1 Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Uzbekistan Uzbekistan Bukhara and Samarkand Sewerage Project (P112719) Operation Name: Uzbekistan Bukhara and Samarkand Sewerage Project Project Stage: Implementation Seq.No: 5 Status: ARCHIVED Archive : 29-Dec-2012 (P112719) Country: Uzbekistan Approval FY: 2010 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key s Board Approval 04-Aug-2009 Original Closing Planned Mid Term Review 04-Mar-2013 Last Archived ISR 26-Jun-2012 Effectiveness 01-Apr-2010 Revised Closing Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objectives (PDO) are to mitigate the environmental impact from wastewater pollution and improve the efficiency and sustainability of wastewater management in Bukhara and Samarkand. This will be achieved through (a) rehabilitating select sections of the sewerage system that are deteriorated; (b) limited expansion of the sewerage system into currently unconnected central historical areas, (c) installing more energy-efficient equipment such as wastewater pumps and aeration systems at the wastewater treatment plants and pumping stations; and (d) improving the capacity of the water utilities (vodokanals) in the areas of management, communications and public outreach. Has the Project Development Objective been changed since Board Approval of the Project? losure Authorized Public Disclosure Authorized Yes No Component(s) Component Name Component Cost A1/Bukhara physical investment A2/Samarkand physical investment B1/Bukhara institutional strengthening and capacity building 0.46 B2/Samarkand institutional strengthening and capacity building 0.53 C/Feasibility studies for future investmetns 1.01 D/Project management 1.56 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Page 1 of 6

2 Implementation Status Overview Despite on-going acceleration, the Bukhara and Samarkand Sewerage Project (BSSP) remains a slow disbursing project, with about 20.2% of available funding disbursed after 31 months of implementation (i.e. after 45% of planned implementation duration). Since Effectiveness in April 1, 2010, and mobilization of the Implementation Consultant in January 2011, the Project has experienced a range of delays, some of which associated with the lengthy completion of infrastructure surveys and preliminary design of necessary works, before the procurement and execution of detailed designs and then construction activities could initiate in full, others linked to quality and procedural issues in the processing of initial procurement packages. Despite satisfactory implementation of works to date, some contractor payment delays have also unduly affected disbursements. With the completion or pending finalization of the main detailed design packages for works, and the growing number of large contracts under execution or being procured, continued acceleration of BSSP disbursements pace is expected in coming months. This acceleration must be sustained by increased attention to the quality of bid packages, procurement processes and contract administration. Weak Financial Management performance under the project has been confirmed in the 2011 audit reports, flagging weak internal controls and some potential ineligible expenditures. Questions pertaining to potential ineligible expenditures have since been further documented and resolved. An action plan is under way to address capacity issues, such as staffing, systems and methods underlying the internal control and reporting issues. The surveys and preliminary design activities have identified more extensive infrastructure rehabilitation needs than originally assessed in the feasibility study, leading to substantial revisions of investment needs and costs. Network and plant rehabilitation needs have been significantly underestimated in the feasibility study which supported appraisal. Available funding is to be applied to priority needs, and a restructuring of BSSP objectives and scope may be decided at the mid-term review. Opportunities for additional financing may subsequently be assessed based on improved performance and level of disbursement of the Project. Locations Country First Administrative Division Location Planned Actual Uzbekistan Samarqand Viloyati Samarqand Uzbekistan Buxoro Viloyati Buxoro Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target 1.1 Pollution load on downstream communities measured by amount of sewerage/bod5 removed at WWTP in BVK 1.2 Pollution load on downstream communities measured by amount of sewerage/bod5 removed at WWTP in SVK Metric ton Value Jul-2009 t/a No change. Not recently measured. Parameter will not be impacted until WTTP rehabilitation is effective t/a Metric ton Value t/a No change. Not recently t/a measured. Parameter will not Page 2 of 6

3 2.1 Collection of Sewage into the wastewater treatment plant (WWTP) in BVK 2.2 Collection of Sewage into the wastewater treatment plant (WWTP) in SVK 3.1 Energy efficiency at the WWTP and wastewater pumping stations in BVK 3.2 Energy efficiency at the WWTP and wastewater pumping stations in SVK be impacted until WTTP rehabilitation is effective Metric ton Value t/a No change, Not recently t/a measured. Metric ton Value Nov-2009 t/a No change. Not recently t/a measured. Text Value Nov-2009 Kwh/kg of BOD5 No changes. Parameter will Kwh/kg of BOD5 not be affected until rehabilitation and expansion works come online Text Value kwh/kg of BOD5 No changes. Parameter will kwh/kg of BOD5 not be affected until rehabilitation and expansion works come online 4.1 Financial working ratio in BVK Number Value Year 2 (2011) Added point available, 2010 Working ratio Financial working ratio in SVK Number Value Year 2 (2011) 5.1 Number of sewer blockages per year in BVK Added point available, Working Ratio: 0.89 Number Value year 2 ( ) Added point available: Page 3 of 6

4 5.2 Number of sewer blockages per year in SVK Intermediate Results Indicators 1580 avge blockages in Year 1 ( ) Number Value Year 2 ( ) Added point available: 1189 blockages in Year 1 ( ) Indicator Name Core Unit of Measure Baseline Current End Target A1.1 Cumulative length of sewer lines in Kilometers Value Bukhara This indicator measures length of sewer rehabilitation A1.2 Cumulative length of sewer lines in Kilometers Value Samarkand This indicator measures length of sewer rehabilitation Penjikent Street are new works, previously double counted as new and rehabilitations A2.1 Cumulative length of new sewer lines Kilometers Value constructed in Bukhara new sewers NYD A2.2 Cumulative length of new sewer lines Kilometers Value constructed in Samarkand Penjikent Street works A3.1 Cumulative number of new households Number Value connected to the public sewer system in Bukhara NYD A3.2 Cumulative number of new households Number Value connected to the public sewer system in Samarkand Previous year 2010 = 65 Page 4 of 6

5 B1 Development of Communication and Public Awareness Strategy for BVK and SVK B2 % of VK and Makhalla staff trained in utility management, O&M and communications B3 Improved management and emergency responsiveness of BVK & SVK due to installation of a pilot SCADA system C1 Feasibility studies for future investments Text Value Text Value no CPA strategy implementaion of CPA strategy 06-Jul-2009 Number Value Activities not started annually starting from 2011 Text Value no system in place system operational NYD FS for Alat & Karakul WSP Data on Financial Performance (as of 03-Dec-2012) Financial Agreement(s) Key s Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P IDA Effective 04-Aug Nov Apr-2010 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P IDA Effective XDR Disbursement Graph Page 5 of 6

6 Key Decisions Regarding Implementation There are no key decisions to report for disclosure with this ISR. Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Page 6 of 6