ACHIEVING EXCELLENCE IN ENERGY MANAGEMENT. Karen Hearn PDP, FMA, MA, LEED AP Executive Director, Facilities

Size: px
Start display at page:

Download "ACHIEVING EXCELLENCE IN ENERGY MANAGEMENT. Karen Hearn PDP, FMA, MA, LEED AP Executive Director, Facilities"

Transcription

1 ACHIEVING EXCELLENCE IN ENERGY MANAGEMENT Karen Hearn PDP, FMA, MA, LEED AP Executive Director, Facilities

2 ENERGY CONSERVATION Our accomplishments: Electrical consumption reduced by more than 35% from base year of 2000 Energy density 0.85 compared to 1.42 for community colleges and 2.59 for universities Utilities budget same in 2009 as in 2001 despite utility rate increases and 29% increase in space

3 THE CASE STUDY INSTITUTION Examples are based on experience at Kwantlen 1981 Kwantlen began as a Community College 1995 Designated a University College 2008 became a Polytechnic University Multi-campus commuter campus

4 17,000 students 10,000 (FTE) Bachelor degrees, Associate degrees, Diplomas, Certificates & Citations Over 135 programs

5 Cloverdale Campus Opened April 2007 USGBCLEEDGold Gold

6 Langley Campus g y p Opened September 1993 Expansion 2009

7 Richmond Campus Opened September 1992

8 Surrey Campus Opened September 1990 Expansions 1999, 2006 & 2008

9 EARLY ADOPTERS (LEADERS) Fluorescent lamps recycled since the early 1990 s 1995 Committed to reduce greenhouse gases 2001 BC Green Building Initiative Pilot Site 2008 Frost & Sullivan Bright Green Building Case Study

10 ENERGY CONSERVATION Targets by 2010 R d l t i l ti b 45% Reduce electrical consumption by 45% per sq. m. Reduce natural gas consumption by 25% per sq. m.

11 GETTING ADMINISTRATIVE SUPPORT

12 Start small - minimal or no cost measures Compact Fluorescent Lamp Pay back 4 months Faucet Aerators Pay back 0.7 years

13 Do pilot projects

14 Try new technologies LED lamps

15 Replicate your success

16 Measure and report on your success

17 Resource Management Action Plan OPPORTUNITIES TO ACHIEVE 2010 GOAL Surrey Campus Estimated Co st Estimated Savings/Year kwh GJ ekwh Total Replace weather-stripping $2, ,004 Review AHU operation at night $850 3, ,907 Occupancy sensors in washrooms $1,000 4,000 4, % recirc during pre-occupancy $4, , (est) Add CO2 sensors to classrooms $60, ,352 (est) Improve lab fume hood controls $12, ,280 Total $81,050 7,404 2, ,433 All Campus Total $371,114 22,012 5,792 1,631,122 Approximate payback term anticipated to be 6 years

18 Resource Management Action Plan RESOURCE MANAGEMENT ACTION PLAN OTHER OPPORTUNITIES Surrey Campus Est im at e d Co st Estimated Savings/Year kwh GJ ekwh Total Replace/modify boiler - gas/draft restrictor $150,000 2, ,712 Turn off parking lot lights when closed $3,000 16,425 16,425 Convert to 25 & 30 watt lighting where practical $17,000 82,800 82,800 (est) Increase efficiency of stairwell lighting $22,000 35,880 35,880 Rewiring to reduce night lighting $18,000 30,000 30,000 Entrance ceiling lights replace with wall mount $ Conference centre lobby to photocell $624 1,248 1,248 Gym conversion lighting $13,832 36,400 36,400 Replace Bldg G courtyard lights with overhead fixt. $950 4, ,672 Turn off exterior floodlights Bldg-G noncourtyard $1,000 4,380 4,380 Total $226, ,405 2, ,117 All Campus Total $493, ,470 4,830 2,093,336

19 Use the language of the Administrators Student engagement Return on investment Employee retention Life cycle costing Total cost of ownership Employee recruitment t

20 Received: BC Hydro $ 90,458 BC Hydro Energy Audit $72,000 CBIP - Cloverdale $ 48,000 NRCan $263,000 PSECA HVAC/Lighting Upgrade, Surrey & Langley campus $457,596 Province Library Mechanical Retrofit $1,200, Province Geothermal $450,000 Sub Total $2,581,054 Pending (estimated): BC Hydro Energy Manager $100,000 BC Hydro Retro Commissioning $30,000 Sub Total $130, TOTAL $2,711,054

21 PROVIDE RECOGNITION - PUBLICATIONS Business Excellence May 2008 & June 2009 Award Magazine June 2007 Innovation July-August 2007 Wood Design & Building Winter 2007 Business In Vancouver February-March 2008 Construction Business March-April 2008 & September-October 2007

22 Provide Recognition - Awards 2009 BC Hydro Power Smart Leader 2008 BC Hydro Excellence in Energy Management 2004 BC Hydro Certified Energy Efficiency Leader (only 9 in province) 2003 BC Hydro Power Smart Partner Excellence Award 2003 National Research Canada (NRC) Energy Innovator 2003 Voluntary Challenge Leadership Award for Canadian Universities & Registry (VCR) Colleges for reduction of greenhouse gas emissions

23 KWANTLEN POLYTECHNIC UNIVERSITY Provide Recognition Awards

24 DEVELOPING PARTNERSHIPS

25 DEVELOPING PARTNERSHIPS Identify key partners. Determine what will help improve the partnership how to make everyone successful. to make everyone successful. Explore what more you can do together get creative. Trust your partners and take risks.

26 Partnership at its best

27 DEVELOP INTER RELATIONSHIP WITH PARTNERS Introduce them to each other Encourage them to collaborate Encourage learning from each other & laddering from each other s experience Take an integrated approach to challenges We is smarter than me

28 OPTIMIZE BUILDING OPERATIONS

29 OPTIMIZE BUILDING OPERATIONS Free cooling

30 Reducing fixture light tubes

31

32 TRAINING - CONTROL SYSTEM - OPERATION PROCEDURES Introduction Operating a control system effectively is a complex task and requires considerable experience. This section is intended to provide basic information to be aware of. Learning Objectives Aft l ti thi ti h ld b bl t After completing this section you should be able to: Describe what set points are. Describe how set points are changed and why. Describe how major equipment is started and stopped. Demonstrate how to change operating times for equipment. Demonstrate how to collect trend information. Explain how to respond to alarm conditions.

33

34 MINIMAL INVESTMENT MEASURES Strategict maintenance Re-commission key components Change maintenance practice

35 Boiler Tuning

36 Utilizing sensors for multiple purposes

37 CO2 Sensor

38 Natural Light

39 Natural Light

40 Predicted 74% more energy efficient than other buildings and reduces GHG emissions by 91%

41 ENSURING CONTINUED SUCCESS Monitor, monitor, monitor Night audits On-going training Regular reviews of energy consumption Follow-up on anomalies Provide awareness training