1 (For BE Mechanical Engineering Students) (As per New Syllabus of Leading Universities) Dr SRamachandran, ME, PhD, Professor and Research Head Faculty of Mechanical Engineering SATHYABAMA UNIVERSITY Jeppiaar Nagar, Chennai AIR WALK PUBLICATIONS (Near All India Radio) 80, Karneeshwarar Koil Street Mylapore, Chennai Ph: , aishram2006@gmailcom, airwalk800@gmailcom wwwairwalkpublicationscom

2 First Edition : Second Edition : April 2016 and

3 POWER PLANT ENGINEERING SYLLABUS Unit 1: Coal Based Thermal Power Plants Rankine Cycle - Improvisations - Layout of modern coal power plant, Supercritical Boilers, FBC boilers, Turbines, Condensors, Steam and Heat rate, Subsystems of Thermal power plants - Fuel and handling, Draught system, Feed water treatment, Binary cycles and Cogeneration systems Unit 2: Diesel, Gas Turbine and Combined Cycle Power Plants Otto, Diesel, Dual and Brayton Cycle - Analysis and Optimisation, Components of Diesel and Gas Turbine power plants Combined Cycle Power Plants Integrated Gasifier based Combined Cycle systems Unit 3: Nuclear Power Plant Basics of Nuclear Engineering, Layout and subsystems of Nuclear Power Plants, Working of Nuclear Reactors : Boiling Water Reactor (BWR), Pressurized Water Reactor (PWR), CANada Deuterium- Uranium reactor (CANDU), Breeder, Gas Cooled and Liquid Metal Cooled Reactors Safety measures for Nuclear Power plants Unit 4: Power from Renewable Energy Hydro Electric Power Plants - Classification, Typical Layout and associated component including Turbines Principle, Construction and working of Wind, Tidal, Solar Photo Voltaic (SPV), Solar Thermal, geo Thermal, Biogas and Fuel Cell power systems Unit 5: Energy, Economic and Environmental issues of Power Plants Power tariff types, Load distribution parameters, load curve, Comparison of site selection criteria, relative merits & demerits, Capital & Operating Cost of different power plants Pollution control technologies including Waste Disposal Options for Coal and Nuclear Power Plants

4 Contents I Coal Based Thermal Power Plants 1 11 Rankine Cycle (Simple Steam Power Cycle) Improvisations - Modern Trends in Rankine Cycle Improvements Reheat Cycle Advantages (or) effects of Re-heating Disadvantages Methods of Reheating Gas Reheating Live-Steam Reheating Combined gas and live steam reheater Regenerative Cycle (Bleeding Cycle) Advantages of Regenerative cycle Layout of Modern Coal Power Plant (or) Layout of Steam Power Plant Coal and ash Circuit Air and Flue gas circuit Feed water and steam flow circuit Cooling Water Circuit Selection of Site For A Steam Power Plant Super Critical Boilers Benson Boiler Loefler Boiler Velox boilers Fluidized Bed Combustion (FBC) Boilers 159

5 2 181 Conversion of Oil fired boilers to fluidized bed boilers Types of Fluidised Bed Combustion system 163 (i) Bubbled fluidised bed combustion system 163 (ii) Circulating Fluidised Bed Combustion system (CFBC) 166 (iii) Pressurised Fluidised Bed Combustion system Steam Turbines Types of steam turbine Impulse Turbine Reaction turbine Velocity diagram for reaction turbine blade Degree of reaction Steam Condensers Jet condensers Surface condenser Capacity of a Steam Power Plant Sub System of Thermal Power Plant Boiler Accessories Cooling tower Type of Cooling towers Atmospheric (or) natural draft cooling towers Mechanical Draft Cooling Towers1107

6 Air Cooled or Dry-type Cooling System Boiler Mountings Fuel and Ash Handling Handling of coal Ash handling and dust collecting system Draught Classification of Draught Natural draught Artificial draught Forced draught Induced draught Balanced draught Stockers Overfeed stokers Under feed stokers Pulveriser Unit (or) Direct system BIN (or) Central System Feed Water Treatment Need for feed water treatment Arrangements for Feed Water Treatment Binary Vapour Cycle Waste Heat Recovery / Cogeneration System 1168 Waste Heat Boilers 1169

7 4 2 Diesel, Gas Turbine and Combined Cycle Power Plants 21 Otto Cycle Diesel Cycle Mixed/Dual Cycle Brayton Cycle Diesel Engine Power Plant Types of Diesel Power Plants Layout of Diesel Power Plant Diesel Engine Used For Diesel Power Plants Selection of Engine Type Super charging Gas Turbine Power Plant Gas turbine Classification of Gas Turbine Power Plants Layout of Open Cycle Gas Turbine Power Plant Working of Gas Turbine Power Plant Fuels For Gas Turbines Fuel qualities Gas Turbine Materials Open and Closed Cycles Open cycle gas turbine Closed cycle gas turbine Reheating, Regeneration and Intercooling Intercooling Reheating 264

8 Regeneration Combined Power Cycles Combined Gas Turbine and Diesel Cycles Integrated Gasifier Based Combined Cycle (IGCC) System Nuclear Power Plant 31 Introduction Basics of Nuclear Engineering Radioactivity Nuclear Reactions Nuclear Fission and Chain Reaction Layout of Nuclear Power Plant Site Selection For A Nuclear Power Plant Nuclear Reactor Boiling Water Reactor (BWR) Pressurized Water Reactor (PWR) CANada Deuterium Uranium (CANDU) reactor Gas Cooled Reactor Fast Breeder Reactor Liquid Metal Cooled Reactor Safety Measures For Nuclear Power Plant Power From Renewable Energy 41 Hydel Power Plants Essential Elements of Hydel Power Plant Site Selection For Hydel Power Plant Working of Hydro Electric Power Plant 424

9 6 45 Classification of Hydraulic Turbines Impulse turbine Working of a Pelton Wheel Reaction turbine Francis Turbine Axial Flow Reaction Turbines Working Principle of A Kaplan Turbine Turbine Governing Working of oil pressure governor Selection of Turbine Micro Hydel Development Components of Micro hydel power plant Power from a micro hydro plant Suitable conditions for micro-hydro power Turbines for micro hydro power Turgo Turbine Working of Turgo Turbine Load factor Load control governors Electrical power from micro hydro plant Economics of micro hydel plant Low cost grid connection Advantages of Micro hydro plant Wind Energy and Wind Power Advantages of Wind energy Disadvantages of Wind energy 463

10 Characteristic of a good wind power plant site Wind-Electrical generating power plant Wind Turbine Types Types of wind mills Performance of wind machine Tidel Power Plant Pumped Storage Types of pumped storage plant Solar Power Plants Solar Central Receiver system 487 Heliostats (Mirrors) Solar Photovoltaics (SPV) Geo Thermal Power Plant Geothermal sources Hydrothermal convective system Ocean Energy Conversion (OTEC) Plant Types of OTEC Closed-cycle OTEC System Open-Cycle OTEC system Hybrid OTEC System Important points about OTEC Biogas Power Plant Fuel Cell MHD Power Plant Open cycle MHD 4120

11 8 2 Closed cycle MHD Closed Cycle MHD with Liquid metal Energy, Economic and Environmental Issues of Power Plants 51 Economics in Plant Selection Important Terms and Definitions Economics of Power Generation Land, building and equipment cost and installation cost Depreciation cost 512 (i) Straight line method 512 (ii) Sinking fund method 513 (iii) Diminishing value method Insurance Management cost Operating cost Total cost 516 Customer charges Cost of power generation Power Tariffs Aim of tariffs Selection of tariffs Types of tariffs Flat demand rate Straight line meter rate Step meter rate 521

12 9 4 Block meter rate Two-part tariff or Hopkinson demand rate Three-part tariff (or) Doherty rate Wright demand rate Choice of Power Plant and its Site Electric Load (or) Power Distribution System Load Duration Curves Important terms and definition 534 (i) Load curve 534 (ii) Residential load 534 (iii) Industrial load 535 (iv) Municipal load 535 (v) Irrigation load 535 (vi) Traction load 535 (vii) Commercial load 535 (a) Residential load curve 535 (b) Industrial load curve for one shift 536 (c) Municipal load curve 536 (d) Traction load curve 537 (e) Commercial load curve 538 (f) Load duration curve Pollution and its Control Air Pollution by Thermal Power Plants Control of Atmospheric Pollution by Thermal Power Plants 544

13 Water Pollution By Thermal Power Plant and its Control Instrument used to monitor pollution CO 2 recorders Automatic controls for feed water Automatic combustion control Indian Boiler Act Boiler Inspection Boiler Performance Boiler Testing Boiler Trial Boiler safety regulations as per Indian Boiler Act Nuclear Waste Disposal and Safety 568

14 Chapter - I COAL BASED THERMAL POWER PLANTS 11 RANKINE CYCLE (Simple Steam Power Cycle) Rankine Cycle - Improvisations - Layout of modern coal power plant, Supercritical Boilers, FBC boilers, Turbines, Condensors, Steam and Heat rate, Subsystems of Thermal power plants - Fuel and handling, Draught system, Feed water treatment, Binary cycles and Cogeneration systems Rankine cycle is the theoretical cycle on which the steam turbine (engine) works Boiler Refer the process (4) to (1): Feed water is passing to the boiler Heat is added to the water in the boiler The water gets heated and becomes dry saturated steam (or) super heated steam Turbine Refer the process (1) to (2): The high pressure steam is expanding in the turbine, thus work is produced ie The turbine rotates The steam leaves the turbine as low pressure steam Condenser: Condenser is used to convert the low pressure steam into water Refer the process (2) to (3) The low pressure steam is passing through condenser where heat is liberated from the steam So the steam becomes water To cool the steam, separate cooling water is circulated through condenser from the cooling tower This cooling water and the steam will not mix together in most of the condensers

15 12 Power Plant Engineering - wwwairwalkpublicationscom High Pressure Water (4) (4) Boiler High Pressure Steam (1) Q in W in Pump Steam Turbine W out (3) Low Pressure Steam (2) Condenser Low Pressure Water (3) (2) Low Pressure Steam Q out Fig:11 (a) Pump Refer the process (3) to (4) The water leaving condenser is pumped to the boiler by pump Usually, pump work is neglected since it is very small work when compared to turbine work output W = h -h p 4 3 T 4 3 = 1 4 p p Q s = h1-h4 p =p 2 3 p =p 1 4 Fig:11 (b) s = s W = h -h T 1 2 S

16 Coal Based Thermal Power Plants Turbine work Turbine work output (Isentropic expansion in Turbine) W T h 1 h 2 kj/kg Turbine power m h 1 h 2 kw where m Mass flow rate of steam in kg/sec h 1 and h 2 can be taken from steam table for p 1 and p 2 respectively (p 1 high pressure (or) boiler pressure (or) inlet to turbine pressure) (p 2 low pressure (or) condenser pressure) Also, we can use Mollier diagram to find h 1 and h Constant pressure condensation Q 2 Heat rejected h 2 h 3 kj/kg Q 2 in kw m h 2 h 3 kw h 3 h f at low pressure p 2 3-4: Pump Work W pump W p h 4 h 3 kj/kg v f p 1 p 2 kj/kg where v f for p 2 from steam table p 1 and p 2 in kpa Pump power m W p Net Work W net W T W p W T If W p is negligible

17 14 Power Plant Engineering - wwwairwalkpublicationscom Thermal Efficiency: It is the ratio of net work done to the heat supplied W net cycle or rankine or thermal Q supply 4-1 Heat Supplied in Boiler: Q supply (Constant pressure heat supply) Q supply h 1 h 4 kj/kg Q supply in kw m h 1 h 4 kw Specific steam consumption SSC (or) steam flow rate per kw 3600 W net kg kwhr Work ratio W net W T Problem 11: A steam turbine receives steam at 15 bar and 350C and exhausts to the condenser at 006 bar Determine the thermal efficiency of the ideal rankine cycle operating between these two limits Neglect the pump work Solution p 1 15 bar; t 1 350C; p bar Boiler pressure From Mollier diagram, Condenser pressure h kj; h kj/kg; h 3 h f for 006 bar 1515 kj/kg h 4 h 3 W p h kj/kg [ W p is negligible ] W net W T h 1 h kj/kg Q s h 1 h 4 h 1 h kj/kg [ h 4 h 3 ]

18 Coal Based Thermal Power Plants 15 h Mollier Diagram h =31475kJ/kg o c 1 5 bar h =21881kJ/kg bar Fig:12 s rankine W net Q s % Problem 12: In a rankine cycle, the steam flows to turbine as saturated steam at a pressure of 35 bar and the exhaust pressure is 02 bar Determine (using steam table only) (i) pump work (ii) the turbine work (iii) the rankine efficiency (iv) the condenser heat flow (v) the dryness fraction at the end of expansion The mass flow rate of steam is 95 kg/sec Solution p 1 35 bar dry saturated; p 2 02 bar; m 95 kg/sec To Find h 1 h 1 h g for 35 bar 2802 kj/kg To Find x 2 s 1 s g for 35 bar = 6123 kj/kg K Isentropic expansion So, s 1 s 2

19 16 Power Plant Engineering - wwwairwalkpublicationscom So, s kj/kg K T But at 02 bar, s g 7909 kj/kg K p=p=35bar Since s s g, 7909 it is wet steam at exit of turbine 4 3 p=p=02bar So, s 2 s f x 2 s fg for 02 bar Fig:13 S x x Dryness fraction at the exit of turbine x To Find h 2 h f 2515 ; h fg for 02 bar h 2 h f x 2 h fg for 02 bar kj/kg To Find h 3 h 3 h f for 02 bar To Find h 4 v f m 3 /kg for 02 bar h 4 h 3 W p W p v f3 p 1 p kj/kg h kj/kg

20 Coal Based Thermal Power Plants 17 To Find Pump Work W p 354 kj/kg Pump power m W p kw To Find Turbine Work W T h 1 h Turbine power m W T kw To Find Rankine Efficiency rankine W net Q s Q s h 1 h kj/kg W net W T W p kj/kg rankine % To Find Condenser Heat Flow Q rej Q rej h 2 h kj/kg Q rej in kw m h 2 h kw Problem 13: Steam at 10 MPa and degree of super heat of 90C is supplied to a rankine cycle The condenser pressure is 10 KPa For mass rate of flow of 1 kg/sec determine (i) Power output (ii) thermal Solution h kj/kg; h kj/kg from Mollier diagram

21 18 Power Plant Engineering - wwwairwalkpublicationscom h 3 h f3 for 01 bar 1918 kj/kg W p h 4 h 3 v f3 p 1 p 2 v f for 01 bar h 4 h 3 v f3 p 1 p kj/kg [ 10 2 for making bar into kpa] To Find W T, W p and Q s W T h 1 h kj/kg W p v f kj/kg W net W T W p kj/kg Q s h 1 h kj/kg Power output m W net kw thermal W net Q s % T 1 90 o c h h = 3100kJ/kg ba r 40 1 c o o 90 c 4 p 2=01bar 3 2 h = 1975kJ/kg c o 01 ba r Fig:14 (a) s Fig:14 (b) s

22 Coal Based Thermal Power Plants 19 Problem 14: Dry saturated steam at 15 bar is supplied to a rankine cycle where exhaust pressure is 1 bar Find (a) thermal (rankine), steam consumption per kw, carnot (b) If the exhaust pressure is reduced to 02 bar by introducing a jet condenser, then determine % increase in rankine efficiency and % decrease in SSC (Apr 96-Madras University) Solution Given: p 1 p 4 15 bar; p 2 p 3 1 bar; Initially dry saturated rankine W net Q supply W T W p Q s W T h 1 h 2 W p h 4 h 3 v f p 1 p 2 Q s h 1 h 4 Find h 1, h 2, h 3 and h 4 h 1 h g for p 1 15 bar 2790 kj/kg from steam table (or) from Mollier chart, hs diagram T p = p 1 4 h 1 - h 4 p =p h = h 1 5bar 1 1 bar W P=h 4-h p =p 2 3 s=s Fig:15 (a) W =h -h T 1 2 s h = Saturated Curve S 1=S2 Fig:15 (b) s

23 110 Power Plant Engineering - wwwairwalkpublicationscom 15 bar line will cut saturated curve at (1) Draw vertical line from (1) This vertical line will cut the 1 bar line at (2) h kj/kg h 3 h f (for 1 bar from steam table) = 4175 kj/kg v f m 3 /kg (for 1 bar) h 4 h 3 v f p 1 p 2 h 4 h 3 v f p 1 p kj/kg [15 bar and 1 bar are multiplied by 10 2 to make KPa 1 bar 100 KPa ] To Find W T, W p and Q s W T h 1 h kj/kg W p v f p 1 p kj/kg Q s h 1 h kj/kg To Find rankine rankine W net Q s W T W p Q s % To Find Specific Steam Consumption (SSC) SSC kj/kwhr W net 44854

24 Coal Based Thermal Power Plants 111 To Find carnot T carnot T max T min T max For 15 bar, t sat t max 1983 C 273 p=p= 15bar K 4 For 1 bar, t sat t min 9963 C K 3 p=p=02bar 2 3 Fig:16 (a) 2 S carnot % Case (b) When p 2 02 bar h 3 h f for 02 bar 2515 kj v f m 3 /kg (for 02 bar) h 4 h 3 v f3 p 1 p 2 h kj/kg W T h 1 h kj/kg W p v f3 p 1 p kj/kg W net W T W p kj/kg Q s h 1 h kj/kg New rankine rankine W net Q s %

25 112 Power Plant Engineering - wwwairwalkpublicationscom Increase in rankine efficiency New SSC 393% SSC 3600 W net kg/kwhr h h = h = ba r 02 bar Decrease in SSC % Fig:16 (b) s 12 IMPROVISATIONS - MODERN TRENDS IN RANKINE CYCLE IMPROVEMENTS Rankine Cycle - Reheating and Regenerative cycle 121 Reheat Cycle: If the dryness fraction of steam leaving the turbine is less than 088, then corrosion and erosion of turbine blades occur To avoid this situation, reheat is used In the reheat cycle, the expansion of steam takes place in one (or) more turbines Steam is expanded in the HP turbine first, then it is reheated The reheated steam is again expanded in the LP turbine Reheat cycle gives small increase in cycle efficiency It increases the net work output Reheating means heating the steam between turbine stages (between HP stage and LP stage) P 1 - Boiler pressure; P 2 P 3 = Reheat pressure; P 4 = Condenser pressure; T 1 = boiler temperature (or) superheat temperature; T 3 = Reheat temperature

26 Coal Based Thermal Power Plants Reheater 2 6 Boiler 1 HPT LPT Pump 5 Condenser Fig:17 T Fig:18 (a) S h 6 1 p =C 5 1 T 1 p =C 4 3 p 2 =p =C 4 Fig:18 (b) 3 T 3 s Note: If T 3 is not given, then we can assume T 3 T 1

27 114 Power Plant Engineering - wwwairwalkpublicationscom h 1, h 2, h 3, h 4 - Take from mollier chart h s diagram) (or) from steam table h 5 h f for condenser pressure W p h 6 h 5 v f P 1 P [ v f sp volume of fluid at condenser pressure] W T h 1 h 2 h 3 h 4 W p h 6 h 5 W net net work W T W P Q s heat supplied h 1 h 6 h 3 h 2 thermal W net Q s The ordinary Rankine cycle efficiency can be increased by increasing the pressure and temperature of the steam entering into the turbine When the initial pressure increases, the expansion ratio in the turbine also increases, and the steam becomes quite wet at the end of expansion This is not desirable because the increased moisture content of the steam causes corrosion in the turbine blades and so increase the losses Due to this, the nozzle and blade is decreased In reheat cycle, the steam is taken out from the turbine and it is heated by the flue gases in the boiler The main purpose of reheating is to increase the dryness fraction of steam passing through the lower stages of the turbine The dryness fraction of steam coming out from the turbine should not fall below 088 By using the

28 Coal Based Thermal Power Plants 115 reheat cycle, the specific steam consumption decreases and thermal also increases The increase in thermal due to reheat depends upon the ratio of reheat pressure to original pressure of steam The reheat pressure is generally kept within 20% of the initial pressure of steam: At low pressure, the of the cycle is reduced It is preferred for only high capacity plants, (or) 50,000 kw and the steam pressure range is 100 kgf/cm 2 ab 122 Advantages (or) effects of Re-heating Due to reheating, net work done increases Due to reheating, heat supply increases Due to reheating, thermal efficiency increases Due to reheating, the turbine exit steam dryness fraction increases - so moisture decreases - so blade erosion becomes minimum - so life of the turbine will be increased It reduces the fuel consumption upto 4 to 5% The size of the low pressure turbine blades can be reduced It reduces the steam flow of 15 to 20% with corresponding reductions in boiler, turbine and feed water heating equipments It also reduces the pumping power Less costly materials are used for lower steam pressures and temperatures to obtain required thermal efficiency It has higher thermal

29 116 Power Plant Engineering - wwwairwalkpublicationscom It has reduced feed pump power The condenser and boiler sizes are small The turbine has a very long life 123 Disadvantages: This cycle is more expensive than simple Rankine cycle It occupies more space The second stage turbine blade s design is complicated and expensive The operation and control reheat rankine cycle is complicated At light loads, the superheated steam will overheat the blades To avoid this, the feed water should be sprayed on the blades 13 Methods of Reheating: (a) Gas reheating (b) Live-steam reheating (c) Combined gas live steam reheater 131 Gas Reheating The steam taken from the high pressure turbine (HP) turbine is sent back to the reheater to reheat the steam to its initial throttle temperature The reheater is normally placed after the superheater so that the superheater receives the flue gases first and then the reheater receives flue gases Since the reheater should operate at much smaller temperature difference between the gas and steam, the counter flow heat exchanger is used for reheating

30 Coal Based Thermal Power Plants 117 To make the steam to be reheated to its initial throttle temperature in this gas reheating system, the following disadvantages are faced 1 Long and large pipe connections are required and hence cost is more and the pressure drop becomes higher Boiler To condenser Super heater HP LP Reheater Fig:19 Steam Reheating with Flue Gases 2 For piping system, the expansion and contraction allowances should be given 3 The amount of steam stored within the piping and reheater may cause considerable rise in turbine speed and it leads to accident in case of failure of emergency control 132 Live-Steam Reheating: The live steam reheating circuit is shown in Fig110 The high pressure steam from the superheater is used for reheating the steam coming out from the HP turbine in a specially designed reheater

31 118 Power Plant Engineering - wwwairwalkpublicationscom Boiler High Pressure Steam for Reheating HPT LPT Super Heater Live Steam Reheater Condensate Fig:110 Steam Reheating with Live Steam The advantages of live-steam reheating over gas heating are given here 1 The operation of this reheating system is simple 2 The reheater can be placed near the HP turbine and minimise extra pipe fittings 3 The control of temperature is easy since varying combustion condition will not affect the live steam reheater performance 4 Wet steam can also be reheated 5 More than one reheating can be used since the piping requirements are less 133 Combined gas and live steam reheater The combined gas and live steam reheater system is shown in Fig111 Live steam reheating system does not allow the steam to be reheated to its initial throttle temperature By using combined reheating system, this problem can be solved The live steam reheating system is

32 Coal Based Thermal Power Plants 119 Boiler To condenser HPT SH LPT Gas Reheater Live Steam Reheater Condensate Fig:111 Combined Live Steam and Reheating System placed in series with the gas reheater The steam extracted from HP turbine is first sent to live steam reheater and then to gas reheater as shown in fig In order to maintain a constant final temperature, the supply of live steam to first reheater is thermostatically controlled Problem 15: Steam at 90 bar, 480C is supplied to a steam turbine The steam is reheated to its original temperature by passing it through a reheater at 12 bar The condenser pressure is 007 bar Steam flow rate is 1 kg/sec Determine (a) network output; (b) thermal [neglect the pressure loss in reheating and boiler The expansion is isentropic (FAQ) Given: p 1 boiler pressure 90 bar; T 1 boiler temperature 480C T 3 Reheat temperature T 1 given 480C

33 120 Power Plant Engineering - wwwairwalkpublicationscom p 4 condenser pressure 007 bar From mollier chart, h kj/kg h kj/kg h 6 a p =90 1 o T 1= b p =12 3 h kj/kg h kj/kg 5 p =007 c 4 h 5 h f for Fig:112 (a) s h 6 h 5 v f p a p c 100 v f for condenser pressure h W T h 1 h 2 h 3 h kj/kg W p h 6 h kj/kg W net W T W p kj/kg Q s h 1 h 6 h 3 h kj/kg kj/kg thermal W net Q s

34 Coal Based Thermal Power Plants 121 Extra Compare network done & efficiency of the above cycle with that of the simple cycle The simple cycle is shown here h kj/kg h kj/kg h 3 h f for condenser pressure 1634 kj/kg h 4 h 3 v f P a P c 100 [v f for condenser pressure P c ] h W T h 1 h kj/kg W P h 4 h kj/kg W net W T W p kj/kg Q s h 1 h kj/kg thermal Q s W net h o T 1=480 thermal % Note: reheat cycle p =9 0 a o 1 W net kj/kg thermal 4208% 4 p =007 c 2 Because of reheating, work output increases and also thermal efficiency 3 Fig:112 (b) s

35 122 Power Plant Engineering - wwwairwalkpublicationscom Problem 16: In the reheat cycle, steam at 150 bar and 550C enters into the HP turbine The condenser pressure is 01 bar The moisture content at condenser inlet is 5% Determine (a) reheat pressure; (b) cycle efficiency; (c) steam flow rate per KW [FAQ] Solution Hint: condenser inlet is condition (4) x Assumption T 3 T 1 h kj/kg h kj/kg h kj/kg h 6 1 p =150bar 2 T 1 1 p =01 bar 5 Fig:112 (c) 4 4 T 3 = 550 o C 3 x=095 4 s h kj/kg h 5 h f for condenser pressure v c 1918 kj/kg h 6 h 5 v f p 1 p [v f is for condenser pressure 01 bar] h h kj/kg (a) P 3 reheat pressure 1275 bar W T h 1 h 2 h 3 h kj/kg

36 Coal Based Thermal Power Plants 123 W p h 6 h kj/kg W net W T W p kj/kg Q s h 1 h 6 h 3 h Q s kj/kg (b) thermal (c) SSC q s W net W net kg kw hr Problem 17: In a reheat rankine cycle, the condenser pressure is 75 bar The boiler temperature and reheat temperature are 500C The moisture content at any stage should not exceed 15 % Determine (a) Boiler pressure; (b) reheat pressure; (c) work done; (d) thermal Solution x 2 x [moisture is 15%] 100 Condenser Pressure P c 75 KPa 0075 bar From mollier chart h kj/kg h 1 T =T = 550 c o h kj/kg P 1 h kj/kg h kj/kg h 5 h f for p c kj/kg P = Fig:112 (d) x =x = s

37 124 Power Plant Engineering - wwwairwalkpublicationscom h 6 h 5 v f p 1 p h h kj/kg (a) boiler pressure P bar; (b) reheat pressure P 2 38 bar W T h 1 h 2 h 3 h kj/kg W p h 6 h kj/kg (c) W net W T W p kj/kg Q s h 1 h 6 h 3 h Q s kj/kg (d) the Q s W net 4478 % Problem 18: Steam at a pressure of 10 MPa, 500C is supplied to a reheat rankine cycle After expansion in the HPT, the steam is reheated at an optimum pressure to an optimum temp The moisture content at LPT exit should not exceed 15% Network done is 1600 KJ/Kg Determine (a) heat supply per kg; (b) thermal Condenser pressure is 7 kpa Solution Hint: Dont assume T 1 T 3 because steam is reheated to optimum temperature P 2 is not given, reheat temperature is not given

38 Coal Based Thermal Power Plants 125 P c P 4 pressure = 007 bar condenser The moisture content m in LP turbine is 15% (ie) x h kj/kg h kj/kg h 5 h f for 007 bar h 6 1 P =1 00bar T = 500 c 1 o P =007bar 4 Fig:113 4 T 3 3 x=085 2 s h kj/kg h 6 h 5 v f p 1 p v f for p c h W T h 1 h 2 h 3 h 4 W p h 6 h kj/kg W net 1600 kj/kg h 1 h 2 h 3 h 4 h 6 h 5 W net W T W P ; W T W net W p W T kj/kg W T h 1 h 2 h 3 h 4 h 1 h 4 h 3 h h 3 h 2

39 126 Power Plant Engineering - wwwairwalkpublicationscom h 3 h KJ/Kg Q s h 1 h 6 h 3 h Q s KJ/Kg thermal W Q s the 43876% Problem 19: In an reheat rankine cycle steam at 3 MPa, 450C is supplied to a HPT The reheat temperature is 450C Condenser pressure is 4 KPa The HPT expansion is limited with dry & saturation Determine (a) reheat pressure; (b) net work; (c) the Solution From Mollier Chart h kj/kg h kj/kg h o c 3 h kj/kg h kj/kg h 5 h f for P c P kj/kg 6 1 p =30bar 5 2 Dry & Saturation p =004 bar 4 Fig:114 4 s h 6 h 5 v f p 1 p h h kj/kg

40 Coal Based Thermal Power Plants 127 (a) reheat pressure 25 bar W T h 1 h 2 h 3 h kj/kg W p h 6 h kj/kg W net W T W p kj/kg Q s h 1 h 6 h 3 h kj/kg the W Q s the 3853% Problem 110: A steam power plant uses the Reheat cycle Steam Inlet to turbine 150 bar, 550C Reheat at 40 bar to 550C Condenser pressure is at 01 bar Using mollier diagram, find (i) the dryness fraction of steam at exit of turbine (ii) cycle efficiency (iii) specific steam consumption SSC Solution From mollier chart, T p =150 bar o c 1 3 h kj/ kg; h kj/kg; h kj/kg h kj/kg; x p =40 bar 2 6 p 3=01 bar 5 4 Fig:115 (a) 2 x 4 S h 5 h f at 01 bar from steam table 1918 kj/kg

41 128 Power Plant Engineering - wwwairwalkpublicationscom Pump work W p W p v f P 1 P [ ] 1499 kj/kg W p h 6 h h o c h 6 h kj/kg 6 5 p =150 bar 1 2 p =40 bar 2 P =01 bar 3 4 x 4 s Heat supplied Q s Fig:115 (b) Q s h 1 h 6 h 3 h kj/kg Turbine Work W T W T h 1 h 2 h 3 h kj/kg Net work donew net W net W T W P kj/kg cycle W net Q s Specific steam consumption SSC W net % 2182 kg/kwhr

42 Coal Based Thermal Power Plants REGENERATIVE CYCLE: (Bleeding Cycle) Assume 1 kg of steam is expanded in the turbine Before complete amount of steam is expanded, some amount of steam (m kg) is extracted (this process is called bleeding) and utilized for heating the feedwater So remaining amount of steam 1 m kg is completely expanded in the turbine and condensing in condenser In the regenerator, m kg of high temperature steam and 1 m kg of condensate are passing Heat transfer from steam to condensate (feed water) takes place So this process increases the enthalpy of feed water Thus the heat supplied to boiler will be reduced Re-generation means heating the feed water by steam taken from the turbine The steam is exhausted (or) bled from the turbine at several locations (before exhaust) and is supplied to regenerator (feed water heater) to heat the feed water Extracting the steam in the turbine before exhaust is called bleeding 1kg 7 Boiler 1kg 1 T Pump 2 mkg 2 bleeding mkg 3 (1-m)kg Condenser 1kg 6 Heat Exchanger (or) Regenerator (or) Feed Water Heater (1-m)kg (1-m)kg 5 Pump 1 4 Fig:116

43 130 Power Plant Engineering - wwwairwalkpublicationscom Energy - balance Assume 1 kg of working fluid is circulated Energy in = Energy out m mass of steam bled mass of steam circulated Energy entering regenerator = Energy leaving regenerator m h 2 1 m h 5 1 h 6 m h 2 h 5 mh 5 h 6 m h 2 h 5 h 6 h 5 mass of steam bled mass of steam circulated m h 6 h 5 kg of steam bled h 2 h 5 kg of steam circulated Take h 1, h 2, h 3 from mollier diagram h s diagram) (or) from steam table h 4 h f for condenser pressure p 3 p 4 h 6 h f for regenerator pressure p 6 p 2 p 5 h 5 h 4 v f p 6 p [ p is in bar; p 10 2 kpa] [v f for condenser pressure P c P 3 P 4 ] h 7 h 6 v f p a p b 10 2 [p b for regenerator pressure p b and v f for P b W T 1 h 1 h 2 1 m h 2 h 3

44 Coal Based Thermal Power Plants 131 h 1 T mkg 1 kg p =C (1-m ) (1-m) p =C a b p =C c 1kg 2 (1-m) 3 h 7 1kg kg mkg 2 (1-m) (1-m) 3 4 Fig:117 (a) s Fig:117 (b) s W P h 5 h 4 1 m 1 h 7 h 6 W net W T W P Q s h 1 h 7 thermal W net Q s Problem 111: A steam turbine plant equipped with a single regenerative feed water heating operates with the following data Initial pressure 165 bar; Initial super heat 93C; Extraction pressure 2 bar; exhaust pressure 005 bar Compare regenerative and non-regenerative cycle for (a) the ; (b) network; (c) SSC [Frequenty Asked University Questions] Solution Given data: P a P bar t sat C Degree of superheat 93C t 1 t sat 1 t C

45 132 Power Plant Engineering - wwwairwalkpublicationscom P b regenerative pressure 2 bar P 2 P c condenser pressure 005 bar Case (a) non-regenerative (simple cycle) From mollier chart, h p =165 bar 1 1 o T 1=2959 c h kj/kg; 4 h kj/kg; h 3 h f for P kj/kg p = h 4 h 3 v f P 1 P v f for P 2 h h kj kg W T 1 h 1 h kj/kg W p h 4 h W p W net W T W p kj/kg Fig:118 (a) s Q s h 1 h kj/kg thermal W net Q s 3223%

46 1 1 SSC 3600 W net Case (b) regenerative cycle Coal Based Thermal Power Plants kg/kwhr h kj/kg h 1 o T 1=296 c h kj/kg h kj/kg h 4 h f forp c 7 1kg 6 p =165 bar=p a 1 mkg p =2bar b 1kg 2 (1-m) 1378 kj/kg h 5 h 4 v f P b P c (1-m ) 4 p =005 c 3 Fig:118 (b) s h kj/kg h 6 h f for 2 bar P b h kj/kg h 7 h 6 v f P a P b 100 h h kj/kg W T 1 h 1 h 2 1 m h 2 h m m h 6 h h 2 h

47 134 Power Plant Engineering - wwwairwalkpublicationscom m 0148 kg of steam bled kg of steam circulated W T kj/kg W p h 5 h 4 1 m 1 h 7 h kj/kg W p 171 kj/kg W net W T W p kj/kg Q s h 1 h kj/kg the W Q s % SSC 1 W net kg/kwhr Simple cycle W net kj/kg Regenerative cycle W net kj/kg the % the 3392% Note: Work out put slightly decreases and efficiency increases Problem 112: A steam turbine operates on a simple regenerative cycle Steam is supplied dry saturated at 40 bar and exhausted to condenser pressure of 007 bar The condensate is pumped to a pressure of 35 bar at which it is mixed with bled steam from the turbine at 35 bar The resulting water at saturation is then pumped to the boiler For

48 Coal Based Thermal Power Plants 135 the ideal cycle, calculate (a) the amount of steam bled per kg of supply steam and (b) the of the plant, neglecting pump work (FAQ) Solution h kj/kg h kj/kg h kj/kg h p =40bar a p =35bar b 1 2 h 4 h f for p c 1634 kj/kg p =00 7 c 3 h 4 h 5 Neglecting pump work h 6 h f for p b 35 bar 5843 kj/kg h 6 h 7 Neglecting pump work Fig:119 s m h 6 h h 2 h kg of steam bled kg of steam circulated W T 1 h 1 h 2 1 m h 2 h W T W net KJ/Kg [ W p is neglected ] Q s h 1 h kj/kg

49 136 Power Plant Engineering - wwwairwalkpublicationscom the W Q s % Problem 113: A ideal regenerative cycle operates with steam supplied at 30 bar and 400C and condenser pressure of 010 bar For this cycle, find (a) W T in KJ/Kg; (b) cycle efficiency; (c) steam rate in Kg/KW hr The feed water heater can be assumed to be direct contact type which operates at 5 bar (FAQ) 30 bar 400 o c 1kg 1 Turbine Boiler 5 bar m kg 5 bar 2 01 bar 3 condenser Heater Pump 5 Pump 1kg (1-m)kg Fig:120 Solution h kj/kg h kj/kg h kj/kg h 4 h f for P c 1918 kj/kg

50 Coal Based Thermal Power Plants 137 T bar 1kg 5 bar mkg 1 T 1 = 400 o c 1kg 2 (1-m) kg h 7 1kg p = 6 a 3 0bar p = 5 ba r b (m kg) 1 1kg 2 (1-m) bar (1-m) kg Fig:120 (a) 3 S 5 (1-m) p c= Fig:120 (b) 3 s h 5 h 4 v f P b P c 100 h h kj/kg h 6 h f for P b 6401 kj/kg h 7 h 6 v f P a P b 100 h h kj/kg m h 6 h h 2 h kg of steam kg of steam circulated W T h 1 h 2 1 m h 2 h W T kj/kg

51 138 Power Plant Engineering - wwwairwalkpublicationscom W P 1 m h 5 h 4 h 7 h kj/kg W net W T W p kj/kg Q s h 1 h kj/kg the W Q s 3587% SSC W net kj/kwhr Problem 114: A steam turbine plant, working on a single stage of regenerative feed heating receives steam at 3 MPa and 300C The turbine exhausts to a condenser at 15 KPa while the bled steam is at 300 KPa Assuming that the cycle uses actual regenerative cycle, calculate the thermal efficiency of cycle Compare this value with a rankine cycle operating between same boiler and condenser pressures (FAQ) h kj/kg; h kj/kg; h kj/kg; h 4 h f forp c 226 kj/kg h 5 h 4 v f p b p c 100 h h kj/kg h 6 h f for P b 5615 kj/kg h h kj/kg

52 Coal Based Thermal Power Plants 139 m h 6 h h 2 h kg of steam bled kg of steam circulated W T h 1 h 2 1 m h 2 h kj/kg W p 1 m h 5 h 4 h 7 h kj/kg W net W T W p kj/kg Q s h 1 h kj/kg the W net Q s 3341% Simple Rankine cycle h kj/kg h kj/kg h kj/kg h kj/kg h 7 6 p =30bar a p =3bar b 1 (m kg) o T 1=300 c 1kg 2 (1-m) kg W T h 1 h p =015bar c kj/kg 4 Fig:121 (a) s W p h 4 h 3

53 140 Power Plant Engineering - wwwairwalkpublicationscom h 1 o T 1=300 c 303 kj/kg p =30ba r a 1kg W net W T W P kj/kg 4 Q s h 1 h p =015 bar b kj/kg the W net Q s Fig:121 (b) s 3158% Note Mass rate of steam bled m m [ m kg of steam circulated /s ] mass of steam bled m mass of steam circulated kg of steam bled kg of steam circulated kg of steam circulated sec So mass rate of steam bled kg of steam bled sec 141 Advantages of Regenerative cycle m m 1 Heat supplied to boiler becomes reduced 2 The heating process in the boiler approaches the reversible process

54 Coal Based Thermal Power Plants Since feed water temperature is high, the range of temperature in the boiler is minimum It reduces the thermal stresses produced in the boiler 4 Thermal efficiency is increased since the average temperature of heat addition to the cycle is increased 5 Due to bleeding in the turbine, erosion of turbine due to moisture is reduced 6 Condenser can be a smaller size This type of heating arrangement gives the efficiency equivalent to the Carnot cycle efficiency This type of arrangement cannot be used in practice because steam becomes too wet in the later stages of the turbine In actual practice, the advantage of regenerative heating principle is taken by bleeding a part of steam from the turbine at certain stages of expansion and it is used for heating the feed water in the separate feed heaters This arrangement does not reduce the dryness fraction of remaining steam passing through the turbine There are different methods of using the bled steam for heating the feed water as discussed here Methods: (a) Direct contact heaters The steam bleed from the different points of turbine is mixed directly with the feed water to increase the temperature of feed water and the steam mixed with feed water is extracted with the help of the pump and supplied to the boiler

55 142 Power Plant Engineering - wwwairwalkpublicationscom To boiler m 1 kg 1kg p b p 1 m 2 kg p 2 (1-m 1 -m 2 )kg Feed (1-m 1) Feed Heater heater condenser Pump 1 Pump 2 Pump 3 The main disadvantage is that The pump has to work with hot feed water So this system is normally not used in practice (b) Drain pump method: Fig:122 Direct Contact Heaters (1-m-m) 1 2 kg To B oiler 1kg p b condenser m kg 1 m kg 2 1kg (1- m 1 ) p 1 (1- m 1 ) p 2 (1-m 1 -m 2) kg m kg 1 m kg 1 m kg 2 m kg 2 Fig:123 In this method, the feed water is heated with indirect contact of bled steam in the heat exchangers The bled condensate is extracted by the drain pump discharges into the feed pipe line This method also suffers from the same disadvantage as mentioned in the direct contact heaters arrangement

56 Coal Based Thermal Power Plants 143 (b) All drains to hot well: All drains to hot well method is shown in Fig124 (1-m -m )kg 1 2 To boiler m 1 kg m 2 kg condenser p C 1kg p C p 1 1kg p 2 p a Feed heater Feed heater m 2 kg 1kg (1-m 1 -m )kg 2 In this method, the condensate of bled steam coming out from the indirect heat exchangers is fed to the hotwell The total condensate (Condensate coming from condenser + Condensate from bled steam) from the hot well is pumped to the boiler through the regenerative feed heaters (c) Cascade System: m kg 1 Fig:124 All Drain to Hot Well (1-m -m )kg 1 2 To boiler p b m kg 1 m kg 2 Condenser p c 1kg 4kg 1kg p a p a Feed Heater m kg 1 (m +m )kg 1 2 Fig:125 Cascade System

57 144 Power Plant Engineering - wwwairwalkpublicationscom In this method, the condensate of bled steam coming out from the first heat exchanger is passed through the second heat exchanger and lastly to hot well as shown in Fig LAYOUT OF MODERN COAL POWER PLANT (OR) LAYOUT OF STEAM POWER PLANT In steam power plant, the water is converted into steam and the steam expanded in a turbine to produce kinetic energy which is converted into mechanical energy The steam power plant has four major circuits by which the layout can be studied in detail These are Ash Storage Hot Ash or Slag Handling Air from atmosphere FD Fan To Atmosphere Chimney Coal handling Coal Preparation Fuel Superheater Preheated air Control Air Preheater Valve Economiser Pump IDFan Dust Collector Turbine Generator Turbine Exhaust Hot Water Cooling Water In Cooling Tower Coal Storage Boiler Feed Pump High Pressure Heater Deaerator Low Pressure Heater Fig:126 Steam Power Plant or Thermal Power Plant

58 Coal Based Thermal Power Plants Coal and ash circuit 2 Air and flue gas circuit 3 Feed water and steam circuit 4 Cooling water circuit 151 Coal and ash Circuit: This circuit consists of coal delivery, preparation of coal, handling of coal to the boiler furnace,ash handling and ash storage The coal which is received from the mines are stored in coal storage This raw coal is sized by crushers and then this prepared coal is transferred to the boilers In the boiler, the coal is burnt and converted into ash This ash is usually quenched to reduce the temperature, corrosion and dust content Then it is stored at ash storage 152 Air and Flue gas circuit Air from Atmosphere To Atmosphere FD F an Chimney Super Heater Preheated Air Air Preheater IDFan Dust Collector Economizer Fig:127 Air and Flue Gas Circuit This circuit consists of forced draught fan, air-preheater, boiler furnace, super heater, economiser, dust collector, induced draught (ID) fan and chimney

59 146 Power Plant Engineering - wwwairwalkpublicationscom The air from the atmosphere is forced into the circuit by a forced draught fan This air is preheated in the air preheater by flue gases This pre heated air is supplied to the furnace where this air is converted into flue gases This flue gases pass over the boiler tubes by which the water is converted into steam Then this flue gas is passed to the super heater where the steam is converted into super heated steam Then it is passed to the economiser to heat the feed water and to the air preheater The dust in the flue gases are collected by the dust collector and then left to atmosphere through chimney 153 Feed water and steam flow circuit: Superheater Control Valve Economiser Pump Turbine Generator Turbine Exhaust Hot Water Boiler Feed Pump High Pressure Heater Deaerator Low Pressure Heater Fig:128 Feed Water And Steam Flow Circuit This circuit consists of feed pump, economiser, boiler drum super heater, turbine and condenser From the hot well, the feed water is pumped to the economiser where the water is preheated by the flue gases This preheated water is supplied to the boiler drum In the boiler drum, the pre heated water is converted into steam by burning of coal The steam raised in boiler is passed through the super heater where the steam is converted into super

60 Coal Based Thermal Power Plants 147 heated steam The super heated steam is expanded in turbine which is coupled with generator The expanded steam is then passed through the condenser in which the steam is converted into water and this water is recirculated 154 Cooling Water Circuit This circuit consists of a pump, condenser and cooling tower In the condenser, cold water is circulated to condense the steam in to waterthe steam is condensed by loosing its latent heat to the circulating cold water By this, the Turbine Exhaust Steam Hot Water Cooling Water in circulating water is heated This hot water is cooled at the cooling tower, where the water is sprayed in the form of droplet through nozzles The cold air enters the cooling tower from the bottom which cools the sprayed hot water The cooled water is collected in the cooling pond and the same is re circulated again and again To compensate the water lost due to vapourisation, the make up water is added to the pond by means of a pump 16 SELECTION OF SITE FOR A STEAM POWER PLANT The following consideration should be taken while selecting the site for a steam power plant 1 Availability of raw materials Huge quantity of coal and fuel are required to run a steam (thermal) power plant Therefore, it is important to Cooling Tower water Fig:129 Cooling Water Circuit

61 148 Power Plant Engineering - wwwairwalkpublicationscom locate the plant as near as possible to the coal fields to reduce the transportation cost If it is not possible to locate the plant near the coal field, then it should be located near the railway station or near to a port 2 Ash disposal facilities As a huge quantity of coal is burnt, this results in a huge quantity of ash too The ash handling problem is more serious as compared to handling of coal because it comes out very hot and is very corrosive If not disposed properly it will result in environmental pollution and other hazards Therefore there must be sufficient space to dispose this large quantity of ash 3 Nature of land The land should have good bearing capacity about 1 MN/m 2 as it has to withstand the dead load of plant and force transmitted to the foundation due to working of heavy machinery 4 Cost of land Large area is required to build a thermal power plant, therefore the land price should be affordable (cheap) For eg: Large plant in the heart of city will be very costly 5 Availability of water Water is the working fluid in a steam power plant, and a large quantity of water is converted to steam in order to run the turbine It is important to locate the plant near the water source to fulfill its water demand through out the year

62 Coal Based Thermal Power Plants Size of the plant The capacity of the plant decides the size of the plant, large plant requires large area and the smaller plant requires considerably smaller area Therefore, the size of the plant and its capacity play an important role in selection of site 7 Availability of workforce During construction of plant, enough labour is required The labour should be available at the proposed site at cheap rate 8 Transportation facilities Availability of proper transportation is another important consideration for the selection of site as a huge quantity of raw materials (coal & fuel) through out the year and heavy machinery are to be brought to the site during the installation 9 Load centre The plant must be near to the load centre to which it is supplying power in order to decrease transmission loss and minimize transmission line cost 10 Public problems The plant should be away from the town or city in order to avoid nuisance from smoke, ash, heat and noise from the plant 11 Future extension A choice for future extension of the plant should be made in order to meet the power demand in future

63 150 Power Plant Engineering - wwwairwalkpublicationscom 17 SUPER CRITICAL BOILERS Super critical boiler is a boiler that operates at super critical pressure (high pressure) to increase the efficiency of the plant and to reduce the cost of electricity production Normally, water tube boilers are generally preferred for high pressure In this water tube boilers, the water is circulated through tubes and their external surfaces are exposed to the flue gases It is the most economical cycle The working steam pressure range is 125 bar to 300 bar and temperature is 510C to 600C Usually sub-critical boiler consists of three distinct sections as preheater, evaporator and superheater And in case of supercritical boiler, only preheater and super heater are required Generally super critical boilers are used for more than 300 MW power plants Advantages of super critical boilers: 1 The amount of scale formation is less since the velocity of water through pipes are more 2 In this method, light weight tubes with better heating surface arrangement can be used It occupies less space The cost for foundation, time for erection are very less 3 All parts of the system are heated uniformly So there is no danger of over heating 4 The differential expansion is reduced due to uniform temperature throughout structure So there is no leakages of gas (or) air 5 The flexibility is more

ME 6701 POWER PLANT ENGINEERING -DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK

ME 6701 POWER PLANT ENGINEERING -DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/318753065 ME 6701 POWER PLANT ENGINEERING -DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF MECHANICAL ENGINEERING QUESTION BANK VII SEMESTER ME-6701 POWER PLANT ENGINEERING Regulation 2013 Academic Year 2017-2018

More information

VALLIAMMAI ENGINEERING COLLEGE

VALLIAMMAI ENGINEERING COLLEGE VALLIAMMAI ENGINEERING COLLEGE SRM Nagar, Kattankulathur 603 203 DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK V SEMESTER ME6701 POWER PLANT ENGINEERING Regulation 2013 Academic Year

More information

Chapter 1 STEAM CYCLES

Chapter 1 STEAM CYCLES Chapter 1 STEAM CYCLES Assoc. Prof. Dr. Mazlan Abdul Wahid Faculty of Mechanical Engineering Universiti Teknologi Malaysia www.fkm.utm.my/~mazlan 1 Chapter 1 STEAM CYCLES 1 Chapter Objectives To carry

More information

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET 1. A vessel of volume 0.04m 3 contains a mixture of saturated water and steam at a temperature of 250 0 C. The mass of the liquid present is 9 kg. Find the pressure, mass, specific volume, enthalpy, entropy

More information

ASSIGNMENT 2 Coal and Ash Handling System and Draught Systems

ASSIGNMENT 2 Coal and Ash Handling System and Draught Systems ASSIGNMENT 1 Thermal Power Plant & High Pressure Boiler 1. State the factors to be considered for selection of site for thermal power plant 2. State desirable to control the super heat temperature. Explain

More information

Ms.P.Aileen Sonia Dhas

Ms.P.Aileen Sonia Dhas SUBJECT CODE SUBJECT NAME STAFF NAME : ME8792 : Power Plant Engineering : Prof.V.Tamil Selvi Ms.P.Aileen Sonia Dhas UNIT- I COAL BASED THERMAL POWER PLANTS Rankine cycle - improvisations, Layout of modern

More information

POWER PLANT ENGINEERING. Time: Three Hours Maximum Marks: 100

POWER PLANT ENGINEERING. Time: Three Hours Maximum Marks: 100 POWER PLANT ENGINEERING Time: Three Hours Maximum Marks: 100 Answer five questions, taking ANY TWO from Group A, any two from Group B and all from Group C. All parts of a question (a, b, etc. ) should

More information

R13 SET - 1 '' ''' '' ' '''' Code No: RT31035

R13 SET - 1 '' ''' '' ' '''' Code No: RT31035 R13 SET - 1 III B. Tech I Semester Regular/Supplementary Examinations, October/November - 2016 THERMAL ENGINEERING II (Mechanical Engineering) Time: 3 hours Max. Marks: 70 Note: 1. Question Paper consists

More information

Feedwater Heaters (FWH)

Feedwater Heaters (FWH) Feedwater Heaters (FWH) A practical Regeneration process in steam power plants is accomplished by extracting or bleeding, steam from the turbine at various points. This steam, which could have produced

More information

MECHANICAL ENGINEERING DEPARTMENT, OITM

MECHANICAL ENGINEERING DEPARTMENT, OITM Sem.:4 th Subject: Energy Conversion Paper: ME-201E UNIT-1 Q1. Explain the seismometer with its working principle. (Important Question) (20) Q2. Classify the fuels and define calorific value of fuels.

More information

2. The data at inlet and exit of the turbine, running under steady flow, is given below.

2. The data at inlet and exit of the turbine, running under steady flow, is given below. 3 rd week quiz 1. Identify the correct path of fluid flow in a steam power plant. a) Steam turbine-pump-boiler-condenser. b) Economizer- evaporator- superheater. c) Pump-turbine-condenser-evaporator. d)

More information

Chapter 10 POWER CYCLES. Department of Mechanical Engineering

Chapter 10 POWER CYCLES. Department of Mechanical Engineering Chapter 10 VAPOR AND COMBINED POWER CYCLES Dr Ali Jawarneh Department of Mechanical Engineering Hashemite University it 2 Objectives Analyze vapor power cycles in which h the working fluid is alternately

More information

Chapter 10. In Chap. 9 we discussed gas power cycles for which the VAPOR AND COMBINED POWER CYCLES. Objectives

Chapter 10. In Chap. 9 we discussed gas power cycles for which the VAPOR AND COMBINED POWER CYCLES. Objectives Chapter 0 VAPOR AND COMBINED POWER CYCLES In Chap. 9 we discussed gas power cycles for which the working fluid remains a gas throughout the entire cycle. In this chapter, we consider vapor power cycles

More information

Chapter 10. In Chap. 9 we discussed gas power cycles for which the VAPOR AND COMBINED POWER CYCLES. Objectives

Chapter 10. In Chap. 9 we discussed gas power cycles for which the VAPOR AND COMBINED POWER CYCLES. Objectives Chapter 0 VAPOR AND COMBINED POWER CYCLES In Chap. 9 we discussed gas power cycles for which the working fluid remains a gas throughout the entire cycle. In this chapter, we consider vapor power cycles

More information

Problems in chapter 9 CB Thermodynamics

Problems in chapter 9 CB Thermodynamics Problems in chapter 9 CB Thermodynamics 9-82 Air is used as the working fluid in a simple ideal Brayton cycle that has a pressure ratio of 12, a compressor inlet temperature of 300 K, and a turbine inlet

More information

Chapter 9: Vapor Power Systems

Chapter 9: Vapor Power Systems Chapter 9: Vapor Power Systems Table of Contents Introduction... 2 Analyzing the Rankine Cycle... 4 Rankine Cycle Performance Parameters... 5 Ideal Rankine Cycle... 6 Example... 7 Rankine Cycle Including

More information

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: )

SHRI RAMSWAROOP MEMORIAL COLLEGE OF ENGG. & MANAGEMENT B.Tech. [SEM IV (ME-41, 42,43 & 44)] QUIZ TEST-1 (Session: ) QUIZ TEST-1 Q.1. In a stage of an impulse turbine provided with a single row wheel, the mean diameter of the blade ring is 80cm and the speed of the rotation is 3000rpm. The steam issues from the nozzle

More information

Chapter 10 VAPOR AND COMBINED POWER CYCLES

Chapter 10 VAPOR AND COMBINED POWER CYCLES Thermodynamics: An Engineering Approach, 6 th Edition Yunus A. Cengel, Michael A. Boles McGraw-Hill, 2008 Chapter 10 VAPOR AND COMBINED POWER CYCLES Copyright The McGraw-Hill Companies, Inc. Permission

More information

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT UNIT 47: Engineering Plant Technology Unit code: F/601/1433 QCF level: 5 Credit value: 15 OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT 2 Be able to apply the steady flow energy equation (SFEE) to plant and equipment

More information

Chapter Two. The Rankine cycle. Prepared by Dr. Shatha Ammourah

Chapter Two. The Rankine cycle. Prepared by Dr. Shatha Ammourah Chapter Two The Rankine cycle Prepared by Dr. Shatha Ammourah 1 The Ideal Rankine Cycle Schematic Diagram of ideal simple Rankine 2 Superheater Economizer line 3 Heat Addition Types In The Steam Generator

More information

S.Y. Diploma : Sem. III [PG/PT/ME] Thermal Engineering

S.Y. Diploma : Sem. III [PG/PT/ME] Thermal Engineering S.Y. Diploma : Sem. III [PG/PT/ME] Thermal Engineering Time: 3 Hrs. Prelim Question Paper Solution [Marks : 70 Q.1 Attempt any FIVE of the following. [10] Q.1(a) Explain difference between Thermodynamic

More information

Code No: R31034 R10 Set No: 1

Code No: R31034 R10 Set No: 1 Code No: R31034 R10 Set No: 1 JNT University Kakinada III B.Tech. I Semester Regular/Supplementary Examinations, Dec - 2014/Jan -2015 THERMAL ENGINEERING-II (Com. to Mechanical Engineering and Automobile

More information

Rankine cycle. Contents. Description

Rankine cycle. Contents. Description Page 1 of 7 Rankine cycle From Wikipedia, the free encyclopedia The Rankine cycle is a model that is used to predict the performance of steam turbine systems. The Rankine cycle is an idealized thermodynamic

More information

Reading Problems , 11.36, 11.43, 11.47, 11.52, 11.55, 11.58, 11.74

Reading Problems , 11.36, 11.43, 11.47, 11.52, 11.55, 11.58, 11.74 Rankine Cycle Reading Problems 11.1 11.7 11.29, 11.36, 11.43, 11.47, 11.52, 11.55, 11.58, 11.74 Definitions working fluid is alternately vaporized and condensed as it recirculates in a closed cycle the

More information

CHAPTER 2 STUDY OF 210 MW BOILER SYSTEM 2.1 DESCRIPTION OF 210 MW BOILER

CHAPTER 2 STUDY OF 210 MW BOILER SYSTEM 2.1 DESCRIPTION OF 210 MW BOILER 8 CHAPTER 2 STUDY OF 210 MW BOILER SYSTEM 2.1 DESCRIPTION OF 210 MW BOILER Detailed study has been carried out on a 210 MW boiler system with regard to model development, control and optimization. Figure

More information

PESIT Bangalore South Campus Hosur road, 1km before Electronic City, Bengaluru -100 Department of Basic Science and Humanities

PESIT Bangalore South Campus Hosur road, 1km before Electronic City, Bengaluru -100 Department of Basic Science and Humanities USN 1 P E PESIT Bangalore South Campus Hosur road, 1km before Electronic City, Bengaluru -100 Department of Basic Science and Humanities INTERNAL ASSESSMENT TEST 1 Date : 28/08/2017 Marks: 40 Subject &

More information

CHAPTER 1 BASIC CONCEPTS

CHAPTER 1 BASIC CONCEPTS GTU Paper Analysis CHAPTER 1 BASIC CONCEPTS Sr. No. Questions Jan 15 Jun 15 Dec 15 May 16 Jan 17 Jun 17 Nov 17 May 18 Differentiate between the followings; 1) Intensive properties and extensive properties,

More information

Lecture No.1. Vapour Power Cycles

Lecture No.1. Vapour Power Cycles Lecture No.1 1.1 INTRODUCTION Thermodynamic cycles can be primarily classified based on their utility such as for power generation, refrigeration etc. Based on this thermodynamic cycles can be categorized

More information

Chapter 8. Vapor Power Systems

Chapter 8. Vapor Power Systems Chapter 8 Vapor Power Systems Introducing Power Generation To meet our national power needs there are challenges related to Declining economically recoverable supplies of nonrenewable energy resources.

More information

TIME SCHEDULE. MODULE TOPICS PERIODS 1 Introduction. 17 Steam Generators Properties of Steam Thermodynamic Vapour Cycle 2 Steam Engines

TIME SCHEDULE. MODULE TOPICS PERIODS 1 Introduction. 17 Steam Generators Properties of Steam Thermodynamic Vapour Cycle 2 Steam Engines COURSE TITLE : POWER PLANT ENGINEERING COURSE CODE : 50 COURSE CATEGORY : E PERIODS/WEEK : 4 PERIODS/SEMESTER : 72 CREDITS : 4 TIME SCHEDULE MODULE TOPICS PERIODS 1 Introduction Steam Generators Properties

More information

Practice Final Exam (A) Six problems. (Open-book, HW solutions, and notes) (Plus /minus 10 % error acceptable for all numerical answers)

Practice Final Exam (A) Six problems. (Open-book, HW solutions, and notes) (Plus /minus 10 % error acceptable for all numerical answers) ME 3610 Practice Final Exam (A) Six problems. (Open-book, HW solutions, and notes) (Plus /minus 10 % error acceptable for all numerical answers) (18 points) 1. A gasoline engine operating on the ideal

More information

LESSON PLAN. Sub Name : EE2252- POWER PLANT ENGINEERING Unit: I Branch: EEE Semester: IV. Topics to be covered (Min)

LESSON PLAN. Sub Name : EE2252- POWER PLANT ENGINEERING Unit: I Branch: EEE Semester: IV. Topics to be covered (Min) Unit I Unit: I Branch: EEE Semester: IV LP-EE2252 LP Rev. : 00 Page: 1 of 5 1 THERMAL POWER PLANTS Basic thermodynamic cycles, various components of steam power plant-layout-pulverized coal burners- Fluidized

More information

Chapter 10 Vapor and Combined Power Cycles

Chapter 10 Vapor and Combined Power Cycles Chapter 10 Vapor and Combined Power Cycles Dr. Mohammad Tarawneh Thermodynamics: An Engineering Approach, 5th edition by Yunus A. Çengel and Michael A. Boles We consider power cycles where the working

More information

Lecture (6) on. Schematic of a Thermal Power Plant. By Dr. Emad M. Saad. Mechanical Engineering Dept. Faculty of Engineering.

Lecture (6) on. Schematic of a Thermal Power Plant. By Dr. Emad M. Saad. Mechanical Engineering Dept. Faculty of Engineering. 1 2 Lecture (6) on Schematic of a Thermal Power Plant By Dr. Emad M. Saad Mechanical Engineering Dept. Faculty of Engineering Fayoum University Faculty of Engineering Mechanical Engineering Dept. 2015-2016

More information

COURSE CODE : 5023 COURSE CATEGORY : E PERIODS/ WEEK : 4 PERIODS/ SEMESTER : 60 CREDIT : 4 TIME SCHEDULE

COURSE CODE : 5023 COURSE CATEGORY : E PERIODS/ WEEK : 4 PERIODS/ SEMESTER : 60 CREDIT : 4 TIME SCHEDULE COURSE TITLE : POWER PLANT ENGINEERING COURSE CODE : 5023 COURSE CATEGORY : E PERIODS/ WEEK : 4 PERIODS/ SEMESTER : 60 CREDIT : 4 TIME SCHEDULE MODULE TOPIC PERIODS 1 Fuels and combustion, Steam boilers,

More information

a. The power required to drive the compressor; b. The inlet and output pipe cross-sectional area. [Ans: kw, m 2 ] [3.34, R. K.

a. The power required to drive the compressor; b. The inlet and output pipe cross-sectional area. [Ans: kw, m 2 ] [3.34, R. K. CHAPTER 2 - FIRST LAW OF THERMODYNAMICS 1. At the inlet to a certain nozzle the enthalpy of fluid passing is 2800 kj/kg, and the velocity is 50 m/s. At the discharge end the enthalpy is 2600 kj/kg. The

More information

Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on

Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on Chapter 10, Problem 8C. Consider a simple ideal Rankine cycle with fixed turbine inlet conditions. What is the effect of lowering the condenser pressure on Pump work input: Turbine work output: Heat supplied:

More information

Power Engineering II. Technological circuits of thermal power plants

Power Engineering II. Technological circuits of thermal power plants Technological circuits of thermal power plants Lay out scheme of coal power plant climatetechwiki.com Technological circuits 2 Coal and ash circuit Air and gas circuit Feed water and steam circuit Cooling

More information

Vapor and Combined Power Cycles

Vapor and Combined Power Cycles 9 CHAPTER Vapor and Combined Power Cycles 9-1 The Simple Ideal Rankine Cycle The 9-2 Rankine Cycle: Actual Vapor Power Deviation and Pump and Turbine Irreversibilities (a) Deviation of actual vapor power

More information

Lecture No.3. The Ideal Reheat Rankine Cycle

Lecture No.3. The Ideal Reheat Rankine Cycle Lecture No.3 The Ideal Reheat Rankine Cycle 3.1 Introduction We noted in the last section that increasing the boiler pressure increases the thermal efficiency of the Rankine cycle, but it also increases

More information

Advanced. FOR B.E / B.Tech MECHANICAL ENGINEERING STUDENTS

Advanced. FOR B.E / B.Tech MECHANICAL ENGINEERING STUDENTS Advanced ENERGY ENGINEERING FOR BE / BTech MECHANICAL ENGINEERING STUDENTS As Per Revised Syllabus of Leading Universities in India Including Dr APJ Abdul Kalam Technological University, Kerala Dr S Ramachandran,

More information

GUJARAT TECHNOLOGICAL UNIVERSITY BRANCH NAME: Mechanical Engineering SUBJECT NAME: Power Plant Engineering SUBJECT CODE: B.E.

GUJARAT TECHNOLOGICAL UNIVERSITY BRANCH NAME: Mechanical Engineering SUBJECT NAME: Power Plant Engineering SUBJECT CODE: B.E. GUJARAT TECHNOLOGICAL UNIVERSITY BRANCH NAME: Mechanical Engineering SUBJECT NAME: Power Plant Engineering SUBJECT CODE: 2171910 B.E. 7 th SEMESTER Type of course: Applied Engineering Prerequisite: Engineering

More information

S.E. (Mechanical) (First Semester) EXAMINATION, 2012 APPLIED THERMODYNAMICS (2008 PATTERN) Time : Three Hours Maximum Marks : 100

S.E. (Mechanical) (First Semester) EXAMINATION, 2012 APPLIED THERMODYNAMICS (2008 PATTERN) Time : Three Hours Maximum Marks : 100 Total No. of Questions 12] [Total No. of Printed Pages 8 Seat No. [4162]-111 S.E. (Mechanical) (First Semester) EXAMINATION, 2012 APPLIED THERMODYNAMICS (2008 PATTERN) Time : Three Hours Maximum Marks

More information

NUCLEAR TRAINING CENTRE COURSE 134 FOR ONTARIO HYDRO USE ONLY

NUCLEAR TRAINING CENTRE COURSE 134 FOR ONTARIO HYDRO USE ONLY NUCLEAR TRAINING CENTRE COURSE 134 FOR ONTARIO HYDRO USE ONLY NUCLEAR TRAINING COURSE COURSE 134 1 - Level 3 - Equipment & System Principles 4 - TURBINE, GENERATOR & AUXILIARIES Index 134.00-0 Objectives

More information

Steam Power Station (Thermal Station)

Steam Power Station (Thermal Station) Steam Power Station (Thermal Station) A generating station which converts heat energy into electrical energy through turning water into heated steam is known as a steam power station. A steam power station

More information

R13. (12M) efficiency.

R13. (12M) efficiency. SET - 1 II B. Tech I Semester Regular/Supplementary Examinations, Oct/Nov - 2016 THERMAL AND HYDRO PRIME MOVERS (Electrical and Electronics Engineering) Time: 3 hours Max. Marks: 70 Note: 1. Question Paper

More information

B.E. DEGREE EXAMINATION VII Semester Mechanical Engineering ME2403 Power Plant Engineering

B.E. DEGREE EXAMINATION VII Semester Mechanical Engineering ME2403 Power Plant Engineering 1 B.E. DEGREE EXAMINATION VII Semester Mechanical Engineering ME2403 Power Plant Engineering SHORT QUESTIONS AND ANSWERS 1. Name the four major circuits in steam power plant. Coal and ash circuit Air and

More information

Rankine cycle. Contents. Description

Rankine cycle. Contents. Description 페이지 1 / 6 Rankine cycle From Wikipedia, the free encyclopedia The Rankine cycle is a cycle that converts heat into work. The heat is supplied externally to a closed loop, which usually uses water. This

More information

Practical Boiler. Operation Engineering and Power Plant FOURTH EDITION. Amiya Ranjan Mallick

Practical Boiler. Operation Engineering and Power Plant FOURTH EDITION. Amiya Ranjan Mallick Practical Boiler Operation Engineering and Power Plant FOURTH EDITION Amiya Ranjan Mallick General Manager (Power Plant) B.K. Birla Group of Industries Maharashtra Delhi-110092 2015 PRACTICAL BOILER OPERATION

More information

- 2 - SME Q1. (a) Briefly explain how the following methods used in a gas-turbine power plant increase the thermal efficiency:

- 2 - SME Q1. (a) Briefly explain how the following methods used in a gas-turbine power plant increase the thermal efficiency: - 2 - Q1. (a) Briefly explain how the following methods used in a gas-turbine power plant increase the thermal efficiency: i) regenerator ii) intercooling between compressors (6 marks) (b) Air enters a

More information

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS PAPER EM2: Energy Efficiency in Thermal Utilities Date: 22.05.2004 Timings: 1400-1700 HRS Duration: 3 HRS Max. Marks: 150 General instructions:

More information

SUMMER 13 EXAMINATION

SUMMER 13 EXAMINATION Important Instructions to examiners: 1) The answers should be examined by key words and not as word-to-word as given in the model answer scheme. 2) The model answer and the answer written by candidate

More information

Code No: RR Set No. 1

Code No: RR Set No. 1 Code No: RR410304 Set No. 1 1. (a) Explain the different components used in steam power plant. (b) What are the basic coal ingredients and how do they affect furnace design. 2. Describe the electrostatic

More information

PI Heat and Thermodynamics - Course PI 25 CRITERION TEST. of each of the following a. it

PI Heat and Thermodynamics - Course PI 25 CRITERION TEST. of each of the following a. it Heat and Thermodynamics - Course PI 25 CRITERION TESTS PI 25-1 - 1. Define: heat temperature (c) enthalpy 2. State the applies to meaning water: of each of the following a. it saturation temperature subcooled

More information

FEE, CTU in Prague Power Engineering 2 (BE5B15EN2) Exercise 3

FEE, CTU in Prague Power Engineering 2 (BE5B15EN2) Exercise 3 Example 1: How is the applied heat for 1 kg of water steam at constant pressure p = 1.47 MPa, if the dryness of wet water is increased from x 1 = 0.8 to x 2 = 0.96? Dryness of wet steam the ratio of steam

More information

To Study of Maximum Efficiency Of Power Generation in Thermal Power Plant

To Study of Maximum Efficiency Of Power Generation in Thermal Power Plant To Study of Maximum Efficiency Of Power Generation in Thermal Power Plant Md Saddam Hussain 1, M A Haque Khushroo 2 1 Department of Electrical & Electronics Engineering, 2 Department of Electronics & Communication

More information

Applied Thermo Fluids-II: (Autumn 2017) Section-A: Thermal Power Plants

Applied Thermo Fluids-II: (Autumn 2017) Section-A: Thermal Power Plants Applied Thermo Fluids-II: (Autumn 2017) Section-A: Thermal Power Plants Module-1 (Introduction & Thermodynamics of thermal power plants) Dr. M. Ramgopal, Mechanical Engineering, IIT Kharagpur Reference:

More information

water is typically used as the working fluid because of its low cost and relatively large value of enthalpy of vaporization

water is typically used as the working fluid because of its low cost and relatively large value of enthalpy of vaporization Rankine Cycle Reading Problems 10-2 10-7 10-16, 10-34, 10-37, 10-44, 10-47, 10-59 Definitions working fluid is alternately vaporized and condensed as it recirculates in a closed cycle water is typically

More information

Secondary Systems: Steam System

Secondary Systems: Steam System Secondary Systems: Steam System K.S. Rajan Professor, School of Chemical & Biotechnology SASTRA University Joint Initiative of IITs and IISc Funded by MHRD Page 1 of 10 Table of Contents 1 SECONDARY SYSTEM

More information

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad -500 043 MECHANICAL ENGINEERING ASSIGNMENT Course Name : THERMAL ENGINEERING II Course Code : A50518 Class : III B. Tech I Semester

More information

DEPARTMENT OF MECHANICAL ENGINEERING ME6701 POWER PLANT ENGINEERING (2 MARKS QUESTIONS) UNIT I COAL BASED THERMAL POWER PLANTS

DEPARTMENT OF MECHANICAL ENGINEERING ME6701 POWER PLANT ENGINEERING (2 MARKS QUESTIONS) UNIT I COAL BASED THERMAL POWER PLANTS SYED AMMAL ENGINEERING COLLEGE (Approved by the AICTE, New Delhi, Govt. of Tamilnadu and Affiliated to Anna University, Chennai) Established in 1998 - An ISO 9001:2008 Certified Institution Dr. E.M.Abdullah

More information

Code No: RR Set No. 1

Code No: RR Set No. 1 Code No: RR310303 Set No. 1 III B.Tech I Semester Regular Examinations, November 2006 THERMAL ENGINEERING-II (Mechanical Engineering) Time: 3 hours Max Marks: 80 Answer any FIVE Questions All Questions

More information

ANNAI MATHAMMAL SHEELA ENGINEERING COLLEGE VII Semester Mechanical Engineering ME2403 Power Plant Engineering

ANNAI MATHAMMAL SHEELA ENGINEERING COLLEGE VII Semester Mechanical Engineering ME2403 Power Plant Engineering ANNAI MATHAMMAL SHEELA ENGINEERING COLLEGE VII Semester Mechanical Engineering ME2403 Power Plant Engineering SHORT QUESTIONS AND ANSWERS UNIT I INTRODUCTION TO POWER PLANTS 1. Name the four major circuits

More information

Course Name : Diploma in Mechanical Engineering Course Code : ME/MH/MI Semester : Fourth Subject Title : Thermal Engineering Subject Code : 17410

Course Name : Diploma in Mechanical Engineering Course Code : ME/MH/MI Semester : Fourth Subject Title : Thermal Engineering Subject Code : 17410 Course Name : Diploma in Mechanical Engineering Course Code : ME/MH/MI Semester : Fourth Subject Title : Thermal Engineering Subject Code : Teaching and Examination Scheme: Teaching Scheme TH TU PR PAPER

More information

ME6701 POWER PLANT ENGINEERING

ME6701 POWER PLANT ENGINEERING ME6701 POWER PLANT ENGINEERING OBJECTIVES: L T P C 3 0 0 3 Providing an overview of Power Plants and detailing the role of Mechanical Engineers in their operation and maintenance. UNIT I COAL BASED THERMAL

More information

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN (EXECUTIVE SESSION) November, 2007 JAPAN EXTERNAL TRADE ORGANIZATION JAPAN CONSULTING INSTITUTE SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN 1. Power Generation

More information

Superior Efficiency Reduced Costs Viable Alternative Energy Kalex Kalina Cycle Power Systems For Biomass Applications

Superior Efficiency Reduced Costs Viable Alternative Energy Kalex Kalina Cycle Power Systems For Biomass Applications Superior Efficiency Reduced Costs Viable Alternative Energy Kalex Kalina Cycle Power Systems For Biomass Applications Copyright 2009, 2010, Kalex LLC. Kalex LLC's Kalina Cycle for Biomass Applications

More information

St.MARTIN S ENGINEERING COLLEGE Dhulapally,Secunderabad,

St.MARTIN S ENGINEERING COLLEGE Dhulapally,Secunderabad, St.MARTIN S ENGINEERING COLLEGE Dhulapally,Secunderabad, 500014. MECHANICAL ENGINEERING TUTORIAL QUESTION BANK Course Name : THERMAL ENGINEERING II Course Code : A50326- Class : III B. Tech I Semester

More information

Module-3A: Heat Transfer Equipment. Applied Thermo Fluids-II (Autumn 2017) Dr. M. Ramgopal, Mechanical Engineering, IIT Kharagpur

Module-3A: Heat Transfer Equipment. Applied Thermo Fluids-II (Autumn 2017) Dr. M. Ramgopal, Mechanical Engineering, IIT Kharagpur Module-3A: Heat Transfer Equipment Applied Thermo Fluids-II (Autumn 2017) Dr. M. Ramgopal, Mechanical Engineering, IIT Kharagpur Introduction From 1 st law of thermodynamics applied to the combustion reaction;

More information

Efficiency improvement of steam power plants in Kuwait

Efficiency improvement of steam power plants in Kuwait Energy and Sustainability V 173 Efficiency improvement of steam power plants in Kuwait H. Hussain, M. Sebzali & B. Ameer Energy and Building Research Center, Kuwait Institute for Scientific Research, Kuwait

More information

3.1 Syllabus EE2252 POWER PLANT ENGINEERING 3 1 0 4 1 THERMAL POWER PLANTS Basic thermodynamic cycles, various components of steam power plant-layout-pulverized coal burners- Fluidized bed combustion-coal

More information

S.K.P. Engineering College, Tiruvannamalai

S.K.P. Engineering College, Tiruvannamalai SKP Engineering College Tiruvannamalai 606611 A Course Material on POWER PLANT ENGINEERING By Dr.K.Venkatesan,Mr.K.Venkatesh,Mr.M.Martincharles Assistant Professor 1 Quality Certificate This is to Certify

More information

Exergy Analysis of 210 Mw of Vijayawada Thermal Power Station (V.T.P.S)

Exergy Analysis of 210 Mw of Vijayawada Thermal Power Station (V.T.P.S) Exergy Analysis of 210 Mw of Vijayawada Thermal Power Station (V.T.P.S) N. Naga Varun Department of Mechanical Engineering K L University, Vaddeswaram, Guntur, India. G. Satyanarayana Department of Mechanical

More information

Design Features of Combined Cycle Systems

Design Features of Combined Cycle Systems Design Features of Combined Cycle Systems 1.0 Introduction As we have discussed in class, one of the largest irreversibilities associated with simple gas turbine cycles is the high temperature exhaust.

More information

CHEM 103: Chemistry in Context

CHEM 103: Chemistry in Context CHEM 103: Chemistry in Context Unit 3 Energy Sources Reading: CC Chapters 4, 7, 8, and G&R 4.1, 6, 5 Unit 3.1 Introduction; Fossil Fuels Interconnectedness of Issues: Energy Life We use energy for transportation,

More information

PEMP RMD & Cycle Performance. M.S.Ramaiah School of Advanced Studies

PEMP RMD & Cycle Performance. M.S.Ramaiah School of Advanced Studies Steam Se Turbine ub ecyces Cycles & Cycle Performance Session delivered by: Prof. Q.H. Nagpurwala 1 Session Objectives This session is intended to discuss the following: Basic construction and classification

More information

ANALYSIS OF DIFFERENT TYPES OF REGULATION AND ITS EFFICIENCY IN STEAM POWER CYCLES MASTER THESIS

ANALYSIS OF DIFFERENT TYPES OF REGULATION AND ITS EFFICIENCY IN STEAM POWER CYCLES MASTER THESIS ANALYSIS OF DIFFERENT TYPES OF REGULATION AND ITS EFFICIENCY IN STEAM POWER CYCLES MASTER THESIS Author: Ricardo Sánchez Pereiro Advisor: Piotr Krzyslak Poznan University of Technology 11/06/2012 INDEX

More information

Due Diligence: Efficiency Increase in Existing Power Stations - a Practice Report-

Due Diligence: Efficiency Increase in Existing Power Stations - a Practice Report- Due Diligence: Efficiency Increase in Existing Power Stations - a Practice Report- Nick Peters, Dr. Wolfgang A. Benesch Steag Energy Services Germany 1 Background and methodology Steag owns and operates

More information

Services to Technology Providers

Services to Technology Providers Services to Technology Providers Training and Capacity building activities with HP boiler manufacturers Session 1: the water and steam system Trainer: Frans Baltussen Date: first half 2015 Sugar processing

More information

Cleaner Production and Energy Efficiency in Industry. With Focus on the Electricity Supply

Cleaner Production and Energy Efficiency in Industry. With Focus on the Electricity Supply Cleaner Production and Energy Efficiency in Industry With Focus on the Electricity Supply 1 Cleaner Production (CPEE) Prevent or reduce pollution and waste by implementing measures that are: Environmentally

More information

HIGH PRESSURE BOILERS

HIGH PRESSURE BOILERS Power Plant Engg. High Pressure Boilers & FBC Assi. Professor Mechanical Engineering Department HIGH PRESSURE BOILERS High Pressure Boiler, P > 60 bar Critical Pressure Boiler, P = 221.2 bar Super Critical

More information

Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat

Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat Energy Audit of 250 MW Thermal Power Stations PTPS, Panipat Vikrant Bhardwaj 1, Rohit Garg 2, Mandeep Chahal 3, Baljeet Singh 4 1 Asstt. Professor in Deptt. Of Mechanical Engineering, IIET, (Kinana) Jind

More information

Eng Thermodynamics I - Examples 1

Eng Thermodynamics I - Examples 1 Eng3901 - Thermodynamics I - Examples 1 1 pdv Work 1. Air is contained in a vertical frictionless piston-cylinder. The mass of the piston is 500 kg. The area of the piston is 0.005 m 2. The air initially

More information

5. Steam Turbine Performance

5. Steam Turbine Performance 5. Steam Turbine Performance h HP = 88-90% IP = 90-94% Fossil Reheat HP = 82% LP = 85% LP = 87% LP = 90-91% Saturation Line Nuclear Reheat Nuclear Non-Reheat s Steam Turbine 5. Performance 1 / 93 1 2 3

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 4.72 International Journal of Advance Engineering and Research Development Volume 4, Issue 9, September -2017 Review of Thermal Characteristics of Diesel Fired

More information

Faculty of Engineering 2 nd year 2016 Mechanical Engineering Dep. Final-exam (code: M 1222)

Faculty of Engineering 2 nd year 2016 Mechanical Engineering Dep. Final-exam (code: M 1222) Benha University Thermodynamics II Faculty of Engineering 2 nd year 2016 Mechanical Engineering Dep. Final-exam (code: M 1222) Time: Three Hours (attempt all questions) (assume any missing data) Question1

More information

Eng Thermodynamics I - Examples 1

Eng Thermodynamics I - Examples 1 Eng3901 - Thermodynamics I - Examples 1 1 pdv Work 1. Air is contained in a vertical frictionless piston-cylinder. The mass of the piston is 500 kg. The area of the piston is 0.005 m 2. The air initially

More information

Decentralized Biomass Power Production

Decentralized Biomass Power Production Decentralized Biomass Power Production by Dr. Eric Bibeau University of Manitoba (Alternative Energy Research) Biomass Energy II Heat and Power Workshop November 13, 2003 Activity at U of M biomass alternative

More information

Chapter 6 Steam Generators MEE 325 Power Plants Engineering

Chapter 6 Steam Generators MEE 325 Power Plants Engineering Chapter 6 Steam Generators MEE 325 Power Plants Engineering Atikorn W. Mechanical Engineering Department King Mongkut s University of Technology Thonburi Basics components Main Structure Furnance Superheater

More information

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa.

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa. Chapters 5, 6, and 7 Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa. 5-1. Steam enters a steady-flow device at 16 MPa and 560 C with

More information

HEAT ENGINES VOL. I. By Dr. N. C. Pandya, Dr. C. S. Shah & Dr. S. S. Khandare ` Checklist [ THERMODYNAMICS AND THERMAL ENGINEERING ]

HEAT ENGINES VOL. I. By Dr. N. C. Pandya, Dr. C. S. Shah & Dr. S. S. Khandare ` Checklist [ THERMODYNAMICS AND THERMAL ENGINEERING ] HEAT ENGINES VOL. I [ THERMODYNAMICS AND THERMAL ENGINEERING ] By Dr. N. C. Pandya, Dr. C. S. Shah & Dr. S. S. Khandare Edition : 10 th Revised and Enlarged Edition : 2005 ISBN : 81-85594-49-X, 978-81-85594-49-1

More information

Performance Optimization of Steam Power Plant through Energy and Exergy Analysis

Performance Optimization of Steam Power Plant through Energy and Exergy Analysis I NPRESSCO NTERNATIONAL PRESS CORPORATION International Journal of Current Engineering and Technology, Vol.2, No.3 (Sept. 2012) ISSN 2277-4106 Research Article Performance Optimization of Steam Power Plant

More information

Thermal Power Station

Thermal Power Station 2 Thermal Power Station 2.1 INTRODUCTION Energy is an important input in all the sectors of any country s economy. The standard of living of a given country can be directly related to per capita energy

More information

DE-TOP User s Manual. Version 2.0 Beta

DE-TOP User s Manual. Version 2.0 Beta DE-TOP User s Manual Version 2.0 Beta CONTENTS 1. INTRODUCTION... 1 1.1. DE-TOP Overview... 1 1.2. Background information... 2 2. DE-TOP OPERATION... 3 2.1. Graphical interface... 3 2.2. Power plant model...

More information

Guidance page for practical work 15: modeling of the secondary circuit of a PWR

Guidance page for practical work 15: modeling of the secondary circuit of a PWR Guidance page for practical work 15: modeling of the secondary circuit of a PWR 1) Objectives of the practical work The aim is to investigate the potential of Thermoptim in modeling and calculation of

More information

MARAMA Webinar August 7, Angelos Kokkinos Chief Technology Officer Babcock Power, Inc.

MARAMA Webinar August 7, Angelos Kokkinos Chief Technology Officer Babcock Power, Inc. MARAMA Webinar August 7, 2014 Angelos Kokkinos Chief Technology Officer Babcock Power, Inc. Rankine cycle is a thermodynamic cycle which converts heat into work. The heat is supplied externally to a closed

More information

Boilers & Fired Systems. Clean Coal Technology Dr. Tanveer Iqbal

Boilers & Fired Systems. Clean Coal Technology Dr. Tanveer Iqbal Boilers & Fired Systems Clean Coal Technology Dr. Tanveer Iqbal 1 What is a Boiler? Vessel that heats water to become hot water or steam At atmospheric pressure water volume increases 1,600 times Hot water

More information