1 APPLICATION OF THE NAMAF (NATIONAL ASSET MANAGEMENT ASSESSMENT FRAMEWORK) TO IMPROVE ASSET MANAGEMENT IN DUBBO, NSW Abstract Stewart McLeod Director Technical Services, Dubbo City Council, NSW Mark Loaney Director, Oranasoft, Mudgee NSW Dubbo City Council, a major regional City in central NSW with a population of 41,000 people, has long been focused on responsibly managing its asset base. In 2009/10 it sought to improve the management of infrastructure by engaging Review Today to undertake a financial sustainability review of the whole Council. This review included an assessment of the state of Council Infrastructure together with estimated costs to address funding gaps. An important outcome was the creation of a Superior Asset Management project to undertake a full review of Council s asset management practices and processes to ensure accurate and up to date information is available. The consultancy Core Business facilitated a self-assessment (July 2012) using the 11 elements of the National Asset Management Assessment Framework (NAMAF). This assessment indicated that Council had 43% compliance, with significant opportunities for improvement. The NAMAF allowed Council to develop a detailed improvement plan that resulted in Council achieving 87% compliance by March 2015, and has now moved it from a Core competency level to Advanced competency. This paper details the activities and improvements achieved over the past two and a half years by creating and updating responsibilities, processes, data management, asset condition and renewal modelling. Details on the infrastructure backlog and funding gaps across all the major asset groups have been quantified and used to develop the Council s latest Asset Management Strategy. Keywords: NAMAF, asset management, strategy, backlog, funding gap, improvement program Introduction Asset management as a discipline was introduced to NSW Councils in The new Local Government Act of that year required all Councils for the first time to recognise their assets on a balance sheet, with a due by date of 1 July 1995 for all classes of assets. Australian Accounting Standard (AAS) No. 27 Financial Reporting By Local Government detailed how this was to be done. The earliest technical guidance for the industry was that provided by the NSW Department of Public Works. They published Strategic Business Planning Guidelines for use with water supply and sewerage assets in November 1993, which included very detailed chapters on asset management as we know it today. One of us (McLeod) was on the steering committee set up by the Department to oversee these Guidelines as they progressed from Draft to Final form. This exposure made Mr McLeod an early adopter and champion of asset management within NSW Local Government. The second major resource made available to industry was the IPWEA (then IMEA) National Asset Management Manual published in October This has now become the widely read and used IIMM. Dubbo City Council (DCC) duly completed its first cut of asset registers for roads, water supply, sewerage, drainage, parks, gardens and buildings by 1995 as required. ROCOND rating of roads was undertaken between 1993 and 1995, updated again in 2001, and then periodically thereafter up to the present day. Mr McLeod has a history of working with identified industry leaders to update and

2 improve DCC s asset management practices. Ballarat City Council won the 1997/98 Australia and New Zealand Asset Management Quality Competition, so a visit was made there to absorb new and better ideas. In 1999 Max Anderson of the Melbourne consultancy MWH was engaged to introduce advanced asset management techniques for Council s water utility function (water supply and sewerage), and continued to carry out that role until In 2000 Council engaged Jeff Roorda of JRa to prepare a Transport Asset Management Strategy for Dubbo (published 2001), and this was updated at various intervals in 2005, 2007, 2008 and Also in 2009 DCC became a NAMS.Plus Council and migrated all of its existing Asset Management Plans into that new format. In December 2008 Professor Percy Allan of Review Today was invited to Dubbo to undertake a Sustainability Review of DCC including its asset management capability. This latter component was sub-contracted to GHD Pty Ltd. The result in 2010 was a Review which warned of apparent backlogs in Council s asset renewals which needed to be addressed urgently to avoid the Council becoming unsustainable. Road funding was reported by Prof Allan as the elephant in the room, most of the other is mice and rats. Improvements to Council s existing asset management processes were also recommended. In 2010 Mr McLeod became aware that the NAMAF was under development by the Australian Centre of Excellence for Local Government (ACELG). It was recognised immediately by him that this new conceptual framework/checklist represented a step change in Councils ability to implement asset management more holistically than previously. Superior Asset Management Project After lengthy consideration of the Percy Allan Review, Dubbo City Council formally committed in July 2012 to what it termed a Superior Asset Management Project. Mr McLeod commenced the project by engaging Bruce Lorimer and his Core Business consultancy team from Western Australia. Lorimer s initial action was to facilitate a workshop with key internal staff to complete a self assessment using the NAMAF at a Core level. This tool provides a nationally consistent approach and enables an assessment on progress in implementing the LGPMC Financial Sustainability Framework. Further details on the NAMAF are available on the LGAM Knowledge Base website ( A self-assessment tool is also now available via the NAMS Plus web portal. Essentially, the assessment consists of eleven (11) elements and at core level seventy six (76) objectives to achieve core compliance. The elements are: 1. Strategic Long Term Planning 2. Annual Budget 3. Annual Report 4. Asset Management Policy 5. Asset Improvement Strategy 6. Asset Management Plans (AMPs) 7. Governance and Management 8. Defining Levels of Service (LOS) 9. Data & Systems 10. Skills and Processes 11. Evaluation The result of the self-assessment in 2012 indicated that DCC had a 43% compliance with these objectives. An improvement plan (Appendix A) was developed and recommended by the Asset Management Working Group (AMWG) to the Executive Staff Committee (ESC). This plan was adopted in December The implementation of the plan is being project managed by Mark Loaney from Oranasoft and is being overseen by the Asset Management Working Group, which consists of 20 representatives from across the organisation. From this a core team of 7 have been undertaking most project tasks.

3 Monthly reports are presented to the ESC who have provided strong leadership to ensure progress of the project. Council has improved significantly since the original assessment and achieved 87% overall compliance by March Strategic Long Term Planning Dubbo City Council already had a robust framework in 2012 around the development of a strategic long term plan having finalised development of its Community Strategic Plan (CSP) Dubbo A gap existed in the alignment of the AMP s with the CSP. The asset plans developed originally did not contain long term renewal modelling or forecasting of operations, maintenance and other capital works. Over the past two years with the capture of condition ratings on all major asset components, and completion of the asset registers, Long Term Financial Plans (LTFPs) have been included in each AMP and summarised in the Asset Management Strategy (AMS). For the first time, this analysis is being used to assist in the development of the Council LTFP, and is now available to link into the Delivery Programs. Any changes made to the LTFP during the adoption of the budget will be reflected in the next round of AMP s and the AMS. This element has improved from 80 to 95%. Annual Budget Due to the lack of integration between long term forecasts for asset expenditure and the LTFP, Council did not have the integration expected under the NAMAF for budgeting. Work has focused on updating the Operational Plan template to clearly explain the assumptions and methodologies used to underpin the estimates included, and how these align with the CSP and AMP s. The element has improved from 75 to 100%. Annual Report The annual report produced by Council met the requirements of the NSW Office of Local Government (OLG), however under the NAMAF there was a gap in reporting how variations between actual and budget figures impact on the LTFP. The poor linkages between AMPs and LTFP affected the performance within this criteria. Development of the AMP LTFP can now be used to assess the impact of these changes. This element has improved from 70 to 100%. Asset Management Policy Council had adopted a policy as part of the CSP which met most of the requirements of the NAMAF. Improving the policy required detailing linkages with the Strategic Long Term Plan and LTFP. The updating of the policy to ensure it complied with these requirements was straightforward with the updated policy adopted by Council in April This element has improved from 70 to 100%. Asset Improvement Strategy Originally the Asset Management Strategy didn t include most of the elements required under the NAMAF. It had poor linkage to the policy and lacked integration with strategic longer term planning and annual budgets. The NAMAF workshop and gap analysis helped focus the development of an improvement plan which was subsequently incorporated into the AMS. The AMS (Appendix B) was completely rewritten focusing on the requirements of the NAMAF and setting the requirements for the development of the AMP s. The improved AMS was adopted by Council in June From discussions with Councillors and General Managers in recent years, it has become obvious that the Executive Summary in the AMS needs to be a punchy document

4 that provided a good overview of the findings of the AMPs and forecasted financial data. The following table and graphs extracted from the AMS highlight the high level information sought, focusing on the funding gap and backlog as well as the overall asset condition based on replacement value. The rolling backlog is the shortfall in funding in any year, it is not a cumulative figure. This element has improved from 42 to 100%. Asset Management Plans Dubbo City Council has had a suite of Function Plans since the early 1990 s that cover each business unit within Council. As a result details on the management of assets were scattered throughout a number of these documents. The most impacted were buildings which had minimal asset information scattered across 24 Function Plans. Under the NAMAF, 22 core objectives are identified to assist in developing robust asset management plans.

5 In the first year, the information from the Function Plans was collated to develop 6 Asset Management Plans: 1. Transport 2. Water 3. Sewer 4. Drainage 5. Buildings 6. Parks & Landcare Within each a hierarchy was developed, linkages made to the AMS and CSP, and a first cut renewal model developed based on very high level data and average lifecycle costs. These plans were adopted by Council in June Over the next 12 months, the team spent considerable time improving the knowledge of their assets and ensuring that asset registers were complete and accurate. A Condition Assessment Manual was developed that contained photographs of all the major asset components in each condition on a 0 to 10 scale. This information was then used to rate these assets. The next key element was the determination and documentation of useful lives. A review of the actual life being achieved indicated that water, sewer and drainage pipes were lasting much longer than originally modelled. Road pavements in residential areas were increased to 90 years and collector roads to 60 years. The AMP template was modified to capture the core elements of the NAMAF, with a focus on making the plans more readable. Their length reduced to around 30 pages, with a 1-½ page executive summary. Each AMP has sections dedicated to renewals, upgrade/new, maintenance and also operational expenditure. One of the main challenges in bringing this information together was the ability to extract historical information from the Financial System. The separation of renewal and maintenance was particularly challenging. Work is currently underway to code the General Ledger so that historical costs and future budgets can be extracted for development of AMPs. Each AMP now incorporates a 20 year LTFP for each of these programs which is rolled up into the AMS. This information is also being used to assist in the development of the Corporate LTFP. The intent is that the information from the AMP s will be finalised in October and used to assist in the development of forward budgets. The Council will determine spending during April and June. This information will then be used in the next suite of AMP s. Future focus is on improving knowledge of the assets and their rate of deterioration, incorporating the corporate ERM (risk) analysis and improving details on Levels of Service. This element has improved from 13 to 84%. Governance and Management Dubbo already had a strong corporate asset focus with an Asset Management Working Group (AMWG) having been established in The existence of this group has enabled the excellent progress on the NAMAF improvements detailed in this paper. The first task was reviewing the roles and responsibilities for Assets within the organisation. A matrix of asset responsibilities were workshopped, together with the assets and those staff having asset responsibility. Position Descriptions were updated and assisted in identifying training needs. A Capital Works Evaluation Framework was developed that uses the Council Intranet to score and prioritise future capital projects. This element has improved from 71 to 100%. Levels of Service The 2014 AMP s included a review of the LOS previously identified. We decided that there were too many indicators that didn t tie clearly to the LOS we considered the community were seeking.

6 The LOS were simplified and presented in a format that tightened the linkage to the CSP, however more work is still required. The IPWEA training on the Practice e (8) has helped the team identify the improvements required. The final phase will be the development of Service Plans in consultation with the community and investigating the cost of providing services at differing levels. This element has improved from 31 to 56%. Data & Systems Good detail was held on water and sewer pipe network data in PipePak, however the data for Transport and Park s whilst detailed was only captured within spreadsheets. The drainage network is also captured in PipePak, however there had previously been a period where the data was not kept up to date, hence some time has been needed completing this data set. Of all the data, buildings were the most incomplete. The only information available was either contained within insurance registers or the capital value register. As part of our project all buildings were inspected, components measured, condition rated, and captured in the Buildings Plus system by a contractor working with staff. This system had the flexibility to also capture Parks information and due to the facility structure we were using, this became a good option for Council. To enable validation of the Transport data and undertake modelling, the spreadsheets were imported into the Civica AM system. Linking this system with the GIS made it easier to identify data gaps. Council worked with the supplier of PipePak to modify that system to undertake renewal modelling (updates delivered mid 2014). While there is a common framework for the capture of data and the information needed, none of these systems apart from Civica s can easily integrate with the financial system. The process to import asset data into the corporate Capital Value Register is an arduous one and can currently only contain a snapshot of information at the time. Council is considering an option to investigate a single corporate asset management system. If that doesn t occur, the project identifies the need for a more formal linkage between the systems. As part of this element, a number of processes are required. Rather than have a disparate range of policies, procedures and flow charts, a decision was made to develop an Asset Management Manual (AMM). The intention is that this will be the go to source of information for all asset management activities required within Council. It continues to be a work in progress, with the following sections in a final draft form (March 2015): 1. Roles & Responsibilities 2. Governance and Management 3. Consultation & Communication 4. Data & Systems 5. Life Cycle Analysis & Costing 6. Capital Evaluation Preliminary flow charts have been developed for operations, maintenance, project management, and asset creation processes for inclusion in the AMM. At present unit rates are stored in the individual asset management systems, however the process for determining and updating these rates will also be included in the AMM. This element has improved from 44 to 91%. Skills & Processes Processes have been developed to ensure that the AMS and AMP s are updated and adopted by Council at least on a 5 yearly cycle, with the last plans adopted in A number of informal processes exist for the handover of new assets and ensuring that

7 they are captured in the appropriate systems (AMS / GIS). Work is underway this year to investigate the implementation of ACDC to automate the capture of data and support formal asset handover. As a result of defining responsibilities in the Governance element, training needs for key staff were identified. Meetings were held in each division to confirm whether skills needed were already held or whether they would benefit from training. Based on these sessions, 3 priority areas were identified for the first round of training. Sessions were facilitated by Mark Weller from Core Business over 5 days in October 2013 with over 40 staff attending at least one of the following sessions: Conduct Asset Inspections (2 x 1 day) Coordinate Asset Maintenance (2 x 1) Whole of Lifecycle Analysis (1 day) A second round of training was held on Project Management in April 2014 with a 2- day course attended by 25 people. These 4 courses covered the highest priority areas within Council, however additional training needs have been identified and courses scoped (Appendix C). This element has improved from 45 to 80%. Evaluation The final element included in the NAMAF is the evaluation of the improvement processes. At this stage minimal formal work has been undertaken on documenting the evaluation process. However monthly reports are presented to the AMWG and ESC for review and feedback. As part of the finalisation of the 2014 AMS and AMP s, Council engaged Morrison-Low to undertake an audit of the plans and Council s overall progress in its Asset Management Process. The results of this audit were very pleasing with Council achieving a score of 7.2, just below Morrison-Low s assessment of an advanced level of competence (requiring 7.5). Since the audit, a major gap being the identification of critical assets has been addressed in the AMS and AMP s. This would move the overall score up to 7.5. This element has improved from 17 to 42% Conclusion Measuring the maturity of Dubbo s asset management processes and documentation against the NAMAF enabled the development of a clear project plan to ensure effective improvements were achieved. Over a period of some 30 months Dubbo City Council was able to progress from Core competency to Advanced competency in its asset management. Successful delivery of the project required exceptional support and direction from the General Manager and Directors. This enabled the allocation of resources and time to complete the tasks necessary. The project required the focus of a project manager to keep activities moving along and to provide mentoring to staff undertaking the activities. For a project of this size and with the timeframes defined, it s important to recognise that external help may be required, especially if there isn t an asset team whose sole focus is on Asset Management. As with all projects, it was important to define tasks, timeframes and responsibilities, then monitor and report on progress. The easy tasks were the long term financial plan, annual budget and annual report as these tasks were already operating at a mature level within Council. The development of the Policy was also an easy target. Most time has been spent improving the knowledge of our assets and developing robust AMP s. With detail information on our assets, the revaluation of transport and drainage was a far less arduous process. Over the coming months the focus will be on improving details relating to LOS, risk management, system integration and

8 updating condition assessments and the AMS and AMP s. The following figure from the AMS highlights the progress made at Dubbo and compares this performance to benchmarked Councils from Core Business obtained in late Figure 1.3 Status of the NAMAF Improvement Program

9 Appendix A : NAMAF Improvement Plan e that the improvement plan has been continually updated over the past 30 months, with new tasks identify to assist in the effective management of assets. The scoring in the body of the report reflects Council s achievement of the key elements in each objective. # Details Status Due 1 Strategic Long Term Planning On Track 31/03/ Council has a Strategic Longer Term Plan (planning horizon of at least 5 years) that incorporates a vision, strategic outcomes, mission, values and service outcomes that Council wants to achieve. 1.2 The development of the Strategic Longer Term Plan included community consultation and reflects community needs. 1.3 The Strategic Longer Term Plan incorporates priorities and performance measures and indicates how they will be monitored and measured. 1.4 Council has a sustainable Long Term Financial Plan covering the period of the Strategic Longer Term Plan (at least 5 year) supporting the implementation of its Long Term Plan. 1.5 The Long Term Financial Plan has been prepared based on the resource requirements and strategic objectives detailed in Council s Long Term Plan and Asset Management Plans. Completed 30/01/2013 On Track 31/03/2017 Completed 9/04/2013 Completed 1/12/2012 On Track 31/03/ Annual Budget Completed 16/03/ The Annual Budget contains estimates of revenue and expenditure with an explanation of the assumptions and methodologies underpinning the estimates, an explanation of the financial performance and position of the Council and has been prepared based on the resource requirements and strategic objectives detailed in Council s Strategic Longer Term Plan, Asset Management Plans and Long Term Financial Plan. 2.2 The Annual Budget reflects the Council's strategic objectives and contains a statement of how Council will meet the goals and objectives of its Strategic Longer Term Plan. 2.3 The Annual Budget aligns with Year 1 of the Long Term Financial Plan, and was adopted following community consultation 2.4 Council s Annual Budget includes resources to implement Strategic Longer Term Plan strategies. Completed 16/03/2015 Completed 16/03/2015 Completed 16/03/2015 Completed 16/03/ Annual Report Completed 1/10/ The Annual Report complies with all statutory requirements including publication by the due date and is made widely available to the public. 3.2 The Annual Report includes independently audited financial statements that are prepared on an accrual basis in accordance with the Australian Accounting Standards. 3.3 The Annual Report reviews the performance of the Council against its strategic objectives and explains variations between the budget and actual results and how these variations impact on the Strategic Longer term plan 3.4 The Annual Report includes details of any major changes in functions of the Council, organisation structure and/or policy initiatives and how these changes might impact on Council s Strategic Longer Term Plan Completed 1/09/2013 Completed 31/10/2013 Completed 31/10/2013 Completed 30/10/2013

10 # Details Status Due 3.5 In relation to the financial reporting framework in the Annual Report, the Annual Report addresses the following issues in accordance with relevant state policies, Australian Accounting Standards and other best practice guidelines: a. Asset valuations and revaluations b. Asset acquisitions including capitalisation policy c. Asset disposals Completed 1/10/ Asset Management Policy Ongoing 30/3/ Council has an adopted Asset Management Policy which defines the Council s vision and service delivery objectives for asset management. 4.2 The Asset Management Policy has a direct linkage with Council s Strategic Longer Term Plan and Long Term Financial Plan. 4.3 The Asset Management Policy requires the adoption of Asset Management Plans informed by community consultation and local government financial reporting frameworks. 4.4 The Asset Management Policy defines asset management roles, responsibilities and reporting framework. 4.5 The Asset Management Policy identifies a process for meeting training needs in financial and asset management practices for councillors and staff. Completed 1/04/2013 Completed 13/02/2013 Completed 13/02/2013 Completed 15/02/2013 Completed 1/03/ Asset Improvement Strategy Ongoing 6/10/ Council has an Asset Management Strategy which shows how the asset portfolio can meet the service delivery needs of the community and defines the future vision of asset management practices within Council 5.2 Council s Asset Management Strategy is linked to Council's Asset Management Policy and integrated into Council s Strategic Longer Term planning and annual budgeting processes. 5.3 Council's Asset Management Strategy documents the current status of asset management practices (processes, asset data and information systems) within the Council and what actions Council must take to implement the Asset Management Policy, including resource requirements, timeframes and accountabilities. Completed 13/02/2013 Completed 13/04/2013 Completed 18/12/ Asset Plans Ongoing 30/11/ There are documented Asset Management Plans for all material asset groups in a consistent format in accordance with industry best practice (E.g. Appendix A of the International Infrastructure Management Manual (IIMM)) available to all relevant staff across the organisation. 6.2 The Asset Management Plans define which asset groups are covered by each Plan in accordance with a clearly documented Infrastructure Asset Hierarchy. 6.3 a. AMP refers to Council's Asset Management Policy and Asset Management Strategy; 6.4 b. AMPs Include all assets and document asset inventory information for the asset group/category as recorded in the asset register; Completed 1/02/2013 Completed 1/02/2013 Completed 1/02/2013 Completed 1/02/ c. AMPs Document the asset hierarchy within each asset group; Completed 1/02/ d. AMPs Document the current condition of assets; Completed 31/07/ e. AMPs Document the adopted useful lives of assets; Completed 3/10/ f. AMPs Include risk assessment and criticality profiles; On Track 25/09/2015

11 # Details Status Due 6.9 g. AMPs Provide information about assets, including particular actions and costs to provide a defined (current and/or target) level of service in the most cost effective manner; 6.10 h. AMPs Include demand management forecasts; Completed 1/08/2015 1/08/ i. AMPs Address life cycle costs of assets; Completed 27/05/ j. AMPs Include forward programs identifying cash flow forecasts projected for i. Asset Renewals; 6.13 j. AMPs Include forward programs identifying cash flow forecasts projected for ii. New Assets and Upgrades of existing assets; 6.14 j. AMPs Include forward programs identifying cash flow forecasts projected for iii. Maintenance expenditure 6.15 j. AMPs Include forward programs identifying cash flow forecasts projected for iv. Operational expenditure (including depreciation expense); 6.16 k. AMPs Address asset performance and utilisation measures and associated targets as linked to levels of service; 6.17 l. AMPs Include an asset rationalisation and disposal program; and Completed 14/08/2014 Completed 1/09/2014 Completed 30/06/2014 Completed 30/06/2014 On Track 6/10/ /09/ m. AMPs Include an asset management improvement plan. Completed 30/09/ n. AMPs Include consideration of non-asset service delivery solutions (leasing private/public partnerships) 6.20 o. AMPs Recognise changes in service potential of assets through projections of asset replacement costs, depreciated replacement cost and depreciation expense The Asset Management Plans link to the Council s Asset Management Policy, Asset Management Strategy, Strategic Longer Term Plan, Long Term Financial Plan and other relevant Council Policy objectives The Asset Management Plans have all been prepared in association with community consultation. 30/09/2016 Completed 3/10/2014 Completed 1/10/ /11/ Governance and Management Ongoing 31/07/ Council has mechanisms in place to provide high level oversight by the Council, CEO/GM and Executive Management Team, for development and implementation of the Asset Management Strategy and Asset Management Plans. 7.2 Roles and responsibilities are clearly defined in a matrix or policy, identifying positions responsible for determining levels of service and positions responsible for managing the assets to meet service delivery needs 7.3 The staff structure and position descriptions clearly define asset management functions, responsibilities and skill requirements for managing all asset classes. Completed 6/08/2013 Completed 25/03/2013 Completed 30/04/2013

12 # Details Status Due 7.4 Council has a documented process for making capital investment decisions, which is driven by Council s Strategic Longer Term Plan, Long Term Financial Plan and the Council Plan and explicitly details the impacts on the future operations and maintenance budgets, Whole of Life costs and risk management assessments. Completed 31/07/ Council involves all its departments in Asset Management. Completed 5/02/ Council has an Asset Management Steering Committee, with cross functional representation and clearly defined and documented terms of reference, focussed on coordinating the linkages between service delivery and asset management implementation. Completed 1/12/ There are internal processes to promote Asset Management across Council Completed 29/11/ Levels of Service On Track 30/09/ Council has Service Plans for each of its services which have been developed in consultation with the community. 8.2 Council has undertaken the process of defining, quantifying and documenting current community levels of service and technical levels of service, and costs of providing the current levels of service. 8.3 Current and target levels of service (for both community levels of service and associated technical levels of service) are clearly defined in each Asset Management Plan. 8.4 Technical levels of service are incorporated into service agreements and/or maintenance, operational and capital renewal procedures. 30/09/ /09/2015 On Track 30/09/ /09/ Data & Systems On Track 30/06/ Council has a consolidated, integrated, accurate, up to date and complete componentised asset register with the required functionality to ensure security and data integrity, which includes all information about each asset sorted by asset group. 9.2 There is a common corporate data framework used across all asset groups, which is defined by Council s Infrastructure Asset Hierarchy. 9.3 Council has documented repeatable methodologies to carry out consistent asset condition surveys and defect identification assessments, as documented in a Condition Rating Assessment Manual for applicable asset classes 9.4 Council's asset financial reporting functionality is comprehensive and includes audit trails, depreciation calculations, reporting thresholds and records of acquisition and disposal of assets 9.5 Council's systems, procedures and processes allow it to benchmark its asset management performance against like Councils over time. 9.6 Asset Management systems have the functionality to generate maintenance and renewal programs and produce associated cash flow forecasts. 9.7 Council has defined and documented procedures for determining asset replacement and treatment unit rates, which are then stored in Council s Asset Management system. 9.8 Council has a defined process for operations, maintenance, renewal and upgrade planning for its existing assets. On Track 31/03/2015 On Track 30/06/2015 Completed 18/10/2013 Completed 30/03/2014 Completed 30/08/ /06/2016 Completed 28/04/2014 On Track 1/12/2015

13 # Details Status Due 10 Skills & Processes On Track 30/10/ Council has a process to review and update the Asset Management Strategy on a maximum of a 5 year cycle. The Asset Management Strategy is to be formally adopted by Council Council has a process to review and update Asset Management Plans for all asset groups on a maximum of a 3 to 4 year cycle consistent with the Council election cycle. Asset Management Plans are formally adopted by Council 10.3 Council has a process to identify operational risks, assign responsibilities and monitor risk treatment actions all recorded within a risk register Council has a process to annually review and update the financial forecasts for all asset classes and update the Long Term Financial Plan Council has assessed the skills and knowledge required to perform asset data management activities, conduct financial reporting valuations and develop Asset Management Plans. Council has a current asset management skills matrix. Staff training needs have been identified and training scheduled Council has a defined methodology for assessing the Remaining and Useful Life, Residual Value and Depreciation Method of assets Council has a process to collect and record asset data into an Asset Management system upon the commissioning of new (and/or modified) assets, including built and contributed assets Council has formal processes for the handover of assets to asset custodians/owners Council has a process to communicate the financial implications of the Asset Management Plans to internal and external stakeholders Council provides ongoing training programs for councillors, council management and officers on key asset management topics. Completed 30/04/2013 Completed 1/10/2014 On Track 30/04/2015 On Track 30/09/2015 Completed 27/09/2013 Completed 28/03/2014 On Track 31/03/2015 On Track 30/03/ /03/ /10/ Evaluation On Track 15/07/ Council has a documented evaluation process by which asset management improvements are identified, timeframes established, resources allocated, actioned, monitored and reported to the Executive Management Team and /or CEO Technical levels of service are monitored and performance reported. Community levels of service are monitored and performance reported. Commence d On Track 15/07/2016 1/07/2016 1/07/2016

14 Appendix B: Asset Management Strategy Contents The contents of the AMP s reflect closely that contained in the strategy. The key difference is the inclusion of works programs (maintenance, renewal, and upgrade / new) in the AMP s. 1. Executive Summary 2. Strategic Framework 3. Services Provided 4. Levels of Service 5. Condition of Council s Assets 6. Operations 7. Maintenance 8. Capital Renewal / Rehabilitation 9. Capital Upgrades & New Assets 10. Disposal Plan 11. Financial Plan 12. Key Performance Measures 13. Plan Improvements 14. Risk Management Plan 15. Appendix A: Example of Annual Service Costs 16. Appendix B: Improvement Action Plan (Feb 2015) 17. Appendix C: 20 Year Financial Plan (2014 $,000)

15 Appendix C: Training Priorities The following table was used to assist in the determination of which training sessions to conduct initially. A course outline was developed for each course and then staff with those responsibilities rated as low medium or high their need for training. The first three courses that were held are shaded.

16 Author Biographies: Stewart McLeod has worked in public works engineering since 1974, initially with the NSW Department of Public Works and then in Local Government from Stewart has held Director Technical Services positions at both Orange and Dubbo City Councils over the last 21 years, and received a Public Service Medal in the 2011 round of Australian Honours for services to public works engineering in regional NSW. He was an early adopter of asset management principles and practices in NSW Local Government and as early as 1999 presented a paper on asset management at Dubbo City Council to the APWA Conference in Denver, Colorado. Contact: Stewart.McLeod@dubbo.nsw.gov.au Mark Loaney has over 25 years experience in Local Government, commencing at Dubbo City Council in 1988 then continuing at Brisbane, Mudgee and Orange City Councils until Mark held senior management positions for nearly 20 years in Local Government. At the end of 2011 he commenced his full time consulting practice assisting Dubbo, Orange and Parkes Councils with implementation of Asset Systems and Strategies. At Dubbo and Orange he successfully led teams at each Council to deliver a total of 12 Asset Management Plans and 2 Asset Management Strategies, identify asset responsibilities and implement training programs together with development of process improvements and implementation of asset systems. Contact: mloaney@oranasoft.com.au

NATIONAL SUSTAINABILITY FRAMEWORK - Financial Planning & Reporting + Asset Planning & Management

NATIONAL SUSTAINABILITY FRAMEWORK - Financial Planning & Reporting + Asset Planning & Management National Competency Status Assessment Opinion Competency - Self Improvement Questionnaire NATIONAL SUSTAINABILITY FRAMEWORK - Financial Planning & Reporting + Asset Planning & Management Competency - Self

More information

10.0 ASSET MANAGEMENT PRACTICES. Table of Contents

10.0 ASSET MANAGEMENT PRACTICES. Table of Contents 10.0 ASSET MANAGEMENT PRACTICES Table of Contents 10.0 ASSET MANAGEMENT PRACTICES... 1 10.1 Current Asset Management Practices... 2 10.2 Asset Management Processes... 3 10.2.1 Attribute data collection

More information

Southern Councils Group Regional Procurement Roadmap Report October 2012

Southern Councils Group Regional Procurement Roadmap Report October 2012 Southern Councils Group Regional Procurement Roadmap Report October 2012 Background Procurement has been increasingly acknowledged world-wide as a vital strategic tool to reduce costs and improve performance

More information

ASSET MANAGEMENT SYSTEMS IN COUNCILS

ASSET MANAGEMENT SYSTEMS IN COUNCILS ASSET MANAGEMENT SYSTEMS IN COUNCILS White Paper Shoal Engineering Pty Ltd ACN 604 474 204 PO Box 7038 Hutt St SA 5000 Australia www.shoalgroup.com Overview For any organisation, asset management outcomes

More information

WOLLONGONG CITY COUNCIL CASE STUDY ON STRATEGIC, TACTICAL AND OPERATIONAL SERVICE LEVEL DEVELOPMENT USING NAMS.PLUS TEMPLATES

WOLLONGONG CITY COUNCIL CASE STUDY ON STRATEGIC, TACTICAL AND OPERATIONAL SERVICE LEVEL DEVELOPMENT USING NAMS.PLUS TEMPLATES WOLLONGONG CITY COUNCIL CASE STUDY ON STRATEGIC, TACTICAL AND OPERATIONAL SERVICE LEVEL DEVELOPMENT USING NAMS.PLUS TEMPLATES Mike Dowd, IMF Project Manager, Wollongong City Council. Ross Waugh, Director,

More information

ASSET LIFECYCLE MANAGEMENT OPTIMISE ASSET PERFORMANCE

ASSET LIFECYCLE MANAGEMENT OPTIMISE ASSET PERFORMANCE ASSET LIFECYCLE MANAGEMENT OPTIMISE ASSET PERFORMANCE A LIFECYCLE APPROACH TO ASSET MANAGEMENT Achieve alignment to asset management best practice, with a holistic approach to managing assets throughout

More information

TECHNICAL GOVERNANCE AND ADVISORY STRUCTURES FOR THE STANDARDS DEVELOPMENT PROCESS

TECHNICAL GOVERNANCE AND ADVISORY STRUCTURES FOR THE STANDARDS DEVELOPMENT PROCESS STANDARDISATION GUIDE 005: TECHNICAL GOVERNANCE AND ADVISORY STRUCTURES FOR THE STANDARDS DEVELOPMENT PROCESS COPYRIGHT Standards Australia Limited ABN: 85 087 326690 All rights are reserved. No part of

More information

Quick Guide: Meeting ISO Requirements for Asset Management

Quick Guide: Meeting ISO Requirements for Asset Management Please visit the NAMS.org.nz website for downloading the digital version of this quick guide. Supplement to the IIMM 2011 Quick Guide: Meeting ISO 55001 Requirements for Asset Management Using the International

More information

MARCH 2018 CITY OF HOBART PROCUREMENT STRATEGY

MARCH 2018 CITY OF HOBART PROCUREMENT STRATEGY MARCH 2018 CITY OF HOBART PROCUREMENT STRATEGY 2018 22 2 City of Hobart Transport Strategy 2018 30 Consultation Paper 1: Freight, Port and Air TABLE OF CONTENTS INTRODUCTION 5 PURPOSE 6 OUTCOMES 7 OUR

More information

ACTIVITY WORK PLAN CONTENTS

ACTIVITY WORK PLAN CONTENTS ACTIVITY WORK PLAN Activity Program Organisation Activity Plan Timeframe Strengthening the capacity, efficiency and effectiveness of Clinical Trials Networks through the Australian Clinical Trials Alliance

More information

A FIT FOR PURPOSE CORPORATE ASSET MANAGEMENT FRAMEWORK DESCRIPTION OF A JOURNEY

A FIT FOR PURPOSE CORPORATE ASSET MANAGEMENT FRAMEWORK DESCRIPTION OF A JOURNEY A FIT FOR PURPOSE CORPORATE ASSET MANAGEMENT FRAMEWORK DESCRIPTION OF A JOURNEY Phillip Burton Manager Assets and Contracts, District Council of Mount Barker Ashay Prabhu Managing Director, ACEAM Pty Ltd

More information

International Scan on Asset Management: Australia, Canada, England, and New Zealand. April 8-April 23, 2005

International Scan on Asset Management: Australia, Canada, England, and New Zealand. April 8-April 23, 2005 International Scan on Asset Management: Australia, Canada, England, and New Zealand April 8-April 23, 2005 Purpose Investigate best case examples of asset management techniques and processes in the world

More information

ISO AM STANDARDS AND NAMS RESOURCES WORKING TOGETHER

ISO AM STANDARDS AND NAMS RESOURCES WORKING TOGETHER ISO 55000 AM STANDARDS AND NAMS RESOURCES WORKING TOGETHER Peter Way PSM - Director NAMS Council - IPWEA peter.way@ipwea.org Abstract IPWEA has been involved in developing the ISO 55000 Asset Management

More information

MANAGING ASSETS THROUGH CAPABILITY AND KNOWLEDGE (MACK)

MANAGING ASSETS THROUGH CAPABILITY AND KNOWLEDGE (MACK) MANAGING ASSETS THROUGH CAPABILITY AND KNOWLEDGE (MACK) Ben Clark, Assets Business Administrator, City of Tea Tree Gully Abstract Managing Assets through Capability and Knowledge is a continuous improvement

More information

NSW Government Capability Framework - Benchmark Job Evaluations. NSW Department of Premier and Cabinet

NSW Government Capability Framework - Benchmark Job Evaluations. NSW Department of Premier and Cabinet NSW Government Capability Framework - Benchmark Job Evaluations NSW Department of Premier and Cabinet Contents 1. Work Value Assessments...1 Human Resources...1 Engineering...1 Finance...1 Legal...2 Project

More information

An IPWEA View on the ISO AM Standards. Peter Way PSM Member of MB 19 Standards Australia Mirror Committee Chair, IPWEA NAMS.AU

An IPWEA View on the ISO AM Standards. Peter Way PSM Member of MB 19 Standards Australia Mirror Committee Chair, IPWEA NAMS.AU An IPWEA View on the ISO AM Standards Peter Way PSM Member of MB 19 Standards Australia Mirror Committee Chair, IPWEA NAMS.AU Can these new ISO AM standards help you? Should you apply these standards?

More information

Asset Management Plans Within the Framework of the IIMM and ISO 55000

Asset Management Plans Within the Framework of the IIMM and ISO 55000 Asset Management Plans Within the Framework of the IIMM and ISO 55000 Water Infrastructure Conference Bethesda, Maryland October 13, 2015 What is an Asset Management Plan?. Long-term plan (usually 10-20

More information

6.1 CORPORATE ASSET MANAGEMENT POLICY

6.1 CORPORATE ASSET MANAGEMENT POLICY 6.1 CORPORATE ASSET MANAGEMENT POLICY Date Adopted Next Review Officer Responsible 3 February 2011 30 June 2015 Manager, Performance & Delivery Group Policy Purpose: The intent of this policy is to set

More information

Asset Management Policy

Asset Management Policy Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset

More information

7 Plan Improvement & Monitoring

7 Plan Improvement & Monitoring 7 Plan Improvement & Monitoring The City of Brampton s current asset management practices were assessed using a variety of tools including ISO 55000, Systems Review, PSAB Workflows, and workshops with

More information

Loch Lomond & The Trossachs National Park Authority and Cairngorms National Park Authority

Loch Lomond & The Trossachs National Park Authority and Cairngorms National Park Authority Loch Lomond & The Trossachs National Park Authority and Cairngorms National Park Authority Internal audit report 2014-15 Project Management 15 January 2015 Contents This report is for: Action David Cameron

More information

TEMPLATE. Asset Management. Assetivity

TEMPLATE. Asset Management. Assetivity TEMPLATE Asset Management Assetivity EXECUTIVE SUMMARY This section provides an overview of the Strategic Asset Management Plan (SAMP) including: Purpose of the document Overall strategy statement List

More information

Contractors may report to this position as required by projects

Contractors may report to this position as required by projects POSITION DESCRIPTION 1. POSITION DETAILS Position Title: Division: Unit: Management Level: Community Property Manager City Projects & Property Property Services Professional 2. ORGANISATIONAL RELATIONSHIPS

More information

Externally Facilitated Board Effectiveness Review

Externally Facilitated Board Effectiveness Review Draft issued: 16 March 2017 2 nd Draft issued: 20 March 2017 Final issued: 20 March 2017 CONTENT Page No. Section 1 Background 1 Section 2 Scope, Objectives and Overall Findings 1-2 Section 3 Audit Approach

More information

CONTENT. 2 Resourcing Strategy

CONTENT. 2 Resourcing Strategy CONTENT ABOUT THIS STRATEGY 5 INTRODUCTION 6 OUR INTEGRATED PLANNING AND REPORTING FRAMEWORK 6 LONG-TERM FINANCIAL PLAN 10 Overview 11 Background 12 Planning assumptions 12 Key assumptions 13 Financial

More information

A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT. [ T y p e t h e c o m p a n y a d d r e s s ]

A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT. [ T y p e t h e c o m p a n y a d d r e s s ] A PRACTICAL GUIDE TO: S.M.A.R.T.E.R. SUPPLIER MANAGEMENT Entire contents 2009 Procurementtoolkit.com. All rights reserved. Page 1 EVALUATION REPORT HISTORY Document Location This document becomes uncontrollable

More information

GREATER MANCHESTER HEALTH AND SOCIAL CARE PARTNERSHIP STRATEGIC PARTNERSHIP BOARD

GREATER MANCHESTER HEALTH AND SOCIAL CARE PARTNERSHIP STRATEGIC PARTNERSHIP BOARD NHS Bury CCG Governing Body Paper 6 appendix 6a 5ci GREATER MANCHESTER HEALTH AND SOCIAL CARE PARTNERSHIP STRATEGIC PARTNERSHIP BOARD Date: 29 April 2016 Subject: The Transformation Fund Report of: Katy

More information

POSITION OVERVIEW. Media & PR Manager Marketing and Communications Manager Accounts Assistant

POSITION OVERVIEW. Media & PR Manager Marketing and Communications Manager Accounts Assistant POSITION OVERVIEW TITLE: REPORTS TO: DIRECT REPORTS: Chief Operating Officer Chief Executive Commercial and Sponsorship Manager Media & PR Manager Marketing and Communications Manager Accounts Assistant

More information

Building Infrastructure Asset Management: Australian Practices

Building Infrastructure Asset Management: Australian Practices Building Infrastructure Asset Management: Australian Practices Session CIB T2S5 Facilities management and maintenance Mr. Ashish Shah* B.E. (Civil), M.E. (I.T.) RMIT University, Melbourne, Australia Mr.

More information

Level 2, 77 Hereford St Christchurch. Bill Dwyer (Chair) Bruce Irvine Bob Lineham. Fiona Mules Dr Jane Gregg Darren Wright Peter Houghton

Level 2, 77 Hereford St Christchurch. Bill Dwyer (Chair) Bruce Irvine Bob Lineham. Fiona Mules Dr Jane Gregg Darren Wright Peter Houghton STATEMENT OF INTENT FY 2017 Directory Address: C/o Christchurch City Holdings Ltd PO Box 73049 Christchurch 8154 Registered office: Level 2, 77 Hereford St Christchurch Establishment Board: Bill Dwyer

More information

OFFICIAL. Scottish Police Authority Board. Meeting. Case: Paper by Interim Chief Officer and Accountable Officer Reference B 08.

OFFICIAL. Scottish Police Authority Board. Meeting. Case: Paper by Interim Chief Officer and Accountable Officer Reference B 08. Agenda Item 8 Meeting Scottish Police Authority Board Meeting Date Location Stirling Court Hotel, Stirling Title of Paper Digital Data & ICT Outline Business Case: Paper by Interim Chief Officer and Accountable

More information

POST LICENSING OVERSIGHT AND INSPECTION OF MAJOR HAZARD FACILITIES AN AUSTRALIAN REGULATOR S EXPERIENCE

POST LICENSING OVERSIGHT AND INSPECTION OF MAJOR HAZARD FACILITIES AN AUSTRALIAN REGULATOR S EXPERIENCE POST LICENSING OVERSIGHT AND INSPECTION OF MAJOR HAZARD FACILITIES AN AUSTRALIAN REGULATOR S EXPERIENCE Geoff Cooke, Sarah Sinclair and Rob Sheers Hazard Management Division, WorkSafe Victoria The Occupational

More information

Procurement Systems Report

Procurement Systems Report Procurement Systems Report Internal Audit Final Follow-up Report March 2017 1 Contents 1. Background page 3 2. Purpose of this report - page 3 3. Executive Summary page 4 4. Summary of Findings page 5

More information

Roles and Responsibilities

Roles and Responsibilities Growth Deal Programme Roles and Responsibilities Appendix 17 The Programme Management Office A dedicated PMO has been established within Black Country Consortium Ltd to support all aspects of Black Country

More information

Policy Title Quality Management and Continuous Improvement Policy Preamble

Policy Title Quality Management and Continuous Improvement Policy Preamble Policy Title Quality Management and Continuous Improvement Policy Preamble The Quality Management and Continuous Improvement Policy replaces the Quality Management and Assurance Framework initially approved

More information

Meeting Date 15 March 2018 Agenda Item 2b

Meeting Date 15 March 2018 Agenda Item 2b Meeting Date 15 March 2018 Agenda Item 2b Report Title Stocktake Report Author Pam Wenger, Report Sponsor Pam Wenger, Presented by Pam Wenger, Freedom of Open Information Purpose of the Report The purpose

More information

Enterprise Asset Management. Enterprise Asset Management 1

Enterprise Asset Management. Enterprise Asset Management 1 Enterprise Asset Management 1 Introduction Managing assets effectively is critical to the success of organisations that depend on complex physical assets to deliver services. Increasingly, operators and

More information

Communicating an Evidence Based Asset Management Program By Daryush Esmaili

Communicating an Evidence Based Asset Management Program By Daryush Esmaili Communicating an Evidence Based Asset Management Program By Daryush Esmaili December 1, 2017 Agenda Communicating Asset Management 2 Introduction Challenges Service-Supporting Assets Governance and Strategic

More information

Asset Management. Activity Management Plan. Amended Long Term Plan As amended through the FitForFuture restructure 22 April /

Asset Management. Activity Management Plan. Amended Long Term Plan As amended through the FitForFuture restructure 22 April / Christchurch City Council Activity Management Plan Amended Long Term Plan 2016 2025 As amended through the FitForFuture restructure 22 April 2016 16/1098088 Christchurch City Council Quality Assurance

More information

Asset Management BC Roadmap Project PROJECT REPORT

Asset Management BC Roadmap Project PROJECT REPORT Asset Management BC Roadmap Project Asset Management BC PROJECT REPORT MAY 2011 Asset Management BC ROADMAP PROJECT Report on the development of the Asset Management BC Roadmap Asset Management BC PROJECT

More information

Sustainability and Environment Manager

Sustainability and Environment Manager POSITION DESCRIPTION 1. POSITION DETAILS Position Title: Division: Unit: Management Level: Sustainability and Environment Manager City Projects & Property Property Services M4 2. ORGANISATIONAL RELATIONSHIPS

More information

Procurement Functional Leadership Progress Report October 2015 to March 2016

Procurement Functional Leadership Progress Report October 2015 to March 2016 Office of the Minister for Economic Development The Chair Cabinet State Sector Reform and Expenditure Control Committee Procurement Functional Leadership Progress Report October 2015 to March 2016 Proposal

More information

Roles and Responsibilities

Roles and Responsibilities Local Growth Deal Programme Roles and Responsibilities The Programme Management Office () A dedicated has been established within Black Country Consortium (BCC) Ltd to support all aspects of Black Country

More information

Stewart McLeod Jacqui Hansen Mike Brearley

Stewart McLeod Jacqui Hansen Mike Brearley Stewart McLeod Jacqui Hansen Mike Brearley 1. LMWUA Leading the way Stewart McLeod 2. Regional Asset Management Initiative Jacqui Hansen 3. The Performance Reporting Initiative Mike Brearley The LMWUA

More information

CGMA Competency Framework

CGMA Competency Framework CGMA Competency Framework Technical skills CGMA Competency Framework 1 Technical skills : This requires a basic understanding of the business structures, operations and financial performance, and includes

More information

Strategic Decision Making Tool for Renewals

Strategic Decision Making Tool for Renewals Case Study Strategic Decision Making Tool for Renewals Initiative number 2014_07 August 2014 Version No Date Item Affected Description of Change 1 01/08/2014 1 st Draft of Report Completed 2 20/10/2014

More information

Procurement Strategy Version 08 October Reference Version 08

Procurement Strategy Version 08 October Reference Version 08 Strategy 2016-2020 Version 08 October 2016 Reference Version 08 Issue date October 2016 Review date October 2018 Introduction At Red Kite, achieving value for money in delivering our corporate vision is

More information

Occupational Health and Safety. Improvement Standard

Occupational Health and Safety. Improvement Standard Premier s Department New South Wales Occupational Health and Safety Improvement Standard A tool for measuring OHS performance within NSW Government Agencies OHS IMPROVEMENT STANDARD NSW GOVERNMENT - REVIEW

More information

CGMA Competency Framework

CGMA Competency Framework CGMA Competency Framework Technical Skills CGMA Competency Framework 8 Technical Skills : This requires a basic understanding of the business structures, operations and financial performance, and includes

More information

Building trust and confidence in our reporting Data Assurance Summary 2017/18

Building trust and confidence in our reporting Data Assurance Summary 2017/18 Building trust and confidence in our reporting 1 Contents 1 About this document Statement of risks, strengths and weaknesses Assurance plans Data summary Our 2020-25 business plan reporting risks and 2

More information

Building an. Effective Board

Building an. Effective Board Building an Effective Board Who we are Established in 1996, Effective Governance is now Australasia s largest and most experienced independent corporate governance consulting firm. Our mission is to deliver

More information

MASTERTON DISTRICT COUNCIL

MASTERTON DISTRICT COUNCIL POSITION DESCRIPTION POSITION: RESPONSIBLE TO: EMPLOYMENT PERIOD: CHIEF EXECUTIVE Mayor and Council Four years fixed term POSITION PURPOSE The CEO is responsible for proactively leading and managing the

More information

In partnership with EXCLUSIVE COURSE OFFERING - PAN PACIFIC HOTEL, PERTH. Course 1 Course 2

In partnership with EXCLUSIVE COURSE OFFERING - PAN PACIFIC HOTEL, PERTH. Course 1 Course 2 In partnership with EXCLUSIVE COURSE OFFERING - PAN PACIFIC HOTEL, PERTH Course 1 Course 2 Project Controls & the Asset Life Span Project Controls & the Project Life Span 3 Day Course: 16 18 November 2016

More information

Town of Oakville - Asset Management Plan. Town of Oakville Asset Management Plan

Town of Oakville - Asset Management Plan. Town of Oakville Asset Management Plan Town of Oakville - Asset Management Plan Town of Oakville Asset Management Plan December 2017 Town of Oakville - Asset Management Plan 1. Executive Summary The Town of Oakville has been on the Asset Management

More information

Risk Management Policy and Framework

Risk Management Policy and Framework Risk Management Policy and Framework Introductory Note to User: CompanyLongName There is no requirement in Australia for a non-publicly listed entity (other than a company regulated by APRA) to comply

More information

Project Steering Committee. Executive Leadership Team Assets leadership team Superintendents team Business Analyst/PMO

Project Steering Committee. Executive Leadership Team Assets leadership team Superintendents team Business Analyst/PMO POSITION DESCRIPTION Position Title: Projects Manager Location: Newcastle Primary Purpose of the Position The primary purpose of this position is to provide a full project life cycle approach to the management

More information

The role of Asset Management in the Public Sector. Ernst Swanepoel SAAMA Council Member

The role of Asset Management in the Public Sector. Ernst Swanepoel SAAMA Council Member The role of Asset Management in the Public Sector Ernst Swanepoel SAAMA Council Member What is the purpose of Asset Management? TOPICS Accountability for Asset Management Physical asset management: Strategic

More information

RISK STATEMENT & ASSURANCE PLAN. Statement of risks, strengths and weaknesses and draft assurance plans for 2015/16. For consultation.

RISK STATEMENT & ASSURANCE PLAN. Statement of risks, strengths and weaknesses and draft assurance plans for 2015/16. For consultation. RISK STATEMENT & ASSURANCE PLAN Statement of risks, strengths and weaknesses and draft assurance plans for 2015/16. For consultation. November 2015 About this document Severn Trent Water is one of the

More information

POSITION DESCRIPTION Property Operations Manager

POSITION DESCRIPTION Property Operations Manager POSITION DESCRIPTION Property Operations Manager The BlueCross Vision A dynamic organisation, BlueCross is supported by a team of great staff, who are willing to challenge traditions. With a long history

More information

Belfast Health and Social Care Trust (BHSCT) Personal and Public Involvement (PPI) Monitoring Report September 2017

Belfast Health and Social Care Trust (BHSCT) Personal and Public Involvement (PPI) Monitoring Report September 2017 Belfast Health and Social Care Trust (BHSCT) Personal and Public Involvement (PPI) Monitoring Report September 2017 Prepared by Martin Quinn and Claire Fordyce, PHA 1 Contents Introduction...... 3 Rationale

More information

SAYONA MINING LIMITED CORPORATE GOVERNANCE STATEMENT 2017

SAYONA MINING LIMITED CORPORATE GOVERNANCE STATEMENT 2017 Sayona Mining Limited ( Sayona Mining or Company ) is committed to implementing the highest standards of corporate governance and to determine these standards, the Company has used the reporting recommendations

More information

Marketing and Social Media Executive Summary

Marketing and Social Media Executive Summary Appendix D CODA Audit Reports Completed and Presented to CODA Assurance, Audit and Risk Committee Marketing and Social Media Executive Summary 1 Introduction Internal Audit has recently completed an audit

More information

JOB DESCRIPTION SALARY: 36,004

JOB DESCRIPTION SALARY: 36,004 JOB DESCRIPTION JOB TITLE: Asset Information Manager SALARY: 36,004 RESPONSIBLE TO: Head of Asset Management RESPONSIBLE FOR: Asset Information Officer Asset Information Assistant Customer Involvement

More information

2009 Post Review Implementation Plan. Water Corporation Western Australia. December Odysseus-imc Pty Ltd

2009 Post Review Implementation Plan. Water Corporation Western Australia. December Odysseus-imc Pty Ltd 2009 Post Review Implementation Plan Water Corporation Western Australia December 2009 TABLE OF CONTENTS Introduction... 4 Implementation Plan - 2009... 6 Actions Yet To Be Completed 2006 Review... 20

More information

Business Plan

Business Plan Business Plan 2013 2014 Message from the Chief Ombudsman We operate in a continually changing environment and has experienced changes in the demand for our services. While back in 2011 2012 our dispute

More information

DEVELOPMENT CHRISTCHURCH LTD

DEVELOPMENT CHRISTCHURCH LTD DEVELOPMENT CHRISTCHURCH LTD Statement of Intent For the year ending 30 June 2018 Directory Postal Address: Development Christchurch Limited PO Box 333 Christchurch 8011 Registered office: Level 2, 181

More information

DEVELOPMENT CHRISTCHURCH LTD

DEVELOPMENT CHRISTCHURCH LTD DEVELOPMENT CHRISTCHURCH LTD Statement of Intent For the year ending 30 June 2018 Directory Postal Address: Development Christchurch Limited PO Box 333 Christchurch 8011 Registered office: Level 2, 181

More information

Position Description. Title Financial Accountant Date June Division Finance Grade PO2/Accountant Grade 2. Branch Financial Control Reference

Position Description. Title Financial Accountant Date June Division Finance Grade PO2/Accountant Grade 2. Branch Financial Control Reference Position Description Title Financial Accountant Date June 2017 Division Finance Grade PO2/Accountant Grade 2 Branch Financial Control Reference Reports to Financial Policy & Accounting Manager SAP Position

More information

APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2016

APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2016 APPLICATION OF KING III CORPORATE GOVERNANCE PRINCIPLES 2016 This table is a useful reference to each of the King III principles and how, in broad terms, they have been applied by the Group. KING III ETHICAL

More information

POSITION DESCRIPTION

POSITION DESCRIPTION POSITION DESCRIPTION Position Title CHIEF FINANCIAL OFFICER Date: April 2016 Group: WA Local Government Superannuation Plan Reports to: Chief Executive Officer Employment Status: Permanent SECTION 1 CORPORATE

More information

The Annual Audit Letter for South West London and St George's Mental Health NHS Trust

The Annual Audit Letter for South West London and St George's Mental Health NHS Trust The Annual Audit Letter for South West London and St George's Mental Health NHS Trust Year ended 31 March 2016 July 2016 Paul Grady Engagement Lead T 020 7728 2301 E paul.d.grady@uk.gt.com Marcus Ward

More information

Research & Development (R&D) Strategy 2012 to 2016 Sustaining Growth

Research & Development (R&D) Strategy 2012 to 2016 Sustaining Growth Research & Development (R&D) Strategy 2012 to 2016 Sustaining Growth Document Status Version: 1.0 Approved DOCUMENT CHANGE HISTORY Initiated by Date Author Clinical Development & Effectiveness (CDE) First

More information

Integrated Property Management Solution

Integrated Property Management Solution Integrated Property Management Solution 30 minutes to discuss: Value proposition why Vision and SPM Best of Breed there is an alternative The concept incorporating good practice The process working with

More information

1. OBJECTIVE 1.1 This Charter outlines the roles and responsibilities of the Board.

1. OBJECTIVE 1.1 This Charter outlines the roles and responsibilities of the Board. Board Charter Table of Contents 1. OBJECTIVE... 1 2. SCOPE... 1 3. DEFINITIONS AND INTERPRETATION... 1 4. POLICY STATEMENT... 2 Director Responsibilities... 2 Size and Composition of the Board... 4 Criteria

More information

PUBLIC REPORT TEMPLATE 2011

PUBLIC REPORT TEMPLATE 2011 PUBLIC REPORT TEMPLATE 2011 Please note that this template has been updated based on feedback from a number of Corporations during the recent review of regulations. It is not compulsory for you to use

More information

Strategic Plan:

Strategic Plan: Strategic Plan: 2014-2018 Contents Contents... 2 Introduction... 2 Sunnyhaven: who we are and where we come from... 3 Sunnyhaven: the world we work in... 4 Sunnyhaven: our purpose, vision, values and priorities...

More information

Australian National Audit Office REPORT ON RESULTS OF A PERFORMANCE AUDIT OF THE STRATEGIC PLANNING FRAMEWORK. April kpmg

Australian National Audit Office REPORT ON RESULTS OF A PERFORMANCE AUDIT OF THE STRATEGIC PLANNING FRAMEWORK. April kpmg Australian National Audit Office REPORT ON RESULTS OF A PERFORMANCE AUDIT OF THE STRATEGIC PLANNING FRAMEWORK April 2000 kpmg Contents 1. Executive Summary... 1 Introduction...1 Objectives...1 Scope and

More information

Corporate Governance Policy

Corporate Governance Policy BACKGROUND Scope (Vic) Ltd. ( Scope ) was established in 1948 as The Spastic Children s Society of Victoria by a group of parents of children with cerebral palsy. It became The Spastic Society of Victoria

More information

2017 TIMBER BRIDGE MANAGEMENT REPORT

2017 TIMBER BRIDGE MANAGEMENT REPORT IPWEA (NSW) ROADS & TRANSPORT DIRECTORATE ROAD ASSET BENCHMARKING PROJECT 2017 TIMBER BRIDGE MANAGEMENT REPORT May 2018 The Roads & Transport Directorate is a joint initiative with IPWEA NSW Division Roads

More information

GUIDELINES FOR PUBLIC SECTOR REVIEWS AND EVALUATIONS

GUIDELINES FOR PUBLIC SECTOR REVIEWS AND EVALUATIONS Department of the Premier and Cabinet Government of Western Australia GUIDELINES FOR PUBLIC SECTOR REVIEWS AND EVALUATIONS PUBLIC SECTOR MANAGEMENT DIVISION 19 December 2007 CONTENTS EXECUTIVE SUMMARY

More information

Australian Hardware. Risk Management Plan

Australian Hardware. Risk Management Plan Australian Hardware Risk Management Plan This is a simulated business, not a real one. It is provided for education purposes only, for Learn.com.au courses (content provided by IBSA [ibsa.org.au]. Risk

More information

Chart 1.1 The business planning process

Chart 1.1 The business planning process 1 1 Introduction This book is designed for those with an inspired idea who wish to translate it into a successful new business or incorporate it in an existing business. Usually, the first challenge for

More information

Loch Lomond & The Trossachs National Park Authority. Annual internal audit report Year ended 31 March 2015

Loch Lomond & The Trossachs National Park Authority. Annual internal audit report Year ended 31 March 2015 Loch Lomond & The Trossachs National Park Authority Annual internal audit report Year ended 31 March 2015 Contents This report is for: Information Chief executive Audit committee Jaki Carnegie, director

More information

RTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning

RTI Release. Project Management Plan. Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning 1 Project Management Plan Brisbane Infrastructure Transport Planning & Strategy Strategic Transport Planning SOUTH WEST CORRIDOR STUDY (OXLEY ROAD) PROJECT OWNER: GRAEME READ 2 Document Change History

More information

Risk Based Bridge Asset Management

Risk Based Bridge Asset Management Risk Based Bridge Asset Management David Coe, Director Pitt & Sherry SYNOPSIS Following the High Court decision in May 2001 in Brodie vs Singleton Shire Council, common law non feasance protection can

More information

ATTACHMENT 6.1 INVESTMENT GOVERNANCE AN OVERVIEW ATCO PLAN

ATTACHMENT 6.1 INVESTMENT GOVERNANCE AN OVERVIEW ATCO PLAN ATTACHMENT 6.1 INVESTMENT GOVERNANCE AN OVERVIEW ATCO 2020-24 PLAN EIM # 96784645 PUBLIC 31 August 2018 An appropriate citation for this paper is: Attachment 6.1 Investment Governance An Overview Our Ref:

More information

Annual Procurement Report 2017/18. Prepared by: Gillian Berry, Senior Accountant Contact:

Annual Procurement Report 2017/18. Prepared by: Gillian Berry, Senior Accountant Contact: Annual Procurement Report 2017/18 Prepared by: Gillian Berry, Senior Accountant Contact: 01382 207140 Approved by: Board: 18 December 2018 1 Contents 1.0 Introduction 1.1 About the Care Inspectorate 2.0

More information

The Gateshead Housing Company

The Gateshead Housing Company The Gateshead Housing Company Working with the community to provide excellent homes and housing services. Updated Value For Money Strategy and Three Year Programme 23 rd April 2008 Copyright.. 2008 All

More information

MARITIME OPERATOR SAFETY SYSTEM FEES

MARITIME OPERATOR SAFETY SYSTEM FEES Chair Cabinet Economic Growth and Infrastructure Committee Office of the Minister of Transport MARITIME OPERATOR SAFETY SYSTEM FEES Proposal 1. This paper proposes that the Economic Growth and Infrastructure

More information

Topic for today: From tactical to strategic the journey of a PMO

Topic for today: From tactical to strategic the journey of a PMO Topic for today: From tactical to strategic the journey of a PMO The Start-up PMO Structure Chief Executive Officer Director: Strategy Group Executive: Strategic Projects Project Administrator Portfolio

More information

Adult Migrant English Program Research Centre Quality Assurance Policy

Adult Migrant English Program Research Centre Quality Assurance Policy Adult Migrant English Program Research Centre Quality Assurance Policy July 2008 Contents Page Quality Policy 4 Schedule of Quality Principles 5 Overview of the Quality Management System 6 Table of AMEP

More information

Summary 2018 Price Submission. A summary of our submission for water and sewerage pricing for the regulatory period

Summary 2018 Price Submission. A summary of our submission for water and sewerage pricing for the regulatory period Summary 2018 Price Submission A summary of our submission for water and sewerage pricing for the 2018-23 regulatory period Page 2 At a glance This submission proposes South East Water s five-year approach

More information

Auckland Transport HS08-01 Safety In Design

Auckland Transport HS08-01 Safety In Design Auckland Transport HS08-01 Safety In Design (Procedure uncontrolled when printing) Relating to Standard: HS08 Safety In Design December 2016 Health and Safety-Procedure-HS08-01 Safety In Design Contents

More information

Asset Management Plan. Tool of Trade Fleet Management Plan

Asset Management Plan. Tool of Trade Fleet Management Plan Asset Management Plan Tool of Trade Fleet Management Plan 2019-2024 Info Zone Record Number: Version Number: 1.0 Date: October 2017 Table of Contents Authorisations... 2 Responsibilities... 2 1 Purpose...

More information

2017 Four Year Plan Guide

2017 Four Year Plan Guide 2017 Four Year Plan Guide June 2016 ISBN: 978-0-478-43458-3 Crown copyright ISBN 978-0-478-43458-3 (Online) This copyright work is licensed under the Creative Commons Attribution 4.0 International licence.

More information

Guide - Alternative Procurement - Unsolicited Proposals

Guide - Alternative Procurement - Unsolicited Proposals 1 Introduction 1.1 The Guidelines Good ideas are not the preserve of the public sector. AT welcomes unique, innovative and opportune proposals from business and individuals that support its vision and

More information

Community Engagement Report Carbon Neutrality Action Plan December 2017 February 2018

Community Engagement Report Carbon Neutrality Action Plan December 2017 February 2018 ATTACHMENT 3 Community Engagement Report Carbon Neutrality Action Plan 2017-2020 December 2017 February 2018 Background In 2008, Council committed to be carbon neutral for its operations by 2020 and in

More information

PROCUREMENT STRATEGY & ACTION PLAN. April 2012 March 2015

PROCUREMENT STRATEGY & ACTION PLAN. April 2012 March 2015 PROCUREMENT STRATEGY & ACTION PLAN CONTENTS Page 1 Executive Summary 2 2 Strategic Context 2 3 Scope 3 4 Values 3 5 Structure and Responsibilities 5 6 Aims, Objectives and Initiatives 6.1 Sustainability

More information

Asset Management Competence Framework

Asset Management Competence Framework 1 ACKNOWLEDGEMENTS This document has been commissioned by the UK Roads Liaison Group Asset Management Board, with support from Transport for London and the Department for Transport and supports the implementation

More information

ONEWATER ENTERPRISE SOFTWARE FOR WATER UTILITIES

ONEWATER ENTERPRISE SOFTWARE FOR WATER UTILITIES ONEWATER ENTERPRISE SOFTWARE FOR WATER UTILITIES Transforming Business, Making Life Simple. TechnologyOne supports over 100 customers in the water business, every day. Our commitment to innovation ensures

More information