TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER

Size: px
Start display at page:

Download "TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER"

Transcription

1 TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck Gerhard HARER

2 2 Project overview Koralm railway Part of the Baltic-Adriatic Core Network Corridor, which is one of the most important transeuropean traffic axes. Client Ref.: baltic-adriatic.eu

3 3 Project overview Koralm tunnel 32,9 km 2 tubes, 2 ventilation shafts, 1 emergency stop 1/3 NATM, 2/3 TBM Ref.: ÖBB, 2015

4 4 Project overview Koralm tunnel - Geological framework E KAT1 Tertiary sediments KAT2 Crystalline basement KAT3 W Tertiary sediments 32,9 km Exploratory tunnels Ref.: Harer/ÖBB, 2014

5 5 Excursus: Selection of the appropriate excavation method The selection of the appropriate excavation method is one of the most crucial decisions for a tunnel project. It is influenced from a plenty of parameter, such as: Geological conditions Excavation lengths and cross section Construction program Logistic demands and accessibility Environmental aspects Dumping demands and the re-use of mucking material...

6 6 2 TBM lots KAT2 & KAT3 Ref. Infothek.bmvit.gv.at KAT2: TBM-DS km KAT3: TBM-S (EPB) 10.5 km

7 7 Lining concept Single shell lining In general drained Pressure-tight for sediment section KAT3 Option for inner lining Ref.:Harer/ÖBB, 2014

8 8 High-performance hard-rock TBM KAT2 Technical data*: DN = 9.93 m Cutter dia Spacing 80 mm Driving power 4,900 kw Contact force 20,000kN Torque nom. 7,800 knm Torque max. 30,000 knm *) according to technical offer JV KAT2 Ref.: ÖBB, 2013

9 9 TBM performance KAT2 Start of TBM excavation 2012/2013 Already excavated 12.4 km (S) km (N) Best daily performance 45.7 m Best weekly performance 210 m Recent weekly average performance 100 m Excavation rate Status: 03/ /2013 Development of excavation rates (South tube, schematic) 2014 fault zone 2015 Construction time

10 10 TBM performance KAT2 Geological conditions are not significantly different compared to prognosis The technical performance of the JV is outstanding However, a time lag between planned and actual advance occurred So what is the reason of the loss of time?

11 11 TBM performance KAT2 Singularities: A collapse within a predicted major fault zone caused severe time loss and required additional measures Crumbling/friable rockmass and insufficient annular bedding required additional injection measures (which negatively affected logistics) to avoid additional load and deformation of the tunnel lining Ref.: Harer/ÖBB, 2014

12 12 TBM performance KAT2 Decrease in penetration: Penetration decreases locally from 4-6 mm/rev. down to 1 2 mm/rev. Locally increased rock stress is the most probable reason for local decrease of penetration (Büchi, 2014) However, This theory is controversially discussed How to predict realistically abnormal stress conditions?

13 13 TBM performance KAT2 Cutter disk damages: Outbreaks in heading face cause extraordinary high damage of disc cutters The original cutter wear decreases from roughly m3 cutting volume/disc down to 100m3 cutting volume/disc

14 14 TBM performance KAT2 Conveyor belt damages: Locally friable and crumbling conditions cause coarse, swordshaped blocks (passing the primary crusher and cutting the conveyor belt) Increase of primary crushing negatively influences the re-use of mucking material normal mucking material sword-shaped mucking material

15 15 TBM performance KAT2

16 16 TBM performance KAT2 TBM defects: TBM possesses unexpected high requirement of maintenance and repair Main bearing and main bearing seal Cutter head welding Motors Fire

17 17 TBM performance KAT3 South tube excavated by means of NATM TBM excavation started in N-tube in late 2015 Already excavated 2.2 km Ref.: metz-partner.at, 2015

18 18 Re-use of mucking material (KAT2)

19 19 Mucking material flow (KAT2) Total excavation 8,6 Mio. to Concrete 1,5 Mio. to Open sections 2,9 Mio. to The re-use of 60 % of the excavated material is part of the project! Dumping 3,0 Mio. to External recycling 1,2 Mio. to (removal by rail)

20 20 Typical petrology for aggregate production Ref. Posch & Tauer, 2016

21 21 Typical petrology for aggregate production Ref. Posch & Tauer, 2016

22 22 Requirement of extensive site logistics (KAT2) Ref. Posch & Tauer, 2016

23 23 Principal facilities (KAT2) Primary crusher on the TBM Conveyor belts (horiz. & vert.) Pre-screening Secondary screening (option.) Gravel and sand plant Aggregates deposits Rail loading facilities Feeder line Open sections and dumping grounds Ref. Posch & Tauer, 2016

24 24 Aggregate production (KAT2) Up to now (03/2016) 550,000 t successfully produced Ref. Posch & Tauer, 2016

25 25 Aggregate production (KAT2) Processing rate: Highly volatile Rate (products : input) at present appears to be slightly lower than predicted However, rate tends to increase (since improvement measures have been successfully established) Ref. Posch & Tauer, 2016

26 26 Re-use of TBM muck concluding remarks: Material processing must be properly designed in advance However, only a few reliable/coherent data from former projects are available Petrological & geochemical conditions as well as the degree of fracturing are highly influencing the output rate Furthermore cutter head design and TBM operation may influence the grain size distribution of muck It s a specialist s job Best available technology, material and interface management, triage at the face and partnership are required

27 27 Re-use of TBM muck concluding remarks: No shortages in supply occurred Excellent products were achievable (C35/45 up to C50/60) However, the average output rate in the past appears to be slightly lower than predicted The project was honored with an award from the Federal Ministry of Agriculture, Forestry, Environment and Water Ref.: oewav.at

28 28 Concluding remarks TBM drives: Investigation and design, which considers specific ground parameter and behavior is essential for TBM-, excavationand support design Competent staff on site, good workmanship and partnership are absolutely necessary (both contractor and consumer) To consider only net penetration rates or daily performance is misleading The occurrence of singularities has to be respected Flexibility is very limited in comparison to NATM/drill&blast, in particular in case of special situations Logistics directly influences the advance rates

29 29 Concluding remarks TBM drives: We are exactly in time and budget (Harer, Oslo 2014) As per the information of ÖBB this is still valid, since a proper overall risk assessment has been made and risk mitigation measures were planned in advance. However, the system limits might be reached soon. Different perceptions of contractors and owner regarding deviations and spheres will cause contractual claim negotiations.

30 30 Concluding remarks TBM drives: The selection of the appropriate excavation method (and a suitable TBM system) is one of the most crucial decisions Since the geological risk belongs to the owner it is also his responsibility to define appropriate minimum criteria It is also in the responsibility of the TBM suppliers not to arouse false hopes It seems that properly evaluated ground parameter do not fully flow in the TBM design Further research and improvement is requested Communication across the interfaces customer consultant contractor supplier has to be improved

31 31 Concluding remarks TBM drives: For the lot KAT2 Continuous investigation in advance of heading is performed (TSWD, if required probe drilling) to reduce uncertainties The complex interplay between logistics and TBM excavation was underestimated A state-of-the-art excavation with NATM/drill&blast would have caused considerable additional works and expenses (addl. ventilation shafts, widening of diameter,.) The average daily advance with TBM (in average 13 m/calendar day) is better compared to NATM/drill&blast and comparable or larger than in comparable projects

32 32 Concluding remarks TBM drives: The advantages of TBMs in the author s opinion arise esp. in: Uniform tunnel shapes (constant diameter, no niches etc.) Long tunnels (taking into account construction time, logistics, ventilation, environment,.. 10 km?) Smaller diameters Homogenous geological/geotechnical conditions Soft ground tunnels with little overburden

33 Thank you very much for your attention!

The Austrian Koralm tunnel - Investigation, Design and Construction Process for a large Base Tunnel Project

The Austrian Koralm tunnel - Investigation, Design and Construction Process for a large Base Tunnel Project The Austrian Koralm tunnel - Investigation, Design and Construction Process for a large Base Tunnel Project Gerhard Harer ÖBB Austrian Federal Railways gerhard.harer@oebb.at ÖBB-Infrastruktur/NA (Öffentlich)

More information

TBM Selection and Specification

TBM Selection and Specification By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements

More information

Semmering Base Tunnel Large Caverns in Challenging Conditions

Semmering Base Tunnel Large Caverns in Challenging Conditions Semmering Base Tunnel Large Caverns in Challenging Conditions M. Proprenter ic consulenten ZT GesmbH, Vienna, Austria. O. K. Wagner ÖBB - Austrian Federal Railways, Graz, Austria. ABSTRACT: Semmering Base

More information

Hardrock Tunnel Boring Machines

Hardrock Tunnel Boring Machines Bernhard Maidl, Leonhard Schmid, Willy Ritz, Martin Herrenknecht Hardrock Tunnel Boring Machines In co-operation with Gerhard Wehrmeyer and Marcus Derbort -=rnst & Sohn '-A Wiley Company Contents 1 Historical

More information

2

2 Company(ผ บรรยาย): Shimizu Corporation Technical Name(ห วข อเทคโนโลย ): High Performance TBM TBM ค ณภาพส ง Presenter: 水戸聰 Akira Mito 1 2 Example of Water Supply Tunnel High Overburden Ing-Yot Tunnel L=50.9km

More information

SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING

SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING Dipl. Ing. Josef Daller ic consulenten ZT GmbH Vienna, Austria Mail: j.daller@ic-group.org Abstract For construction of long infrastructure tunnels in

More information

TUNNEL WIENERWALD ABSTRACT

TUNNEL WIENERWALD ABSTRACT TUNNEL WIENERWALD Franz BAUER 1, Josef DALLER 2 and Michael PROPRENTER 2 ABSTRACT The paper provides an insight into the design and tender of the more than 13 km long Wienerwald railway tunnel in Austria.

More information

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd. Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd., Switzerland 1. Introduction The 9.4 km Zimmerberg base tunnel is an important part

More information

Excellence in tunnel engineering. Consulting, planning, realisation

Excellence in tunnel engineering. Consulting, planning, realisation Excellence in tunnel engineering Consulting, planning, realisation Excellence in tunnel engineering Tunnelling remains one of the great challenges for engineers. Today, tunnels are built mainly in densely

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

RISK MANAGEMENT. Harald Wagner PhD, PE

RISK MANAGEMENT. Harald Wagner PhD, PE WATER RESOURCES & HYDROPOWER DEVELOPMENT IN ASIA TRAINING COURSE ON CONTRACT MANAGEMENT VIENTIANE, LAO PDR February 28-29, 2016 GUEST LECTURE RISK MANAGEMENT Principles in Hydropower Tunnelling Harald

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY

HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY Chapter 11 HIGH PERFORMANCE TUNNEL BORING MACHINE FOR QUEENS WATER TUNNEL, NO. 3: A DESIGN AND CASE HISTORY Brian B. Khalighi and Joseph J. Diehl Atlas Copco Robbins Inc. and Grow Tunneling Corp. ABSTRACT

More information

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch SEMINAR Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013 Facilitator: Martin Larisch 1 Brief History of Piling Contractors, its capabilities and market Introduction to CFA piling

More information

Pump storage hydro power plant (PSKW) Reißeck

Pump storage hydro power plant (PSKW) Reißeck Roland Schorn Short description The new pump storage power plant (PSKW) Reißeck II represents an expansion of the already existing group of power plants, Malta and Reißeck/Kreuzeck in Carinthia. The new

More information

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS fib Symposium Keep Concrete Attractive, Budapest 2005 COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS Kolic D. 1, Hörlein N. 2, Schneider K. 3, Steiner H. 3 NEURON Consult ZT 1, PORR Tunnelbau GmbH 2, ÖBB-Infrastruktur

More information

2.1 Backfill - General

2.1 Backfill - General 2.1 Backfill - General Excavations are made for the purpose of constructing bridge substructure elements, and consequently requiring competent backfill material. The backfill material must be adequately

More information

FAST-Tunn Future Advanced Steel Technology for Tunnelling

FAST-Tunn Future Advanced Steel Technology for Tunnelling FAST-Tunn Future Advanced Steel Technology for Tunnelling Chief scientist/professor Eivind Grøv, SINTEF/ NTNU Project manager FAST-Tunn Background Innovative idea The aim is to increase cutter life by

More information

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul

Analysis of the EPB-TBM Excavation Parameters Used in a Tunnel Construction in Istanbul Proceedings of the 2 nd World Congress on Mechanical, Chemical, and Material Engineering (MCM'16) Budapest, Hungary August 22 23, 2016 Paper No. MMME 113 DOI: 10.11159/mmme16.113 Analysis of the EPB-TBM

More information

Prof. Eng. Daniele PEILA

Prof. Eng. Daniele PEILA Course in Tunnelling and Tunnel Boring Machine Kurs w zakresie drążenia tuneli oraz maszyny drążącej TUNNEL FACE STABILITY WITH MECHANIZED TUNNELING GENERAL CONCEPTS Prof. Eng. Daniele PEILA 0 When tunneling

More information

HORIZONTAL CONCRETE MIXING PLANTS. Horizontal Concrete Mixing Plants HN 1.5 HN 4.0 H 5 H 6

HORIZONTAL CONCRETE MIXING PLANTS. Horizontal Concrete Mixing Plants HN 1.5 HN 4.0 H 5 H 6 HORIZONTAL CONCRETE MIXING PLANTS Horizontal Concrete Mixing Plants HN 1.5 HN 4.0 H 5 H 6 0238_Horizontalmischer.indd 1 16.04.2007 14:47:32 Uhr SCHWING-STETTER MOVES CONCRETE. WORLDWIDE. Wherever concrete

More information

Pipetron Tunnel Construction Issues

Pipetron Tunnel Construction Issues Pipetron Tunnel Construction Issues James E. Friant Colorado School of Mines and Excavation Engineering Associates, Inc., 1352 SW 175th St., Seattle, WA 98166 Robert A. Bauer and David L. Gross Illinois

More information

CONCRETE FOR THE WORLD S LONGEST TUNNEL REQUIREMENTS, PRODUCTION AND TRANSPORT OF CONCRETE AND SHOTCRETE FOR THE GOTTHARD BASE TUNNEL.

CONCRETE FOR THE WORLD S LONGEST TUNNEL REQUIREMENTS, PRODUCTION AND TRANSPORT OF CONCRETE AND SHOTCRETE FOR THE GOTTHARD BASE TUNNEL. CONCRETE FOR THE WORLD S LONGEST TUNNEL REQUIREMENTS, PRODUCTION AND TRANSPORT OF CONCRETE AND SHOTCRETE FOR THE GOTTHARD BASE TUNNEL Jens Classen ABSTRACT The Gotthard Base Tunnel with its length of 57km

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information

GBR Fundamentals. Past Practices and Lessons Learned. Seminar on Geotechnical Baseline Reports. October 5, 2013

GBR Fundamentals. Past Practices and Lessons Learned. Seminar on Geotechnical Baseline Reports. October 5, 2013 GBR Fundamentals Past Practices and Lessons Learned Seminar on Geotechnical Baseline Reports October 5, 2013 Association of Geotechnical and Geoenvironmental Specialists Randall J. Essex, P.E. Executive

More information

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group Best Practices for Building High-Performance Resource Roads Road Drainage Developed by: The Roads and Infrastructure Group THIS GUIDE IS INTENDED FOR EQUIPMENT OPERATORS CONSTRUCTION CONTRACTORS FIELD

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) Topic 5 Tunnelling 1. Introduction Tunnels can be defined as underground passages constructed for the purpose of transportation connection between two points. 2. Type of Tunnels There are many types of

More information

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China Qing-Long Cui, Ph.D. student Co-authors: Ye-Shuang Xu, Shui-Long Shen*, Huai-Na

More information

Tunnel Kennedy Santiago de Chile

Tunnel Kennedy Santiago de Chile Tunnel Kennedy Santiago de Chile Juan Kuster Technical Manager, Costanera Norte Stakeholders Tunnel Kennedy (Santiago de Chile) Owner: Ministry of Public Works (MOP) Concessionaire: Costanera Norte Project

More information

Performance review of a pipe jacking project in Hong Kong

Performance review of a pipe jacking project in Hong Kong Geotechnical Aspects of Underground Construction in Soft Ground Ng, Huang & Liu (eds) 2009 Taylor & Francis Group, London, ISBN 978-0-415-48475-6 Performance review of a pipe jacking project in Hong Kong

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY CROSSRAIL INFORMATION PAPER TUNNEL CONSTRUCTON METHODOLOGY This paper sets out the proposed Crossrail tunnel construction strategy and methodology. It will be of particular relevance to those in the vicinity

More information

Introduction to Tunnel Construction

Introduction to Tunnel Construction Introduction to Tunnel Construction David Chapman, Nicole Metje and Alfred Stark *< \ Spon Press an imprint of Taylor & Francis LONDON AND NEWYORK * V TECHNISCHE INFORMATION S8IBLIOTHEK UNIVERSITATSBIBUOTHEK

More information

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by Construction Technology B (CON4313) Self Assessment Questions: Chapter 1 Prestressed Concrete 1. How does the prestressing of steel tendons in prestressed concrete offer a higher loading capacity than

More information

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS

MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS MANAGING UNDERGROUND RISKS: GEOTECHNICAL BASELINE REPORTS Randall J. Essex, PE Executive Vice President Tunnels Practice Breakthroughs in Tunneling Short Course August 14-16, 2017 Embassy Suites - O Hare,

More information

INTERNATIONAL SEMINAR LONG TUNNELS

INTERNATIONAL SEMINAR LONG TUNNELS INTERNATIONAL SEMINAR LONG TUNNELS Desafío para el Diseño, Construcción y Operación Challenges for Design, Construction and Operation Construction of long road s in Norway including the Lærdal Chief Scientist

More information

INTERNATIONAL DESIGN & CONSTRUCTION

INTERNATIONAL DESIGN & CONSTRUCTION INTERNATIONAL DESIGN & CONSTRUCTION 40 September 2013 ROADS&BRIDGES Sea and seismicity Istanbul Strait Tunnel overcomes unique set of risks By Sanja Zlatanic, P.E., and Nasri Munfah, P.E. Contributing

More information

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA

Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India. D.Harding 1 1 The Robbins Company, Solon, Ohio, USA Tunnel Boring Machines used for Irrigation in Andhra Pradesh, India D.Harding 1 1 The Robbins Company, Solon, Ohio, USA 1 INTRODUCTION The AMR project has been planned since 1983 and will provide irrigation

More information

Pipe Jacking. Japan Sewage Works Association

Pipe Jacking. Japan Sewage Works Association Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,

More information

Challenges in the Remediation of the Glatscheras-Railway-Tunnel, Bergün, Switzerland

Challenges in the Remediation of the Glatscheras-Railway-Tunnel, Bergün, Switzerland Bereich für Kundenlogo rechtsbündig, vertikal zentriert Challenges in the Remediation of the Glatscheras-Railway-Tunnel, Bergün, Switzerland Zilina, 11. November 2015 Content _ 1. Introduction _ 2. Project

More information

Optimization of Supports in a Road Tunnel through Conglomerate during Construction

Optimization of Supports in a Road Tunnel through Conglomerate during Construction Optimization of Supports in a Road Tunnel through Conglomerate during Construction Tülin SOLAK, Temelsu International Engineering Services Inc., Turkey, tulin.solak@temelsu.com.tr Bülent ULUKAN, Temelsu

More information

DESIGN AND CONSTRUCTION OF LARGE LAINZER TUNNEL PROJECT. Josef Daller, ic consulenten, Vienna - Austria

DESIGN AND CONSTRUCTION OF LARGE LAINZER TUNNEL PROJECT. Josef Daller, ic consulenten, Vienna - Austria DESIGN AND CONSTRUCTION OF LARGE TUNNELS IN SOIL AND FAULTED ROCK LAINZER TUNNEL PROJECT Josef Daller, ic consulenten, Vienna - Austria International NATM Workshop Singapore 2010 LAINZER TUNNEL PROJECT

More information

2015 UTAH ASPHALT CONFERENCE AGGREGATE PRODUCTION 101. Kilgore Companies and Kimball Equipment

2015 UTAH ASPHALT CONFERENCE AGGREGATE PRODUCTION 101. Kilgore Companies and Kimball Equipment 2015 UTAH ASPHALT CONFERENCE AGGREGATE PRODUCTION 101 Kilgore Companies and Kimball Equipment Table of Contents Types of Aggregates used in Asphalt Production Extraction Processes Primary Crushing Secondary

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan West Rail Tsing Kwai Tunnel Location of major Tunnel Portal West Rail Tsing Kwai Tunnel Construction Features -

More information

From Colonia Jardín to Cuatro Vientos

From Colonia Jardín to Cuatro Vientos 60 METROSUR Line 10, Section 1A Contractor: From Colonia Jardín to Cuatro Vientos The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was

More information

EINRIP. Specification and Construction Issues

EINRIP. Specification and Construction Issues EINRIP Specification and Construction Issues There are a significant number of changes in the Specification Not all issues can be discussed here A more detailed list of changes will be provided with bid

More information

Application of Chemical Grouts to Tunnel Repair Latest Technology

Application of Chemical Grouts to Tunnel Repair Latest Technology Technical Meeting HKIE Geotechnical Dev. Application of Chemical Grouts to Tunnel Repair Latest Technology Vincent Chien / Thorsten Tatzki 23 May 2007 Hong Kong Chien / Tatzki 1 The Speaker Vincent Chien

More information

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID TRANSIT SYSTEM Chi-Te Chang, Ming-Jung Wang, Chien-Tzen Chang, and Chieh-Wen Sun Central District Office, Department of Rapid Transit System, Taipei

More information

Metro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban tunnelling

Metro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban tunnelling EUROCK 2004 & 53 rd Geomechanics Colloquium. Schubert (ed.) 2004 VGE Metro Montreal Successful operation of a state-of-the-art roadheader ATM 105-ICUTROC competing with drill & blast operation in urban

More information

COVERING THE HIGHWAY E12 IN THE CENTRE OF HÄMEENLINNA INNOVATIVE USE OF FOAMED GLASS AS LIGHT WEIGHT MATERIAL OF APPROACH EMBANKMENT

COVERING THE HIGHWAY E12 IN THE CENTRE OF HÄMEENLINNA INNOVATIVE USE OF FOAMED GLASS AS LIGHT WEIGHT MATERIAL OF APPROACH EMBANKMENT The XXVIII International Baltic Road Conference COVERING THE HIGHWAY E12 IN THE CENTRE OF HÄMEENLINNA INNOVATIVE USE OF FOAMED GLASS AS LIGHT WEIGHT MATERIAL OF APPROACH EMBANKMENT Turo Auvinen 1, Jarmo

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT Principal Contractor: ROBERT LIVINGSTONE Project Address: 123 SYDNEY ROAD SYDNEY NSW 2000 High Risk Work Hazards and Risks Identified Control Measures Persons working at a height

More information

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore

More information

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling

Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling Remote Monitoring of Gauge Cutter Wear in Pressurized Face Tunneling Glen Frank, JayDee Contractors, Inc., Seattle, WA Ehsan Alavi Gharahbagh, The Pennsylvania State University, University Park, PA Michael

More information

Anti-wear and Anti-dust Solutions for Hard Rock TBMs

Anti-wear and Anti-dust Solutions for Hard Rock TBMs Anti-wear and Anti-dust Solutions for Hard Rock TBMs L. Langmaack 1, B. Grothen 2, P. D. Jakobsen 3 1 BASF Construction Chemicals, Zuerich, Switzerland; 2 The Robbins Company, Solon, USA; 3 The Norwegian

More information

Aggregate Specifications

Aggregate Specifications Qualified Aggregate Technician Kentucky Specifications Aggregate Specifications State, FHWA, FAA, Contractor Kentucky Transportation Cabinet 107 Aggregate Size Designations Nominal Maximum Size The largest

More information

Pipe Jacking. Progress is built on ideas.

Pipe Jacking. Progress is built on ideas. Pipe Jacking Progress is built on ideas. Frankfurt airport, enlargement of hydrant-fuelling system elongation of southeast-sewer, Nuremberg U 55 subway station, Brandenburger Tor, Berlin subway station

More information

Mitigation of the effects induced by shallow tunneling in urban environment: The use of compensation grouting in the underground Line B1 works in Rome

Mitigation of the effects induced by shallow tunneling in urban environment: The use of compensation grouting in the underground Line B1 works in Rome Geotechnical Aspects of Underground Construction in Soft Ground Viggiani (ed) 2012 Taylor & Francis Group, London, ISBN 978-0-415-68367-8 Mitigation of the effects induced by shallow tunneling in urban

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis. PART 1 GENERAL 1.1 DESCRIPTION A. The WORK under this Section includes providing all labor, materials, tools and equipment necessary for excavation and embankment construction to the lines, grades and

More information

Slab Track Austria. System ÖBB-PORR elastically supported slab

Slab Track Austria. System ÖBB-PORR elastically supported slab Slab Track Austria System ÖBB-PORR elastically supported slab 5. 2. 3. 4. 7. 6. Five holes for spindles 2. ÖBB-PORR slab 3. elastomeric layer 4. concrete joint sealing compound 5. rail support seat 6.

More information

Tender for the Supply of Fine Sand for 33kV Cabling Works in Suva

Tender for the Supply of Fine Sand for 33kV Cabling Works in Suva Tender for the Supply of Fine Sand for 33kV Cabling Works in Suva MR 53/2015 PURPOSE AND DESCRIPTION OF THE TENDER The Fiji Electricity Authority (FEA) is requesting proposal from Interested Contractors

More information

3 rd Edition of the ITA Tunnelling Awards - the winners 2017!

3 rd Edition of the ITA Tunnelling Awards - the winners 2017! Geneva, 17 th November, 2017 PRESS RELEASE 3 rd Edition of the ITA Tunnelling Awards - the winners 2017! Anyone who owns a car or has taken the metro has already experienced underground space. If tunnels

More information

Transport development between Helsinki-Tallinn twin cities

Transport development between Helsinki-Tallinn twin cities Transport development between Helsinki-Tallinn twin cities Feasibility study of the Helsinki-Tallinn fixed link January 2018 Kari Ruohonen, project director Malla Paajanen, chief adviser FinEst Link Over

More information

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project

Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project Urban EPB Tunneling in Limited Space: A Case Study of the San Francisco Central Subway Project Noah Johnson The Robbins Company ABSTRACT: The San Francisco Central Subway project is a challenging modern

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION During the early 1960s, the Virginia Department of Transportation undertook a program to upgrade aggregate materials. The Department felt this was necessary since the highway construction

More information

Partial Factors of Safety

Partial Factors of Safety APPENDIX A Partial Factors of Safety A.I Introduction The capacity of single piles in axial compression should provide an adequate safety factor against failure due to insufficient soil-pile interface

More information

Field trips 7, 14, 15. Brenner Base Tunnel

Field trips 7, 14, 15. Brenner Base Tunnel Geo.Alp, Vol. 13 2016 205-214 Field trips 7, 14, 15 Brenner Base Tunnel Ulrich Burger 1, Georg Orsi 1, Roland Arnold 1, Andrea Lussu 1, Heimo Schierl 1 1 Brenner Basistunnel BBT-SE, Amraser Str. 8, 6020

More information

Diaphragm wall Construction

Diaphragm wall Construction Diaphragm wall Construction Diaphragm wall is a continuous wall constructed in ground in to facilitate certain construction activities, such as: a) As a retaining wall b) As a cut-off provision to support

More information

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics HEKAPLAST PE-HD twin wall cable ducts and cable protection pipes for underground installation HEGLER HEKAPLAST III/ HEKAPLAST: Twin wall cable ducts or cable protection pipes to DIN 696, manufactured from

More information

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION

SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION Proceedings of the 1999 Winter Simulation Conference P. A. Farrington, H. B. Nembhard, D. T. Sturrock, and G. W. Evans, eds. SPECIAL PURPOSE SIMULATION TEMPLATE FOR UTILITY TUNNEL CONSTRUCTION Simaan M.

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information

DEEP FOUNDATIONS. Rio de Janeiro Subway Line 4: An OPA Finalist. Battered Piles. Sheet Piling. Challenging SOE

DEEP FOUNDATIONS. Rio de Janeiro Subway Line 4: An OPA Finalist. Battered Piles. Sheet Piling. Challenging SOE N TIONS DA I JAN/FEB 2016 DEEP FOUNDATIONS N DFI ITUTE ST EP FO U DE THE MAGAZINE OF THE DEEP FOUNDATIONS INSTITUTE Rio de Janeiro Subway Line 4: An OPA Finalist Battered Piles Sheet Piling Challenging

More information

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS

Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS Secoroc Rock Drilling Tools CASING ADVANCEMENT SYSTEMS PRODUCTIVITY IN A PIPE Creating stability Drilled casings, or casing advancement systems, are today's preferred method for drilling in difficult ground

More information

Membrane for tunnels and underground construction

Membrane for tunnels and underground construction System Components and applications System Platon Membrane for tunnels and underground construction Platon Tunnel membrane Platon P0 Fixing and sealing options: Platon Rock Plug Platon Brick Plug Platon

More information

REPORT STATUS: DATE: Report n :

REPORT STATUS: DATE: Report n : REPORT: Expanded clay LWA in CEA Lightweight fill and thermal insulation products for civil engineering applications. Installation and structural quality control on site. STATUS: Technical report DATE:

More information

h Installation Manual

h Installation Manual h Installation Manual 1 General Information The installation of HOBAS GRP Pipes is subject to applicable standards and guidelines such as EN 1610 and ISO/ TS 10465-1. Correct installation always requires

More information

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. H A Y W A R D B A K E R I N C. RIGID INCLUSIONS Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. Above: HBI installed Rigid Inclusions on a congested downtown

More information

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB)

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB) Rudolf Schilder Track Innovations by Austrian Railways (OEBB) Dr. Rudolf Schilder, former Head of Business Unit Railway Line and Station Management, OEBB-Infrastructure AG (Austrian Railways Infrastructure),

More information

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

NPTEL Course GROUND IMPROVEMENT USING MICROPILES Lecture 22 NPTEL Course GROUND IMPROVEMENT USING MICROPILES Prof. G L Sivakumar Babu Department of Civil Engineering Indian Institute of Science Bangalore 560012 Email: gls@civil.iisc.ernet.in Contents

More information

UNDERPINNING A CRANE FOUNDATION

UNDERPINNING A CRANE FOUNDATION UNDERPINNING A CRANE FOUNDATION Donald R. McMahon, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New York, USA Andrew J. Nichols, P.E., McMahon & Mann Consulting Engineers, P.C., Buffalo, New

More information

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The Work of this Section shall be all labour, materials, equipment and supervision necessary

More information

engineering innovation

engineering innovation engineering innovation reliability, quality, flexibility and expertise For the latest company information visit our website at www.jones-bros.com C I V I L E N G I N E E R I N G U K Head Office: Jones

More information

SITE INVESTIGATION Validation and Interpretation of data

SITE INVESTIGATION Validation and Interpretation of data SITE INVESTIGATION Validation and Interpretation of data Dr. G.Venkatappa Rao The Impact 1 The Need To determine the type of foundation To assess bearing capacity/settlement Location of Ground water table,issues

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015

SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015 SAMPLE SPECIFICATION for CROSSHOLE SONIC LOGGING (CSL) September 2015 Note: This sample specification contains recommended or typical quantities in parenthesis, in the format (quantity); the specifying

More information

MANAGEMENT. Construction. Jason Adams, VP of Systems

MANAGEMENT. Construction. Jason Adams, VP of Systems Construction MANAGEMENT Jason Adams, VP of Systems After two decades in the industry, Jason has gained a reputation as a kind, hard-working man who always puts customers first. Family TRADITION The first

More information

EUROPEAN AGGREGATES ASSOCIATION. A Sustainable Industry for a Sustainable Europe

EUROPEAN AGGREGATES ASSOCIATION. A Sustainable Industry for a Sustainable Europe EUROPEAN AGGREGATES ASSOCIATION A Sustainable Industry for a Sustainable Europe The UEPG 2020 Vision A Sustainable Aggregates Industry for a Sustainable Europe 2020 Vision for a Sustainable Aggregates

More information

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department 2017 [Type a quote from the document or the summary of an interesting point. You can position the text box anywhere in the document. Use the Drawing Tools tab to change the formatting of the pull quote

More information

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary

EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary EMERGENCY STORAGE PROJECT San Vicente Pipeline and San Vicente Dam Raise Update Presentation Summary DATE: Nov. 2, 2005 EVENT: MEETING LOCATION: PRESENTER(S): STAFF RESOURCES: TIME: 7:30 p.m. Lakeside

More information

FIBRE REINFORCED SHOTCRETE FOR LONG TUNNEL PROJECTS IN SWITZERLAND

FIBRE REINFORCED SHOTCRETE FOR LONG TUNNEL PROJECTS IN SWITZERLAND FIBRE REINFORCED SHOTCRETE FOR LONG TUNNEL PROJECTS IN SWITZERLAND Volker Wetzig, Roland Weiss VSH Hagerbach Test Gallery, Switzerland Abstract Fibre reinforced shotcrete is nowadays a common support mean

More information

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. Current Status of the Nuclear Waste Management Programme in Finland 13441

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA. Current Status of the Nuclear Waste Management Programme in Finland 13441 Current Status of the Nuclear Waste Management Programme in Finland 13441 ABSTRACT Kimmo Lehto and Petteri Vuorio Posiva Oy, Olkiluoto, FI-27160 Eurajoki, Finland (kimmo.lehto@posiva.fi) Pursuant to the

More information

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report

More information

Job Reports WR 240 / WR 240 i. Performing to highest quality standards whatever the job

Job Reports WR 240 / WR 240 i. Performing to highest quality standards whatever the job Job Reports WR 240 / WR 240 i Performing to highest quality standards whatever the job Construction of a dam for effective fl ood control Job description In the event of floods, a dam of up to 6 m in height

More information

Tel: Neil: Tony: Website:

Tel: Neil: Tony: Website: Australian Tunnelling Services are a consortium that has been formed to offer specialist underground services to both clients and contractors in the Civil Engineering, Mining & Building Industries. The

More information

Optimized crusher selection for the cement industry

Optimized crusher selection for the cement industry Optimized crusher selection for the cement industry - Technical Paper for - APCAC, XXVI Technical Congress, September 7 th -10 th, 2009 Bogota Colombia By Jürgen Muckermann ThyssenKrupp Fördertechnik GmbH,

More information

THE GROUNDBREAKING TUNNEL

THE GROUNDBREAKING TUNNEL Gotthard Base Tunnel, Switzerland Allplan Engineering in practice THE GROUNDBREAKING TUNNEL In Amsteg, where two adits meet two tunnel tubes, the 3D model created with Allplan Engineering was very useful

More information

Oil and gas companies are pushing for improved performance and better efficiency from service providers

Oil and gas companies are pushing for improved performance and better efficiency from service providers RIGMINDER TECHNICAL PRESENTATION December 7, 2017 Industry Trends Oil and gas companies are pushing for improved performance and better efficiency from service providers Drillers are responding with integrated

More information