M&V Plan for DG/CHP System

Size: px
Start display at page:

Download "M&V Plan for DG/CHP System"

Transcription

1 for DG/CHP System Adelphi University Revised June 21, 2016 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY Submitted by: CDH Energy Corp Bingley Road Cazenovia, NY

2

3 Project Team: NYSERDA Project Manager: Joanna Moore Tel (518) x 3220 joanna.moore@nyserda.ny.gov Developer / Applicant: Simon Lessard Ecosystem th Avenue, Suite 1605 New York, NY Tel (646) x 2217 Simon.Lessard@ecosystem.ca NYSERDA QC Contractor: John Defrees Modern Energy, LLC 5533 State Route 80 Tully, NY Tel (315) john@modernenergyllc.com NYSERDA M&V Contractor: Adam Walburger Jeremy Wade CDH Energy Corp Bingley Rd Cazenovia, NY Tel (315) adam.walburger@cdhenergy.com jeremy.wade@cdhenergy.com CDH Energy Corp. 6/2016 Page i

4 Introduction Ecosystem is in the process of installing a combined heat and power (CHP) system at the Adelphi University campus in Garden City, NY. The CHP system is based on a Jenbacher JMS612, natural gas fueled, reciprocating engine generator set with a nominal electrical output rating of 1,979 kw. The site s electrical demand is sufficient to keep the system operating at or near its rated capacity on a continuous basis. The CHP system will be housed in a container to limit the noise level and allow the radiative heat to be rejected from the space. This will be accomplished by circulating tempered air through the container. The exhaust side of the container air stream will pass through a heat dump coil that will be used to reject excess waste heat from the system. A separate dry cooler will be located outside the building to provide some additional low temperature cooling requirements. The Jenbacher has separate high temperature (HT) and low temperature (LT) heat recovery loops. The HT heat will be recovered as hot water from both the engine jacket and exhaust at a final supply temperature of 205 F and supplied directly to the campus hot water loop to displace boiler operation, with a peak recovery rate of 6.75 MMBtu/h. Excess HT heat will be rejected to the container s exhaust air stream through the HT dump coil with a capacity of 2.75 MMBtu/h and exhausted to ambient. All of the LT heat will be rejected using an external dry cooler rated at MMBtu/h. Peak operation of the CHP system will result in the following performance: Gross Electrical Output: Parasitic Electrical Input (estimated): High Temperature Loop Heat Recovery: Fuel Input: 1,979 kw ~75 kw (estimated) 6.75 MMBtu/h 15.7 MMBtu/h CDH Energy Corp. 6/2016 Page 1

5 Instrumentation In order to quantify the performance of the proposed CHP system, the CHP system fuel input, net electrical output, and useful thermal output must be measured. To capture these energy flows, an instrumentation plan was developed by CDH Energy based on system configuration and information provided by the applicant, Ecosystem. The instrumentation plan covers the location and type of sensors necessary to provide the appropriate measurements of the energy flows of the system. In accordance to the instrumentation plan, Ecosystem will supply the instrumentation listed below in Table 1 for use in meeting the NYSERDA CHP program monitoring requirements. Table 1. Instrumentation Supplied by Ecosystem for CHP Analysis No. Data Point Description Eng Units Instrumentation Output Location 1 WGgross Gross Generator Output kw/ kwh Schweitzer SEL-735 Modbus CTs at Generator Mains 2 WPAR Parasitic Load kw/ kwh Carlo Gavazzi WM30 96 Type AV5 Modbus Parasitic Load MCC 3 FG Gas Consumption cf Utility Pulser Pulse Gas Service Entrance 4 FH HT Loop Flow gpm Endress Hauser Promag L 400, 5L4C1F, DN150 6" 4-20 ma (PLC Analog Input) Between V2 and V3 5 THS HT Loop Temp - After EHR HX ⁰F Siemens 100-OHM Platinum RTD Ohms (PLC Analog Input) Existing before Boiler Loop 6 THR1 HT Loop Temp - After Boiler Loop ⁰F Siemens 100-OHM Platinum RTD Ohms (PLC Analog Input) Existing after Boiler Loop 7 THR2 HT Loop Temp - After HTHC ⁰F Siemens 100-OHM Platinum RTD Ohms (PLC Analog Input) Between V2 and V3 EHR: HTHC: Exhaust Heat Recovery High Temperature Heating Coil CDH Energy Corp. 6/2016 Page 2

6 FROM GAS UTILITY WG TO ELECTRIC UTILITY WPAR TO PARASITIC LOADS COGEN CONTAINER FROM BUILDING Bypass THS Exhaust Heat Recovery HX FG WG gross FROM RETURN Bypass High Temp HX Jenbacher Gen Set 2 MW TOTAL Low Temp HX Bypass Dry Cooler THR1 THR2 FH AIR DILUTION FROM BOILER ROOM Bypass High Temp Dump Coil TO BOILERS TO RETURN TO EXHAUST Figure 1. Energy Flow Schematic for Adelphi University CHP CDH Energy Corp. 6/2016 Page 3

7 Figure 2. CHP P&ID with Locations for the Heat Recovery Instrumentation Readings for the installed instrumentation will be recorded by an Obvius AcquiSuite data logger provided and installed by CDH Energy. All field point sensors will report to a Siemens plant control system (PCS), and the CDH data logger will interface with the PCS system via a BACNET MS/TP connection, which is translated to a MODBUS RTU connection via a Control Solutions BB gateway. The data logger will sample all sensors via the PCS connection approximately once per minute and record the resulting register values. The one minute readings of heat recovery temperatures and flows will be used to provide an accurate calculation of the heat transfer on the heat recovery loop. In addition, if integrated heat transfer calculations are performed by the PCS, the data logger will collect these point for comparison to the fundamental flow and temperature difference readings. Based on the number of monitored data points, the logger will have sufficient memory to store 30-days of data if communications with the logger are interrupted. The data will be CDH Energy Corp. 6/2016 Page 4

8 downloaded from the data logger once per day via an internet connection provided by the site/applicant. The data will be loaded into a database, checked for validity, and posted on the NYSERDA web site. On Site Installation The CDH data logger and MODBUS gateway are installed in the Siemens PCS control panel. The PCS control panel provides 24 VDC power, Ethernet connection to the Internet, and BACNET MS/TP connection to the PCS. Communications The data logger will require a connection to the internet. A dedicated external static IP address will be provided by the facility that will allow access to the logger remotely for configuration purposes. The logger will upload data every night to the CDH servers. The logger has the following static IP address and network configuration. IP Address: Netmask: Gateway DNS #1 DNS #2 XXX.XXX.XXX.XXX XXX.XXX.XXX.XXX XXX.XXX.XXX.XXX XXX.XXX.XXX.XXX XXX.XXX.XXX.XXX On Site Support CDH Energy will communicate with the site and applicant for access to all areas necessary to complete the monitoring installation, as well as any return trips for verification of sensors or service to the monitoring system. CDH Energy Corp. 6/2016 Page 5

9 Data Analysis The collected data will be used to determine the net power output of the system as well as the fuel conversion efficiency (FCE). Table 2. Full Data Point List Used for CHP Energy Balance and Analysis No. Data Point Description Eng Units Notes: 1 WGgross_KW Gross Generator Output kw 2 WGgross_KWH Gross Generator Output kwh 3 WPAR_KW Parasitic Load kw 4 WPAR_KWH Parasitic Load kwh 5 WG_KW Net Generator Output kw Calculated 6 WG_KWH Net Generator Output kwh Calculated 7 FG Gas Consumption cf 8 FH HT Loop Flow gpm 9 THS HT Loop Temp - After EHR HX ⁰F 10 THR1 HT Loop Temp - After Boiler Loop ⁰F 11 THR2 HT Loop Temp - After HTDC ⁰F 12 QU Useful Recovered Heat MBtu Calculated 13 QR HT Loop Rejected Heat MBtu Calculated EHR HTDC Exhaust Heat Recovery High Temperature Dump Coil Peak Demand or Peak kw The peak electric output or demand for each power reading will be taken as the average kw in a fixed 15-minute interval (0:00, 0:15, 0:30, etc.), or Δ 0.25 The power meter measures the gross output of the generator and the net power output from the CHP system is defined as: The parasitic power is measured by a single power transducer installed in MCC-2, the CHP plant parasitic panel. The panel contains all necessary parasitic loads for operation of the CDH Energy Corp. 6/2016 Page 6

10 CHP plant. Table 3 lists the parasitic loads for the CHP system. An estimated total of kw of parasitic loads are identified. Table 3. MCC-2 Parasitic Load Panel Schedule Loads Power (HP) Power (KW) RLA (A) MCC Location Note Supply Fans : 1 VFD for 2x15 hp fans C1 2 Power from 80% LF Exhaust Fans : 1 VFD for 3x20 hp fans C2 1 Power from 80% LF Dry cooler Fan 4fans MCA 17,85 MOP C3 3 Power from 0.8 PF Boiler air make up fan 9900CFM C1 3 Power from 80% LF Scavenging fan M.02 M C4 3 Primary Oil pump # C3 1 Power from 0.85 PF Primary Oil pump # C3 2 Power from 0.85 PF HT pump 385 gpm (cold side) C2 2 Power from 80% LF Engine jacket water pump M.04 M C3 4 LT pump 110 gpm (cold side) C3 5 Power from 80% LF Prelubrification oil pump M.03 M C4 1 Suppy gearcooling water pump M.18 M C4 2 Supply 480V auxiliares 1.0 C5 4 Supply battery charge C4 4 Power from 1.0 PF Supply battery charge C4 5 Power from 1.0 PF Supply heating rods M.04 W C5 2 Gas booster C5 3 Power from 0.85 PF Lubrification Oil Pump C3 6 Power from 80% LF Maximum Parasitic Power CDH Energy Corp. 6/2016 Page 7

11 Heat Recovery Rates The heat recovery rates will be calculated offline based on the 1-minute data collected. The piping arrangement at this site allows for multiple heat rates to be determined with three temperature sensors and one flow measurement on the heat recovery loop. Useful Recovered Heat (QU) is defined as the heat transferred to the building boiler loop: 1 1 Rejected Heat (QR) is defined as the unused heat dumped into the container exhaust air stream: N is the number of scan intervals included in each recording interval (e.g., with 1-minute data, N=60). The k-factor is the product of the density and specific heat of the heat transfer fluid. The heat transfer fluid for the high temperature loop is expected to be pure water, which has a k- factor of 500Btu h gpm at an operating temperature of 205 F. CDH Energy Corp. 6/2016 Page 8

12 Calculated Quantities The net power output from the CHP system (WG), will be defined as the gross output of the generator (WG gross )minus the measured parasitic loads (WPAR). The fuel conversion efficiency of the CHP system, based on the higher heating value of the fuel, will be defined consistent with the NYSERDA CHP Systems Manual 2013 as:. 3,413 Where: QU - Useful heat recovery (Btu) Nominal boiler efficiency displaced by useful heat WG - Net generator output (kwh) FG - Generator gas consumption (Std CF) HHV gas - Higher heating value for natural gas (~1,030 Btu/CF). The FCE can be calculated for any time interval. When converting to daily, monthly, or annual values, each value is summed and then the formula below is applied:. 3,413 Where N is equal to the number of intervals in the period of interest. CDH Energy Corp. 6/2016 Page 9

13 Drawings CDH Energy Corp. 6/2016 Page 10

14

15 Waldron ecosys Tem

16 Approval manual 15 avril 2011 DRAWER SPECIFICATION TABLE ELKON drawer Identification Customer Identification Fonction Power Fuse size Voltage Phase C1-1 Power meter Energy analyser - 2/10A 480V 3 C1-2 Supply Fans Variable frequency drive 30HP 60A 480V 3 C1-3 Boiler air make up fan Variable frequency drive 20HP 40A 480V 3 C2-1 Exhaust Fans Variable frequency drive 60HP 100A 480V 3 C2-2 HT pump 385 gpm (cold side) Variable frequency drive 20HP 30A 480V 3 C3-1 Primary Oil pump #1 Starter 2HP 15A 480V 3 C3-2 Primary Oil pump #2 Starter 2HP 15A 480V 3 C3-3 Dry cooler Fan Supply 15HP 25A 480V 3 C3-4 Engine jacket water pump M.04-M002 Starter 10HP 15A 480V 3 C3-5 LT pump 110 gpm (cold side) Starter 2HP 15A 480V 3 C3-6 Lubrification oil pump Starter 1/3HP 15A 480V 3 C4-1 Prelubrification oil pump M.03-M002 Starter 3HP 15A 480V 3 C4-2 Supply gearcooling water pump M.18-M002 Starter 3/4HP 15A 480V 3 C4-3 Scavenging fan M.02-M001 Starter 1-1/2HP 15A 480V 3 C4-4 Supply battery charge 1 Supply - 15A 480V 3 C4-5 Supply battery charge 2 Supply - 15A 480V 3 C4-6 SPARE Supply - 60A 480V 3 C5-1 SPARE Supply - 150A 480V 3 C5-2 Supply heating rods M.04-W-001 Supply 12KW 20A 480V 3 C5-3 Gas booster Supply - 20A 480V 3 C5-4 Auxiliary supply Supply 1KW 15A 480V 3 C5-5 SPARE Supply - 60A 480V 3

17

18 Site Photos Woodruff Hall CHP Gross Output Meter (WG gross ) SEL-735 (top) MCC-2 Parasitic Power Meter (WPAR) THS CHP Supply to Campus Loop CDH Energy Corp. 6/2016 Page 14

19 THR1 CHP Return From Campus Loop THR2 CHP Return To CHP Unit (After Dump Coil) FHW Flow Meter & HT Circulation Pump CDH Energy Corp. 6/2016 Page 15

300 Central Park West. Site Contact. Overview. Monitoring Notes. M&V Instrumentation Installation. 300 Central Park West Site Information

300 Central Park West. Site Contact. Overview. Monitoring Notes. M&V Instrumentation Installation. 300 Central Park West Site Information 300 Central Park West 300 Central Park West New York, NY 10024 Site Contact Kevin May Project Engineer Aegis Energy Services Inc. 55 Jackson St, Holyoke MA, 01040 413-536-1156 Kmay@aegisenergyservices.com

More information

Times Square Apartments. Site Contact. Overview. M&V Instrumentation Installation. Times Square Apartments Site Information

Times Square Apartments. Site Contact. Overview. M&V Instrumentation Installation. Times Square Apartments Site Information Times Square Apartments 255 West 43 rd Street New York, NY 10036 Site Contact Sean Pringle Senior Engineer Aegis Energy Services Inc. 55 Jackson St, Holyoke MA, 01040 413-536-1156 springle@aegisenergyservices.com

More information

Avalon Fort Greene. Site Contact. Summary. Avalon Fort Greene Site Information. 343 Gold St Brooklyn, NY 11201

Avalon Fort Greene. Site Contact. Summary. Avalon Fort Greene Site Information. 343 Gold St Brooklyn, NY 11201 Avalon Fort Greene 343 Gold St Brooklyn, NY 11201 Site Contact Kevin May Project Engineer Aegis Energy Services Inc. 55 Jackson St Holyoke MA, 01040 413-536-1156 kmay@aegisenergyservices.com CDH was on

More information

FOR THE PURECELL 200 FUEL CELL. Draft. July 5, Submitted to: United Technologies Power 195 Governor s Hwy South Windsor, CT

FOR THE PURECELL 200 FUEL CELL. Draft. July 5, Submitted to: United Technologies Power 195 Governor s Hwy South Windsor, CT MONITORING PLAN FOR THE PURECELL 200 FUEL CELL AT PRICE CHOPPER IN GLENVILLE, NY Draft July 5, 2011 Submitted to: United Technologies Power 195 Governor s Hwy South Windsor, CT 06074 Submitted by: CDH

More information

MONITORING AND DATA COLLECTION STANDARD FOR DISTRIBUTED ENERGY RESOURCE (DER) SYSTEMS. Submitted to:

MONITORING AND DATA COLLECTION STANDARD FOR DISTRIBUTED ENERGY RESOURCE (DER) SYSTEMS. Submitted to: MONITORING AND DATA COLLECTION STANDARD FOR DISTRIBUTED ENERGY RESOURCE (DER) SYSTEMS July 2018 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399

More information

Addendum Gateway CHP Verification and Commissioning

Addendum Gateway CHP Verification and Commissioning Gateway CHP Verification and Commissioning Location Gateway Building 1 North Lexington Ave. White Plains, NY 10601 Attendees CDH Energy Corp. (CDH) Hugh Henderson Jeremy Wade GI Energy Peter Falcier Curtis

More information

CLARKSON UNIVERSITY, DG/CHP SYSTEM NOTES

CLARKSON UNIVERSITY, DG/CHP SYSTEM NOTES CLARKSON UNIVERSITY, DG/CHP SYSTEM NOTES The CHP system at Clarkson University consists of three (3) 65-kW Carrier microturbines and a Carrier absorption chiller packaged onto a Carrier Pure Comfort system.

More information

FOR. Burrstone Energy Center LLC. August Submitted to:

FOR. Burrstone Energy Center LLC. August Submitted to: MONITORING PLAN FOR August 2009 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Submitted by: Burrstone Energy Center,LLC 22 Century Hill

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR ONE PENN PLAZA Revised January 2011 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Submitted by: CDH

More information

MONITORING PLAN FOR THE PURECELL 400

MONITORING PLAN FOR THE PURECELL 400 MONITORING PLAN FOR THE PURECELL 400 AT 1211 AVENUE OF THE AMERICAS IN MANHATTAN, NY Draft December 6, 2011 Submitted to: United Technologies Power 195 Governor's Hwy South Windsor, CT 06074 NYSERDA 17

More information

Ultraflex MV2 Final Data Summary

Ultraflex MV2 Final Data Summary Ultraflex Final Data Summary The Ultraflex CHP site concluded on May 26, 213. As a final check on the system measured data, overall trends in the fundamental temperature, flow, power and gas use data were

More information

MONITORING PLAN FOR THE PURECELL 400 FUEL CELL

MONITORING PLAN FOR THE PURECELL 400 FUEL CELL MONITORING PLAN FOR THE PURECELL 400 FUEL CELL AT ST. FRANCIS HOSPITAL IN HARTFORD, CT Draft June 5, 203 Submitted to: Clear Edge Power 95 Governor s Hwy South Windsor, CT 06074 Submitted by: CDH Energy

More information

Allied Frozen Storage Site - Data Integrator Notes

Allied Frozen Storage Site - Data Integrator Notes Site - Data Integrator Notes Allied Food Services provides frozen food storage and warehousing services for a variety of customers. The three AFS facilities provide for approximately 9.8 million cubic

More information

Rochester Airport Data Integrator Notes

Rochester Airport Data Integrator Notes Rochester Airport Data Integrator Notes This site is an international airport located in Rochester, NY. The site has two 750 kw Waukesha engines each serving one concourse of the airport. The engines have

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN M MEASUREMENT AND VERIFICATION PLAN FOR COOP CITY RIVERBAY CORP. Revised March 2011 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Submitted

More information

THE INTREPID MUSEUM PIER 86, NEW YORK, NY COMBINED HEAT, COOLING AND POWER INSTALLATION

THE INTREPID MUSEUM PIER 86, NEW YORK, NY COMBINED HEAT, COOLING AND POWER INSTALLATION THE INTREPID MUSEUM PIER 86, NEW YORK, NY COMBINED HEAT, COOLING AND POWER INSTALLATION NYSERDA MONITORING AND VERIFICATION PLAN DRAFT SUBMISSION TO CDH, Rev 2 April 21, 2014 NYSERDA AGREEMENT NUMBER 22252

More information

SAMPLE MEASUREMENT AND VERIFICATION (M&V) PLAN

SAMPLE MEASUREMENT AND VERIFICATION (M&V) PLAN SAMPLE MEASUREMENT AND VERIFICATION (M&V) PLAN FOR BOB S FARM ANAEROBIC DIGESTER GAS (ADG) SYSTEM Agreement # ADG-XXXX July 10, 2009 Submitted to: New York State Energy Research and Development Authority

More information

MEASUREMENT AND VERIFICATION (M&V) PLAN

MEASUREMENT AND VERIFICATION (M&V) PLAN MEASUREMENT AND VERIFICATION (M&V) PLAN FOR LAMB FARM S Agreement # - ADG 121N January 19, 2010 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399

More information

Schenectady Water Pollution Control Plant

Schenectady Water Pollution Control Plant Schenectady Water Pollution Control Plant The Schenectady Water Pollution Control site has one 280 kw, turbocharged, lean burn engine generator. The engine generator system is a packaged unit and will

More information

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C L A R K S O N U N I V E R S I T Y

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C L A R K S O N U N I V E R S I T Y NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C L A R K S O N U N I V E R S I T Y October 9, 2013 Clarkson University Clarkson University DISCLAIMER OF WARRANTY Information

More information

4C Foods Data Integrator Notes

4C Foods Data Integrator Notes 4C Foods Data Integrator Notes This site is a food processing plant located in Brooklyn, NY. Three 150 kw Coast Intelligen engine generators use natural gas to generate the electric baseload for the facility.

More information

Burrstone Energy Center, LLC, St. Lukes Hospital, Home, and Utica College Data Integrator Notes

Burrstone Energy Center, LLC, St. Lukes Hospital, Home, and Utica College Data Integrator Notes Burrstone Energy Center, LLC, St. Lukes Hospital, Home, and Utica College Data Integrator Notes The Burrstone Energy Center s cogeneration plant includes four engine-generators that serve the electrical

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR DG/CHP SYSTEM AT BREVOORT EAST As-Built April 2015 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399

More information

NYSERDA s s DG/CHP Integrated Data System. chp.nyserda.org

NYSERDA s s DG/CHP Integrated Data System. chp.nyserda.org NYSERDA s s DG/CHP Integrated Data System and chp.nyserda.org Protocols for Data Collection from DG/CHP Systems Hugh Henderson, Jr., P.E. CDH Energy Corp. Cazenovia, NY What is DG/CHP? DG/CHP stands for

More information

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C O - O P C I T Y - R I V E R B A Y

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C O - O P C I T Y - R I V E R B A Y NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C O - O P C I T Y - R I V E R B A Y October 9, 2013 Co-op City - Riverbay Coop City - Riverbay DISCLAIMER OF WARRANTY Information

More information

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 300 E 40 th St Manhattan, NY The Churchill

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 300 E 40 th St Manhattan, NY The Churchill Monitoring Plan for Aegis AGEN-75 CHP System at the Churchill Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 300 E 40 th St Manhattan, NY The Churchill This document describes the measurements,

More information

Hazel Towers Data Integrator Notes

Hazel Towers Data Integrator Notes Hazel Towers Data Integrator Notes This site is a multi-family residence located in the New York City borough of the Bronx. Two CoastIntelligen generators provide electricity and heat is recovered from

More information

Noblehurst Dairy Linwood, NY

Noblehurst Dairy Linwood, NY Data Integrator Initial Data Summary Site Description This site is a dairy farm located in the Central New York town of Linwood. A 13 kw Caterpillar engine generator uses digester gas to produce electricity

More information

MEASUREMENT AND VERIFICATION (M&V) PLAN

MEASUREMENT AND VERIFICATION (M&V) PLAN MEASUREMENT AND VERIFICATION (M&V) PLAN FOR GLOVERSVILLE-JOHNSTOWN JOINT WASTEWATER TREATMENT FACILITY March 2010 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR DG/CHP SYSTEM AT SILVER TOWERS February 2013 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Submitted

More information

Adjustments To Aegis CHP Thermal Data at The Schwab House

Adjustments To Aegis CHP Thermal Data at The Schwab House Adjustments To Aegis CHP Thermal Data at The Schwab House On January 28, 2 the temperature sensors measuring CHP system glycol loop temperatures were replaced. The existing sensors (Mamac Systems TE-211Z

More information

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the th Avenue The Chelsea Mercantile

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the th Avenue The Chelsea Mercantile Monitoring Plan for Aegis AGEN-75 CHP System at The Chelsea Mercantile Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 252 7 th Avenue The Chelsea Mercantile This document describes the

More information

Vassar College - Data Integrator Notes

Vassar College - Data Integrator Notes Vassar College - Data Integrator Notes Vassar College (Vassar), located in Poughkeepsie, New York, is one of the nation's leading liberal arts colleges. The college first opened its doors in 1865 and was

More information

NORTH AMERICAN MONITORING OF A HOTEL WITH ROOM SIZE GSHPS

NORTH AMERICAN MONITORING OF A HOTEL WITH ROOM SIZE GSHPS NORTH AMERICAN MONITORING OF A HOTEL WITH ROOM SIZE GSHPS Hugh I. Henderson, Jr. P.E.*, Steven W. Carlson, P.E., and Adam C. Walburger CDH Energy Corp. Cazenovia, NY USA ABSTRACT This paper presents the

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR CHP SYSTEM AT BIRCHWOOD APARTMENTS THE KYOTO April 2015 CDH Energy Corp. PO Box 641 2695 Bingley Rd Cazenovia, NY 13035 (315) 655-1063 www.cdhenergy.com Project Team:

More information

MEASUREMENT AND VERIFICATION (M&V) PLAN FOR ROACH DAIRY FARM ANAEROBIC DIGESTER GAS (ADG) SYSTEM

MEASUREMENT AND VERIFICATION (M&V) PLAN FOR ROACH DAIRY FARM ANAEROBIC DIGESTER GAS (ADG) SYSTEM MEASUREMENT AND VERIFICATION (M&V) PLAN FOR ROACH DAIRY FARM ANAEROBIC DIGESTER GAS (ADG) SYSTEM June, 2010 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany,

More information

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 250 West 50 th Street Manhattan, NY Archstone Midtown

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 250 West 50 th Street Manhattan, NY Archstone Midtown Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the 250 West 50 th Street Manhattan, NY Archstone Midtown This document describes the measurements, sensors, and data logging equipment proposed

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR D/CHP SYSTEM AT JEWISH HOME AND HOSPITAL REENWALL PAVILION Revised August 20, 2012 Submitted to: New York State Energy Research and Development Authority 17 Columbia

More information

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T T O R E N C O N D O M I N I U M S

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T T O R E N C O N D O M I N I U M S NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T T O R E N C O N D O M I N I U M S October 9, 2013 Toren Condominiums Toren Condominiums DISCLAIMER OF WARRANTY Information contained

More information

MEASUREMENT AND VERIFICATION (M&V) PLAN

MEASUREMENT AND VERIFICATION (M&V) PLAN MEASUREMENT AND VERIFICATION (M&V) PLAN FOR TWIN BIRCH FARM ANAEROBIC DIGESTER GAS (ADG) SYSTEM June 25, 2009 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany,

More information

MONITORING AND DATA COLLECTION FOR DISTRIBUTED GENERATION/ COMBINED HEAT AND POWER (DG/CHP) SYSTEMS AT ALLIED FROZEN FOODS BROCKPORT, NEW YORK.

MONITORING AND DATA COLLECTION FOR DISTRIBUTED GENERATION/ COMBINED HEAT AND POWER (DG/CHP) SYSTEMS AT ALLIED FROZEN FOODS BROCKPORT, NEW YORK. MONITORING AND DATA COLLECTION FOR DISTRIBUTED GENERATION/ COMBINED HEAT AND POWER (DG/CHP) SYSTEMS AT ALLIED FROZEN FOODS BROCKPORT, NEW YORK. SYSTEM OVERVIEW The power generation shall be delivered via

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR DG/CHP SYSTEM AT BETH ISRAEL KINGS HIGHWAY DIVISION ECOSYSTEM ENERGY As Built December 21, 2012 Submitted to: New York State Energy Research and Development Authority

More information

Arrow Linen: CHP Washes Away Energy Costs of Commercial Laundry

Arrow Linen: CHP Washes Away Energy Costs of Commercial Laundry DISTRIBUTED ENERGY PROGRAM CASE STUDY BRIEF Arrow Linen: CHP Washes Away Energy Costs of Commercial Laundry Arrow Linen Supply Company is a commercial linen service in Brooklyn, New York, that provides

More information

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the Trump Towers City Center

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the Trump Towers City Center Monitoring Plan for Aegis AGEN-75 CHP System at the Trump Towers City Center Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the Trump Towers City Center This document describes the measurements,

More information

MEASUREMENT AND VERIFICATION (M&V) PLAN

MEASUREMENT AND VERIFICATION (M&V) PLAN MEASUREMENT AND VERIFICATION (M&V) PLAN FOR BOXLER DAIRY FARMS ANAEROBIC DIGESTER GAS (ADG) SYSTEM Contract # 116N August 26, 2009 Submitted to: New York State Energy Research and Development Authority

More information

Energy Management Workshop

Energy Management Workshop Energy Management Workshop Variable Frequency Drives for Water Systems August 24, 2016 Presenters Amanda Keyes, Tighe & Bond Mark Mizia, Eaton Corporation Michael Toto, Tighe & Bond Example VFD Application

More information

Heat Recovery. Integrated CHP Systems Corp.

Heat Recovery. Integrated CHP Systems Corp. Heat Recovery In order to achieve CHP efficiencies of 80% the recovery of waste heat for useful purposes is more significant than the electric efficiency This isn t necessarily in sync with the economics

More information

Cabrini Terrace Combined Heat and Power

Cabrini Terrace Combined Heat and Power Cabrini Terrace Combined Heat and Power NYSERDA CHP Monitoring Plan Cabrini Terrace 900 West 190 th Street New York, NY 10036 September 27, 2010 DSM Low Carbon ENGINEERING ASSOCIATES, P.C. 1363-26 Veterans

More information

Monitoring Plan for the. Cornell Combined Heat and Power Project (CCHPP) October 2008

Monitoring Plan for the. Cornell Combined Heat and Power Project (CCHPP) October 2008 Monitoring Plan for the Cornell Combined Heat and Power Project (CCHPP) October 2008 Submitted to: New York State Energy Research and Development Authority 17 Columbus Circle Albany, New York 12203-6399

More information

Energy metering is required to comply with the requirements of the Building Regulations.

Energy metering is required to comply with the requirements of the Building Regulations. Sub-Metering Aesthetic Energy metering is required to comply with the requirements of the Building Regulations. All energy usage for water, heat, chilled water, steam, compressed air, electricity and gas

More information

VLM10 In-line Vortex Mass Flow Meter

VLM10 In-line Vortex Mass Flow Meter VLM10 In-line Vortex Mass Flow Meter Description The VLM10 in-line vortex flowmeter measures process fluid flow by detecting the frequency at which vortices are shed from an obstruction in the process

More information

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T V A S S A R C O L L E G E

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T V A S S A R C O L L E G E NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T V A S S A R C O L L E G E October 9, 2013 Vassar College Vassar College DISCLAIMER OF WARRANTY Information contained on this web

More information

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the th Ave Manhattan, NY Archstone Chelsea

Monitoring and Analysis Plan for Aegis AGEN-75 CHP System at the th Ave Manhattan, NY Archstone Chelsea Monitoring and Analysis Plan for Aegis AEN-75 CHP System at the 800 6 th Ave Manhattan, NY Archstone Chelsea This document describes the measurements, sensors, and data logging equipment proposed to quantify

More information

PROJECT NAME CLEVELAND CLINIC PROJECT #

PROJECT NAME CLEVELAND CLINIC PROJECT # CLEVELAND CLINIC PROJECT # [This is a sample of a general project M&V specification these specifications should be incorporated into the HVAC Control specifications and modified to the specific job requirements]

More information

TransPacific Energy Advantage: Case Studies

TransPacific Energy Advantage: Case Studies TransPacific Energy Advantage: Case Studies Typical Power Plant TPE-ORC 0.60 KWh ORC 2.3 KWh LP steam 0.35 KWh 30% (maximum) 2.05 KWh CHP Typical Power Generated 1.1 KWh Typical Power Wasted 2.31 KWh Typical

More information

East Rochester School District East Rochester, NY

East Rochester School District East Rochester, NY East Rochester School District East Rochester, NY Data Integrator Initial Data Summary Data Description Beginning on June 11, 28, ATSI began submitting data to CDH Energy data for the East Rochester School

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR DG/CHP SYSTEM AT MILLENNIUM BROADWAY HOTEL March 2015 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399

More information

FLEXIM. FLUXUS Energy. Precision Ultrasonic Flow and Thermal Energy Meters. Unparalleled measurement of low flow rates.

FLEXIM. FLUXUS Energy. Precision Ultrasonic Flow and Thermal Energy Meters. Unparalleled measurement of low flow rates. Unparalleled measurement of low flow rates Energy Efficiency - Continuous Commissioning - Building Optimization Precision Ultrasonic Flow and Thermal Energy Meters Technical Data / BTU: Cost of Not Metering

More information

MEASUREMENT AND VERIFICATION PLAN

MEASUREMENT AND VERIFICATION PLAN MEASUREMENT AND VERIFICATION PLAN FOR ARKER COMPANIES 195 STEUBEN STREET CHP SYSTEM March, 2015 Submitted to: New York State Energy Research and Development Authority 17 Columbia Circle Albany, NY 12203-6399

More information

YANMAR s 35 kw Combined Heat and Power System.

YANMAR s 35 kw Combined Heat and Power System. YANMAR s 35 kw Combined Heat and Power System www.yanmar-es.com YANMAR s 35 kw Combined Heat and Power System A DIFFERENT MINDSET = GAME CHANGER When thinking about heat and power for commercial buildings,

More information

Electromagnetic Flange Type BTU METERS. eflow 800H SERIES. Size DN10 to DN1200 DESCRIPTION APPLICATION FEATURES

Electromagnetic Flange Type BTU METERS. eflow 800H SERIES. Size DN10 to DN1200 DESCRIPTION APPLICATION FEATURES DESCRIPTION eflow 800H series is flange type Electromagnetic Heat or BTU meter that can be used for measuring energy consumption in heating or cooling application for HVAC and other energy measurement

More information

Equipment Design. Detailed Plant Conceptual Design. Version 9.0

Equipment Design.  Detailed Plant Conceptual Design. Version 9.0 Equipment Design Version 9.0 Detailed Plant Conceptual Design SOAPP CT sizes all major plant equipment, based on your Project Input, the process configuration derived from this input, and the results of

More information

Organic Rankine Cycle Waste Heat Solutions And Opportunities In Natural Gas Compression > The renewable energy source

Organic Rankine Cycle Waste Heat Solutions And Opportunities In Natural Gas Compression > The renewable energy source Organic Rankine Cycle Waste Heat Solutions And Opportunities In Natural Gas Compression > The renewable energy source BY JOHN FOX t takes a significant amount of energy to transport the ever-growing supply

More information

Equipment Design. Detailed Plant Conceptual Design. Version 7.0

Equipment Design.   Detailed Plant Conceptual Design. Version 7.0 Equipment Design Version 7.0 Detailed Plant Conceptual Design SOAPP CT sizes all major plant equipment, based on your Project Input, the process configuration derived from this input, and the results of

More information

A TECHNOLOGY FOR TODAY. Atlanta 2010

A TECHNOLOGY FOR TODAY. Atlanta 2010 A TECHNOLOGY FOR TODAY Atlanta 2010 Mechanical Systems Manager Smith College, Northampton, MA Overview Cogeneration Benefits Technologies Case Studies Why do Colleges have Physical Plants? Power Houses?

More information

December 13, 2012 Energy Efficient Cooling Information Service Webinar Series Christine Brinker and Gearoid Foley CHP with Absorption Chilling

December 13, 2012 Energy Efficient Cooling Information Service Webinar Series Christine Brinker and Gearoid Foley CHP with Absorption Chilling December 13, 2012 Energy Efficient Cooling Information Service Webinar Series Christine Brinker and Gearoid Foley CHP with Absorption Chilling Technical Assistance Education and Outreach Executive Order

More information

Applying Geothermal Technology for Large Scale Projects

Applying Geothermal Technology for Large Scale Projects Jeff Urlaub, PE MEP Associates, LLC jeffu@mepassociats.com 715.832.5680 Engineering Future Focused Solutions Applying Geothermal Technology for Large Scale Projects Breakout Session Category (e.g. Residential)

More information

Knowledge is Power Belimo Energy Valve CHW DELTA T MITIGATION STUDY AHR Expo Innovation Award Winner in the Category of Building Automation

Knowledge is Power Belimo Energy Valve CHW DELTA T MITIGATION STUDY AHR Expo Innovation Award Winner in the Category of Building Automation Knowledge is Power Belimo Energy Valve CHW DELTA T MITIGATION STUDY 2014 AHR Expo Innovation Award Winner in the Category of Building Automation The Belimo Energy Valve won the Technical Innovation of

More information

Implications of Measured Commercial Building Loads on Geothermal System Sizing

Implications of Measured Commercial Building Loads on Geothermal System Sizing Implications of Measured Commercial Building Loads on Geothermal System Sizing ASHRAE Annual Meeting June 23, 1999 Hugh I Henderson, Jr.. P.E. CDH Energy Corp. Cazenovia,, NY www.cdhenergy.com Overview

More information

You can t manage what you don t measure. Accurate solutions for District Energy, HVAC and Energy Efficiency. Process Instrumentation

You can t manage what you don t measure. Accurate solutions for District Energy, HVAC and Energy Efficiency. Process Instrumentation You can t manage what you don t measure. Accurate solutions for District Energy, HVAC and Energy Efficiency. Process Instrumentation usa.siemens.com/hvacr The Siemens promise: Quality our first priority

More information

Heat recovery from industrial installations

Heat recovery from industrial installations Environmentally friendly For high temperature applications, AQYLON s organic working fluids have a very low Global Warming Potential (320). Rugged AQYLON s ORC modules are designed for durability and fit

More information

Mechanical Project Proposal

Mechanical Project Proposal Mechanical Project Proposal Miller Children s Hospital Prepared for: Dr. James Freihaut Department of Architectural Engineering The Pennsylvania State University Prepared by: Stephen Haines December 18

More information

ENERGY AUDIT of FULLY CONDENSING BOILER STACK ECONOMIZER

ENERGY AUDIT of FULLY CONDENSING BOILER STACK ECONOMIZER FULLY CONDENSING BOILER STACK ECONOMIZER for: CENTRAL WASHINGTON UNIVERSITY Ellensburg, Washington prepared by: 12655 Center Drive, Suite 250 Beaverton, Oregon 97005 Contact: Mark E. Kinzer markk@abacusrm.com

More information

SolarCity Partnership. Toronto Fire Station # kwt Solar Water Heating Installation. Technology. Monitoring. Best Practices

SolarCity Partnership. Toronto Fire Station # kwt Solar Water Heating Installation. Technology. Monitoring. Best Practices Toronto Fire Station #212 12.5 kwt Solar Water Heating Installation Final Report January 2012 Technology Monitoring Best Practices SolarCity Partnership PROJECT SNAPSHOT Address: 8500 Sheppard Avenue East,

More information

UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall th Street San Francisco, California

UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall th Street San Francisco, California UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall 1550 4th Street San Francisco, California Monitoring Based Recommissioning Project Project Implementation: June 2005 to December 2005 Funded by a

More information

QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) PLAN

QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) PLAN QUALITY ASSURANCE/QUALITY CONTROL (QA/QC) PLAN FOR AURORA RIDGE DAIRY LLC BIOLOGICAL SCRUBBER SYSTEM Agreement # 42049 June 5, 2015 Submitted to: New York State Energy Research and Development Authority

More information

Measurement & Verification Report for Alltemp Refrigerant: Preliminary Results Macy s Department Store Manhattan Beach, CA

Measurement & Verification Report for Alltemp Refrigerant: Preliminary Results Macy s Department Store Manhattan Beach, CA Measurement & Verification Report for Alltemp Refrigerant: Preliminary Results Macy s Department Store Manhattan Beach, CA Mark Stetz, P.E. CMVP CRM BEAP Stetz Consulting LLC Durango, CO www.stetzconsulting.com

More information

Fume Incinerators Engines. Thermal Oxidizers Turbines. Catalytic Converters. Fuel Cells. Furnaces

Fume Incinerators Engines. Thermal Oxidizers Turbines. Catalytic Converters. Fuel Cells. Furnaces Cain Industries manufactures waste heat recovery and steam generator systems for the cogeneration (CHP), boiler economizer and industrial heat exchanger markets. Combustion Sources: Boilers Fume Incinerators

More information

Traditional and Non-Traditional Applications of Condensing Heat Exchangers

Traditional and Non-Traditional Applications of Condensing Heat Exchangers Traditional and Non-Traditional Applications of Condensing Heat Exchangers John DeFrees, LaBella Associates Amy Dickerson, New York State Energy Research and Development Authority ABSTRACT Combustion processes

More information

TECHNICAL ASSISTANCE STUDY IN SUPPORT OF NEW CONSTRUCTION PROGRAM

TECHNICAL ASSISTANCE STUDY IN SUPPORT OF NEW CONSTRUCTION PROGRAM Version 3.1 TECHNICAL ASSISTANCE STUDY IN SUPPORT OF NEW CONSTRUCTION PROGRAM Completed by Pathfinder Engineers & Architects 134 South Fitzhugh Street Rochester, NY 14608 For Binghamton University PO Box

More information

Army Exceeds Energy Goal Ahead of Mandate (Actual Energy Reduction of 38% vs 30% and Achieved in 2010 vs 2015)

Army Exceeds Energy Goal Ahead of Mandate (Actual Energy Reduction of 38% vs 30% and Achieved in 2010 vs 2015) Army Exceeds Energy Goal Ahead of Mandate (Actual Energy Reduction of 38% vs 30% and Achieved in 2010 vs 2015) NDIA E 2 S 2 May 9-12, 2011 New Orleans, LA Overview Background Energy Conservation Measures

More information

Meters Performance Guide

Meters Performance Guide MEASUREMENT & VERIFICATION SYSTEM FOR NEW MEXICO PUBLIC SCHOOLS Meters Performance Guide Revised on: March 20, 2017 Hisham Tariq Environmental Operations Engineer Contents 1. System Description... 3 2.

More information

How to Use Your Existing SCADA for Energy Management. Don Best, HDR Engineering, Inc.

How to Use Your Existing SCADA for Energy Management. Don Best, HDR Engineering, Inc. How to Use Your Existing SCADA for Energy Management Don Best, HDR Engineering, Inc. Presentation Outline Energy Management Connect a Power Meter to SCADA Understand Your Electric Bill Energy Benchmark

More information

Thesis Final Presentation

Thesis Final Presentation Acoustical lanalysis Thesis Final Presentation Facility Information Mechanical Information Goals Facility Information Location: Total Cost: $56,000,000 Occupancy: Office, Media Center Delivery Method:

More information

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load. Redesign Introduction This report is an in depth analysis of the mechanical systems of the Outreach Innovation Building located in University Park, PA and the impact these changes had on other systems

More information

Energy Reduction Programs: Understanding, Implementing & Delivering. PL Energy Services

Energy Reduction Programs: Understanding, Implementing & Delivering. PL Energy Services Energy Reduction Programs: Understanding, Implementing & Delivering PL Energy Services PL Energy Services Value to Condominium Directors Control Maintenance Fees Maximize Rebates Measurement & Verification

More information

Pepsi Co. College Point, NY

Pepsi Co. College Point, NY Pepsi Co. College Point, NY Data Integrator Initial Data Summary Data Description Beginning on March 1, 7, Consolidated Edison Solutions began sending CDH Energy data for the Pepsi Co. plant located in

More information

6 Cost Analysis. Table 6.1 Initial System Costs

6 Cost Analysis. Table 6.1 Initial System Costs 6.1 Considerations 6 Analysis There are two parts that need to be considered when looking into a cost analysis. The first is determining the initial cost of the system to determine whether or not a simple

More information

Altivar AC Drives. Advanced energy management and performance in motor control. altivardrives.com

Altivar AC Drives. Advanced energy management and performance in motor control. altivardrives.com Altivar AC Drives Advanced energy management and performance in motor control altivardrives.com 988-19614608_US_A.indd 1 2 altivardrives.com Schneider Electric Segment focused. Customer centric. Schneider

More information

Pro-V Multivariable Flowmeter Model M23 Insertion Vortex

Pro-V Multivariable Flowmeter Model M23 Insertion Vortex Pro-V Multivariable Flowmeter Model M23 Insertion Vortex Pro-V TM Advantage: Volumetric or mass flow monitoring of most liquids, gases, and steam Multivariable meter delivers mass flow, temperature, pressure,

More information

Characteristics of Energy Consumption by building type of a U.S. Navy Installation in Hot and Humid Climate

Characteristics of Energy Consumption by building type of a U.S. Navy Installation in Hot and Humid Climate Purdue University Purdue e-pubs International High Performance Buildings Conference School of Mechanical Engineering 216 Characteristics of Energy Consumption by building type of a U.S. Navy Installation

More information

Development of the First Combined Heat and Power Plant in the Caribbean (CHP District Energy)

Development of the First Combined Heat and Power Plant in the Caribbean (CHP District Energy) Development of the First Combined Heat and Power Plant in the Caribbean (CHP District Energy) Presented at the IDEA2016 107 th Annual Conference & Trade Show June 20-23, 2016 St. Paul, MN This paper will

More information

Section 17 Metering and Controls.

Section 17 Metering and Controls. Design Guidelines Section 17 Metering and Controls. www.canterbury.ac.nz/learningresources Standards in the Design Guidelines Suite Design Standard Guidelines Index: 01 General 02 Architecture 03 Audio

More information

Series TUF Ultrasonic Energy Meter with BACnet Communication. Specifications - Installation and Operating Instructions 4-1/4 [108.

Series TUF Ultrasonic Energy Meter with BACnet Communication. Specifications - Installation and Operating Instructions 4-1/4 [108. Series TUF Ultrasonic Energy Meter with BACnet Communication Specifications - Installation and Operating Instructions Bulletin F-TUF-B-DC 4-1/4 [18.] 2.8 WATER-IN FLOW SENSOR 4 FLOW PIPE TEMP SENSOR 2.8

More information

Development of the First Combined Heat and Power plant in the Caribbean (CHP District Energy)

Development of the First Combined Heat and Power plant in the Caribbean (CHP District Energy) Development of the First Combined Heat and Power plant in the Caribbean (CHP District Energy) Presented in the DistribuGen Conference & Trade Show for Cogeneration/CHP 2015 April 7-9, 2015 Houston, Texas

More information

SGM Engineering, Inc.

SGM Engineering, Inc. SGM Engineering, Inc. 1. What is a typical Central Energy Plant consists of? BAS controls, chillers, pumps, cooling towers, electrical distribution, piping, chemicals, heating systems, and generators.

More information

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012 Cogeneration and Thermal Chillers.. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012 Agenda Cogeneration Interest and Application Basics Equipment Matching Thermal Chiller Overview Steam Components

More information

Pro-V Multivariable Flowmeter Model M23 Insertion Vortex

Pro-V Multivariable Flowmeter Model M23 Insertion Vortex Pro-V Multivariable Flowmeter Model M23 Insertion Vortex Pro-V TM Advantage: Volumetric or mass flow monitoring of most liquids, gases, and steam Multivariable meter delivers mass flow, temperature, pressure,

More information

Risto Lahdelma Professor, Energy technology for communities Tel:

Risto Lahdelma Professor, Energy technology for communities   Tel: Energiatekniikan laitos District heating engineering - DH Production Risto Lahdelma Professor, Energy technology for communities Email: risto.lahdelma@aalto.fi Tel: +358 40 503 1030 Haichao Wang Doctor

More information

BUILDING FOR THE FUTURE

BUILDING FOR THE FUTURE BUILDING FOR THE FUTURE The following article was published in ASHRAE Journal, September 4. Copyright 4 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented

More information