6) FORM 1 Sr. Item Details 1 Name of the Project WHITE LILLIES (Residential Project) 2 S. number in schedule 8(a) Proposed 3 capacity/area/length/tonnage
More informationAPPENDIX- I FORM- 1. (I) Basic Information:
(I) Basic Information: APPENDIX- I FORM- 1 Item Details 1. Name of Project Sand Stone Mining Project, M.L..-08/1987, Area 150.926 Ha., located n/v -Gubrenda, Tehsil -Karauli, District Karauli, (Rajasthan)
More informationAPPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE
APPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE (AI) (viii) (ix) (x) Basic Information Name of the Mining Lease
More informationFORM 1. Gownivaripalli Village, Tehsil. Gorantla Mandal, District. Anantapur District, State
FORM 1 (I) Basic Information Sl.. Item Details 1. Name of the project/s M/s. Squadm Mines & Minerals Pvt. Ltd - Road Metal & Building Stone 2. S.. in the schedule Item- 1(a) (Mining of Minerals) 3. Proposed
More informationUPDATED FORM-1 EXTENSION OF VALIDITY OF ENVIRONMENTAL CLEARANCE. Sri Fakir Rohidas
UPDATED FORM-1 EXTENSION OF VALIDITY OF ENVIRONMENTAL CLEARANCE At: Brahmanipali, Dustrict: Sambalpur, Odisha Sri Fakir Rohidas Prepared By Centre for Envotech and Management Consultancy Pvt. Ltd. Bhubaneswar
More informationFORM 1 (As per new Notification of MoEF dated vide S.O 3067 (E))
FORM 1 (As per new Notification of MoEF dated 01-12-2009 vide S.O 3067 (E)) I) BASIC INFORMATION Item Details 1 Name of the project/s Sri.Gandi Suryanarayana color Granite 2 S. No. in the schedule Item
More informationAPPENDIX I (See paragraph 6) FORM 1. Plot area: 10,439 m 2 Built up area: 50, m 2
(I) Basic Information APPENDIX I (See paragraph 6) FORM 1 Sr. Item 1 Name of the Project Commercial Project 2 S. number in schedule 8(a) Proposed 3 capacity/area/length/tonnage to be handled/command area/lease
More informationAPPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE
APPENDIX VIII (See paragraph 6) FORM 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE (II) (viii) (ix) (x) Basic Information Name of the Mining Lease
More informationProject: Bhidauni Khadar Ordinary Sand Mining Project on Yamuna River FORM 1 Applicant: M/s Satyug Foods Pvt. Ltd. FORM- I
FORM- I Page 0 of 14 APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information S.. Item Details 1. Name of the project/s Bhidauni Khadar Ordinary Sand Mining Project 2. S.. in the schedule 1(a) mining
More informationFORM-1. PROJECT: Sati & Garhi Sand Ghat,Ulai River (Area-22 Ha), Dist:-Jamui. APPLICANT: M/s Westlink Trading Pvt. Ltd. FORM- I.
FORM- I Page 0 of 15 APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information S.. Item Details 1. Name of the project/s Sati & Garhi Sand Ghat on Ulai River of District- Jamui. 2. S.. in the schedule
More informationFORM 1. No condition? If yes, please specify. 8. Does it attract the specific. No condition? If yes, please specify. 9. Location Geo Coordinates
FORM 1 (I) Basic Information Sl.. Item Details 1. Name of the project/s 9.890 ha. of Proposed Colour Granite Mine of Sri S. Senthil Kumar 2. S.. in the schedule Item- 1(a) (Mining of Minerals) 3. Proposed
More informationM/s. SURYA ENTERPRISES H.No: , Sri Paradise Apartments, New Andhra Bank Colony, Anantapuramu District
Application for Prior Environmental Clearance (Form 1) For Proposed Road Metal / Building Stone/ Robo/Manufacture Sand Mine Over An Extent Of 9.712 Hectares, in Sy.. 743 of Somandepalli Village, Somandepalli
More informationNo 1 Name of the Project/s M/s. Velchal Laterite Mine 2 S. No in the Schedule 1(a)
APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information S. Item Details No 1 Name of the Project/s 2 S. No in the Schedule 1(a) 3 Proposed capacity/area/length/tonnage to Mine lease area is 8.91 Ha,
More informationProposed Construction Multi Specialty Hospital Naruvi Hospitals 2. S. No. in the schedule 8(a)
FORM I (I) Basic Information S.. Item Details 1. Name of the project Proposed Construction Multi Specialty Hospital Naruvi Hospitals 2. S.. in the schedule 8(a) 3. Proposed capacity/area/length/tonnage
More informationFORM 1. /area/length/tonnage. No condition? If yes, please specify. 8. Does it attract the specific
FORM 1 (I) Basic Information Sl.. Item Details 1. Name of the project/s 6.490 ha. of Proposed Colour Granite Mine of M/s. Alief Exports 2. S.. in the schedule Item- 1(a) (Mining of Minerals) 3. Proposed
More informationFORM 1. 1 Name of the Project Pinakin Mangubhai Patel 2 S. number in schedule 8 (a)
FORM 1 (I) Basic Information Item Details 1 Name of the Project Pinakin Mangubhai Patel 2 S. number in schedule 8 (a) 3 Proposed capacity/ area/ length/ tonnage to be handled/command area/lease area/number
More informationREPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR
REPORT OF SAND STONE MINING PROJECT (KHATADARI Q.L. No. 178 FOR Near Village Tehsil District State Capacity Lease Area Category of Project Project Cost KANTBARA BIJOLIYA Bhilwara Rajasthan 36561 TPA of
More informationAppendix I. Form 1 BASIC INFORMATION MASONARY STONE MINING PROJECT VILLAGE KOLIYA, TEHSIL DIDWANA, DISTRICT NAGAUR, RAJSTHAN
Appendix I Form 1 BASIC INFORMATION MASONARY STONE MINING PROJECT VILLAGE KOLIYA, TEHSIL DIDWANA, DISTRICT NAGAUR, RAJSTHAN AREA: 1.0 HECT (NON FOREST LAND) ML: 27/1990 ( R ) 53/2009 PROPOSED PRODUCTION
More information.APPENDIX I (See paragraph 6) FORM 1. Sl. No. Item Details 1. Name of the project/s
.APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information. Item Details 1. Name of the project/s Peddayekkaluru White Shale Mine M/s. Swathi Mines 2.. in the schedule Proposed capacity/area/length/ tonnage
More information(I) Basic Information:
(I) Basic Information: Item Details 1 Name of the project Proposed River Bed Ordinary Sand Mining At River Sharda, Village- Mudi, Gata - 443, Tehsil- Dhaurahra, District-Khiri, State-Uttar Pradesh. (Leased
More informationAPPENDIX I. (See Paragraph 6) FORM 1
APPENDIX I (See Paragraph 6) FORM 1 (I) Basic Information Item Details 1 Name of the Project Satva Shiva Gold 2 S. in the Schedule 8(a) 3 Proposed capacity/ area/ length/ tonnage to be handled/ command
More informationRenewal of Environmental Clearance for Commercial Complex City Square 2 S. No. in the Schedule 8 (a), Building & Construction project
1 SCOPING 1.1 FORM 1 The scoping for the project has been done based on Form-I, as per EIA tification, dated September 14, 2006 amended as on date. The scoping details are as follows: I. Basic Information
More informationAPPENDIX I (See paragraph 6) FORM 1. Plot area: 13,114 m 2 Built up area: 81, m 2
(I) Basic Information APPENDIX I (See paragraph 6) FORM 1 Sr. Item 1 Name of the Project Residential Project 2 S. number in schedule 8(a) Proposed 3 capacity/area/length/tonnage to be handled/command area/lease
More informationFORM 1. Basic Information Sr. No. 1 Name of the project River Sand Mining Project of Shree Sabarmati Majur Kamdar Sahakari Mandali LTD.
FORM 1 Basic Information Item Details 1 Name of the project River Sand Mining Project of Shree Sabarmati Majur Kamdar Sahakari Mandali LTD. located at Survey : 64 ne Lagu, Sabarmati Nadi Patt Village:
More informationDetails required for submitting Fresh EC Application. (Category B2 Projects: Mining of Minor Minerals)
Details required for submitting Fresh EC Application (Category B2 Projects: Mining of Minor Minerals) 1. Project Sector (Non-Coal Mining) 2. Project Type (New, Expansion, Modernization) If Project Type
More informationRevised FORM - I & PRE-FEASIBILITY REPORT
Hind Energy & Coal Beneficiaton (India) Ltd. [Change in Technology from Dry to Wet Type of Coal Washery in EC issued by MoEF letter vide no. J-11015/364/2009-IA-II(M) dated 21st May 2014] at Hindadih Village,
More informationForm I. for. Proposed Construction of High Rise Residential Cum Commercial Building Eco Gardens
Form I for Proposed Construction of High Rise Residential Cum Commercial Building Eco Gardens at T.P.S. 2, F.P.. 182/P, Sub Plot-A, OP. 43, R.S.. 85/P Vesu-Bhartana-Vesu, Tal: Choryasi Dist: Surat, Gujarat
More informationAPPENDIX I (See paragraph 6) FORM 1
APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information S.. Item Details 1. Name of the project Limestone Mine 2. S.. in the schedule S.. 1(a) mining of mineral is 3. Proposed capacity/area/length/tonnage
More informationFORM I. [Vide M.o.E.F & C.C Notification dated 14 th September, 2006] For Proposed Residential & Commercial Project ALCOVE. M/s.
FORM I [Vide M.o.E.F & C.C tification dated 14 th September, 2006] For Proposed Residential & Commercial Project ALCOVE At. 100/1, 100/2, 100/3, 100/4, 100/5, 100/6B, 101/1, 101/2, 101/3, 101/4, 101/5B,
More informationProposed Ordinary Sand Mining Project at Gata No.- 8Ka/195, Village- Ratauli, Tehsil- Laharpur, District- Sitapur, U.P. FORM 1
Proposed Ordinary Sand Mining Project at Gata.- 8Ka/195, Village- Ratauli, (I) Basic Information: Sl. Item Details. 1 Name of the project Proposed Ordinary Sand Mining Project in Sharda River at Gata.-
More informationAPPENDIX I (See paragraph - 6) FORM 1
APPENDIX I (See paragraph - 6) FORM 1 (I)Basic Information S. Item Details 1 Name of the project 1.79Acr nakti Limestone Mines (Minor Mineral) 2 S.. in schedule Category B, Project or Activity 1(a) (As
More informationApplication Forms for Prior Environmental Clearance as per Environmental Impact Assessment Notification dtd &
Application Forms for Prior Environmental Clearance as per Environmental Impact Assessment Notification dtd 14-09-2006 & 01-12-09 To be submitted By Project Proponent To Madhya Pradesh State Environmental
More informationAnnexure-IV. Form-I for seeking clearance for project attracting CRZ notification. At Thengamputhur Village, Tamil Nadu by
Annexure-IV Form-I for seeking clearance for project attracting CRZ notification Basic Information: Name of the Project :- Location or site alternative under consideration: - Construction of Beach Resort
More informationAPPENDIX I (See paragraph - 6) FORM 1
APPENDIX I (See paragraph - 6) FORM 1 (I) Basic Information S. Item Details 1 Name of the project 3.274 Ha Kapsada Limestone Mines (Minor Mineral) of M/s I.V.R.C.L Limited 2 S.. in schedule Category B,
More informationM/S Overseas Min Tech Consultants, Jaipur 1
(I) Basic Information: APPENDIX I (See paragraph 6) FORM 1 S.. Item Details 1. Name of Project Proposed Soapstone Mining Project, Khasra 60, 61, 63, Area: 11.1830Hect., Production: 17508 TPA, Near Village:
More informationA 'N 'E B 'N 'E C 'N 'E D 'N 'E
Gata. 12, Gata. 164, 352 & 1295/5 Basic Information FORM- 1 S.. Item Details 1. Name of the project/s Sand/Moram Mining 2. S.. in the schedule 1(a)i 3. Proposed capacity/area/length/tonnage to be handled
More informationFORM 1 SRI LAKSHMI GAYATRI HOSPITAL (P) LTD.
FORM 1 (Submitted to Ministry of Environment, Forests & Climate Change) BY SRI LAKSHMI GAYATRI HOSPITAL (P) LTD. Proposed at: SY. NO. 306, BACHUPALLY VILLAGE, QUTHABULLAPUR MANDAL, RANGAREDDY DISTRICT,
More informationFORM-I. Environmental Clearance (EC)
FORM-I Environmental Clearance (EC) FOR M/S. Mahanth mica mines (MICA, QUARTZ & FELDSPAR MINES) Léase Area : 47.01 Acres/ 19.05 Ha Sy.. 140/P, 142, 143/P & 139/3 Kalichedu (V), Sydapuram (M), SPSR Nellore
More informationMs.Thriveni Earthmovers Private Limited HO.22/110,Greenways Roads,Fairlands,Salem,Tamilnadu
Application for Prior (Environmental Clearance) Transfer of EC- Form 1 For Transfer of EC from Ms.K.M.Altaf Kouser to Ms.Thriveni Earthmovers Private Limited Over an Extent of 4.838 Hectares of Road Metal
More informationAPPENDIX I (See paragraph - 6) FORM 1
APPENDIX I (See paragraph - 6) FORM 1 (I) Basic Information S. Item Details 1 Name of the project Ambey Mahila Swa Sahayata Samuh 2 S.. in schedule Category B, Project or Activity 1(a) (As per EIA tification
More informationApplication for Prior Environmental Clearance (EC)
Application for Prior Environmental Clearance (EC) (See Paragraph 6 tification dated14 th September 2006) as amended to EIA tification, 2006 issued vide S.O. 3067(E) on dt.01.12.2009. Basic Information
More informationAPPLICATION FOR OBTAINING ENVIRONMENTAL CLEARANCE FOR QUARRYING BRICK EARTH. Natham Group Village. Kamuthi Taluk, Ramanathapuram District
APPLICATION FOR OBTAINING ENVIRONMENTAL CLEARANCE FOR QUARRYING BRICK EARTH AT SURVEY NOS. 275/1A4, 275/1A6, 275/1A16, 275/1A26 and 275/1A11 Natham Group Village Kamuthi Taluk, Ramanathapuram District
More informationFORM 1 (Application for Environment Clearance)
(I) Basic Information APPENDIX I (See paragraph 6) FORM 1 (Application for Environment Clearance) Name of the Project: Location / site alternatives under consideration: Size of the Project: Shreedhar Sparsh
More informationFORM 1. Basic Information. Sl. No.
(I) Basic Information FORM 1 Sl.. Item Details 1. Name of the project/s Dimensional Stone Useful For Cubes & Kerbs Quarry Of M/s. R.R Stones Private Limited 2. S.. in the schedule Item- 1(a) Mining of
More informationFORM 1 Riverbed Sand Mining Project
FORM 1 Riverbed Sand Mining Project At Gata. 117ध, 1306म ( Kuda River) Village: Gujarauliya, Beltikar, Tehsil: Naugarh, District: Siddharthnagar, Submitted by M/s Baburam Construction Address-1769 B-5
More informationFORM 1 FOR PROPOSED CONSCTRUCTION BUILDING PROJECT ( SQ. M) ANAMOL LIFE STYLE
FORM 1 FOR PROPOSED CONSCTRUCTION BUILDING PROJECT (22309.63 SQ. M) AT ANAMOL LIFE STYLE RESIDENTIAL CUM COMMERCIAL BUILDING S. No. 206, O.P. NO. 129, F.P. NO. 129 OF D.T.P.S. NO. 241, NANA CHILODA, GANDHINAGAR,
More informationApplication Form for Obtaining Environmental Clearance from State Level Environment Impact Assessment Authority (SEIAA), Tamil Nadu
Form 1 as per EIA tification 2006 for Chockampatti Earth Quarry of Thiru.T.Poosai Durai, Chockampatti Village, Kadayanallur Taluk, Tirunelveli District, Tamil Nadu State. Application Form for Obtaining
More informationITHC/PRJ/18-19/EIA/138 1 IND TECH HOUSE CONSULT
Application for Extension of Environmental Clearance (EC) UPDATED (See Paragraph 6 tification dated14 th September 2006) as amended to EIA tification, 2006 issued vide S.O. 3067(E) on dt. 01.12.2009. Basic
More informationAPPENDIX I. (See paragraph-6) FORM 1
(I) Basic Information APPENDIX I (See paragraph-6) FORM 1. Item Details 1 Name of the Project/s M/s Cane Agro Energy India Limited 2 S.. in the Schedule 5(g) 3 Proposed capacity/area/length/tonnge to be
More information30 TPH Fertilizer Blending unit for Customized NPK Production at Zuarinagar, Sancoale, Marmugao, SouthGoa, Goa
2012 Development of Viper Island as a high class tourist destination in A&N Islands with various recreational and entertainment activities Form 1 Form 1 & TOR 30 TPH Fertilizer Blending unit for Customized
More informationAPPENDIX I. (See paragraph 6) FORM 1
Form-1 & Project Feasibility Report for Mopar Limestone Mine (13.25 hect) APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information Sr. No. Item Details 1. Name of the project Mopar Limestone Mine 2. Sr.
More informationFOR THE PROPOSED EXPANSION IN BACKWARD INTEGRATION PROJECT FOR
FOR THE PROPOSED EXPANSION IN BACKWARD INTEGRATION PROJECT FOR MANUFACTURING MAN MADE FIBER (PARTIALLY ORIENTED YARN (POY), FULLY DRAWN YARM (FDY), TEXUTURISED YARN, TWISTED YARN - OTHER THAN RAYON THROUGH
More informationFORM 1. "A TREE desh. STOREY" POOJA CRAFTED HOMES PRIVATE LIMITED
FORM 1 (Submitted to SEIAA, Andhra Pradesh) By "A TREE desh. STOREY" POOJA CRAFTED HOMES PRIVATE LIMITED ( complex) NTS no: 143/3, Block no: 7 Revenue Ward. 11, 40-1-119, Patamata Village, Vijayawada (urban)
More informationFORM 1 Riverbed Sand/Morrum / Mining Project
FORM 1 Riverbed Sand/Morrum / Mining Project At Khand. 19/3 (River Betwa) Village: Tikapur, Tehsil: Maudaha District:Hamirpur, Uttar Pradesh Submitted by Suresh Chandra Gupta S/o Narayan Das Gupta R/o-60
More informationAPPENDIX I. (See paragraph 6) FORM 1
APPENDIX I (See paragraph 6) FORM 1 (I) Basic Information Sr. Item Details 1. Name of the project Mopar Limestone Mine 2. Sr. in the Schedule 1-A 3. Proposed capacity/area/length/tonnage to be handles/command
More informationJSW DHARAMTAR PORT LIMITED
JSW DHARAMTAR PORT LIMITED FORM-I FOR PROPOSED EXPANSION OF THE DHARAMTAR JETTY FACILITY VILLAGE DOLVI, PEN TALUKA, RAIGAD DISTRICT, MAHARASHTRA Submitted to: Ministry of Environment and Forests New Delhi
More informationAPPENDIX - I (See paragraph 6) FORM 1
APPENDIX - I (See paragraph 6) FORM 1 (I) Basic Information Item Details 1. Name of the project Amendment in existing Environmental Clearance i. To reduce the Mining Lease area from 281.339 ha to 252.105
More informationM/S. JUMBO MINING LIMITED Surya Arcade, 4th Floor /4F & D, Near Indian Oil Petrol Pump, Begumpet,Hyderabad Telangana.
Application for Prior Environmental Clearance (Form 1) For Proposed Colour Granite Mine over an Extent of 20.0 Hectares, in Sy..1/1 of Chinnagorigedda Village, Madugula Mandal, Visakhapatnam District,
More informationAPPENDIX I FORM 1. Basic Information:
APPENDIX I FORM 1 (I) Basic Information: S.. Item Details 1 Name of the project/s: M/s JSW Steel Limited Expansion from 10 MTPA to 16 MTPA along with Captive Power Plant 660 MW 2 S.. in the schedule 3
More informationProposed Multiplex & Commercial Complex FORM I
I. BASIC INFORMATION FORM I. Item Details 1 Name of the project Proposed Construction of Multiplex cum Commercial Complex 2 no. in the schedule 8 (a) 3 Proposed area Area Details: Total land area: 13,218.80
More informationTHE SINGARENI COLLIERIES COMPANY LIMITED (A Government Company)
APLICATION IN UPDATED FORM - I FOR ENVIRONMENTAL CLEARANCE AMENDMENT (Ref.: As per MoEF tification. S.O. 1533 dated 14.09.2006 & Subsequent Amendments vide S.O. 3067 dated 01.12.2009) IN RESPECT OF JALAGAM
More informationForm - 1 Appendix- I (See Paragraph-6)
(I) Basic Information Form - 1 Appendix- I (See Paragraph-6) Item Details 1 Name of the Project/s Construction of Proposed Residential, Commercial & Multiplex Buildings By M/s. Sahiti Infratec Ventures
More informationAPPENDIX I (See paragraph 6) FORM 1
APPENDIX I (See paragraph 6) FORM 1 VI(a) (I) Basic Information Serial Item Number Details 1. Name of the project/s Foundry Cluster Development Association 2. S.. in schedule 7 (C) 3. Proposed capacity/area/length/tonnage
More informationFORM min Village. Chowgund, Tehsil. Doru District. Anantnag State
Khasra.- 1273-min, Area: 4.459 Ha, Basic Information FORM- 1 S.. Item Details 1. Name of the project/s Limestone Mine 2. S.. in the schedule 1(a)i 3. Proposed capacity/area/length/tonnage to be/ handled
More informationForm 1, Form 1(A) and Proposed ToR for Residential Project Pramukh Aura at Chala, Taluka: Vapi & District: Valsad, Gujarat.
PYRAMID INFRA Form 1, Form 1(A) and Proposed ToR for Residential Project Pramukh Aura at Chala, Taluka: Vapi & District: Valsad, Gujarat. JANUARY 2018 CONTENTS 1 SCOPING... 4 1.1 FORM 1... 4 1.2 FORM 1(A)...
More information9 Plot/Survey/Khasra No S.No: 153/1, 153/2, 171/1, 171/2A, 172/1B1, 172/1B2, 172/C1, 172/1C2, 172/2A, 172/2B, 172/2C & 180/1.
FORM I I. BASIC INFORMATION Item Details 1 Name of the project Proposed construction of residential building by M/s. CASA GRANDE AXIOM PRIVATE LIMITED. 2 no. in the schedule 8 (a) 3 Proposed area Area
More informationM/s. PRAKRUTHI INFRA & SHELTERSS (INDIA) PVT LTD
` SUBMISSION OF FORM I & IA TOWARDS GETTING PRIOR ENVIRONMENTAL CLEARANCE (EC) For M/s. PRAKRUTHI INFRA & SHELTERSS (INDIA) PVT LTD (Residential Apartment Construction Project) Sy.. 298/1 & 2 Vepagunta,
More informationMOHIT PETROCHEMICALS (P) LTD, (NAGINA ROAD, BIJNOR)
UPDATED FORM 1 SUBMISSION TO MINISTRY OF ENVIRONMENT, FORESTS & CLIMATE CHANGE, NEW DELHI MOHIT PETROCHEMICALS (P) LTD, (NAGINA ROAD, BIJNOR) [AMENDMENT IN ENVIRONMENTAL CLEARANCE] VILLAGE : FIROZPUR HAFIZ
More informationHaridarshan Residency ( Row Type House & School Building )
Survey.. 18, Moje: : Shekhpur, Tal: Kamrej, Dist.: Surat, Gujarat 394 130 FORM 1 AND BASIC INFORMATION FOR OBTAINING ENVIRONMENTAL CLEARANCE FOR NEW PROJECT OF Haridarshan Residency Block. 18, Village:
More informationJAI MAA SHARDA STONE CRUSHING
JAI MAA SHARDA STONE CRUSHING Prop. Hukum Singh (M.. 9425585252) Near-Pahunadukan Kedarpur Ambikapur, (C.G.) To, The Member Secretary, SLEIAA(State Level Environment Impact Assessment Authority), Ministry