Groundwater Master Plan Update: Emergency Groundwater Supply Analysis & Water Quality Discussion

Size: px
Start display at page:

Download "Groundwater Master Plan Update: Emergency Groundwater Supply Analysis & Water Quality Discussion"

Transcription

1 Groundwater Master Plan Update: Emergency Groundwater Supply Analysis & Water Quality Discussion BPU Study Session October 4, 2012

2 Presentation Outline Groundwater Quality Discussion Basin Overview Groundwater Contamination Test Boring Program Screening Criteria Emergency Groundwater Supply Analysis Overview of Planning Criteria Existing Water System and Operational Zones Need for Emergency GW Supplies Recommended Projects and Priorities Potential Policy Decisions

3 Restructured Agreement Requirements Sections 1.13 and 1.15 of the Restructured Agreement contain specific requirements for local supply and recycled water Summarized from Restructured Agreement: 1.13 Recycled Water and Local Supply Project Requirements Within 10 years from the date of the Agreement, the Water Contractors shall use best efforts to develop at least 7,500 AFY of recycled water or local supply projects, with approximately 50% coming from recycled water projects Local Production Capacity Goals Highly desirable for each Water Contractor to develop and maintain local water production capacity capable of meeting approximately 40% of the Water Contractor s average day maximum month demand.

4 Basin Overview: Groundwater Basins

5 Basin Overview: Geology Legend:

6 Basin Overview: Geologic Cross Sections

7 Basin Overview: Groundwater Flow Groundwater flow direction generally follows topography

8 Basin Overview: Groundwater Basin groundwater flow Contaminated releases can find their way into the groundwater aquifers

9 Basin Overview Site Specific Geologic Conditions Vary By Location Gravels Sands Silts Clays North Village Test Well Clay Doyle Park Test Well Rodgers Creek Fault Zone Martha Way Test Well Gravels Sands Silts Clays Bedrock 185 ft bgs 1,000 ft bgs 1,000 ft bgs 1,000 ft bgs

10 Groundwater Contamination: Common Contaminants Naturally Occurring Iron Manganese Arsenic Man-made Floaters: Petroleum Hydrocarbons Sinkers: Chlorinated Solvents

11 Groundwater Contaminants: Generic Spill Site

12 Groundwater Contamination: McMinn Superfund Site

13 Groundwater Contamination: Freeway Well Closure Toxic Release Site Status

14 Groundwater Contamination: Montgomery Village

15 Groundwater Contamination California Leaking Underground Fuel Tank (LUFT) Historical Case Analyses Lawrence Livermore National Laboratory November 16, 1995 The resulting estimated total volume of groundwater that may have been impacted above a concentration of 1 ppb benzene is approximately 7,060 acre-feet. The estimated total basin storage capacity in California is 1.3 billion acre-feet (CDWR, 1975). The proportion of the estimated total basin storage capacity that may be affected by LUFT benzene plumes can be calculated to be %.... (1) average site benzene concentrations have a high probability of decreasing even if no treatment is attempted, (2) benzene plume lengths rarely extend beyond 250 feet...

16 Screening Sites: Selection Criteria List All Parcels Parcels which meet hydrogeologic criteria (geology, aquifer region, etc ) Parcels which meet engineering criteria (proximity to pipelines, pump stations etc ) Parcels > 1,000 feet from documented toxic releases Parcels large enough to perform work Parcels with work area > 50 feet from sewer line Parcels with access to water Parcels with access to trunkline for sewer discharge

17 Screening Sites: General Well Construction Steel Conductor Casing Steel Well Casing Borehole Wall Annular Seal 100 Sanitary Seal Sand w/ some Clay Clay Gravel Pack Continuous Wire Wrap Screen Gravel and Sand (or fractured bedrock) Bull Nose Cap Hole Plug Gravel Fill

18 Screening Sites: Exploration Area Over 85% of Santa Rosa is more than 1,000 feet from a documented toxic release site

19 Screening Sites: Extensive Testing Pump Testing Title 22 Testing

20 Questions and Answers Discussion

21 Emergency Planning Framework City Plans Emergency Operations Plan Utilities Department Water System Emergency Response Plan How much Emergency Groundwater Supply is required? Urban Water Shortage Contingency Plan County Plans SCWA Emergency Response Plan

22 Emergency GW Planning Criteria EMERGENCY SCENARIOS Full Loss of Agency Supply Partial Loss of Agency Supply OUTAGE DURATIONS Short-term (2 days) Long-term (14 days) DEMAND CONDITIONS Existing & Buildout Conditions Buildout Demand based on uniform growth in City Health & Safety = 50% Average Day Demand FACILITY STATUS All Tanks Half Full Pump Stations Operational Pipelines Operational Existing City Wells Operational New Wells Produce 700 gpm (equivalent to 1 mgd) LEVEL OF SERVICE Service to all pressure zones to extent possible Provide supply to key pump stations or other key locations within City for distribution to customers

23 Existing Water System Storage Reservoirs 8 Agency Reservoirs 61.5 MG total capacity 50% of 61.5 MG=30.75 MG 40% available to City = 12.3 MG 25 City Reservoirs 28.3 MG total capacity 50% of 28.3 MG=14.2 MG Pressure Zones 31 Hillside Pressure Zones 2 Aqueduct Pressure Zones (Central City and Oakmont)

24 Operational Zones Master Zones Pressure Zones S-1 R1, R2, R3, R5 S-4 R4, R16, R17 S-6 R6, R7, R8 S-9 R9, R10, R11 S-12 R12, R13, R14, R15 Central City Oakmont Aqueduct Zone Each Master Zone has a key pump station that can provide water to other Pressure Zones within that Master Zone A8

25 S-1

26 S-1 S-4

27 S-1 S-4 S-6

28 S-1 S-4 S-6 S-9

29 S-1 S-4 S-6 S-9 S-12

30 S-1 S-4 S-6 Oakmont Aqueduct S-9 S-12

31 Methodology Calculate Health & Safety Demand (50% of Average Day Demand) for each scenario for each Master Zone Determine available City and/or Agency storage in each Master Zone Identify existing well capacity in each Master Zone Calculate emergency supply shortage under each scenario Determine the number of new wells required within each Master Zone Living document, to be reviewed every 5 years

32 Scenario Existing Demand Condition day Outage-----No Supply from Agency Master Zone Demand (MG) Supply (MG) Deficit (MG) Deficit (mgd) Number of Wells Reqd Master Zone S Master Zone S Master Zone S (9.3) (0.7) 1 Master Zone S ** 0** 0** Master Zone S (0.9) (0.1) 1 Central City--Aqueduct * (18.7) (1.3) 2 Oakmont--Aqueduct A (2.8) (0.2) 1 Totals (2.3) Total New Wells 700 gpm each 5 to 6 * Includes GW from Farmers Lane 1 & 2, Carley and Peters Spring Wells. ** Could require 1 well, depends on specific field operational conditions

33 Scenario Buildout Demand Condition day Outage-----No Supply from Agency Master Zone Demand (MG) Supply (MG) Deficit (MG) Deficit (mgd) Number of Wells Reqd Master Zone S (8.6) (0.6) 1 Master Zone S * Master Zone S (33.0) (2.4) 3 Master Zone S * 0*** 0*** 0*** Master Zone S (7.2) (0.5) 1 Central City--Aqueduct ** (90.0) (6.4) 7 Oakmont--Aqueduct A (4.7) (0.3) 1 Totals (10.2) Total New Wells 700 gpm each 13 to 14 * Increased supply due to higher % of available production capacity from Farmers Lane 1 & 2 dedicated to meet increased hillside demand at buildout ** Decreased supply because less GW available from Farmers Lane 1 & 2 for Central City *** Could require 1 well, depends on specific field operational conditions

34 Master Zone S-1 Leete Well is out of service, if fixed, can only serve ~45 homes due to location; low priority fix Two proposed test boring locations identified, could provide emergency supply to both S-1 and Central City Number of New Emergency Wells Required for S-1 Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA Partial Supply from SCWA Rodgers Creek Fault Rupture

35 Master Zone S-4 No problems or issues in this zone due to availability of Farmers Lane Wells 1 and 2 to provide emergency supply Number of New Emergency Wells Required for S-4 Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA Partial Supply from SCWA Rodgers Creek Fault Rupture

36 Master Zone S-6 ~1 well short of supply, will need up to 3 wells Need to identify potential additional well sites Madrone Test Well data looks promising. Identify new emergency well location in vicinity of Madrone Need to construct pump around/jumper project identified by Operations staff to provide system operational flexibility Number of New Emergency Wells Required for S-6 Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA Partial Supply from SCWA Rodgers Creek Fault Rupture

37 Master Zone S-9 Feasibility-wise, no major issues due to the ability of City emergency wells; however, need construction of several operational projects. A new test boring site and emergency well in Bennett Valley would allow increased system operational flexibility to deliver water to Central City. Number of New Emergency Wells Required for S-9 Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA 0 Possibly 1 0 Possibly 1 Partial Supply from SCWA Rodgers Creek Fault Rupture 0 Possibly 1 0 Possibly 1

38 Master Zone S-12 Zone is ~1 well short of supply Critical need to further explore use/transition of private well acquisition and/or explore potential test boring sites Emergency well could also be used to supply Oakmont Aqueduct Zone needs Number of New Emergency Wells Required for S-12 Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA Partial Supply from SCWA Rodgers Creek Fault Rupture

39 Central City-Aqueduct In an emergency Operations staff would open isolation valves from R6R1 to allow Farmers Lane and Carley/Peters Wells to also supply Central City Critical need for 2 wells now; 7 wells needed for buildout Some test wells already drilled in northern portion of service area Need to identify potential test well sites in southern portion of service area Need to move forward to identify location of potential emergency well(s) in the vicinity of Martha and Slater test sites Number of New Emergency Wells Required for Central City Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA Partial Supply from SCWA Rodgers Creek Fault Rupture

40 Oakmont-Aqueduct No wells in this Zone Critical need for 1 well now Need to aggressively move forward with identifying potential test well sites and/or transition or acquire private wells to meet shortages today Number of New Emergency Wells Required for Oakmont Existing Demand Conditions Buildout Demand Conditions 2 day outage 14 day outage 2 day outage 14 day outage No Supply from SCWA Partial Supply from SCWA Rodgers Creek Fault Rupture

41 Summary of Required Emergency Groundwater Wells Master Zone Existing Demands 2-day outage 14-day outage Buildout Demands 2-day outage 14-day outage S * S S S-9 0 ~1 0 ~1 S ** 0 1** Central City Aqueduct * Oakmont Aqueduct 1 1** 1 1** Total Number of New 700 gpm 3 4 to 5 8 ~11*** * S-1 well could also be used to serve Central City--Aqueduct ** S-12 well could also be used to serve Oakmont Aqueduct *** Number of required wells reduced to account for 2 wells which can be used to serve multiple zones.

42 Summary of Required Emergency Supply Master Zone Existing Demands 14-day outage gpm 14-day outage mgd Buildout Demands 14-day outage gpm 14-day outage mgd S S S , S-9 ~0* ~0* ~0* ~0* S Central City Aqueduct , Oakmont Aqueduct Add l Emergency GW Supply Required ~1,600 ~2.4 ~7,150 ~10.2 Notes: Original City target of 8.7 mgd of emergency groundwater production capacity Current emergency supply capacity accounted for: Farmers 1&2, Carley, Peters Spring = ~4.3 mgd * Depending on specific operational conditions, S-9 could be short of supply (but would be balanced by an equal reduction in required supply in Central City)

43 Recommended Projects & Priorities Critically Needed Projects (Short-term Program, 2-3 years) Design/Construct 3 new emergency wells Identification & construction of 2 emergency wells in Central City (1 well near S-1 and 1 well in central/southern portion of service zone) Identification & construction of 1 emergency well in Oakmont Aqueduct Zone Design and construction of pump around/jumper in S-6 and S-9 by Operations Division Identify next test well site in S-6, and possibly in S-9 Evaluate possible new emergency well(s) in vicinity of Martha and Slater test sites Mid-term Needs (5-7 years) Revisit/revise project prioritization list every 5 years to reflect actual areas of specific development and/or other potential changed conditions Construct 1 emergency well in S-6, and possibly in S-9 Construct 2 additional emergency wells in Central City Longer-term Needs (10-15 years) Construct 1 to 2 additional emergency wells in Central City Construct 1 to 2 additional emergency wells in S-6

44 Potential Policy Direction for Use of Groundwater Use groundwater for emergency use only Develop an additional 10.2 mgd to meet anticipated buildout demands (total of 14.5 mgd) Move forward to phase in Emergency Wells over next ~15-year period, focusing on addressing critical need areas first

45 Other Policy Direction to be Considered Adopt GW Master Plan and implement recommendations to inform City s participation in the GW Management Plan Prepare an Annual GW Status Report to track local GW conditions Consider Aquifer Storage & Recovery, if feasible We will be providing a general overview of ASR at the Oct 18 BPU Study Session

46 Questions and Answers Discussion

Madison Water Utility Pressure Zone 4 Well Siting Study

Madison Water Utility Pressure Zone 4 Well Siting Study Madison Water Utility Summary of Potential Well Sites March 24 2011 Site Status Comment 1 Dairy Center In consideration Several suitable properties in this area are available. 2 Tradewinds In consideration

More information

Wellhead Protection General Guidelines for New Private Domestic Wells

Wellhead Protection General Guidelines for New Private Domestic Wells Wellhead Protection General Guidelines for New Private Domestic Wells Key principles for wellhead protection for private domestic wells are as follows. Proper Location of Well (Proper sanitary control

More information

SPECIFIC SITUATION The potential conditions that the City of Oxnard may face in the earthquake include:

SPECIFIC SITUATION The potential conditions that the City of Oxnard may face in the earthquake include: MAJOR EARTHQUAKE GENERAL SITUATION The City of Oxnard is in the vicinity of several known active and potentially active earthquake faults including the San Andreas (42 miles), Oak Ridge (1 mile), Pitas

More information

INVESTIGATION RESULTS

INVESTIGATION RESULTS September 13, 2011 Burt Fleischer, R.E.A., R.E.P. Director, Environmental Affairs Hilmar Cheese Company 9001 N. Lander Avenue Hilmar, CA 95324 Subject: Revised Work Plan for Supply Well IN 1 Destruction

More information

NOTE ON WELL SITING AT CORNER OF CASTLE VALLEY DRIVE AND SHAFER LANE FOR TOWN OF CASTLE VALLEY, GRAND COUNTY, UTAH

NOTE ON WELL SITING AT CORNER OF CASTLE VALLEY DRIVE AND SHAFER LANE FOR TOWN OF CASTLE VALLEY, GRAND COUNTY, UTAH NOTE ON WELL SITING AT CORNER OF CASTLE VALLEY DRIVE AND SHAFER LANE FOR TOWN OF CASTLE VALLEY, GRAND COUNTY, UTAH Authors: Dr. Kenneth E. Kolm, Hydrologic Systems Analysis, LLC., Golden, Colorado and

More information

Case Study Casing Path Well An Effective Method to Deal with Cascading Water

Case Study Casing Path Well An Effective Method to Deal with Cascading Water Roscoe Moss Company Technical Memorandum 004-5 Case Study Casing Path Well An Effective Method to Deal with Cascading Water Executive Summary Air entrainment can be a serious problem with the potential

More information

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14

NGWA s Water Well Construction Standard: ANSI/NGWA 01-14 NGWA s Water Well Construction Standard: ANSI/NGWA 01-14 NGWA Standard Development Process as Approved by ANSI What is ANSI? The American National Standards Institute (ANSI), founded in 1918, promotes

More information

MONTEREY COUNTY HEALTH DEPARTMENT ENVIRONMENTAL HEALTH BUREAU DRINKING WATER PROTECTION SERVICES APPLICATION FOR A NEW OR AMENDED WATER SYSTEM PERMIT

MONTEREY COUNTY HEALTH DEPARTMENT ENVIRONMENTAL HEALTH BUREAU DRINKING WATER PROTECTION SERVICES APPLICATION FOR A NEW OR AMENDED WATER SYSTEM PERMIT MONTEREY COUNTY HEALTH DEPARTMENT ENVIRONMENTAL HEALTH BUREAU DRINKING WATER PROTECTION SERVICES APPLICATION FOR A NEW OR AMENDED WATER SYSTEM PERMIT Return Application to: Monterey County Health Department

More information

REGIONAL GROUND-WATER STUDY TOWN OF WOODBURY ORANGE COUNTY, NEW YORK INTRODUCTION

REGIONAL GROUND-WATER STUDY TOWN OF WOODBURY ORANGE COUNTY, NEW YORK INTRODUCTION WB- INTRODUCTION The Town of 's municipal water system consists of the and the Water District (District 6), which was previously a small private system acquired by the Town in 978. EXISTING WATER SUPPLY

More information

Michigan Department of Environmental Quality Resource Management Division Office of Oil, Gas, and Minerals

Michigan Department of Environmental Quality Resource Management Division Office of Oil, Gas, and Minerals Michigan Department of Environmental Quality Resource Management Division Office of Oil, Gas, and Minerals DEQ Mission Statement The Michigan Department of Environmental Quality promotes wise management

More information

Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #2 City of Santa Barbara, California January 27, 2016

Subsurface Desalination Intake & Potable Reuse Feasibility Studies. TAP Workshop #2 City of Santa Barbara, California January 27, 2016 Subsurface Desalination Intake & Potable Reuse Feasibility Studies TAP Workshop #2 City of Santa Barbara, California January 27, 2016 Agenda Feasibility Study Background & Objectives Update following TAP

More information

(this cover page left intentionally blank)

(this cover page left intentionally blank) 4. Siting the Well (this cover page left intentionally blank) 4. Siting the Well Chapter Table of Contents Chapter Table of Contents Chapter Description... 4 Regulatory Requirements Well Siting... 4 Relevant

More information

Executive Summary. ES.1 Background

Executive Summary. ES.1 Background Executive Summary Over the past several years the Zone 7 Water Agency (Zone 7) has undertaken a series of studies to guide construction of new wells in the local groundwater basin. Results of this work

More information

Slant Well Desalination Feedwater Supply

Slant Well Desalination Feedwater Supply Slant Well Desalination Feedwater Supply Comparison Between Dana Point Test Slant Well and CEMEX Test Slant Well CalAm 9 Oct 14 Doheny Ocean Desalination Project Dana Pt. Project Location & Layout 30 mgd

More information

REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM PROJECT DESCRIPTION

REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM PROJECT DESCRIPTION REQUEST FOR BIDS WELL DRILLING & TESTING SERVICES I-77 EXIT 1 WATER SYSTEM The Carroll County Public Service Authority requests bids from properly licensed well drilling firms, hereafter referred to as

More information

Cadiz Inc. Corporate Presentation November 2017

Cadiz Inc. Corporate Presentation November 2017 Cadiz Inc. Corporate Presentation November 2017 Cadiz Valley 1,300 square-mile watershed in Mojave Desert. Aquifer system holds approx. 20 million AF, like Lake Mead. Natural recharge 32,500 AF/year. Cadiz

More information

Worksheet #1 Assessing the Risk of Groundwater Contamination from Drinking Water Well Condition

Worksheet #1 Assessing the Risk of Groundwater Contamination from Drinking Water Well Condition Worksheet #1 Assessing the Risk of Groundwater Contamination from Drinking Water Well Condition Drinking Water Well Condition Why should I be concerned? How will this worksheet help me protect my drinking

More information

Division Mandates. Supervise the drilling, operation, and maintenance of wells to prevent damage to life, health, property, and natural resources.

Division Mandates. Supervise the drilling, operation, and maintenance of wells to prevent damage to life, health, property, and natural resources. Division Mandates Supervise the drilling, operation, and maintenance of wells to prevent damage to life, health, property, and natural resources. Supervise and permit the owners/operators to utilize all

More information

Volume 1 Executive Summary

Volume 1 Executive Summary 2013 Cheyenne Water and Wastewater Master Plans Final November 27, 2013 Prepared for: City of Cheyenne Board of Public Utilities 2416 Snyder Ave. Cheyenne, WY 82001 Prepared by: HDR Engineering AMEC Earth

More information

City of Yakima ASR: Supplying Municipal Demand in the Face of Climate Change. David Brown Water/Irrigation Manager City of Yakima

City of Yakima ASR: Supplying Municipal Demand in the Face of Climate Change. David Brown Water/Irrigation Manager City of Yakima City of Yakima ASR: Supplying Municipal Demand in the Face of Climate Change David Brown Water/Irrigation Manager City of Yakima AWRA National Conference - November 6, 2017 City of Yakima Location & Water

More information

Case Study A Comparison of Well Efficiency and Aquifer Test Results Louvered Screen vs. Continuous Wire-Wrapped Screen Big Pine, California

Case Study A Comparison of Well Efficiency and Aquifer Test Results Louvered Screen vs. Continuous Wire-Wrapped Screen Big Pine, California Case Study A Comparison of Well Efficiency and Aquifer Test Results Louvered Screen vs. Continuous Wire-Wrapped Screen Big Pine, California Executive Summary Aquifer test results demonstrated that the

More information

In support of an alternative water supply

In support of an alternative water supply FWRJ Stormwater Harvesting for Alternative Water Supply in Volusia County Lena Rivera, Lee P. Wiseman, Scott Mays, and George Recktenwald In support of an alternative water supply plan for Volusia County

More information

in the Midsouth Management Chris Henry, Ph.D., P.E. Assistant Professor and Water Management Engineer Merritt McDougal Graduate Research Assistant

in the Midsouth Management Chris Henry, Ph.D., P.E. Assistant Professor and Water Management Engineer Merritt McDougal Graduate Research Assistant Lessons Pasture Learned / Hay from Irrigation Pump options Monitoring and in the Midsouth Management Chris Henry, Ph.D., P.E. Assistant Professor and Water Management Engineer Merritt McDougal Graduate

More information

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon

Rock Fill Layer Management and Maintenance Plan Former BNSF Site 13 Highway 99 Eugene, Oregon Rock Fill Layer Management and Maintenance Plan 13 Highway 99 Prepared for: Half Moon LLC P.O. Box 25112 97402 PBS Project No. 51833.000 Rock Fill Layer Management and Maintenance Plan TABLE OF CONTENTS

More information

Section 7 Hydraulic Model Development and Evaluation Criteria

Section 7 Hydraulic Model Development and Evaluation Criteria Section 7 Hydraulic Model Development and Evaluation Criteria The hydraulic evaluation conducted to develop this master plan was performed using a computer model of the reclaimed water distribution system.

More information

Prepared For: Town of Castle Valley, Utah

Prepared For: Town of Castle Valley, Utah HYDROLOGIC ASSESSMENT OF THE SURFACE WATER AND GROUNDWATER RESOURCES OF CASTLE VALLEY, UTAH: PART 2: HESA-BASED SITING OF CULINERY WELL FOR TOWN OF CASTLE VALLEY Authors: Dr. Kenneth E. Kolm, Hydrologic

More information

West Hernando County Sewer Master Plan SECTION 7.0 RECLAIMED WATER

West Hernando County Sewer Master Plan SECTION 7.0 RECLAIMED WATER SECTION 7.0 RECLAIMED WATER 7.1 Introduction The use of highly treated wastewater effluent, or reclaimed water, has expanded greatly in Florida over the past several decades. In particular, the use of

More information

Montecito Water District Desalination Facilities Status Update. Board of Directors Meeting March 17, 2015

Montecito Water District Desalination Facilities Status Update. Board of Directors Meeting March 17, 2015 Montecito Water District Desalination Facilities Status Update Board of Directors Meeting March 17, 2015 Desalination Studies Update 1) Desalination Feasibility Study 2) Desalination Technical Support

More information

Regional Water Study of the Foothill and Mountain Areas of Eastern Fresno County

Regional Water Study of the Foothill and Mountain Areas of Eastern Fresno County Regional Water Study of the Foothill and Mountain Areas of Eastern Fresno County Prepared for: Fresno County Department of Public Works and Planning 2220 Tulare Street, Courtyard Level Fresno, California

More information

THERMAL REMEDIATION: TWO ERH CASE STUDIES

THERMAL REMEDIATION: TWO ERH CASE STUDIES THERMAL REMEDIATION: TWO ERH CASE STUDIES NEWMOA In Situ Thermal Remediation Workshop June14 14, 2012 Westford, MA Presentation by Janet Waldron, MassDEP Groveland Wells No.s 1 & 2 Groveland, MA 850 acre

More information

Section 5 - Planning Criteria. Section 5

Section 5 - Planning Criteria. Section 5 Section 5 - Planning Criteria Section 5 SECTION 5 PLANNING CRITERIA This section presents the design criteria and methodologies for analysis used to evaluate the existing distribution system and its facilities

More information

REGIONAL GROUND-WATER STUDY TOWN OF HAMPTONBURGH ORANGE COUNTY, NEW YORK. Prepared for. Orange County Water Authority. June 1994

REGIONAL GROUND-WATER STUDY TOWN OF HAMPTONBURGH ORANGE COUNTY, NEW YORK. Prepared for. Orange County Water Authority. June 1994 REGIOL GROUND-WATER STUDY Prepared for Orange County Water Authority June 1994 Lanc & Tully Engineering and Surveying, P.C. P.O. Box 687 - Route 207 Goshen, New York 10924 TABLE OF CONTENTS Page EXECUTIVE

More information

ABBOTT SCHOOL DISTRICT ENVIRONMENTAL FEATURES FACT SHEET & LEGEND SYMBOL REFERENCE KEY

ABBOTT SCHOOL DISTRICT ENVIRONMENTAL FEATURES FACT SHEET & LEGEND SYMBOL REFERENCE KEY ABBOTT SCHOOL DISTRICT ENVIRONMENTAL FEATURES FACT SHEET & LEGEND SYMBOL REFERENCE KEY This Fact Sheet provides additional detail on the types of facilities and land areas identified in maps prepared for

More information

STORMWATER HARVESTING FOR ALTERNATIVE WATER SUPPLY IN VOLUSIA COUNTY, FLORIDA

STORMWATER HARVESTING FOR ALTERNATIVE WATER SUPPLY IN VOLUSIA COUNTY, FLORIDA STORMWATER HARVESTING FOR ALTERNATIVE WATER SUPPLY IN VOLUSIA COUNTY, FLORIDA Lena Rivera, P.E., D.WRE (CDM); Lee P. Wiseman, P.E., BCEE (CDM); Scott Mays, P.E. (Volusia County); and George Recktenwald

More information

Tennessee Underground Injection Control Program Overview

Tennessee Underground Injection Control Program Overview Tennessee Underground Injection Control Program Overview Mission of the UIC Program The UIC program s mission is to protect underground sources of drinking water from contamination by regulating the construction

More information

DAVID SPEARS STATE GEOLOGIST

DAVID SPEARS STATE GEOLOGIST Hydraulic Fracturing for Natural Gas in Virginia DAVID SPEARS STATE GEOLOGIST What is hydraulic fracturing? An industrial process in which reservoir rocks are fractured using high-pressure fluid Used to

More information

EFFECTIVE CLEANUP AT LAWRENCE LIVERMORE NATIONAL LABORATORY: INNOVATIVE TECHNOLOGIES AND APPROACHES

EFFECTIVE CLEANUP AT LAWRENCE LIVERMORE NATIONAL LABORATORY: INNOVATIVE TECHNOLOGIES AND APPROACHES EFFECTIVE CLEANUP AT LAWRENCE LIVERMORE NATIONAL LABORATORY: INNOVATIVE TECHNOLOGIES AND APPROACHES Albert L. Lamarre Lawrence Livermore National Laboratory Kathy Angleberger U.S. Dept. of Energy Michael

More information

Raw Water Supply Master Plan Development

Raw Water Supply Master Plan Development Raw Water Supply Master Plan Development Stakeholder Outreach Meeting - II 31 August 2016 Welcome Introductions Master Plan Goals and Objectives Refine our standard approach to long-term plan for securing

More information

The Transport of MTBE through Groundwater in the Bootheel, an Alluvial Setting

The Transport of MTBE through Groundwater in the Bootheel, an Alluvial Setting The Transport of MTBE through Groundwater in the Bootheel, an Alluvial Setting John Pate Department of Natural Resources, Missouri Geological Survey, Geological Survey Program, Environmental Geology Section,

More information

WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS. GENERAL WATER POLLUTION CONTROL PERMIT Permit Number: GP-WV-1-07

WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS. GENERAL WATER POLLUTION CONTROL PERMIT Permit Number: GP-WV-1-07 WEST VIRGINIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS GENERAL WATER POLLUTION CONTROL PERMIT Permit Number: GP-WV-1-07 FACT SHEET, RATIONALE AND INFORMATION FOR GENERAL PERMIT FOR

More information

Wastewater ENVIRONMENTAL SETTING. Wastewater Collection

Wastewater ENVIRONMENTAL SETTING. Wastewater Collection 4.15.3.1 ENVIRONMENTAL SETTING Wastewater Collection The City owns, operates, and maintains the local sewer lines that collect wastewater generated within the City. The existing sewer lines include a gravity

More information

Bottled Water: What s the problem?

Bottled Water: What s the problem? Bottled Water: What s the problem? Where does your water come from? Groundwater Reservoir River What is groundwater? Aquifers and Groundwater Groundwater: any water that is found underground in cracks

More information

GROUNDWATER DISCHARGE

GROUNDWATER DISCHARGE GROUNDWATER DISCHARGE C O N N E C T I O N F A C T S H E E T S E R I E S D I S C H A R G E : The movement of groundwater from the subsurface to the surface P E R M E A B I L I T Y : The ability of a material

More information

Virgin Valley Water District Water System Deficiencies VVWD BOARD MEETING DECEMBER 6, 2016

Virgin Valley Water District Water System Deficiencies VVWD BOARD MEETING DECEMBER 6, 2016 Virgin Valley Water District Water System Deficiencies VVWD BOARD MEETING DECEMBER 6, 2016 Recap of Growth Projections 2.75% growth rate Average daily demand per Equivalent Dwelling Unit (EDU) of 410 gallons

More information

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...

TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed

More information

7. Completing the Well s Structure

7. Completing the Well s Structure 7. Completing the Well s Structure 7. Completing the Well s Structure Chapter Table of Contents Chapter Table of Contents Chapter Description... 5 Regulatory Requirements Completing the Well s Structure...

More information

Example Application of Long Term Stewardship for the Chlorinated Vapor Intrusion Pathway (and VOC sources)

Example Application of Long Term Stewardship for the Chlorinated Vapor Intrusion Pathway (and VOC sources) Example Application of Long Term Stewardship for the Chlorinated Vapor Intrusion Pathway (and VOC sources) Megan Hamilton Director of Vapor Intrusion and Risk Assessment EnviroForensics March 24, 2015

More information

Montana Ground-Water Assessment Statewide Monitoring Well Network

Montana Ground-Water Assessment Statewide Monitoring Well Network Montana Ground-Water Assessment Statewide Monitoring Well Network Montana Ground-Water Assessment Water-level Monitoring and Drought: January - March 2003 Tom Patton - Montana Bureau of Mines and Geology

More information

Harford County Health Department Resource Protection Division

Harford County Health Department Resource Protection Division Harford County Health Department Resource Protection Division www.harfordcountyhealth.com Harford County Wells - Water Quantity and Quality Booklet # 02-08 Water Quantity Water sources for individual wells

More information

Soquel Creek Water District s Groundwater Recharge Feasibility Study. Lydia Holmes

Soquel Creek Water District s Groundwater Recharge Feasibility Study. Lydia Holmes Soquel Creek Water District s Groundwater Recharge Feasibility Study Lydia Holmes Soquel Creek Water District (SqCWD) Filename.ppt/2 Small beach community east of Santa Cruz 37,000 residents 100% reliant

More information

Design and Operation of Landfills

Design and Operation of Landfills Design and Operation of Landfills Soils and hydrogeology Site selection criteria Site layout and landfill operations Liner design Water balance Biological reactions in landfills Leachate quality Gas production

More information

Los Angeles 3 rd Regional

Los Angeles 3 rd Regional Los Angeles 3 rd Regional Investors Conference Los Angeles, California March 31, 2016 Metropolitan Water District of Southern California 1 Metropolitan Water District of of Southern California 2 Metropolitan

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY WATER QUALITY DIVISION PERMIT APPLICATION FORM UNDERGROUND INJECTION CONTROL (UIC) CLASS V WELL

DEPARTMENT OF ENVIRONMENTAL QUALITY WATER QUALITY DIVISION PERMIT APPLICATION FORM UNDERGROUND INJECTION CONTROL (UIC) CLASS V WELL DEPARTMENT OF ENVIRONMENTAL QUALITY WATER QUALITY DIVISION PERMIT APPLICATION FORM UNDERGROUND INJECTION CONTROL (UIC) CLASS V WELL Mail To: WDEQ/WQD ATTN: UIC Program 122 W. 25 th St. 4W Cheyenne, WY

More information

Awesome Aquifers A DEMONSTRATION. THE GROUNDWATER FOUNDATION

Awesome Aquifers A DEMONSTRATION. THE GROUNDWATER FOUNDATION Awesome Aquifers A DEMONSTRATION THE GROUNDWATER FOUNDATION www.groundwater.org Groundwater is water found underground in the spaces and cracks between rocks, sand, soil and clay. Groundwater is stored

More information

Aquifer Storage and Recovery Using Reclaimed Water: Successful Applications and Critical Opportunities

Aquifer Storage and Recovery Using Reclaimed Water: Successful Applications and Critical Opportunities Aquifer Storage and Recovery Using Reclaimed Water: Successful Applications and Critical Opportunities Agenda Benefits Water Resource Water Quality Improvement Energy Savings Existing Applications Around

More information

2015 Urban Water Management Plan for Mojave Water Agency

2015 Urban Water Management Plan for Mojave Water Agency Courtesy: Google Earth FINAL 2015 Urban Water Management Plan for Mojave Water Agency Prepared by Kennedy/Jenks Consultants June 2016 300 North Lake Avenue, Suite 1020 Pasadena, California 91101 626-568-4300

More information

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK COST EVALUATION FOR ROLLING HILLS AREA WATER MAIN EXTENSION PROFESSIONAL CONSULTING, LLC. Octagon 10, Office Center 1719 Route 10, Suite 225 Parsippany,

More information

Groundwater. Chapter 10 11/22/2011. I. Importance of groundwater

Groundwater. Chapter 10 11/22/2011. I. Importance of groundwater Groundwater Chapter 10 I. Importance of groundwater A. Groundwater is water found in the pores of soil and sediment, plus narrow fractures in bedrock B. Where is fresh water - 2 % of all water is fresh

More information

CONSTRUCTION RULES TABLE OF CONTENTS

CONSTRUCTION RULES TABLE OF CONTENTS CONSTRUCTION RULES TABLE OF CONTENTS RULE 1 TITLE... 3 RULE 2 AUTHORITY... 3 RULE 3 SCOPE OF RULES... 3 RULE 4 PURPOSE OF RULES... 4 RULE 5 DEFINITIONS... 5 RULE 6 GENERAL RULES... 14 RULE 7 LICENSING...

More information

Indirect Reuse with Multiple Benefits The El Monte Valley Mining, Reclamation, and Groundwater Recharge Project

Indirect Reuse with Multiple Benefits The El Monte Valley Mining, Reclamation, and Groundwater Recharge Project ABSTRACT & POWERPOINT PRESENTATION Indirect Reuse with Multiple Benefits The El Monte Valley Mining, Reclamation, and Groundwater Recharge Project Tim Smith Principal Engineer Helix Water District La Mesa,

More information

LAB 11: GROUNDWATER PROCESSES AND WATER RESOURCES

LAB 11: GROUNDWATER PROCESSES AND WATER RESOURCES Environmental Geology 103L team Fall 2015 names LAB 11: GROUNDWATER PROCESSES AND WATER RESOURCES The objectives of this lab are to: Understand the relationship between sedimentary rock types and groundwater

More information

PHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe

PHASE I ERNEST MINE COMPLEX. The objective of the project was to develop an economically feasible, safe PHASE I ERNEST MINE COMPLEX Project Objectives The objective of the project was to develop an economically feasible, safe method of diverting all flows from the Ernest Mine Complex to a central discharge

More information

Operator Basics: Water Supply & Sources WELCOME!

Operator Basics: Water Supply & Sources WELCOME! Operator Basics: Water Supply & Sources WELCOME! This training is presented by RCAC with funding provided by the California State Revolving Fund (SRFCA) from the California State Water Resources Control

More information

SCAMA / NOGALES WATER STORAGE STUDY APPRAISAL STUDY

SCAMA / NOGALES WATER STORAGE STUDY APPRAISAL STUDY Photo by John Hoffman. The Santa Cruz River between Nogales and Tumacácori SCAMA / NOGALES WATER STORAGE STUDY APPRAISAL STUDY Presentation to GCASE Milestone Workshop 2 November 20, 2013 Presentation

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites. Bud Ivey Ivey International

Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites. Bud Ivey Ivey International Surfactant Enhanced Remediation Of Petroleum and Chlorinated Contaminated Sites Bud Ivey Ivey International SMART Remediation Ottawa, ON February 16, 2017 SMART is Powered by: www.vertexenvironmental.ca

More information

Injection Wells. An injection well is a vertical pipe in the ground into which water, other liquids, or gases are

Injection Wells. An injection well is a vertical pipe in the ground into which water, other liquids, or gases are Injection Wells An injection well is a vertical pipe in the ground into which water, other liquids, or gases are pumped or allowed to flow. They are used for many purposes. In the 1930 s oil companies

More information

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore Maryland

MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore Maryland MARYLAND DEPARTMENT OF THE ENVIRONMENT 1800 Washington Boulevard Baltimore Maryland 21230-1719 1-800-633-6101 http:/www.mde.state.md.us Darlington Citgo 3940 Conowingo Road, Darlington Harford County,

More information

13.Well Records, Documentation, Reporting & Tagging

13.Well Records, Documentation, Reporting & Tagging 13.Well Records, Documentation, Reporting & Tagging (this page left intentionally blank) Chapter Table of Contents Chapter Table of Contents Chapter Description... 5 Regulatory Requirements Well Records,

More information

Application for Gas Exploration and Production

Application for Gas Exploration and Production 1800 Washington Blvd. Suite 655 Baltimore Maryland 21230 Application for Gas Exploration and Production This application is to be used to obtain a permit to Drill and Operate a well, within the State for

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY

IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY IV. ENVIRONMENTAL IMPACT ANALYSIS G. HYDROLOGY/WATER QUALITY ENVIRONMENTAL SETTING The project site is located in the Wilshire community of the City of Los Angeles and is bound by S. Wetherly Drive to

More information

Numerical Groundwater Model for the Kaweah Delta Water Conservation District

Numerical Groundwater Model for the Kaweah Delta Water Conservation District Numerical Groundwater Model for the Kaweah Delta Water Conservation District Nels Ruud and Peter Leffler Fugro West, Inc. Larry Dotson Kaweah Delta Water Conservation District Presentation Outline Background

More information

Thermal Remediation Services, Inc.

Thermal Remediation Services, Inc. Thermal Remediation Services, Inc. Electrical Resistance Heating for Rapid Remediation of DNAPL April 2003 David Fleming 425-396-4266 dfleming@thermalrs.com www.thermalrs.com What is Electrical Resistance

More information

Alamogordo Desalination Project

Alamogordo Desalination Project Alamogordo Desalination Project 2015 Multi State Salinity Conference Robert Fowlie, PE, BCEE February 19, 2015 Alamogordo Regional Water Supply Project Existing Water Sources Surface Water City has 5400

More information

ALAMEDA COUNTY WATER DISTRICT GROUNDWATER MANAGEMENT POLICY

ALAMEDA COUNTY WATER DISTRICT GROUNDWATER MANAGEMENT POLICY ALAMEDA COUNTY WATER DISTRICT GROUNDWATER MANAGEMENT POLICY (Adopted January 26, 1989) (Amended March 22, 2001) TABLE OF CONTENTS Page BACKGROUND 1 AUTHORIZATION 1 POLICY STATEMENT 2 OBJECTIVES 2 ATTACHMENT

More information

STRAWMAN OUTLINE March 21, 2008 ISWS/ISGS REPORT ON THE OPPORTUNITIES AND CHALLENGES OF MEETING WATER DEMAND IN NORTH-EAST ILLINOIS

STRAWMAN OUTLINE March 21, 2008 ISWS/ISGS REPORT ON THE OPPORTUNITIES AND CHALLENGES OF MEETING WATER DEMAND IN NORTH-EAST ILLINOIS STRAWMAN OUTLINE March 21, 2008 ISWS/ISGS REPORT ON THE OPPORTUNITIES AND CHALLENGES OF MEETING WATER DEMAND IN NORTH-EAST ILLINOIS REPORT TO BE DELIVERED TO THE RWSPG BY SEPTEMBER 30, 2008 Table of Contents

More information

Remediation of a Hexavalent Chromium Release To Groundwater Using Ion-Specific Resins

Remediation of a Hexavalent Chromium Release To Groundwater Using Ion-Specific Resins Proceedings of the Annual International Conference on Soils, Sediments, Water and Energy Volume 15 Article 7 June 2010 Remediation of a Hexavalent Chromium Release To Groundwater Using Ion-Specific Resins

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

3.0 CUMULATIVE PROJECTS SCENARIO

3.0 CUMULATIVE PROJECTS SCENARIO 3.0 CUMULATIVE PROJECTS SCENARIO The CEQA Guidelines define cumulative impacts as two or more individual effects that, when considered together, are considerable or which compound or increase other environmental

More information

WATER RESOURCES - WATER SUPPLY

WATER RESOURCES - WATER SUPPLY EXECUTIVE SUMMARY Sacramento County Water Agency (SCWA) constructs water supply improvement projects to serve both newly developing areas and existing customers. This report summarizes those construction

More information

Phased Implementation of In Situ Chemical Oxidation for a Large TCE DNAPL Source Area at the Portsmouth Gaseous Diffusion Plant

Phased Implementation of In Situ Chemical Oxidation for a Large TCE DNAPL Source Area at the Portsmouth Gaseous Diffusion Plant WM 7 Conference, February 25 - March 1, 27, Tucson, AZ Phased Implementation of In Situ Chemical Oxidation for a Large TCE DNAPL Source Area at the Portsmouth Gaseous Diffusion Plant P.E. Cross, S.L. Thompson

More information

Portsmouth Water Response

Portsmouth Water Response CONSULTATION UNDER THE TOWN AND COUNTRY PLANNING (DEVELOPMENT MANAGEMENT PROCEDURE ENGLAND) ORDER 2010 Applicant: UK Oil and Gas Investments PLC Planning Application Reference: SDNP/16/04679/CM Proposal:

More information

Figure 1 Demands on Lake Athens

Figure 1 Demands on Lake Athens Table 1 Projected Demands for Athens MWA and Lake Athens Water User Group Demand on Lake Athens 2010 2020 2030 2040 2050 2060 Comments City of Athens 2,326 2,832 3,431 4,111 5,003 6,108 Henderson Co. Irrigation

More information

Template. For Preparing a Source Water Assessment and Protection Plan. The. Fill-in-the-Blank Form

Template. For Preparing a Source Water Assessment and Protection Plan. The. Fill-in-the-Blank Form Template For Preparing a Source Water Assessment and Plan The Fill-in-the-Blank Form Prepared for: West Virginia Department of Health and Human Resources Bureau for Public Health Office of Health Services

More information

Ground Source Heat Pump System Design and Permitting AWWA Pacific Northwest Section Conference, May 6-8, 2009 Salem, Oregon

Ground Source Heat Pump System Design and Permitting AWWA Pacific Northwest Section Conference, May 6-8, 2009 Salem, Oregon Paul D. Stull III, P.E. Paul.Stull@amec.com Tyler Clary, PE Tyler.Clary@ci.vancouver.wa.us City of Vancouver Vancouver, WA 360.487.7169 Ground Source Heat Pump System Design and Permitting AWWA Pacific

More information

SHELL ONSHORE OPERATING PRINCIPLES

SHELL ONSHORE OPERATING PRINCIPLES SHELL ONSHORE OPERATING PRINCIPLES FOR TIGHT SAND OR SHALE OIL AND GAS In 2011, Shell publicly shared five aspirational operating principles that govern the activities where we operate and where hydraulic

More information

Aquifer Science Staff, January 2007

Aquifer Science Staff, January 2007 Guidelines for Hydrogeologic Reports and Aquifer Tests Conducted Within the Jurisdictional Boundaries of the Barton Springs / Edwards Aquifer Conservation District I. Introduction Aquifer Science Staff,

More information

The City and MID adopted this 2010 UWMP in Copies of the adoption resolutions are included in Appendix B. ES-1

The City and MID adopted this 2010 UWMP in Copies of the adoption resolutions are included in Appendix B. ES-1 ES.1 INTRODUCTION This (UWMP) has been prepared for the City of Modesto (City) and the Modesto Irrigation District (MID) by West Yost Associates (West Yost) as a joint UWMP. This 2010 UWMP for the City

More information

https://comptroller.texas.gov/economy/fiscal-notes/2015/october/frackin...

https://comptroller.texas.gov/economy/fiscal-notes/2015/october/frackin... 1 of 7 11/21/2017, 12:31 PM Glenn Hegar Texas Comptroller of Public Accounts [comptroler.texas.gov/economy/fiscal-notes/] Drillers Reuse, Repeat by Jackie Benton By now, most Texans surely know that the

More information

Summary of Issues Strategies Benefits & Costs Key Uncertainties Additional Resources

Summary of Issues Strategies Benefits & Costs Key Uncertainties Additional Resources Summary of Issues Strategies Benefits & Costs Key Uncertainties Additional Resources KEY POINT: In some cases, subsurface intakes can be less expensive than surface water intakes at stand-alone facilities.

More information

5.14 CONTAMINATED MATERIALS

5.14 CONTAMINATED MATERIALS 5.14 CONTAMINATED MATERIALS 5.14.1 Introduction Contaminated materials are toxic or potentially harmful substances that may be present in soil, groundwater, and building materials. Contaminated materials

More information

APPLICATION OF SUBSURFACE VAPOUR ASSESSMENT AT HYDROCARBON IMPACTED SITES

APPLICATION OF SUBSURFACE VAPOUR ASSESSMENT AT HYDROCARBON IMPACTED SITES APPLICATION OF SUBSURFACE VAPOUR ASSESSMENT AT HYDROCARBON IMPACTED SITES Mitch Kenaschuk, P.Eng. Peter Olmsted, M.Sc.,P.Eng. October 2004 OUTLINE Introduction Regulatory Framework and Methodology Vapour

More information

Site selection: Technical site selection criteria and information needs

Site selection: Technical site selection criteria and information needs UNFCCC SBSTA Technical Workshop on modalities and procedures for carbon dioxide capture and storage in geological formations as clean development mechanism project activities Site selection: Technical

More information

DEPARTMENT OF ENVIRONMENTAL RESOURCES REVIEW NOTICE

DEPARTMENT OF ENVIRONMENTAL RESOURCES REVIEW NOTICE DEPARTMENT OF ENVIRONMENTAL RESOURCES REVIEW NOTICE This report, prepared by outside consultants, has been reviewed by the Department of Environmental Resources and approved for publication. The contents

More information

HILTON HEAD WATER SUPPLY & SALTWATER INTRUSION. Beaufort County Council September 2012

HILTON HEAD WATER SUPPLY & SALTWATER INTRUSION. Beaufort County Council September 2012 HILTON HEAD WATER SUPPLY & SALTWATER INTRUSION Beaufort County Council September 2012 HILTON HEAD S WATER UTILITIES Three public water, wastewater, reused water utilities on Hilton Head Formerly, 10 different

More information

How Groundwater Interacts with Lakes and Streams

How Groundwater Interacts with Lakes and Streams How Groundwater Interacts with Lakes and Streams Ken Bradbury Wisconsin Geological and Natural History Survey University of Wisconsin-Extension AGI Critical Issues Webinar July 13, 2015 Groundwater basics

More information

Embedded Energy in Water Studies Study 1: Statewide and Regional Water-Energy Relationship

Embedded Energy in Water Studies Study 1: Statewide and Regional Water-Energy Relationship Embedded Energy in Water Studies Study 1: Statewide and Regional Water-Energy Relationship Prepared by GEI Consultants/Navigant Consulting, Inc. Prepared for the California Public Utilities Commission

More information

City of Cottage Grove WATER SERVICE FEASIBILITY STUDY FOR TRANSMISSION LINE CUSTOMERS FEASIBILITY REPORT FINAL. November In Association With

City of Cottage Grove WATER SERVICE FEASIBILITY STUDY FOR TRANSMISSION LINE CUSTOMERS FEASIBILITY REPORT FINAL. November In Association With City of Cottage Grove WATER SERVICE FEASIBILITY STUDY FOR TRANSMISSION LINE CUSTOMERS The undersigned has approved this document for and on behalf of Carollo Engineers, P.C. Partner FEASIBILITY REPORT

More information

Aurora Water Pursues New Water Source Water rights purchase provides environmental benefits

Aurora Water Pursues New Water Source Water rights purchase provides environmental benefits NEWS RELEASE FOR IMMEDIATE RELEASE January 22, 2018 Contact: Greg Baker Manager of Aurora Water Public Relations 303.739.7081 office 720.278.1299 cell gbaker@auroragov.org Aurora Water Pursues New Water

More information

PROPOSED DECISION DOCUMENT. CE - E. 19th St. Station Voluntary Cleanup Program New York, New York County Site No. V00542 October 2017

PROPOSED DECISION DOCUMENT. CE - E. 19th St. Station Voluntary Cleanup Program New York, New York County Site No. V00542 October 2017 PROPOSED DECISION DOCUMENT CE - E. 19th St. Station Voluntary Cleanup Program New York, New York County Site No. V00542 October 2017 Prepared by Division of Environmental Remediation New York State Department

More information