1 LOUISIANA URBAN STORMWATER COALITION EXECUTING A SWPPP DURING CONSTRUCTION Presented by: Diane T. Baum
2 SWPPP NOTIFICATION SIGN Post sign at entrance of site or areas where the public can easily access. Identify inspector and contact numbers. Prefer contacting SWPPP inspector than municipality or DEQ.
3 OVERVIEW : SECTIONS OF A SWPPP SECTION 1: SITE EVALUATION, ASSESSMENT & PLANNING SECTION 2: EROSION AND SEDIMENT CONTROL BMPS SECTION 3: GOOD HOUSEKEEPING BMPS SECTION 4: SELECTING POST-CONSTRUCTION BMPs SECTION 5: INSPECTIONS SECTION 6: RECORDKEEPING AND TRAINING SECTION 7: FINAL STABILIZATION SECTION 8: CERTIFICATION AND NOTIFICATION SWPPP APPENDICES
4 EROSION CONTROL Minimizing the Impact of Construction: 1. Minimize disturbed area and protect natural features and soil 2. Phase construction activity 3. Control stormwater flowing onto and through the project 4. Stabilize soils promptly 5. Protect slopes Sediment Controls (the second line of defense): 6. Protect storm drain inlets 7. Establish perimeter controls 8. Retain sediment on-site and control dewatering practices 9. Establish stabilized construction exits 10. Inspect and maintain controls September 21-22, 2011
5 WHAT IS STABILIZATION IN A SWPPP? EPA s Construction General Permit : stabilization measures must be initiated as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased, but in no case more than 14 days after the construction activity in that portion of the site has temporarily or permanently ceased.
6 WASTE MANAGEMENT Provide for waste management. Design proper management procedures and practices to prevent or reduce the discharge of pollutants to stormwater from solid or liquid wastes that will be generated at your site. Practices such as trash disposal, recycling, proper material handling, and cleanup measures can reduce the potential for stormwater runoff to pick up construction site wastes and discharge them to surface waters. Determine if your site is following LEED requirements.
7 NON-STORMWATER DISCHARGES Non-stormwater discharges that are allowable should be identified: Discharges from fire-fighting activities, Fire hydrant flushings Waters used to wash vehicles where detergents are not used Water used to control dust in accordance with EPA s CGP, Part 3, Subpart 3.4.G Potable water including uncontaminated water line flushing Routine external building wash down that does not use detergents Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spilled material has been removed) and where detergents are not used Uncontaminated air conditioning or compressor condensate Uncontaminated ground water or spring water Foundation or footing drains where flows are not contaminated with process materials such as solvents Uncontaminated excavation dewatering Landscape irrigation
8 SWPPP SECTION 4 SECTION 4: SELECTING POST-CONSTRUCTION BMPs Depends on the local municipality and codes but should have some stormwater post features.
9 SWPPP SECTION 5 SECTION 5: INSPECTIONS Inspections Delegation of Authority Corrective Action Log
10 INSPECTION FREQUENCY > Your construction general permit describes the minimum frequency of inspections, which is typically weekly or every 14 days and after each rainfall event exceeding one-half inch. > To meet the requirement to maintain all BMPs in good working order, EPA recommends that you develop an inspection schedule that goes beyond these minimums and is customized for your site and the conditions affecting it.
11 Training Log SWPPP SECTION 6 SECTION 6: RECORDKEEPING AND TRAINING Recordkeeping Log of Changes to the SWPPP Training Always keep a log of changes and amend the SWPPP as needed. Make sure all records are kept in an orderly fashion. Make sure training is conducted for all employees and signatures are kept for records.
12 SWPPP SECTION 7 SECTION 7: FINAL STABILIZATION Final stabilization is when more than 70% of the site is stabilized with temporary (hay mats with seed) or permanent stabilization (landscape and grass). Only then can the permit and the SWPPP plan be closed out Make sure NOI is terminated at DEQ offices is submitted. Insure the SWPPP and inspections are archived for 3 years in the event of an audit.
13 SIGNATORY All SWPPP plans and inspections needs to be signed by someone in the company with authority. It must have this certification: I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Do not falsify records EVER! then it becomes criminal violation
14 QUESTIONS AND DISCUSSION SWPPP, BMPS, SPECIFICATIONS?
CHAPTER 6 - How to Prepare a SWPPP
All construction sites which disturb an area of 1 acre or more, currently need a UPDES permit from the State of Utah. As a condition of the permit, a Stormwater Pollution Prevention Plan (SWPPP) must be
More informationCITY OF VIRGINIA BEACH STORMWATER POLLUTION PREVENTION PLAN (SWPPP) FOR SINGLE FAMILY RESIDENCES AND ACCESSORY STRUCTURES ONLY
CITY OF VIRGINIA BEACH STORMWATER POLLUTION PREVENTION PLAN (SWPPP) FOR SINGLE FAMILY RESIDENCES AND ACCESSORY STRUCTURES ONLY Activities Information: Project Site Name: Location & Address: City, State,
More informationStormwater Pollution Prevention Plan (SWPPP) For Single Family Residential Construction within a larger plan of development
COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Tel. (434) 296-5832 Fax (434) 972-4126 Stormwater Pollution Prevention Plan (SWPPP)
More informationStormwater Pollution Prevention Plan (SWPPP) For Single Family Residential Construction within a larger plan of development
COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Tel. (434) 296-5832 Fax (434) 972-4126 Stormwater Pollution Prevention Plan (SWPPP)
More informationCOUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia Tel.
COUNTY OF ALBEMARLE Department of Community Development 401 McIntire Road, North Wing Charlottesville, Virginia 22902-4596 Tel. (434) 296-5832 Fax (434) 972-4126 Stormwater Pollution Prevention Plan (SWPPP)
More informationProject Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)
Compliance Assistance Program Checklist 1 Start of Construction Stormwater Self-Certification Checklist Note: This checklist must be completed and submitted to the DEM no later than 30 days after initiating
More informationLAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET
Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000
More informationLAMINATE AND POST AT JOB SITE NOTICE MUST BE VISIBLE FROM STREET
Permit. ARR150000 SITE WITH AUTOMATIC COVERAGE (LESS THAN 5 ACRES) CONSTRUCTION SITE NOTICE FOR THE Arkansas Department of Environmental Quality (ADEQ) Storm Water Program NPDES GENERAL PERMIT NO. ARR150000
More informationAppendix A: SWPPP Template Instructions
Appendix A: SWPPP Template Instructions To help you develop the narrative section of your construction site SWPPP, EPA has created this electronic SWPPP template. The template is designed to help guide
More informationTexas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR Storm Water Pollution Prevention Plan Worksheet Instructions
Texas Pollutant Discharge Elimination System Industrial Storm Water Permit TXR050000 Storm Water Pollution Prevention Plan Worksheet Instructions The TCEQ Small Business and Local Government Assistance
More informationSTORM WATER POLLUTION PREVENTION PLAN TEMPLATE
STORM WATER POLLUTION PREVENTION PLAN TEMPLATE Cover Page Certifications Project, Owner, Operator, SWPPP Preparer, Date, Project Dates Signed by RIDOT (Owner) and CONTRACTOR (as Operator) of Contents Introduction
More information901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT
SECTION 901 STORMWATER POLLUTION MANAGEMENT 901.1 DESCRIPTION Design, implement, inspect and maintain appropriate best management practices to minimize or eliminate erosion, sediment and other pollutants
More informationFACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES
FACT SHEET GENERAL KPDES PERMIT FOR STORM WATER POINT SOURCE DISCHARGES CONSTRUCTION ACTIVITIES 1. COVERAGE UNDER THIS GENERAL PERMIT Area of Coverage: This permit covers all areas of the Commonwealth
More informationClean Water Act Industrial Stormwater Applicability Flowchart. July 2009
Clean Water Act Industrial Stormwater Applicability Flowchart July 2009 Office of Compliance Office of Enforcement and Compliance Assurance U.S. Environmental Protection Agency 1200 Pennsylvania Avenue,
More informationChecklist Stormwater Pollution Prevention Plan (SWPPP)
Checklist Stormwater Pollution Prevention Plan (SWPPP) Project: Reviewed: 1. Site Evaluation and Design Development A. Collect Site Information Existing soils information Existing runoff water quality
More informationStormwater Pollution Prevention Plan Engineering Department Requirements
Stormwater Pollution Prevention Plan Engineering Department Requirements The following are the stormwater pollution prevention plan requirements for the above referenced project. If you have any questions
More informationPOLLUTION PREVENTION TEAM MEMBER ROSTER. Leader: Members: (1) Title: Worksheet #1 Completed by: Title: Date: Title: Office Phone: Responsibilities:
POLLUTION PREVENTION TEAM MEMBER ROSTER Worksheet #1 Leader: Responsibilities: Office Phone: Members: (1) Responsibilities: Office Phone: (2) Responsibilities: Office Phone: (3) Responsibilities: Office
More informationSINGLE FAMILY RESIDENCE COMMON PLAN of DEVELOPMENT or SALE STORMWATER POLLUTION PREVENTION PLAN (SWPPP) For Construction Activities At:
SINGLE FAMILY RESIDENCE COMMON PLAN of DEVELOPMENT or SALE (SWPPP) For Construction Activities At: Project/Site Name Project/Site Location & Address City, State, Zip Code Latitude:. N (decimal degrees)
More informationStormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Small Construction Sites
Stormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Small Construction Sites National Pollutant Discharge Elimination System (NPDES) General Permit # Prepared for: Date: Prepared
More informationDIVISION of WATER QUALITY NDPDES PROGRAM
DIVISION of WATER QUALITY NDPDES PROGRAM THIS PAGE IS NOT PART OF ANY SWPPP CONSTRUCTION Storm Water Pollution Prevention Plan * SWPPP Template (2016-01) A SWPPP must be prepared and implemented for all
More informationStormwater Pollution Prevention Training
Stormwater Pollution Prevention Training Arkansas General Stormwater Permit For Industrial Activities (ARR00000) Presented by Jeremy Stehle ECCI Senior Environmental Scientist Background and Development
More informationSWPPP Inspection Procedures and Form 247 Instructions
SWPPP Inspection Procedures and Form 247 Instructions 1. Pre-Construction Conference a. A stormwater pollution pre-construction conference shall be held prior to beginning work on each project. b. The
More informationCity of Waukegan, Illinois
City of Waukegan, Illinois NPDES Phase II Stormwater Program Stormwater Pollution Prevention Plan Public Works Facility July 2011 City of Waukegan, Illinois Stormwater Pollution Prevention Plan for the
More informationRisk Level 1 Annual Report Questions GENERAL INFO
GENERAL INFO A. Site Owner Information Owner Name: Owner Address: City: State: Owner Contact: E-Mail: Phone: Zip: B. Site Information Site Business Name: Site WDID No: Physical Address: City: Site Contact:
More informationSection 4: Managing the Construction Site
Section 4: Managing the Construction Site 4.1 Mobilization 33 4.1.1 Posting the SWPPP 33 4.1.2 Initial installation of BMP s 33 4.1.3 Mobilization Checklist for Initial Installation 34 4.2 Maintaining
More informationCommon Plan SWPPP for
Stormwater Pollution Prevention Plan Template (SWPPP) (This SWPPP Template is for the Only, and does NOT address SWPPP requirements found in the CGP.) Common Plan SWPPP for Date 1. Project Information
More informationCity of Glendale Stormwater Management Plan Checklist
City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP
More informationSTORM WATER POLLUTION PREVENTION PLAN (SWPPP)
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) Name of Tenant and Facility Date: Emergency Contact: Title: Phone: INSTRUCTIONS FOR MERRILL FIELD TENANTS TO OBTAIN COVERAGE UNDER THE NPDES STORM WATER DISCHARGE
More informationUnderstanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)
Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department
More informationStormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Large Construction Sites
Stormwater Pollution Prevention Plan (SWPPP) for Construction Activity for Large Construction Sites National Pollutant Discharge Elimination System (NPDES) General Permit # ARR150000 Prepared for: Date:
More informationMinnesota Pollution Control Agency requires that the City of Brainerd develop written procedures for
I. INTRODUCTION The owns and operates an MS4 ( Municipal Separate Storm Sewer System). The Minnesota Pollution Control Agency requires that the develop written procedures for the purpose of eliminating
More informationStorm Water Pollution Prevention Plan for CES Gravel #3800
David Lewis Cell: (870) 310-2757 Rickey Vaughn Cell: (870) 310-9602 Buddy McAdams Cell: (870) 310-8733 Local (870) 881-8830 Fax: (870) 881-8809 LICENSED, BONDED & INSURED Howard Cupp, Jr. Cell: (870) 314-2877
More informationSTORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY
STATE OF COLORADO GENERAL PERMIT APPLICATION Updated 11/04 STORMWATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITY This application is for use by all stormwater dischargers engaged in construction
More informationSTORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No
STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents Site Description A description of construction activity. The proposed sequence for major activities. Estimates of the total
More informationDEQ Form Oct 18, Part A: Operator Information and Certification. DEQ Authorization Number: OKR10
DEQ Form 606-005 Oct 18, 2017 Oklahoma Department of Environmental Quality Annual Comprehensive Site Compliance Evaluation Report (ACSCER) for Stormwater Discharges Associated with Construction Activity
More informationVillage of Northbrook, Illinois Stormwater Pollution Prevention Plan Public Works and Fleet Maintenance Garage Facilities
Village of Northbrook, Illinois Stormwater Pollution Prevention Plan Public Works and Fleet Maintenance Garage Facilities Village of Northbrook, Illinois Stormwater Pollution Prevention Plan Public Works
More informationConstruction Phasing Bad
Construction Entrances Construction Phasing Remove mud and dirt from the tires of construction vehicles before they enter a paved roadway. Propoerly size entrance BMP's for all anticipated vehicles. Make
More informationCON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist
Con Appendix FINAL US Army Garrison, Hawaii October 2015 CON APPENDIX C USAG HI Storm Water Pollution Prevention Plan Content Review Checklist Storm Water Management Plan CON Appendix C U.S. Army Garrison-Hawaii
More informationOutdoor Equipment Operations SC-32
Description Outside process equipment operations and maintenance can contaminate stormwater runoff. Activities, such as grinding, painting, coating, sanding, degreasing or parts cleaning, landfills and
More informationErosion Control Inspection Form
Project Name Address Inspection Date Time Name of Certified Erosion Sediment Lead (CESCL) or qualified inspector if less than one acre Print Name: Approximate rainfall amount since the last inspection
More informationQSD/QSP Training Module 9 SWPPP Preparation
QSD/QSP Training Module 9 SWPPP Preparation Anna Lantin, P.E., CPESC, CPSWQ Overview and Learning Objectives Given a project Risk Level or LUP Type, you will learn to: Prepare a compliant SWPPP Determine
More informationConstruction Site Runoff (CSR) Permit Application Permit Fee $150.00
Construction Site Runoff (CSR) Permit Application Permit Fee $150.00 Site Address or Lot and Subdivision: Applicant Name: Applicant s E-Mail: Applicant s Address: Telephone: (office) City, State, ZIP (cell)
More informationSTORMWATER POLLUTION PREVENTION PLAN (SWP3)
City of Moore, Oklahoma Community Development Department 301 North Broadway Moore, Oklahoma 73160 STORMWATER POLLUTION PREVENTION PLAN (SWP3) The SWP3 is a written narrative describing the site, potential
More informationEROSION CONTROL AND GRADING PERMIT APPLICATION
EROSION CONTROL AND GRADING PERMIT APPLICATION COMMUNITY DEVELOPMENT DEPARTMENT 1735 MONTGOMERY STREET OROVILLE, CA 95965 530-538-2420 FAX (530) 5382426 www.cityoforoville.org APPLICATION DATE PERMIT FEE
More informationATTACHMENT C RISK LEVEL 1 REQUIREMENTS
ATTACHMENT C RISK LEVEL 1 REQUIREMENTS A. Effluent Standards [These requirements are the same as those in the General Permit order.] 1. Narrative Risk Level 1 dischargers shall comply with the narrative
More informationStormwater Outreach for Regional Municipalities (STORM) Overview. Maintaining an Updated SWPPP Site Map Required Elements Good Examples Bad Examples
Stormwater Outreach for Regional Municipalities (STORM) Kevin Boesch, CPESC Overview Maintaining an Updated SWPPP Site Map Required Elements Good Examples Bad Examples Inspection Frequencies Inspection
More informationSWPPP Checklist. Project Name: Review Date(s): Reviewer(s): Project Type: Subdivision. Site Plan City Project
SWPPP Checklist Project Name: Review Date(s): Reviewer(s): Project Type: Subdivision Site Plan City Project Project Description: Are the following provided? Project location - street address and/or latitude/longitude
More informationBuilding Better Storm Water Quality
Building Better Storm Water Quality s Storm Water Pollution Prevention Guidelines for Development Construction Projects City of El Segundo 350 Main Street (310) 524-2380 El Segundo, California 90245 Introduction
More informationDivision of Water Quality (701)
Division of Water Quality (701) 328-5210 stormwater@nd.gov March April 2018 1 Construction Permit Permit #: NDR10-0000 Reissued April 1, 2015 Expires March 31, 2020 2 Discharges Covered Stormwater Discharges
More informationInspection Requirements of the CGP 2013
Inspection Requirements of the CGP 2013 Stormwater Outreach for Regional Municipalities (STORM) Dennis L. Turner Surface Water Programs Consultant Arizona Department of Environmental Quality (ADEQ) dt1@azdeq.gov
More informationContractors, Illicit Discharges, & Best Management Practices. Chris Allen Stormwater Inspector
Contractors, Illicit Discharges, & Best Management Practices Chris Allen Stormwater Inspector What is an Illicit Discharge? Georgetown County Stormwater Ordinance defines an Illicit Discharge as: Any activity
More informationAPPENDIX A BLANK RECORDKEEPING FORMS AVI-CPL-001
APPENDIX A BLANK RECORDKEEPING FORMS Checklist 1 Quarterly SWP3 Inspection Business Name: Date: Weather: Inspector(s): Inspector Affiliation: Inspector familiar with industrial activities performed at
More informationSCDOT & the NPDES Program
SCDOT & the NPDES Program Presentation Outline Introduction and Overview Permitting Storm Water Management and Planning What is the NPDES Program? National Pollutant Discharge Elimination System Controls
More informationNDDOT Erosion & Sediment Control Construction Course
NDDOT Erosion & Sediment Control Construction Course Module 4: Stormwater Pollution Prevention Plan (SWPPP) 1 What s covered in this module? 1. What is a SWPPP 2. Important initial considerations that
More informationLAKE CHARLES HARBOR & TERMINAL DISTRICT BULK TERMINAL NO. 1 SULPHUR, LOUISIANA
LAKE CHARLES HARBOR & TERMINAL DISTRICT BULK TERMINAL NO. 1 SULPHUR, LOUISIANA STORM WATER POLLUTION PREVENTION PLAN LPDES PERMIT NO. LA0091812 March 2013 Prepared by: C-K Associates, LLC 17170 Perkins
More informationWatershed Enforcement Environmental Services (ESD)
Watershed Enforcement Environmental Services (ESD) Construction Inspector Training 2009 Presented by: Watershed Enforcement Outline Overview of Watershed Enforcement Program Role of Watershed Enforcement
More informationAppendix O Example Industrial SWPPP Template
Appendix O Example Industrial SWPPP Template Arizona Department of Environmental Quality Multi-Sector General Permit Stormwater Pollution Prevention Plan (SWPPP) Template Introduction To help you develop
More informationRegulatory Requirements
7B-1 Design Manual Chapter 7 - Erosion and Sediment Control 7B - Regulatory Requirements Regulatory Requirements A. National Pollutant Discharge Elimination System (NPDES) The Clean Water Act established
More informationStorm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water
Storm Water Permitting Requirements for Construction Activities John Mathews Storm Water Program Manager Division of Surface Water Why Permit Storm Water? Impacts During Construction Not an issue until
More informationConstruction site inspections are conducted for all projects that receive an approved site plan and proceed to construction.
Standard Operating Procedures for implementation of the Stormwater, Erosion and Sedimentation Inspection Program for Construction Sites Discharging Stormwater to the MS4 Construction site inspections are
More informationCITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre
Approved by: City of Camarillo Stormwater Program Manager Date: CITY OF CAMARILLO STORMWATER POLLUTION CONTROL PLAN Demolition or Stockpile Activity Under One Acre Project Name: Project #: Project Location:
More informationLOS ANGELES UNIFIED SCHOOL DISTRICT REFERENCE GUIDE
TITLE: NUMBER: ISSUER: Storm Water Discharges Associated with Construction and Land Disturbance Activities REF-6286.0 John Sterritt, Director Enrique G. Boull t, Chief Operating Officer Office of the Chief
More informationLAND DISTURBANCE PERMIT
SPRINGVILLE CITY Application Date: 110 South Main Springville, UT 84663 Permit Number: (801) 491-2780 Caselle #2208 Project Name: Project Address: LAND DISTURBANCE PERMIT Priority Site Owner s Name Phone
More informationSTORMWATER COMPLIANCE & INSPECTION TRAINING
WELCOME STORMWATER COMPLIANCE & INSPECTION TRAINING For Commercial Construction Sites Table of Contents Stormwater Compliance & Inspection Training Topic 1: Introduction & Overview Topic 2: History & Requirements
More informationSUDAS Revision Submittal Form
SUDAS Revision Submittal Form Status Date: As of 3/15/2018 Topic: General Permit No. 2 updates Manual: Design Manual Location: Sections 7A-1 and 7B-1 Requested Revision: Section 7A-1 (General Information),
More informationStormwater Pollution Prevention Training Arlington Public Schools August 8, 2014
Stormwater Pollution Prevention Training Arlington Public Schools August 8, 2014 Diana Handy AC DES OSEM Overview Stormwater 101 Regulations / Permits Stormwater Pollution Illicit Discharges Pollution
More informationCommon Plan of Development Storm Water Pollution Prevention Plan for: Operator(s):
Common Plan of Development Storm Water Pollution Prevention Plan for: Insert Subdivision Name Address City, State, Zip Code Operator(s): Insert Company Name Company Representative Name Address City, State,
More informationINDUSTRIAL WATER & SEWER USE SURVEY. 3. Operator (If different from the Owner, the name of the person, or firm, legally the operating the facility):
INDUSTRIAL WATER & SEWER USE SURVEY 1. Facility (PROVIDE THE OFFICIAL OR LEGAL NAME OF THE FACILITY) 2. Owner - The name of the person, firm, or organization that legally owns the facility. 3. Operator
More informationFor a complete list of all BMP categories, see Stormwater: Best Management Practices Index.
Stormwater: General Inspection Checklist Department: Environmental Protection Program: Stormwater This inspection checklist can be used by Stormwater Division or Environmental Services Coordinator to Conduct
More informationAMERICAN FORK CITY PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION
SWPPP INSPECTION OF CITY OWNED FACILITIES Facility Name: Date: City Inspector Contact Information Name: Aaron Brems, RSI Email: ABrems@afcity.net Name: Harlan Nielson. RSI Email: HNielson@afcity.net Name:
More information2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS
2. Section 2 TW O SECTIONTWO 2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS Unless specifically exempted, all Development Construction Projects will be required
More informationCORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN
CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN SITUATED IN THE SW ¼ OF SECTION 18, T.2S., R.67W., OF THE 6 TH P.M. COUNTY OF ADAMS, STATE OF COLORADO PREPARED FOR: Thornton Cornerstone
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION
Sheet 1 of 7 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 901 and replace with the following: SECTION 901 STORMWATER POLLUTION MANAGEMENT
More informationAPPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS
APPENDIX C EROSION AND SEDIMENTATION CONTROL STANDARDS City of Bradenton January 2017 1 INTRODUCTION This appendix to the City of Bradenton Department of Public Works and Utilities Utility Specifications
More informationNevada Department of Transportation (NDOT)
Nevada Department of Transportation (NDOT) Stormwater Pollution Prevention Plan (SWPPP) Template for Construction Activities NDOT STORMWATER COMPLIANCE & ENFORCEMENT Table of Contents Page # STORM WATER
More informationAnnual Stormwater Pollution Prevention Training
Annual Stormwater Pollution Prevention Training Columbus Airport August 2018 Agenda 1. Regulatory Background 2. Regulated Activities 3. Roles and Responsibilities 4. Best Management Practices 5. Spill
More informationConstruction Site Inspections
Construction Site Inspections Keep The Mud Out of The Creek Barry Tonning, Tetra Tech Inspections help to identify and correct problems! Inspection requirements Must inspect site every 14 days (LA) Some
More informationMCM#6 Pollution Prevention/Good Housekeeping for Municipal Operations. Licking County MS
MCM#6 Pollution Prevention/Good Housekeeping for Municipal Operations Licking County MS4 12 14 2016 1 Why are we here? Heath is an MS4 Community MS4 = Municipal Separate Storm Sewer System SWMP Storm Water
More informationState of Georgia Department of Natural Resources Environmental Protection Division NOTICE OF INTENT. NOI - Version 2012
State of Georgia Department of Natural Resources Environmental Protection Division For official use only NOTICE OF INTENT NOI - Version 2012 For Coverage Under NPDES General Permit GAR050000 (2012 IGP)
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION
Sheet 1 of 7 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 901 and replace with the following: SECTION 901 STORMWATER POLLUTION MANAGEMENT
More informationRe: Erosion Control Report and Drawings Requirements Accompanying Document
Re: Erosion Control Report and Drawings Requirements Accompanying Document This document was created to help engineers and other design staff to better understand, meet and exceed the erosion control requirements
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION
Sheet 1 of 7 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 901 and replace with the following: SECTION 901 STORMWATER POLLUTION MANAGEMENT
More informationSWPPP Development. What are Storm Water Pollution Prevention Plans. Jerald S. Fifield, Ph.D., CISEC HydroDynamics Incorporated Parker, CO
What are Storm Water Pollution Prevention Plans S&EC PLANS (DRAWINGS) PROJECT SITE NARRATIVE Jerald S. Fifield, Ph.D., CISEC HydroDynamics Incorporated Parker, CO 303-841-0377 SWPPP SWPPP Development Section
More informationIllinois EPA MS4/ILR10 permit overview & changes
Illinois EPA MS4/ILR10 permit overview & changes Stasi Brown, CPESC Resource Analyst Kane-DuPage Soil & Water Conservation District Questions We Hope To Answer: Requirements of an MS4 & ILR10 permits how
More informationThree copies (one original and two copies) of your completed NOI should be submitted to:
To: Prospective Applicants for a Stormwater General Permit Associated with Construction Activity Greater than 5 Acres Attached is a Stormwater General Permit Associated with Construction Activity Greater
More informationNew Administration Building
New Administration Building Stormwater Pollution Prevention Plan Hudson Valley Community College Troy, New York Prepared for: Hudson Valley Community College 80 Vandenburgh Avenue Troy, New York 12180
More informationCITY OF CHICO. Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects. Project Address: Building Permit Number:
CITY OF CHICO Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Address: Building Permit Number: What is this document for? The City s Phase II MS4 NPDES General
More informationCity of West Sacramento Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects
Erosion and Sediment Control Plan (ESCP) Worksheet for Small Construction Projects Project Name: Page intentionally left blank. - 2 - What is this document for? The City s Phase II MS4 NPDES General Permit
More informationGENERAL INFORMATION:
' Reporting Period of 3/8/2012 through 2/12/2013. GENERAL INMATION: A. Facility 10 No. (Permit No.): ARR OOA391 (ARROOAOOO General Permit) B. Owner/Operator: Busch Agricultural Resources, LLC Jonesboro
More informationTHE UNIVERSITY OF TEXAS AT TYLER. Stormwater Pollution Prevention Program
THE UNIVERSITY OF TEXAS AT TYLER Stormwater Pollution Prevention Program 2016 Table of Contents 1. INTRODUCTION... 3 2. PURPOSE... 3 3. SCOPE... 3 4. DEFINITIONS... 3 5. PROGRAM RESPONSIBILITIES... 4 6.
More informationAppendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702
Appendix M Framework Stormwater Pollution Prevention Plan Prepared by: Idaho Power Company 1221 W Idaho Street Boise, ID 83702 November 2011 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 PURPOSE... 1 3.0
More informationConstruction Site Runoff Inspections and Enforcement
Construction Site Runoff Inspections and Enforcement Stormwater Program 12/01/11 Table of Contents Introduction... 1 Purpose of Document... 1 Definition of Terms... 1 Compliance and Inspections... 3 Site
More informationOctober 2016 CDRPC Workshop
The New Blue Book NYS Standards and Specifications for Erosion and Sediment Control Dated July 2016 October 2016 CDRPC Workshop Blue Book Update Overview Reorganization of standard to reflect recommended
More informationBlue Book Update Overview
The New Blue Book NYS Standards and Specifications for Erosion and Sediment Control Dated July 2016 October 2016 CDRPC Workshop Blue Book Update Overview Reorganization of standard to reflect recommended
More informationStorm Water Permitting
Storm Water Permitting July 12, 2018 N E S g l o b a l. n e t Your Participation Join audio: You have joined using computer speakers by default Choose Telephone and dial using the information provided
More informationSECTION STORMWATER POLLUTION PREVENTION
PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02133 STORMWATER POLLUTION PREVENTION A. Prohibit illicit discharge (non-rainwater) into the storm drain system. B. Construct any and all necessary systems to
More informationSTANDARD CONSTRUCTION DETAILS EROSION CONTROL REVISED - JANUARY 2018
STANDARD CONSTRUCTION DETAILS REVISED - JANUARY 2018 TABLE OF CONTENTS STORM WATER POLLUTION PLAN NOTES - - - - - - - - - - - - - - - - - - - - - - - - - SD-EC01 SILT FENCE NOTES - - - - - - - - - - -
More informationNon-Storm Water Discharges
06/30/2009. This fact sheet was developed for the Port sector but can be used by any sector. The following information was extracted from the 2008 Multi Sector General Permit (MSGP) for industrial storm
More informationSingle Family Residential Construction Erosion/Sediment Control Standards
Single Family Residential Construction Erosion/Sediment Control Standards Introduction: This booklet contains standard plans and procedures sufficient for typical building construction. It is not intended
More informationStorm Water Pollution Prevention Plan. Wastewater Treatment Facility and Streets & Parks Facility. Village of Fox River Grove, Illinois
Storm Water Pollution Prevention Plan Wastewater Treatment Facility and Streets & Parks Facility Village of Fox River Grove, Illinois Village of Fox River Grove, Illinois Storm Water Pollution Prevention
More information