1 LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT YUBA AND NEVADA COUNTIES, CALIFORNIA DRAFT SUPPLEMENTAL ENVIRONMENTAL ASSESSMENT June 2013 Approved for public release; distribution is unlimited

2 REPLY TO ATTENTION OF DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, SACRAMENTO CORPS OF ENGINEERS 1325 J STREET SACRAMENTO, CALIFORNIA Environmental Resources Branch DRAFT FINDING OF NO SIGNIFICANT IMPACT Lower Yuba River Gravel Augmentation Project Yuba and Nevada Counties, California The U.S. Army Corps of Engineers, Sacramento District, has determined that implementing the proposed gravel augmentation project on the Lower Yuba River, immediately below Harry L. Englebright Dam and Reservoir for a third year, would have no significant effects on the quality of the human environment. The project area is located in the steep Lower Yuba River canyon off Highway 20, about 23 miles east of Marysville, California, in the Englebright Dam Reach. Project activities would include placing 5,000 short tons of a heterogeneous mix of gravel and cobble directly into the Lower Yuba River channel below Englebright Dam using a gravel sluicing method. The proposed action is a conservation measure to help improve habitat above Daguerre Point Dam in the area known as the Englebright Dam Reach. Implementation of a gravel augmentation plan would improve the overall function of the habitat of the Lower Yuba River by providing spawning gravel to key areas that have been designated as critical habitat for the Central Valley spring-run Chinook salmon (Oncorhynchus tshawytscha) and the Central Valley steelhead (O. mykiss). A 2013 Supplemental Environmental Assessment (Supplemental EA) was prepared to evaluate the potential effects to natural and cultural resources in the proposed project area. The EA was circulated for a 15 day public review period from June 20 July 5, Based on the evaluation of potential effects described in the Supplemental EA, I have determined that the proposed gravel injection project would have no significant adverse effects on existing resources including special status species, fish and wildlife, vegetation, air and water quality, and cultural resources. No additional environmental documentation is required, and the project activities may proceed as proposed. Date William J. Leady, P.E. Colonel, U.S. Army District Engineer

3 Contents 1.0 Purpose and Need for Action Background Proposed Action Location Purpose and Scope of the Supplemental Environmental Assessment Decision Needed Project Authority Alternatives No Action Gravel Sluicing (Preferred Alternative) Gravel Placement Process Gravel and Cobble Gravel and Cobble Placement Location Staging and Stockpiling Work Schedule Monitoring Program Affected Environment and Environmental Consequences Environmental Resources Not Considered in Detail Soils, Topography, and Geomorphology Existing Conditions, Effects, and Mitigation Hydrology and Water Quality Existing Conditions, Effects, and Mitigation Traffic Existing Conditions, Effects, and Mitigation Hazardous, Toxic, and Radiological Waste Existing Conditions, Effects, and Mitigation Aquatic Fauna Existing Conditions, Effects, and Mitigation Special Status Species Existing Conditions, Effects, and Mitigation Air Quality Existing Conditions, Effects, and Mitigation Recreation Existing Conditions, Effects, and Mitigation Noise Existing Conditions, Effects, and Mitigation Cultural Resources Existing Conditions, Effects, and Mitigation Growth-Inducing Effects Cumulative Effects i

4 6.0 Compliance with Environmental Laws and Regulations Agencies Consulted Public Notice Conclusions List of Preparers References ii

5 PLATES 1. Project Area Vicinity Map 2. Project Area Map 3. Lower Yuba River 4. Location of Project Features and Schematic of the Gravel/Cobble Delivery System 5. Design Concept for using gravel augmentation in the Englebright Dam Reach, to possibly obtain a salmon-spawning riffle with diverse microhabitat features APPENDIX A. Section 401 Water Quality Certification Application May 2013 iii

6 1.0 Purpose and Need for Action Englebright and Daguerre Point Dams play a crucial role in protecting the downstream region from being overwhelmed by sedimentary mining waste debris still being eroded off hillsides and stored in long sections of the channel network upstream. Most of the active Lower Yuba River also still has tens of millions of cubic yards of sedimentary mining waste debris in it that pre-date the dams and are still being re-worked as part of a highly dynamic, meandering gravel-bed river. However, the reach between Englebright Dam and the confluence with Deer Creek was almost devoid of river-rounded gravel and cobble necessary for salmon spawning, until the U.S. Army Corps of Engineers (Corps) implemented a gravel augmentation program in In particular, spring-run Chinook salmon that historically went far upstream would substantially benefit from a gravel augmentation program below Englebright Dam. However, this critical reach is in a narrow canyon that is difficult to access and manage, let alone place thousands of tons of coarse sediment into (Pasternack 2010). The purpose of the proposed gravel augmentation project is to place suitable-sized spawning gravel within Englebright Dam Reach (EDR) of the Lower Yuba River. The proposed action is a conservation measure that would also satisfy the Reasonable and Prudent Alternative 4 Gravel Augmentation Program, GAP1 included in the February 29, 2012 Biological Opinion (BO) prepared by National Marine Fisheries Service (NMFS) pursuant to Section 7 of the Endangered Species Act (ESA) of 1973, as amended (16 U.C et seq.). Additionally, the Corps proposed gravel augmentation as a conservation measure in the January 2012 Biological Assessment. 1.1 Background The Lower Yuba River, downstream of Harry L. Englebright Dam and Reservoir (Englebright), has experienced extensive sediment deposition as a result of the hydraulic gold mining that occurred in the watershed during the mid- to late 1800s. An estimated 685 million cubic yards of mining debris was washed out of the mountains and into the Yuba River (Hagwood 1981). As the sediment migrated downstream, the river bed rose, causing extensive flooding in the Marysville area. To control this sediment movement, the California Debris Commission constructed Daguerre Point Dam in 1906 and Englebright in Since its construction, Englebright has continued to fulfill its primary purpose of debris control with containment of 17,750 acre-feet of sediment (Chiles 2003). The elimination of the upstream supply of sediment, however, has lead to progressive degradation of the downstream channel below Englebright, at least as far downstream as Parks Bar, where the Highway 20 (Plates 1 2) bridge footings have been exposed (Musseter Engineering, Inc. 2000). Lack of sediment input and gravel loss within this reach of the Lower Yuba River have reduced the availability of quality spawning gravel for the Central Valley steelhead (Oncorhynchus mykiss) and spring-run Chinook salmon (Oncorhynchus tshawytscha). 1

7 Below Parks Bar, sediment sources from tributary input; gravel entrained from bars, piles of dredger tailings, and hill slopes; and gravel existing in the channel bed continue to provide large areas of suitable spawning habitat (Moir 2006). However, without additional gravel delivery, the existing gravel supply in the bed and usable gravel stored in bars will decrease as it is gradually transported downstream, leading to a net deficit of spawning-caliber sediment. In 2007, 500 short tons of gravel was injected into the river as a pilot study to determine how frequently the gravel is mobilized in the reach. The results of the study contributed to the development of the current gravel augmentation injection plan (GAIP) for the project. In 2011, the Corps placed an additional 5,000 short tons of gravel into the river, however the augmentation was not sufficient to achieve the specific conditions required for the spawning riffle determined by the GAIP. Eventually the gravel moved downstream and created high quality spawning habitat outside of the project area. Monitoring results from recommended an additional injection of 5,000 short tons of gravel. This second injection of 5,000 short tons was completed during the summer of To date, a total of 10,500 short tons of gravel have been placed into the river reach with associated monitoring. The monitoring results have again shown that placement of additional gravel is still needed to achieve the target conditions of the GAIP. 1.2 Proposed Action The Corps is proposing to place additional gravels in accordance with the existing GAIP in the summer of 2013, by placing 5,000 short tons of a heterogeneous mix of gravel and cobble (0.25 to 5.0 inches in diameter) directly into the EDR below Englebright Dam. The material would be monitored after the placement, adding to the understanding of the Lower Yuba River geomorphic processes. The information gathered from the monitoring of the placed gravel will allow the Corps to determine the quantity of additional gravel to be placed within the EDR below Englebright Dam in future years. The action described herein is identical to that described in the environmental assessment (EA) prepared in 2010 and a Supplemental EA prepared in 2012 with the exception of the dates of implementation, and the gravel mix specifications, which were changed slightly in the 2012 Supplemental EA. The Corps intends to develop a multi-year gravel placement plan for enhancing spawning riffle habitat for implementation beginning in 2014, and will prepare a separate EA later this year. 1.3 Location The project area is located on the Lower Yuba River, starting at Englebright Dam (Yuba River mile 23.9) downstream to Daguerre Point Dam (Yuba River mile 11.4), in Yuba and Nevada Counties, California (Plate 1). The proposed gravel placement site is located 115 feet downstream of the Narrows II Powerhouse. This site is less than one-acre and would be confined to the river channel within the EDR, a 0.89-mile long bedrock reach starting at Englebright Dam and ending at the junction with Deer Creek, located in the steep Narrows Canyon off Highway 20, approximately 23 miles east of Marysville, California (Plates 2, 3, and 4). 2

8 1.4 Purpose and Scope of the Supplemental Environmental Assessment The purpose of this Supplemental EA is to determine whether the proposed action would result in adverse effects on the environment that were not identified and disclosed in the 2010 or the 2012 Supplemental EA (2010, 2012 EA). The project as described in this EA is identical to that described in the 2010 and 2012 EA with the exception of the dates of implementation and the gravel mix specifications, which changed slightly in the 2012 EA. 1.5 Decision Needed The District Engineer, the Commander of the Sacramento District of the Corps, must decide whether the proposed action described in this Supplemental EA qualifies for a Finding of No Significant Effect or whether an Environmental Impact Statement must be prepared to comply with the National Environmental Policy Act. 1.6 Project Authority Harry L. Englebright Dam and Lake were authorized by the River and Harbor Act of 1935 (49 Stat. 1028) as a unit of the Sacramento River Debris Control Project. Construction of recreation facilities at Englebright Lake and provision of services to the public by concessionaire is in accordance with Section 4 of the Flood Control Act of 1944 (58 Stat. 887) and subsequent amendments. Daguerre Point Dam was authorized by the Rivers and Harbors Act of June 13, 1902 (H.D. No. 431, 56 th Congress, 1 st Session) as a part of the Yuba River Debris Control Project. 2.0 Alternatives A GAIP for the EDR of the Lower Yuba River, CA was developed to thoroughly assess the results of the 2007 pilot gravel injection project (Corps 2007), analyze the monitoring data collected post-pilot project, and to assess methods and measures that could be utilized in the proposed gravel augmentation project. A GAIP has been drafted, which thoroughly documents a plan for implementing a gravel/cobble augmentation program below Englebright Dam. This plan addresses the biogeomorphic impact of the proposed project on the Lower Yuba River. With the exception of the date of implementation, and the gravel mix specifications, which changed slightly in the 2012 EA, the preferred alternative in this Supplemental EA is the same alternative from the 2010 and 2012 EAs. 3

9 2.1 No Action The No-Action alternative serves as the environmental baseline against which the proposed action is compared. Under this alternative, the Corps would not implement the gravel augmentation project on the Lower Yuba River immediately downstream of Englebright. If no action is taken, the existing gravel supply in the stream bed and usable gravel stored in current bars would gradually decrease as it is transported downstream, leading to a net deficit of spawning caliber sediment. There are currently several projects and programs, either in the planning stages or underway on the Lower Yuba River, that involve various efforts to improve conditions for anadromous fisheries. However, the existing geomorphic processes related to recruitment and transport of suitable spawning gravels below Englebright would essentially remain the same. 2.2 Gravel Sluicing (Preferred Alternative) The preferred alternative consists of placing 5,000 short tons (18, cubic yards) of gravel and cobble directly into the Lower Yuba River channel near the Narrows I Powerhouse via gravel sluicing, which involves drawing water up from a source and into a flexible pipe, where gravel and cobble is added from the top to produce a water/ sediment slurry that is then piped down to a site for directed placement by one to two operators. Details of staging, gravel sizes, placement, and monitoring for the alternative are provided below. Project features are provided in Plate 4. The gravel/cobble mixture would be monitored after placement within the EDR. The information gathered from the monitoring of the placed material will allow the Corps to determine if it will be necessary to place additional quantities of gravel within the Lower Yuba River channel below Englebright (Pasternack 2010) Gravel Placement Process The sluicing process involves drawing water up from a source (the reservoir) and into an 8-inch diameter Yelomine flexible pipe, where gravel and cobble is added from the top to produce a water, sediment slurry that is then piped down to a site for directed placement by one to two operators. The amount of water used to do the sluicing depends on the pipe and pump configurations, and is typically 1,000 to 1,500 gallons per minute, which is 2.23 to 2.34 cubic feet per second (cfs) (Pasternack 2010). The water pump would be located at the reservoir water s edge, to push the water uphill in a 6 to 8 inch pipe. The pump inlet would be screened to prevent aquatic fauna from being taken up into the pumping system. This process is normally a five-person operation: one person would operate the water pump at the source, one, in a loader, would bring gravel to the feeder, one person would operate the feeder in order to prevent clogs and coordinate communications, and two at the end nozzle, directing gravel placement and to add pipe as needed to periodically move downstream. This approach 4

10 would have a minimal construction footprint; Plates 4 and 5 illustrate the project design and layout. The rate of gravel placement via sluicing is approximately 100 to 300 short tons per day, all dependent upon how frequently the system clogs. This is slow relative to gravel placement by truck-mounted conveyor belt (approximately 500 short tons per day) or truck/front loaders (approximately 1,000 short tons per day) (Pasternack 2010). At an average rate of 150 short tons per day, it would take 33 days to place 5,000 short tons of gravel. The approach that would be used with gravel sluicing is to start at the water s edge, build across the river, and then work downstream. At the outlet of the system, gravel would go into a rigid pipe supported by floating, air-filled barrels. The outlet would be manually directed to the placement point with the aid of ropes as needed. Using this approach, it is possible to place gravel according to a sophisticated design with few constraints. The water intake pump system, which includes fish screening, would be positioned right on the water s edge, along the gravel road on the north side of the reservoir that runs close to the dam. From there, the water would be pumped in one or two 6 to 8-inch diameter pipes approximately 1,070-feet up the side of the road to the crest (Plate 4). The pipes would go over the crest of the hill, and down the side of the paved road, approximately 300-feet towards the Narrows II powerhouse, until a point at which there is a noticeable slope break favorable to beginning the gravel addition to the pipe. At that location, a screened hopper on the north side of the road would receive sediment from a front loader, transferring the material the short distance from the stockpile. The loader operator would gently bounce the bucket to trickle the sediment into the hopper as the primary control on the flow rate; a hopper operator would be stationed there to ensure no blockages, clean out finger rocks as needed, and communicate conditions with other operation participants by radio. Under the hopper, the gravel and water would join in a metal pipe that would then connect to the beginning of the 8-inch diameter, semi-flexible Yelomine pipe. This pipe would then run approximately 1,270-feet down the ditch on the north side of the road to the switchback. From that point, the pipe would go 264-feet straight down the grassy hillside to a terrace level, where an old roadbed and foot-trail are located. From that point, the pipe would make a straight line, 130 feet down to the water s edge near the upstream end of the gravel placement area (Plate 4) Gravel and Cobble The Anadromous Fish Restoration Program, a U.S. Fish and Wildlife Service (USFWS) program that is tasked by the Central Valley Project Improvement Act to make "all reasonable efforts to at least double natural production of anadromous fish in California's Central Valley streams on a long-term, sustainable basis (USFWS 2010) has recommended gravel specifications to ensure that the placed gravel provide some usable spawning habitat and optimal egg survival rates for the salmonids within the Lower Yuba River. These specifications are showing in Table 1 (Pasternack 2012). This gravel would be obtained from a commercial 5

11 aggregate source located near the project site, within the Lower Yuba River watershed, and would arrive screened and pre-washed to the placement site. The composition of the gravel mix was changed slightly in 2012 based on the results of the 2011 monitoring program (discussed in Section 2.2.6). Results from the 2012 monitoring program indicated the gravel mix for this year should remain the same as the mix from The mix will be monitored during the sluicing process to ensure that it meets the specifications described below. TABLE 1. Gravel and Cobble Specifications for Salmonid Spawning and Egg Incubation. Gravel Size (inches) Percent Retained Target % of Total Mix 3.5 to to /4 to /2 to 3/ /4 to 1/ Gravel and Cobble Placement Location The selection of the specific location for focusing gravel and cobble location has been guided by constraints in powerhouse operations, potential benefits to the river, and feasible delivery methods. Powerhouse operations presently preclude gravel augmentation between Englebright Dam and the Narrows powerhouses. To get the most benefit and longevity from adding gravel to the river, the further upstream it is introduced, the better. To avoid having to fill the scour pool adjacent to the Narrows I facility, and yield riffle habitat for immediate spawning use with the least amount of initial gravel placement during a gravel sluicing operation, the placement should begin approximately 115-feet downstream of the end of the Narrows I powerhouse, where the maximum depth of the pool is under five-feet at 855 cfs of flow (Pasternack 2010) Staging and Stockpiling There would be one staging area for the project, located at the gravel turnouts along the paved access road to Narrows II. This area would be used primarily for vehicle parking and temporary storage of truck trailers loaded with gravel. The same turnouts would be used to stockpile the gravel; prior to the start of sluicing operations, the gravel would be stockpiled in the three parking/turnout areas at the overlook on the north side of the dam. This location is behind a locked gate and inaccessible to the public. The likely truck haul route that would be used to deliver gravel from the commercial source to the project site would begin at the intersection of State Route 20 and Peoria Road, and 6

12 end on the Narrows II access road, at a bench downstream of, and level with, the top of Narrows II (Plate 2) Work Schedule The proposed work would be conducted from July 2013 through the end of August Work hours would be limited to normal workdays, from 8:00 a.m. to 5:00 p.m. Any work conducted past August 2013 will also conform to the same time frames, or as approved by the resource agencies Monitoring Program Outflow release from the Narrows II powerhouse and spill flows over the top of Englebright would aid in transporting the gravel placed downstream within the upper Narrows reach of the Lower Yuba River. Gravel placed within the river would be monitored through the fall of 2013 and winter of 2014 by the Lower Yuba River Accord River Management Team for salmonid use, via protocol-level redds surveys. Data from the monitoring program would be compared with hypothetical quantitative predictions based on the ecologic, geomorphic, and hydrodynamic conditions present at the placement site. Confirmation of predictions would relate to how much the channel would be affected and how long the effect would persist, coupled with the potential beneficial qualities of the changes induced, would allow optimization of a the long-term gravel augmentation program design with a more accurate cost/benefit analysis. 3.0 Affected Environment and Environmental Consequences. 3.1 Environmental Resources Not Considered in Detail Initial evaluation of the potential effects of the alternatives indicated that there would not be any adverse direct, indirect, or cumulative effects on several resources due to the scale, scope, and schedule of the proposed action. Resources not discussed in detail include climate, geology and seismicity, land use, agriculture and prime and unique farm land, socioeconomics and environmental justice, esthetics, and vegetation and wildlife. 3.2 Soils, Topography, and Geomorphology Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required. 7

13 3.3 Hydrology and Water Quality Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required. An updated 401 water quality certification application was posted on May 24, 2013 for a 21 day public review by the Regional Water Quality Control Board (CRWQCB). 3.4 Traffic Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required 3.5 Hazardous, Toxic, and Radiological Waste Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required 3.6 Aquatic Fauna Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required. 3.7 Special Status Species Existing Conditions, Effects, and Mitigation 8

14 The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required. 3.8 Air Quality Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required. 3.9 Recreation Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required Noise Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required Cultural Resources Existing Conditions, Effects, and Mitigation The existing conditions would be the same as described in the 2010 and 2012 EA. The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects. No additional mitigation would be required. 9

15 4.0 Growth-Inducing Effects The change in the project implementation date proposed in this Supplemental EA would have no effect on population growth or densities. 5.0 Cumulative Effects As discussed in the two previous EA s, the proposed gravel augmentation, in combination with past, present, and potential future actions, would likely contribute to the overall health and vigor of the watershed. 6.0 Compliance with Environmental Laws and Regulations As disclosed in the 2010 EA, the proposed gravel augmentation would be compliant with the following environmental laws and regulations. Bald Eagle Protection Act of 1940, as amended, 16 U.S.C d, 54 Stat Clean Air Act of 1972, as amended, 42 U.S.C. 7401, et seq. Clean Water Act of 1972, as amended, 33 U.S.C. 1251, et seq. Endangered Species Act of 1973, as amended, 16 U.S.C. 1531, et seq. Executive Order 12989, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations. Executive Order 13112, Invasive Species. Farmland Protection Policy Act, 7 U.S.C et seq. Fish and Wildlife Coordination Act of 1958, as amended, 16 U.S.C. 661, et seq. Magnuson-Stevens Fishery Conservation and Management Act. Migratory Bird Treaty Act of 1936, as amended, 16 U.S.C. 703 et seq National Environmental Policy Act of 1969, as amended, 42 U.S.C. 4321, et seq. National Historic Preservation Act of 1966, as amended. Wild and Scenic Rivers Act, 16 U.S.C et seq. 10

16 7.0 Agencies Consulted The EA was prepared in consultation with the following USFWS and NMFS contacts. Amber Aguilera U.S. Fish and Wildlife Service 2800 Cottage Way, Room W-2605 Sacramento, California Gary Sprague National Marine Fisheries Service 650 Capital Mall, Suite Sacramento, Ca Public Notice The 2013 Supplemental EA will be circulated for 15 days to concerned agencies, organizations, and the public, as identified in Appendix E of the 2010 EA (40 CFR (e)(1); 33 CFR ). All comments received will be considered and incorporated into the final Supplemental EA, as appropriate. 9.0 Conclusions The change in the project implementation date proposed in this Supplemental EA would not result in any new adverse effects or requirements for new mitigation from those disclosed in the 2010 and 2012 EA. Based on the findings presented in the two prior EA s and reconsidered in this Supplemental EA, the proposed gravel placement project will not result in a significant adverse effect on the environmental resources in the project area, including threatened and endangered species, and other wildlife and vegetation List of Preparers Natalie Houghton, Environmental Manager U.S. Army Corps of Engineers Brian Luke, Biologist U.S. Army Corps of Engineers Brian Mulvey, Fisheries Biologist U.S. Army Corps of Engineers Brad Johnson, Environmental Manager U.S. Army Corps of Engineers 11

17 11.0 References Chiles, J.R., Snyder, N.P., Hampton, M.A Bathymetric and geophysical surveys of Englebright Lake, Yuba-Nevada Counties, California. U.S. Geological Survey Open-File Report Hagwood, Joseph J The California Debris Commission: A History. U.S. Army Corps of Engineers, Sacramento District. Sacramento, CA. Moir, H. J., Pasternack, G. B Implications of a Dynamic Hydromorphic Regime for Environmental Management on a Disturbed Large Gravel-bed River. EOS, Transactions of the American Geophysical Union 87(52), Fall Meet. Suppl., Abstract H41C Mussetter Engineering, Inc Letter report regarding geomorphological issues for the Daguerre Point Dam Fish Passage Study. Prepared for the U.S. Army Corps of Engineers. Pasternack, G. B Gravel/cobble Augmentation Implementation Plan for the Englebright Dam Reach of the Lower Yuba River. University of California, Davis. August 30, U.S. Army Corps of Engineers (Corps) Lower Yuba River Pilot Gravel Injection Project, Yuba and Nevada Counties: Final Environmental Assessment. Sacramento District, Sacramento, CA. U.S. Army Corps of Engineers (Corps) Lower Yuba River Gravel Augmentation Project, Yuba and Nevada Counties: Supplemental Environmental Assessment. Sacramento District, Sacramento, CA. U.S. Fish and Wildlife Service (USFWS) Species Lists for Smartville and Browns Valley U.S. Geological Survey 7.5 Minute Quads. Available at: Personal Communications Pasternack, G. B University of California, Davis. to Doug Grothe, Park Manager, U.S. Corps of Engineers. Subject: 2012 gravel mix concept. June 25, Lee, Elizabeth California Environmental Protection Agency, Regional Water Quality Control Board, 401 Water Quality Certification Program. Phone and correspondence with Brian Luke, Environmental Manager, U.S. Corps of Engineers, May 23, Subject: Amendment to the Approved November 2010, Clean Water Act 401 Technically Conditioned Water Quality Certification for Discharge of Dredged and/or Fill Materials for the Englebright Dam Reach Gravel Injection Project (WDID#5A58CR00081). 12

18 APPENDIX A SECTION WATER QUALITY CERTIFICATION 13

19

20

21

22

23

24

25

26 Daguerre Point Dam Englebright Dam Project Area Plate 1. Project Area Vicinity Map

LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT

LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT YUBA AND NEVADA COUNTIES, CALIFORNIA FINAL SUPPLEMENTAL ENVIRONMENTAL ASSESSMENT July 2013 Approved for public release; distribution is unlimited Contents

More information

LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT

LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT YUBA AND NEVADA COUNTIES, CALIFORNIA DRAFT SUPPLEMENTAL ENVIRONMENTAL ASSESSMENT June 2013 Approved for public release; distribution is unlimited Contents

More information

LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT

LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT LOWER YUBA RIVER GRAVEL AUGMENTATION PROJECT YUBA AND NEVADA COUNTIES, CALIFORNIA FINAL ENVIRONMENTAL ASSESSMENT November 2010 Approved for public release; distribution is unlimited Contents 1.0 Purpose

More information

Public Notice. Public Notice No. Date: April 8, 2016 CENAP-PL-E Comment Period Closes: May 9, 2016

Public Notice. Public Notice No. Date: April 8, 2016 CENAP-PL-E Comment Period Closes: May 9, 2016 Public Notice Public Notice No. Date: April 8, 2016 CENAP-PL-E-16-02 Comment Period Closes: May 9, 2016 USACE Philadelphia District: http://www.nap.usace.army.mil COBBS CREEK FISH PASSAGE PROJECT SECTION

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District ANCHORAGE Regulatory Division (1145) CEPOA-RD Post Office Box 6898 JBER, Alaska 99506-0898 Public Notice of Application for Permit PUBLIC NOTICE DATE: July 31,

More information

ENVIRONMENTAL IMPACT STATEMENT CLEVELAND HARBOR, CUYAHOGA COUNTY, OHIO DREDGED MATERIAL MANAGEMENT PLAN PUBLIC SCOPING INFORMATION PACKET

ENVIRONMENTAL IMPACT STATEMENT CLEVELAND HARBOR, CUYAHOGA COUNTY, OHIO DREDGED MATERIAL MANAGEMENT PLAN PUBLIC SCOPING INFORMATION PACKET ENVIRONMENTAL IMPACT STATEMENT CLEVELAND HARBOR, CUYAHOGA COUNTY, OHIO DREDGED MATERIAL MANAGEMENT PLAN PUBLIC SCOPING INFORMATION PACKET March 16, 2006 ANNOUNCEMENT OF PUBLIC SCOPING MEETINGS The U.S.

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District Regulatory Division (1145) CEPOA-RD Post Office Box 6898 JBER, Alaska 99506-0898 Public Notice of Application for Permit PUBLIC NOTICE DATE: January 15, 2014

More information

NOTICE OF PREPARATION

NOTICE OF PREPARATION NOTICE OF PREPARATION Date: June 12, 2014 To: From: Subject: Governor s Office of Planning and Research/State Clearinghouse Unit, Responsible Agencies, Trustee Agencies, and Interested Parties Announcement

More information

Public Notice PUBLIC NOTICE 30 DAY PUBLIC NOTICE

Public Notice PUBLIC NOTICE 30 DAY PUBLIC NOTICE PUBLIC NOTICE Date: January 30, 2015 Comment Period Ends: February 28, 2015 Reply by Mail to: Kirk Bargerhuff; or by email to: Kirk.E.Bargerhuff@usace.army.mil Engineering/Planning 696 Virginia Road Concord,

More information

Public Notice: Application for Permit

Public Notice: Application for Permit US Army Corps Of Engineers Walla Walla District 201 North Third Avenue Walla Walla, WA 99362-1876 Public Notice: Application for Permit APPLICATION NO.: NWW-2012-127-I02 WATERWAY: Big Wood River APPLICANT:

More information

~ate: d~o/~o/h. h ~~~ Date:,;z//o/a?0/6. Managing Water in the West. Upper Sacramento River Anadromous Fish Habitat Restoration Project

~ate: d~o/~o/h. h ~~~ Date:,;z//o/a?0/6. Managing Water in the West. Upper Sacramento River Anadromous Fish Habitat Restoration Project M Managing Water in the West Finding of No Significant Impact Upper Sacramento River Anadromous Fish Habitat Restoration Project Recommended by: ~~ Ben Nelson Natural Resources Specialist Bay-Delta Office

More information

Farmington Dam Repurpose Project

Farmington Dam Repurpose Project Farmington Dam Repurpose Project 2017 $158,100,000 to re-purpose the Farmington Dam from flood protection only to a long-term water storage facility that increases water supply reliability to the region.

More information

Notice of Intent to Prepare a Draft Environmental Impact Statement for the

Notice of Intent to Prepare a Draft Environmental Impact Statement for the BILLING CODE: 3720-58 This document is scheduled to be published in the Federal Register on 02/10/2017 and available online at https://federalregister.gov/d/2017-02779, and on FDsys.gov DEPARTMENT OF DEFENSE

More information

Meacham Creek Restoration Project

Meacham Creek Restoration Project Meacham Creek Restoration Project Meacham Creek Restoration Project Umatilla National Forest Walla Walla Ranger District Michael Rassbach, District Ranger Public Scoping Document Proposal Summary The Walla

More information

Appendix P. U.S. Fish and Wildlife Service Planning Aid Letter

Appendix P. U.S. Fish and Wildlife Service Planning Aid Letter Appendix P U.S. Fish and Wildlife Service Planning Aid Letter This page is intentionally left blank. United States Department of the Interior FISH AND WILDLIFE SERVICE Missouri Ecological Services Field

More information

Temporary Stream Crossing

Temporary Stream Crossing Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Temporary Stream Crossing

Temporary Stream Crossing Temporary Stream Crossing NS-4 Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution

More information

VII - WATER CONTROL PLAN

VII - WATER CONTROL PLAN VII - WATER CONTROL PLAN 7-01. General Objectives. Regulation of Saylorville Lake in conjunction with Lake Red Rock provides flood control benefits along both the Des Moines and Mississippi Rivers. Additionally,

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District Juneau Field Office Regulatory Division (1145) CEPOA-RD 8800 Glacier Highway, Suite 106 Juneau, Alaska 99801-8079 Public Notice of Application for Permit PUBLIC

More information

RE: Fishery evaluation for South, Old Cow Creek Hydroelectric Facilities

RE: Fishery evaluation for South, Old Cow Creek Hydroelectric Facilities April 29th, 2008 Richard Ely, Davis Hydro 27264 Meadowbrook Drive Davis CA 95618 RE: Fishery evaluation for South, Old Cow Creek Hydroelectric Facilities On January 29 th, 2008 Cramer biologists Joseph

More information

Notice of Preparation of Environmental Impact Report

Notice of Preparation of Environmental Impact Report Notice of Preparation of Environmental Impact Report September 29, 2010 TO: State Clearinghouse Responsible and Trustee Agencies Interested Agencies and Parties FROM: Sonoma County Water Agency 404 Aviation

More information

Spring Forecast Based Operations, Folsom Dam, California

Spring Forecast Based Operations, Folsom Dam, California Spring Forecast Based Operations, Folsom Dam, California Paul E. Pugner, P.E. Chief, Water Management Section Sacramento District U.S. Army 1325 J Street, Room 1126 Sacramento, CA 95814-2922 Tel: (916)

More information

Public Notice: Application for Permit

Public Notice: Application for Permit US Army Corps Of Engineers Walla Walla District 201 North Third Avenue Walla Walla, WA 99362-1876 Public Notice: Application for Permit APPLICATION : NWW-2008-00579 WATERWAY: Bruno Creek Drainage, Pat

More information

Public Notice. Navigation Section Notice Date: May 23, 2018 PO Box 3755 Expiration Date: June 21, 2018

Public Notice. Navigation Section Notice Date: May 23, 2018 PO Box 3755 Expiration Date: June 21, 2018 Public Notice Navigation Section Notice Date: May 23, 2018 PO Box 3755 Expiration Date: June 21, 2018 Seattle, WA 98124-3755 Reference: PMP-18-15 ATTN: John Pell (OD-TS-NS) or Joanne Gardiner (PMP-E) US

More information

PUBLIC NOTICE PROJECT: U.S. Coast Guard Base Alameda Boat Basin Dredging Project

PUBLIC NOTICE PROJECT: U.S. Coast Guard Base Alameda Boat Basin Dredging Project Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: U.S. Coast Guard Base Alameda Boat Basin Dredging Project PUBLIC NOTICE NUMBER:

More information

Battle Creek Salmon and Steelhead Restoration Project January 2017

Battle Creek Salmon and Steelhead Restoration Project January 2017 Battle Creek Salmon and Steelhead Restoration Project January 2017 Battle Creek has the unique geology, hydrology, and habitat suitability to support threatened and endangered Chinook salmon and Central

More information

J O I N T P U B L I C N O T I C E

J O I N T P U B L I C N O T I C E J O I N T P U B L I C N O T I C E CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina 29403-5107 and THE S.C. DEPARTMENT OF HEALTH AND ENVIRONMENTAL CONTROL Water Quality

More information

COUGAR DOWNSTREAM PASSAGE

COUGAR DOWNSTREAM PASSAGE COUGAR DOWNSTREAM PASSAGE Upper Baker Swift 255 255 255 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122 239 65 53 80 119 27 252 174.59 83 36 118 110 135 120 112 92 56 62 102 130 102 56

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Section 408 Request to Alter the Brookville Local Protection Project for State Route 3033 Bridge Replacement in Jefferson County, PA May 16, 2018 Prepared By: Environmental and

More information

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE PLYMOUTH HARBOR FEDERAL NAVIGATION PROJECT PLYMOUTH, MASSACHUSETTS

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE PLYMOUTH HARBOR FEDERAL NAVIGATION PROJECT PLYMOUTH, MASSACHUSETTS 696 Virginia Road Concord, MA 01742-2751 Public Notice In Reply Refer to: Mr. Michael Walsh nae-pn-nav@usace.army.mil Programs & Project Management Division Date: June 14, 2018 Comment Period Closes: July

More information

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE

PUBLIC NOTICE NO. FP13-AB03-05 August 30, 2013 CESAM-PD-EC JOINT PUBLIC NOTICE DEPARTMENT OF THE ARMY MOBILE DISTRICT, CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, ALABAMA 36628-0001 REPLY TO ATTENTION OF: JOINT PUBLIC NOTICE U. S. ARMY CORPS OF ENGINEERS, MOBILE DISTRICT AND FLORIDA

More information

Subject: Notice of Preparation of a Draft Environmental Impact Report

Subject: Notice of Preparation of a Draft Environmental Impact Report NOTICE OF PREPARATION From: Santa Clara Valley Water District 5750 Almaden Expressway San Jose, CA 95118 Subject: Notice of Preparation of a Draft Environmental Impact Report Project Title: Guadalupe Dam

More information

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact Blanche Park Reservoir Decision Notice and Finding of No Significant Impact U.S. Forest Service Grand Mesa, Uncompahgre, and Gunnison National Forests Delta County, Colorado INTRODUCTION The Grand Mesa

More information

PUBLIC NOTICE. Town of Beech Mountain Mr. Tim Holloman 503 Beech Mtn. Parkway Banner Elk, North Carolina 28604

PUBLIC NOTICE. Town of Beech Mountain Mr. Tim Holloman 503 Beech Mtn. Parkway Banner Elk, North Carolina 28604 US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: April 9, 2019 Comment Deadline: April 23, 2019 Corps Action ID Number: SAW-2018-02144 The Wilmington District, Corps of Engineers

More information

PUBLIC NOTICE PROJECT: Port of Redwood City Municipal Marina and F-Dock Maintenance and New-work Dredging Project

PUBLIC NOTICE PROJECT: Port of Redwood City Municipal Marina and F-Dock Maintenance and New-work Dredging Project SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Port of Redwood City Municipal Marina and F-Dock Maintenance and New-work Dredging Project Regulatory Division 1455 Market Street, 16 th Floor San Francisco,

More information

PUBLIC NOTICE PROJECT: Larkspur Marina Maintenance Dredging

PUBLIC NOTICE PROJECT: Larkspur Marina Maintenance Dredging SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Larkspur Marina Maintenance Dredging Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 PUBLIC NOTICE NUMBER: 2015-00036N PUBLIC

More information

Santa Clara Valley Habitat Plan Regional General Permit #18. Training and Workshop for Co-Permittees April 5, 2016

Santa Clara Valley Habitat Plan Regional General Permit #18. Training and Workshop for Co-Permittees April 5, 2016 Santa Clara Valley Habitat Plan Regional General Permit #18 Training and Workshop for Co-Permittees April 5, 2016 Agenda Welcome and Objectives (5 min.) Overview of Regional General Permit #18 (40 min.)

More information

P U B L I C N O T I C E. CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina

P U B L I C N O T I C E. CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina P U B L I C N O T I C E CHARLESTON DISTRICT, CORPS OF ENGINEERS 69A Hagood Avenue Charleston, South Carolina 29403-5107 REGULATORY DIVISION Refer to: P/N SAC-2018-00950 June 14, 2018 Pursuant to Section

More information

Environmental Assessment White Rock Mining Plan of Operations

Environmental Assessment White Rock Mining Plan of Operations Environmental Assessment White Rock Mining Plan of Operations April 2015 Figure 1: Grant Lake aerial view Lead Agency Responsible Official For Further Information, Contact: US Forest Service Seward Ranger

More information

PUBLIC NOTICE Application for Permit

PUBLIC NOTICE Application for Permit PUBLIC NOTICE Application for Permit Issue Date: March 4, 2016 Expiration Date: April 4, 2016 US Army Corps of Engineers No: NWP-2015-432 30-Day Notice Oregon Department of State Lands No: 58511 Interested

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District KENAI FIELD OFFICE Regulatory Division (1145) CEPOA-RD 805 Frontage Road, Suite 200C Kenai, Alaska 99611-7755 Public Notice of Application for Permit PUBLIC NOTICE

More information

MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA)

MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA) MONTEREY PENINSULA WATER MANAGEMENT DISTRICT PROJECT DESCRIPTION FOR SELECTIVE VEGETATION MANAGEMENT AND BANK RESTORATION (RANCHO SAN CARLOS AREA) IN THE CARMEL RIVER CHANNEL, SUMMER AND FALL 2014 SELECTIVE

More information

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California

Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California Conceptual Design and Feasibility of a Natural Fishway at the Fremont BART Weir, Alameda Creek, California Final Report September 2005 Prepared by Center for Ecosystem Management and Restoration, Oakland,

More information

DECISION MEMO FOR CATEGORICAL EXCLUSION HOLY JIM CREEK CROSSING REPLACEMENT

DECISION MEMO FOR CATEGORICAL EXCLUSION HOLY JIM CREEK CROSSING REPLACEMENT DECISION MEMO FOR CATEGORICAL EXCLUSION HOLY JIM CREEK CROSSING REPLACEMENT U.S.D.A. Forest Service Cleveland National Forest Trabuco Ranger District Orange County, California Background The current configuration

More information

LEGAL AUTHORITY AND JURISDICTIONS

LEGAL AUTHORITY AND JURISDICTIONS CALIFORNIA DEPARTMENT OF FISH AND GAME RIPARIAN RESOURCES AND REGULATORS: The DFG Lake and Streambed Alteration 1600 Process LEGAL AUTHORITY AND JURISDICTIONS Serge Glushkoff CENTRAL COAST REGION YOUNTVILLE

More information

SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Port of Richmond Terminals 2, 3, 7, and 8 Berth Maintenance Dredging

SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Port of Richmond Terminals 2, 3, 7, and 8 Berth Maintenance Dredging Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Port of Richmond Terminals 2, 3, 7, and 8 Berth Maintenance Dredging PUBLIC

More information

Scope of the Yuba River Ecosystem Restoration Feasibility Study

Scope of the Yuba River Ecosystem Restoration Feasibility Study December 4, 2015 U.S. Army Corps of Engineers, Sacramento District Attn: Michael Fong, CESPK-PD-RP 1325 J Street Sacramento, CA 95814-2922 Yuba County Water Agency Attn: Dianne Simodynes HDR Engineering,

More information

SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: San Francisco Marina West Harbor Maintenance Dredging

SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: San Francisco Marina West Harbor Maintenance Dredging Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: San Francisco Marina West Harbor Maintenance Dredging PUBLIC NOTICE NUMBER:

More information

Minnesota EAW Supplement

Minnesota EAW Supplement Appendix I: Minnesota EAW Supplement Lower Pool 2 Channel Management Study: Boulanger Bend to Lock and Dam No. 2 Minnesota EAW Item Identification A supplement prepared for the Minnesota DNR to identify

More information

DRAFT FINDING OF NO SIGNIFICANT IMPACT DWORSHAK LONG-TERM NUTRIENT SUPPLEMENTATION PROGRAM AHSAHKA, IDAHO JANUARY 2017

DRAFT FINDING OF NO SIGNIFICANT IMPACT DWORSHAK LONG-TERM NUTRIENT SUPPLEMENTATION PROGRAM AHSAHKA, IDAHO JANUARY 2017 DRAFT FINDING OF NO SIGNIFICANT IMPACT DWORSHAK LONG-TERM NUTRIENT SUPPLEMENTATION PROGRAM AHSAHKA, IDAHO JANUARY 2017 1. INTRODUCTION/PROPOSED ACTION The U.S. Army Corps of Engineers, Walla Walla District

More information

Instructions for the South Pacific Division Nationwide Permit Pre- Construction Notification (PCN):

Instructions for the South Pacific Division Nationwide Permit Pre- Construction Notification (PCN): This PCN integrates the requirements of the U.S. Army Corps of Engineers (Corps) Nationwide Permit Program within the South Pacific Division (SPD), including the Albuquerque, Los Angeles, San Francisco,

More information

Public Scoping Meetings

Public Scoping Meetings Public Scoping Meetings GRASS VALLEY Wednesday, March 9, 2016 6:00 8:00 p.m. Holiday Inn Express 121 Bank Street Grass Valley, CA 95945 AUBURN Thursday, March 10, 2016 6:00 8:00 p.m. Forest Lake Christian

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District Juneau Field Office Regulatory Division (1145) CEPOA-RD 8800 Glacier Highway, Suite 106 Juneau, Alaska 99801-8079 Public Notice of Application for Permit PUBLIC

More information

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM U.S. ARMY CORPS OF ENGINEERS, NEW ENGLAND DISTRICT CONCORD, MA PROJECT: Northfield Brook Dam, Naugatuck River

More information

PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS

PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS ISSUE DATE: December 15, 2015 EXPIRATION DATE: January 15, 2016 PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS Availability of Draft Environmental Assessment and Draft Finding of No Significant Impact REPLY

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT, FINDING OF NO SIGNIFICANT IMPACT, and DECISION RECORD 1 ENVIRONMENTAL ASSESSMENT EA Number: OR-080-05-10 BLM Office: Marys Peak Resource Area, Salem District Office 1717 Fabry

More information

Environmental Assessment Gold Digger Mining Plan of Operations

Environmental Assessment Gold Digger Mining Plan of Operations Environmental Assessment Gold Digger Mining Plan of Operations June 2016 i ;..-.I ' Lead Agency Responsible Official For Further Information, Contact: US Forest Service Seward Ranger District Francisco

More information

Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description

Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description Warren Wagon Road Improvement Project McCall Ranger District, Payette National Forest Project Description Introduction The analysis of the Warren Wagon Road Improvement Project is tiered to the 2003 Environmental

More information

1. NWPs 29 and 39 are revoked for activities located in the Primary or Secondary Zone of the Legal Delta.

1. NWPs 29 and 39 are revoked for activities located in the Primary or Secondary Zone of the Legal Delta. Final Sacramento District Nationwide Permit (NWP) Regional Conditions for California, excluding the Lake Tahoe Basin (Effective March 19, 2017 until March 18, 2022) A. Revoked NWPs 1. NWPs 29 and 39 are

More information

1. NWPs 29 and 39 are revoked for activities located in the Primary or Secondary Zone of the Legal Delta.

1. NWPs 29 and 39 are revoked for activities located in the Primary or Secondary Zone of the Legal Delta. Final Sacramento District Nationwide Permit (NWP) Regional Conditions for California, excluding the Lake Tahoe Basin (Effective March 19, 2017 until March 18, 2022) A. Revoked NWPs 1. NWPs 29 and 39 are

More information

Sacramento Area Flood Control Agency. May State Clearinghouse No Prepared for: Prepared by: Consulting Engineers and Scientists

Sacramento Area Flood Control Agency. May State Clearinghouse No Prepared for: Prepared by: Consulting Engineers and Scientists Addendum No. 3 (North Sacramento Streams) to the Environmental Impact Report on the North Sacramento Streams, Sacramento River East Levee, Lower American River, and Related Flood Improvements Project Prepared

More information

Lower Cherry Aqueduct Emergency Rehabilitation (44896) Scoping Package

Lower Cherry Aqueduct Emergency Rehabilitation (44896) Scoping Package Lower Cherry Aqueduct Emergency Rehabilitation (44896) Scoping Package Groveland Ranger District Tuolumne County, California Introduction The (STF) is seeking initial scoping comments on the proposed Lower

More information

DECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing

DECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing Page 1 of 6 Background DECISION MEMO USDA Forest Service Madison Ranger District Madison County T12S, R4W, Section 30 The project is in the Gravelly Landscape, Snowcrest Recommended Wilderness Management

More information

SECTION 1.0 INTRODUCTION AND EXECUTIVE SUMMARY

SECTION 1.0 INTRODUCTION AND EXECUTIVE SUMMARY SECTION 1.0 INTRODUCTION AND EXECUTIVE SUMMARY Pursuant to the work plan adopted by the Yuba Salmon Forum (YSF) for assessment of infrastructure to support anadromous fish passage to the Yuba watershed,

More information

PUBLIC NOTICE PROJECT: River Park Marina Maintenance Dredging

PUBLIC NOTICE PROJECT: River Park Marina Maintenance Dredging SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: River Park Marina Maintenance Dredging Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 PUBLIC NOTICE NUMBER: 2016-00150N PUBLIC

More information

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE FEDERAL NAVIGATION PROJECT IN THE ROYAL RIVER, YARMOUTH, MAINE

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE FEDERAL NAVIGATION PROJECT IN THE ROYAL RIVER, YARMOUTH, MAINE PUBLIC NOTICE 696 Virginia Road Concord, MA 01742-2751 In Reply Refer to: Programs Project Management Division Email: nae-pn-nav@usace.army.mil Date: February 28, 2013 Comment Period Closes: April 1, 2013

More information

32. Relationship Between Short-term Uses and Long-term Productivity

32. Relationship Between Short-term Uses and Long-term Productivity 32. Relationship Between Short-term Uses and Long-term Productivity 32.1 Introduction The Council on Environmental Quality (CEQ) NEPA regulations (40 CFR 1502.16) require consideration of the relationship

More information

COTTON CREEK CULVERT REPLACMENT

COTTON CREEK CULVERT REPLACMENT COTTON CREEK CULVERT REPLACMENT Integrating Mobility with Environmental Innovation Located along a scenic section of Highway 3/95 in British Columbia, Moyie Bluffs, a 6.5 km stretch of inland highway had

More information

Case Study 12. Grubbs Concrete Slab Vented Ford

Case Study 12. Grubbs Concrete Slab Vented Ford Appendix A Case Study Case Study. Grubbs Concrete Slab Vented Ford Location North central California. Plumas National Forest. Mount Hough Ranger District. Grizzly Creek. 3 miles west of Bucks Lake, CA.

More information

CESAM-RD-A December 4, 2017 PUBLIC NOTICE NO. SAM SBC

CESAM-RD-A December 4, 2017 PUBLIC NOTICE NO. SAM SBC DEPARTMENT OF THE ARMY MOBILE DISTRICT, CORPS OF ENGINEERS P.O. BOX 2288 MOBILE, AL 36628-0001 PUBLIC NOTICE NO. SAM-2017-01123-SBC JOINT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS AND STATE OF ALABAMA

More information

Notice of Intent to Prepare a Draft Environmental Impact Statement for the Intake. Diversion Dam Fish Passage Project, Dawson County, Montana

Notice of Intent to Prepare a Draft Environmental Impact Statement for the Intake. Diversion Dam Fish Passage Project, Dawson County, Montana This document is scheduled to be published in the Federal Register on 01/04/2016 and available online at http://federalregister.gov/a/2015-33066, and on FDsys.gov BILLING CODE: 3720-58 DEPARTMENT OF DEFENSE

More information

JUVENILE SALMON MIGRATION SECTION 5. blank page

JUVENILE SALMON MIGRATION SECTION 5. blank page blank page FISH AND WILDLIFE PROGRAM 5-16 September 13, 1995 SECTION 5 JUVENILE SALMON MIGRATION temperature improvement measures contained in this program will have a substantial impact on the operations

More information

Freight Street Development Strategy

Freight Street Development Strategy Freight Street Development Strategy Appendix B: Naugatuck River Floodplain Analysis Freight Street Development Strategy DECEMBER 2017 Page B-1 1.0 NAUGATUCK RIVER FLOODPLAIN AT FREIGHT STREET 1.1 Watershed

More information

ANNUAL PROGRESS REPORT FOR 2014 ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN ROGUE WATERSHED DISTRICT OREGON DEPARTMENT OF FISH AND WILDLIFE

ANNUAL PROGRESS REPORT FOR 2014 ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN ROGUE WATERSHED DISTRICT OREGON DEPARTMENT OF FISH AND WILDLIFE ANNUAL PROGRESS REPORT FOR 2014 ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN ROGUE WATERSHED DISTRICT OREGON DEPARTMENT OF FISH AND WILDLIFE INTRODUCTION In September of 2007, the Oregon Fish and

More information

Public Notice: Application for Permit

Public Notice: Application for Permit U.S. ARMY CORPS Of Engineers Walla Walla District 201 North Third Avenue Walla Walla, WA 99362-1876 Public Notice: Application for Permit APPLICATION NO.: NWW-2014-00446 WATERWAY: Snake River APPLICANT:

More information

Pickwick Landing Dam South Embankment Seismic Upgrade. DRAFT ENVIRONMENTAL ASSESSMENT Hardin County, Tennessee

Pickwick Landing Dam South Embankment Seismic Upgrade. DRAFT ENVIRONMENTAL ASSESSMENT Hardin County, Tennessee Document Type: EA-Administrative Record Index Field: Draft Environmental Assessment Project Name: Pickwick Landing Dam Seismic Upgrade Project Number: 2016-3 Pickwick Landing Dam South Embankment Seismic

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District Regulatory Division (1145) CEPOA-RD Post Office Box 6898 JBER, Alaska 99506-0898 Public Notice of Application for Permit PUBLIC NOTICE DATE: June 28, 2012 EXPIRATION

More information

DRAFT FINDING OF NO SIGNIFICANT IMPACT (FONSI) LEVEE VEGETATION MAINTENANCE MILL CREEK FLOOD CONTROL PROJECT WALLA WALLA, WASHINGTON JULY 2015

DRAFT FINDING OF NO SIGNIFICANT IMPACT (FONSI) LEVEE VEGETATION MAINTENANCE MILL CREEK FLOOD CONTROL PROJECT WALLA WALLA, WASHINGTON JULY 2015 DRAFT FINDING OF NO SIGNIFICANT IMPACT (FONSI) LEVEE VEGETATION MAINTENANCE MILL CREEK FLOOD CONTROL PROJECT WALLA WALLA, WASHINGTON JULY 2015 I. Introduction/Proposed Action The U.S. Army Corps of Engineers,

More information

FINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE

FINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE FINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE OURAY RANGER DISTRICT OURAY COUNTY, COLORADO BACKGROUND The Owl Creek Gravel Pit, also known as the Spruce Ridge Pit,

More information

Detailed Project Description

Detailed Project Description Detailed Project Description The current sedimentation patterns in the river have resulted in the expansion and downstream migration of the gravel bar. Because the portion of the bar that must be removed

More information

ENVIRONMENTAL ASSESSMENT

ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL ASSESSMENT Section 408 Request to Alter the Dubois Local Protection Project for the Beaver Drive sidewalk construction in Clearfield County, PA June 28, 2018 Prepared By: Environmental and

More information

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R February 2, 2018

THIS IS NOT A PAID ADVERTISEMENT. Public Notice. Public Notice No. CENAP-OP-R February 2, 2018 THIS IS NOT A PAID ADVERTISEMENT Public Notice Wanamaker Building 100 Penn Square East Philadelphia, PA 19107-3390 ATTN: CENAP-OP-R Public Notice No. Date CENAP-OP-R-2015-1060-24 February 2, 2018 Application

More information

Public Notice: Application for Permit

Public Notice: Application for Permit US Army Corps Of Engineers 201 North Third Avenue Walla Walla, WA 99362-1876 Public Notice: Application for Permit APPLICATION NO.: WATERWAY: Big Wood River APPLICANT: James E. Daverman, Dwayne Clark,

More information

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: June 17, 2014 Comment Deadline: July 17, 2014 Corps Action ID#: SAW-2009-00655 NC DOT TIP: R-4903 The Wilmington District, Corps

More information

REQUEST FOR CONSTRUCTION BIDS February 22, 2010

REQUEST FOR CONSTRUCTION BIDS February 22, 2010 REQUEST FOR CONSTRUCTION BIDS February 22, 2010 Roaring Branch Channel and Floodplain Restoration Project 1.0 Project Background Roaring Branch (watershed area ~ 41 square miles) flows generally west through

More information

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT

U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS BUILDING STRONG LOS ANGELES DISTRICT APPLICATION FOR PERMIT Deer Valley Road, El Mirage Road to 109 th Avenue Public Notice/Application No.: SPL-2010-00884-AP

More information

Chapter 6 Erosion & Stormwater Study Team

Chapter 6 Erosion & Stormwater Study Team Chapter 6 Erosion & Stormwater Study Team Objective How do we stabilize the Las Vegas Wash environment to most effectively reduce erosion and enhance wetlands? Introduction The Las Vegas Wash (Wash) has

More information

PUBLIC NOTICE PROJECT: Paradise Cay Yacht Harbor Maintenance Dredging

PUBLIC NOTICE PROJECT: Paradise Cay Yacht Harbor Maintenance Dredging SAN FRANCISCO DISTRICT PUBLIC NOTICE PROJECT: Paradise Cay Yacht Harbor Maintenance Dredging Regulatory Division 1455 Market Street, 16 th Floor San Francisco, CA 94103-1398 PUBLIC NOTICE NUMBER: 2015-00034N

More information

Appendix B Example of the Tiered NEPA Document to be used for Categorically Permitted Alterations PROGRAMMATIC ENVIRONMENTAL ASSESSMENT CATEGORICAL PERMISSIONS SECTION 408 ALTERATIONS TO EXISTING U.S.

More information

Decision Notice/Finding of No Significant Impact 1

Decision Notice/Finding of No Significant Impact 1 DECISION NOTICE FINDING OF NO SIGNIFICANT IMPACT BULL RUN CULVERT REPLACEMENTS U.S. FOREST SERVICE WHITMAN RANGER DISTRICT, WALLOWA-WHITMAN NATIONAL FOREST GRANT COUNTY, OREGON TOWNSHIP 9 SOUTH, RANGE

More information

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT 1325 J STREET SACRAMENTO CA PUBLIC NOTICE

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT 1325 J STREET SACRAMENTO CA PUBLIC NOTICE DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS, SACRAMENTO DISTRICT 1325 J STREET SACRAMENTO CA 95814-2922 Operations and Readiness Branch PUBLIC NOTICE CATEGORICAL PERMISSION FOR SECTION 408 REQUESTS

More information

Public Notice of Application for Permit

Public Notice of Application for Permit US Army Corps of Engineers Alaska District ANCHORAGE FIELD OFFICE Regulatory Division (1145) CEPOA-RD 1600 A Street, Suite 110 Anchorage, AK 99501-5146 Public Notice of Application for Permit PUBLIC NOTICE

More information

PUBLIC NOTICE US Army Corps of Engineers, Honolulu District

PUBLIC NOTICE US Army Corps of Engineers, Honolulu District PUBLIC NOTICE US Army Corps of Engineers, Honolulu District Regulatory Office (CEPOH-RO) Public Notice Date: March 16, 218 Building 23 Expiration Date: March 3, 218 Fort Shafter, Hawaii 9688-44 Permit

More information

Chehalis Basin Strategy Programmatic SEPA Draft EIS

Chehalis Basin Strategy Programmatic SEPA Draft EIS Chehalis Basin Strategy Programmatic SEPA Draft EIS History of Flooding I-5 closed in 1990, 1996, 2007, 2009 Five largest flood events occurred since 1986 2 History of Habitat Degradation Harvest has been

More information

404(b)(1) EVALUATION

404(b)(1) EVALUATION 404(b)(1) EVALUATION SECTION 404(b)(1) EVALUATION DETAILED PROJECT REPORT AND ENVIRONMENTAL ASSESSMENT POMEROY SECTION 14 EMERGENCY STREAMBANK PROTECTION PROJECT POMEROY, OH I. INTRODUCTION As required

More information

Indirect and Cumulative Effects

Indirect and Cumulative Effects Chapter 21: Indirect and Cumulative Effects 21-1 INTRODUCTION The federal Council on Environmental Quality s (CEQ) regulations implementing the procedural provisions of the National Environmental Policy

More information

CALFED Ecosystem Restoration Program (ERP)

CALFED Ecosystem Restoration Program (ERP) CALFED Ecosystem Restoration Program (ERP) The goal of the Ecosystem Restoration Program is to improve and increase aquatic and terrestrial habitats and improve ecological functions in the Bay-Delta to

More information

Public Notice.

Public Notice. Public Notice US Army Corps of Engineers Louisville District Public Notice No. Open Date: Close Date: LRL-2014-24-mad 4 Aug 2014 3 Sep 2014 Please address all comments and inquiries to: U.S. Army Corps

More information

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE GUILFORD HARBOR FEDERAL NAVIGATION PROJECT GUILFORD, CONNECTICUT

30 DAY PUBLIC NOTICE MAINTENANCE DREDGING OF THE GUILFORD HARBOR FEDERAL NAVIGATION PROJECT GUILFORD, CONNECTICUT US Army Corps of Engineers New England District 696 Virginia Road Concord, MA 1742-2751 Public Notice In Reply Refer to: Daniel Stenstream nae-pn-nav@usace.army.mil Programs/Project Management Division

More information

APPENDIX A. Project Scoping

APPENDIX A. Project Scoping APPENDIX A Project Scoping Notice of Preparation To: From: Agencies and Interested Parties Paul Brunner, Executive Director, Three Rivers Levee Improvement Authority Date: June 13, 2006 Subject: Notice

More information