1 Florida Gas Transmission Section #1 Hydrostatic Test 14-Inch Saint Petersburg Lateral Pipeline From Compressor Station 30 (Plant City West) to Main Line Valve (Tampa East Regulator) Hillsborough County

2 Today s Outline Who is Florida Gas Transmission (FGT)? Why is FGT testing? What is the test exactly? When will the test occur? Where will the test take place? How will the test be conducted? How will the test affect me? 1

3 Florida Gas Transmission Company Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf Provide majority of the natural gas for power generation in Hillsborough County 14-inch diameter pipeline serving Tampa area Customers include: Electric utility companies Local distributors Industrial clients 2

4 Need for the Test The U.S. Department of Transportation regulates all interstate pipelines Testing is federally mandated Best practice to confirm the safety and reliability of the pipeline Safety is our #1 priority Ensure continued superb client service 3

5 Nature of the Test Hydrostatic Test Remove the natural gas from the line Controlled release vents harmlessly into atmosphere Service is maintained on another system Test the integrity of the pipeline by filling the line with water Put the water under pressure for a fixed period of time 4

6 Hydrotesting the 14-inch lateral system Standard, common pipeline test procedure Recent, successful pipeline tests were completed in: Miami-Dade Saint Lucie Palm Beach Background Martin Broward Hillsborough testing began in September

7 Project Process Begin Project Obtain Permits Prepare System for Testing Conduct Hydrotest End Project Public Awareness Campaign 6

8 Project Schedule TASK Community Awareness Permit Applications System Preparation Test Preparation DATE July October June July July August August September Conduct Hydrotest 3 October 2014 Test window is set: Friday, 3 October 2014 Early morning, midnight 4:00 a.m. 7

9 Project Location Total Project Length = 17.0 miles Begin: West Plant City End: Tampa By-Pass Canal Generally follows 3 roadway alignments: East Fowler Avenue (SR 582) US 301 (SR 41) West Knights Griffin Road Within Plant City and Unincorporated Hillsborough County 8

10 Project Location (con t) 9

11 How the Test is Performed Remove natural gas from the pipeline Completed the week before the hydrotest Fill the line with water Pressurize the system Normal operating pressure is 888 PSI Test pressure is up to 1,500 PSI Relatively short duration (approx. 30 minutes) Reduce to intermediate pressure at 1,357 PSI Maintain for 8 hours 10

12 How the Test is Performed (con t) De-pressurize the line Drain the water from the system If any integrity issues are found: They are corrected as soon as possible The hydrotest is performed again Any re-testing will be performed as soon as possible, during the same hours Resume normal natural gas service 11

13 Safety During the Test Safety is our #1 priority Performed extensive test preparations, including an inspection of the entire system Any pipe anomalies will be repaired in advance of conducting the hydrotest For the duration of the high pressure test, as a safety consideration, we plan to isolate sections of the pipeline route from people and traffic 12

14 Conducting the Test Advance Preparations Make all key stakeholders aware Adjacent property owners Emergency service providers General driving public Announcements Flyers, newspaper, website, etc. Dynamic message signs 2 weeks in advance 13

15 Conducting the Test (Con t) Night of the Test Begin at midnight Close roads/lanes with barricades Law enforcement support Confirm all-clear along the 17.0-mile corridor Conduct hydrotest Reopen roadways at approximately 4:00 AM 14

16 Traffic Control During the Test General Utility Permit from the Florida Department of Transportation is in process Officers will be stationed at road and lane closures Emergency responders will be able to cross as needed Detours will include signs and officer support 15

17 Detours During the Test For Northbound US 301: E Fowler Ave Main St Ft King Hwy Stacy Rd 16

18 Detours During the Test (Con t) For West Knights Griffin Road: Cooper Road Thonotosassa Road McIntosh Road Fort King Highway 17

19 Project Location District 2 18

20 Project Location District 4 19

21 For More Information Please visit our website: Or contact FGT: Mr. Terry Coleman 2405 Lucien Way, Suite 200 Maitland, FL Toll Free 844-FGT-INFO ( ) Office Fax

22 FGT Section #1 Hydrotest Summary Federal mandate Testing with water Test will be Friday, 3 October 2014 Midnight 4:00 AM US 301 lane closure NB West Knights Griffin Road full road closure With law enforcement Emergency vehicles can always cross 21