1 MACKENZIE GATHERING SYSTEM MACKENZIE VALLEY PIPELINE SUPPLEMENTAL INFORMATION PROJECT UPDATE GLOSSARY > The symbol for greater than. < The symbol for less than. C The symbol for degrees Celsius. % The symbol for percent. µg/m 3 Aboriginal person access road Active I channel Active II channel AENV AHCV airshed all-weather road ambient air quality anchor fields The metric symbol for micrograms per cubic metre. Any Indian, Inuit or Métis person who was born in the Northwest Territories or who is descended from an Aboriginal person born in the Northwest Territories. A temporary, permanent, or winter road that provides access to a facility, camp site, borrow site, barge landing site or a pipeline right-of-way, and that is not open to the public. A water channel that has a perennial flow or is partially frozen to the channel bed during winter. A water channel that is frozen to the bed or that has no flow during winter. The abbreviation for Alberta Environment. The abbreviation for area of high conservation value. The geographic area associated with movement of air and emissions. An area over which model predictions are made and within which emissions from different facilities interact. Emissions from one airshed are not considered to interact with emissions from other airsheds. A paved or unpaved, i.e., gravel, road that is open to traffic all year. The quality of any unconfined portion of the atmosphere, open air or surrounding air. The three natural gas fields, Niglintgak, Taglu and Parsons Lake, whose production will provide the initial volume of gas shipped in the project pipelines. November 2005 GL-1
2 aquatic baseline Bcf/d biophysical environment block valve borrow site BTEX CASA CH 4 channel CO CO 2 compressor station cumulative effects db dba discontinuous permafrost dispersion modelling Growing in, living in or frequenting water. Also, occurring, or situated in or on water. A surveyed condition that serves as a reference point to which later surveys or assessments are coordinated or correlated. The abbreviation for billion cubic feet per day. An environment that includes air, noise, aquatic (hydrogeology, hydrology, water quality and fisheries) and terrestrial (soils, landforms, permafrost, vegetation and wildlife) conditions. A device, positioned at intervals along a pipeline, that controls the rate of flow in the pipeline, opens or shuts off the pipeline completely, or serves as an automatic or semi-automatic safety device. An area that could be excavated to provide material, such as gravel or sand, to be used, where required, by the project. The abbreviation for benzene, toluene, ethylbenzene and xylene. The abbreviation for the Clean Air Strategic Alliance. The chemical symbol for methane. A natural or artificial waterway that periodically or continuously contains moving water, has a definite bed, and has banks that confine the water at low to moderate streamflow. The chemical symbol for carbon monoxide. The chemical symbol for carbon dioxide. A facility containing equipment that is used to increase pressure to compress natural gas for transportation in a pipeline. Changes to the environment caused by an action, including projects and activities, in combination with other past, present and future human actions. The abbreviation for decibel. The abbreviation for A-weighted decibel. A zone of permafrost containing patches of unfrozen ground, such as beneath large rivers and lakes. A computer modelling technique used to predict downwind concentrations of air contaminants from a known discharge rate, height and temperature. GL-2 November 2005
3 disturbed site ECO 2 ecosystem EIS emission facilities fine particulate matter footprint fugitive emission gathering system granular material greenhouse gas groundwater groundwater recharge ha habitat habitat fragmentation heritage resources An area with evidence of previous anthropogenic activity. The abbreviation for equivalent carbon dioxide. An integrated and stable association of all living organisms and the nonliving physical and chemical factors of their environment, within a defined physical location. The abbreviation for environmental impact statement. Air pollutant discharged into the atmosphere. Gathering and gas pipeline systems, including compressor and pump stations, block valves, pig launchers and receivers, heater stations and meter stations. Particulate matter that is small enough to be breathed deeply into the respiratory tract. The amount and shape of the area disturbed. An uncontrolled output of air pollutants to air, water or land. A system of pipelines and related facilities that include four gathering pipelines, the Inuvik area facility, the NGL pipeline and related facilities, such as valves, pig launchers and receivers. Material deposits that have a granulated surface or structure, such as gravel. Any of various gases, e.g., CO 2, CH 4, NO 2, that are more transparent to incoming solar radiation than to reflected radiation from the earth and that contribute to the heating of the earth s surface and lower atmosphere. Subsurface water that is recharged by infiltration and enters streams through seepage and springs. The processes involved in the absorption and addition of water to the zone of saturation. Also refers to the amount of water added. The metric symbol for hectare. The place or environment where a plant or animal naturally and normally lives and grows. Breaking up continuous tracts of habitat, creating barriers to migration or dispersal of organisms, and reducing the size of homogeneous areas. Fragmentation can be induced by human activities or by natural processes. Cultural, historic, archaeological and palaeontological resources. November 2005 GL-3
4 HRIA INAC infrastructure Inuvik area facility keq/ha/a key indicator kg/ha/a km KP kt/a L lateral LSA logistics m MACA mg/l mitigation mm Mm 3 /d The abbreviation for heritage resources impact assessment. The abbreviation for Indian and Northern Affairs Canada. The basic facilities, such as transportation, communications, electrical power supplies and buildings, that enable an organization, project or community to function. The facility near Inuvik that processes and separates gas and NGLs delivered from the gathering pipelines and which directs the processed streams to the NGL and gas pipelines. The metric symbol for kiloequivalents per hectare per year. A factor used to measure the status of a valued component. The metric symbol for kilograms per hectare per year. The metric symbol for kilometre. The abbreviation for kilometre post. The metric symbol for kilotonnes per year. The metric symbol for litre. A gathering pipeline that connects the production area facilities to the Inuvik area facility. The abbreviation for local study area. The activities associated with procuring, maintaining and transporting materials, equipment and personnel. The metric symbol for cubic metres. The abbreviation for Municipal and Community Affairs. The metric symbol for milligrams per litre. The elimination, reduction or control of a project s adverse effects, including restitution for any damage caused to the environment by such effects through avoidance, replacement, restoration, compensation or other means. The metric symbol for millimetres. The metric symbol for million cubic metres per day. GL-4 November 2005
5 monitoring N 2 O N/A NGL NGTL Niglintgak lateral NO 2 NO x non-point flow pad PAI particulate matter permafrost pipeline corridor PM 2.5 potential acid input process heater proponents, Mackenzie gathering system The act of maintaining regular surveillance over something over a period of time. The chemical symbol for nitrous oxide. The abbreviation for not applicable. The abbreviation for natural gas liquid. The abbreviation for NOVA Gas Transmission Ltd. The gathering pipeline connecting the Niglintgak gas conditioning facility to a connection point on the Taglu lateral at the outlet of the Taglu gas conditioning facility. The chemical symbol for nitrogen dioxide. The chemical symbol for oxides of nitrogen. Water introduced into a receiving stream from diffuse sources, i.e., without a single point of origin and not from a specific outlet. The surface parts of a multiwell drilling or production site, including wells, buildings, piping and electrical facilities. The abbreviation for potential acid input. Matter in the form of small liquid or solid particles. Perennially frozen ground, occurring wherever the ground temperature remains below 0 C for two or more consecutive years. The 1-km-wide area that centres on the combined right-of-way for the gas and NGL pipelines, from the Inuvik area facility south to the NGTL interconnect facility in Alberta. Respirable particulate matter with a nominal diameter smaller than 2.5 µm. The sum of the wet and dry deposition of sulphur and nitrogen compounds that have the potential to contribute to acidification of the receiving environment. Equipment for heating chemical process streams, e.g., gases, liquids or solids. Usually refers to furnaces, in contrast to heat exchangers. Imperial Oil Resources Ventures Limited, ConocoPhillips Canada (North) Limited, Shell Canada Limited and ExxonMobil Canada Properties. November 2005 GL-5
6 proponents, Mackenzie Valley pipeline reclamation reconnaissance right-of-way RSA SO 2 stockpile Storm Hills lateral t/d TBD topography valued component vegetated channel vegetation type watercourse Imperial Oil Resources Ventures Limited, the APG, ConocoPhillips Canada (North) Limited, Shell Canada Limited and ExxonMobil Canada Properties. The process of re-establishing a disturbed site to a former or other productive use, not necessarily to the same condition that existed before disturbance. The land capability might be at a level different, i.e., lower or higher, than that which existed before the disturbance, depending on the goal of the process. Reclamation includes the management of a disturbed site and revegetation where necessary. A mission to obtain information about the characteristics of a particular area. The easement in which the pipeline will be installed and operated. The abbreviation for regional study area. The chemical symbol for sulphur dioxide. A storage supply of something, such as line pipe or soil, to be used later. The gathering pipeline connecting the Storm Hills pigging facility to a connection point at the inlet of the Inuvik area facility. The metric symbol for tonnes per day. The abbreviation for to be determined. The natural surface features of a region, or the general configuration of a surface, including its relief. Characteristic or feature that represents important environmental conditions identified by assessment specialists, communities or stakeholders. A watercourse with ephemeral flow, no discernible banks or sediment transport, and a drainage area less than 15 km 2. It is primarily a shallow flow through shrubs and trees during spring runoff or rainfall. It is dry most of the year. A vegetation community or complex of communities that can be identified on air photos and is large enough to map. Vegetation types are clearly defined and named. A natural or artificial channel with perennial or intermittent flow and definable bed and banks. GL-6 November 2005
Assessment of Landfill Footprint Alternatives West Carleton Environmental Centre. Option #4 Impact on Agriculture
Assessment of Landfill Footprint Alternatives Figure 422 99 Option #4 Impact on Agriculture The net effects with respect to continued service to customers, the optimized site life/ capacity is 65 million
More informationNoront Ferrochrome Production Facility (FPF) Environmental Issues and Approach. October 2017
Noront Ferrochrome Production Facility (FPF) Environmental Issues and Approach October 2017 (Simulated FPF) INTRODUCTION Noront is proposing to develop a Ferrochrome Production Facility (FPF) in Northern
More informationGOVERNMENTS OF CANADA & OF THE NORTHWEST TERRITORIES FINAL RESPONSE TO THE JOINT REVIEW PANEL REPORT FOR THE PROPOSED MACKENZIE GAS PROJECT
GOVERNMENTS OF CANADA & OF THE NORTHWEST TERRITORIES FINAL RESPONSE TO THE JOINT REVIEW PANEL REPORT FOR THE PROPOSED MACKENZIE GAS PROJECT November 2010 INTRODUCTION 2 The following document is the Governments
More informationEmissions to air and CO 2 footprint related to shale gas operations
Emissions to air and CO 2 footprint related to shale gas operations Paula Costa Ana Picado Hugo Denier van der Gon www.m4shalegas.eu Outline Key points Types of emissions Different sources Assessment of
More informationMackenzie Valley Project
Mackenzie Valley Project Nicole Hamm, Wilson Howe, Blair Jarvis, JohnPaul Portelli School of Business University of Alberta Agenda Introduction Project Components Stakeholders Production North American
More information22 HUMAN AND CULTURAL RESOURCES SUMMARY
Volume 2: Environmental and Sturgeon Upgrader Project 22 HUMAN AND CULTURAL RESOURCES SUMMARY 22.1 Introduction This section summarizes the predicted effects of the Project on human and cultural resources
More informationShell Quest Carbon Capture and Storage Project. Shell Canada Limited
SCREENING SCOPING DOCUMENT For the proposed Shell Quest Carbon Capture and Storage Project Shell Canada Limited Prepared by: Canadian Environmental Assessment Agency Natural Resources Canada Fisheries
More informationComparative Evaluation Option #1 & Option #2
Comparative Evaluation Option #1 & Option #2 Option #1 Existing Landfill Approx. 47 metres/14 stories Proposed Layout Approx. 31 metres/9.5 stories Option #2 Existing Landfill Approx. 47 metres/14 stories
More informationAPPENDIX 2. Nova Scotia Department of Environment and Labour Environmental Assessment Terms and Conditions for Environmental Assessment Approval
APPENDIX 2 Nova Scotia Department of Environment and Labour Terms and Conditions for Approval Approval Approval Date: March 14, 2007 Keltic Petrochemicals Inc. LNG and Petrochemical Plant Facilities Keltic
More informationMackenzie Gas Project EIS Additional Information for the Joint Review Panel Environmental Inputs and Outputs
Mackenzie Gas EIS Additional Information for the Joint Review Panel Environmental Inputs and Outputs Submitted to: Joint Review Panel Submitted by: Imperial Oil Resources Ventures Limited February 2006
More informationGLNG PROJECT - ENVIRONMENTAL IMPACT STATEMENT
6 J:\Jobs\42626220\07 Deliverables\EIS\FINAL for Public Release\6. Values and Management of Impacts\6-8 Air Quality\06 08 Air Quality (Section 6.8) FINAL PUBLIC track.doc GLNG Project - Environmental Impact
More informationOperations Mine Site, Tote Road and Railway
Operations Mine Site, Tote Road and Railway 2 Panel Members Michael Anderson Richard Cook John Binns Fernand Beaulac Steve Walker Mike Lepage Michael Sheahan 3 The Panel will address: FEIS Volumes 3, 5,
More informationTemporary Watercourse Crossing: Culverts
Temporary Watercourse Crossing: Culverts DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent Symbol
More informationPROPOSED TERMS OF REFERENCE ENVIRONMENTAL ASSESSMENT REPORT FOR THE PROPOSED QUEST CARBON CAPTURE AND STORAGE PROJECT
PROPOSED TERMS OF REFERENCE ENVIRONMENTAL ASSESSMENT REPORT FOR THE PROPOSED QUEST CARBON CAPTURE AND STORAGE PROJECT ISSUED BY: Shell Canada Limited DATE: August 6, 2010 Executive Summary Executive Summary
More informationConditions Annexed to and Forming Part of Land Use Permit # MV2013C0021
Conditions Annexed to and Forming Part of Land Use Permit # MV2013C0021 Part A: Scope of Permit 1. This Permit entitles New Discovery Mines Ltd. to conduct the following land-use operation: a) Use, construction
More informationAIR MANAGEMENT IN ALBERTA
AIR MANAGEMENT IN ALBERTA Air Management In Alberta Alberta Environment January 2009 ISBN No. 978-0-7785-8088-1 (Printed) ISBN No. 978-0-7785-8089-8 (On-line) Web Site: http://www.environment.alberta.ca/
More informationFebruary Reference Section in Supplemental. Reference Section in Consultants Reports. Reference Section in Application. TOR No.
Request i Final Terms of Environmental Impact Assessment Report for Coal Valley Resources Inc. (CVRI) Proposed Robb Trend Project Cross (Concordance) Table to Location in ii PURPOSE OF THE TERMS OF REFERENCE
More informationSemCAMS Area Project Description
REGULATORY The Redwillow Pipeline Project involves crossing a provincial boundary, and therefore, approval for it will require the preparation of an application to the NEB. plans to proceed with the regulatory
More information3.4 AQUATIC ECOSYSTEMS AND FISH SPECIES
3.4 AQUATIC ECOSYSTEMS AND FISH SPECIES The following section supplements the analysis found in Chapter Three, Section 3.4 - Aquatic Ecosystems and Fish Species of the Draft EIS on page 3.59, Impacts Related
More informationGroundwater 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology
GG22A: GEOSPHERE & HYDROSPHERE Hydrology Definitions Groundwater Subsurface water in soil or rock that is fully saturated. Aquifer Contains enough saturated material to yield significant quantities of
More informationFINAL TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE PROPOSED
FINAL TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR THE PROPOSED UTS ENERGY CORPORATION/TECK COMINCO LIMITED FRONTIER OIL SANDS MINE PROJECT Approximately 60 km from Fort McKay, Alberta
More informationDRAFT CH 10 & CH 11 October 7, 2015 From: SLDCProposedAmendmentsBCCPacket part3-1Nsm
DRAFT CH 10 & CH 11 October 7, 2015 From: SLDCProposedAmendmentsBCCPacket10-13-2015part3-1Nsm 10.19. SMALL SCALE SAND AND GRAVEL EXTRACTION. 10.19.1. Applicability. This section applies to any mineral
More informationTABLE OF CONTENTS. Page
TABLE OF CONTENTS Page 1 PROJECT INTRODUCTION... 1-1 1.1 PROJECT BACKGROUND... 1-2 1.2 PROJECT PROPONENT... 1-2 1.3 PROJECT OVERVIEW... 1-3 1.4 PROJECT REGULATORY APPROVAL PROCESS... 1-4 1.4.1 Existing
More informationFINAL TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT (EIA) REPORT FOR THE ALBERTA SULPHUR TERMINALS SULPHUR FORMING AND SHIPPING FACILITY
FINAL TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT (EIA) REPORT FOR THE ALBERTA SULPHUR TERMINALS SULPHUR FORMING AND SHIPPING FACILITY (formerly referred to as the Bruderheim Sulphur Forming & Pastille
More informationAppendix 14-I Description of Stream Crossing for Electrical Interconnect
Appendix 14-I Description of Stream Crossing for Electrical Interconnect 14.0 Ecology Appendix 14-I CPV Valley Energy Project Description of Stream Crossing for Electrical Interconnect The CPV Valley Energy
More informationPERFORMANCE OF AN ENGINEERED COVER SYSTEM FOR A URANIUM MINE WASTE ROCK PILE IN NORTHERN SASKATCHEWAN AFTER SIX YEARS
PERFORMANCE OF AN ENGINEERED COVER SYSTEM FOR A URANIUM MINE WASTE ROCK PILE IN NORTHERN SASKATCHEWAN AFTER SIX YEARS B. Ayres, P.Eng. 1 M. O Kane, P.Eng. 1 L. Barber 1 D. Hiller 2 D. Helps 2 ABSTRACT
More informationPROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED HORIZON NORTH PIT EXTENSION PROJECT
PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED HORIZON NORTH PIT EXTENSION PROJECT Approximately 70 km North of Fort McMurray, Alberta ISSUED
More informationDRAFT Type B Water Licence G18L8-001 NWT Energy Corporation (03) Ltd. Inuvik Wind Project
DRAFT Type B Water Licence G18L8-001 NWT Energy Corporation (03) Ltd. Inuvik Wind Project Table of Contents Part A: Scope and Definitions Part B: General Conditions Annual Report Schedule 1 Part C: Conditions
More informationEnvironment Canada Alberta Environment and Water March 2012
Environment Canada Alberta Environment and Water March 2012 1 Multiple reviews by independent scientific panels have concluded that more rigorous environmental monitoring is needed to adequately detect
More informationTerms of Reference. As Required by the Environment Act For Preparation of an Environmental Assessment Report
The public is invited to submit comments on this draft Terms of Reference until : Comments should be submitted to : January 21, 2008 Environmental Assessment Branch Nova Scotia Environment and Labour PO
More informationTemporary Watercourse Crossing: Fords
Temporary Watercourse Crossing: Fords DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
More informationSummary of Relief Sought by Transpower New Zealand Limited
Summary of Relief Sought by Transpower New Zealand Limited Relief sought in Transpower s further submission and supported by evidence The following consolidates the amendments to the Proposed Southland
More informationENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass
ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County, NS NOVA SCOTIA DEPARTMENT OF THE ENVIRONMENT
More informationSouth Landfill Annual Cover Rate Screening Criteria Checklist
South Landfill Annual Cover Rate Screening Criteria Checklist The following checklist is taken from the Guide to Environmental Assessments for Waste Management Projects, Part B Environmental Screening
More informationConditions Annexed to and Forming Part of Land Use Permit # S18X-004
Conditions Annexed to and Forming Part of Land Use Permit # S18X-004 Part A: Scope of Permit 1. This Permit entitles the Permittee to conduct the following land-use operation: a) Geotechnical borehole
More informationAmbient Air Quality Monitoring Update, Kirby Misperton A Wellsite, KM8 Production Well
Ambient Air Quality Monitoring Update, Kirby Misperton A Wellsite, KM8 Production Well. Prepared for: Third Energy UK Gas Ltd. Document Control Page Client Third Energy UK Gas Ltd. Document Title Ambient
More informationFORM B: DAMMING AND DIVERSION OF WATER
APPLICATION FOR RESOURCE CONSENT FORM B: DAMMING AND DIVERSION OF WATER NOTES Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan
More informationInputs. Outputs. Component/store. Section of a system where material or energy is held. Something that enters the system (material or energy)
.. Inputs Something that enters the system (material or energy) Outputs Something that leaves the system (material or energy) Component/store Section of a system where material or energy is held Transfer/flow
More informationFish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory
Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Version 1.0 April 2008 This document is available from the Yukon Placer Secretariat, Yukon
More informationPreliminary Disclosure; Application for Approval; Operating Permits, Volume 2: Licences and Approvals; and Abandonment Approval and
Information required by EUB Guide G-23 1.0 GENERAL INFORMATION 1.1 INTRODUCTION The application should include: a brief project summary, objectives, approvals requested, technical and economic details,
More informationPRELIMINARY SCREENING REPORT FORM
PRELIMINARY SCREENING REPORT FORM PRELIMINARY SCREENER: Sabrina Sturman REFERENCE / FILE NUMBER: S17X-006 APPLICANT: Government of Northwest Territories, Department of Municipal and Community Affairs EIRB
More informationNICO COBALT-GOLD-BISMUTH-COPPER PROJECT Community Scoping Session Environmental Overview
NICO COBALT-GOLD-BISMUTH-COPPER PROJECT Community Scoping Session Environmental Overview 1 INTRODUCTION Screening level environmental impact assessment provided in application package Many of the potential
More informationCATEGORY a protection of the natural environment, its ecosystems and biodiversity.
29. ENVIRONMENTAL DEVELOPMENT PERMIT AREA CATEGORY a protection of the natural environment, its ecosystems and biodiversity. The requirement to obtain an environmental development permit is cited in Section
More informationFort McKay Specific Assessment
SURFACE WATER HYDROLOGY Fort McKay Specific Assessment Fort McKay Industry Relations Corporation March 2010 Contents 4.0... 1 4.1 Fort McKay s Key Concerns Related to Surface Water... 1 4.2 Fort McKay
More informationWetlands in Alberta: Challenges and Opportunities. David Locky, PhD, PWS, PBiol Grant MacEwan University
Wetlands in Alberta: Challenges and Opportunities David Locky, PhD, PWS, PBiol Grant MacEwan University Overview What & Where Function & Value Alberta s Keystone Ecosystem Losses & Impacts Restoration
More informationHow to avoid getting bogged down by the Nova Scotia Wetland Conservation Policy
How to avoid getting bogged down by the Nova Scotia Wetland Conservation Policy for the Environmental Services Association of Nova Scotia By Krista Hilchey Wetland Specialist, Nova Scotia Environment To
More informationNorthern Frontier Northern Homeland
Northern Frontier Northern Homeland THE REPORT OF THE MACKENZIE VALLEY PIPELINE INQUIRY Volume Two Terms and Conditions Mr. Justice THOMAS R. BERGER ii NORTHERN FRONTIER, NORTHERN HOMELAND - Mackenzie
More informationThe Peace Watershed. Current and Future Water Use and Issues, 2011
This is an Executive Summary. For full report go to: www.mightypeacewatershedalliance.org The Peace Watershed Current and Future Water Use and Issues, 2011 March 2012 EXECUTIVE SUMMARY This study was undertaken
More informationFERC PDF (Unofficial) 10/08/2014. Environmental Impact Statement ES-1 Corpus Christi LNG
EXECUTIVE SUMMARY The staff of the Federal Energy Regulatory Commission (FERC or Commission) prepared this Environmental Impact Statement (EIS) to assess the environmental issues associated with the construction
More informationTERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR KOCH OIL SANDS OPERATING ULC PROPOSED DUNKIRK IN SITU PROJECT
TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR KOCH OIL SANDS OPERATING ULC PROPOSED DUNKIRK IN SITU PROJECT Approximately 76 km from Fort McMurray, Alberta and Approximately 111 km Northeast
More informationAppendix 1-A Well Testing
Appendix 1-A Well Testing FLOW TESTING PURPOSE Flow testing is used to determine the performance of oil and gas wells and their economic potential. Various tests will be done to determine the amount of
More informationLow Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]
Diversion Channels DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] The design of permanent
More informationSteve Mailath, M.Sc., P.Geol. April 10, 2014 WATER NATURAL RESOURCES ENVIRONMENT INFRASTRUCTURE ENERGY
IN-SITU REMEDIATION OF HYDROCARBON IMPACTED GROUNDWATER IN PERMAFROST TERRAIN AT A REMOTE SITE. TIBBITT TO CONTWOYTO WINTER ROAD, NORTHWEST TERRITORIES Steve Mailath, M.Sc., P.Geol. April 10, 2014 WATER
More informationSpectra Energy Midstream Canada Partner Corporation 2016 Application for Approval to Reactivate the Pesh Creek Pipeline and Pesh Creek Loop
APPLICATION Spectra Energy Midstream Canada Partner Corporation 2016 Application for Approval to Reactivate the Pesh Creek Pipeline and Pesh Creek Loop Spectra Energy Midstream Canada Partner Corporation,
More informationGROUSE GROUSE IN SITU OIL SANDS PROJECT. Proposed Development Plan. Plain Language Project Summary
GROUSE Proposed Development Plan GROUSE IN SITU OIL SANDS PROJECT Plain Language Project Summary ABOUT CANADIAN NATURAL WHO WE ARE Canadian Natural Resources Limited (Canadian Natural) is a senior independent
More informationAPPENDIX I Air Quality Technical Data Report. PDF Page 1 of 117
APPENDIX I Air Quality Technical Data Report PDF Page 1 of 117 PDF Page 2 of 117 Air Quality Technical Data Report Prepared for: NOVA Gas Transmission Ltd. Calgary, Alberta Prepared by: Stantec Consulting
More informationAPPENDIX D 2017 PHOTO ESSAY
APPENDIX D 2017 PHOTO ESSAY Mary River Project 2017 NIRB Annual Report March 2018 Project Overview - 2017 In 2017, Baffinland focused on mine production from Deposit No. 1 with 4.54 million tonnes mined
More informationGlen Hall Falconbridge Ltd., Sudbury Operations Sudbury, Ontario
A NEW APPROACH TO TAILINGS MANAGEMENT: THE GRANULAR COVER SYSTEM Glen Hall Falconbridge Ltd., Sudbury Operations Sudbury, Ontario Linda C. M. Elliott, Lakefield Research Ltd., PO Box 4300, 185 Concession
More informationTelephone Lake project
Telephone Lake project Cenovus Energy Inc. is a Canadian oil company. We re committed to applying fresh, progressive thinking to safely and responsibly unlock energy resources the world needs. Our operations
More informationGroundwater and Surface Water Overview of the Lochend Area, Alberta
Groundwater and Surface Water Overview of the Lochend Area, Alberta The Lochend Industry Producers Group (LIPG) conducted a hydrogeological / hydrological study in the Lochend operating field. The objectives
More informationPapua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV
Esso Highlands Limited Papua New Guinea LNG Project Environmental and Social Management Plan Appendix 11: PGGP-EH-SPENV-000018-013 LNG Project Page 2 of 13 CONTENTS 1.0 Objectives... 3 2.0 Legal and Other
More informationFish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory
Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory Version 1.3 November 2010 This document is available from: Yukon Placer Secretariat, 206B
More informationCockburn Cement Limited. Summary of stack emission and ground level concentration data. September 2010
Cockburn Cement Limited Summary of stack emission and ground level concentration data September 2010 THIS REPORT CONTAINS INFORMATION EXTRACTED FROM THE KATESTONE ENVIRONMENTAL AIR QUALITY IMPACT ASSESSMENT
More information14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring
14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring An effective monitoring program provides results to: indicate whether the facility is working as expected and that the assumptions used in the assessment
More informationTERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED S PROPOSED HORIZON NORTH PIT EXTENSION PROJECT
TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR CANADIAN NATURAL RESOURCES LIMITED S PROPOSED HORIZON NORTH PIT EXTENSION PROJECT Approximately 70 km North of Fort McMurray, Alberta ISSUED
More informationTOWERBIRCH EXPANSION PROJECT
TOWERBIRCH EXPANSION PROJECT FEDERAL/PROVINCIAL CONSULTATION AND ACCOMMODATION REPORT Proposed by: NOVA Gas Transmission Ltd. Prepared by: Major Projects Management Office British Columbia Environmental
More informationNorth Mackenzie District Telephone: (867) P.O. Box 2100 Fax: (867) Inuvik, NT XOE 0T0
Aboriginal Affairs and Northern Development Canada www.inac.gc.ca Affaires autochtones et Développement du Nord Canada www.ainc.gc.ca North Mackenzie District Telephone: (867) 777-8901 P.O. Box 2100 Fax:
More informationgroundwater. Because watersheds are complex systems, each tends to respond differently to natural or human activities.
The private development of Altos del María is located at an altitude between 550 and 1,000 meters above sea level in the environmentally sensitive Cordillera Central of Panama that separates the Pacific
More informationApplication for resource consent Form B Damming and diversion of water
Application for resource consent Form B Damming and diversion of water Notes Resource use activities must meet all the conditions of any relevant Permitted Activity Rules in the Waikato Regional Plan or
More informationAddendum. This NWT appendix has been updated to reflect these changes. When the Government Is the Landlord
Addendum Since its initial release on August 17, 2004, the following changes have been identified and should be made to this document; incorrect text in bold and new or revised text is in italics. Regional
More informationAPPENDIX E SATURN (UNITS 1 & 2) AIR TDR
APPENDIX E SATURN (UNITS 1 & 2) AIR TDR Technical Data Report for Saturn Compressor Station (Units 1&2) Air Quality Prepared for: NOVA Gas Transmission Ltd. Calgary, Alberta Prepared by: Stantec Consulting
More informationSchedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw
Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw 6410 2006 The Erosion and Sediment Control plan should seek (i) to protect the soil surface from erosion where possible and (ii) capture
More informationProposed Terms of Reference for EIA studies
1 Proposed Terms of Reference for EIA studies Collection of Base line data in any season other than Monsoon season in study area of 10 kms radius from Lease Area. Based on the Meteorological data from
More informationb r e a k i n g gr o u n d g l o s s a r y an d su p p l e m e n ta r y in f o r m at i o n
SaskEnergy Annual Report b r e a k i n g gr o u n d 2008 g l o s s a r y an d su p p l e m e n ta r y in f o r m at i o n 87 1. Our Future Competitive Rates: SaskEnergy Commodity SaskEnergy Delivery This
More informationREASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT
REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT SASKATCHEWAN WATER CORPORATION BUFFALO POUND NON-POTABLE WATER SUPPLY SYSTEM EXPANSION PROJECT Introduction
More informationQuintillion Subsea Project Applicant Proposed Mitigation Statement
1. Avoidance of impacts to waters of the U.S., including wetlands: Please describe how, in your project planning process, you avoided impacts to waters of the U.S., including wetlands, to the maximum extent
More informationClimate change, permafrost and water in the NWT. Steve Kokelj INAC
Climate change, permafrost and water in the NWT Steve Kokelj INAC Indian and Northern Affairs Canada Steve Kokelj Outline Permafrost and climate change Climate change impacts in the NWT Case study climate
More informationPARTICULATE MATTER AND OZONE MANAGEMENT FACT SHEET ( )
PARTICULATE MATTER AND OZONE MANAGEMENT FACT SHEET (2010 2012) April 2014 What is PM 2.5? Particulate matter can be emitted by any combustion source. PM 2.5 is fine particulate matter less than 2.5 micrometres
More informationGeneral Groundwater Concepts
General Groundwater Concepts Hydrologic Cycle All water on the surface of the earth and underground are part of the hydrologic cycle (Figure 1), driven by natural processes that constantly transform water
More informationWetlands. Development of a Functional Matrix. Andrea Borkenhagen B.Sc., B.I.T Geetha Ramesh PhD., P.Biol
Wetlands Development of a Functional Matrix ndrea Borkenhagen B.Sc., B.I.T Geetha Ramesh PhD., P.Biol genda Introduction Purpose Regulations Development Example wetland assessment pplication 2 Introduction
More informationNottawasaga Valley Conservation Authority
Nottawasaga Valley Conservation Authority PROCEDURAL GUIDELINE FOR THE PLACEMENT OF LARGE QUANTITIES OF FILL Effective: October 28, 2011 Nottawasaga Valley Conservation Authority 8195 8th Line, Utopia,
More informationFor inspection purposes only. Consent of copyright owner required for any other use. EPA Export :23:33:57
EPA Export 11-02-2014:23:33:57 P03/3343 CORRIB GAS FIELD DEVELOPMENT Prepared in respect of the proposed Bellanaboy Bridge Gas Terminal and associated Srahmore Peat Deposition Site RESPONSE TO REQUEST
More informationWhat is the Terms of Reference?
What is the Terms of Reference? Framework for content of the Environmental Assessment Certificate Application Provides the scope of technical studies and consultation processes with the public and First
More informationResearch Question What ecological and other services do coastal wetlands provide?
Bringing Wetlands to Market Part 1 Introduction Blue, Green, and Bountiful: Wetlands and carbon Estuary Principle Principle 5: Humans, even those living far from the coast, rely on goods and services supplied
More informationEnvironmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores
Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores October 2015 Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores WaterNSW on behalf of the NSW Government
More informationConservation and Reclamation INFORMATION LETTER. Environmental Protection Guidelines for Oil Production Sites - Revised January 2002
March 2002 Conservation and Reclamation INFORMATION LETTER C&R/IL/02-1 Environmental Protection Guidelines for Oil Production Sites - Revised January 2002 CHANGES TO THE INFORMATION LETTER This Information
More informationChapter 10 Summary of Project Effects
Chapter 10 Summary of Project Effects MINAGO PROJECT Environmental Impact Statement i TABLE OF CONTENTS 10. SUMMARY OF PROJECT EFFECTS 10-1 10.1 Key Findings 10-1 10.1.1 Aquatic Habitat 10-1 10.1.2 Wildlife
More informationAbout WCC LNG Project Ltd.
About WCC LNG Project Ltd. WCC LNG Project Ltd. (WCC LNG) is a proposed project led by ExxonMobil to develop and operate a liquefied natural gas (LNG) export facility on the eastern shore of Tuck Inlet
More informationAppendix E : Guidelines for Riparian Buffer Areas
Appendix E : Guidelines for Riparian Buffer Areas This document should be read in conjunction with the CRCA Planning Policy. 1.0 PURPOSE The purpose of this document is to summarize the recommendations
More informationIntroduction to Ecology p
Introduction to Ecology 19-1 p. 359-365 Essential Question 1. Identify three ways in which the expanding human population impacts the environment. 2. Describe the hierarchical levels of organization in
More informationUGFI Environmental Protection Plan (EPP) Ikhil UGFI et al 02/J-35 Gas Well DRILLING AND FACILITIES TIE-IN PROGRAM
(EPP) Ikhil UGFI et al 02/J-35 Gas Well DRILLING AND FACILITIES TIE-IN PROGRAM Rev 2. January 10, 2012 1 ENVIRONMENTAL PROTECTION PLAN - IKHIL UGFI 02 / J-35 GAS WELL DRILLING AND FACILITIES TIE-IN PROGRAM
More information6. GREENHOUSE GAS EMISSIONS
Supplementary Report to the EIS 6. GREENHOUSE GAS EMISSIONS This chapter summarises the findings of the supplementary greenhouse gas assessment undertaken to address updates to the project description
More informationFINAL TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR TOWN OF CANMORE S PROPOSED COUGAR CREEK DEBRIS FLOOD RETENTION STRUCTURE PROJECT
FINAL TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR TOWN OF CANMORE S PROPOSED COUGAR CREEK DEBRIS FLOOD RETENTION STRUCTURE PROJECT ISSUED BY: Alberta Environment and Parks DATE: March
More informationSummary of relief sought by Dairy Holdings Limited
Summary of relief sought by Dairy Holdings Limited Evidence or legal submission paragraph reference Issue (including objective/policy /rule reference) Explanation Relief sought by DHL [5] [15] Definition
More informationDublin Airport Air Quality Monitoring
Dublin Airport Air Quality Monitoring Annual Report 2017 HSSE Environment Dublin Airport Air Quality Monitoring Annual Report 2017 Contents 1.0 Introduction... 4 1.1 Background... 4 1.2 Purpose... 4 2.0
More informationOption #2 Impact on Agriculture
Environmental Assessment Figure 5-27 5-81 Option #2 Impact on Agriculture Socio-Economic The ratio of air space achieved to volume of soil handled has a ratio of 6.5 million m 3 to 2.2 million m 3. There
More informationEAO s Assessment of an Application for Certificate Amendment Prince Rupert Gas Transmission Project
EAO s Assessment of an Application for Certificate Amendment Prince Rupert Gas Transmission Project EA Certificate #E14-06 Amendment #4, Additional Construction Camps and Stand-by Compressor Units Requested
More information4. Ponds and infiltration BMPs can achieve 60 to 100% removal efficiencies for sediment.
Landscape BMPs For the purposes of this project, preventive measures have been categorized into two categories: landscape BMPs and source prevention BMPs. Landscape BMPs includes both vegetative practices
More informationATTACHMENT 1 GEPA CHECKLIST & Historical Archeological & Natural Heritage Preservation Documents
ATTACHMENT 1 GEPA CHECKLIST & Historical Archeological & Natural Heritage Preservation Documents INTRODUCTION The 1991 Session of the Georgia General Assembly passed Senate Bill 97, as amended, and it
More informationPROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR VALUE CREATION INC. S PROPOSED ADVANCED TRISTAR PROJECT
PROPOSED TERMS OF REFERENCE ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR VALUE CREATION INC. S PROPOSED ADVANCED TRISTAR PROJECT Approximately 10 km to the Proposed Plant Site from Fort McMurray, Alberta