VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED ENVIRONMENTAL MANAGEMENT PLAN

Size: px
Start display at page:

Download "VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED ENVIRONMENTAL MANAGEMENT PLAN"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject: Mai Chau 110 kv substation and 35 kv power line supply for construction of Trung Son hydropower project VIETNAM ELECTRICITY TRUNGSON HYDROPOWER COMPANY LIMITED E2248 v14 ENVIRONMENTAL MANAGEMENT PLAN MAI CHAU 110 KV SUBSTATION AND 35 KV POWER LINE SUPPLY FOR CONSTRUCTION OF TRUNG SON HYDROPOWER PROJECT Ha Noi, January 2013 Environmental Management Plan (EMP) 1

2 Table of Contents 1. PROJECT DESCRIPTION AND SCOPE OF WORK Construction of Mai Chau 110 kv Substation and its 68 m Connection Line Construction of 35kV Power Line Supply for Construction of Trung Son HPP Supplement of Materials and Equipment for the Subproject Transportation of Construction Materials and Equipment Number of Workers and Workers Camps Subproject Schedule Total of Subproject Investment Some Pictures of the Subproject Site POLICY AND REGULATION FRAMEWOR Regulations of Vietnamese Government The World Bank Safeguard policies ENVIRONMENTAL SCREENING Screening for Eligibility of Subproject Siting Potential Impacts MITIGATION MEASURES EMERGENCY ACTION PLAN COMMUNITY CONSULTATION AND INFORMATION DISCLOSURE ENVIRONMENTAL MONITORING PLAN ARRANGEMENT FOR EMP IMPLEMENTATION REPORTING PROCEDURE CAPACITY BUILDING PLAN ESTIMATED COST FOR IMPLEMENTATION OF EMP REFERENCES APPENDI 1 LIST OF MEMBERS PREPARING THE REPORT APPENDI 2: TOR for Construction Supervision Consultant (CSC) Environmental Management Plan (EMP) 2

3 ABBREVIATIONS DEP Distribution Efficiency Project ECOPs Environmental Code of Practices EIA Environmental Impact Assessment EMP Environmental Management Plan EG Environmental Guideline EVN Electricity of Vietnam HHs Households HPP Hydropower project PAHs Project Affected Households PECC4 Power Engineering and Consulting Company 4 PMU Project Management Unit PC Power Company ROW Right of Ways WB World Bank Environmental Management Plan (EMP) 3

4 1. PROJECT DESCRIPTION AND SCOPE OF WORK GENERAL DESCRIPTION This is a subproject under the Trung Son hydropower project financed by the World Bank. Reasons of Subproject proposals: Trung Son hydropower plant will be constructed on the Ma River, in the territory of Trung Son commune, Quan Hoa district, Thanh Hoa province. Installed capacity of the hydropower project is 260 MW, annual electricity produced will be 1056 GWh. Trung Son hydropower project will bring benefit in term of power generation and flood control. Construction of the subproject Mai Chau 110 kv substation and 35 kv power line supply for construction of Trung Son hydropower project is aimed to meet the local power demand, supply electricity for construction of Trung Son hydropower project and supply electricity for ressettlement sites. The subproject is consisted of two components: - Mai Chau 110 kv substation and connections; - 35kV power line supply for construction of Trung Son hydropower project ( km). The construction of Mai Chau 110 kv substation and km of 35 kv power line can cause negative impacts on the environment and local communities during preconstruction phase, construction phase and operation phase. In order to ensure that potential negative impacts are identified and mitigated during subproject implementation and that the subproject complies with the Environmental Assessment policy (OP/BP 4.01) of the WB, an Environmental Management Plan (EMP) of the subproject has been prepared in compliance with the Environmental Guideline (EG) prepared under Trung Son hydropower project. This EMP is prepared with reference to Environmental Management Framework (EMF) of the Distribution Efficiency Project sponsored by the WB. Application of some items of EMF is suitable in this case due to similarities of the Subproject and other subproject under DEP. This EMP includes: the subproject description, legal and policy frameworks, applicable environmental technical standards and regulations, potential negative impacts, proposed mitigation measures to be implemented prior and during construction and operation, and implementation arrangements. The EMP also includes Environmental Codes of Practice (ECOP) that will be integrated into bidding and contractual documents, monitoring and supervision during the implementation. Environmental Management Plan (EMP) 4

5 EIA of Trung Son hydropower project (including the subproject Mai Chau 110 kv substation and 35 kv power line supply for Trung Son HP) was approved by Ministry of Environment and Natural resource by Decision N0 1257/QD-BTNMT dated 17/6/2008 on approval of EIA for Trung Son hydropower project. PROJECT DESCRIPTION 1.1. Construction of Mai Chau 110 kv Substation and its 68 m Connection Line Alternatives for subproject location. General requirements on Subproject s locations Selection of location for Mai Chau 110 kv substation is made based on the following technical and financial requirements: - To comply with Master plan for power development No 6 and comply with Local socio-economic plannings; - Technical requirement: To ensure to have enough area for the substation and power line connections. The location should be optimized in term of having minimum power loss for power grid; - Natural condition requirement: Geological pattern is suitable for substation construction, climate is suitable. Topography is preferably to be flat, open to enable access and connections with the power grid. - Location should be convineinent for construction, transportation of substation s equipment during operation phase. - Minimize compensation and ressettlement, avoid impact in cultural and historical valuable sites. Minimize impact on local landscape and views. - Minimize loads on ground leveling. - Make use of the existing facilities such as road, power source, water source. - Minimize environmental impacts caused by the substation to surrounding areas. Substation location alternatives Based on the above-mentioned requirement, technical consultants (PECC4) have investigated and proposed 3 alternatives described bellow: - Option 1: Mai Chau 110 kv substation will be constructed on rice and dry crop field of Na Quan (Tong and Dau villages), Tong Dau commune, Mai Chau district, Hoa Binh province. - Option 2: Mai Chau 110 kv substation will be constructed on agricultural alnd of Vang village, Mai Chau township, Mai Chau district, Hoa Binh province. - Option 3: Mai Chau 110 kv substation will be constructed on the agricultural land next to the existing Mai Chau 35 kv substation in Mai Chau township, Mai Chau district, Hoa Binh province. Environmental Management Plan (EMP) 5

6 Among these three options, the option 3 having connecting 110 kv power line overpassing deeply in center of Mai Chau township. This affect affect development of Mai Chau township so there will be many disadvantages to local development planning. Beside that, the option 3 will not comply with Decision 5638/QDD-BCT dated 22/20/2008 of MOIT on Decision on amandement of Power Development Planning for Hoa Binh Province in period with vision to So option 3 is excluded before go to further considerations. Table 1.1. Comparison of alternatives for Mai Chau 110 kv substation location Aspects to be considered Planning issue Natural conditions, work load for ground leveling and substation foundation Connection scale and possibilities for extension Existing infrastructures Environmental and social impacts Financial issue Comparison of power loss when connects to the power grid Consultation with local authorities Selected alternative Option 1 (Tong Dau commune) This option is not conflict with other local planning. - Area is open, quite flat, and dry. At the present time, the area is 1- harvest rice field. - Convenient for connections with 110 kv, 35 kv with possibility to connect with 22 kv. Extension of the substation is possible. - Convenient for construction and management during operation phase. - Limited environmental impacts. Limited resettlement and compensation. Higher investment cost Investment cost of the option 1 is about 2 billion VND due to: - Length of the access road to the substation is 300 m longer; - Length of 35 kv supply for Trung Son HPP is 1,800 m longer. Option 2 (Mai Chau township) Near planned residential areas of Mai Chau township. - Area is open, quite flat, and dry. At the present time, the area is 2-harvest rice field. - Connections are limited because of planned residential area. There is limited possibility of the subproject extension. - Convenient for construction and management during operation phase. - Larger impacts on rice field in the substation location as well as in connecting power lines. Lower investment cost There is no difference between two options. During site investigations, Consulting company PECC4 has worked and consulted with relevant authorities in Hoa Binh province. Even the option 1 having higher investment cost than the option 2 (2.05 billions), but this location is more suitable for the socio-economic planning of Hoa Binh province. Local authorities approve the Option 1. Environmental Management Plan (EMP) 6

7 Specific description of substations by selected location Table 1.2 Project Scope and Site Summary New 110/35kV Substation and Connection lines Name of 110 kv sub-station, other substations and length of ROW: Location of each substation (specify name of commune and district) Mai Chau 110 kv substation ROW width and length An acquired area is 8,336.0 m 2. - Width of the ROW of the connection is 4 m. Length is 68 m. List communes where transmission lines come through, by district Hoa Binh province, Mai Chau district, Tong Dau commune - Total acquired land for the substation including access road is 8,336.9 m 2 Total land area acquired for sub-stations construction and existing land use - Total land permanently acquired for foundations of towers of the 68 m connection line is m 2 List by sub-station, total land area include access road Attach a simplified layout showing existing land use within 50 m from the boundaries of each substation Is there any sub-station or ROW located within 3 km from natural reserves or forests...? Is there any sub-station or ROW located within 300m from historical sites, temples, pagodas or other cultural structure? Is there any sub-station or ROW located within 300m from to a commune centre rung (CPC, school, market, clinic etc) or within 2 km from a residential cluster? Yes No If yes, declare in (6) Yes No If yes, declare in (6) Yes No If yes, declare in (6) List of environmental sensitive structures claimed in (3) (5) No. Name of sub-station/row location Environmental sensitive objects (name and brief Distance Environmental Management Plan (EMP) 7

8 1 - Mai Chau 110 kv substation and its connection line - Tong Dau primary school The school is about 150 m far from Mai Chau 110 kv substation. The first part of 35 kv supply power line is going along the edge of the school. Mai Chau 110 kv subsation is proposed to be built in the land used for 1-harvest rice field and dry crop cultivation on Tong Dau commune, Mai Chau dictrict of Hoa Binh province. - North of the proposed subsation is bordered with field for rice and dry crop cultivation; - South of the substation is field and about 100 m far from Tong Dau primary school. - East of the substation is borderd with national road N West of the substation is field and is about 100 m far from 110 kv Hoa Binh- Moc Chau power line and 35 kv Mai Chau- Hoa Binh power line. Total acquired land for the substation is 8,336.0 m2. Of which: - Land for the substation and access road is: 7,336.0 m 2. - Land for resting house of operating team is: 1,000.0 m 2. An access road to the substation An access road to the substation is m in length connecting substation to the national road 15. This road is made by reinforced concrete, 4 m wide. Slope of the road is 2% in both sides. The pavement is 1.5 m and ROW of the road is 6 m (calculated from the outest point of the pavement). The road is constructed by widening of the existing inter commune road in Tong Dau commune. At the present time, this inter commune road is also passing Tong Dau primary school. From the widening point to Tong Dau primary school is about 150 m. During construction, widening of the road might cause short term environmental impacts on the traffic in the inter commune road. In long term, subproject s vehicles will use only the extended road for transportation so no impact on local traffic will occur. Water supply system Water used for living and construction will be purchased from the water supply utility of Mai Chau district. Water supply pipe is available at 100 m far from the substation. Water for construction will be supplied to construction sites by tank truck and plastic water pipes. During operation phase, water will be supplied through zinc-coated steel pipe (34 Environmental Management Plan (EMP) 8

9 mm in diameter). Water will be stored in 10m 3 reinforced cisterns and will be pumped up to tank fixed in roof of operating house and resting house. Water drainage system - Domestic water will be collected to underground cistern and will self soaked to the soil. - Drainage system for the substation s surface water run off: rain water will be drained out through designed slope. Collecting holes are designed along road inside the substation. Holes are connected by PVC 150. By this PVC pines, rain water is collected and discharged to the existing water canal outside the substation. Table 1.3. Main Work Load for Construction of Mai Chau Subsation No Work Unit Amount 1 Remove vegetation cover (0.1 m thick) m Soil excavation for foundation m Soil leveling m 3 7,802.5 Basin for oil collection in emergency Basin for oil collection in emergency will be constructed under each transformer. Basin will be constructed by reinforced concrete. This basin is under grounded and has a volume about 22 m 3. This volume is enough to collect oil in the designed transformers (including the transformer reserved to install in later phase from 110 kv - 25MVA to 110 kv - 40 MVA). Walls (0.5 m high) around foundation of transformers are constructed to avoid oil spill. In case, accident of oil spill is occurred, spilled oil will be collected through steel pipe Ф200, 5mm thick. Fire prevention and protection system There are 2 water tanks (3 m 3 /each tank) and 6 sand containers (1m and 1m in height). Water tanks and sand containers are allocated along road and near inflammable subjects such as transformers, operating house. Beside these, there are fire extinguishers (powder type, CO 2 type) and manual tools for fire control are equipped. Environmental Management Plan (EMP) 9

10 Scheme 1. Sketch map of Mai Chau 110 kv Substation Environmental Management Plan (EMP) 10

11 110 kv connection line Start point: in between tower N (the point is 40.3 m far from tower No 187) of the existing 110kV Hoa Binh - Moc Chau power line. End point: Gate tower of the proposed Mai Chau 110 kv substation; Length: 68m. Topography in the area (that the connection line will overpassing) is quite flat. Land use pattern in the ROW is rice and dry crop field. The connection line will overpass land of Tong Dau commune, Mai Chau district, Hoa Binh province. Route of the connection line is agreed by People committee of Hoa Binh province by document 285/UBND-CT dated 09/3/ Construction of 35kV Power Line Supply for Construction of Trung Son HPP (19,427 km). Table 1.4. Project scope and Site Summary 1. Total length of power lines km 2. Name of communes where powerlines come through Commune in Hoa Binh province, Mai Chau district: Tong Dau, Mai Chau township, Chieng Chau, Mai Ha, Van Mai. Thanh Hoa province, Quan Hoa district: Phu Thanh - 3 m 3. Width of ROW 4. Is there any ROW located within 3 km from natural reserves or forests...? 5. Is there any ROW located within 300m from historical sites, temples, pagodas or other cultural structure? 6. Is there any ROW located within 300m from to a commune centre (CPC, school, market, clinic etc) or within 2 km from a residential cluster? - Total land permanently acquired for foundations of km of 35 kv power line is: 3, m 2 Yes No If yes, declare in (7) (Note: the power line will overpass planted bamboo Luong forest of the local people). Yes No If yes, declare in (7) Yes No If yes, declare in (7) Environmental Management Plan (EMP) 11

12 7. List of environmental sensitive structures claimed in (4) (6) No Name of ROW location Environmental sensitive objects (name and brief description) Distance 1 - Start point to G1 - Tong Dau primary school The school is about 150 m far from Mai Chau 110 kv substation. 2 - Section G3-G4 - Residential area of Mai Chau township - The power line is about 200 m far from the residential area. 3 - Section G7 G8 - Centre of Chieng Chau commune - 70m 4 - Section G15 G16 - National road N o 15 in Mai Ha commune area - The power line is about 50 m far from National road N o Section G21 G22 - Admistrative area of Van Mai commune - 70m 6 - Section G25 - The power line will overpass ia stream - The power line will overpass ia stream - The power line will 7 - Section G25 to the end point - Bamboo Luong forest planted by local people for commercial purpose overpass bamboo Luong forest planted by local people for commercial purpose Route of the 35 kv power line was approved by People committee of Hoa Binh province and Quan Hoa district agreed. The power line will mainly go along national road No 15, along the road used for construction of Trung Son HPP, along inter commune road. The power line will mainly overpass rice field. Main characters of the power line are described in Table 1.4. Table 1.5. Main Characteristics of the 35 kv Power Line No Characteristics Information 1 Starting point 35 kv feeder of Mai Chau 110 kv Environmental Management Plan (EMP) 12

13 No Characteristics Information substation 2 Ending point Tower No 59 of 35 kv power line supply for Ban Uon 110 kv substation 3 Voltage level 35 kv 4 Number of phases 01 5 Length 19,427 m 6 Number of direction changes 38 7 Number of houses within ROW 0 8 Length of part overpassing rice field 11,461 m 9 Length of part overpassing fruit gardens 145 m 10 Length of part overpassing planted eucalyptus 210 m 11 Length of part overpassing planted bamboo Luong forest 3,759 m 12 Length of part overpassing dry crop fields 2,403 m 13 Length of part overpassing unused land 1,429 m 14 Number of times overpassing streams 3 times 15 Number of times ovepassing road <10 m 4 times 16 Number of times ovepassing road <5 m 21 times The 35 kv power line is composed of two main sections as described bellows: - Section 1: From the starting point to G26 (15,396 m in length). The power line is started from Mai Chau 110 kv/30 kv substation in Tong Dau commune (Mai Chau district, Hoa Binh province). The power line will overpass Mai Chau- Hoa Binh 35 kv power line and Hoa Binh- Moc Chau 110 kv power line. In this section, the power line will go along national road N o 15 (in the right hand side). Distance from the power line to the national road is ranging from 250 m to 500 m. Turnings (change direction of the route) are required to avoid residential areas. Topography of the area is quite plain. Main land use patterns are fruit tree gardens, rice and dry crop fields, hills with bamboo Luong planted forest. The power line will overpass land of Tong Dau commune, Mai Chau Township, Chieng Chau, Mai Ha, Van Mai of Mai Chau district, Hoa Binh province. Environmental Management Plan (EMP) 13

14 - Section 2: From G26 to tower No 59 of 35 kv power line supply for Ban Uon 110 kv substation (under RE 2 WB loan). This section is 4,031 m long. From G26, the power line will turn left and go along inter commune road to reach to construction site of Trung Son HPP. Distance of the power line to this inter commune road is ranging from 100 m 300 m. Topography of this section is quite complex with high hills and deep creeks. Main land use pattern is bamboo Luong forest mixed with dense shrubs. From G37, the power line will connect with 35 kv power line of RE 2 project in Quan Hoa district of Thanh Hoa province. The power line will overpass land of Van Mai commune of Mai Chau district (Hoa Binh province) and Phu Thanh, Trung Son communes of Quan Hoa district (Thanh Hoa province) Supplement of Materials and Equipment for the Subproject Sand, rocks, gravels, cements etc... are supplied by local suppliers. Other materials will be provided from warehouse of PMU at Moc Chau and Co Luong communes Transportation of Construction Materials and Equipment Long-way transportation Cars will be used for transportation of materials, equipment from ware house of PMU to subproject s construction sites as well as for transportation within construction sites. Concrete centrifugal towers will be purchased from Hoa Binh province will be separated according to type of towers and provided to each site as required. Loading and unloading materials and equipment will be done manually or by cranes. Local suppliers will directly transport materials to gathering points along the power line. Transportation within the construction sites National road, provincial road, inter-district and inter commune roads will be used for transportation of materials and equipment among the construction sites. An average transportation is 15 km. Short-way transportation From gathering points, materials and equipment are transported manually or halfmanually to construction sites. An average distance for short way transportation is 300 m Number of Workers and Workers Camps Mai Chau 110 kv substation and connection line: Warehouse, camp are proposed bo be located in reserve area for the second transformer in the substation area. These structures will be build by assembling steel structures to easily dismount in later phase. Environmental Management Plan (EMP) 14

15 Foundations of these warehouse and camp will be build by bricks. Colums, beams will be made by wood or steel. Roof will be made by corrugated iron sheets (or cement sheets). Walls will be made by plywoods. Ground will be montared by cement to ensure cleaness, hygenity. Camp will consist of living area, office area... Number of workers for construction of the substation and 68 m connection line is as bellows: Direct worker : 60 people In-direct worker : 07 people Site managers : 05 people 35 kv power line: There will be two construction team. Each team will consist of 40 people. These workers will hire houses of local people for their camps Subproject Schedule Some of main milestones of Mai Chau 110 kv substation is: - Preparation of technical design and approval : 01/ / Preparation of Request for Proposal for Bidding : 9/ / Ground breaking : 12/ Completion and commissioning : 3 rd quarter 2013 Table 1.6. Estimated Schedule for the 35 kv power line No Work Days after commencement 1 Preparation of construction site 2 Construction of foundations 3 Tower erections 4 Cable pulling 5 Commissioning Environmental Management Plan (EMP) 15

16 1.7. Total of Subproject Investment Table 1.7. Total of Subproject Investment Item Substation and connection line 35 kv power line Unit: VND Total 1. Construction cost 16,107,900,270 9,914,755,000 26,022,655, Equipment cost 21,841,810, ,367,000 22,217,177, Construction investment consulting cost 3,207,180, ,720,000 3,968,900, Other cost 2,008,482, ,257,000 2,130,739, Contingency 3,453,229,995 1,136,115,000 4,589,344,995 Grand total Environmental Management Plan (EMP) 16

17 1.8. Some Pictures of the Subproject Site Location of Mai Chau 110 kv substation The substation is proposed to be build in rice, dry crop field The nearest house is about 200 m far from the subsation location There is an access road to the substation area. Tong Dau primary school is in the right This road leads to Tong Dau primary school handside of the road This road will be widened to create an access road to the Mai Chau substation. Section from G3- G4 (in Mai Chau township) The power line will overpass field for rice and dry crop cultivation of Mai Chau township Environmental Management Plan (EMP) 17

18 Small road turning from national road No 15 to near section G3- G4. Residential area of Mai Chau township us about m far from the power line Section from G7- G8 (Lac village - Chieng Chau commune) The power line will overpass rice field far from residential area. There is a small stream near rice field. This stream is about 100 m far from the foundations of the power line. At this section, the power line will overpass inter commune road Environmental Management Plan (EMP) 18

19 Section from G15- G16 (Van Mai commune) The power line will overpass rice field The power line will in the right hand side and along national road N o 15 and is about 50 m far from this road. Section from G 18 G19 (Khoe village, Van Mai commune) The power line will overpass rice field, small stream The power line will overpass inter commune road, bridges. There are houses scattered in the subproject area (about 50 m- 70 m far from the power line) Section G21 G22 (Van Mai commune) The power line will overpass rice field The power line will overpass inter commune road Environmental Management Plan (EMP) 19

20 The power line will go near primary school, administrative house of Van Mai commune (about 70 m far) The power line is about 70 m far from residential area. Section G25 G26 (Van Mai commune) The power line will overpass ia stream (6 m wide) A chain bridge above ia stream (near the power line position). Section from G26 to end point The power line will overpass bamboo Luong planted forest of the local people. Environmental Management Plan (EMP) 20

21 2. POLICY AND REGULATION FRAMEWOR 2.1. Regulations of Vietnamese Government The following laws and regulations in Vietnam are applied for the subproject: Environment Protection Law 52/2005/QH11 passed by the National Assembly dated on 29/11/2005 regulating responsibilities of individuals and organizations regarding environmental protection. Law on Cultural Heritage No. 28/2001/QH10. Decree no. 29/2011/NÐ-CP dated 18 April 2011 regarding regulations on strategic environmental assessment, environmental impacts assessment and environmental protection commitments. Circular no. 26/2011/TT-BTNMT dated 18 July 2011 detailing some articles of Decree no. 29/2011/ND-CP dated 18 April 2011 regarding regulations on strategic environmental assessment, environmental impacts assessment and environmental protection commitments. Decree 106/2005/ND-CP dated 17 th August 2005 on detailed regulations and guidance on implementation of some Articles of the Law on Electricity related to safe protection of high voltage networks. Decree 81/2009/ND-CP dated 12 th October 2009 on revision and addition of some Articles of Decree 106/2005/ND-CP dated 17 th August 2005 on detailed regulations and guidance on implementation of some Articles of the Law on Electricity related to safe protection of high voltage networks. Circular no. 12/2011/TT-BTNMT dated 14 April 2011 regarding the management of hazardous wastes. National Technical Regulations: QCVN01:2009/BYT - National technical regulations on quality of drinking water; QCVN02:2009/BYT - National technical regulations on quality of domestic water; QCVN08:2008/BTNMT - National technical regulations on quality of surface water; QCVN09:2008/BTNMT - National technical regulations on quality of groundwater; QCVN05:2009/BTNMT - Air quality Standards for ambient air quality; QCVN06:2009/BTNMT - Air quality Maximum allowable concentration of hazardous substances in the ambient air. EVN Guidance no. 2623/CV-EVN KHCN&MT, dated 28 May 2007 regarding the management and pollution prevention and exposure to PCBs. Environmental Management Plan (EMP) 21

22 2.2. The World Bank Safeguard policies The environmental screening according to criteria described in the EG for subproject has been carried out and the result shows that the WB policies on Environmental Assessment (OP 4.01) and Involuntary Resettlement (OP 4.12) are triggered for this subproject. The subproject has also to comply with the Bank s requirement on Public Consultation and Information Disclosure Policy. The implementation of policy on Involuntary Resettlement (OP 4.12) is addressed in a separate safeguard document. 3. ENVIRONMENTAL SCREENING 3.1. Screening for Eligibility of Subproject Siting Subproject name: Province: Hoa Binh, Thanh Hoa 110 kv Mai Chau substation and 35 kv power line supply for Trung Son HPP District: Mai Chau (Hoa Binh province); Quan Hoa (Thanh Hoa province). Commune: Tong Dau, Mai Chau township, Chieng Chau, Mai Ha, Van Mai commune (Mai Chau- Hoa Binh) and Phu Thanh commune (Quan Hoa, Thanh Hoa). Table 3.1. Environmental Screening for Subproject Eligibility 1. Subproject's sitting: Screening Question Construction Operation Is the Subproject site adjacent to or within any of the following environmental sensitive areas? Yes No Yes No Cultural heritage site Protected areas such as National Parks, Nature Reserves, Bio-conservation areas, bird yards, mangrove forest etc. Wetlands Forests 1 Estuaries 1 Planted bamboo Luong forest Environmental Management Plan (EMP) 22

23 Screening Question Construction Operation Buffer zone of Protected areas Rivers and reservoirs Canals and irrigation system Agricultural land 2. Potential environmental impacts Will the Subproject cause: Encroachment on historical/cultural areas Encroachment on critical ecosystem (e.g. sensitive or protected area, national park, nature reserve etc...) Disfiguration of landscape and increase waste generation Removal of vegetation cover or cut down of trees resulted from clearance at the sub-station and along ROW? Change of surface water quality or water flows Increase water turbidity due to run- off and erosion Waste water from camping sites is directly discharged to the surface water resources or not? Construction waste is directly discharged to the surface water or not? Increase the dust level? Increase noise and/or vibration? Permanent land acquisition Temporary land acquisition Resettlement of households? If yes, how many households? Would the resettlement site is environmentally and/or culturally sensitive Environmental Management Plan (EMP) 23

24 Screening Question Construction Operation Is there any risk of disease dissemination from construction workers to the local people (and vice versa)? Is there any potential for conflict between construction workers and local people (and vice versa)? Are explosive and hazardous chemicals used within the Subproject? In the past, there was any accident incurred due to landmines or explosive materials remaining from the war? Will Subproject's construction cause disturbance to the transportation in the Subproject's site? Subproject's construction will cause any damage to the existing local roads, bridges or other rural infrastructures? Will soil excavation during Subproject's construction cause soil erosion? Will Subproject need to open new access roads? 2 Will Subproject cause fragmentation of habitat of flora and fauna? Will Subproject cause impact on air quality? Will Subproject cause accident risks for workers and community during construction phase? Will Subproject generate hazardous wastes including PCBs from the replacement of transformers? Will Subproject cause risk to safety and human health (electric and magnetic fields, electric shock etc.)? 2 Access road to the substation. Beside this road there will not be any access road need to create for ROW maintenance Environmental Management Plan (EMP) 24

25 Conclusion: Since implementation of the subproject would mainly cause land acquisition, increased dust generation, air pollution, and domestic waste production during the construction phase. However, these impacts are not significant, temporary, and localized, and can be mitigated available mitigation measures. During the operational phase the main impacts would be visual, due to the alteration of the previously existing landscape, and potentially on the avifauna, who is at risk of collision and electrocution. However, as the TL follows exiting infrastructure and the height of pylons and wires is moderate; these impacts are anticipated to be low. Therefore, the subproject is assessed as B environmental category according to the World Bank s operational policy OP4.01 on environmental assessment, requiring an ESIA and an EMP as analytical and mitigation instruments. Environmental Management Plan (EMP) 25

26 3.2. Potential Impacts Table 3.2. Potential impact No Impact Magnitude Duration Description of the impacts Evaluation of impacts Pre-construction phase 1 Permanent and temporary Medium Short Total permanent land acquisition of the Subproject is as follows: Medium and mitigable land acquisition Long - Mai Chau substation: 8,336.0 m 2 ; - The land acquired for pole foundations of the power line is m 2. - Area of land within ROWs is 115,482 m 2. This land is not acquired but trees higher than 4 m can not planted. Total temporary land acquisition is 27,728 m 2, of which rice field land is m 2 ; land for dry crops is 4,806 m 2. 2 Impact on Subproject affected household 3 Loss of vegetation due to land clearance for the substation Medium Long term - Total number of HHs affected by the Subproject is 306 HHs; - Affected types: land loss for foundation, substation; having house within ROWs; loss of trees and crops, rice; trees will be damaged during cable pulling. Medium Long - In Hoa Binh province, the substation and power line are located and overpassed mainly rice fields. In Thanh Hoa province, the power line will overpass area planted by bamboo Luong forest. Number of Luong trees will need to be cut is Some other trees will also need to be cut for land acquisition, they are: 24 fruit trees, 25 eucalyptus trees, etc. Medium Medium 4 Health risk due to None None - The Subproject would not use chemicals or explosives; None Environmental Management Plan (EMP) 26

27 No Impact Magnitude Duration Description of the impacts Evaluation of impacts explosives, hazard chemical - Subproject sites were cleared for landmine after war time and used for agriculture for a long time. 5 Impact on historical and cultural properties Construction phase 6 Impact in Tong Dau primary school None None - There are no historical and cultural resources near and inside the Subproject area Medium Short - Tong Dau primary school is about 150 m far from the proposed substation. Therefore, the school might be affected by noise, dust, vibration during construction time. However, these impacts will last only in a short period of time (about 3 months, when ground leveling and civil work are occurred). These impacts can be mitigated by application of mitigation measures as specified in Chapter 4. - An access road to the substation is created by widening an inter commune road of Tong Dau commune. This inter commune road is also passing Tong Dau primary school. So transportation of pupils and teachers might be affected during construction time. This impact will mostly occur during ground leveling, road construction, civil work for substation construction. When the access road is completed, subproject s vehicles will use only the new road. So impact on local traffic will not be considerably affected. None Medium and Mitigable 7 Surface water contamination. Medium Short - Ground leveling, construction of foundation, substation and substation s access road might washout soil, rock to the surface water Medium Mitigable and system of region; Environmental Management Plan (EMP) 27

28 No Impact Magnitude Duration Description of the impacts Evaluation of impacts - Mai Chau 110 kv substation is about 50 m far from a small stream. This stream is going along national road N o 15. This is the only one surface water source near the substation. - The 35 kv power line will 2 times overpass ia stream and one time overpass other small stream in Chieng Chau commune. Width of these steams at the over passing point is from 4-7 m. Beside these, the power line will not overpass other surface water such as river, stream, and reservoir. - Construction of foundations near the streams might cause risk on water contamination due to debris, construction materials washed out to the water bodies. - The Subproject area is quite flat; therefore, the risks of erosion, soil and construction materials runoff are not high. - Excavation is planned to do in dry season. Excess soil will be reused to fill in the poles foundations. Thus there will be no soil, rock left after the Subproject implementation. - No tower will be constructed in the above mentioned streams. - Thus the impact on surface water pollution in the Subproject area is medium and can be mitigated. 8 Noise and vibration Medium Short - Noise and vibration are caused by: equipment, material transportation, Subproject's vehicles, pole's erection and cable's pulling, generators (if there are any); Medium and mitigable Environmental Management Plan (EMP) 28

29 No Impact Magnitude Duration Description of the impacts Evaluation of impacts - About 100 m far from the substation is Tong Dau primary school. Few houses are about 200 m far from the substation location. These are the nearest areas with human living in the substation location. The nearest residential area of the substation is center of Chieng Chau commune (2 km far from the substation). - The 35 kv power line will mainly overpass rice fields, bamboo Luong forest. Sections of the power line going near residential area is G3-G4 (Mai Chau township), G21-G22 (Van Mai commune). These residential areas are about 70 m far from the power line. Main part of the power line are far from residential areas so construction activities of the subproject will not impact to normal life of local people. - Construction materials will be supplied by local supplier within medium distance to construction sites. - Equipment, cables, materials transported from Ha Noi and from Mai Chau district to the sites through national road 15 and provincial roads system. After that these materials will be transported manually or halfmanually to construction sites. - Due to the above reasons, the noise and vibration impact caused by the Subproject is considered as medium, happening in a short period of time and can be mitigated. 9 Soil erosion Small Short - The topography of the substation area and the power line is quite flat. Vegetation cover is quite good. From G26 to the end point (about 4,031 Mitigable Environmental Management Plan (EMP) 29

30 No Impact Magnitude Duration Description of the impacts Evaluation of impacts m), the power line will overpass hills with high slopes. However, in this area is bamboo Luong forest. Luong trees are very well grown. Vegetation cover is quite thick so risk of soil erosion is low. - Excavation, backfill and ground leveling are prioritized to be done in dry season; - Regarding soil erosion, the impact is assessed as small according to small scale of the sub-station site, short construction time. Furthermore, these impacts can be reduced to even smaller when implementing mitigation measures. 10 Air pollution Medium Short -Dust generated from soil excavation, ground leveling especially during dry seasons. The subjects to be affected by dust are people living, working near roads used for transportation of the constriction materials such as national, provincial, district, inter commune roads. Medium and Mitigable - The Subproject site is away from residential and urban areas therefore air pollution (dust) would not affect much on people living in the Subproject area; The most affected area by air pollution will be substation location, center of Chieng Chau commune, center of Van Mai commune. These areas will be sprayed by water during dry and strong wind times. - There are 3 residential areas about 70 m far from the Subproject sites. Construction activities at these sites are just construction of foundations. Size of the foundations is 2 m x 2.3 m x 2 m (depth) so impact can be assessed as medium and can be mitigated as described in Table 4.1. Environmental Management Plan (EMP) 30

31 No Impact Magnitude Duration Description of the impacts Evaluation of impacts Other residential areas are far from the subproject sites. 11 Ecological impact Small Short - Proposed substation is located in very intensively used by human activities. Small and mitigable 12 Traffic disturbance including water-way transportation - The main land use pattern in the substation area and ROWs are rice fields and dry crops. There are km from km of the power line overpassing bamboo Luong forest. This forest is planted and periodically exploited for commercial purpose. - Except rice field, Luong forest, there are few other trees, fruit trees, eucalyptus are impacted. These trees mainly have economic but not ecological value. - There is also no special impact caused by Subproject on fauna since the Subproject sites are mainly rice fields, planted Luong forests, gardens, land along roads. These are very common patterns in the area. Beside these, there is no special habitat observed. Small Short - Transportation of materials and equipment will disturb the normal traffic in the areas during short period of time. - The substation is located in an open area; the transportation of construction materials is generally easy due to relatively developed traffic system in the subproject area. - The power line will 4 times overpassing roads having width from 5-10 m; 21 times overpassing roads having width less than 5 m. When pulling wires across these roads, scaffolds will be constructed to enable Medium and Mitigable Environmental Management Plan (EMP) 31

32 No Impact Magnitude Duration Description of the impacts Evaluation of impacts normal transportation on this road. These roads are quite small with low density of transportation so traffic in these areas will not be seriously affected. 13 Degradation of the existing rural roads, rice fields and path at edges of rice fields. 14 Solid waste generated from soil excavation Medium Short - Transportation of construction materials with high frequency may cause damage to the inter-commune roads; - Currently local authorities and people supervise the management of rural road quite well. Large load transportations are not allowed to run through roads whose quality is not good enough. This is also an issue that the contractors have to comply and thoroughly calculate transporting options to avoid rural road degradation. - Manually or half-manually transportation material to construction sites might also cause damages to the rice fields, path at edges of the rice fields. - The road section that most potentially be damaged by subproject activities is the inter commune road that will be widened for an access road of the Mai Chau substation. Other roads used by subproject s vehicles are potentially less affected. Minor Short Excessive soil and materials will be used for poles foundations filling. The volume of excessive soil is often not enough for foundations, sometimes it has to purchase and transport from other places. Therefore it could be said that impact is in minor level. Medium and Mitigable Minor 15 Environmental Medium Short - The subproject implementation is expected to be completed in 9 Medium and Environmental Management Plan (EMP) 32

33 No Impact Magnitude Duration Description of the impacts Evaluation of impacts impacts caused by months, from that construction period will last for 5-6 months. High mitigable construction workers construction time is last from 5 to 6 months. The remaining time is mainly reserved for the installation of equipments; - It is expected to be 72 workers involving with construction of the substation. These worker will create their camps in substation's area, where is reserved for the second phase (installation of another transformer). Number of workers involving with construction of the power line is about 80; they will be divided into two groups and will stay in houses rent from local people. Workers will be chosen from the skilled ones in the region so in this camp number of worker will be also about workers/each site. - In the camp for substation, other ancillary s constructions such as bathrooms, toilets will be built for workers to use. 16 Conflict between construction worker and local people - Camp sites will dispose domestic solid wastes that can cause environmental pollution. However these wastes are mainly package materials, leftover food... with small amount. Small Short - Conflict might cause because of: Difference in incomes, cultures, behaviors; However worker are come from the region so these differences are not considerable. - The subproject will be implemented in well developed area with high population density; the number of workers is not considerable in comparison with local people. Minor Environmental Management Plan (EMP) 33

34 No Impact Magnitude Duration Description of the impacts Evaluation of impacts - Stay duration of workers in each site is short (6-9 months), so the impact therefore considered as minor. 17 Health and safety Medium Short - Accidents might happen during construction if the safety issues are not well considered. Medium and mitigable 18 Flooding of an area surrounding the substation 19 Interruption of utility services - Accidents might happen to the workers or local people living around the subproject area. Small Long - An area used for substation is land used for rice field. This area will be leveled to 0.3 m higher than the existing level. - By leveling up the ground for the substation, rice field in surrounding area might be flooded; - Water level in rice field is controllable by farmers with support of irrigation system. In case water is increased, farmer will regulate water level accordingly. Flooding will not occur. - Experiences from other similar projects show that this impact was not happened. However subproject owner will work with farmers during construction phase and operation phase to check the problem. In case flooding would occur, Project owner will design proper drainage system to keep water regime as closed as the existing conditions. The impact is assessed as small and can be mitigated. Small Short - Installation of power line requires power interruption to some areas. -Due to power interruption some services which' operation depend on Small Small Environmental Management Plan (EMP) 34

35 No Impact Magnitude Duration Description of the impacts Evaluation of impacts Operation phase power supply would be interrupted. 20 Supplying electricity for construction of Trung Son HPP 21 Impact on Tong Dau primary school. Large Long - Subproject is primary aimed to supply for construction of Trung Son HPP. In later phase, the power line and substation will supply electricity for resettlement sites of trung Son HPP. - The subproject actively supports for development of the area; handcraft and traditional work and services can be developed. - Increase the quality of life for local residents due to sufficiency and stability of power supply. None None - During operation phase, the substation will not cause noise, dust, vibration... so Mai Chau substation will not cause impact on activities of the school. - The substation protected by walls, guards so pupils can not access, therefore accidents related to electricity could not occurred to pupils as well as to local people. Positive No impact 22 Health and safety Minor Long - There are no habitants in the substation area. The number of employments in the substation is small (about people divided into shifts). The safety regulations in the substation are guaranteed so there will be no impact on health and safety of workers; Minor and mitigable - If safety regulations are not complied, it might affect on heath workers, however this case is extremely rare. Environmental Management Plan (EMP) 35

36 No Impact Magnitude Duration Description of the impacts Evaluation of impacts - According to Vietnam Government regulations, houses are allowed to be existed in the ROW of 110 kv and 220 kv power line. However these houses are required to meet certain requirements as described in Table 4.1 of the EMP kv power line will not cause impact to people living within and near ROW. 23 Electromagnetic field None None - The power line is designed according to existing technical regulations; electromagnetic field will not exceed permissible value (5kV/m). 5 kv/m is safe electromagnetic field level for human health. None 24 Oil, hazardous waste contamination - When the power line is designed according to technical standards, the electromagnetic field in the ROW is always lower than 5 kv/m for power line with voltage under 220 kv. - At this electromagnetic field level, there will not be effect of electromagnetic field on human health. Minor Long - No PCBs containing oil will be used during the subproject s construction and operation; - During the subproject operation, some chemical will be used such as accumulators, batteries, dielectric oil, lubricants etc. These equipment and chemicals will be registered and managed as regulated by Circular 12/2011/TT-BTNMT dated 14/4/2011 on Management of hazardous wastes. These practices are applied for all other substations of EVN and will apply for Mai Chau substation as well. Minor and mitigable Environmental Management Plan (EMP) 36

37 4. MITIGATION MEASURES Table 4.1. Mitigation measures The subproject is very similar to the subprojects of Distribuion Efficiency Project (DEP), which is also supported by loan from the WB. The environmental code of practices (ECOPs) was developed for DEP. During preparation of this EMP, consultant has reffered to these ECOPs and recommended to apply for the subproject. Table 4.1. Mitigation Measures Applied for Impact No Impact Mitigation measures applied for the impact Responsible for Implementation General mitigation measures according to ECOP in Construction phase 1 Impacts to vegetation cover and ecological resources The Contractor shall prepare a Clearance, Revegetation and Restoration Management Plan for prior approval by the Construction Engineer, following relevant regulations. The Clearance Plan shall be approved by Construction Supervision Consultant and followed strictly by contractor. Areas to be cleared should be minimized as much as possible. Site clearance in a forested area is subject to permission from Department of Agriculture and Rural Development. The Contractor shall remove topsoil from all areas where topsoil will be impacted on by rehabilitation activities, including temporary activities such as storage and stockpiling, etc; the stripped topsoil shall be stockpiled in areas agreed with the Construction Supervision Consultant for later use in re-vegetation and shall be adequately protected. The application of chemicals for vegetation clearing is not permitted. When needed, erect temporary protective fencing to efficiently protect the preserved trees before commencement of any works within the site. No area of potential importance as an ecological resource should be disturbed unless there is prior authorization from CSC, who should consult with PMUs, and the relevant local authorities. This could include areas of breeding or feeding of birds or animals, fish Contractor Environmental Management Plan (EMP) 37

38 No Impact Mitigation measures applied for the impact Responsible for spawning areas, or any area that is protected as a green space. Implementation 2. Impacts of dust The Contractor is responsible for compliance with relevant Vietnamese legislation with respect to ambient air quality. Contractor The Contractor shall implement dust suppression measures (e.g. water sprays vehicles, covering of material stockpiles, etc.) as required. Spray water in construction sites for the substation and its access road during dry and windy weather. Construction vehicles shall comply with speed limits and haul distances shall be minimized. Material loads shall be suitably covered and secured during transportation to prevent the scattering of soil, sand, materials or dust. The Contractor shall be responsible for any clean-up resulting from the failure by his employees or suppliers to property secure transported materials. Exposed soil and material stockpiles shall be protected against wind erosion and the location of stockpiles shall take into consideration the prevailing wind directions and locations of sensitive receptors. Dust masks should be used where dust levels are excessive. 3 Air pollution All vehicles must comply with Vietnamese regulations controlling allowable emission limits of exhaust gases. Contractor Vehicles in Vietnam must undergo a regular emissions check and get certified named: Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD-BGTVT. There should be no burning of waste or construction materials or cleared vegetation on site. Cement processing plants should be far from residential areas. 4 Noise and vibration The contractor is responsible for compliance with the relevant Vietnamese legislation with respect to noise and vibration. Contractor All vehicles must have appropriate Certificate of conformity from inspection of quality, technical safety and environmental protection following Decision No. 35/2005/QD- Environmental Management Plan (EMP) 38

39 No Impact Mitigation measures applied for the impact Responsible for 5 Water pollution 6 Solid waste BGTVT; to avoid exceeding noise emission from poorly maintained machines. When needed, measures to reduce noise to acceptable levels must be implemented and could include silencers, mufflers, acoustically dampened panels or placement of noisy machines in acoustically protected areas. Avoiding or minimizing transportation though or material processing near community areas. The Contractor must be responsible for compliance with the relevant Vietnamese legislation relevant to wastewater discharges into watercourses. Portable or constructed hygienic toilets must be provided on site for construction workers. Wastewater from toilets as well as kitchens, showers, sinks, etc. shall be discharged into a conservancy tank for removal from the site or discharged into municipal sewerage systems; there should be no direct discharges to any water body. Wastewater over standards set by relevant Vietnam technical standards/regulations must be collected in a conservancy tank and removed from site by licensed waste collectors. Using techniques as berms, silt barriers, settlement ponds, drainage channels, minimization of the time soil is left open and unprotected, immediate landscaping an seeding after completion of works, during construction to limit the exposure of disturbed sediments to moving water. Before construction, all necessary wastewater disposal permits/licenses and/or wastewater disposal contract have been obtained. At completion of construction works, wastewater collection tanks and septic tanks shall be safely disposed or effectively sealed off. Before construction, a solid waste control procedure (storage, provision of bins, site cleanup schedule, bin clean-out schedule, etc.) must be prepared by Contractors and it must be carefully followed during construction activities. Before construction, all necessary waste disposal permits or licenses must be obtained or hire local environmental services (such as environmental service team of Mai Chau district. which is under management of Mai Chau environmental management division of Mai Chau district) for collection of house hould waste from camp sites and construction waste (if there Implementation Contractor Contractor Environmental Management Plan (EMP) 39

40 No Impact Mitigation measures applied for the impact Responsible for is any). Measures shall be taken to reduce the potential for litter and negligent behavior with regard to the disposal of all refuse. At all places of work, the Contractor shall provide litter bins, containers and refuse collection facilities. Solid waste may be temporarily stored on site in a designated area approved by the Construction Supervision Consultant and relevant local authorities prior to collection and disposal through a licensed waste collector, such as environmental service team of Mai Chau district which is under management of Mai Chau environmental management division of Mai Chau district. Waste storage containers shall be covered, tip-proof, weatherproof and scavenger proof. No burning, on-site burying or dumping of solid waste shall occur. Recyclable materials such as wooden plates for trench works, steel, scaffolding material, site holding, packaging material, etc shall be collected and separated on-site from other waste sources for reuse, for use as fill, or for sale. If not removed off site, solid waste or construction debris shall be disposed of only at sites identified and approved by the Construction Supervision Consultant and included in the site specific measures. Under no circumstances shall the contractor dispose of any material in environmentally sensitive areas, such as in areas of natural habitat or in or close to watercourses. Implementation 7 Chemicals or hazardous wastes Chemical waste of any kind shall be disposed of at an approved appropriate landfill site and in accordance with local legislative requirements. The Contractor shall obtain needed disposal certificates. Contractor The removal of asbestos-containing materials or other toxic substances shall be performed and disposed of by specially trained and certified workers. Used oil and grease shall be removed from site and sold to an approved used oil recycling company. Used oil, lubricants, cleaning materials, etc. from the maintenance of vehicles and machinery shall be collected in holding tanks and removed from site by a specialized oil Environmental Management Plan (EMP) 40

41 No Impact Mitigation measures applied for the impact Responsible for recycling company for disposal at an approved hazardous waste site. Used oil or oil-contaminated materials that could potentially contain PCBs shall follow procedures provided in the EMF to avoid any leakage or affecting workers. The local DONRE must be contacted for further guidance. Unused or rejected tar or bituminous products shall be returned to the supplier s production plant. Relevant agencies shall be promptly informed of any accidental spill or incident. Store chemicals appropriately and with appropriate labeling. Appropriate communication and training programs should be put in place to prepare workers to recognize and respond to workplace chemical hazards. Prepare and initiate a remedial action following any spill or incident. In this case, the contractor shall provide a report explaining the reasons for the spill or incident, remedial action taken, consequences/damage from the spill, and proposed corrective actions. Implementation 8 Traffic management Before construction, carry out consultations with local government and community and with traffic police. Contractor Significant increases in number of vehicle trips must be covered in a construction plan previously approved. Routing, especially of heavy vehicles, needs to take into account sensitive sites such as schools, hospitals, and markets. Installation of lighting at night must be done if this is necessary to ensure safe traffic circulation. Place signs around the construction areas to facilitate traffic movement, provide directions to various components of the works, and provide safety advice and warning. Employing safe traffic control measures, including road/rivers/canal signs and flag persons to warn of dangerous conditions. Avoid material transportation for construction during rush hour. Passageways for pedestrians and vehicles within and outside construction areas should be segregated and provide for easy, safe, and appropriate access. Signpost shall be installed appropriately in both water-ways and roads where necessary. Environmental Management Plan (EMP) 41

42 No Impact Mitigation measures applied for the impact Responsible for 9 Interruption to utilitiy services Planned and unplanned interruptions to water, gas, power, internet services: the Contractor must undertake prior consultation and contingency planning with local authorities about the consequences of a particular service failure or disconnection. Coordinate with relevant utility providers to establish appropriate construction schedules. Provide information to affected households on working schedules as well as planned disruptions (at least 5 days in advance). Interruptions of water supply to agricultural areas must also be avoided. The contractor should ensure alternative water supply to affected residents in the event of disruptions lasting more than one day. Any damages to existing utility systems of cable shall be reported to authorities and repaired. Implementation Contractor 10 Restoration of affected areas Cleared areas such as borrow pits which are no longer in use, disposal areas, site facilities, workers camps, stockpiles areas, working platforms and any areas temporarily occupied during construction of the project works shall be restored using landscaping, adequate drainage and revegetation. Contractor Start revegetation at the earliest opportunity. Appropriate local native species of vegetation shall be selected for the planting and restoration of the natural landforms. Spoil heaps and excavated slopes shall be re-profiled to stable batters, and grassed to prevent erosion. All affected areas shall be landscaped and any necessary remedial works shall be undertaken without delay, including green-spacing, roads, bridges and other existing works. Trees shall be planted at exposed land and on slopes to prevent or reduce land collapse and keep stability of slopes. Soil contaminated with chemicals or hazardous substances shall be removed and transported and buried in waste disposal areas. Restore all damaged road and bridges caused by project activities. 11 Worker and public Contractor shall comply with all Vietnamese regulations regarding worker safety. Contractor Environmental Management Plan (EMP) 42

43 No Impact Mitigation measures applied for the impact Responsible for Safety Prepare and implement action plan to cope with risk and emergency. Preparation of emergency aid service at construction site. Training workers on occupational safety regulations. If blasting is to be used, additional mitigation measures and safety precautions must be outlined in the EMP. Ensure that ear pieces are provided to and used by workers who must use noisy machines such as piling, explosion, mixing, etc., for noise control and workers protection. During demolition of existing infrastructure, workers and the general public must be protected from falling debris by measures such as chutes, traffic control, and use of restricted access zones. Install fences, barriers, dangerous warning/prohibition site around the construction area which showing potential danger to public people (such as unfinished power pole foundation, high risk electrical shock areas, etc.). The contractor shall provide safety measures as installation of fences, barriers warning signs, lighting system against traffic accidents as well as other risk to people and sensitive areas. If previous assessments indicate there could be unexploded ordnance (UO), clearance must be done by a relevant army unit. Implementation 12 Communication with local communities about Subproject environmental issues Maintain open communications with the local government and concerned communities; the contractor shall coordinate with local authorities (leaders of local wards or communes, leader of villages) for agreed schedules of construction activities at areas nearby sensitive places or at sensitive times (e.g., religious festival days). Copies in Vietnamese of relevant parts of these ECOPS should contain in contractor documents and of other relevant environmental safeguard documents shall be made available to local communities and to workers at the site. Contractor Reduced playground space, loss of playing fields and car parking: The loss of amenities during the construction process is often an unavoidable source of inconvenience to users in sensitive areas. However, early consultation with those affected, provides the opportunity to investigate and implement alternatives. In all cases damages shall be compensated. Environmental Management Plan (EMP) 43

44 No Impact Mitigation measures applied for the impact Responsible for Disseminate project information to affected parties (for example local authority, enterprises and affected households, etc) through community meetings before construction commencement. Provide a community relations contact from whom interested parties can receive information on site activities, project status and project implementation results. Provide all information, especially technical findings, in a language that is understandable to the general public and in a form of useful to interested citizens and elected officials through the preparation of fact sheets and news release, when major findings become available during project phase. Monitor community concerns and information requirements as the project progresses; Respond to telephone inquiries and written correspondence in a timely and accurate manner. Inform local residents about construction and work schedules, interruption of services, traffic detour routes and provisional bus routes, blasting and demolition, as appropriate. Provide technical documents and drawings to PC s community, especially a sketch of the construction area and the EMP of the construction site. Notification boards shall be erected at all construction sites providing information about the project, as well as contact information about the site managers, environmental staff, health and safety staff, telephone numbers and other contact information so that any affected people can have the channel to voice their concerns and suggestions. Implementation 13 Workforce, camp and site management Workers camps will be located at least 100 m away from schools and health care centres and not be located on steep slopes. The workforce shall be provided with safe, suitable and comfortable accommodations and safe portable water. They have to be maintained in clean and sanitary conditions. Contractor Site offices, worker camps, mixing stations, and workshops shall be located NOT within 100m from any water courses, 500 meters of existing residential area. Engineers and workers shall register their temporary residence with the local authority. Contractor should sign committeemen with local authorities on keeping of security and social safety on subproject s areas. Environmental Management Plan (EMP) 44

45 No Impact Mitigation measures applied for the impact Responsible for Allocate officer to be the Contractor s Workplace Safety and Environment Officer responsible for environmental and safety issues including training for workers. Septic tank toilets must be provided at all construction camp areas where there will be concentration of labor. First aid boxes shall be provided in each construction camp site. Implementation 14 Chance finding procedures in case of founding objects with historical or cultural values See Table 4.2. Contractor in coordination with Project owner and relevant local authorities Specific Mitigation Measures Applied for the sub-project in Construction Phase 15 Impact on land acquisition to the local HHs, vegetation covers Careful site survey for substation location, power line routes, consult with local authorities for optimal selection of Subproject construction sites ; Disclose detail information on temporarily and permanently acquired land to affected households; Proper compensation for affected households. It is estimated that compensation cost for land acquisition of substation is 624 millions VND; and power line is 12,851 millions VND Schedule land acquisition after rice or crop harvesting seasons to avoid harvest losses to people as well as avoid other high activities time in agricultural cultivation. The subproject owner shall prepare and carry out the compensation plan according to Vietnamese and the WB Regulations in accordance with RPF for the DEP Project and RP of the subproject. Select pole s foundation locations properly to minimize impacts on land, rice field, or garden losses of local people; Pole locations should be arranged properly in local people land so that affected households can still use the remaining part of their land comfortably. -Design Consultant; - Sub-project owner coordinates with local authorities Environmental Management Plan (EMP) 45

46 No Impact Mitigation measures applied for the impact Responsible for Specific Measures Applied during Operation Phase Simple scaffolds will be created when pulling cables overpassing rice fields, gardens to avoid damages to the rice fields and trees. 16 ROW protection Comply with Decree 106/2005/ND-CP dated 17/8/2011 on the protection of high-voltage power grid corridor; Decree 81/2009/ND-CP dated 12/10/2009 on safety protection for high voltage power network; 17 Oil, hazardous chemical contamination Carry out regular supervision of ROWs protection. Oil containing PCB is not allowed to use for the subproject; Oil refilling (if required) of transformers shall be done in the Workshop. Ussually, after certain time of operation (5 year in average) the oil inside the transformer might be degraded in term of lower dielectric quality, high content of moisture so the oil must be retrofilled to phase out moisture and other contaminats. After retrofilling, the oil will be reused. After use, the transformer will be handled to agency that is lisenced to transport and treat used oil as regulated by Cicular 12/2011/TT-BTNMT dated 14/4/2011 on management of hazardous waste. Design and construct basin under transformers for spill oil collection and central larger basin for oil collection for whole substation as they were described in the approved Subproject technical design report. Use oil collectors during maintenance services for unexpected oil spills into environment. Carry out regular check and maintenance the transformers so as any leakage and/or failure risks can be detected timely; Replace or repair transformer as soon as possible after leakage from transformers detected. Isolate the leakage and fix the problem to ensure that the leakage does not cause pollution in water sources nearby; Maintain and regularly check the fire protection devices at the Thoai Son substation; Comply with regulation of Vietnam Government as required by Circular 12/2011/TT- Implementation - Southern High Voltage Power Network Company operation) - Southern Hịgh Voltage Power Network Company Designed consultant Environmental Management Plan (EMP) 46

47 No Impact Mitigation measures applied for the impact Responsible for 18 Fire prevention and protection system BTNMT dated 14/4/2011 on management of hazardous waste. Designed system for Fire prevention and protection of the substation was certified and approved by Fire prevention and protection system from authorized agency (PC66) by Document No 78/TD-PCCC (PC66) dated 26/5/2010. Implementation Designed consultant High Voltage Power Network Company Environmental Management Plan (EMP) 47

48 5. EMERGENCY ACTION PLAN Table 5.1. Chance finding procedures and Emergency action plan No. Risk Action Responsibility 1 Artifacts found during excavation works 2 Remains found during excavation works 3 There are complaints from community about environmental problems related to construction Contractor shall protect the site and report to the Construction Supervisor/PMUs and local museum/ cultural management authority. Deliver the object found to local museum/ cultural management authority. Determine whether construction can be continued or halted for further investigation The Directors of the provincial Department of Cultural and Information and local Museum shall be responsible for the subsequent handling of the objects found in accordance with Article 21 of the Decree no. 92/2002 guiding the Implementation of the Protect the site and report to local authority Determine who/where/how to address and propose next actions Implement the proposed actions Fix the problem immediately if possible Take note in log book Discuss with the Employer/local authority where conflicts occur Contractor, construction supervisor to coordinate Contractor Contract Contractor All relevant authorities Those who are assigned to Contractor Contractor, PMUs and local authority 4 Worker accidents Carry out first aid where possible and transfer the victim the nearest hospital as soon as possible and if necessary Worker/people at the site Protect the site and place warning site Prepare incident notes Environmental Management Plan (EMP) 48 Contractor Contractor and local authority

49 No. Risk Action Responsibility 5 Unexploded ordinances is found Protect the site Report to local authority Contractor Contractor/local authority Environmental Management Plan (EMP) 49

50 6. COMMUNITY CONSULTATION AND INFORMATION DISCLOSURE During subproject preparation stage ( ), the following activities were carried out: Activity 1: Investigate and discussion with local authorities about the substation location and power line routing. Activity 2: Site investigation, preparation of Environmental Management Plan for the Subproject Activity 3: Organizing public consultation. The subproject will overpass 6 communes and town of Mai Chau district (hoa Binh province) and Phu Thanh commune of Quan Hoa district (Thanh Hoa province). Public consultation in 6 communes of Mai Chau district: Subproject Management Unit and Consultants organized 6 consultation meetings at 6 subproject s communes. Details of the meetings are described in Table 6.1. Project owner and consultant held public consultation for Environmental management plan of 110 kv uan Mai substation and 35 kv power line Subproject. The representatives of Subproject Owner and Consulting Company presented to the public on the following main issues: Subproject description: route of power line, the substation location, the necessity of construction of the above-mentioned Subprojects; The potential environmental impacts might be caused by the Subproject; Measures to mitigate the impact. Participants of the meetings are: representatives of affected HHs, representatives of local authorities and representatives of local power company. Table 6.1. Summary of comments at public consultation meetings in Mai Chau district No Comments received Response of Project owner and consultant At office of people committee of Chieng Chau commune - 8h30-12/9/2012 Number of participants: 40 people 1 - It is required to spray water in intensive construction sites such as substation and its access road. - This comments will be integrated in Chapter for mitigation measures 2 - Subproject s construction work might cause damage to the local existing roads. Contractors are required to repair road if there are some damages during construction, transportation of materials. 3 - Contractors are required to arrange proper construction schedule to avoid cultivation and harvest activities of local people. (Table 4.1. Item 2) - This measure was already described in Table 4.1. Item 10 on Restoration of affected areas - This measure will be added on Table 4.1. Item 15 on Impact on land Environmental Management Plan (EMP) 50

51 No Comments received Response of Project owner and consultant acquisition to the local HHs, vegetation covers At office of people committee of Mai Ha commune - 8h30-13/9/2012 Number of participants: 26 people 4 - Contractors are required to strictly follow EMP and inform in - Comments are advance construction schedule to local people for cooperation recorded and PMU will and avoid damages to agricultural cultivation of local people. cooperate with Contractor to early inform construction schedule. 5 - PMU should early inform local people on compensation plan, land acquired from affected HHs. -Comments are recorded and PMU will early inform acquired land and compensation plan for affected HHs. At Cultural house of Mai Hoang Son village Mai Hich commune. 13h30-13/9/2012. Number of participants: 15 people (details of participants are listed in Annex 5). 6 - Environmental impacts of the subproject are minor. However Project owner and Contractors should pay attention on management of worker as described in EMP to avoid impact on normal life of local people. 7 - Contractors are required to commit with local authorities on keeping security and social safety in the subproject s areas. At office of people committee of Tong Dau commune - 10h30-12/9/2012 Number of participants: 56 people 8 - PMU and Contractors are required to strictly follow this EMP to minimize environmental impact on health of local people 9 - Transportation of materials might cause impact on traffic in the subproject s site, so PMU and Contractor are required to implement mitigation measures as described in EMP to minimize this impact Common experiences showed that after construction Contractors are not pay attention on implementation of advanced committeemen, so PMU should have measure to require Contractor to implement rehabilitation of affected areas during construction. -Comments are recorded and PMU will pay attention on supervision of implementation of EMP and management of worker as well. - This comment will be added in mitigation measure in Table 4.1. Item 13 on Workforce, camp and site management -Comments are recorded and PMU will pay attention on supervision of implementation of EMP. -Comments are recorded and PMU will pay attention on supervision of implementation of EMP. -Comments are recorded and PMU will pay attention on supervision of Contractors on implementation of EMP. At office of people committee of Mai Chau township - 13h30-12/9/2012 Number of participants: 19 people PMU should pay attention on supervision of Contractor on -Comments are recorded Environmental Management Plan (EMP) 51

52 No Comments received Response of Project owner and consultant cleaning of construction materials when the construction work is completed. At office of people committee of Van Mai commune - 8h30-14/9/2012 Number of participants: 70 people Solid wastes of worker should be collected and treated to ensure hygenity of subproject s areas Contractors are required to commit with local authorities on keeping security and social safety in the subproject s areas. and PMU will pay attention on supervision of Contractors on implementation of EMP. -Comments are recorded and PMU will pay attention on supervision of Contractors on implementation of EMP in general and on measures applied for solid wastes of worker camp in particular. - This comment will be added in mitigation measure in Table 4.1. Item 13 on Workforce, camp and site management Public consultation in Phu Thanh commune- Quan Hoa district In Phu Thanh commune, number of affceted HHs are limited (6 HHs are directly affected in term of land and properties, other are living far from the subproject s site so they are likely not affected in term of environmental impacts). Therefore, public consultation are implemented by giving in advace the summary EMP and interveiw for comments of the affected HHs. Summary of comments are given in Table 6.2. Table 6.2. Summary of comments at public consultation meetings in Phu Thanh commune, Quan Hoa district No Name of interviewed HHs Comments for EMP 1 Luong uan Thao - Agree on the given EMP 2 Kha Văn Tha - PMU should pay attention on request Contractors to keep securiry and social safety for people in houses rent by worker. 3 Luong Van Kham - Agree on the given EMP 4 Be uan Tinh - PMU should inform in advance compensation paln and construction plan so local people can arrange harvesting of bamboo Luong in proper time. 5 Luong Thi Tho - Agree on the given EMP 6 Ha Van Minh - If contractors damages local roads during construction, they should repair the roads. Environmental Management Plan (EMP) 52

53 The comments received in Phu Thanh commune are similar to comments received through public consultation meetings in Mai Chau districts. The Project owner and Consultant received comments and integrated them during updating of the EMP report. Activity 4: Review and edit the EMP according to collected ideas. Continue to receive feedback for affected households. Activities 5: Disclosure of the EMP (Supposed to disclose in October, 2012) - The Vietnamese version of EMP report will be disclosure at People s Committee of Tong Dau commune, at People s Committee of Mai Chau district and at People s Committee of Phu Thanh commune, so interested public and organizations can access and monitor EMP compliance - The English and Vietnamese versions of the EMP will be sent to the Vietnam Development Information Center, 63 Ly Thai To, Hanoi for information disclosure. - The English version of the EMP will be sent to Infoshop of the WB at Washington to be disclosed. Environmental Management Plan (EMP) 53

54 7. ENVIRONMENTAL MONITORING PLAN Table 7.1. Environmental monitoring plan No. Environmental Issues Parameter is to be monitored CONSTRUCTION PHASE 1 Surface water 1) Visual observation to assess whether turbidity and soil the excavation and other construction erosion activities cause any pollution to the surface water as in irrigation system, in rivers where power line is crossing. 2) The measures applied by Contractor to avoid the pollution of water; 3) Measures applied to strengthen the canal s shores at locations where the construction of pole foundation is near canal? 4) If there is some complaints from local people about the pollution of water source caused by Subproject activity the measurement of water quality parameters should be taken. Location Where is the parameter to be monitored? Section from G26 to end point (part over passing hills in Van Mai commune (Mai Chau district) and in Phu Thanh (Quan Hoa district). Method How Are the parameter to be monitored/ type of monitoring equipment? Frequency - By observation - Daily observation will be recorded and Monthly report will be prepared and submitted during whole construction period Responsibility - Contractor - PMU (Technical supervisors or so called Technical supervisors of PMU is responsible to carry out ) Environmental Management Plan (EMP) 54

55 No. Environmental Issues 2 Noise level around Subproject s construction sites and in adjacent areas Parameter is to be monitored 1) Assess by observation whether (i) the noise level from Subproject s construction site is acceptable for surrounding residential areas (ii) The construction machines, or equipment make noise that annoy local people. 2) The mitigation measures of noise applied by the Contractor. 3) In case of some complaints from local people, Consultant should carry out measurements. 3 Dust 1) Assess by visual observation whether (i) the dust caused by construction is serious; (ii) the measures taken by Contractor to control the dust level 2) The mitigation measures applied by the Contractor if dust level increases in the area 3) Measurement should be taken if there are some complaints from local people Recommended areas with emphasis to be monitored: Subproject construction sites; residential areas near construction site. Location Where is the parameter to be monitored? - The residential area nearest to the substation; road along transportation route of the subproject vehicles. - Subproject s sites along national road no 15, centre of Chieng Chau and Van Mai communes. Method How Are the parameter to be monitored/ type of monitoring equipment? Frequency Responsibility - By observation As above As above - By observation As above As above Environmental Management Plan (EMP) 55

56 No. Environmental Issues 4 Solid waste and site cleaning after the construction 5 Transportation disturbance 6 Transportation disturbance Parameter is to be monitored Assess observe whether: 1) Construction residues are clean up after the construction 2) The way that Contractor disposes solid wastes from construction site. Special attention should be paid on the time after construction work. Assess, observe: (1) Whether the construction and other Subproject's activities such as pole's erection, cable pulling cause any serious disturbance to the local traffic; (2) Necessary measures taken to avoid the disturbance to local traffic such as: warning signs of construction site, transportation is avoiding heavy traffic hours etc. (see more details in section Mitigation measures). Assess, observe: (1) Whether the construction and other Subproject's activities such as pole's erection, cable pulling cause any serious disturbance to the local traffic; (2) Necessary measures taken to avoid the disturbance to local traffic such as: warning signs of construction site, transportation is avoiding heavy traffic hours etc.(see more details in section Location Where is the parameter to be monitored? - Construction site for the substation and sites for completed or ongoing construction of foundations - Access road to the substation, sites along national road N o Along national road No 15; - Along inter commune road used for transportation of the materials and equipment Method How Are the parameter to be monitored/ type of monitoring equipment? Frequency Responsibility - By observation As above As above - By observation and interview local people. As above As above - By observation As above As above Environmental Management Plan (EMP) 56

57 No. Environmental Issues 7 Sanitation facilities worker camp at 8 Conflict between worker and local people 9 Current situation of safety and Parameter is to be monitored Mitigation measures); (3) Contractor did repair roads, paths in rice fields damaged by construction activities? (4) Is there any complaint of the local people on the issue? Assess and observe whether: - Camps are keeping clean? Toilets area is keep in hygienic condition or not? - Solid waste container is properly located? - Municipal waste water is collected and properly discharged? - Interview workers and local people living near site that there is any disease dissemination between workers and local people and via versa or not? Interview authority staffs, workers and local people on: - Whether staying of workers seriously affect life, living habits of local people? - There is any conflict occurred during stay of worker or not? If there is any, how it was resolved? The Contractor and Subproject owner are taken on solving this conflict actively? Assess safety level during construction works: Location Where is the parameter to be monitored? - Camp sites in the substation and rent houses of workers constructing the power line - Subproject s communes - Construction sites in the substation and Method How Are the parameter to be monitored/ type of monitoring equipment? - By observation and interview local people. - Interview local people. - By observation and interview staffs of Frequency As above As above As above Responsibility As above As above As above Environmental Management Plan (EMP) 57

58 No. Environmental Issues health protection measures 10 Construction material management 11 Affect on agriculture activities 12 Emergency action plan OPERATION PHASE 13 Health and safety Parameter is to be monitored - The Contractor has provides personnel safety protection to worker or does not? - Regulations, standards on electrical technique and safety to avoid electricity shock, accidents. Assess and observe: (1) The management of construction material in the warehouses, stockpiles (2) The management of construction material in the construction site Interview the Contractor, local people and assess whether: - The working schedule is properly arranged; avoid harvesting season and the weeks with high agricultural activities. 1) There is a case of founding artifact with cultural, historical, spiritual values during operation or not? 2) The Constructor, Subproject owner, and relevant parties are carrying out the procedures as required in the Table 4.1 and Table 4.2 or not? Operation agency should make report on the following issues: - Summary of accidents occurring during power line operation; Location Where is the parameter to be monitored? along the power line - Ware houses for construction materials of the subproject. - Agricultural land near by the subproject sites. Method How Are the parameter to be monitored/ type of monitoring equipment? PMU Frequency - By observation As above As above - By observation and interview Contractor, local people. - Subproject sites - By interview local people, Contractor and staffs of PMU - The substation and the power line areas. - Operating unit collects data As above As above Annually Responsibility As above As above - Northern High Voltage Power Network Company Environmental Management Plan (EMP) 58

59 No. Environmental Issues 14 Management of ROW and electric and magnetic field intensity 15 Use and evidence oil pollution and other hazardous chemical at Mai Chau 110 kv substation Parameter is to be monitored - Situation on provisions of safety protection equipment. Operation agency should make report on the following issues: - Situation on implementation of the power line s ROW protection; - Mitigation measures to prevent ROW violation event (if there is) - The Electromagnetic field intensity inside ROW meet required standard or not? - There is any complain of local people related to ROW and Electromagnetic field or not? If is, the measurement should be made. Assessment by visual observation: (1) There is leakage of oil, chemicals from electrical equipments to the environment or not? (2) Where are the maintenance and reparation of electrical equipments implanted? Are these activities safe to health and environment? (3) To comply with the regulation on Location Where is the parameter to be monitored? - The substation and the power line areas. Method How Are the parameter to be monitored/ type of monitoring equipment? - Operating unit collects data - The substation area. - Operating unit collects data Annually Frequency Responsibility (manages the substation) and Hoa Binh power company (manages the power line). - As above Annually Northern High Voltage Power Network Company Environmental Management Plan (EMP) 59

60 No. Environmental Issues Parameter is to be monitored environmental management or not (Submit periodic reports to the Department of Natural Resources and Environment; Register ownership for hazardous waste, and other regulations of as required by Circular 12/2009/TT- BTNMT on management of HZW) Location Where is the parameter to be monitored? Method How Are the parameter to be monitored/ type of monitoring equipment? Frequency Responsibility Environmental Management Plan (EMP) 60

61 Scheme illustrates environmental monitoring TSHP Co. The WB PMU Contractor Local authorities and people Notes: Supervision work flow Reporting work flow Environmental Management Plan (EMP) 61

ENVIRONMENTAL MANAGEMENT FRAMEWORK. For Vietnam Distribution Efficiency Project

ENVIRONMENTAL MANAGEMENT FRAMEWORK. For Vietnam Distribution Efficiency Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SOCIALIST REPUBLIC OF VIETNAM VIETNAM ELECTRICITY ENVIRONMENTAL MANAGEMENT FRAMEWORK

More information

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board RESETTLEMENT PLAN (RP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Sub-project: Improving grid medium, low voltage NORTH POWER COORATION Electric Network

More information

E1712 VOL. 28 ENVIRONMENTAL MANAGEMENT PLAN ELECTRICITY OF VIETNAM POWER COMPANY I

E1712 VOL. 28 ENVIRONMENTAL MANAGEMENT PLAN ELECTRICITY OF VIETNAM POWER COMPANY I Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ELECTRICITY OF VIETNAM POWER COMPANY I COMPONENT: RD - 110KV THANH NONG - KIM BOI TRANSMISSION

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized NATIONAL POWER TRANMISSION CORPORATION Northern Power Projects Management Board ------------------------------- Public Disclosure Authorized TRANSMISSION EFFICIENCY PROJECT

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

Meeting Vietnam s Energy Demands in a Sustainable Way

Meeting Vietnam s Energy Demands in a Sustainable Way TRUNG SON HYDROPOWER PROJECT Meeting Vietnam s Energy Demands in a Sustainable Way Photo by: World Bank 1 Photo by: Mai Ky/World Bank, 2012 OVERVIEW Trung Son Hydropower Project (TSHPP) is a US$411.57

More information

REGULATIONS OF ENVIRONMENTAL MANAGEMENT OF THE CONSTRUCTION PROJECTS Dr. Pham Van Bo Vice president Academy of Managers for Construction and Cities Ministry of Construction - Vietnam List of abbreviations

More information

SUBPROJECT: Rehabilitation of transmission overheadline 180, 181 E1.1 Dong Anh (Section from pole No. 70 to E1.15)

SUBPROJECT: Rehabilitation of transmission overheadline 180, 181 E1.1 Dong Anh (Section from pole No. 70 to E1.15) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized HA NOI POWER CORPORATION ------------------------------------------------------------

More information

FAQs on ESIA of CASA-1000

FAQs on ESIA of CASA-1000 FAQs on ESIA of CASA-1000 I. Technical Questions A. When will the project start in my (province/municipality/region)? The project implementation schedule will be finalized after selection of the contractor

More information

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation Energy Resilience for Climate Adaptation Project (ERCAP) Environmental Code of Practice (ECOP) for COMPONENT 2: Demonstration Measures to Enhance Resilience of Energy Sector (Pilot for Strengthening Transmission

More information

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL POWER TRANSMISSION CORPORATION SOUTHERN POWER PROJECT MANAGEMENT BOARD -------------------------------

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TABLE OF CONTENTS 1. INTRODUCTION... 5 2. LEGAL FRAMEWORKS... 5 2.1. Vietnamese Legislations...

More information

VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line

VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Environmental Monitoring Report 4th Quarterly Report February 2016 VIE: Power Transmission Investment Program - Tranche 2 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Prepared by Southern

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Due Diligence Report April 2016 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh City Power Corporation for the Asian Development Bank. Resettlement

More information

Public Disclosure Authorized EXECUTIVE SUMMARY

Public Disclosure Authorized EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized EXECUTIVE SUMMARY Introduction Georgia is an important transport corridor connecting

More information

4. Agency (or Institution) Responsible for Implementing the Project

4. Agency (or Institution) Responsible for Implementing the Project Summary of Preparatory Study 1. Full Title of the Project Urban Transport Policy and System Development Master Plan for the ity of Dar es Salaam 2. Type of Study Master Plan 3. ategorisation and Its Reason

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

E671 vol. 5. Lesson 11. Environmental Impact of Small-Scale Infrastructure Projects. November L&-~~A>f. Technical Support Staff Basic Training

E671 vol. 5. Lesson 11. Environmental Impact of Small-Scale Infrastructure Projects. November L&-~~A>f. Technical Support Staff Basic Training Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized -4L&-~~A>f Technical Support Staff Basic Training Training Documents (English Translations)

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

City of Glendale Stormwater Management Plan Checklist

City of Glendale Stormwater Management Plan Checklist City of Glendale Stormwater Management Plan Checklist Project: Title of Plan: Date: Date of Plan: Reviewer: Most Recent Revision: Criteria Yes No Identify a SWMP Administrator and an alternate - The SWMP

More information

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION 10.1 Objective The main objective is to confirm the implementation of mitigation measures recommended in

More information

VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE

VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE ENVIRONMENTAL MONITORING REPORT Project Number: 42039-036 Period: April - June, 2017 VIE: POWER TRANSMISSION INVESTMENT PROGRAM, TRANCHE 3 Loan: 3374-VIE COVERING THE FOLLOWING SUBPROJECTS: (i) 500kV My

More information

Subproject: Jointing 110kV line at 220kV Bim Son substation

Subproject: Jointing 110kV line at 220kV Bim Son substation Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject: Jointing 110kV line at 220kV Bim Son substation NORTH POWER CORPORATION Electric

More information

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP)

CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP)

More information

IN THE KYRGYZ REPUBLIC

IN THE KYRGYZ REPUBLIC Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NATIONAL ROAD REHABILITATION (OSH-ISFANA) PROJECT (NRRP)- WORLD BANK PPA Q 6240 CONSULTANCY

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line Environmental Monitoring Report Quarterly Report October to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NORTH POWER CORPORATION Electric Network Project Management Board

More information

VIE: Power Transmission Investment Program -Tranche 3

VIE: Power Transmission Investment Program -Tranche 3 Environmental Monitoring Report # Quarterly Report (Q2 2018) Jan 2019 VIE: Power Transmission Investment Program -Tranche 3 COVERING THE FOLLOWING SUBPROJECTS: (i) 500kV My Tho Duc Hoa transmission line,

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY TRUNG SON HYDROPOWER COMPANY LIMITED TRUNG SON HYDROPOWER PROJECT

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

Big Thunder Wind Park

Big Thunder Wind Park Construction Plan Report DRAFT Prepared by: M.K. Ince and Associates Ltd. May 18, 2010 TABLE OF CONTENTS BIG THUNDER WIND PARK... 1 1 PROJECT OVERVIEW... 1 1.1 PROJECT SCHEDULE... 2 2 CONSTRUCTION ACTIVITIES...

More information

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani

Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Livezeni Coal Washing Plant, Hunedoara County, Design: ICPM Petrosani DESCRIPTION OF

More information

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10 22 NETWORK UTILITIES 22.1 ISSUES 3 22.2 OBJECTIVES 4 22.3 POLICIES 4 22.4 RULES 6 22.5 PERFORMANCE STANDARDS 10 Whanganui District Plan (15 January 2018) Chapter 22 Network Utilities 22-1 22 NETWORK UTILITIES

More information

Trung Son Hydropower. Project Overview and Description

Trung Son Hydropower. Project Overview and Description Trung Son Hydropower Project Overview and Description (As of February 2011) Overview and Objective The Trung Son is a $ 411.57 million medium-sized hydropower and development project located in the Hoa

More information

Chapter MINERAL EXTRACTION AND MINING OPERATIONS

Chapter MINERAL EXTRACTION AND MINING OPERATIONS Chapter 17.31 MINERAL EXTRACTION AND MINING OPERATIONS Sections: 17.31.010 Purpose 17.31.020 Procedure for Extraction and Rehabilitation Requests 17.31.030 Operation and Rehabilitation Standards for all

More information

DRAFT FOR CONSULTATION OCTOBER 7, 2014

DRAFT FOR CONSULTATION OCTOBER 7, 2014 The Board has authorized the release of this document for consultation purposes to seek feedback on its content. It has not endorsed the content of the draft, and the Committee on Development Effectiveness

More information

Annex L. Project Risk Analysis Matrix

Annex L. Project Risk Analysis Matrix Annex L Project Risk Analysis Matrix L1 Table L1 Project Environmental Risk Analysis Local Road upgrades: Loss/damage cultural heritage values Low Acceptable Loss/damage of biodiversity value, EEC Construction

More information

Execute Phase. GGIC Operations Environmental and Social Impacts Assessment: Screening Data Sheet for GLDANULA RIVER CROSSING (Category B)

Execute Phase. GGIC Operations Environmental and Social Impacts Assessment: Screening Data Sheet for GLDANULA RIVER CROSSING (Category B) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Management Consultant's Emergency Services for the North-South Gas Pipeline GIC

More information

Sri: Sustainable Power Sector Support Project

Sri: Sustainable Power Sector Support Project Environmental Monitoring Report June 2015 Sri: Sustainable Power Sector Support Project Prepared by Ceylon Electricity Board for the Asian Development Bank. This environmental monitoring report is a document

More information

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction

CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction 2.7 Generic Mitigation Measures 2.7.1 Avifauna CONSTRUCTION PHASE ENVIRONMENTAL ISSUE MITIGATION REQUIREMENTS 1. Access road selection and construction Vehicles and machinery can impact on natural vegetation

More information

Main Check Items. 1 Are wastes properly treated and disposed of in accordance with the laws and regulations of the host country?

Main Check Items. 1 Are wastes properly treated and disposed of in accordance with the laws and regulations of the host country? Checklist: 16. Power Transmission and Distribution Lines(1) Confirmation of and Social (1) ESIA and Permits 1 Have ESIA reports been officially completed? Have ESIA reports been written in the official

More information

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan Report on 1. PROJECT LOCATION & LAND USE The Ganesh Park 3 is a residential building project constructed on plot 608 to 613/5 Vil: GIDC Ankleshwar in Bharuch district of Gujarat state. The project land

More information

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP) SFG3446 V1 REV BINH DINH PROVINCIAL PEOPLE S COMMITTEE BINH DINH PMU FOR CONSTRUCTION INVESTMENT WORKS OF AGRICULTURE AND RURAL DEVELOPMENT --------------o0o-------------- ENVIRONMENTAL AND SOCIAL MANAGEMENT

More information

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Social Monitoring Report #1 Semestral Report Project Number: 46391-001 August 2017 VIE: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Prepared by Ho Chi Minh Power Corporation for the

More information

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e) Checklist: 3. Hydropower Stations, Dams and Reservoirs (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders Main Check s Have EIA reports been

More information

MOIT FiT Circular No. 02 Decision No. 39

MOIT FiT Circular No. 02 Decision No. 39 Renewable Energy Vietnam Client Alert January 2019 For further information, please contact: Fred Burke +84 28 3520 2628 frederick.burke@bakermckenzie.com Dang Chi Lieu +84 24 3936 9341 chilieu.dang@bakermckenzie.com

More information

Summary of Preparatory Study

Summary of Preparatory Study Summary of Preparatory Study 1. Title of the Cooperation Project, Relevant Project Report Preparatory Survey on the Project for the Establishment of Rural Water Supply System in Kambia Town in the Republic

More information

Environment Management Report Pagsanjan-Luisiana-Lucban-Lucena City Road Section March 31, 2007

Environment Management Report Pagsanjan-Luisiana-Lucban-Lucena City Road Section March 31, 2007 E1467 v 25 Environment Management Report Pagsanjan-Luisiana-Lucban-Lucena City Road Section March 31, 2007 1 losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure

More information

E767 May 2003 ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT. Objectives

E767 May 2003 ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT. Objectives Objectives ENVIRONMlENT AND SOCIAL SAFEGUARD FRAMEWORK ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT E767 May 2003 The environmental and social safeguards framework provides general policies,

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

POWER GRID IMPROVEMENT PROJECT

POWER GRID IMPROVEMENT PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Draft Environmental Code of Practices POWER GRID IMPROVEMENT PROJECT (Project ID: P149599)

More information

Technical Data

Technical Data 4906-17-05 Technical Data (A) PROJECT AREA SITE have occurred in this section. (1) Geography and Topography have occurred in this section. (2) Aerial Photography have occurred in this section. (3) Site

More information

YUCE HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN

YUCE HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized YUCE HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

Alberta Transportation The City of Edmonton The City of Calgary

Alberta Transportation The City of Edmonton The City of Calgary Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for

More information

Resettlement Plan. Dong Chum 2 Hydropower Subproject. Da Bac District Hoa Binh Province. Submitted by:

Resettlement Plan. Dong Chum 2 Hydropower Subproject. Da Bac District Hoa Binh Province. Submitted by: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Ministry of Trade and Industry The World Bank Renewable Energy Development Project Resettlement

More information

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT:

NORTH POWER CORPORATION Electric Network Project Management Board ENVIRONMENTAL MANAGEMENT PLAN (EMP) SUBPROJECT: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Subproject NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

REPORT ON ENVIRONMENTAL IMPACT ASSESSMENT

REPORT ON ENVIRONMENTAL IMPACT ASSESSMENT Ha Nam Province People's Committee Phu Ly City People's Committee Public Disclosure Authorized Public Disclosure Authorized MEDIUM CITIES DEVELOPMENT PROJECT - PHU LY CITY SUBPROJECT, HA NAM PROVINCE REPORT

More information

Environmental Management Plan Prov l. Brdry-Caticlan-Kalibo-Capiz Brdy. May 31, 2007

Environmental Management Plan Prov l. Brdry-Caticlan-Kalibo-Capiz Brdy. May 31, 2007 Environmental Management Plan Prov l. Brdry-Caticlan-Kalibo-Capiz Brdy. May 31, 2007 E1467 v 22 1 losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

More information

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT Environmental and Social Action Plan August 2016 Project: Bosnia and Herzegovina

More information

ROADS: OPERATION AND MAINTENANCE

ROADS: OPERATION AND MAINTENANCE ROADS: OPERATION AND MAINTENANCE GEMS Environmental Compliance- ESDM Training Series Kabul July / August 2016 8/1/2016 1 ROADS AND DEVELOPMENT Improved access = benefits across economic sectors Service

More information

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized E3072 v2 GEF Large City Congestion and Carbon Reduction Project Environment Management

More information

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 311000 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI 220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TERMS OF REFERENCE Transmission line Akhalsikhe-Batumi Georgia Terms of Reference for Tender docs and ESIA 2 1 PROJECT

More information

DOORNVALLEI EXT 5 & 6

DOORNVALLEI EXT 5 & 6 DOORNVALLEI EXT 5 & 6 Proposed township establishment on portion 107 the farm Doornkloof 391 JR Sewer Pipe Crossings - Sesmylspruit Construction Method Statement April 2016 Revision 3 PREPARED FOR: PREPARED

More information

6. CONCLUSIONS AND RECOMMENDATIONS

6. CONCLUSIONS AND RECOMMENDATIONS Environmental Impact Assessment Report: Proposed third 400 kv Transmission line between Poseidon and Grassridge, Eastern Cape and Extension to Grassridge 6. CONCLUSIONS AND RECOMMENDATIONS This Environmental

More information

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003)

Subsection or plan to be revised: 7-1, 7-8, , On page(s): 27-31(2006), 48-49(2003) Proposed Revision To: Standard Specifications For Public Works Construction Standard Plans For Public Works Construction Public Works Standards, Inc. AGC Southern California Regional Office 1906 West Garvey

More information

Qty (1) 1 Lot. 1 Lot. 1 Lot

Qty (1) 1 Lot. 1 Lot. 1 Lot Schedule No. 4c. Environmental, Social, Health And Safety () Cost Schedule Item Description Unit Price Total Price 1001 Air quality & dust Qty (1) a. The Contractor to protect stockpiles of friable material

More information

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project May 2018 Third Draft GEO: East West Highway (Khevi Ubisa Section) Improvement Project Section F2 of the Khevi Ubisa Shorapani Argveta Road (E60 Highway) Part 6 Appendices A D Prepared by JV IRD Engineering

More information

V: PROJECT SCOPING & METHODOLOGY

V: PROJECT SCOPING & METHODOLOGY V: PROJECT SCOPING & METHODOLOGY 5.0 INTRODUCTION The scoping exercise is carried out to define the focus and scope of the EIA Study. The scoping exercise is required to understand the type of activities

More information

VIE: Mong Duong 1 Thermal Power Plant

VIE: Mong Duong 1 Thermal Power Plant 7 th Independent Monitoring Report September 2011 VIE: Mong Duong 1 Thermal Power Plant Prepared by the Development Research and Consultancy Center (DRCC) for Viet Nam Electricity (EVN) Thermal Power Project

More information

Summary of Preliminary Study Result for Technical Cooperation Project

Summary of Preliminary Study Result for Technical Cooperation Project Summary of Preliminary Study Result for Technical Cooperation Project 1. Title of the Cooperation Project, Relevant Project Report The Project for Bridge Construction in Southeast Sulawesi Province Project

More information

Japanese ODA Loan. Ex-Ante Evaluation

Japanese ODA Loan. Ex-Ante Evaluation Japanese ODA Loan Ex-Ante Evaluation 1. Project Country: People's Republic of Bangladesh Name of the Project: Haor Flood Management and Livelihood Improvement Project Loan Agreement: June 16, 2014 Loan

More information

VIE: Power Transmission Investment Program -Tranche 3

VIE: Power Transmission Investment Program -Tranche 3 Environmental Monitoring Report # Quarterly Report January March 2018 VIE: Power Transmission Investment Program -Tranche 3 COVERING THE FOLLOWING SUBPROJECT (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) (ix)

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Copy Public Disclosure Copy Date ISDS Prepared/Updated: 04-Apr-2014

More information

Manningham Works Code of Practice

Manningham Works Code of Practice Manningham Works Code of Practice June 2017 Manningham City Council 699 Doncaster Road (PO Box 1) Doncaster Vic 3108 t 9840 9333 f 9848 3110 e manningham@manningham.vic.gov.au www.manningham.vic.gov.au

More information

C. Project Description [from section 3 of PCN] The proposed project would comprise of the following three components:

C. Project Description [from section 3 of PCN] The proposed project would comprise of the following three components: Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 02/17/2012 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014 The United States Forest Service (USFS), Shawnee National Forest (SNF), is analyzing a request from Ameren Services (Ameren), a group

More information

ENVIRONMENTAL IMPACT ASSESSMENT

ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized VIETNAM ELECTRICITY NATIONAL POWER TRANSMISSION CORPORATION ---------------------------------------------------------------

More information

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line

VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Environmental Monitoring Report Semestral Report July to December 2014 VIE: Power Transmission Investment Program, Tranche 1 220kV Song May-Uyen Hung Transmission Line Prepared by the Southern Vietnam

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

Environmental Checklist: 26. Forestry Projects(1) Confirmation of Environmental and Social Considerations. Environmental Item.

Environmental Checklist: 26. Forestry Projects(1) Confirmation of Environmental and Social Considerations. Environmental Item. Checklist: 26. Forestry Projects(1) 1. Permits and Approvals, Explanations 2. Antipollution Measures (1) ESIA and Permits (2) Explanations to the Public (1) Air Quality (2) Water Quality (3) Waste (4)

More information

The Northern Delta Transport Development Project (NDTDP) Environmental Management Process Framework For Phase 2 Investments

The Northern Delta Transport Development Project (NDTDP) Environmental Management Process Framework For Phase 2 Investments Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The Northern Delta Transport Development Project (NDTDP) Environmental Management Process

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized b Date ISDS Prepared/Updated: 13-Feb-212 1. BASIC INFORMATION INTEGRATED SAFEGUARDS DATA

More information

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process 10 January 2018 Introduction 1. Environmental and social screening is an essential and

More information

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item Checklist: 17. Roads, Railways and Bridges(1) 1. Permits and Approvals, Explanations (1) ESIA and Permits (2) Explanations to the Public Main Check s 1 Have ESIA reports been officially completed? Have

More information

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item

Environmental Checklist: 17. Roads, Railways and Bridges(1) Confirmation of Environmental and Social Considerations. Environmental Item Checklist: 17. Roads, Railways and Bridges(1) 1. Permits and Approvals, Explanations (1) ESIA and Permits (2) Explanations to the Public Main Check s 1 Have ESIA reports been officially completed? Have

More information

Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY PROJECT Rehabilitation works on the big arch of Krk Bridge

Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY PROJECT Rehabilitation works on the big arch of Krk Bridge Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY

More information

Environment Management Plan

Environment Management Plan Environment Management Plan Project Activity Pre Location of transmission towers and transmission line and Equipment specifications and parameters Transmission line Substation location and Location of

More information

WATERSHED. Maitland Valley. Report Card 201

WATERSHED. Maitland Valley. Report Card 201 Maitland Valley WATERSHED Report Card 201 The Maitland Valley Conservation Authority has prepared this report card as a summary on the state of our forests, wetlands, surface water, and ground water resources.

More information

Section 51 Light Industrial Zone

Section 51 Light Industrial Zone Section 51 Light Industrial Zone 51.1 ZONE DESCRIPTION The Light Industrial Zone is located outside and within the settlements of Pauanui, Tairua, Coromandel, Thames, Whangamata and Matarangi. The Zone

More information

CATEGORY a protection of the natural environment, its ecosystems and biodiversity.

CATEGORY a protection of the natural environment, its ecosystems and biodiversity. 29. ENVIRONMENTAL DEVELOPMENT PERMIT AREA CATEGORY a protection of the natural environment, its ecosystems and biodiversity. The requirement to obtain an environmental development permit is cited in Section

More information

Network utilities, subject to compliance with Part 6 (Infrastructure) A.3 Existing vegetation cover.

Network utilities, subject to compliance with Part 6 (Infrastructure) A.3 Existing vegetation cover. 5.3.2. Rural Zone 5.3.2.1. Permitted Activities 5.3.2.1.1. Residential, recreational, agricultural, exotic forestry or tourist related activities which comply with the standards for permitted activities

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized MINISTRY OF TRANSPORT DIRECTORATE FOR ROADS OF VIETNAM PROJECT MANAGEMENT UNIT 3 June

More information

ENVIRONMENTAL CHECKLIST (WAC )

ENVIRONMENTAL CHECKLIST (WAC ) Fee: $400.00 Date Fee Paid: Received by: 186 Iron Horse Court, Suite 101, Yakima WA 98901 Phone: (509) 834-2050 Fax: (509) 834-2060 Website: http://www.yakimacleanair.org ENVIRONMENTAL CHECKLIST (WAC 197-11-960)

More information

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous

Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous Proposed Terms of reference for EIA studies ToR for EIA studies in respect of the isolated storages, which are involved in handling of hazardous chemicals may include, but not limited to the following

More information

HOI HOP 110KV SUBSTATION

HOI HOP 110KV SUBSTATION Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized NPC NORTH POWER CORPORATION Electric Network Project Management Board -------------------------------

More information

ENVIRONMENTAL CODES OF PRACTICE (ECOP)

ENVIRONMENTAL CODES OF PRACTICE (ECOP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized HOA BINH PROVINCIAL PEOPLE S COMMITTEE DEPARTMENT OF HOA BINH AGRICULTURE AND RURAL DEVELOPMENT

More information

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E Ambassador Bridge Enhancement Project CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT Replacement Span and Plaza Expansion APPENDIX E DRAFT EROSION AND SEDIMENT

More information