The following sections provide the approved standard infiltration testing specifications.

Size: px
Start display at page:

Download "The following sections provide the approved standard infiltration testing specifications."

Transcription

1 APPENDIX F.2 INFILTRATION TESTING To properly size and locate stormwater management facilities, it is necessary to characterize the soil infiltration conditions at the location of the proposed facility. All projects that propose onsite infiltration must evaluate existing site conditions and determine: 1. If the infiltration rate is adequate to support the proposed stormwater management facility (satisfied through the Simplified Approach infiltration test). or 2. The design infiltration rate prior to facility design (satisfied through Presumptive or Performance infiltration testing conducted by a qualified professional). The following sections provide the approved standard infiltration testing specifications. Simplified Approach Open Pit Infiltration Test The purpose of the Simplified Approach is to provide a method which can be conducted by a nonprofessional for design of simple stormwater systems on small projects. The Simplified Approach open pit test is applicable only to projects on private property with less than 10,000 square feet of new or redeveloped impervious area (see Section 2.2.1). The results of infiltration testing must be documented on the Simplified Approach Form (see Appendix D.3). The Simplified Approach cannot be used to find a design infiltration rate. The intent of the open pit test is to determine whether or not the local infiltration rate is adequate (2 inches/hour or greater) for the predesigned stormwater facilities described in Section 2.3 (infiltration swales, basins, planters, drywells, and trenches). The Simplified Approach Infiltration Test does not need to be conducted by a licensed professional. Simplified Approach Procedure 1. A simple open pit infiltration test is required for each facility designed through the Simplified Approach. The test should be where the facility is proposed or within the immediate vicinity. 2. Excavate a test hole to the depth of the bottom of the infiltration system, or otherwise to 4 feet. The test hole can be excavated with small excavation equipment or by hand using a shovel, auger, or post hole digger. If a layer hard enough to prevent further excavation is encountered, or if noticeable moisture/water is encountered in the soil, stop and measure this depth from the surface and record it on the Simplified Approach Form. Proceed with the test at this depth. F.2-1

2 3. Fill the hole with water to a height of about 6 inches from the bottom of the hole, and record the exact time. Check the water level at regular intervals (every 1 minute for fast-draining soils to every 10 minutes for slower-draining soils) for a minimum of 1 hour or until all of the water has infiltrated. Record the distance the water has dropped from the top edge of the hole. 4. Repeat this process two more times, for a total of three rounds of testing. These tests should be performed as close together as possible to accurately portray the soil s ability to infiltrate at different levels of saturation. The third test provides the best measure of the saturated infiltration rate. 5. For each test pit required, submit all three testing results with the date, duration, drop in water height, and conversion into inches per hour. If the results of the Simplified Approach open pit test show an infiltration rate greater than 2.0 inches per hour, the applicant can proceed with Simplified Approach facility design (where applicable). If the applicant would like to use an infiltration rate for design purposes, a Presumptive or Performance Infiltration Test must be conducted. Presumptive and Performance Infiltration Testing The Presumptive Approach (Section 2.2.2) or Performance Approach (Section 2.2.3) must be used for all public and private developments where the Simplified Approach is not applicable. The qualified professional must exercise judgment in the selection of the infiltration test method. The three infiltration available testing methods used to determine a design infiltration rate are: Open pit falling head (see page F.2-4) Encased falling head (see page F.2-6) Double-ring infiltrometer (see page F.2-7) Where satisfactory data from adjacent areas is available that demonstrates infiltration testing is not necessary, the infiltration testing requirement may be waived. Waiver of the site specific testing is subject to approval by the city stormwater system design reviewer. Recommendation for foregoing infiltration testing must be submitted in a report which includes supporting data and is stamped and signed by the project geotechnical engineer or project geologist. F.2-2

3 Testing Criteria 1. Testing must be conducted or overseen by a qualified professional. This professional must be a Professional Engineer (PE) or Registered Geologist (RG) licensed in the State of Oregon. 2. The depth of the test must correspond to the facility depth. If a confining layer, or soil with a greater percentage of fines, is observed during the subsurface investigation to be within 4 feet of the bottom of the planned infiltration system, the testing should be conducted within that confining layer. Based on DEQ requirements and conformance with Appendix F.1, the boring log must be continued to a depth adequate to show separation between the bottom of the infiltration facility and the seasonal high groundwater level. (The boring depth will vary, based on facility depth.) See Appendix F.1 for further details on depth to water investigations. 3. Tests must be performed in the immediate vicinity of the proposed facility. Exceptions can be made to the test location provided the qualified professional can support that the strata are consistent from the proposed facility to the test location. 4. Infiltration testing should not be conducted in engineered or undocumented fill. Minimum Number of Required Tests Land Division A total of two infiltration tests for every 10,000 square feet of lot area available for new or redevelopment. An additional test for every 10,000 square feet of lot area available for new or redevelopment. At least one test for any potential street facility. One test for every 100 lineal feet of infiltration facility. No more than five tests are required per development (at the discretion of the qualified professional assessing the site, as well as the City of Portland). Tests performed for a proposed land division can be used at the building permit stage as long as the results of the test are submitted with the separate applications. Building Permits The Simplified Approach requires one infiltration test for every proposed facility. The Presumptive and Performance Approaches: F.2-3

4 Require at least one test for any proposed street facility. Require one test for every 100 lineal feet of proposed infiltration facility. The number of tests is at the discretion of the qualified professional assessing the site, as well as the City of Portland. Where multiple types of facilities are used, it is likely that multiple tests will be necessary, since an infiltration test can test only a single soil stratum. It is highly recommended to conduct an infiltration test at each stratum used. City staff reserve the right to require additional testing. Factors of Safety Exhibit F.2-1 lists the minimum allowable factors of safety applied to field obtained infiltration rates for use in stormwater system design. To obtain the infiltration rate used in design, divide the infiltration rate measured in the field by the factor of safety. The factor of safety used in design should be chosen by collaboration between the geotechnical engineer or geologist overseeing the infiltration testing and the civil engineer designing the stormwater management system. Determination of the factor of safety should include consideration of project specific conditions such as soil variability, testing methods, consequences of system failure, complexity of proposed construction, etc. Note that the maximum allowable design infiltration rate is 20 inches per hour. Exhibit F.2-1: Minimum Allowable Factor of Safety Test Method Minimum Required Factor of Safety Encased Falling Head 2 Open Pit Falling Head 2 Double-Ring Infiltrometer Public Facilities: 1 Private Facilities: 2 Presumptive & Performance Infiltration Testing Instructions Open Pit Falling Head Procedure The open pit falling head procedure is performed in an open excavation and therefore is a test of the combination of vertical and lateral infiltration. 1. Excavate a hole with bottom dimensions of approximately 2 feet by 2 feet into the native soil to the elevation of the proposed facility bottom. The test can be F.2-4

5 conducted in a machine-excavated pit or a hand-dug pit using a shovel, post hole digger, or hand auger. If smooth augering tools or a smooth excavation bucket is used, scratch the sides and bottom of the hole with a sharp pointed instrument, and remove the loose material from the bottom of the test hole. 2. Fill the hole with clean water a minimum of 1 foot above the soil to be tested, and maintain this depth of water for at least 4 hours (or overnight if clay soils are present) to presoak the native material. In sandy soils with little or no clay or silt, soaking is not necessary. If after filling the hole twice with 12 inches of water, the water seeps completely away in less than 10 minutes, the test can proceed immediately. 3. Determine how the water level will be accurately measured. The measurements should be made with reference to a fixed point. A lath placed in the test pit prior to filling or a sturdy beam across the top of the pit are convenient reference points. The tester and excavator should conduct all testing in accordance with OSHA regulations. 4. After the presaturation period, refill the hole with water to 12 inches above the soil and record the time. Alternative water head heights may be used for testing provided the presaturation height is adjusted accordingly and the water head height used in infiltration testing is 50 percent or less than the water head height in the proposed stormwater system during the design storm event. Measure the water level to the nearest 0.01 foot (⅛ inch) at 10-minute intervals for a total period of 1 hour (or 20-minute intervals for 2 hours in slower soils) or until all of the water has drained. In faster draining soils (sands and gravels), it may be necessary to shorten the measurement interval in order to obtain a well defined infiltration rate curve. Constant head tests may be substituted for falling head tests at the discretion of the professional overseeing the infiltration testing. 5. Repeat the test. Successive trials should be run until the percent change in measured infiltration rate between two successive trials is minimal. The trial should be discounted if the infiltration rate between successive trials increases. At least three trials must be conducted. After each trial, the water level is readjusted to the 12 inch level. Enter results into the data table (See Exhibit F.2-3). 6. The average infiltration rate over the last trial should be used to calculate the unfactored infiltration rate. Alternatively, the infiltration rate measured over the range of water head applicable to the project stormwater system design may be used at the discretion of the professional overseeing the testing. The final rate must be reported in inches per hour. See the calculation following Exhibit F.2-3. F.2-5

6 7. Upon completion of the testing, the excavation must be backfilled. 8. For very rapidly draining soils, it may not be possible to maintain a water head above the bottom of the test pit. If the infiltration rate meets or exceeds the flow of water into the test pit, conduct the test in the following manner: A. Approximate the area over which the water is infiltrating. B. Using a water meter, bucket, or other device, measure the rate of water discharging into the test pit. C. Calculate the infiltration rate by dividing the rate of discharge (cubic inches per hour) by the area over which it is infiltrating (square inches). Note that a maximum infiltration rate of 20 inches per hour can be used in stormwater system design. Encased Falling Head Test The encased falling head procedure is performed with a 6-inch casing that is embedded approximately 6 inches into the native soil. The goal of this field test is to evaluate the vertical infiltration rate through a 6-inch plug of soil, without allowing any lateral infiltration. The test is not appropriate in gravelly soils or in other soils where a good seal with the casing cannot be established. 1. Embed a solid 6-inch diameter casing into the native soil at the elevation of the proposed facility bottom (see Exhibit F.2-2). Ensure that the embedment provides a good seal around the pipe casing so that percolation will be limited to the 6-inch plug of the material within the casing. This method can also be used when testing within hollow stem augers, provided the driller and tester are reasonably certain that a good seal has been achieved between the soil and auger. 2. Fill the pipe with clean water a minimum of 1 foot above the soil to be tested, and maintain this depth for at least 4 hours (or overnight if clay soils are present) to presoak the native material. Any soil that sloughed into the hole during the soaking period should be removed. In sandy soils with little or no clay or silt, soaking is not necessary. If after filling the hole twice with 12 inches of water, the water seeps completely away in less than 10 minutes, the test can proceed immediately. 3. To conduct the first trial of the test, fill the pipe to approximately 12 inches above the soil and measure the water level to the nearest 0.01 foot (⅛ inch). Alternative water head heights may be used for testing provided the presaturation height is F.2-6

7 adjusted accordingly and the water head height used in infiltration testing is 50 percent or less than the water head height in the proposed stormwater system during the design storm event. The level should be measured with a tape or other device with reference to a fixed point. The top of the pipe is often a convenient reference point. Record the exact time. 4. Measure the water level to the nearest 0.01 foot (⅛ inch) at 10-minute intervals for a total period of 1 hour (or 20-minute intervals for 2 hours in slower soils) or until all of the water has drained. In faster draining soils (sands and gravels), it may be necessary to shorten the measurement interval in order to obtain a well defined infiltration rate curve. Constant head tests may be substituted for falling head tests at the discretion of the professional overseeing the infiltration testing. Successive trials should be run until the percent change in measured infiltration rate between two successive trials is minimal. The trial should be discounted if the infiltration rate between successive trials increases. At least three trials must be conducted. After each trial, the water level is readjusted to the 12 inch level. Enter results into the data table (see Exhibit F.2-3). 5. The average infiltration rate over the last trial should be used to calculate the unfactored infiltration rate. Alternatively, the infiltration rate measured over the range of water head applicable to the project stormwater system design may be used at the discretion of the professional overseeing the testing. The final rate must be reported in inches per hour. See the calculation following Exhibit F Upon completion of the testing, the casing should be pulled and the test pit backfilled. F.2-7

8 Exhibit F.2-2: Encased Falling Head Procedure EXISTING GROUND SURFACE EXCAVATE OR USE SOIL-BORING CASING GOOD SEAL BETWEEN SOIL AND CASING IS NECESSARY 6" DIAMETER SOLID CASING 6" PROPOSED DEPTH OF TRENCH OR FACILITY BOTTOM Double Ring Infiltrometer Test The double-ring infiltrometer test procedure should be performed in accordance with ASTM The test is performed within two concentric casings embedded and sealed to the native soils. The outer ring maintains a volume of water to diminish the potential of lateral infiltration through the center casing. The volume of water added to the center ring to maintain a static water level is used to calculate the infiltration rate. The double-ring infiltrometer is appropriate only in soils where an adequate seal can be established. F.2-8

9 Reporting Requirements The following information should be included in the Infiltration Testing Report. The Infiltration Testing Report should be attached to the project s Stormwater Management Report: 1. Statement of project understanding (proposed stormwater system). 2. Summary of subsurface conditions encountered. 3. Summary of infiltration testing including location and number of tests and testing method used. Discussion of how the tests were performed (i.e. pipe type or diameter or test pit dimensions). 4. Infiltration testing results in inches per hour. 5. Recommended design infiltration rate. 6. Groundwater observations within exploration and an estimate of the depth to seasonal high groundwater. 7. Site plan showing location of infiltration tests. 8. Boring or test pit logs. The logs should include an associated soil classification consistent with ASTM D , Standard Practice for Classification for Description and Identification of Soils (Visual-Manual Procedure). The logs should also include any additional pertinent subsurface information, such as soil moisture conditions, depth and description of undocumented or engineered fill, soil color and mottling conditions, soil stiffness or density, and approximate depth of contact between soil types. 9. Infiltration Test Data Tables (see following pages for example and blank tables) F.2-9

10 Exhibit F.2-3: Example Infiltration Test Data Table Location: Lot 105, Point Heights Subdivision Depth to bottom of hole: 57 inches Tester s Name: C.J. Tester Tester s Company: Tester Company Tester s Contact Number: Depth (feet): Date: 6/28/2008 Test Hole Number: 3 Dimension of hole: 0.5 feet diameter Soil Texture: Black Top Soil Brown SM Brown ML Brown CL Presaturation Start Time: Presaturation End Time: Time: Time interval (minutes): Measure ment, (feet): Drop in water level, (feet): Infiltration rate, (inches per hour): Test Method: Encased Falling Head Remarks: 9: Filled with 6 9: : : : : : : Adjusted to 6 level for Trial #2 Calculation is performed for each water level drop = (Drop in water level/time interval) x conversion = 0.055ft/20min x (12in/ft) x (60min/hr) = 1.98 inches per hour F.2-10

11 Location: Date: Test Hole Number: Depth to bottom of hole: Dimension of hole: Test Method: Tester s Name: Tester s Company: Tester s Contact Number: Depth (feet): Soil Texture: Presaturation Start Time: Presaturation End Time: Time: Time Interval (minutes): Measure ment, (feet): Drop in water level, (feet): Infiltration rate, (inches per hour): Remarks: F.2-11

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide

Stormwater Standards. Clackamas County Service District No. 1. Infiltration Testing Guide Stormwater Standards Clackamas County Service District No. 1 APPENDIX E Infiltration Testing Guide Table of Contents Appendix E - Infiltration Testing Guide... Page E.1 General... 1 E.2 Basic Method -

More information

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities

Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities Determination of Design Infiltration Rates for the Sizing of Infiltration based Green Infrastructure Facilities 1 Introduction This document, developed by the San Francisco Public Utilities Commission

More information

Native Soil Assessment for Small Infiltration- Based Stormwater Control Measures

Native Soil Assessment for Small Infiltration- Based Stormwater Control Measures Native Soil Assessment for Small Infiltration- Based Stormwater Control Measures Prepared for the Central Coast Low Impact Development Initiative by Dennis Shallenberger, PE, GE, and Robert Down, PE of

More information

UC SANTA CRUZ NATIVE SOIL ASSESSMENT FOR SMALL INFILTRATION BASED STORMWATER CONTROL MEASURES

UC SANTA CRUZ NATIVE SOIL ASSESSMENT FOR SMALL INFILTRATION BASED STORMWATER CONTROL MEASURES CAMPUS STANDARDS APPENDIX F UC SANTA CRUZ NATIVE SOIL ASSESSMENT FOR SMALL INFILTRATION BASED STORMWATER CONTROL MEASURES December 2013 Native Soil Assessment for Small Infiltration- Based Stormwater Control

More information

Maria Cahill, Green Girl Land Development Solutions; Derek C. Godwin and Marissa Sowles, Oregon Sea Grant Extension

Maria Cahill, Green Girl Land Development Solutions; Derek C. Godwin and Marissa Sowles, Oregon Sea Grant Extension Maria Cahill, Green Girl Land Development Solutions; Derek C. Godwin and Marissa Sowles, Oregon Sea Grant Extension IInfiltration tests estimate the rate at which runoff will pass through the native soil

More information

STORMWATER MANAGEMENT. 158 Attachment 2. Borough of Perkasie

STORMWATER MANAGEMENT. 158 Attachment 2. Borough of Perkasie 158 Attachment 2 Borough of Perkasie Appendix B Site Soil Evaluation and Soil Infiltration Testing Source: Pennsylvania Stormwater Best Management Practice Manual, December 2006. SITE SOIL EVALUATION AND

More information

To The Applicant For A Small Wastewater System Permit Sheridan County, Wyoming

To The Applicant For A Small Wastewater System Permit Sheridan County, Wyoming To The Applicant For A Small Wastewater System Permit Sheridan County, Wyoming PRIOR TO SUBMITTING APPLICATION 1) Ground water test pit This pit is required to be inspected by a representative of Sheridan

More information

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 November 13, 2015 103IP3406 Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 Subject: Infiltration Testing Hopeland Road Valve Site Sunoco Pennsylvania Pipeline

More information

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112

November 13, IP3406. Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 November 13, 2015 103IP3406 Mr. Uriah Sowell Rooney Engineering 115 Inverness Drive East, Suite 300, Englewood, CO 80112 Subject: Infiltration Testing Gates Road Valve Site Sunoco Pennsylvania Pipeline

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 1 (GR) GR8 June 2015 GR8.01 Purpose This Chapter establishes the standards for performing subsurface investigations for CUE Projects. Although not required for

More information

CHAPTER 4 GEOTECHNICAL SITE CHARACTERIZATION

CHAPTER 4 GEOTECHNICAL SITE CHARACTERIZATION CHAPTER 4 GEOTECHNICAL SITE CHARACTERIZATION Chapter Organization 4.1 Introduction... 4-1 4.2 Applicability... 4-1 4.3 Minimimum Requirements... 4-2 4.3.1 Geotechnical Site Characterization Report... 4-3

More information

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1

April 7, Webster Street Sub-Surface Stormwater Storage System Bid No Bid Date: 4/13/17 ADDENDUM NO 1 PUBLIC WORKS DEPARTMENT David A. Jones, P.E., Director April 7, 2017 Webster Street Sub-Surface Stormwater Storage System Bid No. 2017-022 Bid Date: 4/13/17 ADDENDUM NO 1 Please make the following changes

More information

***NO SEPTIC SYSTEM EXCAVATION WITHOUT AN APPROVED PERMIT IN POSSESSION****

***NO SEPTIC SYSTEM EXCAVATION WITHOUT AN APPROVED PERMIT IN POSSESSION**** SMALL WASTEWATER FACILITY APPLICATION PACKET A PERCOLATION TEST WITH A 10 SITE HOLE AND/OR AN APPLICATION ALONG WITH AN ADDRESS MUST BE COMPLETED AND SUBMITTED TO THE DIVISION OF ENVIRONMENTAL HEALTH BEFORE

More information

PROJECT NO A. ISSUED: February 29, 2016

PROJECT NO A. ISSUED: February 29, 2016 INTERPRETIVE REPORT FOR INFILTRATION SYSTEM DESIGN, PROPOSED VILLA VERONA APARTMENT COMMUNITY, ASSESSOR S PARCEL NUMBERS 311-040-015, 311-040-021, 311-040-024, 311-040-026 AND 311-040-013, LOCATED ON THE

More information

Wyoming Water Quality Application Form Permit to Construct Small Wastewater System. Complete attached package and submit to appropriate office:

Wyoming Water Quality Application Form Permit to Construct Small Wastewater System. Complete attached package and submit to appropriate office: Wyoming Water Quality Application Form Permit to Construct Small Wastewater System Conventional Septic System with Leachfield less than 2,000 gallons per day only. Not to be used for mound, evaporation

More information

Appendix A. Infiltration and Soil Texture Testing Methods. Appendix A. A.1 General Description. A.2 Infiltration Testing: A Four-Step Process

Appendix A. Infiltration and Soil Texture Testing Methods. Appendix A. A.1 General Description. A.2 Infiltration Testing: A Four-Step Process Infiltration and Soil Texture Testing Methods A.1 General Description Appendix A A.2 Infiltration Testing: A Four-Step Process A.3 Other Soil Tests A.3.1 Soil Compaction Bulk Density Tests A.3.2 Soil Contamination

More information

The Presby Wastewater Treatment System

The Presby Wastewater Treatment System The Presby Wastewater Treatment System Advanced Enviro-Septic WYOMING APPLICATION PACKAGE FOR PERMIT TO CONSTRUCT (Five Bedrooms - 550 GPD or Less) Presby Environmental, Inc. The Next Generation of Wastewater

More information

GRAY WATER RECYCLING SYSTEMS

GRAY WATER RECYCLING SYSTEMS GRAY WATER RECYCLING SYSTEMS Note: Section P2601.2 of the International Residential Code requires all plumbing fixtures that receive water or waste to discharge to the sanitary drainage system of the structure.

More information

ADMINISTRATIVE MANUAL COUNTY OF LOS ANGELES 6/30/17 DEPARTMENT OF PUBLIC WORKS GEOTECHNICAL AND MATERIALS ENGINEERING DIVISION

ADMINISTRATIVE MANUAL COUNTY OF LOS ANGELES 6/30/17 DEPARTMENT OF PUBLIC WORKS GEOTECHNICAL AND MATERIALS ENGINEERING DIVISION ADMINISTRATIVE MANUAL GS200.2 COUNTY OF LOS ANGELES 6/30/17 DEPARTMENT OF PUBLIC WORKS GEOTECHNICAL AND MATERIALS ENGINEERING DIVISION GUIDELINES FOR GEOTECHNICAL INVESTIGATION AND REPORTING LOW IMPACT

More information

The Presby Wastewater Treatment System

The Presby Wastewater Treatment System The Presby Wastewater Treatment System Advanced Enviro-Septic WYOMING APPLICATION PACKAGE FOR PERMIT TO CONSTRUCT (Five Bedrooms - 550 GPD or Less) Presby Environmental, Inc. The Next Generation of Wastewater

More information

CITY OF MONTCLAIR Montclair Civic Center 5111 Benito Street Montclair, CA 91763

CITY OF MONTCLAIR Montclair Civic Center 5111 Benito Street Montclair, CA 91763 CITY OF MONTCLAIR Montclair Civic Center 5111 Benito Street Montclair, CA 91763 I. Introduction Water Quality A National, State, and Local Concern Throughout the United States, many rivers, creeks, streams,

More information

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS Highway 99 and Kelly Street TABLE OF CONTENTS PROJECT INFORMATION... 1 FIELD EXPLORATION... 1 SITE CONDITIONS... 2 Surface Conditions:... 2 Subsurface Conditions:... 2 FILL.... 2 Topsoil.... 2 Clay Alluvium....

More information

Re: Geotechnical Consultation for Storm Infiltration Robert Louis Stevenson ES Modernization th Avenue San Francisco, California

Re: Geotechnical Consultation for Storm Infiltration Robert Louis Stevenson ES Modernization th Avenue San Francisco, California Date: August 4, 2015 Project No.: 608-4-2 Prepared For: Mr. Sajeev Madhaven, AIA SAN FRANCISCO UNIFIED SCHOOL DISTRICT 135 Van Ness Avenue - Room 207a San Francisco, California 94102 Re: Geotechnical Consultation

More information

Appendix B.2. Construction Specifications for Infiltration Practices

Appendix B.2. Construction Specifications for Infiltration Practices Appendix B.2 Construction Specifications for Infiltration Practices B.2.A Infiltration Trench General Notes and Specifications An infiltration trench may not receive run-off until the entire contributing

More information

March 28, Port of Kalama Mr. Jacobo Salan 380 West Marine Drive Kalama, Washington 98625

March 28, Port of Kalama Mr. Jacobo Salan 380 West Marine Drive Kalama, Washington 98625 11917 NE 95 th Street, Vancouver, Washington 98682 Phone: 360-823-2900, Fax: 360-823-2901 March 28, 2014 Port of Kalama Mr. Jacobo Salan 380 West Marine Drive Kalama, Washington 98625 Re: Construction

More information

August 15, 2006 (Revised) July 3, 2006 Project No A

August 15, 2006 (Revised) July 3, 2006 Project No A August 15, 2006 (Revised) July 3, 2006 Project No. 01-05-0854-101A Mr. David Reed, P.E. Protean Design Group 100 East Pine Street, Suite 306 Orlando, Florida 32801 Preliminary Soil Survey Report Polk Parkway

More information

Typical Subsurface Profile. November 28, 2016

Typical Subsurface Profile. November 28, 2016 November 28, 2016 RSCCD Facility Planning, District Construction and Support Services 2323 N. Broadway, Suite 112, Santa Ana, CA 92706 Attn: Re: Ms. Allison Coburn Facilities Project Manager P: (714) 480-7530

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

SMALL WASTEWATER FACILITY APPLICATION PACKET

SMALL WASTEWATER FACILITY APPLICATION PACKET SMALL WASTEWATER FACILITY APPLICATION PACKET A PERCOLATION TEST AND/OR AN APPLICATION ALONG WITH AN ADDRESS MUST BE COMPLETED AND SUBMITTED TO THE DIVISION OF ENVIRONMENTAL HEALTH BEFORE A PERMIT TO INSTALL

More information

EXHIBIT G GEOTECHNICAL REPORT (DRAFT)

EXHIBIT G GEOTECHNICAL REPORT (DRAFT) EXHIBIT G GEOTECHNICAL REPORT (DRAFT) APPENDIX 1 PROJECT SITE 'B' B-1 B-2 I-2 B-3 B-4 B-5 I-1 PROJECT LOCATION LEGEND B-1 = APPROXIMATE BORING LOCATION I-1 = APPROXIMATE INFILTRATION

More information

Appendix A - Vicinity Map Vicinity Map: Palm Beach Gardens City Hall Additions, 000 N Military Trail, Palm Beach Gardens, FL Proposed Location of Police Dept. Attached Addition Proposed Location of New

More information

A-2. Soils. Soil Media. Chapter Contents. Soil Media In-situ Soil Testing Separation from Seasonal High Water Table (SHWT)

A-2. Soils. Soil Media. Chapter Contents. Soil Media In-situ Soil Testing Separation from Seasonal High Water Table (SHWT) A-2. Soils Chapter Contents Soil Media In-situ Soil Testing Separation from Seasonal High Water Table (SHWT) Importance of Soil Composition in SCMs The soil composition of many stormwater SCMs also is

More information

STARK COUNTY HEALTH DEPAIRmEm

STARK COUNTY HEALTH DEPAIRmEm STARK COUNTY HEALTH DEPAIRmEm 4424 US Hwy 34, mwanee, ILLINOIS 6 1443 309-8523 1 15 Dear Applicant: This is your private sewage packet. Enclosed within this packet is important information regarding specifications

More information

South Sound Geotechnical Consulting P.O. Box Lakewood, WA (253) Figure 1 Site Plan. SERA Playground Tacoma, WA.

South Sound Geotechnical Consulting P.O. Box Lakewood, WA (253) Figure 1 Site Plan. SERA Playground Tacoma, WA. N TP -3, E3RA TP -4, E3RA TP -2, E3RA B -6, Terracon HA -2 HA -3 HA -1 TP -1, E3RA Legend HA-1 Approximate Hand Excavation Location by SSGC Approximate Exploration Location by others Scale: NTS South Sound

More information

We have completed the geotechnical investigation for the above-referenced project. Our findings and recommendations are summarized below.

We have completed the geotechnical investigation for the above-referenced project. Our findings and recommendations are summarized below. Foundation Engineering, Inc. Professional Geotechnical Services Memorandum Date: September 7, 2017 To: Unitarian Universalist Fellowship Corvallis c/o Chris Bentley From: Subject: Project: James K. Maitland,

More information

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards... SECTION 02210 - SITE GRADING CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement and Payment...

More information

August 13, Geotechnical Recommendations, New Physical Education Building, Chabot College, Hayward, California

August 13, Geotechnical Recommendations, New Physical Education Building, Chabot College, Hayward, California August 13, 2008 003-09176-17 Douglas Horner, AIA Chabot Las Positas Community College District 25555 Hesperian Boulevard Hayward, California 94545 Subject: Geotechnical Recommendations, New Physical Education

More information

Subsurface Environmental Investigation

Subsurface Environmental Investigation Subsurface Environmental Investigation Lake Development East Lake and 21 st Avenue South February 23, 201 Terracon Project No. MP14738A Prepared for: Minneapolis Public Schools Prepared by: Terracon Consultants,

More information

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER CHAPTER 3 Site Preparation In preparation for constructing buildings on a property, the builder must consider a number of factors related to code requirements. The buildings must be located according to

More information

SECTION SOILS REPORT

SECTION SOILS REPORT SECTION 02300 SOILS REPORT 1. GENERAL: 1.1 All work included under this heading shall be subject to the General Conditions of the entire operation. This Contractor is required to refer especially thereto.

More information

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering Earth Mechanics, Inc. Geotechnical & Earthquake Engineering TECHNICAL MEMORANDUM DATE: June 3, 2009 EMI PROJECT NO: 01-143 TO: COPY: FROM: SUBJECT: John Chun, P.E. / Port of Long Beach (POLB) Jorge Castillo

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET. Revised Soil Survey Report November 24, 2015 Matthew G. Moore, P.E.

DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET. Revised Soil Survey Report November 24, 2015 Matthew G. Moore, P.E. LD-0 /12/09 DEPARTMENT OF TRANSPORTATION DIVISION: MATERIALS REPORT COVER SHEET Revised Soil Survey Report November 2, 201 Matthew G. Moore, P.E. VDOT (Division) or Company Name Insert Location, Virginia

More information

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida

mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA Construct Bin Wall at HERD Eglin AFB, Florida mtec REPORT OF GEOTECHNICAL EXPLORATION FTFA 14-3001 - Construct Bin Wall at HERD Eglin AFB, Florida MTEC Project Number 2014-101 November 10, 2014 Revised: January 5, 2015 Prepared For: Peterson Engineering,

More information

Geotechnical Investigation

Geotechnical Investigation REVISED Geotechnical Investigation Pueblo Pintado Tank Site Includes NGWSP Reaches 26.1 & 26.2 Pueblo Pintado in New Mexico Prepared for: Souder, Miller & Associates Project No.: 15-1-057 June 9, 2016

More information

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Michigan Department Of Transportation 3703B (11/06) 1 Materials SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006 Page 1 of 5 1.1 Pipe - Pipe used in this method includes an external steel

More information

City of Vineland Health Department 640 E. Wood Street, Vineland, NJ (856) (ph.) / (856) (fax)

City of Vineland Health Department 640 E. Wood Street, Vineland, NJ (856) (ph.) / (856) (fax) Permit No. Form 1 General Information Type of Permit Needed (Check Applicable Category): New Construction New (Existing Structure) Repair *Malfunctioning (In-Kind Replacement) Repair No Malfunction (In-Kind

More information

SepticDesign.ca Gunnell Engineering Ltd.

SepticDesign.ca Gunnell Engineering Ltd. SepticDesign.ca Gunnell Engineering Ltd. Presentation Summary Best Practices Code Context Prior to Attending the Site When on Site Site Assessment Assessing Existing Sewage Systems The Septic Test Pit

More information

Public Health STARK COUNTY HEALTH DEPARTMENT

Public Health STARK COUNTY HEALTH DEPARTMENT Public Health Prevent. Promote. Protect. Dear Applicant: STARK COUNTY HEALTH DEPARTMENT 4424 US Hwy 34, Kewanee, IL 61443 309-852-3115 www.henrystarkhealth.com This is your private sewage packet. Enclosed

More information

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description

This report presents the findings of the subsurface exploration concerning the design of the taxiway rehabilitation. Description September 22, 2016 American Infrastructure Development, Inc. 3810 Northdale Boulevard, Suite 170 Tampa, Florida 33624 Attn: Mr. Mohsen Mohammadi, Ph.D., P.E. Senior Consultant Mob: (813) 244-6609 E-mail:

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

November 2007 DRAFT Appendix E: Soil Testing Criteria

November 2007 DRAFT Appendix E: Soil Testing Criteria November 2007 DRAFT Appendix E: Soil Testing Criteria Stormwater management design is dependent upon the changes that occur between pre and postdevelopment conditions. The impacts are assessed based on

More information

TRIP REPORT ARCONA ROAD VALVE SITE INFILTRATION TESTING

TRIP REPORT ARCONA ROAD VALVE SITE INFILTRATION TESTING TRIP REPORT ARCONA ROAD VALVE SITE INFILTRATION TESTING 1.0 PURPOSE This Trip Report presents the field data and results of double-ring soil infiltration tests conducted to support the design of a stormwater

More information

INYO COUNTY ENVIRONMENTAL HEALTH SERVICES RESIDENTIAL ONSITE SEWAGE TREATMENT AND DISPOSAL GUIDE

INYO COUNTY ENVIRONMENTAL HEALTH SERVICES RESIDENTIAL ONSITE SEWAGE TREATMENT AND DISPOSAL GUIDE INYO COUNTY ENVIRONMENTAL HEALTH SERVICES RESIDENTIAL ONSITE SEWAGE TREATMENT AND DISPOSAL GUIDE I. SCOPE This guide has been prepared to inform the residential property owner of the permitting process

More information

Water Resources Management Plan

Water Resources Management Plan B u r n s v i l l e M i n n e s o t a Water Resources Management Plan - Volume Control / Infiltration Worksheet This Appendix contains a worksheet and related information that can be used for evaluating

More information

GEOTECHNICAL SUPPLEMENT NO. 1: STORMWATER INFILTRATION

GEOTECHNICAL SUPPLEMENT NO. 1: STORMWATER INFILTRATION GEOTECHNICAL SUPPLEMENT NO. 1: STORMWATER INFILTRATION Central Kitsap High School and Middle School Redevelopment 13 Frontier Place NW and 37 NW Anderson Hill Road Silverdale, Washington Prepared for:

More information

Civil Geotechnical Surveying

Civil Geotechnical Surveying Civil Geotechnical Surveying Mr. David Burnett Cabarrus County Schools 4425 Old Airport Road Charlotte, North Carolina 28025 May 16, 2017 Reference: Geotechnical Engineering Evaluation Future PLC Site

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of stormwater as it infiltrates into the ground. Dry wells, infiltration

More information

SECTION UTILITY BACKFILL MATERIALS

SECTION UTILITY BACKFILL MATERIALS SECTION 31 23 23 UTILITY BACKFILL MATERIALS PART 1: GENERAL 1.01 SECTION INCLUDES A. Material Classifications B. : 1. Concrete sand 2. Gem sand 3. Pea gravel 4. Crushed stone 5. Crushed concrete 6. Bank

More information

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois AGI Project No. 13-109B Subsurface Investigation Report For the Proposed Roosevelt Middle School Site Improvements 7560 Oak Avenue River Forest, Illinois Prepared for Mr. Jerry Pilipowicz Terra Engineering,

More information

Results of Onsite Percolation Testing Ellis Commons Senior Housing Development APN City of Perris, California

Results of Onsite Percolation Testing Ellis Commons Senior Housing Development APN City of Perris, California Lansing Companies 12671 High Bluff Drive, Suite 150 San Diego, California 92130 April 18, 2017 Project No. 11607.001 Attention: Subject: References: Mr. Casey Malone Results of Onsite Percolation Testing

More information

4.8. Subsurface Infiltration

4.8. Subsurface Infiltration 4.8. Subsurface Infiltration Subsurface infiltration systems are designed to provide temporary below grade storage infiltration of storm water as it infiltrates into the ground. Dry wells, infiltration

More information

GEOTECHNICAL INVESTIGATION ADDENDUM Pavement Improvements for Imperial Avenue, Wake Avenue, and Danenberg Drive, El Centro, California

GEOTECHNICAL INVESTIGATION ADDENDUM Pavement Improvements for Imperial Avenue, Wake Avenue, and Danenberg Drive, El Centro, California Mr. Victor Garcia The Holt Group 1601 N. Imperial Ave. El Centro, California 92243 September 28, 2017 Project No. EC595 SUBJECT: REFERENCE: GEOTECHNICAL INVESTIGATION ADDENDUM Pavement Improvements for

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2

1. Introduction Site Information Site Characteristics Hydrogeologic Setting... 2 Table of Contents 1. Introduction... 1 1.1 Site Information... 1 1.2 Site Characteristics... 1 1.3 Hydrogeologic Setting... 2 2. Closure Plan... 5 2.1 Closure Description... 5 2.2 Closure Timeframe...

More information

How & Where does infiltration work? Context: Summary of Geologic History Constraints/benefits for different geologic units

How & Where does infiltration work? Context: Summary of Geologic History Constraints/benefits for different geologic units Associated Earth Sciences, Inc. Associated Earth Sciences, Inc. Presented by: Matthew A. Miller, PE April 23, 2013 How & Where does infiltration work? Context: Summary of Geologic History Constraints/benefits

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS

17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.0 CONSTRUCTION OF OPEN DRAINAGE SYSTEMS 17.1 Description The work covered by this section of the specifications consists of furnishing all labor, the construction and installation of open storm drain

More information

REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA

REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA REPORT OF GEOTECHNICAL EXPLORATION WEST MARJORY AVENUE TAMPA, FLORIDA AREHNA PROJECT NO. B-15-008 March 11, 2015 Prepared For: City of Tampa Stormwater Division 306 W. Jackson Street, 6N Tampa, Florida

More information

Questions and Answers Environmental Drilling Investigation and Construction Monitoring Oversight

Questions and Answers Environmental Drilling Investigation and Construction Monitoring Oversight Questions and Answers Environmental Drilling Investigation and Construction Monitoring Oversight Question : Answer : Question : Answer : Question : Answer : The Phase I Environmental Site Assessment I

More information

Section 403. DRAINAGE STRUCTURES

Section 403. DRAINAGE STRUCTURES 403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF CONTENTS 422.01 SCOPE 422.02

More information

Lantz-Boggio Architects, P.C LBA Project No

Lantz-Boggio Architects, P.C LBA Project No SECTION 313430- PART 1 GENERAL 1.1 WORK INCLUDED A. Provide all equipment, material, labor and supervision to design and install Engineered Aggregate Piers for the soil reinforcement. Design shall rely

More information

Permeable Pavement Facilities and Surfaces

Permeable Pavement Facilities and Surfaces Permeable Pavement Facilities and Surfaces This checklist is intended to highlight items critical to the performance of permeable pavement facilities and surfaces that need to be addressed in the design

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 APRIL 2004 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS IN OPEN CUT TABLE OF

More information

PART II - SURVEYING AND GRADING CRITERIA

PART II - SURVEYING AND GRADING CRITERIA PART II - SURVEYING AND GRADING CRITERIA A. Surveying Procedures 1. Unless a temporary benchmark is approved in advance by the City Engineer, all submitted civil plans, including but not limited to grading,

More information

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL

Sepetember 27, Florida Department of Environmental Protection Attn: Dawn Templin 160 Governmental Center Pensacola, FL Bay County Solid Waste 11411 Landfill Rd. Panama City Beach, Florida 32413 Telephone: (850) 236-2212 Fax: (850) 233-5053 Board of County Commissioners www.baycountyfl.gov Sepetember 27, 2018 Florida Department

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

APPENDIX A DRAINAGE STUDY PHASE 2 ALTERNATIVE IMPROVEMENTS CRYSTAL LAKE ALTERNATIVE 4C IMPROVEMENTS LAKEWOOD PIRATELAND SWASH HORRY COUNTY, SC

APPENDIX A DRAINAGE STUDY PHASE 2 ALTERNATIVE IMPROVEMENTS CRYSTAL LAKE ALTERNATIVE 4C IMPROVEMENTS LAKEWOOD PIRATELAND SWASH HORRY COUNTY, SC DRAINAGE STUDY PHASE ALTERNATIVE IMPROVEMENTS CRYSTAL LAKE ALTERNATIVE C IMPROVEMENTS ` FOR: LAKEWOOD PIRATELAND SWASH HORRY COUNTY, SC APPENDIX A J-.000 Prepared by: Savannah, GA Charleston, SC Myrtle

More information

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133

CONDUCTED FOR: PREPARED FOR: 18 October 2010 YPC Project No. 10GY133 GEOTECHNICAL EXPLORATION AND ENGINEERING SERVICES REPORT CONDUCTED FOR: Immokalee Stormwater Master Plan Implementation Immokalee, Collier County, Florida PREPARED FOR: Mr. Marc Stonehouse, P. E. Project

More information

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773 September 8, 2016 City of Viborg 101 N. Main Street 57070 Attn:

More information

2.0 METHOD OF INVESTIGATION

2.0 METHOD OF INVESTIGATION The site currently serves as an athletic field for Beacon High School. As we understand it, the project entails miscellaneous improvements to the existing athletic field, to include a new artificial turf

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax

GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota Phone Fax GEOTEK ENGINEERING & TESTING SERVICES, INC. 909 East 50 th Street North Sioux Falls, South Dakota 57104 Phone 605-335-5512 Fax 605-335-0773 May 10, 2016 Banner Associates, Inc. 2307 W. 57 th Street, Suite

More information

July 23, Mr. Richard Miller, Vice President Lake Arrowhead Property Owners Association 7065 Arrowroot Trail Gaylord, Michigan 49735

July 23, Mr. Richard Miller, Vice President Lake Arrowhead Property Owners Association 7065 Arrowroot Trail Gaylord, Michigan 49735 Mr. Richard Miller, Vice President Lake Arrowhead Property Owners Association 7065 Arrowroot Trail Gaylord, Michigan 49735 Re: Task No. 3 Report of Findings Section 32, Township 30 North, Range 4 West

More information

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) PART 1 GENERAL 1.01 WORK INCLUDED SECTION 02360 / 31 34 30.13 ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM) A. Provide all equipment, material, labor and supervision to design and

More information

State of Nevada Department of Transportation Materials Division

State of Nevada Department of Transportation Materials Division State of Nevada Department of Transportation Materials Division STANDARD METHODS OF SAMPLING STONE, GRAVEL, SAND AND PAVING MIXTURES FOR USE AS HIGHWAY MATERIALS SCOPE This test method is used to obtain

More information

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 2004 Specifications CSJ 0264-07-028 SPECIAL SPECIFICATION 4425 Thermoplastic Pipe 1. Description. Furnish and install thermoplastic pipe for constructing thermoplastic pipe culverts or thermoplastic storm

More information

SECTION SUBSURFACE INVESTIGATION. 1. Protection of the environment; Section

SECTION SUBSURFACE INVESTIGATION. 1. Protection of the environment; Section 02011-1 of 5 SECTION 02011 SUBSURFACE INVESTIGATION 02011.01 GENERAL A. Description Subsurface investigation shall include, but not necessarily be limited to, drilling test holes (in rock), auguring holes,

More information

Sampling from Test Pits, Trenches and Stockpiles

Sampling from Test Pits, Trenches and Stockpiles PDHonline Course C289 (3 PDH) Sampling from Test Pits, Trenches and Stockpiles Instructor: John Poullain, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 02222 - EXCAVATION, BACKFILL, AND COMPACTION FOR UTILITIES PART 1 - GENERAL 1.01 SECTION INCLUDES A. Excavating trenches for the installation of utilities and stormwater detention facilities. B.

More information

FIGURES Printed By: aday Print Date: 3/23/2011 12:48:08 PM File Name: \\geodesign.local\files\jobs\m-r\penskeauto\penskeauto-1\penskeauto-1-01\figures\cad\penskeauto-1-01-vm01.dwg Layout: FIGURE 1 VICINITY

More information

Soil Improvement by Compaction Grouting

Soil Improvement by Compaction Grouting CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 31-3223.12 Soil Improvement by Compaction Grouting Part 1 - General 1.01 Introduction

More information

Geotechnical Investigation Report

Geotechnical Investigation Report Geotechnical Investigation Report Proposed,000-Gallon Water Storage Tank Fagasa Pass Tank Upper Pago Pago, American Samoa Prepared for: ASPA Water Engineering Division Tafuna, American Samoa PO Box PPB

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Soil Class Handouts Greeley Colorado October 22 & 23, 2015

Soil Class Handouts Greeley Colorado October 22 & 23, 2015 Soil Class Handouts Greeley Colorado October 22 & 23, 2015 1. Hand Texturing Flow Chart 2. Table 10-1 Soil Treatment Area Long Term Acceptance Rates by Soil Texture, Soil Structure, Percolation Rate and

More information

Anchorplex retaining wall construction guide

Anchorplex retaining wall construction guide Anchorplex retaining wall construction guide Building Anchorplex Retaining Wall Systems Table of Contents and Introduction table of contents ow to Use This Guide......................... 2 About the Anchorplex

More information

Experience Background

Experience Background Experience Background Primarily Eastern Washington Focus on stormwater, LID, and the built environment Specializing in construction documents for: PS&E on public projects Site design in support of vertical

More information

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 422 November 2015 CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS IN OPEN CUT TABLE OF CONTENTS D 422.01 D 422.02 D 422.03

More information

Section 8 Minimum Horizontal and Vertical Setback Distances

Section 8 Minimum Horizontal and Vertical Setback Distances Section 8 Minimum Horizontal and Vertical Setback Distances 1. Horizontal Distances a. Horizontal distances from the various components of a system to pertinent terrain features, including streams, lakes,

More information