Technical Assistance Consultant s Report

Size: px
Start display at page:

Download "Technical Assistance Consultant s Report"

Transcription

1 Technical Assistance Consultant s Report Project Number: September 2014 People s Republic of China: Study on Carbon Capture and Storage in Natural Gas-Based Power Plants (Financed by the Carbon Capture and Storage Fund under the Clean Energy Financing Partnership Facility) Prepared by Beijing Jiaotong University and North China Electric Power University Beijing, China For Datang International Power Generation Co., Ltd. This consultant s report does not necessarily reflect the views of ADB or the Government concerned, and ADB and the Government cannot be held liable for its contents. (For project preparatory technical assistance: All the views expressed herein may not be incorporated into the proposed project s design.

2 ADB Technical Assistance Project: Aspen Simulation and Evaluation of Economic Feasibility of CO 2 Capture for Gaojing Gas Fired Power Plant Final (English Version) September 2014 Beijing Jiaotong University North China Electric Power University Edited by Steve Goldthorpe for ADB

3 Table of Contents 1 Introduction Background and Significance Research Objectives Research Scope Amount of flue gas treatment Operational mode MEA-based Carbon Capture and Chemical Process Simulation MEA-based Carbon Capture Technique Chemical Process Simulation Basic Data for Process Simulation Overview of extraction steam and flue gas conditions Parameters of LP Steam Quality of natural gas supply Flue gas conditions Aspen Plus Modeling Process Simulation for MEA-Based Carbon Capture Process Description Definition and simulation of benchmark conditions Models selection Reaction model Selection of equipment models Parameter research Results and Analysis Benchmark conditions CO 2 removal rate Flow rate of CO 2 -lean solution Operating pressure of stripper The temperature of rich solution at inlet of stripper The temperature of flue gas at inlet of absorber CO 2 -lean MEA temperature at inlet of absorber Summary I

4 4.5 Cooling water considerations Cooling water temperature Cooling water make up requirement Cooling water flow Economic Evaluation of MEA-Based Capture Process Basic Data Fixed Asset Investment Operating costs MEA and demineralised water costs Utilities costs Overall operating Costs Revised overall operating costs Influence of CO 2 Price on Operating Cost Summary Evaluation and Analysis of Retrofitting of Capture-ready Gas Fired Power Plant Land for Construction Power Plant efficiency Retrofitting Investment Summary Summary and Suggestions Tables References Appendix A TABLE 3-1 PARAMETERS OF PILOT PLANT LP STEAM RESOURCE... 3 TABLE 3-2 NATURAL GAS COMPOSITION (% BY VOLUME)... 3 TABLE 3-3 FLUE GAS PARAMETERS... 4 TABLE 3-4 FLUE GAS COMPOSITION... 4 TABLE 4-1 MAIN STREAMS OF THE ASPEN PLUS MODELING OF A SINGLE TRAIN... 8 TABLE 4-2 FLUE GAS FLOW RATE AND COMPOSITION TABLE 4-3 PARAMETERS FOR LP STEAM AND COOLING WATER II

5 TABLE 4-4 PARAMETERS OF THE MODELING MODULES TABLE 4-5 SIMULATION RESULTS AT BENCHMARK CONDITIONS TABLE 4-6 EFFECT OF CO 2 CAPTURE RATE ON THE UTILITIES DEMAND TABLE 4-7 EFFECT OF CO 2 -LEAN MEA FLOW ON THE UTILITIES DEMAND TABLE 4-8 EFFECT OF OPERATING PRESSURE OF STRIPPER ON THE UTILITIES DEMAND TABLE 4-9 EFFECT OF CO 2 -RICH MEA TEMPERATURE ON UTILITIES DEMAND TABLE 4-10 INFLUENCE OF TEMPERATURE OF FLUE GAS AT ABSORBER INLET TABLE 4-11 EFFECT OF TEMPERATURE OF LEAN MEA ON THE UTILITIES DEMAND TABLE 4-12 AIR AND COOLING WATER TEMPERATURE IN THE BEIJING REGION TABLE 5-1 CAPITAL COST EVALUATION BASIS TABLE 5-2 CAPITAL COSTS PARAMETERS TABLE 5-3 OPERATING COSTS ASSUMPTIONS TABLE 5-4 GENERAL INVESTMENT PARAMETERS TABLE 5-5 ESCALATION TABLE 5-6 COST OF EQUIPMENT UNITS INDICATED BY ASPEN PLUS TABLE 5-7 PROJECT CAPITAL COST TABLE 5-8 PRICES OF UTILITIES AND RAW MATERIAL TABLE 5-9 ESTIMATED RAW MATERIAL OPERATING COSTS [ORIGINAL] TABLE 5-10 ESTIMATED UTILITIES OPERATING COSTS [ORIGINAL] TABLE 5-11 OPERATING COST PER TRAIN [ORIGINAL] TABLE 5-12 REVISED OPERATING COST PER TRAIN FOR BENCHMARK CASE TABLE 6-2 PERFORMANCE OF RETROFIT OPTIONS FOR NGCC PLANT (IEAGHG, 2011) TABLE 6-3 COMPARISON OF CAPITAL COST APPENDIX A TABLE A-1 DESIGN DATA OF ADSORBER-TOWER TABLE A-2 DESIGN DATA OF COMPER TABLE A-3 DESIGN DATA OF COOLER TABLE A-4 DESIGN DATA OF COOLER TABLE A-5 DESIGN DATA OF COOLER III

6 TABLE A-6 DESIGN DATA OF EXCH TABLE A-7 DESIGN DATA OF FLASH TABLE A-8 DESIGN DATA OF GGH TABLE A-9 DESIGN DATA OF PUMP TABLE A-10 DESIGN DATA OF SEP TABLE A-11 DESIGN DATA OF STRIPPER-REBOILER TABLE A-12 DESIGN DATA OF STRIPPER-TOWER TABLE A-13 DESIGN DATA OF WASHER FIGURES FIGURE 2-1 ABSORPTION BASED POST COMBUSTION CAPTURE (GCCSI, 2012)... 1 FIGURE 4-1 FLUE GAS PRETREATMENT STAGE OF ASPEN PLUS PROCESS MODELING... 7 FIGURE 4-2 CO 2 CAPTURE STAGE OF ASPEN PLUS PROCESS MODELING... 7 FIGURE 6-1 SITE LAYOUT PLAN OF GAS FIRED POWER PLANT WITHOUT CARBON CAPTURE (IEAGHG, 2012) FIGURE 6-2 SITE LAYOUT PLAN OF GAS FIRED POWER PLANT WITH CARBON CAPTURE (IEAGHG, 2012) FIGURE 6-3 STEAM TURBINE RETROFIT WITH A FIXED INTERMEDIATE TURBINE OUTLET AND TWO LET-DOWN BACK PRESSURE TURBINES (IEAGHG, 2011), FIGURE A FIGURE 6-4 RETROFIT OF A NGCC PLANT WITH THE ADDITIONAL OF TWO BACK-PRESSURE TURBINES (IEAGHG, 2011), FIGURE A FIGURE 6-5 RETROFIT OF A NGCC PLANT WITH TWO THROTTLING VALVES (IEAGHG, 2011), FIGURE A4.7) IV

7 List of Abbreviations ADB ASME CAPEX CCS CER CHP CNY DIPGCL GDP GHG IEA IP LHV LP NGCC PCC PRC ROR USD Asian Development Bank American Society of Mechanical Engineers Capital expenditure Carbon capture and storage Certified emission reduction Combined heat and power Renminbi Yuan Datang International Power Generation Co., Ltd. Gross Domestic Product Greenhouse gas International Energy Agency Intermediate Pressure Lower heating value Low Pressure Natural Gas Combined Cycle Post-Combustion Capture The People s Republic of China Rate of return United States dollar V

8 1 Introduction 1.1 Background and Significance CO 2 is the main greenhouse gas (GHG) responsible for Climate Change. Its atmospheric concentration has increased to 401ppm in June 2014 (CO2now, 2014). With its rapid economic development in recent years, the Peoples Republic of China (PRC) became the largest energy consuming country in the world in 2009, with the consumption of 20% of global primary energy and 47% of global coal. In 2010, the PRC surpassed the U.S. and became the country with the largest total carbon emissions. Consequently, the PRC government made tremendous efforts to control its carbon emissions. On November 26, 2009, it released its ambitious GHG emissions cut target at the Copenhagen Climate Change Conference. China plans to cut its GHG emissions per unit of gross domestic product (GDP) by 40 to 45 percent below 2005 levels by Replacing coal-fired power plants with gas power plants is one of the major measures for CO 2 emissions reduction. Additionally, the gas power plant is especially suited to be used by developing countries, and regions like the PRC, to supply variable loads, provided a low cost natural gas supply can be accessed. In order to reduce CO 2 emissions, and achieve other environmental benefits, Beijing plans to convert all of its coal-fired power plants into gas power plants and heat supply centers. As one part of this plan, Datang International Power Generation Co Ltd. (DIPGCL) is now implementing a gas power plant conversion project at one of its suburban thermal power plants, Gaojing Combined Heat and Power (CHP). This project plans to shut down a 660MW coal-fired unit, which is being replaced by 3 sets of F-Grade gas turbines, each in a 350MW Natural Gas Combined Cycle (NGCC) configuration. After project completion, Gaojing CHP will have the power supply capacity of 6240GWh and winter heat supply capacity of 18 million cubic meters of hot water per annum. Nevertheless, large amounts of CO 2 will still be discharged from gas power plants. In the long run, gas power plants will be incorporated into the industry scope of CO 2 emission restrictions, which could mean that they are required to further reduce their CO 2 emissions, by implementing Carbon Capture and Storage (CCS). In light of this, ADB and the PRC government co-financed a project called, Study on Carbon Capture and Storage in Natural Gas-Based Power Plants (TA 8001-PRC), which was carried out by a research team administered by Beijing Jiaotong University (BJTU). The main purpose of this project is to develop the CCS roadmap for NGCC plants and to establish the CCS ready power plant criteria for Gaojing CHP. The research team conducted a detailed evaluation of technical and economic feasibility of retrofitting CCS to Gaojing CHP s gas-fired power plant, including a top-down economic assessment based on published data. This research project is an extension of the TA 8001-PRC study and attempts to make a bottom-up economic assessment of the proposed Gaojing CHP CCS plant. 1

9 1.2 Research Objectives The main objectives of this project are as below: Through process simulation, to evaluate CO 2 capture energy consumption in different scenarios and optimize that consumption; To make an economic feasibility evaluation of Gaojing CHP s CO 2 capture retrofitting; To evaluate the advantages of meeting capture-ready criteria in subsequent CCS implementation; and To recommend the capture-ready conditions for Gaojing CHP at different carbon capture rates. 1.3 Research Scope The research project will consider six scenarios comprising a matrix of three scales of operation and two load factors Amount of flue gas treatment There are a total of three 350MW NGCC and heat supply units in Gaojing Gas Fired Power Plant. Its three gas turbines are configured based on a one gas turbine with one steam cycle unit and a two gas turbines with one steam cycle unit. The three alternative scales of operation are: One-for-one unit scenario: In this scenario, carbon capture treatment is applied to flue gas in Gaojing CHP s one-for-one unit only. Given there is only one gas turbine in one-for-one unit, this scenario is equivalent to treating one third of flue gas of the plant. Two-on-one unit scenario: in this scenario, carbon capture treatment is applied to the flue gas in Gaojing CHP s two-on-one unit only. There are two gas turbines in the two-on-one unit, and therefore, it is equivalent in this scenario to treating two thirds of flue gas of the plant. All-plant flue gas scenario, i.e. one-for-one unit + two-on-one unit scenario: In this scenario, carbon capture treatment is applied to all flue gas in Gaojing CHP s One-for-one unit and two-on-one unit. Hence, it is equivalent in this scenario to treating the flue gas of the whole plant Operational mode During the heating season, Gaojing Gas Fired Power Plant needs to supply heat externally and generate electricity. During the non-heating season, it only needs to generate electricity. This research analyses CO 2 capture in two operational modes: 2

10 Scenario 1: running 2880 hours during the winter heating seasons + running 2620 hours during the non-heating seasons (spring and autumn), totaling 5500 hours in the year; and Scenario 2: running 2880 hours during the winter heating seasons +running 4620 hours during the non-heating seasons (spring, summer and autumn), totaling 7500 hours in the year. For these six scenarios, this research uses the chemical process simulation software, Aspen Plus, to undertake the process simulation and to analyze fixed asset investment and operating expenses. The influence of some process parameters, such as carbon capture rate, is assessed on LP steam requirement, electricity demand and cooling water requirement. This research carries out the simulation and analysis of carbon capture process only, excluding CO 2 dehydration, compression, transport and sequestration. 3

11 2 MEA-based Carbon Capture and Chemical Process Simulation 2.1 MEA-based Carbon Capture Technique MEA-based carbon capture technology is a mature post-combustion carbon capture technology with fast absorption rate and efficiency. It has been widely used for CO 2 recovery in some industrial processes. Figure 2-1 shows a typical process flow diagram of an MEA-based carbon capture process used to capture of CO 2 from a flue gas. In this process, CO 2 in the flue gas is absorbed by MEA in the absorber at a low temperature (about o C), and the CO 2 -rich MEA is then heated (to about o C) and CO 2 is regenerated in the stripper. Figure 2-1 Absorption based Post Combustion Capture (GCCSI, 2012) The Aspen Plus modeling that has been carried out on this process flow sheet is described in more detail in Chapter Chemical Process Simulation Computer simulation is useful for the preliminary design, operation optimization, sensitivity analysis, and technical and economic assessments of a chemical process. 1

12 Currently, software for chemical process simulation widely used by industry mainly includes ASPEN PLUS, PRO/II, HYSYS, ChemCAD and gproms. This research uses Aspen Tech s Aspen Plus software. The outstanding features of Aspen Plus are its complete physical properties databases. Physical properties models and data are the foundation for accurate simulation, and Aspen Plus software possesses a complete physical properties system most suited to the chemical industry. Its databases include pure component data, electrolyte solution data, solids data, Henry s constants, binary interaction parameter libraries, inorganic material data, combustion data, water solution data and other data for various chemical and physical parameters. Additionally, Aspen Plus provides pre-prepared carbon capture modules that use various amine absorbents for carbon capture in industrial process simulations. It provides physical properties data and binary interaction data that are suited to the simulation of MEA-based carbon capture process in the natural gas power plant. Aspen Plus is widely used and the results of other simulations have been well validated. 2

13 3 Basic Data for Process Simulation 3.1 Overview of extraction steam and flue gas conditions Parameters of LP Steam The stripper reboiler in the process of MEA-based carbon capture uses LP steam heating and stripping of the CO 2 -rich MEA solution to desorb CO 2 and regenerate MEA. The LP steam stream used in the Gaojing pilot plant comes from the gland sealing steam stream at conditions shown in Table 3-1. Table 3-1 Parameters of pilot plant LP steam resource Unit Value Temperature o C 150 Pressure bar 4.75 [Editorial Note - In a commercial scale optimized CO 2 capture plant the large volume of steam required for the stripper reboiler would be extracted from the crossover between the medium pressure and low pressure turbines in the power station steam cycle and would be depressurized is a power recovery turbine and desuperheated to increase its volume.] Quality of natural gas supply Gaojing Gas Fired Power Plant s gas turbine unit uses natural gas supplied via Shanxi-Beijing No. 3 Line. Table 3-2 provides the composition (volume percent) and LHV of natural gas. Table 3-2 Natural Gas composition (% by volume) CH 4 C 2 H 6 C 3 H 8 C 4 H 10 C 5 H 12 CO 2 N 2 H 2 S He 96.12% 0.501% 0.118% 0.033% 0.012% 2.6% 0.147% 4 ppmv 0.469% Lower Heating Value (LHV) MJ/Nm 3 (at normalized conditions of kpa and 20 o C) Flue gas conditions Feed gas processed by the CO 2 capture system comes from the exhaust of the host power station s heat recovery boilers. The flue gas may be subject to denitrification treatment. Table 3-3 and Table 3-4 show flue gas parameters and gas composition. 3

14 Table 3-3 Flue gas Parameters Unit Value Flue gas density kg/nm Flue gas temp. o C 79 Flue gas pressure KPa Flue gas velocity m/s 23.1 Flue gas mass flow kg/s Table 3-4 Flue gas composition Unit Value Ar 0.89 CO H 2 O % by volume 8.23 N O NOx mg/nm SO 2 mg/nm Dust mg/nm Aspen Plus Modeling Simulation of MEA-based carbon capture process Property methods and process simulation options need to be selected for simulating the MEA-based carbon capture process. Property method is the method used for the presentation of thermodynamic and kinetic parameters for physico-chemical properties and inter-species interactions (reactions) of all the species involving in the chemical process, and for the parameters that are unavailable in computer databases. In terms of the amine solution system of the MEA-based carbon capture process, for the property method in the liquid phase, the ELECNRTL method calculated via non-ideal models is used for liquid phase material (such as, water, amine and hydramine) to absorb acid gas. For gaseous phase parameters, Redlich-Kwong equation is selected. For the amine solution system, Aspen Plus possesses a dedicated data package suited to MEA-based carbon capture, which describes the dynamics on the reaction between MEA and CO 2 in the liquid phase. Therefore, KEMEA data package of MELECNRTL is used for this research. This data package is suited to the circumstances where the MEA concentration is <50% and solution temperature is <130 o C. 4

15 3.2.2 Unit models In the simulation of chemical processes, various chemical unit process and equipment are represented by modules. The main unit modules of MEA-based carbon capture process include absorbers, strippers, fans, pumps, splitters, mixers and heat exchangers. The calculation methods for simulation of modules are either equilibrium or non-equilibrium methods. Both the absorber and stripper involve multistage gas-liquid distillation operation, for which RADFRAC or RATEFRAC model can be used. RATEFRAC is a rate-based model for non-equilibrium separation. It simulates actual tray or packed columns, rather than idealized representations. RADFRAC is assumed to be an equilibrium stage model, suited to the optimization for theoretical analysis. RATEFRAC model needs to be used for the optimization of process parameters and in economic efficiency analysis. In these simulations, Aspen s RATEFRAC module is used. 5

16 4.1 Process Description 4 Process Simulation for MEA-Based Carbon Capture An illustrative process flow diagram for the MEA CO 2 capture process is shown in Figure 2-1. The corresponding diagrams for the configuration that has been modeled are shown in Figure 4-1 and Figure 4-2. Data for the main streams of the Aspen Plus modeling of a single train of the MEA process are presented in Table 4-1 Main Streams of the Aspen Plus Modeling of a single train. The flue gas (FLUEGAS) from the denitrification system of the host power station enters a separator (SEP) to condense part of the water vapor from the flue gas to decrease the load on the compressors. The compressors (COMPR1-COMPR4) compress the flue gas to the absorber inlet pressure. The compressed flue gas then enters a gas-gas-heater (GGH) and a cooler (COOLER1) to be cooled to the absorber inlet temperature. In the absorber (ADSORBER), cooled flue gas comes into contact with the recycled CO 2 -lean MEA-water solution (LEAN-ABS), and most of the CO 2 is absorbed by MEA and thus separated from the flue gas. The processed flue gas (TREATGAS) and a CO 2 -rich amine (RICH-MEA) are the output streams from the absorber module. The processed flue gas (TREATGAS) is cooled and enters a separator (WASHER) to condense water vapour and to remove MEA from the vented gas stream. The condensate (CONDWAT) discharged from WASHER flows back to a mixer (MIXER) to mix with the make-up water part of the MEA solution (MEAWAT) and recycled CO 2 -lean solution. The make-up of MEA is not modeled. The temperature of the scrubbed flue gas from WASHER is 32 o C. The flue gas at this low temperature is not buoyant. Ideally, the discharged flue gas should be warmer than 75 o C. Some Chinese plants discharge flue gas at o C after desulphurization. The clean flue gas (VENTGAS) discharged from WASHER enters the gas-gas-heater (GGH) to be heated to a temperature of 60 o C prior to discharge to atmosphere. The CO 2 -rich solution (RICH-MEA) discharged from the absorber is pumped to the lean/rich solution heat exchanger (EXCH), where the CO 2 -rich solution is preheated by the CO 2 -lean solution discharged from the stripper (STRIPPER). The preheated CO 2 -rich solution enters the stripper and is heated by LP steam in the reboiler to strip CO 2 out of the CO 2 -rich solution. CO 2 recovered from the amine solvent leaves from the top of the stripper accompanied by water vapor. That stream is cooled to condense water, which is separated and flows back into the stripper. The CO 2 -lean solution from the base of the stripper column is partially cooled in the heat exchanger EXCH by the CO 2 -rich solution stream. Because absorbent (MEA solution, MEA and H 2 O) degrades in the process and escapes with the processed flue gas, a mixer (MIXER) is added to the system to make up the lost MEA solution. The mixed stream is further cooled in COOLER4 to the absorber inlet temperature before entering the absorber. 6

17 Figure 4-1 Flue gas pretreatment stage of Aspen Plus process modeling [Editorial note The use of a bank of gas compressors, to substantially increase the pressure for the feed gas to the absorber, results from the assumption of a large pressure drop in the vapour phase passing through the absorber. In commercial MEA plant designs the vapour phase pressure drop across the absorber is minimized by equipment design, in particular by ensuring that flooding of the column with liquid does not occur and that the gas flows upwards freely over a packing that is wetted with down-flowing MEA solution. It appears that in this Aspen Plus modeling study the absorber has been modeled as a flooded column in which the gas phase is bubbled through the MEA solution against a large hydraulic head. Furthermore, since the flue gas is the exhaust gas from a gas turbine, the driving force could be provided by a back pressure on the gas turbine. Accordingly, the high capital cost and high energy consumption reported for feed gas compression in this modeling study is not representative of a likely commercial plant design. A low-power booster fan might be used to aid control of the process.] Figure 4-2 CO 2 Capture Stage of Aspen Plus process modeling 7

18 Table 4-1 Main Streams of the Aspen Plus Modeling of a single train Name FLUEGAS SEP-OUT FLUE-ABS TREATGAS CONDWAT VENTGAS Mass Flow kg/hr 637,470 36, , ,240 18, ,546 Mole Flow kmol/hr 23,048 2,021 21,027 21,517 1,036 20,480 Temperature C Pressure bar Vapor Frac Volume Flow m 3 /hr 665, , , ,507 Enthalpy Gcal/hr Component mass flows kg/hr H 2 O 52,468 36,406 16,062 35,071 18,651 16,416 CO 2 26, ,775 2, ,199 N 2 476, , , ,238 O 2 76, ,247 76, ,231 MEA Trace MEA + trace 19.8 MEACOO - trace HCO 3 trace trace CO 3 trace trace 0.5 ARGON 5, ,672 5, ,4510 SO 2 trace trace trace trace - HSO SO 3 trace NO 12 trace trace 12 Main streams of Aspen Plus modeling of a single train - continued Name RICH-MEA RICH-STP FLASHED LEAN-STP MEAWAT LEAN-ABS Mass Flow kg/hr 980, ,663 25, , ,843 Mole Flow kmol/hr 39,941 40, , ,986 Temperature C Pressure bar Vapor Frac Volume Flow m 3 /hr 1,026 1,091 5,743 1, ,008 Enthalpy Gcal/hr , ,905 Component mass flows kg/hr H 2 O 638, , , ,685 CO ,279 24, N trace 0.3 O trace 0.1 MEA 64,958 77,330 trace 130, ,662 MEA + 106, ,760 69, ,102 MEACOO - 160, , , ,227 - HCO 3 6,300 9,854 2,863 1, CO 3 2, ,068 ARGON SO 2 trace trace trace trace trace - HSO 3 trace trace trace trace 2- SO NO trace trace 8

19 In a commercial MEA plant there would be a discharge and reclaim system of waste solvent from the LEAN-STP stream between the reboiler and EXCH. However, due to the difficulty of the simulation of MEA degradation, this system is omitted in this modeling flow sheet. This simplification of the flow sheet does not alter the results of the parameter researches in this chapter. In Chapter 5, the loss of MEA due to degradation is estimated based on the data of process vendors. 4.2 Definition and simulation of benchmark conditions Basic hypothesis for simulation The power plant s exhaust gas consists of many constituents, and various other factors have impacts on the absorption process. In order to simplify the simulation process, the basic hypothesis of simulation is as follows: (1) NOx consists of NO, NO 2 and N 2 O. The content of NOx in post-denitrification flue gas is low, and even lower than the maximum NO 2 concentration that can be tolerated by MEA absorbent. In the simulation, consideration will not be given to the interactions between NOx and MEA in the simulation. The MEA loss resulted from degradation will be estimated based on the data of suppliers. [Editorial note The Chinese NOx emission standard for gas fired power stations is 50 mg (NO2) /Nm 3 (24.6 ppm by volume). The recommended maximum NO x content of MEA scrubber feed gas is 20 ppm by volume. So improved denitrification might be required prior to CO 2 capture.] (2) The influence of oxidation and corrosive effects in the simulation process are not considered; (3) The reaction process is assumed to be adiabatic; (4) In the state of gas-liquid equilibrium, CO 2, oxygen and nitrogen will conform to Henry s Law. Due to huge amounts of flue gas for processing, it is impossible for a single absorber to process such a huge amount of flue gas, even if just handling the flue gas from one gas turbine. For this reason, every gas turbine is equipped with 4 trains of carbon capture system, each train including 4 compressors, 1 absorber and 1 stripper. Each train will process one twelfth of flue gas from all the three gas turbines, i.e. each train will process one quarter of the flue gas from a single gas turbine. Flue gas flow, velocity and composition in the post-denitrification flue gas for the one-for-one unit of Gaojing Gas Fired Power Plant, are shown in Table 4-2. Parameters for low pressure stream extraction and cooling water from the capture process are shown in Table

20 Table 4-2 Flue gas flow rate and composition Units Parameter Temp. o C 79 Pressure kpa GT Flue gas Flow tonnes/h 2,550 Amount of flue gas flow processed by a single train of carbon capture tonnes/h Flue gas composition (volume%) Ar 0.89% CO 2 4.2% H 2 O 8.23% N % O % NOx 20 ppmv SO ppmv Table 4-3 Parameters for LP steam and Cooling Water Unit Value Temperature of LP steam o C 150 Pressure of LP steam bar 4.75 Cold End Temp. difference of the Reboiler o C 5 Temperature of cooling water o C 15 Pressure of cooling water bar Definition of benchmark conditions In the simulation, MEA characteristics embedded in modules of Aspen Plus are used to build thermodynamic and mass transfer models. They use ELECNRTL models to describe the thermodynamic properties of the MEA-H 2 O-CO 2 system. The simulated benchmark conditions are defined as below: CO 2 removal efficiency is nominally 90%; (Table 4-1 shows the simulation results of main streams for one train of CO 2 capture system. Stream FLUEGAS is the flue gas stream flowing into the capture system and stream FLASHED is the CO 2 product stream flowing off the capture system. CO 2 capture rate is calculated according to this equation: Capture rate of CO = mass low of CO in the stream of FLASHED mass low of CO in the steam of FLUEGAS According to the CO 2 flow rate of stream FLUEGAS and stream FLASHED in Table 4-1, the CO 2 capture rate is 91.79% in the benchmark case.) Absorbent concentration is 30% by weight MEA; 10

21 Stripper pressure is 1.9 bar; Temperature of CO 2 -rich solution at the stripper s inlet is 95 o C; Temperature of CO 2 -lean solution at the absorber s inlet is 40 o C; and, Temperature of the flue gas at the absorber s inlet is 40 o C. 4.3 Models selection Reaction model Due to existence of multi-stage equilibrium and dynamic reversible reaction, the reaction and absorption of MEA-H 2 O-CO 2 system are complicated. The equilibrium reactions in this model include the following, in which MEA is represented as R-NH 2 : 2H O=H O! +OH # (4-1) CO +2H O=HCO # +H O! (4-2) HCO # +H O=CO # +H O! (4-3) R NH! +H O=R NH +H O! (4-4) R NH COO # +H O=R NH +HCO # (4-5) SO +2H O=HSO # +H O! (4-6) HSO # +H O=SO # +H O! (4-7) The reaction equilibrium constants and kinetic constants included in the Aspen Plus modeling software are used in this simulation Selection of equipment models RATEFRAC model is used for absorber and stripper; HEATER unit model is used for the COOLER1, COOLER4 and COOLER5; HEATX model, which is a model for a two-stream heat exchanger for the gas-gas heat exchanger GGH and the lean/rich solution heat exchanger EXCH; MIXER model is used for the MIXER and MIXER3; FLASH2 Model is used for the gas-liquid separators (SEP, WASHER and FLASH); PUMP model is used for rich liquid pump. COMPR model is used for feed gas compressors Parameter research In this chapter, the effects of the parameters below on the utility requirements of the CO 2 capture process will be investigated: CO 2 removal efficiency; CO 2 -Lean solution flow rate. Operating pressure of stripper; Temperature of rich solution at the inlet of the stripper; Temperature of flue gas at the inlet of the absorber; 11

22 Temperature of lean solution at the inlet of the absorber; The following performance indicators used to evaluate parameter influence on the absorption/stripping process: Reboiler thermal duty for CO 2 stripper (GJ/t CO 2 ); Amount of low pressure steam needed by the stripper (t/t CO 2 ); [Editorial note the low pressure steam demand is equivalent to the reboiler thermal duty at an enthalpy change of GJ/tonne, which corresponds to the enthalpy difference between saturated steam at 150 o C and 4.75 bar and water condensate at 125 o C. Almost all that heat would be delivered at 150 o C, which may give rise to excessive thermal degradation of the MEA] Electrical power (kw/t CO 2 ); and, Consumption of cooling water (t/t CO 2 ). Table 4-4 Parameters of the modeling modules Model Temperature, o C Pressure, bar COOLER1 DHE TEMA EXCH COOLER4 DHE TEMA EXCH COOLER5 DHE TEMA EXCH EXCH DHE TEMA EXCH 95 GGH DHE TEMA EXCH 60 COMPR1,2,3,4 DGC CENTRIF 1.7 PUMP DCP CENTRIF 2.7 FLASH-flash vessel DVT CYLINDER SEP-flash vessel DVT CYLINDER 30 1 WASHER-flash vessel DVT CYLINDER 32.3 MIXER C 2.1 MIXER3 C 1.7 Temp. - o C Press.- bar No. stages Diam.- m STRIPPER-reboiler DRB THERMOSIPH 125 STRIPPER-tower DTW TRAYED ADSORBER-tower DTW TRAYED Results and Analysis Benchmark conditions The simulation results at benchmark condition are shown in Table 4-5. In the sensitivity studies the effect of one of the parameters on process performance is investigated and the other parameters remain unchanged. In this situation, the CO 2 capture rate may change. If so, the results presented are calculated to correspond to the consistent basis of the amounts of utilities required for capturing one tonne of CO 2. In the reporting of sensitivity studies the benchmark results are presented in bold. 12

23 Table 4-5 Simulation Results at Benchmark Conditions Unit Value Duty of reboiler GCal/h 35.7 GJ/t CO Consumption of LP steam tonnes/h t/t CO Flow of lean solution tonnes/h t/t CO Electricity requirement Electricity for compressors MW kw/t CO Electricity for CO 2 -rich solution pump kw 53.3 kw/t CO Total Electricity requirement MW kw/t CO Cooling water requirement Cooling water for flue gas(cooler1) tonnes/h t/t CO Cooling water for lean solution(cooler4) Tonnes/h t/t CO Cooling water for CO 2 product(cooler5) Tonnes/h t/t CO Total cooling water requirement tonnes/h t/t CO CO 2 removal rate Table 4-6 shows the influence of CO 2 capture rate on the utility requirement. The electricity requirement increases with an increase in CO 2 capture rate. However, the duty of reboiler, steam consumption of reboiler and the cooling water requirement reach their minimum between CO 2 capture rates of 76% and 91%. Table 4-6 Effect of CO 2 capture rate on the utilities demand CO 2 capture rate % Duty of Reboiler GJ/tCO 2 Steam t/tco 2 Electricity kw/tco % % % % % Cooling Water t/tco 2 13

24 4.4.3 Flow rate of CO 2 -lean solution Table 4-7 shows the influence of CO 2 -lean solvent flow rate on the utilities requirement. The duty of reboiler, steam consumption of reboiler and the cooling water requirement decrease with an increase in flow rate of CO 2 -lean solution. On the other hand, with an increase in flow rate of lean solution, the electricity requirement increases and CO 2 capture rate increases also. Table 4-7 Effect of CO 2 -Lean MEA flow on the utilities demand Lean flow tonnes/h Duty of Reboiler GJ/tCO 2 Steam t/tco 2 Electricity kw/tco 2 Cooling Water t/tco Operating pressure of stripper Table 4-8 shows the influence of the operating pressure of the stripper on the utilities requirement. With an increase in operating pressure of stripper, the duty of reboiler, the steam consumption, the cooling water requirement and the electricity requirement reach their minimum at 1.9 bar. Table 4-8 Effect of operating pressure of stripper on the utilities demand Operating pressure bar Duty of Steam Electricity Reboiler t/tco 2 kw/tco 2 GJ/tCO Cooling Water t/tco The temperature of rich solution at inlet of stripper Table 4-9 shows the influence of the temperature of rich solution at inlet of stripper on the utilities requirement. With an increase in the temperature of rich solution at inlet of stripper, the duty of reboiler, the steam consumption and the cooling water requirement decrease. However, the electricity requirement increases with an increase in the temperature of rich solution at inlet of stripper. In the temperature range of o C, an increase in the temperature of rich solution at inlet of stripper exerts few effect on the amount of electrical energy consumption, but results in an large decrease in CO 2 capture rate. As the result, the electricity requirement for capturing one tone of CO 2 increases with an increase in the temperature of rich solution at inlet of stripper. 14

25 Table 4-9 Effect of CO 2 -rich MEA temperature on utilities demand Temperature of CO 2 -rich MEA o C Duty of Reboiler Steam Electricity GJ/tCO 2 t/tco 2 kw/tco 2 95 o C Cooling Water t/tco 2 96 o C o C o C The temperature of flue gas at inlet of absorber Table 4-10 shows the influence of the temperature of flue gas at the inlet of the absorber on the utilities requirement. An increase in the temperature of the flue gas at the inlet of the absorber results in a decrease in the CO 2 adsorption efficiency of solvent, and hence a decrease in CO 2 capture rate. As a result, the duty of reboiler, the steam consumption and electrical energy consumption for capturing one tonne of CO 2 increases. On the other hand, with an increase in the temperature of flue gas at inlet of absorber, the cooling water flow required to cool the flue gas decreases, while the CO 2 capture rate decreases. An outcome is that cooling water requirement for capturing one tonne of CO 2 reaches its minimum at the flue gas temperature of 45 o C. Temperature of flue gas Table 4-10 Influence of temperature of flue gas at absorber inlet Duty of Reboiler GJ/tCO 2 Steam t/tco 2 Electricity kw/tco 2 Cooling Water t/tco 2 40 o C o C o C CO 2 -lean MEA temperature at inlet of absorber Table 4-11 shows the influence of CO 2 -lean MEA temperature at the inlet of the absorber on utilities requirement. With an increase in CO 2 -lean temperature at the inlet of the absorber, the duty of the reboiler, the steam requirement, and also the cooling water requirement decrease. However, electricity requirement for capturing one tonne of CO 2 increases with an increase in the CO 2 -lean temperature at the inlet of the absorber. Table 4-11 Effect of temperature of lean MEA on the utilities demand Temperature of lean MEA Duty of Reboiler GJ/tCO 2 Steam t/tco 2 Electricity kw/tco 2 38 o C o C o C o C Cooling Water t/tco 2 15

26 4.4.8 Summary The energy consumption is lowest at a CO 2 capture rate between 76% and 91%. The effect of certain parameters on one of the energy consumption indicators may be different from its effect on other energy consumption indicators, so the selection of the optimal operating condition should be decided by the evaluation of the effects of these parameters on the total cost of capture process. If the lowest consumption of LP steam is used as an object for optimization of the operating conditions, the optimal operation conditions are as follows: Operating pressure of stripper is 1.9 bar, The temperature of rich solution at the inlet of stripper is 99 o C; The temperature of flue gas at inlet of absorber is 40 o C;and The temperature of lean solution at inlet of absorber is 44 o C. If the lowest consumption of electrical energy is used as an object for optimization of the operating conditions, the different optimal operation conditions are as follows: The temperature of rich solution at the inlet of stripper is 95 o C; and The temperature of lean solution at the inlet of absorber is 38 o C. 4.5 Cooling water considerations Three coolers have been modeled in the carbon capture system, which require cooling water. In the modeled Gaojing CHP s carbon capture system, the coolers are Cooler1, Cooler4 and Cooler5. The required amount of cooling water is related to the temperature of cooling water Cooling water temperature Cooling water in the condenser s recirculation cooling water system in the steam cycle is used as the cooling water for Gaojing CHP s carbon capture system. Table 4-12 shows the average temperature of various seasons and average operating temperature of recirculation cooling water at a power plant in the Beijing region. Table 4-12 Air and Cooling Water Temperature in the Beijing Region o C Average Air Temp. Winter Spring Autumn Summer -5~+5 1~12 15~25 18~29 Temp. of Cooling Water The design temperature of the power station recirculating cooling water system is 33 o C at the maximum required to operate the power station condenser with the LP turbine exhaust at 42 o C. However, the actual operating temperature of recirculation cooling water in spring and autumn may be well under this maximum. The operating temperature for spring and autumn is usually 25 o C, while it is typically 15 o C in winter. 16

27 Cooling water temperature will influence the heat exchange area necessary for the heat exchanger, thus influencing its building cost. However, when designing the coolers, it is necessary to do so in the light of its annual maximum water temperature. Therefore a scenario is considered with an operating time of 5500 hours with the summertime operation avoided. On this basis the cooling water temperature would be 25 o C Cooling water make up requirement Consumption of recirculation cooling water includes the loss from evaporation, windage and blow down in the cooling tower. According to the specifications and data in (L/T5339, 2006), 1.5% is taken for evaporation loss coefficient, 0.4% for windage loss coefficient and 1% for blow down loss coefficient, which combine to make 2.9% for total cooling water make-up requirement Cooling water flow The carbon capture system needs large amounts of recirculation cooling water. Hence, consideration should be given to whether the capacity of Gaojing CHP s existing recirculation cooling water systems can provide sufficient cooling water for its carbon capture system. If it cannot provide sufficient cooling water, it is necessary for the carbon capture system to include new recirculation cooling water systems or to expand its existing recirculation cooling water systems. The carbon capture system extracts steam from the steam cycle, which reduces the steam discharging into the power plant condenser. Therefore the steam cycle condenser cooling water flow will be reduced accordingly. [Editorial note - From an energy balance perspective, the overall energy input to the power station is either exported as electricity or dissipated to cooling water, with only a small part of that energy dissipated by other means. If CO 2 capture is integrated into the power station energy balance, then the net electricity output is reduced, so the net heat dissipated to cooling water must increase by a similar amount, which is manifest as the addition of cooling in the CO 2 capture plant being greater than the reduction of cooling in the power plant condenser. The amount of energy delivered to CO 2 capture, and subsequently rejected to cooling, is about five times greater than the amount of electrical energy production that is lost due to steam extraction from the steam cycle. Therefore the net increase in combined cooling duty is about one fifth of the total CO 2 capture plant cooling duty. Table 4-5 reports a total cooling water demand of 57.7 tonnes per tonne of CO 2 for the Benchmark condition; i.e. 1,418 tonnes per hour. In light of the foregoing discussion, the corresponding net increase in cooling water demand for the power station with CO 2 capture would be about one fifth of that; i.e. 284 tonnes per hour per train. 17

28 The amount of make-up water is 2.9% of the cooling water flow. Therefore the additional cooling water make up requirement attributable to the addition of CO 2 capture would be 8.22 tonnes per hour per CO 2 capture train. Table 4-1 shows that the amount of water condensed from the flue gas feed stream under benchmark condition is 36.4 tonnes per hour, which is about four times greater than the additional amount of make-up water required for the cooling system. Therefore the overall water balance for the power station with CO 2 capture would be comfortably in surplus and no additional make-up water for the cooling systems would be required for replenishment in excess of that which is required for the host power station.] 18

29 5.1 Basic Data 5 Economic Evaluation of MEA-Based Capture Process Table 5-1 through Table 5-5 provide the basic data for economic evaluation. The design life of the capture plant is 30 years; Land for plant construction is a building-free cleared industrial site; Various pressurized equipment items and pipelines will be designed and manufactured based on the ASME standards; and All the control systems are the digital control systems with standard configurations. Table 5-1 Capital Cost Evaluation Basis Currency Conversion Rate Project Type Design code User Currency Name User Currency Symbol Description 6.2 CNY/US$ Cleared industrial site ASME Chinese Yuan CNY Table 5-2 Capital Costs Parameters UNITS Value Number of Weeks per Year Weeks/year 52 Number of Years for Analysis Year 20 Working Capital Percentage Percent/year 3 Desired Rate of Return/Interest Rate (ROR) Percent/year 20 ROR Annuity Factor 5 Project Capital Escalation Percent/year 3 Table 5-3 Operating Costs Assumptions UNITS Value Operating Labour (lump-sum) Cost/year 10 Maintenance Charges (lump-sum) Cost/year 10 User Entered Operating Charges (as percentage) Percent/year 15 Operating Charges (Percent of Operating Labor Costs) Percent/year 20 Plant Overhead (Percent of Operating Labor and Maintenance Costs) General and Administrative Expenses (Percent of Subtotal Operating Costs) Percent/year 25 Percent/year 4 19

30 Table 5-4 General Investment Parameters UNITS Value Tax Rate Percent/year 20% Interest Rate Percent/year 20% Economic Life of Project Years 30 Salvage Value (Fraction of Initial Capital Cost) Percent 10% Depreciation Method Straight Line Table 5-5 Escalation UNITS Value Project Capital Escalation Percent/year 3% Products Escalation Percent/year 3% Raw Material Escalation Percent/year 2% Operating and Maintenance Labor Escalation Percent/year 2% Utilities Escalation Percent/year 2% 5.2 Fixed Asset Investment Table 5-6 shows the cost of equipment for a CO 2 capture rate of 90%. The details of equipment specifications are shown in Appendix A. Table 5-6 Cost of equipment units indicated by Aspen Plus million CNY Total Direct Cost Equipment Cost ADSORBER-tower COMPER COMPER COMPER COMPER COOLER COOLER COOLER EXCH FLASH-flash vessel GGH PUMP SEP-flash vessel STRIPPER-reboiler STRIPPER-tower WASHER-flash vessel Total

31 Table 5-7 shows the project capital cost in various scenarios, including an allowance for CO 2 dehydration and compression. Table 5-7 Project capital cost Capital cost of whole plant Capital cost of one train One-for-one scenario Two-on-one scenario One-for-one + two-one-one scenario 329 million 1,316 million 2,631 million 3,946 million [Editorial note The equipment specifications in Appendix A show that almost all of the plant items are specified to operate at significant elevated pressure. Also, Table 5-6 shows that two thirds of the estimated capital cost is attributable to feed gas compressors that could be designed out of the process. Therefore it is likely to be feasible to design a CO 2 capture plant with a substantially lower capital cost than the plant that has been modeled in this study.] 5.3 Operating costs shows the price of utilities and raw materials. Table 5-8 Prices of utilities and raw material Unit Price Steam(selling price) CNY/t 192 Steam(cost price) CNY/t [see note] Electricity CNY/kWh Cooling water make up CNY/t 1.8 Demineralised water CNY/t 6 MEA CNY/kg 30 A local selling price for LP steam is noted in Table 5.8, but it is more reasonable to calculate the steam cost for CO 2 capture on the basis of the lost opportunity cost of converting that steam into electricity in the power station. Generally, 20 tonne of steam can generate 1MWh electricity, that is, one tonne of steam generate 50kWh electricity. Therefore, the cost price of steam is about 26.55CNY/t (Table 5-8). In this chapter, we use this steam price to calculate the steam cost. [Editorial note When steam extraction is integrated with a power station steam cycle, as described in the editorial note in 3.1.1, the amount of energy delivered as heat to the reboiler is about 5 times greater than the amount of energy in the form of electricity product that is lost from the LP turbine in the power station. That corresponds to about 8 tonnes of steam having the value of 1 MWh of electricity, i.e. 1 tonne of steam has the same value as 125 kwh of electricity. On this basis, the lost opportunity cost in the power station of steam extracted for the MEA reboiler is about 66 CNY per tonne of extracted steam.] 21

32 In this simulation, the expense for cooling water is calculated by the model based on cooling water flow, but the actual consumption of circulating cooling water is 2.9% of circulating flow (for details, see section 4.5). Therefore, the price of cooling water actually being input into the model is 2.9% of the raw price listed in the table, i.e. the price of input cooling water is CNY per ton of water circulated. [Editorial note See discussion in Section identifying that no cooling system make-up water is required.] MEA and demineralised ed water costs The main raw materials used in CO 2 capture process are demineralised water and MEA. Their losses have to be made up. The cost of demineralised water is calculated on the basis of its flow rate and price. According to the flow rate of H 2 O component in stream MEAWAT in Table 4-1 and the price of demineralised water shown in, the cost of demineralised water is 3.23CNY/h for one train of the CO 2 capture system. The loss of MEA includes the loss resulting from degradation and a minor loss resulting from entrainment in the discharge steams. In the simulation, the degradation of MEA is not simulated, but the flow rate of MEA components (including MEA and MEA + ) in stream MEAWAT represents the entrainment loss rate of MEA, by mass balance in the Aspen Plus model. The entrainment loss of MEA indicated in the Aspen Plus modeling is therefore kg/tco 2. The main loss of MEA in the CO 2 capture process is its degradation losses caused by oxidative degradation and thermal degradation. Some estimates of these losses are: China Wuhuan Engineering Corporation states that the specific loss of its MEA solvent (MEA loss per tonne of CO 2 captured) is 2.3 kg/tco 2 for the Gaojing pilot plant at a CO 2 capture rate of 90%. The price of its MEA solvent is 20CNY/kg. China Huneng Clean Energy Research Institute states the specific loss of its MEA solvent is 0.7 kg/tco 2 for PCC of NGCC power plant at a CO 2 capture rate of 85%, where the specific degradation loss of its solvent is 0.3 kg/tco 2. Mitsubishi Heavy Industries, Ltd states that the specific degradation loss of its solvent, KS-1, is only 10% of conventional MEA solvent. The price of KS-1 is 40 CNY/kg. [Editorial note - Table 4-1 shows that the NOx content of the feed gas is 12 kg (NO) /h. If each molecule of NOx degrades one molecule of MEA in the presence of oxygen, then the oxidative degradation of MEA would be 24.4 kg/h, i.e. 1 kg/tco 2. Thermal degradation in the reboiler would be additional.] 22

Post Combustion CO 2 Capture Scale Up Study

Post Combustion CO 2 Capture Scale Up Study Post Combustion CO 2 Capture Scale Up Study Prachi Singh and Mike Haines International Greenhouse Gas R&D programme 6 th International Conference on Clean Coal Technologies (CCT 2013) 12-16 th May 2013

More information

Impact of novel PCC solvents on existing and new Australian coal-fired power plants 1 st PCC Conference, Abu-Dhabi

Impact of novel PCC solvents on existing and new Australian coal-fired power plants 1 st PCC Conference, Abu-Dhabi Impact of novel PCC solvents on existing and new Australian coal-fired power plants 1 st PCC Conference, Abu-Dhabi Dr Narendra Dave Principal Research Engineer CSIRO Energy Technology, North Ryde, Australia

More information

Modelling of CO 2 capture using Aspen Plus for EDF power plant, Krakow, Poland

Modelling of CO 2 capture using Aspen Plus for EDF power plant, Krakow, Poland Modelling of CO 2 capture using Aspen Plus for EDF power plant, Krakow, Poland Vipul Gupta vipul.gupta@tecnico.ulisboa.pt Instituto Superior Técnico,Lisboa, Portugal October 2016 Abstract This work describes

More information

Thermodynamic analysis on post combustion CO 2 capture of natural gas fired power plant

Thermodynamic analysis on post combustion CO 2 capture of natural gas fired power plant Thermodynamic analysis on post combustion CO 2 capture of natural gas fired power plant Abstract Zeinab Amrollahi, 1 Ivar S. Ertesvåg, Olav Bolland Department of Energy and Process Engineering, Norwegian

More information

Modelling of post combustion capture plant flexibility

Modelling of post combustion capture plant flexibility Modelling of post combustion capture plant flexibility Workshop on operating flexibility of power plants with CCS Hanne Kvamsdal London November 11-12, 2009 1 Outline Background and motivation Dynamic

More information

Optimal Design Technologies for Integration of Combined Cycle Gas Turbine Power Plant with CO 2 Capture

Optimal Design Technologies for Integration of Combined Cycle Gas Turbine Power Plant with CO 2 Capture 1441 A publication of CHEMICAL ENGINEERING TRANSACTIONS VOL. 39, 2014 Guest Editors: Petar Sabev Varbanov, Jiří Jaromír Klemeš, Peng Yen Liew, Jun Yow Yong Copyright 2014, AIDIC Servizi S.r.l., ISBN 978-88-95608-30-3;

More information

Steam balance optimisation strategies

Steam balance optimisation strategies Steam balance optimisation strategies Publicado en Chemical Engineering, Noviembre 2002 Background Optimising a steam balance in a plant with several steam mains pressures is not always a simple intuitive

More information

Sandhya Eswaran, Song Wu, Robert Nicolo Hitachi Power Systems America, Ltd. 645 Martinsville Road, Basking Ridge, NJ 07920

Sandhya Eswaran, Song Wu, Robert Nicolo Hitachi Power Systems America, Ltd. 645 Martinsville Road, Basking Ridge, NJ 07920 ABSTRACT COAL-GEN 2010 Advanced Amine-based CO 2 Capture for Coal-fired Power Plants Sandhya Eswaran, Song Wu, Robert Nicolo Hitachi Power Systems America, Ltd. 645 Martinsville Road, Basking Ridge, NJ

More information

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs 1 October 1 November 2006 Royal Sonesta Hotel, Cambridge, MA Oxyfuel Pathways Rodney Allam Consultant Air Products PLC, UK Oxyfuel Technology

More information

ENERGY EFFICIENT SYNTHESIS AND DESIGN FOR CARBON CAPTURE

ENERGY EFFICIENT SYNTHESIS AND DESIGN FOR CARBON CAPTURE Distillation Absorption 2010 A.B. de Haan, H. Kooijman and A. Górak (Editors) All rights reserved by authors as per DA2010 copyright notice ENERGY EFFICIENT SYNTHESIS AND DESIGN FOR CARBON CAPTURE Angelo

More information

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY 19 September 2013 POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY TOM GUENTHER PROJECT MANAGER POWER GENERATION SERVICES PURPOSE OF STUDY Retained by IEA Environmental Projects Ltd. In order for CCS to impact

More information

HYSYS WORKBOOK By: Eng. Ahmed Deyab Fares.

HYSYS WORKBOOK By: Eng. Ahmed Deyab Fares. HYSYS WORKBOOK 2013 By: Eng. Ahmed Deyab Fares eng.a.deab@gmail.com adeyab@adeyab.com Mobile: 002-01227549943 - Email: adeyab@adeyab.com 1 Flash Separation We have a stream containing 15% ethane, 20% propane,

More information

Modelling and Simulation of a Coal-fired Supercritical Power Plant Integrated to a CO 2 Capture Plant

Modelling and Simulation of a Coal-fired Supercritical Power Plant Integrated to a CO 2 Capture Plant Energy Technology and Innovation Initiative (ETII) FACULTY OF ENGINEERING UNIVERSITY OF LEEDS Modelling and Simulation of a Coal-fired Supercritical Power Plant Integrated to a CO 2 Capture Plant Elvis

More information

ChE 455 Fall 2001 Major 1. Ethylene Oxide Production

ChE 455 Fall 2001 Major 1. Ethylene Oxide Production 10/19/01 ChE 455 Fall 2001 Major 1 Ethylene Oxide Production Ethylene oxide is a chemical used to make ethylene glycol (the primary ingredient in antifreeze). It is also used to make poly(ethylene oxide),

More information

CO 2 Capture and Storage: Options and Challenges for the Cement Industry

CO 2 Capture and Storage: Options and Challenges for the Cement Industry CO 2 Capture and Storage: Options and Challenges for the Cement Industry Martin Schneider, Düsseldorf, Germany CSI Workshop Beijing, 16 17 November 2008 CO 2 abatement costs will tremendously increase

More information

Simple Dew Point Control HYSYS v8.6

Simple Dew Point Control HYSYS v8.6 Simple Dew Point Control HYSYS v8.6 Steps to set up a simulation in HYSYS v8.6 to model a simple dew point control system consisting of: Gas chiller Flash separator Liquid stabilizer with gas recycle &

More information

Simultaneous Removal of SO 2 and CO 2 From Flue Gases at Large Coal-Fired Stationary Sources

Simultaneous Removal of SO 2 and CO 2 From Flue Gases at Large Coal-Fired Stationary Sources Simultaneous Removal of SO 2 and CO 2 From Flue Gases at Large Coal-Fired Stationary Sources Y. F. Khalil (1) and AJ Gerbino (2) (1) Chemical Engineering Department, Yale University, New Haven, CT 06520

More information

ADECOS II. Advanced Development of the Coal-Fired Oxyfuel Process with CO 2 Separation

ADECOS II. Advanced Development of the Coal-Fired Oxyfuel Process with CO 2 Separation Fakultät Maschinenwesen Institut für Energietechnik, Professur für Verbrennung, Wärme- & Stoffübertragung ADECOS II Advanced Development of the Coal-Fired Oxyfuel Process with CO 2 S. Grahl, A. Hiller,

More information

Conception of a Pulverized Coal Fired Power Plant with Carbon Capture around a Supercritical Carbon Dioxide Brayton Cycle

Conception of a Pulverized Coal Fired Power Plant with Carbon Capture around a Supercritical Carbon Dioxide Brayton Cycle Available online at www.sciencedirect.com Energy Procedia 37 (2013 ) 1180 1186 GHGT-11 Conception of a Pulverized Coal Fired Power Plant with Carbon Capture around a Supercritical Carbon Dioxide Brayton

More information

PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS

PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS Paper ID: 119, Page 1 PERFORMANCE EVALUATION OF NGCC AND COAL-FIRED STEAM POWER PLANTS WITH INTEGRATED CCS AND ORC SYSTEMS Vittorio Tola Department of Mechanical, Chemical and Material Engineering, University

More information

Experiences from Commissioning and Test Operation of Vattenfall s Oxyfuel Pilot Plant

Experiences from Commissioning and Test Operation of Vattenfall s Oxyfuel Pilot Plant Experiences from Commissioning and Test Operation of Vattenfall s Oxyfuel Pilot Plant 1 st International Oxyfuel Combustion Conference Germany, Cottbus, 7 th 11 th September 2009 Uwe Burchhardt Project

More information

Hadong and Boryeong 10 MW Pilot Projects

Hadong and Boryeong 10 MW Pilot Projects CSLF Technology Workshop in Seoul Korea Hadong and Boryeong 10 MW Pilot Projects Landscape of KEPCO RI Dr. Chong Kul Ryu (ckryu@kepri.re.kr) Renaissance Seoul Hotel, 26 March 2014 1 Contents KEPCO & KEPCO

More information

Improvement of distillation column efficiency by integration with organic Rankine power generation cycle. Introduction

Improvement of distillation column efficiency by integration with organic Rankine power generation cycle. Introduction Improvement of distillation column efficiency by integration with organic Rankine power generation cycle Dmitriy A. Sladkovskiy, St.Petersburg State Institute of Technology (technical university), Saint-

More information

Pilot Test and Simulation of an Advanced Amine Process for CO 2 Capture

Pilot Test and Simulation of an Advanced Amine Process for CO 2 Capture Pilot Test and Simulation of an Advanced Amine Process for CO 2 Capture Xi Chen, Barath Baburao, Frederic Vitse * Alstom Power, 1409 Centerpoint Blvd, Knoxville, TN 37932 Summary An Advanced Amine Process

More information

TRONDHEIM CCS CONFERENCE

TRONDHEIM CCS CONFERENCE TRONDHEIM CCS CONFERENCE June 15, 2011 6th Trondheim Conference on CO 2 Capture, Transport and Storage Pedro Casero Cabezón (pcasero@elcogas.es) ELCOGAS S.A (www.elcogas.es) 1 SCOPE IGCC & ELCOGAS, S.A

More information

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET 1. A vessel of volume 0.04m 3 contains a mixture of saturated water and steam at a temperature of 250 0 C. The mass of the liquid present is 9 kg. Find the pressure, mass, specific volume, enthalpy, entropy

More information

HIGH PUITY CARBON MONOXIDE FROM A FEED GAS ARNOLD KELLER AND RONALD SCHENDEL KINETICS TECHNOLOGY INTERNATIONAL CORPORATION MONROVIA, CALIFORNIA

HIGH PUITY CARBON MONOXIDE FROM A FEED GAS ARNOLD KELLER AND RONALD SCHENDEL KINETICS TECHNOLOGY INTERNATIONAL CORPORATION MONROVIA, CALIFORNIA THE USE OF COSORB R II TO RECOVER HIGH PUITY CARBON MONOXIDE FROM A FEED GAS BY ARNOLD KELLER AND RONALD SCHENDEL KINETICS TECHNOLOGY INTERNATIONAL CORPORATION MONROVIA, CALIFORNIA PRESENTED AT AICHE SUMMER

More information

Panel II Jänschwalde Oxyfuel demonstartion plant.

Panel II Jänschwalde Oxyfuel demonstartion plant. Panel II Jänschwalde Oxyfuel demonstartion plant. IEAGHG 2nd Oxyfuel Conference 2011 11 th 16th of Sept 2011 Yeppoon QLD, Australia Lars Strömberg Vattenfall AB 1 Lars Strömberg, IEA Oxyfuel Combustion

More information

CO 2 Capture by Amine Scrubbing

CO 2 Capture by Amine Scrubbing CO 2 Capture by Amine Scrubbing By Gary T. Rochelle Luminant Carbon Management Program Department of Chemical Engineering The University of Texas at Austin US UK workshop May 9, 2010 Roadmap Research on

More information

Integration and Onsite System Aspects of Industrial Post-Combustion CCS

Integration and Onsite System Aspects of Industrial Post-Combustion CCS Integration and Onsite System Aspects of Industrial Post-Combustion CCS V. Andersson T. Berntsson Department of Energy and Environment Chalmers University of Technology, Sweden Process flowsheet System

More information

CO 2 -flue gas separation for a conventional coal-fired power plant (first approach)

CO 2 -flue gas separation for a conventional coal-fired power plant (first approach) CO 2 -flue gas separation for a conventional coal-fired power plant (first approach) Syed Muzaffar Ali This thesis comprises 30 ECTS credits and is a compulsory part in the Master of Science with a Major

More information

Available online at Energy Procedia 4 (2011) Energy Procedia 00 (2010) GHGT-10

Available online at  Energy Procedia 4 (2011) Energy Procedia 00 (2010) GHGT-10 Available online at www.sciencedirect.com Energy Procedia 4 (2011) 1683 1690 Energy Procedia 00 (2010) 000 000 Energy Procedia www.elsevier.com/locate/procedia www.elsevier.com/locate/xxx GHGT-10 Optimum

More information

MTBE Production. Process Description. Possibility of Changing Process Feed Conditions

MTBE Production. Process Description. Possibility of Changing Process Feed Conditions Production You work in a facility that produces about 100,000 tonne/y of methyl tertiary butyl ether (). is an oxygenated fuel additive that is blended with gasoline to promote CO 2 formation over CO formation

More information

Recent Developments of Hitachi s Advanced Solvent Technology for Post-combustion CO 2 Capture

Recent Developments of Hitachi s Advanced Solvent Technology for Post-combustion CO 2 Capture Recent Developments of Hitachi s Advanced Solvent Technology for Post-combustion CO 2 Capture ABSTRACT Sandhya Eswaran, Song Wu Hitachi Power Systems America, Ltd. 645 Martinsville Road, Basking Ridge,

More information

White Rose Research Online URL for this paper: Version: Accepted Version

White Rose Research Online URL for this paper:  Version: Accepted Version This is a repository copy of Performance viability of a natural gas fired combined cycle power plant integrated with post-combustion CO2 capture at part-load and temporary non-capture operations. White

More information

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN (EXECUTIVE SESSION) November, 2007 JAPAN EXTERNAL TRADE ORGANIZATION JAPAN CONSULTING INSTITUTE SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN 1. Power Generation

More information

Development of Integrated Flexi-Burn Dual Oxidant CFB Power Plant

Development of Integrated Flexi-Burn Dual Oxidant CFB Power Plant Development of Integrated Flexi-Burn Dual Oxidant CFB Power Plant Horst Hack Zhen Fan Andrew Seltzer Foster Wheeler North America Corp., USA Timo Eriksson Ossi Sippu Arto Hotta Foster Wheeler Energia Oy,

More information

White Rose Research Online URL for this paper: Version: Accepted Version

White Rose Research Online URL for this paper:  Version: Accepted Version This is a repository copy of Performance evaluation and optimisation of post combustion CO2 capture processes for natural gas applications at pilot scale via a verified rate-based model. White Rose Research

More information

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Ammonia Your assignment is to continue evaluating the details of a process to produce 50,000 tonne/y of ammonia from a syngas

More information

ScienceDirect. Improving the efficiency of a chilled ammonia CO 2 capture plant through solid formation: a thermodynamic analysis

ScienceDirect. Improving the efficiency of a chilled ammonia CO 2 capture plant through solid formation: a thermodynamic analysis Available online at www.sciencedirect.com ScienceDirect Energy Procedia 63 (2014 ) 1084 1090 GHGT-12 Improving the efficiency of a chilled ammonia CO 2 capture plant through solid formation: a thermodynamic

More information

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT UNIT 47: Engineering Plant Technology Unit code: F/601/1433 QCF level: 5 Credit value: 15 OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT 2 Be able to apply the steady flow energy equation (SFEE) to plant and equipment

More information

Increasing Sales Gas Output from Glycol Dehydration Plants Trina Dreher, SPE, Courtney Hocking, Michael Cavill and Adam Geard, Process Group Pty. Ltd.

Increasing Sales Gas Output from Glycol Dehydration Plants Trina Dreher, SPE, Courtney Hocking, Michael Cavill and Adam Geard, Process Group Pty. Ltd. SPE-171415-MS Increasing Sales Gas Output from Glycol Dehydration Plants Trina Dreher, SPE, Courtney Hocking, Michael Cavill and Adam Geard, Process Group Pty. Ltd. Copyright 2014, Society of Petroleum

More information

CO 2 Capture Utilization and Sequestration (CCUS)

CO 2 Capture Utilization and Sequestration (CCUS) Siemens AG - Energy Sector CO 2 Capture Utilization and Sequestration (CCUS) Copyright Answers for energy. Drivers of CCUS Development Global electricity market : demand for (fossil) electricity still

More information

Fluor s Econamine FG Plus SM Technology For CO 2 Capture at Coal-fired Power Plants

Fluor s Econamine FG Plus SM Technology For CO 2 Capture at Coal-fired Power Plants Fluor s Econamine FG Plus SM Technology For CO 2 Capture at Coal-fired Power Plants Satish Reddy Dennis Johnson John Gilmartin Presented At: Power Plant Air Pollutant Control Mega Symposium August 25-28,

More information

Progress on CO 2 Capture Pilot Plant at RIST

Progress on CO 2 Capture Pilot Plant at RIST IEAGHG/IETS Iron & Steel Industry CCUS & Process Integration Workshop Date: 5th to 7th November 2013 Tokyo Tech Front, Tokyo Institute of Technology, Japan Progress on CO 2 Capture Pilot Plant at RIST

More information

DISPATCHABLE CCS Minimizing the Energy Penalty Costs

DISPATCHABLE CCS Minimizing the Energy Penalty Costs DISPATCHABLE CCS Minimizing the Energy Penalty Costs by Gurpreet Neeraj Dr. Dalia Patino Echeverri, Advisor May 2010 Masters project submitted in partial fulfillment of the requirements for the Master

More information

Modelling of liquid-vapor-solid equilibria in the NH 3 -CO 2 -H 2 O system. Maria G. Lioliou, Statoil ASA

Modelling of liquid-vapor-solid equilibria in the NH 3 -CO 2 -H 2 O system. Maria G. Lioliou, Statoil ASA Modelling of liquid-vapor-solid equilibria in the -CO 2 -H 2 O system Maria G. Lioliou, Statoil ASA Introduction CO 2 capture by amines is state-of-the-art technology Characteristics of a desired technology

More information

Cansolv Technologies Inc.

Cansolv Technologies Inc. 6 C 16 S Cansolv Technologies Inc. About Cansolv Cansolv Technologies Incorporated was formed in 1997 to commercialize and market the CANSOLV SO Scrubbing System developed at Union Carbide Canada. Since

More information

We are IntechOpen, the first native scientific publisher of Open Access books. International authors and editors. Our authors are among the TOP 1%

We are IntechOpen, the first native scientific publisher of Open Access books. International authors and editors. Our authors are among the TOP 1% We are IntechOpen, the first native scientific publisher of Open Access books 3,350 108,000 1.7 M Open access books available International authors and editors Downloads Our authors are among the 151 Countries

More information

Cansolv Technologies Inc. Alberta NOx and SOx Control Technologies Symposium April 9, Rick Birnbaum

Cansolv Technologies Inc. Alberta NOx and SOx Control Technologies Symposium April 9, Rick Birnbaum A Novel SO 2 Scrubbing Process For Industrial SO 2 Emission Control Alberta NOx and SOx Control Technologies Symposium April 9, 2008 Rick Birnbaum rick.birnbaum@cansolv.com OUTLINE Gas Absorption Solutions

More information

Reduction of Emissions from Combined Cycle Plants by CO 2 Capture and Storage

Reduction of Emissions from Combined Cycle Plants by CO 2 Capture and Storage Reduction of Emissions from Combined Cycle Plants by CO 2 Capture and Storage John Davison Project Manager IEA Greenhouse Gas R&D Programme (IEAGHG) The Future Combined Cycle Plant Berlin, 28 th -30 th

More information

Low temperature cogeneration using waste heat from research reactor as a source for heat pump

Low temperature cogeneration using waste heat from research reactor as a source for heat pump National Centre for Nuclear Research in Poland Low temperature cogeneration using waste heat from research reactor as a source for heat pump Anna Przybyszewska International Atomic Energy Agency 14-16

More information

Reforming Natural Gas for CO 2 pre-combustion capture in Combined Cycle power plant

Reforming Natural Gas for CO 2 pre-combustion capture in Combined Cycle power plant Reforming Natural Gas for CO 2 pre-combustion capture in Combined Cycle power plant J.-M. Amann 1, M. Kanniche 2, C. Bouallou 1 1 Centre Énergétique et Procédés (CEP), Ecole Nationale Supérieure des Mines

More information

OPTIMIZATION AND SENSITIVITY ANALYSIS OF POST - COMBUSTION CARBON CAPTURE USING DEA SOLVENT IN A COAL FIRED POWER PLANT

OPTIMIZATION AND SENSITIVITY ANALYSIS OF POST - COMBUSTION CARBON CAPTURE USING DEA SOLVENT IN A COAL FIRED POWER PLANT OPTIMIZATION AND SENSITIVITY ANALYSIS OF POST - COMBUSTION CARBON CAPTURE USING DEA SOLVENT IN A COAL FIRED POWER PLANT Isah Yakub Mohammed Department of Chemical Engineering, Abubakar Tafawa Balewa University

More information

a. The power required to drive the compressor; b. The inlet and output pipe cross-sectional area. [Ans: kw, m 2 ] [3.34, R. K.

a. The power required to drive the compressor; b. The inlet and output pipe cross-sectional area. [Ans: kw, m 2 ] [3.34, R. K. CHAPTER 2 - FIRST LAW OF THERMODYNAMICS 1. At the inlet to a certain nozzle the enthalpy of fluid passing is 2800 kj/kg, and the velocity is 50 m/s. At the discharge end the enthalpy is 2600 kj/kg. The

More information

Gas Turbine Inlet Air Cooling System

Gas Turbine Inlet Air Cooling System Gas Turbine Inlet Air Cooling System Presented by Bob Omidvar Heavy Duty GT - Effects of Ambient Temp 110% 105% 100% 95% 90% 85% 80% 75% 0 5 10 15 20 25 30 35 40 45 GT Inlet Temp (deg C) Heat rate kj/kwh

More information

BLUE OPTION White space is filled with one or more photos

BLUE OPTION White space is filled with one or more photos Driving Innovation Delivering Results BLUE OPTION White space is filled with one or more photos Performance Baseline for Direct-Fired sco 2 Cycles Nathan Weiland, Wally Shelton NETL Chuck White, David

More information

CO 2 -plant Schwarze Pumpe. B. Holling, R. Ritter, (Linde-KCA-Dresden GmbH),

CO 2 -plant Schwarze Pumpe. B. Holling, R. Ritter, (Linde-KCA-Dresden GmbH), First experience in the commissioning i i of the CO 2 -plant Schwarze Pumpe B. Holling, R. Ritter, (Linde-KCA-Dresden GmbH), T. Porsche, M. Biele (Vattenfall Europe Generation AG & Co. KG) 1 st Oxyfuel

More information

ProSimPlus Library (Standard version + rate base option)

ProSimPlus Library (Standard version + rate base option) ProSimPlus Library (Standard version + rate base option) Contents UNIT OPERATIONS... 5 Absorber... 5 Absorber with reboiler... 5 Rigorous two-phase distillation (L-V) with partial condenser and decanter...

More information

Energy Balances and Numerical Methods Design Project. Production of Methyl Tertiary-Butyl Ether

Energy Balances and Numerical Methods Design Project. Production of Methyl Tertiary-Butyl Ether Energy Balances and Numerical Methods Design Project Production of Methyl Tertiary-Butyl Ether Methyl Tertiary-Butyl Ether () is a gasoline additive used to increase octane number that is produced from

More information

Available online at ScienceDirect. Energy Procedia 49 (2014 ) SolarPACES 2013

Available online at  ScienceDirect. Energy Procedia 49 (2014 ) SolarPACES 2013 Available online at www.sciencedirect.com ScienceDirect Energy Procedia 49 (2014 ) 993 1002 SolarPACES 2013 Thermal storage concept for solar thermal power plants with direct steam generation M. Seitz

More information

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa.

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa. Chapters 5, 6, and 7 Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa. 5-1. Steam enters a steady-flow device at 16 MPa and 560 C with

More information

Chapter 8. Vapor Power Systems

Chapter 8. Vapor Power Systems Chapter 8 Vapor Power Systems Introducing Power Generation To meet our national power needs there are challenges related to Declining economically recoverable supplies of nonrenewable energy resources.

More information

Improving energy efficiency in an ammonia plant

Improving energy efficiency in an ammonia plant Improving energy efficiency in an ammonia plant D. Velázquez, F. Rossi and J. Rodríguez of DVA Global Energy Services and F.Galindo of Fertiberia present the results of an energy study carried out in an

More information

Eng Thermodynamics I: Sample Final Exam Questions 1

Eng Thermodynamics I: Sample Final Exam Questions 1 Eng3901 - Thermodynamics I: Sample Final Exam Questions 1 The final exam in Eng3901 - Thermodynamics I consists of four questions: (1) 1st Law analysis of a steam power cycle, or a vapour compression refrigeration

More information

Simple Dew Point Control HYSYS v10. When the simulation is set up the overall PFD should look like the following figure.

Simple Dew Point Control HYSYS v10. When the simulation is set up the overall PFD should look like the following figure. Simple Dew Point Control HYSYS v10 Steps to set up a simulation in HYSYS v10 to model a simple dew point control system consisting of: Gas chiller Flash separator Liquid stabilizer with gas recycle & compression

More information

Dynamic modeling of CO 2 absorption plants for post combustion capture

Dynamic modeling of CO 2 absorption plants for post combustion capture 1st Post Combustion Capture Conference (PCCC1) 17th -19th May 2011, Abu Dhabi Dynamic modeling of CO 2 absorption plants for post combustion capture Development, validation and example case study Andrew

More information

Chapter 1 STEAM CYCLES

Chapter 1 STEAM CYCLES Chapter 1 STEAM CYCLES Assoc. Prof. Dr. Mazlan Abdul Wahid Faculty of Mechanical Engineering Universiti Teknologi Malaysia www.fkm.utm.my/~mazlan 1 Chapter 1 STEAM CYCLES 1 Chapter Objectives To carry

More information

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Ethylbenzene

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Ethylbenzene Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Ethylbenzene We continue to investigate the feasibility of constructing a new, grass-roots, 80,000 tonne/y, ethylbenzene facility.

More information

LV Comparison of methods to utilize CO2 from geothermal gases from Krafla and Þeistareykir

LV Comparison of methods to utilize CO2 from geothermal gases from Krafla and Þeistareykir LV-2015-057 Comparison of methods to utilize CO2 from geothermal gases from and Þeistareykir Report no: LV-2015-057 Comparison of methods to utilize CO2 from geothermal gases from and Þeistareykir May

More information

Item Hydrogen Gas Plant

Item Hydrogen Gas Plant Item 6530. Hydrogen Gas Plant Hydro-Chem Hydrogen Generating Plant 90,000 scfh @ 200 psig. Purity 99.99% Hydrogen generating plant engineered by Hydro-Chem built in 1980. Design capacity is 90,000 scfh

More information

Table 1: Coal polygeneration with CCS (Scheme A) process specification in ASPEN Plus simulation... 2

Table 1: Coal polygeneration with CCS (Scheme A) process specification in ASPEN Plus simulation... 2 Table 1: Coal polygeneration with CCS (Scheme A) process specification in ASPEN Plus simulation.... 2 Table 2: Data extraction and classification for coal polygeneration system (Scheme A).... 3 Table 3:

More information

environmental impacts. These impurity levels may be very heterogeneous and in

environmental impacts. These impurity levels may be very heterogeneous and in CO 2 IMPURITIES Captured CO 2 from an (industrial) activity (such as the CO 2 that will be handled by the CO 2 distribution hub) may contain impurities, which would have practical impacts on CO 2 transport

More information

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: )

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: ) QUIZ TEST-1 Q.1. In a stage of an impulse turbine provided with a single row wheel, the mean diameter of the blade ring is 80cm and the speed of the rotation is 3000rpm. The steam issues from the nozzle

More information

Start-Up of World s First Commercial Post-Combustion Coal Fired CCS Project: Contribution of Shell Cansolv to SaskPower Boundary Dam ICCS Project

Start-Up of World s First Commercial Post-Combustion Coal Fired CCS Project: Contribution of Shell Cansolv to SaskPower Boundary Dam ICCS Project Available online at www.sciencedirect.com ScienceDirect Energy Procedia 00 (2013) 000 000 www.elsevier.com/locate/procedia GHGT-12 Start-Up of World s First Commercial Post-Combustion Coal Fired CCS Project:

More information

CONTROL VOLUME ANALYSIS USING ENERGY. By Ertanto Vetra

CONTROL VOLUME ANALYSIS USING ENERGY. By Ertanto Vetra CONTROL VOLUME ANALYSIS USING ENERGY 1 By Ertanto Vetra Outlines Mass Balance Energy Balance Steady State and Transient Analysis Applications 2 Conservation of mass Conservation of mass is one of the most

More information

Development of the Highly Durable COS Hydrolysis Catalyst for IGCC Gas Clean-up System

Development of the Highly Durable COS Hydrolysis Catalyst for IGCC Gas Clean-up System Development of the Highly Durable COS Hydrolysis Catalyst for IGCC Gas Clean-up System Mitsubishi Heavy Industries, Ltd. Kaori Yoshida 2012 MITSUBISHI HEAVY INDUSTRIES, LTD. All Rights Reserved. October

More information

Post-Combustion Capture (PCC) R&D and Pilot Plant Operation in Australia. IEA GHG 11th Post Combustion CO 2 Capture Network Meeting

Post-Combustion Capture (PCC) R&D and Pilot Plant Operation in Australia. IEA GHG 11th Post Combustion CO 2 Capture Network Meeting Post-Combustion Capture (PCC) R&D and Pilot Plant Operation in Australia IEA GHG 11th Post Combustion CO 2 Capture Network Meeting Vienna, Austria, 20-21 May 2008 Overview Clean Coal Technologies in Australia

More information

Economic Evaluation of Membrane Systems for Large Scale Capture and Storage of CO2 Mixtures

Economic Evaluation of Membrane Systems for Large Scale Capture and Storage of CO2 Mixtures Refereed Proceedings Separations Technology VI: New Perspectives on Very Large-Scale Operations Engineering Conferences International Year 2004 Economic Evaluation of Membrane Systems for Large Scale Capture

More information

Available online at ScienceDirect. Energy Procedia 114 (2017 )

Available online at  ScienceDirect. Energy Procedia 114 (2017 ) Available online at www.sciencedirect.com ScienceDirect Energy Procedia 114 (2017 ) 471 480 13th International Conference on Greenhouse Gas Control Technologies, GHGT-13, 14-18 November 2016, Lausanne,

More information

Plant Utilities and Energy Efficiency CH505

Plant Utilities and Energy Efficiency CH505 Plant Utilities and Energy Efficiency CH505 Teaching Scheme Course code CH505 Course Name Plant Utilities and Energy Efficiency Teaching scheme L T P Credit 3 0 0 3 Process Process is simply a method by

More information

Heat Integration of an Oxy-Combustion Process for Coal- Fired Power Plants with CO 2 Capture by Pinch Analysis

Heat Integration of an Oxy-Combustion Process for Coal- Fired Power Plants with CO 2 Capture by Pinch Analysis CHEMICAL ENGINEERING TRANSACTIONS Volume 21, 2010 Editor J. J. Klemeš, H. L. Lam, P. S. Varbanov Copyright 2010, AIDIC Servizi S.r.l., ISBN 978-88-95608-05-1 ISSN 1974-9791 DOI: 10.3303/CET1021031 181

More information

CANSOLV SO2 Scrubbing System - 10 Years of Reliable Operation Integration with SRU Tail Gas Incineration

CANSOLV SO2 Scrubbing System - 10 Years of Reliable Operation Integration with SRU Tail Gas Incineration CANSOLV SO2 Scrubbing System - 1 Years of Reliable Operation Integration with SRU Tail Gas Incineration NICOLAS EDKINS, NANCY MORETON Cansolv Technologies Inc. (an affiliate of Shell Global Solutions BV)

More information

Energy and economic analysis of the carbon dioxide capture installation with the use of monoethanolamine and ammonia

Energy and economic analysis of the carbon dioxide capture installation with the use of monoethanolamine and ammonia archives of thermodynamics Vol. 36(2015), No. 1, 93 110 DOI: 10.1515/aoter-2015-0007 Energy and economic analysis of the carbon dioxide capture installation with the use of monoethanolamine and ammonia

More information

Reactors and Separations Design Project. Phthalic Anhydride Production

Reactors and Separations Design Project. Phthalic Anhydride Production Reactors and Separations Design Project Phthalic Anhydride Production We are continuing our evaluation of process alternatives for the production of Phthalic Anhydride via the catalytic oxidation of o-xylene.

More information

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Styrene

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Styrene Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Styrene The feasibility of constructing a new, grass-roots, 100,000 tonne/y, styrene plant is being investigated. As part of

More information

Pinch Analysis for Power Plant: A Novel Approach for Increase in Efficiency

Pinch Analysis for Power Plant: A Novel Approach for Increase in Efficiency Pinch Analysis for Power Plant: A Novel Approach for Increase in Efficiency S. R. Sunasara 1, J. J. Makadia 2 * 1,2 Mechanical Engineering Department, RK University Kasturbadham, Rajkot-Bhavngar highway,

More information

The Effects of Membrane-based CO 2 Capture System on Pulverized Coal Power Plant Performance and Cost

The Effects of Membrane-based CO 2 Capture System on Pulverized Coal Power Plant Performance and Cost Available online at www.sciencedirect.com Energy Procedia 00 (2013) 000 000 www.elsevier.com/locate/procedia GHGT-11 The Effects of Membrane-based CO 2 Capture System on Pulverized Coal Power Plant Performance

More information

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Formalin

Fluid Mechanics, Heat Transfer, Thermodynamics Design Project. Production of Formalin Fluid Mechanics, Heat Transfer, Thermodynamics Design Project Production of Formalin Your assignment is to continue evaluating the details of a process to produce 50,000 tonne/y of formalin. Formalin is

More information

OPTIMIZATION OF PARAMETERS FOR HEAT RECOVERY STEAM GENERATOR (HRSG) IN COMBINED CYCLE PLANTS

OPTIMIZATION OF PARAMETERS FOR HEAT RECOVERY STEAM GENERATOR (HRSG) IN COMBINED CYCLE PLANTS OPTIMIZATION OF PARAMETERS FOR HEAT RECOVERY STEAM GENERATOR (HRSG) IN COMBINED CYCLE PLANTS Muammer Alus, Milan V. Petrovic University of Belgrade-Faculty of Mechanical Engineering, Laboratory of Thermal

More information

2. TECHNICAL DESCRIPTION OF THE PROJECT

2. TECHNICAL DESCRIPTION OF THE PROJECT 2. TECHNICAL DESCRIPTION OF THE PROJECT 2.1. What is a Combined Cycle Gas Turbine (CCGT) Plant? A CCGT power plant uses a cycle configuration of gas turbines, heat recovery steam generators (HRSGs) and

More information

Understand boiler performance characteristics. Use these suggestions when buying, designing or optimizing steam generators

Understand boiler performance characteristics. Use these suggestions when buying, designing or optimizing steam generators Understand boiler performance characteristics Use these suggestions when buying, designing or optimizing steam generators V Ganapathy, ABCO Industries, Abilene, An understanding of the major differences

More information

Carbon Clean Combined Heat and Power Production from micro Gas Turbines: Thermodynamic Analysis of Different Scenarios

Carbon Clean Combined Heat and Power Production from micro Gas Turbines: Thermodynamic Analysis of Different Scenarios Available online at www.sciencedirect.com ScienceDirect Energy Procedia 142 (2017) 1622 1628 www.elsevier.com/locate/procedia 9th International Conference on Applied Energy, ICAE2017, 21-24 August 2017,

More information

Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project. Production of Ethanol

Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project. Production of Ethanol Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project Production of Ethanol Your assignment is to continue evaluating the details of a process to produce 30,000 tonne/y of ethanol from ethylene.

More information

Fundamental Investigation Of Whole-Life Power Plant Performance For Enhanced Geothermal Systems

Fundamental Investigation Of Whole-Life Power Plant Performance For Enhanced Geothermal Systems Purdue University Purdue e-pubs International Refrigeration and Air Conditioning Conference School of Mechanical Engineering 2016 Fundamental Investigation Of Whole-Life Power Plant Performance For Enhanced

More information

ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE AT COVANTA S HAVERHILL FACILITY

ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE AT COVANTA S HAVERHILL FACILITY Proceedings of the 18th Annual North American Waste-to-Energy Conference NAWTEC18 May 11-13, 2010, Orlando, Florida, USA Paper Number: NAWTEC18-3563 ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE

More information

Facilitating CO 2 capture at a cement plant. Dr Dennis R Van Puyvelde Chemeca 2013, Brisbane 29 Sep 2 Oct 2013

Facilitating CO 2 capture at a cement plant. Dr Dennis R Van Puyvelde Chemeca 2013, Brisbane 29 Sep 2 Oct 2013 Facilitating CO 2 capture at a cement plant Dr Dennis R Van Puyvelde Chemeca 2013, Brisbane 29 Sep 2 Oct 2013 Background Emissions from Cement Production Direct Emissions/ Pyroprocessing Limestone emissions

More information

Raymond A. Adomaitis. March 7, 2012

Raymond A. Adomaitis. March 7, 2012 Raymond A. Adomaitis March 7, 2012 To be covered: Class syllabus (http://www.isr.umd.edu/ adomaiti/ench446), grading Team selection (4 members per team) Initial project description Approximate schedule

More information

EFFECT OF AMBIENT TEMPERATURE, GAS TURBINE INLET TEMPERATURE AND COMPRESSOR PRESSURE RATIO ON PERFORMANCE OF COMBINED CYCLE POWER PLANT

EFFECT OF AMBIENT TEMPERATURE, GAS TURBINE INLET TEMPERATURE AND COMPRESSOR PRESSURE RATIO ON PERFORMANCE OF COMBINED CYCLE POWER PLANT EFFECT OF AMBIENT TEMPERATURE, GAS TURBINE INLET TEMPERATURE AND COMPRESSOR PRESSURE RATIO ON PERFORMANCE OF COMBINED CYCLE POWER PLANT Harendra Singh 1, Prashant Kumar Tayal 2 NeeruGoyal 3, Pankaj Mohan

More information

NEW RECYCLE PROCESS SCHEME FOR HIGH ETHANE RECOVERY NEW PROCESS SCHEME FOR HIGH NGL RECOVERY INTRODUCTION. Abstract PROCESS FUNDAMENTALS

NEW RECYCLE PROCESS SCHEME FOR HIGH ETHANE RECOVERY NEW PROCESS SCHEME FOR HIGH NGL RECOVERY INTRODUCTION. Abstract PROCESS FUNDAMENTALS Author: Jorge Foglietta, ABB Randall Corporation Tel (713) 821-4313, Fax (713) 821-3544 Mailing Address: Randall Division ABB Lummus Global Inc. P.O. Box 420087 Houston, Texas 77242-0087 NEW PROCESS SCHEME

More information